Sei sulla pagina 1di 226

Griffith Univ., 29, Sept.

, 2010

Overview of
Shield Tunnelling Technology
Lecturer: Prof. M. Sugimoto
Nagaoka University of Technology

CONTENTS
1. Selection of tunnelling methods
2. Shield technology
3. Advanced tecnology
4. Recent topics

1. SELECTION OF
TUNNELLING METHODS
NATM

Item

Shield

Cut &
cover

Ground Soil tupe


conditon
Soil

Soft rock
Hard rock

Ground water level


under
over

Face stabilization
unexpected
expected
Location Depth
near ground surface
shallow
deep
3

2. SHIELD TECHNOLOGY
Interaction between
tunnel & ground

Segment

TBM
4

2.1 TBM
Classification
Shield type

Open shield

EPBS

Slurry shield

Partially open shield

TBM
Dual mode

Classification
Manual excavation mode
Manual excavation
Open shield

Semi-mechanical mode
Excavation by hydraulic shovel etc.
Mechanical mode
Excavation by rotational cutter head

Shield tunnelling
Partially open shield

Blind mode
Soil removed by driving force

Closed shield

Earth pressure balanced mode


Face stability by excavated soil
Removing the excavated soil by screw

conveyor
Slurry mode
Face stability by slurry pressure
Removing the soil by fluid transport
6

Full face open shield - Manual excation mode

Full face open shield - Semi mechanical mode

Full face open shield - Mechanical mode

Partially open shield - Blind mode

10

Closed shield - Slurry mode

11

Closed shield - Earth pressure balance mode

12

Closed shield vs. Open shield


Item
Applicable ground
condition
Face stability
Efficiency of
construction

Closed shield
Can cope with a wide range of
ground conditions, i.e., from soft
clay, loose sand, gravel to soft
rock.
Relatively easy, since the shield
system have the function to
stabilize the face.
Advances in mechanization have
resulted in increasing efficiency
and labor saving. Excavation
rate is faster.
In principle, no auxiliary works
are required for tunnelling.

Open shield
In principle, the face must be
stable.
Relatively difficult.

It is difficult to increase
efficiency or save labor, since it
depends on labor. Excavation
rate is slower.
Ground stabilization
A ground stabilization work is
works
essential to secure the face
stability.
Construction cost
The unit cost per volume is about the same, depending on the ground
condition, sometimes cheaper with closed shield.
Troubles in construction Fewer troubles
Many troubles

13

Slurry shield vs. EPBS


Item
Applicable ground
condition

Slurry shield
Mainly sandy soils. Also can
cope with clay and sand-gravel
layers. Particularly excellent
against high ground water
pressures.

Applicable diameter

Used for medium-and small


diameter tunnels and some largediameter tunnels.
Slurry treatment plant is
necessary, then larger space is
required.
Small
Electric power increasingly

Size of facilities
Cutter torque
Cutter driving mode

Earth pressure balanced shield


Mainly clayey soils. Using mud
pressure shield, can cope with
sandy soils and sand- gravel.
Particularly excellent for handling
larger gravel size. Many
construction records.
Many construction records for
medium- and small-diameter
tunnels.
Relatively small.
Larger
Hydraulic power in many cases

14

Flow of shield selection


1. design condition

(1) shapes
(2) dimension
(3) length
(4) tunnel depth
(5) curve radius
(6) gradient
(7) lining method

2. ground condition

(1) composition and variation of ground


(2) soil condition
(3) ground water level
(4) pore water pressure
(1) face stability
(2) permeability
(3) ventage ratio (air permeability)
Supplemental method is necessary or not

3. environmental condition

(1) river, sea lake


(2) underground structure
(3) structure at ground surface
(4) neighboring structure
(5) road, traffic
(6) condition of the work area
(7) power supply

4. construction capability

(1) construction schedule


(2) safety
(3) working condition
(4) transportation condition

5. economics (cost saving)


6. selection of shield type

15

2.2 Segment
Classification
RC segment Plate type

Steel segment

RC segment Box type

Ductile segment

16

Classification
Material

Section configuration

Joint type

Reinforced concrete

Plate type

Straight bolt joint type

Steel
Ductile cast iron
Composite

Curved bolt joint type


Box type

Pin joint type


Hinge type

17

Design
Classification of structure model
(1) Lining model
1) Bender beam without the reduction of EI.
2) Bender beam with the reduction of EI.
3) Multi-hinge without rotation spring and shear spring.
4) Multi-hinge with rotation spring at hinge.
5) Multi-hinge with rotation spring at hinge and shear spring
between neighbor ring.

18

19

(2) Ground model

1) Continuous medium

2) Spring
4) Nothing
3) No-tension spring
(Winckler's ground model)

20

Classification of load model


(3) Earth pressure
1) V
2) H + V
(4) Resistance earth pressure
1) Resistance earth pressure can be calculated automatically in case that
ground model is composed of 1) continuous medium, 2) spring or
3) non-tension spring.
2) Resistance earth pressure is given apparently in case of 4) nothing in
ground model.
Classification of boundary
(5) Boundary condition between ground and lining
1) Slide in tangential direction
a. fix
b. slide
2) Initial displacement of ground
a. Initial displacement of ground is not omitted.
b. Initial displacement of ground is omitted.
21

Design loads (1)


Category
Main load

Design load
Earth pressure

Hydraulic pressure

Resistance earth pressure

Overburden load
Self-weight

Comment
1. Vertical earth pressure at crown, VU
1) Soft clay or
stiff clay with H/D<1 or
sand with H/D<1
VU = (effective) overburden load
2) Stiff clay with H/D>3 or
sand with H/D>3
VU = Terzaghi's loosening (effective) earth pressure
2. Horizontal earth pressure, H
H = V
V = VU + h
:lateral earth pressure ratio
:(submerged) density of ground
h :depth from crown
H :overburden depth
D :diameter of tunnel
1. Sandy ground
Consider effective earth pressure and hydraulic pressure
separately.
2. Clayey ground
Consider total earth pressure, which means the use of density (not
submerged density) in the calculation of earth pressure.
1. Vertical resistance earth pressure
Assume vertical resistance earth pressure at the bottom of tunnel
so as that vertical force has balanced.
2. Horizontal resistance earth pressure
This pressure is generated due to the deformation of lining.
This load is generated due to the structures on the ground surface.
The weight of lining

22

Design loads (2)


Category
Secondary
load

Design load
Inner-weight
Temporary load under
construction

Dynamic load in earthquake

Comment
The weight of facilities in tunnel.
This load is caused due to following items;
1)Jack thrust
2)Grouting pressure
3)Earth pressure at crown just behind tail
4)Handling
This load is considered in the following conditions;
1)The boundary of layers crosses the tunnel.

Stiff sand

Special load Additional load due to twin


tunnel
Additional load
due to ground settlement

Tunnel
Soft clay

2)Tunnel connects with the vertical shaft.


3)Overburden depth changes rapidly.
4)Soft ground
5)Liquefaction
Geometric shape of twin tunnel causes this load.
1)Additional vertical earth pressure is loaded on tunnel due to
ground settlement.
2)Differential settlement in longitudinal direction causes the
bending moment in the lining.
23

Design load models

Pe :vertical earth pressure


lateral earth pressure ratio
g : self weight of segment per unit length
g :resistance earth pressure due to self weight of segment
qH :resistance earth pressure in horizontal direction
qV: resistance earth pressure in vertical direction
qr: resistance earth pressure in radial direction

24

Moment and axial force on each analysis model

25

Flow of of segment design


START
(1) decide segment type, design load
(2) decide the segment dimension (thickness, reinforced steel)
(3) decide the physical properties (,. spring constant etc.)
(4) calculate sectional force
(5) calculate stress
(6) stress < allowable stress ?
(7) design the detail of segment
(8) check ?
END
26

2.3 Ground movement


Concepts
Ground surface settlement in longitudinal direction

27

Ground surface settlement in transverse direction

28

Three dimensional displacement around face


(a) Clay

(b) Sand

29

Measurements examples
1979 Mexico

1985 Mexico

30

1990s Japan

31

Analysis method
(1) Empirical method: error function form

32

(2) Conventional 2D FEM analysis

: Stress release ratio


33

(3) 3DFEM analysis: Akagi Komiya model


Excavation elements & remesh of ground (Akagi & Komiya)
(a) t=t0
Exca. E

Jack thrust

(c) t=t0+dt

(b) t=t0+dt

Shield

Exca. E

Shield

Ground

Ground

Exca. E

Shield

Ground

34

3D FEM model(NP=7194NE=6636) (Akagi & Komiya)

35

Vertical Disp. at 1.0m above crown (Akagi & Komiya)


Measurement point

0.03514 day

0.21924 day

0.40494 day

0.52266 day

1.12640 day

1.64357 day

36

Vertical Disp. (Akagi & Komiya)


2

Vertical disp. (mm)

Measured
Calculated

-2
-4

1m above crown

-6
-8

0.5

1.5

Time (day)
37

3. ADVANCED TECHNOLOGY
Technology for
safety,
high quality,
economy,
high speed.

3.1 TBM
Sharp curve
Articulated shield
38

Variation of cross section


Rectangular cross section

Swing drum type

Fixed drum type

Box type

DPLEX

39

Double circular cross section

Multi face shield

DOT shield
40

3 circular cross section

41

H & V shield

42

Excavation mechanism
Wing shield

43

DPLEX shield

44

Lattice shield
Lattice jack

Telescopic mechanism

45

Docking / Branching
Mechanical docking

46

Branching

47

3.2 Segment
Saving work
Pin coupler + Mortise & tenon joint Wedge joint

Pin coupler + Bolt joint

48

Segment shape
Honeycomb segment

49

4. RECENT TOPICS
4.1 TBM
Long distance
Wear resistance (cutter bit, seal)
High speed
Continuous excavation
Prediction & control: theoretical model
Lecture 3: Kinematic shield model
Docking / Branching
50

4.2 Segment
Construction loads
Thinner, wider segment

51

No secondary lining: water tight


Wrapping shield

52

Maintenance

Corrosion

Waterproof sheet
53

Renewal
Ex. Renewal of cut & cover tunnel
Advance direction

54

Ex. Renewal of shield tunnel

55

4.3 Ground movement


Neighboring construction
Analysis method
Deep tunnel
Design method (Design loads)

56

Thank you for your kind attention !!

57

Griffith Univ., 29, Sept., 2010

Case studies on shield tunnelling


- SENS Lecturer: Prof. M. Sugimoto
Nagaoka University of Technology
(Courtesy of JRTT and Kumagai-Gumi)

CONTENTS
1. What is SENS?
2. Sanbongihara Tunnel
2.1. Site description
2.2. Quality of primary lining concrete
2.3. Placing primary lining concrete
2.4. Construction records
2

Poster No.15

1. What is SENS ?
Concept of SENS

S hield tunnelling method


+
E xtruded concrete lining
+
N ATM
S ystem

Face stability
=shield tunnelling

Muck handling
=shield tunnelling

Cast-in-place concrete
= ECL

SENS

Primary lining
= NATM

Poster No.15

Target of SENS
G eologicalC haracteristics
AlluvialG round DiluvialG round

Low

Soft Rock

NATM in m ountain area

SENS

cost
NATM in urban area

high

Shield M ethod
4

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Comparison of tunnelling methods

Placing
method
Function
of lining
Groundwat
er leakage
& cracking

NATM

Shield tunnnelling

ECL
Cast-in-place
concrete

Allowable

Not allowable

Not allowable

SENS
Cast-in-place
Segment
Shotcrete
concrete
Stabilizing the
Stabilizing the
Stabilizing the
Stabilizing the
excavated space excavated space excavated space excavated space
Watertight
Watertight
Allowable

2. Sanbongihara Tunnel
2.1. Site description
Location (1)
Sapporo

Aomori
Hachinohe
Morioka

Under construction
Sendai

Tohoku Shinkansen Line


Tokyo-hachinoke (on survice)
Omiya
Tokyo
Osaka

Location (2)
Tohoku Shinkansen Line
Shin-Aomori St.
Lake Ogawarako
Aomori City

Shichinohe St.

Pacific Ocean

Misawa City

Sambongihara Tunnel

Lake Towadako

Hachinohe St.
7

Geological profile
Sambongihara
tunnel
L=4,280
Sanbongi
hara Tunnel

,m
SENS
L=3,014.8
m.
SENSsection
Section
,

NATM
section
L=1,265.2
m

Section
,
.
ExplanatorLegend
y Notes ofStrata
Vol
cani
c Ashes
Strata
l
ta
ta
Volcanic
ash layer
nne
Tun
d
c Ashes
Strata

e Volcani
te
Volcanic
ash layer
oun P oint
Under ground
rgr ntunnel
P.
iSandy
Soi
lStrata Connection
nde ctiopoint
Nos1
Nos1Nohej
Noheji
sandy
layer
Uconection
e
n
Co
iCohesi
ve Soi
lStrata
Noc
Noc Nohej
Noheji
cohesive
layer
iSandy
Soi
lStrata
Nos2Nohej
Noheji
sandy
layer
Nos2

(Under
(Underconstruction)
Construction)
The starting point of SENSEN

ofS
nt
P oi
g
rtin de)
S ta e S i
The thioinoh
cc
(SHea

SENS

(Hachinohe side)

70.00

60.00
50.00

ta

ta

e
Nos1

40.00

ta
Nos1

30.00
20.00
10.00

Noc
A Nos2

Nos2
Noc

ta

Nos1

NATM

ta

Nos1

int
Po
t
r
c
Sta Seside) ide)
(Shin-Aomori
The N A TM oriS
m
of
Ao
in(Sh

The starting pointinofgNATM


tionsection

ta

Nos1

Noc
Nos2
Noc

Nos2
Noc

Noc
Nos2
Noc

Noc

Noc

Nos2
A

0.00

Tunnel length
NATM section length
SENS section length
Maximum
overburden

4,280 m
1,265.2
m
3,014.8
m
45 m

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Collapse at face using NATM


Safety: Collapses occurred twice.
Cost: Measure and restoration work against collapse
Performance: 40m per a month (average progress)

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Construction schedule
2001. 8 Excavation started from Shin-Aomori side by NATM.
2002. 3 Collapses occurred at face.
2002. 9
The development of SENS was started.
2003. 1 Excavation stopped by NATM.
2004. 7 Excavation started from Hachinohe side by SENS.
2006.11Sanbongihara tunnel was opened.

10

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

2.2. Quality of primary lining concrete


Design method of ECL for urban tunnel
Secondary lining
Primary lining
At disassembling tubular form At completion of operation
Reinforced concrete
Plain concrete or steel fiver
Concrete reinforced concrete
Serviceability Ultimate limit
Ultimate
limit
state
Limit state
limit state
state
for design Limit state of destruction
Limit state of
Limit state of
Limit state of buoyancy
crack width
destruction
Lining
Timing

Design method of SENS


Lining
Timing
Concrete

Primary lining
At disassembling tubular form
Plain concrete
Limit state Ultimate limit state
for design Limit state of destruction
Limit state of buoyancy

Secondary lining
At completion of operation
Plain concrete
-

11

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Quality on workability
Performance
No.
1 Flowability
2 Self-compactibility
3 Segregation
resistance
4 Anti-washout
5 Pumpability

Quality standard
Flowability shall be maintained for the
time from mixing-up to casting.
Concrete shall entirely fill 330 mm thick
space (lining thickness).
Concrete shall not segregate during
pumping or filling.
Loss of cement particles from concrete
placed in water shall be limited.
The required flow of concrete can be
pumped under pressure, and the pumped
concrete quality shall not become worse.

The strength at one day shall be 15


6 Early age
compressive strength N/mm2 or more.
12

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Required quality of primary lining concrete


Control Value
Specified slump flow

60 cm 5cm

Specified slump (After 4 hours)

80% of specified
slump flow value

Volume ratio of air

4.5 1.5

Anti-washout test

pH 12

1-day compressive strength

More than 15N/mm2

28-day compressive strength

More than 30N/mm2

Unit water content

Specified water
content + 20kg
13

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Special slump flow

Anti-washout test

14

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

2.3. Placing primary lining concrete


Procedure
Start of excavation,
placing primary lining
Disassemble tubular form at rear end
End of excavation
Start of tubular form erection

End of tubular form erection


Close shut-off valve
Clean pipelines and pumps
Open shut-off valve

15

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Concrete lining system


Inside the shield machine
Lining concrete
Remixer
Tubular form

Agitator truck
Batcher
plant

Concrete supply pump


Two-way
valve

Shut-off valve

Concrete pump
for casting

16

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Concrete supply pump

Remixer

17

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Concrete pump for casting

Two way valve

18

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Shut-off valve
Shield jack

concrete
Shut-off valve

close

open
Stop form jack

Stop form
19

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Placing primary lining concrete


1. Jacking start
Shield skin plate Stop form jack

2. Jacking end

Ground
Lining concrete
Tubular form
Shield jack
The shield jack is
extended with excavation,
Ground
Lining concrete and lining concrete is
placed in the tail void.
Tubular form

Lining concrete placing

Shield jack extended

3. Tubular form assembly

After the shield jack is


retracted, the tubular
Ground
Lining concrete form is assembled, which
was removed from the
Tubular form
rear end.
20
Shield jack retracted

Tubular form assembly

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Tubular form
10.780 m

1.2m
0.45m

21

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

2.4. Construction records


TBM of SENS
1

ABC D
2

5
6
3
ABC D

10

Section A-A

1 Articulation jack
2 Shield jack
3 Shut-off valve jack
4 No.2 screw conveyor

B-B

12

11

C-C

D-D

5 No.1 screw conveyor 9 Tubular form removal device


6 Stop form jack
10 Cutter motor
22
7 Stop form
11 Stop form
8 Tubular form

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

TBM and tubular form

Tubular Form
TBM
23

Tunnel cross section at SENS


Waterproof sheet
Structure Center

Primary lining t=330mm


(plain concrete)
Secondary lining t=300mm
(plain concrete)

300
330

R=
50
90

0
572
=
R

S.L
R=5

390

R.L
F.L

Invert
Central drain ditch

24

Tunnel dimension of SENS


Diameter of excavation

11,440 mm

Inner diameter of primary lining

10,780 mm

Inner diameter of secondary lining

10,180 mm

Thickness of primary lining

330 mm

Thickness of secondary lining

300 mm

Width of a ring

1,200 mm

25

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Entrance at Hachinohe side

26

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Launching of SENS (1)


Launching tunnel by NATM : 40m

27

Launching of SENS (2)

28

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Ground support mechanism


Work step
Placing
concrete

Ground support mechanism


Concrete casting pressure supports ground reaction
force, and this is finally supported by tubular form.

During
concrete
hardening

Load on the primary lining increases gradually, i.e.,


ground reaction force is supported by the tubular
form gradually.

Disassembling The primary lining bears the ground reaction, which


tubular form
was supported by the tubular form.
After concrete As the strength of primary lining develops, structual
safety increases.
hardening
29

Poster No.15

Crown settlement & convergence with time


Measureed position
615k 828m

Concrete age (days)


35.8

36.9

38.1

40.8

42.9

50.8

52.8

56.0

58.8

100

4.0

80

3.0

60

2.0

40

1.0

20

0.0

-1.0

-20

-2.0

-40

-3.0

-60

-4.0

-80

-5.0

8/4

8/5

8/6

8/9

8/11

8/19

8/21

8/24

8/27

Face position (m)

Displacement (mm)

5.0

T1
T2
T3
N1
N2
N3
Dist. from face

-100

Date
30

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Lining (1)
Primary lining

Invert

31

DEVELOPMENT AND APPLICATION OF SENS

Poster No.15

Lining (2)
Waterproof sheet

Secondary lining

32

Thank you for your kind attention !!

33

Griffith Univ., 29, Sept., 2010

Case studies on shield tunnelling


- URUP Lecturer: Prof. M. Sugimoto
Nagaoka University of Technology
(Courtesy of Obayashi Corp.)

CONTENTS
1. What is URUP?
2. Demonstration work
3. OI area Tunnel

1. What is URUP ?
Background
Urban problem

Intersection with traffic jam


Need for intersection grade separation projects by
a construction method with less impact to the traffic.
3

Conventional method (Cut & cover method)


Road cover

Backfilling

Open cut & road cover

Back fill

Heavy secondary traffic jam


Noise and vibration generated by construction equipment
Long-term adverse effects on the local living environment
4

Conventional method (Non cut & cover method)

Construct shafts

Construct a tunnel

Secondary traffic jam


Noise and vibration generated by construction equipment
Long-term adverse effects on the local living environment
5

URUP Method (Ultra Rapid Under Pass)


End at ground level

Start from ground level

Shallow soil cover excavation

TBM excavates from and to the ground level.


(without shield shafts)
Shallow cover excavation under intersection
(Non cut & cover method)
6

Advantages of URUP Method


No tunnel shafts

Rapid construction

No piling machines

Mitigate noise and vibration

No need for Intersection occupancy


Relieve traffic jam
Intersection

Launch at
ground level

Arrival at
ground level
7

2. Demonstration work
Objective
To ensure
1) Start and end of shield tunnel with an angle
at the ground surface
2) Excavation under a thin overburden layer

Pilot TBM

Width 4.8mHeight 2.15mLength 5.65m


9

Alignment of Pilot Tunnel


Plan view
Plane curve
R=300

Start

Total Length = 100m

Arrival

Longitudinal sectional view


End at GL

Intersection area
(assumed)
Center 1.0D
Edge 0.7D
Edge 0.7D
2.2m
1.5m
1.5m

Approach area
20m

Tunnel area
60m
Vertical curve Vertical curve
R=100m
R=100m

Start From GL
GL

Approach area
20m
10

Excavation (1)
Setup

Excavation in Approach Area


(Ring 5)

11

Excavation (2)
Excavation in Tunnel Area
(Ring 16)

Excavation in Tunnel Area


(Ring 79)

12

Excavation (3)

Excavation in Tunnel Area


(Ring 84)

End of shield tunneling


at ground level

13

Measurement (1)
Face earth pressure
S
L
(Head
1,SL center
side)

100
90

Allowable upper limit


Passive earth pressure

(kP a ) (kPa)
Earth pressure

80
70
60
50
40

Total overburden pressure

30
20

Allowable lower limit


Earth pressure at rest

10

Tunnel excavation

0
0

10

20

30

40

50

60

(m
)
Distance
at face
(m)

Face earth pressure Passive earth


pressure(z2)
Z
2

70

Total
overburden pressure(z)
Z

80

90

100

Z
0 .at
5
Earth pressure
rest (z0.5)

Face earth pressure transmitted through lining ring

14

Measurement (2)
Final ground displacement
In approach area (at 1m laterally from the TBM)
5 0

Left side of machine


Right side of machine

(m m )
Disp.
(mm)

4 0
3 0
2 0
1 0
0
1 0

1 2

-1 0

1 4

1 7

2 0

2 3

7 4

7 7

8 0

8 3

N o

-2 0

Launch side

-3 0

8 6

8 9

9 2

9 5

9 8

N o

Arrival side

Measurement point number

-4 0
-5 0

In tunnel area
100
80

(m m )

Disp. (mm)

60

Trial section
Work area
(assumed)

Work area
(assumed)

Intersection
area (assumed)

40
20
0
-2 0
-4 0
60

26

29

32

35

38

41

44

47

50

53

56

59

62

65

68

71

74

N opoint
.
Measurement
number

15

Measurement (3)
Deviation of lining from the planed alignment
Horizontal alignment

Dev. (mm)

Left
2nd control p.
1st control p.

V. curve

V. curve

H. curve

1st control p.
2nd control p.

Right
Approach area

Dev. (mm)

Approach area

Vertical alignment

Up

Down

Tunnel area

2nd control p.
1st control p.

V. curve

V. curve

H. curve

1st control p.
2nd control p.
16

3. OI area tunnel
Location(1)

Metropolitan Expressway

Central Circular
Shinjuku Route

Central Circular
Shinagawa Route
The Central Circular Route
Central Circular Sinagawa Route
Central Circular Sinjuku Route

Route in service
Route under project
section under project

17
(Pamphlet outlining the Central Circular Shinagawa Route construction project)

Location(2)
The Shinagawa Line of the Central Circular Route
About 9.4-km-long route linking Oi Junction and Ohashi Junction

Pamphlet outlining the Central Circular Shinagawa Route construction project

The OI area tunnel


liking the Bayshore Route of the Metropolitan Expressways and
the Central Circular Shinagawa Route
18

Construction method
Construction conditions
The ground is composed of soft cohesive soil.
The maximum overburden depth is about 25 m.
Near the tunnel site, there are structures such as largescale water outlets of a thermal power plant and
power cable tunnels.
There are housing complexes near the construction site.

URUP method
19

Advantage of URUP method

1. Smaller cut-and-cover construction area


The URUP method reduces the excavation area by
82 percent, compared with cut and cover method.

2. Reducing the influence on existing structures


The URUP method does not require any special auxiliary
work, and the influence on existing structures can be reduced.

3. Reduction in environmental loading


Noise and vibration can be reduced.
The volume of excavated material can be reduced.
20

Outline of the OI area tunnel


Project data
Project name
Construction period
Owner

Central Circular Shinagawa Route, OI


area tunnel construction project
June 25, 2008 to June 30, 2011
Tokyo Metropolitan Government

21

Construction data
Tunnel
Shield type
Outside diameter of shield
Outside diameter of
segment
Inside diameter of segment
Width of segment lining
ring
Shield tunneling length
OI bound tunnel
Ohashi bound tunnel
Retaning walls and culverts
Retaining wall length
Culvert length
Ventilation station
Shape of structure in plan
Inside cross section
Excavation depth
Bridge section
Bridge length

URUP method
EPBS
13.6 m
13.4 m
12.5 m
1.7 m
895 m
345 m
550 m
Cut & cover method
265 m
80 m
Pneumatic caisson method
39 m X 35 m
32 m X 28 m
44 m
2 span prestressed concrete
bridge

22

Overview of the OI area tunnel


View from launching point to ventilation station
OI Kita Ventilation Station
OI-bound tunnnel

Ohashi-bound tunnnel

23

View from ventilation station to launching point

24

Tunnel construction procedure


Arrival at ground level

Launch at ground level

TBM

Turning around and


lifting the TBM
Oi Kita Ventilation Station
25

Turning around and lifting the TBM

Arriving at the
ventilation station

Turning the TBM around

Moving the TBM horizontally

Vertically moving and


launching the TBM

26

Thank you for your kind attention !!

27

Griffith Univ., 30, Sept., 2010

Case studies on shield


tunnelling
Lecturer: Prof. M. Sugimoto
Nagaoka University of Technology

CONTENTS
I

Development of kinematic shield model

II Kinematic model of Articulated shield


III Effect of shield behavior on
ground deformation
IV Recent research
2

I Development of
kinematic shield model
1. INTRODUCTION
2. MODEL
3. SIMULATION
4. VERIFICATION
5. CONCLUSIONS
3

1. INTRODUCTION
Design of equipped capacity
Development of new type shield
Neighboring construction Precise excavation
Empirical control

Theoretical control

Theoretical model on shield behavior


Simulation:shield behavior, ground disp.
Control :shield
Reverse analysis: ground properties

2. MODEL
(1) Site experience
(2) Force on shield
(3) Model of loads acting on shield
(4) Characteristics of proposed
model
(5) Configuration of proposed
model

(1) Site experience


1. Crease mechanism & copy cutter
Sharp curve excavation
Interaction between shield & excavation area

2. Contact between shield & segment


at sharp curve
Tail clearance

3. Jack thrust up Excavation speed


up
Kinematic model
6

4. Rotation direction of CF yawing


angle
Model includes influence of rotation dir. of CF

5. Shield direction Tunnel direction at


curve
Shield slide

6. Loosening earth pressure at segment


design
Loosening earth pressure

1. Interaction between shield & excavation area


Excavated area

Shield

Lining

Shield
Passive state of earth pressure
SECTION A-A

Excavated area
Active state of earth pressure

2. Contact between shield & segment


See Detail A

Shield tail Wire brush

Bulk head
Chamber

C
B

Segment ring
Cutter face
Shield tail
A

f21

DETAIL A

Applied grease pressure


Deformation of wire brush
f22

f21 : Contact force between shield and segment


f22 : Force due to deformation of wire brush and

applied grease pressure

5. Shield direction Tunnel direction

Planned
alignment
Center of cutter face

Excavated area

10

6. Loosening earth pressure (TEPCO, 1985)

Shield

2.70 m
+10 mm

Lining

5.100 m
5.214 m

Horizontal ground movement in front of cutter face


Loosening zone
Void or fill up by cutter foam GL -13.00 m
Cutter face

Chamber
High mud pressure zone
Passive earth pressure developed
Tightening zone

-10 mm
11

(2) Force on shield


f4:Force at face
f3:Jack force
f1:Self weight of shield

f2:Force on shield tail


f5:Force on skin plate
12

(3) Model of loads acting on shield


f5

A
C

A
B

Segment ring
f3

f4

f3

f2

f5

f2
q

f1

f5

f2
A
B

A
C

SECTION A-A

Segment ring

p
A

SECTION B-B

f1 : Self-weight of shield
f2 : Forces on shield tail
f3 : Jack force
f4 : Force at face
f5 : Force on skin plate

SECTION C-C

13

f4: Force at face


no

Chamber
Bulk head

Wmud

CF

mud

mud
no

mud

Cutter face

f41:Normal earth pressure distribution on front face


f42:Normal earth pressure acting along
the outer circumference of the cutter face
14
f43:Weight of slurry or mud

av Un

Kv (Un ) Kvo Kv min tanh


Kvo
Kvo Kv min
ah Un

Kh (Un ) Kho Khmin tanh


Kho
Kho Khmin

Coefficient of earth pressure, K

f5: Force on skin plate


Khmax
ah Un
Kh (Un ) Kho Khmax tanh
Kho Khmax

Kho

Kvmax
av Un

Kv (Un ) Kvo Kvmax tanh


Kvo
Kvo Kvmax

Kvo
Kho
Kvmin
Khmin

Un

Inward normal displacement 0 Outward normal displacement


(Extension)
(Compression)

Proposed ground reaction curve


15

Definition of ground displacement

Ground surface (after deformation)


Ground surface (original)
Shield skin plate

16

Status of overcutting area

Segment
Tail void
Rest of muck
Grouting
material

Ground

Overcutting area atempts to be filled up by rest of muck. 17

(4) Characteristics of proposed


model
FEM
Kinematics
Proposed

Ground Tail clance Kinematic


CF
disp.
Rotation
dir.

FEM

Proposed

Method

Slide

Loosening
earth
pressure

Kinematics

18

(5) Configuration of proposed


model
Jack control
Model
Ground property
Analysis
Simulation
Control
Reverse
analysis

Shield behavior
unknown
given
given

Shield behavior
Jack control
given
unknown
given

Ground property
given
given
unknown

19

3. SIMULATION
(1) Index of shield tunnelling
behavior
(2) Objective function
(3) Flow chart of simulation
20

(1) Index of shield tunneling behavior


Shield behavior

Representatives

x
y
z

h and xT
v and yT

y
p

vs

y
p

21

(2) Objective function


FM

i 1

v
5
M
Mi
i
1
5

SSQ v v Minimum(0)

22

(3) Flow chart of simulation


START
Input parameters:
Ground/Slurry properties, Shield dimension and Jack thrust
Initial value x, y, z, y, p,
x, y, z, y, p,
Shield position
Velocity of shield
Normal earth pressure at rest
Ground displacement

Earth pressure acting


on cutter face

Revised
x, y, z, y,p,

Ground reaction curve


Earth pressure acting on
shield periphery

External load on
cutter face

F 5 & M5

F 4 & M4

F 1, F 2, F 3
M 1 , M 2, M 3

Fp, Fq, Fr
Mp, Mq, Mr
Convergence
Yes

END

No

Levenberg-Marquardt
Method

23

4. VERIFICATION
(1) Numerical tests
Sensitive analysis
Copy cutter effect

(2) Questionnaire survey for site


engineers
3D Shield simulator

(3) Application
Ex. Hiromachi Tunnel
24

(1) Numerical tests


Copy cutter effect

25

Dimension of Shield & Ground


Properties

Dimension of shield
Shield

Jack

Outer diameter
Total length
Self weight
Center of gravity in CM
Center of erector in CM
Open ratio of CF
Thickness of CF
Rotating speed of CF
Radius of chamber
Length of chamber
Number of jack
Cross section area
Radius of jack
Center of jack from CF

4.00 m
4.00 m
1000.00 KN
(0.0,0.0,0.0) m
(0.0,0.0,-1.6)m
0.10
0.30 m
0.90 rpm
1.95 m
0.40 m
12
314.16 cm2
1.75 m
1.20 m

Parameters used for sandy ground layer


Khmin Kho
0.00 0.50

Khmax
5.00

Kvmin
0.00

Kvo
1.00

Kvmax
5.00

kh
cm
Kv
cms
ms
m a b
t
mud
3
3
2
2
3
(KN/m ) (KN/m ) (KN/m )
(KN/m )
(KN/m ) (KN/m2) (K
5000
5000
0.00 0.10 0.00 0.00 30 1
20
200

26

Simulation condition
After 15 m advance of the shield
in a horizontal straight line

Jack force and moment


F3r = 5000 kN
M3p = -1590 kN-m
M3q = -1247 kN-m

Time
Total simulation time = 60 hrs (360
steps)
Time interval
= 10 minutes

27

Analysis
Case

Case A without the copy cutter


Case B with the copy cutter
length 4 cm at 22.5 to 157.5 deg
157.5 deg
Range of copy cutter used
q

22.5 deg.

Front face view


28

Shield trace
x -coordinate (m)

19

Case A
20

Case B

21

Vertical plane
22
0

20

40

Advanced distance (m)

60

80

40

y -coordinate (m)

Horizontal plane
30
20

Case B

10
0

Case A
-10
0

10

20

30

40

z -coordinate (m)

50

60

70

29

0.05
0.00
-0.05
0.001
0.000
-0.001
0.06
0.04

-200
3
2
1
0
-1
1.5
1.0
0.5
0.0
0
-2000
-4000

p (min)

yT (min)

0.02
0.00
100
0
-100

y (min)

xT (min) vs (m/min) v (1/m)

h (1/m)

Parameter during shield simulation

-6000
150
100
50
0

C ase A
C ase B

20

40

60

Advanced distance (m)

80

30

Length of shield (m)

Cutter face

Case A

2.0

Length of shield (m)

0.0
4.0

Shield tail
Cutter face

Case B

2.0

0.0
0

Invert

Spring line

Crown

4.0

Spring line

Invert

Normal ground displacement


around the shield for step 100 (cm)

90

180

270

Circumferential direction (degree)

Shield tail

360

31

Length of shield (m)

Length of shield (m)

Invert

Spring line

Crown

4.0

Spring line

Invert

Normal earth pressure acting on shield


for step 100 (kN/m2)
Cutter face

2.0

Case A

0.0
4.0

Shield tail
Cutter face

2.0

Case B

0.0
0

90

180

270

Circumferential direction (degree)

Shield tail

360

32

Force and Moment Components


F1
F2
F3
F4
F5
F

Case A (MN, MN-m)


Fp
Fq
Fr
1.00 0.00 0.00
-0.50 0.00 0.00
0.00 0.00 5.00
0.04 0.03 -4.20
-0.54 -0.03 -0.80
0.00 0.00 0.00

Mp
0.00
0.00
-1.59
-0.03
1.62
0.00

Mq
0.00
0.40
-1.25
0.20
0.65
0.00

Mr
0.00
0.00
0.00
0.92
-0.92
0.00

F1
F2
F3
F4
F5
F

Case B (MN, MN-m)


Fp
Fq
Fr
1.00 0.00 0.02
-0.50 0.00 -0.01
0.00 0.00 5.00
0.04 0.03 -4.53
-0.54 -0.03 -0.48
0.00 0.00 0.00

Mp
0.00
0.00
-1.59
-0.02
1.61
0.00

Mq
0.00
0.40
-1.25
0.21
0.64
0.00

Mr
0.00
0.00
0.00
0.95
-0.95
0.00

33

Summary
1. Steady state -Sensitive analysisQualitatively reasonable results

2. Unsteady state -Copy cutter effect(Tunnel alignment & jack force change)
Qualitatively reasonable results

Confirm the validity of the proposed model


34

(2) Questionnaire survey


for shield operator

35

3DSSPC -real time shield simulator-

36

Respondents
Over 21Y
21%

05Y
25%

1620Y
19%

610Y
9%

1115Y
26%

Skilled shield operators43 persons


Cooperate companies: 10 companies

37

Results
Tunnel alignment

1.2
80.2
18.6
5.8
69.8
24.4
15.1
44.2
38.4
22.1
16.3
59.3
4.7
7.0
86.0
5.8
1.2
90.7

Jack pattern
Copy cutter
Thrust
Dir. of CF
Slurry pressure
Slurry density

0.0
0.0
2.3
2.3
2.3
2.3

ave.
0.98
0.92
0.65
0.34
0.31
-0.17

1.2
0.0
2.3
2.3
2.3
2.3

Rotation direction
ave.

1.2
66.3
31.4
0.94
5.8
53.5
40.7
0.90
12.8
38.4
46.5
0.68
19.8
15.1
62.8
0.34
4.7
7.0
86.0
0.31
5.8
1.2
90.7
-0.17
-: can not evaluate unit:%

100

100

100

100

80

80

80

80

60

60

60

60

40

40

40

40

20

20

20

20

Tunnal Alignment

Rotation direction

Jack pattern (%)

Tunnal Alignment

Rotation direction

Slurry pressure (%)

38

Summary
1. Jack pattern, Thrust, Copy cutter
Good agreement with operators experience

2. Dir. of CF, Slurry pressure, Slurry density


Can not evaluate
Small influence on Tunnel alignment
& Shield rotation
Good agreement with operators experience

Confirm the validity of the proposed model


39

(3) Application
Ex. Hiromachi Tunnel

40

Ooimachi St.

Site map

Plain view

Hiromatchi tunnel

Geological profile
Advance dir.

Analysis area

Site description
Ground

Soil type
Tokyo clay (Dc3) (N=122)
Depth
10.700 13.360 m
Underground water level
GL -4.506 -9.154 m
Alignment min Radius
H 245 m V 4000m
Slope
up 19.05 down 32.50
Shield
Type
Slurry type
Outer diameter
Length of machine

7.260 m
8.685 m

x-coordinate(m)

5.0

Dev. = 2 cm
6.0

Observed

Calculated

end

start

7.0
9000

y-coordinate(m)

H alignment

V alignment

Results -shield trace-

start
8990

Dev. = 3 cm

8980

end
8970
-43795

-43785

-43775

z-coordinate(m)

-43765

-43755

Results -shield rotation & velocityy (min)

Observed

Calculated

8700

8200

p (m in )

-100

100
0.10

v s (m/min)

Velocity Pitching Yawing

9200

Observed

Calculated
0.05

0.00
127

131

135

139

143

147

151

155

159

Distance (m)

44

3.0
2.0
1.0

Kh
Kv

0.0
-0.02

-0.01

0.00

Un (m)

0.01

0.02

Ground reaction curve (Ku)

Invert

Spring line

Crown

Spring line

Invert

Length of shield(m)

4.0

8.565

90

180

270

8.565

Cutter
face

Shield
tail tail
Shield
360
Cutter face

Cutter
face

Length of shield(m)

5.0

Normal earth pressure (kN/m2) Normal disp. (cm)

Results -ground disp. & earth pressure- (L=157.2 m)

Shield
tailtail
Shield
0

90

180

270

360

Circumferential direction(deg)

Summary
1. Shield behavior
Good agreement with measured data

2. Normal disp. of ground around shield


Normal earth pressure around shiel
Good agreement with tunnel alignment

Confirm the validity of the proposed model


46

5. CONCLUSIONS
1. Development of kinematic shield
model
Site experience
Model of loads acting on shield
Simulation algorithm
Real time shield simulator

2. Validation
1) Numerical tests
2) Questionnaire survey for site engineers
3) Application

Confirm the validity of the proposed model


47

II Kinematic model of
Articulated shield
1. INTRODUCTION
2. MODEL
3. SITE DESCRIPTION
4. SIMULATION RESULTS
5. CONCLUSIONS
48

1. INTRODUCTION
Operation at sharp curve
Applying jack moment by selecting jack pattern .
Using copy cutter to increase excavated area.
Articulation of the shield to negotiate a curve.

Decrease ground reaction force against the shield.


Prevent excess over cutting.
Minimize ground disturbance.
49

Copy cutter

End Position
q

Length of CC used
Range of CC used
Start Position
p

View from cutter face


50

Articulated shield

Rear body
Front body
Articulated
mechanism

51

Cross section of articulated shield


Segmental lining
Spreader

Chamber

Cutter spoke

Front section

Articulated jack
Shield jack
Articulation point

Rear section
Articulated seal

52

2. MODEL
Model of loads acting on articulated
A
shield
B
C
A

f5

f5

f4
rF

f32
rR
f1

f31

f5

f31

f2

f1

f2

f32

qF

qR

f2

A
f5 B

Front Section

f5

CA

Segment ring

pF

Segment ring
A

pR
A

Rear Section

SECTION A - A

SECTION B - B

SECTION C - C

f32 : Force due to articulated jack


f1 : Self-weight of shield
f2 : Forces on shield tail
f4 : Earth pressure acting at face
f31 : Force due to shield jack f5 : Earth pressure acting on skin 53
plate

Proposed ground reaction curve


Coef. of earth pressure, K

f5: Force on skin plate


Khmax
Kh
Kvmax
Kv
Kv0

Kvmin
Khmin
Inward normal disp.
(Extension)

Kh0
0

Un
Outward normal disp.
(Compression)

54

Simulation of shield behavior


Shield operations

Ground properties

Kinematic shield model

M
M
FFi FRi
i 1
0
5
M
M
M Fi M Ri
i 1

Simulation

Shield behavior

Shield positions
x y z
= Shield postures
p

r
y
55

3. SITE DESCRIPTION
Test site location
End

Analysis area 87168Ring

Start

56

Geological profile at test site

Ds1
Dc2
Analysis area 87168Ring

Ground properties
Ground layer
Unit weight (kN/m3)
Cohesion (kN/m2)
Internal friction angle (deg)
Kho
Kvo
kh kv (MN/m3)

Ds1
17.9
0
34.0
0.441
1.000
365.4

Dc2
17.8
163
0.0
0.750
1.000
866.6
57

Ground reaction curve


5

Kh
Kv

Kh
Kv

4
Ds1

Dc2

0
-0.010

-0.005

0.000

Un (m)

0.005

0
0.010 -0.010

-0.005

0.000

0.005

0.010

Un (m)
58

Dimensions of tunnel and shield


Item
Tunnel

Segment

Shield

Component
Horizontal radius: leftward
Horizontal radius: rightward
Vertical radius
Overburden depth
Hydraulic pressure
Outer diameter
Width: straight alignment
: curve alignment
Thickness
Outer diamter
Total length

Value
100 m
100 m
m
35 - 39 m
0.34 MPa
6.90 m
1.00 m
0.75 m
0.25 m
7.060 m
8.405 m
59

F 3r(MN)

H(min) CC range(deg)CT (MN-m) M 3q(MN-m) M 3p(MN-m)

Shield operation

30

-40

20
10

0
40
-40
0
40
2
0
-2
0
90
180
270
360
180

3 cm

2 cm

Start
End

2 cm

3 cm

0
-180
60

70

80

90 100 110 120 130 140


Distance(m)
60

y(min)
p(min)

-20

v s(m/min)

m(kPa)
3

Mucking data

20
-60
-30
0
30
60
0.04

400
380
360
340
16
14
12
10
1.2
1.0

m(kN/m )

Slurry operation

Rv

r(min)

Shield behaviour

-3000
-2000
-1000
0

0.02
0.00

0.8
60

70

80

90 100 110 120 130 140


Distance(m)

61

4. SIMULATION RESULTS
x-coordinate (m)

Vertical
plane

Measured
Simulation

10
60

50

y-coordinate (m)

Shield trace

-10

40

30

20

Horizontal
plane
10
65

75

85

95

z-coordinate (m)

105

115

125

62

-3000
-2000
-1000

v (m/min)

p (min)

y (min)

Shield behavior

Measured

Simulation

0
-30
-15
0
15
30
0.06
0.04
0.02
0.00
60

70

80

90

100

110

120

130

140

Distance (m)
63

Invert

SL

Crown

SL

Invert

Distance (shield ground) Un(cm) (L=128.56 m)

Length of shield (m)

4.300

180

4.105

Length of shield (m)

90
0

270
360

0
0

90

180
Circumferential direction (degree)

270

360

64

Invert

90

SL

SL

Crown

Invert

Distance (shield ground) Un(cm) (L=128.56 m)

180

270

360

Length of shield (m)

4.300

Length of shield (m)

4.105

0
Circumferential direction (degree)

Right turn

65

Invert

SL

Crown

SL

Invert

Normal earth pressure n(kN/m2) (L= 128.56 m)


Kh
Kv

4.300

Ds1
Ds1
K

Length of shield (m)

1
-200

0
-0.010
5

-400
0

-600

-0.005

0.005

0.010

0.005

0.010

Kh
Kv

-800
-1000

4
Dc2
Dc2

-1200
-1400

Length of shield (m)

0.000

Un (m)

-1800

-1600

2
-2000
-2200
-2400

-2600
-2800
0

90

180
Circumferential direction (degree)

270

360

0
-0.010

-0.005

0.000

Un (m)

66

Force and moment acting on shield (L=128.56 m)


Type Body Force and moment components (MN, MN-m)
Fp
f1
f2
f3
f4
f5
f

Front
Rear
Front
Rear
Front
Rear
Front
Rear
Front
Rear

Fq

Fr

Mp

Mq

2339
0
0
0 4582
1564
0
0
0 -1797
0
0
0
0
0
0
0
0
1
3
0
0
0
0
0
0
993 22831
0 -2927
312
-11 -22697
36 2833
0
0
0
0
0
-2609
423
-71 -4749 -8933
-1606 -1405
-63 4712 6239
0
0
0
0
0

Mr
0
78
0
0
0
127
-763
0
303
255
0
67

5. CONCLUSIONS
1. Shield behavior
Good agreement with measured data

2. Dist. (shield ground)


Normal earth pressure around shield
Good agreement with tunnel alignment

3. Ground displacement

Copy cutter
Articulation of shield

Predominant factor of shield behavior


(It defines ground reaction force on the shield.)

Confirm the validity of the proposed model

68

III Effect of shield behavior on


ground deformation
1. GROUND DISP. AT SITE
2. SIMULATION OF SHIELD BEHAVIOR
3. FEM ANALYSIS ON
GROUND DISPLACEMENT
4. CONCLUSIONS
69

Site map

1000m to Tunnel
Shinkan-sen
crossing

sub
se-c
tio
ma
secintio

1. GROUND DISP. AT SITE


excavation direction
A

P5

Measurement section

P4

P6

P4
No.10
No.5
No.5
NO.26+3m No.9 No.4
No.4
No.8
No.3
Ishiyama High School
NO.25+42m
No.7
No.3
tennis
court
Ground
No.2
No.2
Oh
B No.6 No.1
t
P7

trainning
room

R=R=
404000
m
m

P7
NOO

No.1

P8

P5
P3
tennis
court

tennis
court

su
-ho

us
uir
o

Sh
iel
d

measurement points

w ay
pres s
x
E
n
hi
Meis

nnel
d Tu
l
e
i
h
S

P2

Oo
tsu
F

NA

loo
dw
ay
T

TM

Tu

P1

unn
e

nne
l

en
Op

settlement
Ishiyama surface
high school
ground5
measure
mainsection inclinometer
differential
settlement gauge
surface settlement
submeasure
section differential
settlement gauge
thermo meter

62
34
5
6
1

t
Cu

70

Geological profile
130

110

Tr

100

Kzc

Kzg

Kzc
Kzs

90

Tunnel top
Test area

80

Kzc

Tunnel bottom

300

200

250

Kzs

150

70

100

Elevation (m)

120

Distance (m)
Tr = River terrain
Kzc = Sandy clay

Kzg = Sandy gravel


Kzs = Gravely sand

71

SPT N-Value
60

River terrain Tr

20.82m

40

11.5m

20

10.0m

10

Sandy clay Kzc


20

Gravely sand Kzsg

1.7 m
1.3 m

5.7 m

Sandy gravel Kzg

25
13.5m

Depth (m)

15

3.3 m

Sandy clay Kzc

30

35

40

Sandy clay Kzcs

Gravely sand Kzs

Geological Profile at Test Site

72

TBM

D=12.64m
L=10.25m

73

Site description
Ground

Soil type
Sandy soil (N30)
Depth
12 23.5 m
Underground water level
GL -10 m
min Radius
R 400m Left turn
Alignment
Slope
up 2.49
Type
Slurry type
Shield
Outer diameter
12640 mm
Length of machine
10250 mm

74

Ground displacement instrumentation


Vertical disp.

Horizontal disp.
No.1 No.2 No.3 No.4 No.5

No.1 No.2

No.3 No.4 No.5

4
5
6

4
5
6
7
8

4
5
6

4
5
6
7
8

4
5
6

H=20.5m

1
=

6
2.

4m

1
2
3
4
5
6
7
8
9
10
11
12

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

1
2
3
4
5
6
7
8
9
10
11
12

75

Vertical displacement
2.0

(mm)

2.0

1.0
1.0

No.3-6
No. 3-6
0.0

0.0

Ground
surface
-1.0
-1.0

Final 1.7mm
-2.0

-2.0
-3.0
-3.0

TBM
passing

-4.0
-4.0
2000/6/26 0:00
6/26

2000/6/27 0:00

6/27

2000/6/28 0:00

6/28

2000/6/29 0:00

6/29

1.8m
(No.3-6)

1.8m above crown

2000/6/30 0:00

6/30

2000/7/1 0:00

7/1

2000/7/2 0

7/2

76

Vertical displacement
(mm)
1.5
No. 3-6

Vertical Ground Movement at No. 3-6

1.0

0.5

0.0

-0.5

-1.0
Cutter face

Tail

77

Horizontal displacement at inward of


curve
3.00
3.0

(mm)
Final 2.0mm

No. 2-13

No.2

2.00
2.0

1.0
1.00

Inward

0.00
0.0

Outward

-1.0

-1.00

K2-13
No. 2-13

-2.0

-2.00

TBM
passing

-3.0
6/26

-3.00
2000/6/26 0:00

2000/6/27 0:00

6/27

2000/6/28 0:00

6/28

2000/6/29 0:00

6/29

2000/6/30 0:00

6/30

2000/7/1 0:00

7/1

2000/7/2 0:

7/2

78

Horizontal displacement at inward of


curve
(mm)
3.0

No.Horizontal
2-13 Ground Movement at No. 2-13

2.0
1.0
0.0
-1.0
-2.0
Cutter face

Tail

79

Horizontal displacement at outward of


curve
(mm)

3.00

3.0

No.4

Final 2.0mm

TBM passing

No. 4-13

2.00

2.0

Inward

1.00
1.0

0.00
0.0

Outward

-1.00
-1.0

-2.00
-2.0

No.K4-13
4-13
-3.0
-3.00
-4.0
-4.00
6/26

6/27

6/28

6/29

6/30

7/1

7/2
80

Horizontal displacement at outward of


curve
(mm)
4.0
No. Horizontal
4-13 Ground Movement at No. 4-13

3.0
2.0

R145
FACE

R146

R147

R148

R149

R150

R151

R152
TAIL

1.0
0.0
-1.0
-2.0
-3.0
-4.0
Cutter face

Tail
81

Interaction between TBM & Excavation Surface

400R Left curve

82

Summary
1. Ground displacement
1D from face 1D behind tail
Ground disp. fluctuates due to excavation.
Around face
Outward ground disp. appears due to excavation
(slurry pressure & jack thrust).
Around tail
Passive ground disp. appears at outward of curve due
to shield rotation.
At final stage
Symmetric inward ground disp. appears due to
shrinkage of
83
grouting & force balance.

2. Vertical ground displacement


V. disp. converged behind 2D from tail due to no consolidation.
V. disp. at final is about 1.7 mm.
V. disp. Difference along depth appears after shield passing.
V. disp. above crown = V. disp. at ground surface x 2 at final.
3. Horizontal ground displacement
H. disp. at final is about 2 mm only.
Ground is self-stabilized due to stiff ground.

84

2. SIMULATION OF
SHIELD BEHAVIOR
2.1. MODEL
Kinematic shield model

85

x -coordinate (m)

Shield trace

Vertical plane

-88.4
-88.2

End

Start

-88.0
9170
Horizontal plane

9165
y -coordinate (m)

2.2 RESULTS

-88.6

9160

End

R = 400 m

9155

9150
Observed
Predicted

Start

9145
-14655

-14650

-14645

-14640

z -coordinate (m)

-14635

-14630
86

Shield behavior
y (min)

17400
17600

vs (m/min)

p (min)

17800
-20
-10
0

0.10
Observed

0.05

Predicted

0.00
175

180

185
190
Distance (m)

195

200
87

Results -ground disp. & earth pressure- (L=197.7 m)


(m) Normal
10.25

disp. of ground (cm) Normal earth pressure (kN/m2)

0.00

90

180

270

360 (deg) 0

90

180

270

360 (deg)

2.3 Summary
1. Kinematic shield model
Site experience
Model of loads acting on shield
Simulation method
Application to site data
Simulation of shield behavior

Confirm the validity of the proposed model


2. Excavated area:
predominant factor of shield behavior
89

3. FEM ANALYSIS ON
GROUND DISPLACEMENT
3.1 Conventional method
1. Analysis
conditions
Stress release ratio
Youngs modulus
Analysis area
2. Analysis results
Symmetric results

Passive state ?

90

3.2 2D FEM Model


0

40

58.62m

20

240.64m

Tr
Kzc
Kzg
Kzc
Kzg
Kzs
Kzs

Depth
m
-11.5
-13.2
-16.5
-17.8
-23.5
-37.0
-58.6

N
value
33
11
50
13
50
48
48

kN/m3
18
14
20
14
20
19
19

c
kN/m2
0
66
50
78
50
30
30

30
35
35
40
40

E
kN/m2
16,000
13,800
35,000
16,300
52,000
35,000
83,000

0.4
0.45
0.4
0.45
0.4
0.3
0.3

91

Enforced disp. at tail

Enforced Disp.
=15%

27.1mm

13.6mm

30 15 0 15

14.5mm

92

2D FEM results
Horizontal disp.
Depth (m)
0

Vertical disp.

(mm)

Depth
5 (m)
(mm)

-5

2.4

0
-10
-15

-5
5.4

5.3

-20
-25

-10
2.6
7.2

-15

-30

-20

-35

-27.1
-40
:Observed
-45
:Predicted
:=15%

-50

-25
-20
Time for FEM 2000/6/29 8:50:00
Time for disp. 2000/6/29 8:49:29

:Observed
:Predicted
:=15%

-10

10

20

Time for FEM: 2000/6/29 8:50:00


Time for disp.: 2000/6/29 8:49:29

93

Summary
1. 2D FEM analysis with enforced disp. was proposed.
2. Advantages
Passive ground disp. at outward curve can be
simulated.
Asymmetric ground disp. at curve can be simulated.
3. Problems
Horizontal disp. at outward curve is excessive.
Ground surface at outward curve shows heave.

94

3.3 3D FEM Model


0

52.0 m

20

40

58.62 m m
240.64 m

Tr
Kzc
Kzg
Kzc
Kzg
Kzs
Kzs

Depth
m
-11.5
-13.2
-16.5
-17.8
-23.5
-37.0
-58.6

N
value
33
11
50
13
50
48
48

kN/m3
18
14
20
14
20
19
19

c
kN/m2
0
66
50
78
50
30
30

30
35
35
40
40

E
kN/m2
16,000
13,800
35,000
16,300
52,000
35,000
83,000

0.4
0.45
0.4
0.45
0.4
0.3
0.3

95

Enforced disp. (view from tail)


0.013
0.012

Cutter face

0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001

0.01359

Tail

0.
-0.001
-0.002
-0.003
-0.004
-0.005

-0.0085

-0.006
-0.007
-0.008

96

3D FEM results
Horizontal disp.
(mm)

Depth (m)

Vertical disp.
Depth
(m)
5

(mm)
-5

2.4
0.1

-10

-5
-15

-10

-20

-25

2.2
2.5

-30

2.6
2.7

-15
7.2

-20
-35

-25
-20

-40

-45
:Observed
:2DFEM
:3DFEM
-50

22000/6/29 8:50:00
Time for FEM:
Time for disp.: 2000/6/29 8:49:29

:Observed
:2DFEM
:3DFEM

-10

0
10
T ime for FEM: 2000/6/29 8:50:00
T ime for disp. :2000/6/29 8:49:29

20

97

Comparison of vertical ground disp.

Measurements
2DFEM Disp. input
3DFEM Disp. input
2DFEM =15%

At tunnel crown
(mm)
-0.8
-2.7
-0.5
-27.1

At ground surface
(mm)
-0.5
0.3
-0.1
-13.1

98

Summary
1. 3D FEM analysis with enforced disp. can simulate
asymmetric ground disp. at curve.
ground disp. during tunneling with high accuracy.
Disp. at excavated surface: predominant factor of ground
disp.
2.
2D FEM vs. 3D FEM
2D FEM overestimates passive ground disp. at tail.
3D FEM has a good agreement with measured data.
3D FEM can take account of dist. of enforced disp. in
axial dir..
behavior
3. Simulation
Advantagesof
of shield
proposed
methodgives reasonable ground
disp..
Relative stiffness of ground gives influence on analysis
99

results.

4. CONCLUSIONS
1. Ground displacement at site
1D from face 1D behind tail
Ground disp. fluctuates due to excavation.
Around face
Outward ground disp. appears due to excavation
(slurry pressure & jack thrust).
Around tail
Passive ground disp. appears at outward curve due to
shield
rotation.
Final stage
Symmetric inward ground disp. appears due to
shrinkage of
grouting & force balance.
100

2. Simulation of shield behavior


Shield behavior has a good agreement with measured data.
Distance between shield and ground &
normal earth pressure around shield
has a good agreement with tunnel alignment.
Excavated area: a predominant factor of shield behavior
3. FEM analysis on ground displacement
Proposed 3D FEM model with enforced disp. can simulate
asymmetric ground disp. at curve.
ground disp. during tunneling with high accuracy.
Disp. at excavated surface: a predominant factor of ground disp.
101

IV Recent research
1. Simulation
Kinematic model of articulated shield
Training on shield operation
Evaluation on new type shield behavior
2. Simulation
Control
Reverse analysis

Integration

Development of
shield steering control system

102

Model of loads acting on articulated shield

Notation
f1 : Self-weight of machine

f4 : Force at face

f2 : Force on shield tail

f5 : Force acting on skin plate

f31 : Shield jack force

A : Articulated angle

f32 : Articulated jack force

Influence of horizontal articulated angle

y -coordinate (m)

15

Horizontal jack moment (Turn right)


No horizontal jack moment

+180 min

0 min

-5
180 min

-15
10

20

30

z -coordinate (m)

40

50

Length of rear body (m)


Length of front body (m)

CC length
10 cm
Length of rear body (m)
Length of front body (m)

CC length
6 cm
Length of rear body (m)

Length of fornt body (m)

CC length
0 cm

Influence of copy cutter and articulation


2

0
2

0
2

0
2

0
0
90

Circumferential direction (degree)

180

Un(mm)
270
3600
90

Circumferential direction (degree)

180
270

n(kN/m2)
360

Effective copy cutter length (cm)

Influence of copy cutter and articulation


10
9
Horizontal radius

8
7

600
Optimum curve radius boundary

400

200

80

60
50

40

30 (m)

1
0

20 40 60 80 100 120 140 160 180

Articulated angle (min)

Interactive shield simulator -3DSSPC -

107

Invert
Spring line

5.8

Invert

SL

Crown

SL

Invert

Crown
Face

-0.3
-0.5

Front body

-0.7

Front

Ground displacement &


earth pressure
by continuous excavation
TBM

-0.9
-1.1

-1.5
-1.7
-1.9
-2.1
-2.3
-2.5
-2.7
190
180

Front body

170

Front

160

0.0
5.1

Articulated Point

150
140
130
120
110

Rear

100

Rear body

Shield pushes ground due to


change of vertical moment.

Piching is changed periodically in


each ring.

Tail
Face

90
80
70
60
50
40
30

0.0

Tail

90

180

270

Circumferential direction (degree)

360

Earth pressure (kN/m2)

0.0
5.8

Ground displacement (mm)

Rear body

Articulated Point

Rear

-1.3

0.0
5.1

20

108

Thank you for your kind attention !!

109

Potrebbero piacerti anche