Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
SERIAL NO. :
REV. :
SERIAL NO. :
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( GENERATOR )
ITEM
CHECK LIST
CHECKED
Check generator data conformity against data sheet / project specification (rating plate)
Check all auxiliary devices (cooling fans, vibration & temperature probes, CT's, VT's,,, if any) for proper
installation and connection
10
11
12
Check cable glands are correctly mounted (power and auxiliary terminal boxes)
13
14
15
Check the availability of certification documents against hazardous area generator installation.
16
17
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 1 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
(MV SWITCHBOARD)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check equipment is correclty aligned, leveled, rigid and secured with correct bolting.
Check all panel mounted devices are undamaged and tagged in accordance with data.
Check bus bars and supports are clean and clear of debris, torque all bolts to specification.
Check gland plates (if any) and terminations are correct and suitable for external cabling.
10
11
12
13
Check C.T's &VT's are properly installed and match drawing and protection diagram.
14
15
16
17
18
Check power cables are properly fitted and armour and screens earthing is correct
19
20
21
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 2 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
(LV SWITCHBOARD)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check equipment is correctly aligned, level, rigid and secured with correct holding
down bolts.
Check all panel mounted devices are undamaged and tagged in accordance with data.
Check bus bars and supports are clean and clear of debris torque all bolts to
specification.
Check earthing and bonding of all equipment is in accordance with project specification.
Check gland plates and terminations are correct and suitable for external cabling.
10
11
Check all circuit breakers and starter cubical run freely in compartments and that
all mechanical interlock and fouling plate are correct.
12
13
Check all C.T's are properly installed and accordance with data.
14
Check all V.T's are properly installed and accordance with data.
15
Check all protection relays fit to project schedules and are tagged correctly.
16
17
18
Check all vendor supplied special tools and safety equipment are available.
19
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 3 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
(TRANSFORMER )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check equipment is undamaged and oil levels are correct with no leaks.
10
Check that non-magnetic gland plates are installed when using single core cables.
11
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 4 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( DISTRIBUTION BOARD )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
4
5
diagrams. Check the mechanical operation of all MCB's, ELCB's and that incoming
breaker is correct.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 5 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( CHARGER / INVERTER )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check equipment is clearly identified and tagged in accordance with layout drawings.
Check all panel-front mounted components, indicators, lamps, meters are securely
mounted and undamaged.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 6 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( BATTERIES )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check cell type and battery make-up are in accordance with data.
Check all nuts and links are fitted, tightened and greased.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 7 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( NAVIGATION AIDS/FOGHORN)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check equipment earthing and bonding are in accordance with project specifications.
Check that foghorn, foghorn controller and accessories have been installed properly
on foghorn.
10
11
12
13
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 8 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( CONTROL PANEL )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
Check that panel is undamaged and that all components are in good condition.
Check panel earthing and bonding are in accordance with project specifications.
CHECKED
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 9 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( ELECTRIC HEATERS )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check cable glands and terminals for tightness and proper installation.
Check the avaibility of certification documents according hazardous area equipment installation.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 10 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( MV MOTOR )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check shaft rotates freely and quietly in both directions, motor uncoupled.
Check motor data conformity against data sheet and project specification (rating plate)
10
11
12
13
Check all auxiliary devices (vibration & temperature probes, CT's if any...) for proper installation and
connection.
14
15
Check the avaibility of certification documents according hazardous area motor installation.
16
17
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 11 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( LV MOTOR )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check that motor terminal box flanges are clean and greased and that all
bolts are present.
Check that motor shaft rotates freely in both directions (driven equipment uncoupled).
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 12 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( NEUTRAL EARTH RESISTOR )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
Check Neutral Earth Resistor is clean and free from dust and debris.
Check cable glands (if any) and terminals for proper size and installation.
10
11
12
13
Ensure gland plates for outgoing single core cables are non-magnetic.
14
15
CHECKED
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 13 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( LIGHTING/OBSTRUCTION LIGHTS )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Record hereunder the characteristics of circuit and check the conformity against design.
Check that all fittings are correctly mounted, accessible and that they do not clash with pipe runs and other equipment.
Check all fittings and J.B's are undamaged and are installed in accordance with layout drawings and one line
diagrams.
Check circuit earthing and bonding are in conformity with project specifications.
Check all circuit idents are complete for fittings, cables and distribution board.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 14 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( SOCKET OUTLETS & WELDING RECEPTACLES)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Record on continuation sheet(s) the characteristics of circuit and the name plate data,
and check conformity against one-line diagram and project data.
Check all socket outlets are undamaged, correctly mounted, accessible, and conform to project specifications.
Check all J.B's are undamaged and are installed in accordance with layout drawings
and one line diagrams.
Check all circuit idents are complete for fittings, cables and distribution board.
10
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 15 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( CONTROL STATION )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
1
2
CHECK LIST
CHECKED
Check all bolts are fitted and all unused entries are suitably plugged.
Check all earthing and bonding are in accordance with project specifications.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 16 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( JUNCTION BOXES/MARSHALLING BOXES )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check all flange faces are clean and greased with approved lubricants, and that
all bolts are fitted and correctly tight (Exd only).
Check all gaskets and bolts are fitted in covers and gland plates where applicable (Exe).
Check that terminals are approved and that the correct numbers are fitted (refer to
manufacturer's certificates).
10
11
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 17 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( BUS DUCT )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Visually inspect the Bus duct for any foreign object inside.
Check all covers and cover bolts are correctly fitted, specified IP rating is achieved and danger labels are
correctly installed.
10
11
12
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 18 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( MV CABLE )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
Check cable tags are correct and installed at both source and destination.
10
11
12
Check stress cones are correctly installed, stress relieved and earthed.
13
14
15
CHECKED
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 19 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( LV POWER AND CONTROL CABLES )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check cables are adequately supported and correctly fixed to rack according to
Project Specification.
8
9
10
11
12
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 20 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( TRACE HEATING )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
Check Heat Trace data is correct and suitable for area classification.
Check all tapes and junction boxes are installed according to drawings.
Check all tapes characteristics against project data (type, rated power).
Check cable glands and terminals for tightness and proper installation.
10
11
12
13
14
15
CHECKED
Check the avaibility of certification documents according hazardous area equipment installation .
Produce a defects list for punch list issue.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 21 of 23
ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( EARTHING & BONDING SYSTEM )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
CHECK LIST
CHECKED
Check all earth bars are installed and labeled in accordance with project drawings.
Check all connections are tight, clean and coated with an approved anti-corrosive
grease.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 22 of 23
INSTRUMENT
PRE-COMMISSIONING CHECK LIST
(FIELD INSTRUMENT )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:
SERIAL NO. :
REV. :
SERIAL NO. :
ITEM
1
2
3
CHECK LIST
Check the capacity of cable racking match the quantity and sizes of cables.
7
8
CHECKED
Check that equipment is earthed and bonded in accordance with drawings and
specifications.
Produce and issue a punch list of defects.
REMARKS:
DATE
NAME
SIGNATURE
Technician
Verified By
Client
FM-PT-05-00
Page 23 of 23