Sei sulla pagina 1di 5

SYED BROTHERS CONSTRUCTION COMPANY

CCA 1, first floor Phase 5 DHA, Lahore Cantt.


Cell # 0333-4312699

CLIENT NAME:
SITE:
SCHEDULE OF FINISHING
1.

EXCAVATION AND FOUNDATIONS


1.5 feet deep and 3 feet width excavation from N.S.L. LEVEL. Anti termite treatment (FMC)
spray as per drawing and specification. In ground floor 6 thick P.C.C with brick ballast well
compact with compactor. Wall foundation will be laid as per drawing and specification cement
mortar (1:6) ratio. Laying of 1 thick (1:2:4) PCC in DPC and painting with Bitumen and one
layer of polythene sheet. External wall double D-P-C and painting with Bitumen and layer of
polythene. Plinth level filled with gassu. Total foundation from PCC till DPC will be 5 feet 6
inches more than this will be paid by house owner.
a. Rait from Ravi
b. Bajri from Texala
c. Cement Maple leaf, Askari, Lucky D.G Cement, Graib wall Cement (Which is easily
Available in the market).

2.

PLINTH
Ground floor plinth level will be + 1.3 from the road level porch and side passages level will
be + 9 from the road level.

3.

SUPER STRUCTURE
a. 9 thick brick work in super structure of 1st class brick masonry
(Approximately Rs.8300) in cement sand mortar ratio (1:4)
b. 4 thick walls will be made with (1:4) cement mortar.
c. 1 thick cement plaster (1:3) ratio on ceiling, shade, internal and external walls.

4.

REINFORCMENT CEMENT CONCREAT (1:2:4)


a. All reinforced cement concrete in, lintels, column, beams, roof slabs, parapet and shelves
shell be carried out in ratio (1:2:4)
b. Local deformed steel bar (40/60 Grade) shell is used in RCC slab as per structure drawing
and design (8 TON without Basement).
5. FLOORING
a. Tile 32 x 32 up to Rs. 1600/ Meter, will be provided and laying in bed rooms and lounge.
Granite slab up to Rs.600/Sq.ft, in kitchen counter bath room vanity counter, Stairs steps,
kitchen counters and entrance steps. Window sill only inside 4 wide and skirting 4same
marble will be provided in all marble area marble @ Rs.250/Sqft.
b. Flooring tiles (Master / EMCO; Rs.1000/Meter) providing and laying in terraces front at
first floor, street marble (Badal) 12x 6x 3/8.
c. All Bath room tiles up to Rs.2500/ Sq. Meter (7 Feet height)
d. Skirting wooden ply will be provided in Wooden Ply/Tile area.
e. Two numbers fireplace will be provided up to Rs.25, 000/- for each fireplace.
f. Drawing dinning wooden floor upto Rs. 300 / sqft

6.

TOP ROOF TREATMENT


a. Applying two coats of cold bitumen with sand spray.
b. Laying one layer of polythene.
OWNER: ______________________ CONTRACTOR: ______________________
Syed Waseem Ahmed

SYED BROTHERS CONSTRUCTION COMPANY


CCA 1, first floor Phase 5 DHA, Lahore Cantt.
Cell # 0333-4312699

c.
d.
e.
f.
7.

Laying a layer of 3 to 4 earth.


Laying 1 x 4 9 first class brick tiles grouted with 1:3 cement mortar.
Making khuras providing adequate slopes adequate slopes for the drainage of rainwater.
Providing and laying 4 (dia) P.V.C pipe of (Atlas Plast) for rainwater.

PUBLIC HEALTH AND SANITARY WORK


a. PVC pipes (Atlas Plast) of appropriate size will be used for internal main and sub main
Lines floor trap covers of 4 dia chromium plated will be provided.
b. Water supply hot and cold lines all bathrooms and kitchen will be provided with best quality
PPR (TURKEY).
c. Providing and fixing PORTA seats, commode seat (up to Rs. 15000/-).
d. One washroom will be provided up Rs.30000/- Vanity and others @ Rs.20000/ Vanity.
e. Powder room vanity up to Rs, 15000/-.

8.

ELECTRIVICATION
a. It shall include conduit PVC pipe (High density Black Color Pipe) of , 1 and 1 1/2 as per
Require in roof slab and walls will be provided.
b. Fan box; chandler box, light box, ceiling light box and bracket light box will
Be provided according to the electric drawing.
c. Fast, Newage cables will be used.
d. 3/29 wires for light plug will be used.
e. 7/29 wires for light circuit will be used.
f. 7/44 wires for power plug will be used.
g. Italian Clipsal boxes for light plugs, power plugs and for switches will be provided
According to the required size.
h. Telephone points in all bedrooms, drawing and TV lounge. TV antenna and cable connection
Line in all bedrooms and TV Lounge.
i. Italian Clipsal fittings as light, switches, two pin socket light plug, power plug and two
Distribution board one on ground floor and other on first floor will be provided circuit
Breaker price Rs.250/each.
j. Wall light will be provided in each bedrooms of (Rs.1500/ Light)
k. Intercom system wiring will be provided.
l. UPS, wiring will be provided for Light and Fan 1+1 in each room and 1 light in each bath room.
Generator soler provision will be provided.
m. All spotlights to be used in house with adaptor (Rs.200/-each), electrical switch board OPAL
Company (Total number of Spot lights _______).
n. 3 Chandeliers will be given in the house up to Rs.15, 000/- for each chandelier.
o. Fan / Exhaust fan, Pressure pump, Geyser.

9.

WOOD WORK
a. Main entrance door will be provided in solid ash wood.
b. All other doors will be provided in semi solid wood. (Rs.3800/feet)
c. Dolly, frames will be fully width of the wall made of Kale Wood. Covered with thick
Lasani.
d. French door with 8 mm Glass in living, Drawing, Dining rooms and TV Lounge Partition.
e. All the Doors shall have Brass Lacquered hinges.350/ hinges
f. Brass Chthonic will be used with all used. 350/ Chthonic
g. Imported doorstoppers will be used.100/ Chthonic
h. All bed and bath doors shall be fitted with locks of Price up to Rs.2000/i. Main Door shall have imported locks of Price up to Rs.7000/-

10.

WARDROBE AND KITCHEN CABNIET


a. All boxes will be made in Ash wood color lamination the shutter of wardrobe will be
OWNER: ______________________

CONTRACTOR: ______________________
Syed Waseem Ahmed

SYED BROTHERS CONSTRUCTION COMPANY


CCA 1, first floor Phase 5 DHA, Lahore Cantt.
Cell # 0333-4312699

Prepared in Sami solid ash wood/Imperial Lasani with deco paint.


b. Imported kitchen up to Rs. 600000/- will be provided and if the House owner wants more
Costly accessories/items in kitchen than the said price he will pay the additional amount.
c. Wardrobe Handles up to Rs.300/- (Each Handle)
d. The shutter of all bed room wardrobes will be prepared in UV Sheets. (Rs. 7000/Sheet)
11.

STEEL WORK
a. Wrought iron stair railing (Cost Price 1000/Sq.ft) will be provided.
b. Terrace railing will be provided up to 1 feet.
c. Main Gate will be provided Rs.50,000/-

12.

WINDOW
a. All Champaign color aluminum (Alcop Brand) window of 1.3 mm section with imported
plain glass
5 mm will be provided top level of all windows 7 at ground and first floor.

13.

PAINT AND POLISH


a.
b.
c.
d.

14.

All woodwork will be polished.


All internal surfaces of walls and ceiling will be painted with ICI paint.
All steel work will be painted in sham pain color with (ICI paint).
Four side plane plaster exposed surface will be painted with rock wall.

SEWERAGE
Good quality 6 dia sewer pipes PPR/R C.C shall be used. It shall be connected to Septic Tank
and t main sewer line.

15.

SUI GAS
Sui Gas connection shall be available in:
a. Kitchen
b. Drawing Room (Fireplace)
c. T.V Lounge.
d. Geyser point and Servant Quarter as required.
e. Extra gas point other than mentioned above will be charged Rs 25000 per point.

16.

PLASTER OF PARIS WORK


a. All Bedrooms, Drawing, Dining, TV Lounge will be will have complete ceiling.

17.

PLANTATION AND GRASS


a. Plantation and grass will be provided up to Rs.60, 000/18. EXTRA WORK WILL BE CHARGES ACCORDINGLY
a.
b.
c.
d.
e.
f.
g.

Boundary wall Rs.1400/-RFT. Running feet height 6 feet from the road level.
External Boundary Walls of the basement will be charged @ Rs. 2500/ Running Feet.
Sunken Area of the basement will be full charged @ Rs. 1800/Sqft (Basement Rate)
Water Tanks and Septic Tank Rs.150 per Gallon. (All R.C.C)
Pergolas charged @ Rs.1200/Sqft.
All shades will be fully charged @ 600/Sqft.
Centar Terrace will be charged @ 600/SQ.FT.

OWNER: ______________________

CONTRACTOR: ______________________
Syed Waseem Ahmed

SYED BROTHERS CONSTRUCTION COMPANY


CCA 1, first floor Phase 5 DHA, Lahore Cantt.
Cell # 0333-4312699

h. Passages and open car porch and drive way area will be charged Rs.250/SQ.FT
i. If Steel Shuttering used for slab poring then no plaster at roof, if wooden shuttering used
for slab poring then roof will plaster. If steel shuttering used and roof also plaster then
owner shall pay Extra amount.
j. Canopy will be Charged @ 1 of the Agreement Price.
19.

PROJECT PERIOD
Period for the completion of bungalow without basement will be 12 month starting from
________________ and ending on ______________________.
Note: M/S Syed Brothers will pay the Electric Billing and watchman salary of above mentioned
project period. In case of delay in project due to payment delay from the Owner, the Owner will
have to pay the extra amount of the billing and salary of further period likewise if Company
delays the project timelines then the further payments will be paid by Company.

Electricity, Gas, Water connection will be provided by the house owner.

CLIENT NAME:
SITE:

Total Rate Rs. 3000/Sq.Ft


SCHEDULE OF PAYMENTS

1. ADVANCE at the time of Signing of Contract

25%

2. BEFORE Poring of Ground Floor Slab

25%

3. BEFORE Poring of First Slab

25%

4. INTERNAL Plaster +Sanitary+ Sewage

15%

5. Paint + Polish + Start Complete Finishing

10%

6.
Note:-

Difference of Price will be paid by House Owner at the time of Purchased in Advance.

WITNESSES:1. ____________________________

OWNER: ______________________

2.__________________________

CONTRACTOR: ______________________
Syed Waseem Ahmed

SYED BROTHERS CONSTRUCTION COMPANY


CCA 1, first floor Phase 5 DHA, Lahore Cantt.
Cell # 0333-4312699

OWNER: ______________________

CONTRACTOR: ______________________
Syed Waseem Ahmed

Potrebbero piacerti anche