Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
3.1
Introduction
The term water treatment and supply describes the process of treat the water
from source, especially river, process of flow water in every section to be treat and supply
it to consumers. These properties collectively determine the overall water treatment
process and supply in mechanical, technical, machineries and sources. Water treatment
and supply is only meaningful when evaluated in relation to the use of the water. The
reason is that water treatment and supply may be important to maintain the quality of
water that will be use by consumer, but important to know the flow of processing water.
For example, we need to know how it processing in the plant through many mechanical
process from water intake to water supply to users. The principal objective therefore of
water treatment is to produce water that is fit for domestic use reliably and consistently
from a raw water source at a cost that is reasonable to the consumers around Saratok
district. A water treatment plant employs many individual treatment processes
(sometimes called unit processes and unit operations) that are linked in a process train to
produce water of the desired quality.
3.2
Project background
This project is important for rural area at Saratok district to get the treated water
supply in daily life. This project is located at Kaki Wong Krian, Saratok. This project was
proposed by Kementerian Kemajuan Luar Bandar Dan Wilayah (KKLW) as a client for
rural area at Saratok. The construction of the Kaki Wong Water Treatment Plant, the
biggest water supply in the state, cost RM120 million. The plant has the capacity of
supplying 25 MLD of clean water to 13,000 households in Saratok, Awik, Krian and
nearby areas. According to record, the project which started on Jan 18, 2012 was
supposed to be completed by June 1, 2013. But, since the contractor failed to beat the
scheduled completion date, it was revised to July 31, 2014. This project was consulted by
Perunding TCS Sdn Bhd as project consultant. The main contractor for this project was
Empayar Setia Sdn Bhd (ESSB). Cekap Air Sdn Bhd also involved in this project as
specialist M&E Contractor. This plant input is 27.6 MLD and Plant output is 25 MLD to
supply the water.
3.3
Water Treatment Plants have many processes and steps before a household turns
on their tap and receives water. From the river to the processing units there is a vigorous
process with many steps that are all essential in assuring high quality water for drinking.
The water treatment process may vary slightly at different locations, depending on the
technology of the plant and the water it needs to process, but the basic principles are
largely the same. This section describes standard water treatment processes.
Cascade aeration
Hydraulic Mixing of coagulant
Baffled Flocculation
Sedimentation tanks (4 Nos)
Rapid sand filtration with combined air water wash
Chlorine contact tank and clear water tank
Intake Structure
The basic function of the intake structure is to help in safely withdrawing water from the
source over predetermined pool levels and then to discharge this water into the
withdrawal conduit (normally called intake conduit), through which it flows up to water
treatment plant.
II.
The intake must be located in the purer zone of the source to draw
best quality water from the source, thereby reducing load on the
treatment plant.
III.
IV.
V.
The intake must be located at a place from where it can draw water
even during the driest period of the year.
VI.
The intake site should remain easily accessible during floods and
should not get flooded. Moreover, the flood waters should not be
concentrated in the vicinity of the intake.
Design Considerations
I.
II.
Pumping
A pump is a device which converts mechanical energy into hydraulic energy. It lifts water
from a lower to a higher level and delivers it at high pressure. Pumps are employed in
water supply projects at various stages for following purposes:
I.
II.
III.
IV.
V.
VI.
VII.
To back-wash filters.
To pump chemical solutions, needed for water treatment.
Classification of Pumps
I.
II.
III.
IV.
Conveyance
There are two stages in the transportation of water:
I.
II.
In the first stage water is transported by gravity or by pumping or by the combined action
of both, depending upon the relative elevations of the treatment plant and the source of
supply. In the second stage water transmission may be either by pumping into an
overhead tank and then supplying by gravity or by pumping directly into the water-main
for distribution.
Pressure System
In pressure conduits, which are closed conduits, the water flows under pressure above the
atmospheric pressure. The bed or invert of the conduit in pressure flows is thus
independent of the grade of the hydraulic gradient line and can, therefore, follow the
natural available ground surface thus requiring lesser length of conduit. The pressure
aqueducts may be in the form of closed pipes or closed aqueducts and tunnels
called pressure aqueducts or pressure tunnels designed for the pressure likely to come on
them. Due to their circular shapes, every pressure conduit is generally termed as
a pressure pipe.
Hydraulic Design
The design of water supply conduits depends on the resistance to flow, available pressure
or head, and allowable velocities of flow. Generally, Hazen-William's formula for
pressure conduits and Manning's formula for free flow conduits are used in construct it.
Fi
gure 1.4 Intake plan layout
I.
II.
III.
IV.
BACKGROUND
Water is clarified using the processes of coagulation and flocculation, which remove
suspended solids (turbidity) from water by causing the suspended particles to aggregate
into a slime, that settles out of the water. This technique is used in treating wastewater,
both industrial and treated sewage, from municipal wastewater treatment plants. It is also
used, as a first step, in treating raw water for industrial use, and in food and beverage
production.
THE PROCESS
I.
Coagulation uses salts such as aluminum sulfate (alum) or ferrous of ferric (iron)
salts, which bond to the suspended particles, making them less stable in
suspension, i.e., more likely to settle out. Figure 1 depicts the coagulation process
in the resident tank by the diagonal lines.
II.
used to form the flocculant (Figure 1 demonstrates the flocculation process in the
clarifier by the merging horizontal lines).
III.
treatment.
Screens
Filtration through screens is usually done at the beginning of the water purification
process. The shape of the screens depends on the particles that have to be removed.
Sand filtration
Sand filtration is a frequently used, very robust method to remove suspended solids from
water. The filter medium consists of a multiple layer of sand with a variety in size and
specific gravity. When water flows through the filter, the suspended solids precipitate in
the sand layers as residue and the water, which is reduced in suspended solids, flows out
of the filter. When the filters are loaded with particles the flow-direction is reversed, in
order to regenerate it. Smaller suspended solids have the ability to pass through a sand
filter, so that secondary filtration is often required.
Cartridge filtration
Cartridge filtration units consist of fibres. They generally operate most effectively and
economically on applications having contamination levels of less than 100 ppm. For
heavier contamination applications, cartridges are normally used as final polishing filters.
Chemical addition
There are various situations in which chemicals are added, for instance to prevent the
formation of certain reaction products. Below, a few of these additions are summed up:
- Chelating agents are often added to water, in order to prevent negative effects of
hardness, caused by the deposition of calcium and magnesium.
- Oxidizing agents are added to act as a biocide, or to neutralize reducing agents.
- Reducing agents are added to neutralize oxidizing agents, such as ozone and chlorine.
Dosing Point
Mixing Chamber
Mixing Chamber
Filtered Water Pipeline
Purpose
pH Adjustment
Coagulation
Disinfection
Fluoride
Post-Soda Ash
Minimu
m
5
Average
Maximum
15
30
Dosage (mg/l)
Soda Ash (Pre) (5% w/w)
Soda Ash (Post) (5% w/w)
Minimu
m
5
2
Average
Maximum
14
3
30
7
2 nos. Pre-Soda Ash Dosing pump of 700 liters/hr (duty & standby)
2 nos. Post-Soda Ash Dosing pump of 150 liters/hr (duty & standby)
Minimum
0.5
Average
0.7
Maximum
0.989
Quantit
y
3 sets (1
duty/2
standby)
2 sets (1
duty/1
standby)
2 sets
(1duty/1
standby)
kW Rating
Type`
Capacity
110 kW
Fixed
Speed
1042 m3/hr@
24.3mH
90 kW
Fixed
Speed
117 m3/hr @
114.5mH
55kW
Fixed
Speed
445 m3hr @
26.7mH
BWPS Plant
Pump
Booster Water
Pump-set
Quantity
3 sets (1 duty/2
standby)
kW Rating
315 kW
Type
Fixed
Speed
Capacity
900 m3/hr @
90.7 mH
Sludge Plant