Sei sulla pagina 1di 2

NORTHERN TERRITORY OF AUSTRALIA

BUILDING ACT
SECTION 40 CERTIFICATE OF COMPLIANCE STRUCTURAL DESIGN
All sections must be completed mark N/A to any question that does not apply
PROPERTY / PROJECT DETAILS
Owner (if known):
Lot/Portion Number:

Address:

Location:

Town / Hundred :

Description of works :
B & D WINDPANEL REINFORCED SECTIONAL DOOR WITH VERTICAL BRACES AND TRACKLOCK 2.64m HIGH X 6.15m WIDE MAXIMUM
FOR USE IN WIND REGION C, TERRAIN CATEGORY 2 AND UP TO A MAXIMUM ULTIMATE WIND PRESSURE RATING AS STIPULATED ON
ENGINEERING DRAWINGS (attached)

DOCUMENTS ATTACHED
Drawing Nos:
Engineering Drawing Numbers 2191/S01J, 2191/S02J, 2191/S03J and 2191/S04J by James Ellis & Associates Pty Ltd (attached)
Other:

DESIGN BASIS (please list relevant Standards used in the design)


Test report nos. TS917 and TS811 (Revision A) from the Cyclone Testing Station School of Engineering and Physical Sciences at
James Cook University, Principles of Mechanics, AS/NZS 1170.2:2011 Structural design actions Part 2: Wind actions, AS4100:1998
Steel structures, AS/NZS 1170.0:2002 Structural design actions Part 0: General principles, AS/NZS 1170.1 Structural design actions
Part 1: Permanent imposed and other actions, AS/NZS 4600:2005 Cold formed steel structures, AS1720.1:2010 Timber structures
Part 1: Design methods, AS/NZS 1664:1997 Aluminium structures Part 1: Limit state design, AS3700:2011 Masonry Structures,
AS4505:2012 Garage doors and other large access doors, AS3600:2009 Concrete Structures, Ramset Specifiers Resource
Handbook, Buildex Fasteners Technical specifications
Type of Construction (BCA volume 1 C1.1):
N/A
Class of Building (BCA): As per NCC
(eg. Type A fire-resisting construction)
Building Importance Level (BCA Table B1.2a):
Region: C
Mz,cat :

0.91

Annual Probability of Exceedance for Wind (BCA Table 1.2b): 1 in

Regional ultimate wind speed VR(m/s): 69.3 m/s


Ms : 1

Terrain Category:

500

Reference height (m): 2.64m

Vdes Design Wind Speed at reference height (m/s): 63.06m/s

Mt : 1

+0.6, -0.3
-0.65, +0.8
Walls
N/A
Roof
N/A
Net Pressure Coefficients: (Cp,n)
Roof / Walls
N/A
Imposed Loads, kPa
Floor / Roof
Earthquake Design Category, EDC (Table 2.1 of AS 1170.4): N/A
Annual Probability of Exceedance for Earthquake Actions (BCA Table 1.2b): 1 in N/A
Importance Level (BCA): N/A
Hazard Factor, Z (Section 3):
N/A
Class of Sub-Soil (Section 4):
Internal Pressure Coefficients (Cp,i):
External Pressure Coefficients (Cp,e)

Safe Foundation Bearing Capacity, kPa:

N/A

N/A

Site classification (AS2870): N/A

COMMENTS / EXCLUSIONS (Exclusions to this Certificate must be clearly identified).


The following items are excluded and shall be certified separately: The structure to which the door is attached including lintel heads,
ceiling wind beams and abutment supports shall be assessed and certified independently as required by a suitably qualified
engineer.
Comments:
The subject doors are rated up to the relevant ultimate design wind pressures as stipulated in the design criteria on engineering
drawings. The building certifier or project engineer is to ensure that the site specific ultimate design wind pressures do not
exceed the ultimate design wind pressure ratings given on engineering drawings. Alternative design parameters to what are
specified on engineering drawings along with alternative site specific local pressure factors may be adopted provided the
calculated ultimate design wind pressures do not exceed the pressure ratings given on engineering drawings. Doors may be
positioned at any location along the building envelope including all local pressure zones (i.e. corners of buildings) provided the
calculated ultimate design wind pressures do not exceed the pressure ratings given on engineering drawings.

CERTIFICATION BY STRUCTURAL ENGINEER


Company Name : James Ellis & Associates Pty Ltd

Company NT Registration Number : 189148ES

We certify that reasonable care has been taken to ensure that the structural engineering aspects of the works as described above have
been designed in accordance with the requirements of the Building Code of Australia and the Northern Territory Building Regulations.
Name : James Ellis

Individual NT
Registration Number : 47429ES

Signature

Date : 16th June 2014

Page 1 of 2

SCHEDULE OF STRUCTURAL INSPECTIONS REQUIRED


Inspection of construction is required at all stages indicated below.
[ ]

1.

Completion of site preparation/site filling/excavations for footings prior to placement of any reinforcement or
concrete.

[ ]

2.

Completion of preparations for placing of concrete strip footings including placement of reinforcement.

[ ]

3.

Completion of preparations for placing concrete slabs including compaction of fill and sand blinding,
placement of formwork, reinforcement, starter bars and cast in items.

[ ]

4.

Completion of preparations for placing of concrete pier footings including reinforcement (if any).

[ ]

5.

Starter bars and cast in items after placing of concrete and prior to any covering up work.

[ ]

Reinforcement to walls completed prior to core filling (inspection holes and cleanout cores to be completed).

[ ]

7.

Structural steelwork and cold formed steelwork completed and prior to any covering up work. Floor framing
system completed before floors are laid or underside is lined.

[ ]

8.

Suspended concrete floor slabs with formwork, reinforcement and cast in items completed, prior to placing of
concrete.

[ ]

9.

Wall framing or blockwork wall core filling completed (with windows fixed in place) and roof framing with
connections completed and prior to sheeting or lining.

Note:

[ ]
[ ]

Prior lodgement of truss manufacturers drawings, details and certification required.


Prior lodgement of windows manufacturers drawings including fixings and certification required.

[ ]

10. Structural wall linings completed and prior to any covering up work.

[ ]

11. Final inspection upon completion of all structural work including fixings of external roof and wall claddings,
flashings, barges & vents.

[ ]

12. Other Inspections as required by the building permit

Important Information:
1) The above inspections are required to be carried out by either the certifying engineer or the building certifier who
issued the building permit for the work. (If no inspections are indicated refer to the certifying engineer for advice).
2) Where works are prescribed building works under the NT Building Act, the building certifier must be provided with
a copy of the inspection record and no further works must be carried out by the builder until the building certifier
issues a release to proceed with further works.
3) Additional non structural inspections may be required during the course of construction before the issue of a
Permit to Occupy (refer to building certifier for requirements).
4) Failure to obtain inspections may prevent the issue of a Permit to Occupy upon completion of the building works.

Page 2 of 2