ELECTRICAL

PRE-COMMISSIONING CHECK LIST


(GENERATOR )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( GENERATOR )
ITEM

CHECK LIST

CHECKED

Check equipment is de-energized and safe.

Check generator data conformity against data sheet / project specification (rating plate)

Check preservation status and anti-condensation heater is ready to be energized

Check general mechanical arrangement.

Check all auxiliary devices (cooling fans, vibration & temperature probes, CT's, VT's,,, if any) for proper
installation and connection

Check generator tagged against drawings

Check earthing and bonding against drawings.

Check neutral eathing

Check power and auxiliary terminal boxes for cleanliness.

10

Check power and auxiliary terminal boxes tightness.

11

Check cable glands conformity.

12

Check cable glands are correctly mounted (power and auxiliary terminal boxes)

13

Carry out all checks as required by Manufacturer.

14

Check coating integrity.

15

Check the availability of certification documents against hazardous area generator installation.

16

Check supplier's documentation and drawings.

17

Produce a defects list for punch list issue.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 1 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
(MV SWITCHBOARD)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check switchboard is de-energized and safe.

Check conformity against data sheet and project specification.

Check preservation status and anti-condensation heaters are ready to be energized.

Check equipment is correclty aligned, leveled, rigid and secured with correct bolting.

Check all panel mounted devices are undamaged and tagged in accordance with data.

Check if construction rating plate data is correct.

Check bus bars and supports are clean and clear of debris, torque all bolts to specification.

Check earthing and bonding of all equipment against drawings

Check gland plates (if any) and terminations are correct and suitable for external cabling.

10

Check all switching devices are mechanically operational and undamaged.

11

Check switchgear mechanical interlocks against interlock diagram

12

Check all shutters are identified, operational and lockable.

13

Check C.T's &VT's are properly installed and match drawing and protection diagram.

14

Check protection relays against protection diagram

15

Check protection relays are tagged correctly.

16

Check interconnection wiring against drawings.

17

Check all fuses and switchgear ratings ( circuit-breakers , contactors , etc,,,)

18

Check power cables are properly fitted and armour and screens earthing is correct

19

Check vendor special tools are available.

20

Check suppliers document

21

Produce a defects list for punch list issue.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 2 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
(LV SWITCHBOARD)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check equipment is de-energized and safe.

Check preservation status and requirements to energize anti condensation heaters.

Check equipment is correctly aligned, level, rigid and secured with correct holding
down bolts.

Check all panel mounted devices are undamaged and tagged in accordance with data.

Check name plate data and equipment tags are correct.

Check bus bars and supports are clean and clear of debris torque all bolts to
specification.

Check bus bars Ductor test at all split joints.

Check earthing and bonding of all equipment is in accordance with project specification.

Check gland plates and terminations are correct and suitable for external cabling.

10

Check all circuit breakers are mechanically operational and undamaged.

11

Check all circuit breakers and starter cubical run freely in compartments and that
all mechanical interlock and fouling plate are correct.

12

Check all shutters are operational and lockable.

13

Check all C.T's are properly installed and accordance with data.

14

Check all V.T's are properly installed and accordance with data.

15

Check all protection relays fit to project schedules and are tagged correctly.

16

Check all internal wiring is correctly loomed and clearly identified.

17

Check all fuses are installed in accordance with data.

18

Check all vendor supplied special tools and safety equipment are available.

19

Produce a defect list for punch list issue.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 3 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
(TRANSFORMER )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check equipment is de-energized and safe.

Check equipment is undamaged and oil levels are correct with no leaks.

Check transformer installation and mountings against drawings.

Check transformer nameplate data is correct.

Check transformer is correctly tagged.

Check cooling fans are fitted correctly, if applicable.

Check all earthing and bonding is in accordance with project specifications.

Check all terminations are clean, undamaged and correctly aligned.

Check that all cables are identified and supported correctly.

10

Check that non-magnetic gland plates are installed when using single core cables.

11

Produce and issue a punchlist of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 4 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( DISTRIBUTION BOARD )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check equipment is de-energized and safe.

Check preservation status and requirements to energize anti condensation heaters.

Check equipment earthing and bonding is in accordance with project specifications.

4
5

Check equipment is correctly mounted, tagged and positioned in accordance with


layout drawings.
Check all covers, doors, gland plates are in order and that all bolts are fitted.
Check all MCB's and ELCB's are rated and tagged in accordance with one line

diagrams. Check the mechanical operation of all MCB's, ELCB's and that incoming
breaker is correct.

Check all internal wiring is correct and clearly identified.

Check name plate and equipment tags are correct.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 5 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( CHARGER / INVERTER )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check equipment is de-energized and safe.

Check equipment is clearly identified and tagged in accordance with layout drawings.

Check equipment is positioned correctly and is accessible and undamaged.

Check manufacturer's nameplate data.

Check all panel-front mounted components, indicators, lamps, meters are securely
mounted and undamaged.

Check all internal components are undamaged.

Check all earthing and bonding are as per the specification.

Check all gland plates are suitable for external cables.

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 6 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( BATTERIES )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check batteries are correctly installed in accordance with manufacturer's instructions


with sufficient clearance and accessibility.

Check batteries are identified and cells tagged correctly.

Check cell type and battery make-up are in accordance with data.

Check all nuts and links are fitted, tightened and greased.

Check all electrolyte levels are correct (if applicable).

Check special tools and safety equipment are available.

Check room is suitably ventilated.

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 7 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( NAVIGATION AIDS/FOGHORN)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check all equipment is correctly installed in accordance with project drawings.

Check equipment earthing and bonding are in accordance with project specifications.

Produce marked-up termination drawing in accordance with installation.

Produce and issue a punch list of defects.

Check that nameplate details and tagging are correct.

Check functionality of local selector switches.

Check that foghorn, foghorn controller and accessories have been installed properly
on foghorn.

Check all cable connection on foghorn frame assembly are proper.

Check Functionality of Nav-aids.

10

Check Functionality of Fog horns.

11

Check Functionality of Secondary Fog horns.

12
13

Check batteries are correctly installed in accordance with manufacturer's


instructions with sufficient clearance and accessibility.
Check cell type and battery make-up are in accordance with data.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 8 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( CONTROL PANEL )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

Check panel is correctly installed in accordance with layout drawing.

Check that panel is undamaged and that all components are in good condition.

Check panel earthing and bonding are in accordance with project specifications.

Check internal wiring is correctly loomed and clearly identified.

Carry out checks in accordance with manufacturer's check list.

Produce and issue a punch list of defects.

CHECKED

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 9 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( ELECTRIC HEATERS )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check equipment is de-energized and safe.

Visually inspect the circuit for external damage.

Check cable glands and terminals for tightness and proper installation.

Check labelling/identification tags are correct and are visible.

Check earthing/bonding are correct and tight..

Check internal wiring is neat and tidy.

Check the avaibility of certification documents according hazardous area equipment installation.

Check Supplier's documentation and drawings.

Produce a defects list for punch list issue.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 10 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( MV MOTOR )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check motor is de-energized and safe.

Check preservation status and anti-condensation heater is ready to be energized.

Check motor is correctly tagged.

Check general mechanical arrangement.

Check shaft rotates freely and quietly in both directions, motor uncoupled.

Check motor data conformity against data sheet and project specification (rating plate)

Check motor earthing against drawings.

Check cooling system is undamaged and is conformity against drawings.

Check phase sequence connection.

10

Check power and auxiliary terminal boxes are clean .

11

Check terminal boxes screws are tighted.

12

Check cable glands are correctly mounted.

13

Check all auxiliary devices (vibration & temperature probes, CT's if any...) for proper installation and
connection.

14

Check painting integrity.

15

Check the avaibility of certification documents according hazardous area motor installation.

16

Check Supplier's documentation and drawings.

17

Produce a defects list for punch list issue.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 11 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( LV MOTOR )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

Check equipment is de-energized and safe.

Check preservation status.

Check motor nameplate data is correct.

Check motor is correctly tagged in accordance with layout drawings.

Check motor earthing is in accordance with project specifications.

Check direction of rotation is marked as per the driven equipment.

CHECKED

Check that motor terminal box flanges are clean and greased and that all
bolts are present.

Check that motor shaft rotates freely in both directions (driven equipment uncoupled).

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 12 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( NEUTRAL EARTH RESISTOR )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

Check equipment is de-energized and safe.

Check equipment is installed according layout.

Check conformity to data sheet / project specification.

Check earthing and bonding against drawings.

Check nameplate data are correct.

Check Neutral Earth Resistor is clean and free from dust and debris.

Check coating integrity.

Check cable glands (if any) and terminals for proper size and installation.

Check all bolts and nuts are tight.

10

Check equipment tagging against drawings.

11

Check no mechnical damage and no damage to paintwork.

12

Check warning labels and safety instruction are installed.

13

Ensure gland plates for outgoing single core cables are non-magnetic.

14

Check Supplier's documentation and drawings.

15

Produce a defects list for punch list issue.

CHECKED

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 13 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( LIGHTING/OBSTRUCTION LIGHTS )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check that the equipment is de-energized and safe.

Record hereunder the characteristics of circuit and check the conformity against design.

Check that all fittings are correctly mounted, accessible and that they do not clash with pipe runs and other equipment.

Check all fittings and J.B's are undamaged and are installed in accordance with layout drawings and one line
diagrams.

Check circuit earthing and bonding are in conformity with project specifications.

Check all circuit idents are complete for fittings, cables and distribution board.

Ensure that lighting is tagged correctly as per drawing.

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 14 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( SOCKET OUTLETS & WELDING RECEPTACLES)
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check that the equipment is de-energized and safe.

Record on continuation sheet(s) the characteristics of circuit and the name plate data,
and check conformity against one-line diagram and project data.

Check all socket outlets are undamaged, correctly mounted, accessible, and conform to project specifications.

Check all J.B's are undamaged and are installed in accordance with layout drawings
and one line diagrams.

Confirm mechanical interlock is operational at each socket.

Check phase connection and tightness of terminals

Check circuit earthing is in accordance with project specifications.

Check all circuit idents are complete for fittings, cables and distribution board.

Produce and issue a punch list of defects.

10

Ensure sockets are tagged correctly as per drawing.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 15 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( CONTROL STATION )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

1
2

CHECK LIST

CHECKED

Check equipment is installed in accordance with layout drawing and is undamaged.


Check that control station and additional emergency stop button are accessible and
within two meters of the controlled device.

Check buttons/selector switch is free and operational.

Check all bolts are fitted and all unused entries are suitably plugged.

Check all earthing and bonding are in accordance with project specifications.

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 16 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( JUNCTION BOXES/MARSHALLING BOXES )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

Check that the equipment is de-energized and safe.

Check enclosure is correctly mounted and easily accessible.

CHECKED

Check all flange faces are clean and greased with approved lubricants, and that
all bolts are fitted and correctly tight (Exd only).

Check all gaskets and bolts are fitted in covers and gland plates where applicable (Exe).

Check enclosure is correctly tagged ad per drawing.

Check nameplate data/certification is in accordance with project data.

Check that terminals are approved and that the correct numbers are fitted (refer to
manufacturer's certificates).

Check enclosures is correctly earthed in accordance with project data.

Check segregation barriers are fitted where necessary.

10

Check all unused entries are plugged with approved blanks.

11

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 17 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( BUS DUCT )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check equipment is de-energized and safe.

Check preservation status and anti-condensation heaters are ready to be energized.

Check bus bar supports/insulators are undamaged and clean.

Check for missing bolts.

Visually inspect the Bus duct for any foreign object inside.

Check Bus duct for any damage.

Check equipment is correclty aligned and leveled, rigid and secured.

Check bolts are torqued according to Manufacturer's requirements.

Check all covers and cover bolts are correctly fitted, specified IP rating is achieved and danger labels are
correctly installed.

10

Check earthing against drawings.

11

Check nameplate data.

12

Produce a defect list for punch list issue.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 18 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( MV CABLE )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

Check cable physical integrity.

Check cable for any physical damage.

Check cable data against cable schedule.

Check cable routing against drawings (segregation, distance).

Check cable is adequately supported, supports and cleating are in place.

Check cable tags are correct and installed at both source and destination.

Check bending radius is within the specified limits.

Check cable and core marking against drawings.

Check glanding and locknuts are in correct size and tight.

10

Check phasing and phase identification are correct and installed.

11

Check cables is mechanicaly protected near equipment.

12

Check stress cones are correctly installed, stress relieved and earthed.

13

Check cable earthing / bonding are correct and tight.

14

Check gland plate for single core cables is non ferrous.

15

Produce list of defects for punch list issue.

CHECKED

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 19 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( LV POWER AND CONTROL CABLES )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

Check cables are routed in accordance with cable layout drawings.

Check cables for any physical damage.

CHECKED

Check cables are adequately supported and correctly fixed to rack according to
Project Specification.

Check all bends are within the specified limits.

Check cable is correctly loomed and segregated in accordance with specification.

Check cable and core marking are in accordance with specification.

Check glands, shrouds and earthing are in accordance with specification.

8
9

Check terminations are in accordance with termination diagram, and produce


"AS BUILT" terminations drawings.
Check spare cores for control cables are terminated/earthed/coiled/capped
as per termination drawing

10

Check cables are as specified in project cable schedule.

11

Check gland plate for single core cables is non ferrous.

12

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 20 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( TRACE HEATING )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

Check that the circuit is de-energized and safe.

Check Heat Trace data is correct and suitable for area classification.

Check labelling / identification tags are correct and are visible.

Check junction box is properly mounted and supported.

Check junction box is clean and free of dust and debris.

Check all tapes and junction boxes are installed according to drawings.

Check all tapes characteristics against project data (type, rated power).

Check cable glands and terminals for tightness and proper installation.

Check cables are correctly supported and cleated at junction box.

10

Check all tapes and junction boxes are undamaged .

11

Check rating of circuit breaker against drawings.

12

Check circuit earthing and bonding against drawings.

13

Check thermostat installation (if any).

14
15

CHECKED

Check the avaibility of certification documents according hazardous area equipment installation .
Produce a defects list for punch list issue.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 21 of 23

ELECTRICAL
PRE-COMMISSIONING CHECK LIST
( EARTHING & BONDING SYSTEM )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

CHECK LIST

CHECKED

Check all earth bars are installed and labeled in accordance with project drawings.

Check all earth cables are correctly installed and tagged.

Check all connections are tight, clean and coated with an approved anti-corrosive
grease.

Verify earthing networks segregation actually conforms to specification.

Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 22 of 23

INSTRUMENT
PRE-COMMISSIONING CHECK LIST
(FIELD INSTRUMENT )
PROJECT NAME:
PROJECT NUMBER:
MODEL NO. :
DATA SHEET NO. :
TEST EQUIPMENT :
TEST EQUIPMENT CAL/DATE:
FULL RANGE AND UNIT:
DRAWING NO:

SERIAL NO. :
REV. :
SERIAL NO. :

ITEM

1
2
3

CHECK LIST

Check cable racking is undamaged and is installed correctly in accordance with


layout drawings without clash with pipe runs or other equipment.
Check all cable rackings are adequately supported in accordance with specifications.
Check that cables segregation is correct according to project standards and
specifications.

Check that MCT's conforms to project standards and specification.

Check the capacity of cable racking match the quantity and sizes of cables.

Check insulation pads are adapted to stainless steel racking.

7
8

CHECKED

Check that equipment is earthed and bonded in accordance with drawings and
specifications.
Produce and issue a punch list of defects.

REMARKS:

DATE

NAME

SIGNATURE

Technician
Verified By
Client

Proj.Team. Dept. PT.CTE

FM-PT-05-00

Page 23 of 23