Section 16
from direct sun and as detailed in the drawing for the project
16.6.24
Page 37 of 48
Rev.01
Volume 2B 2 of 3
The Tiger Woods Dubai
Section 16
Manual fuel transfer pumps shall be of the self priming diaphragm type with detachable
handle arranged to pump diesel fuel from the bulk fuel tank to the day tank.
Provision shall also be made to pump fuel from the day tank to the bulk fuel tank to
empty the day tank for maintenance purposes.
16.6.25
Fuel System
The fuel system shall comprise the following:Fuel transfer pumps controlled by a float type level switch in the day tank.
Overflow back to the bulk fuel tank to be provided to guard against float switch failure.
Mesh type filters not coarser than 120 mesh to be provided on the draw-off line.
Free-fall fire shut-off valves to be fitted operated from the local fire alarm system (where
applicable) or a wire rope and heat sensitive fusible link.
Daily service tank to accommodate fuel for 12 hours running at full load.
Fuel supply piping system to be in suitably sized copper tubing.
16.6.26
Enclosure
Generators shall be nomally housed in purpoes-built structure with proper sand trap
louvres of adequate size.
Generator house shall have suitable overhead crane / hoist
Where purpsebuilt GRP enclosure is specified it shall be compliant to the GRP
fabrication details as decribed elsewhere.
Protection against the ingress of dust and moisture shall be to an approved international
standard and is applicable to any type of generator enclosure
Provide ample access for maintenance by way of hinged and removable covers if GRP
enclosure is installed.
Controls, indication etc. to be enclosed in an integral panel with a polycarbonate hinged
clear cover.
Small power & lighting system for Generator house shall be compliant to general
requirements for Lighting Installations detailed under Electrical Section of the
specification.
Page 38 of 48
Rev.01