THE CONSTRUCTION AND COMPLETION OF BEKALAN AIR

MUKAH,
BAHAGIAN MUKAH, SARAWAK
PHASE 2 PACKAGE 3 : PROPOSED NEW BOOSTER STATION,
RESERVOIR , DELIVERY MAIN, RETICULATION PIPELINE AND
ASSOCIATED FACILITIES

METHOD OF STATEMENT FOR


CONCRETE WORKS
PREPARED BY :
NASCA SYNERGY SDN. BHD

METHOD STATEMENT FOR THE CONSTRUCTION OF RC PIPE SUPPORT


1. All the pile head must be exposed and cut off with reinforcement bars bent at
the correct level as per given by surveyor.
2. All the pile head cut off level will be obtained from drawing and verify by RE
or authorised person before work proceed.
3. All the preparation and fabrication of steel bars will be done at bending yard
area and to be transport to the construction site using lorry during
construction time.
4. All the base slab formworks will be installed first with the correct level,
position and followed by inspection by RE or authorised person.
5. All the reinforcements will be placed into the formwork according to the
construction drawing and galvanized bolts will be placed with the correct
position.
6. Prior concreting carry out, approval will be obtained from Consultant through
RFI.
7. During preparation or concreting near to road area, standard warning and
traffic control signboards are to be displayed to warn the public about the
dangers that construction activities are in progress and to ensure a smooth
and safe traffic flow. Barricades and safety cones are to be used to demarcate
work sites on the carriageway or road when necessary.
8. Concrete will be placed into formwork by excavator or using chute depending
on site condition.
9. The formwork will be removed after concrete curing period
10.For the bolt and nut installation, a plywood plate with the bolt dimension will
used to hold the bolt at its location. After the concreting done, the plate will
be removed.
11.Concrete vibrator will be used during concreting to achieve proper
consolidation of concrete.

WORK METHODOLOGY
The construction sequence for the concrete works is as below:
I.
II.
III.
IV.
V.

Setup the gridlines as per construction drawing for the footing location
Excavate around the pile driven with extra precaution to ensure the
driven piles are not damage due to the excavation works
Carry out the excavation to require depth, then pile to be cut off at the
cutoff level
Check the level of base is correct, then pour lean concrete before
install the steel reinforcement
Once complete the steel reinforcement work, the next step is to install
the formwork

VI.
VII.
VIII.
IX.
X.

Ensure sufficient cover is provided as per specification


Provide enough support for the formwork to ensure no damage during
the pouring of concrete
Once completed the steel requirement works and formworks, recheck
the dimension of the structure to be cast before pouring of concrete
Concrete can now be poured and compacted with the concrete vibrator
After completion of concrete pour, the surface of the concrete shall be
cover with waterproof membrane or soaking with water for curing
purpose.

PLANT AND EQUIPMENT


Major plant and equipment to be used as follow:
I.
II.

Concrete Vibrator
Excavator

MATERIALS
The list of materials for the concrete work include :
a) Concrete G25
b) Reinforcement bar
c) Formwork such as plywood and timber planks

HEALTH, SAFETY AND ENVIRONMENT


a. Basic Personal Protective Equipment : Safety helmet, shoes or boot and
appropriate hand gloves.
b. Work leader/foreman to conduct total safety task induction (safety briefing)
before start of work to remind workers about danger and risk, hazards and
control actions to be taken to avoid untowards incident.
c. Avoid working during heavy rainy days.
d. Housekeeping. Provide safe working environment within working area. The
cut of piles to be arrange properly at temporary storage and removed from
site.