Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
(58.2)
Cycle time used here is 'time required'. Table 58.1 illustrates an example of line
balancing
Table 58.1 Tasks required for assembly of a product (task times in minutes)
Task
Total
Output/day
240
Time
1.2
0.7
0.9
0.9
1.5
1.8
0.4
0.4
1.5
9.3
Hours/day
Table 58.1 shows data about a set of tasks needed to assemble a product. For each
task a standard time is given. The dependence for each activity is an indication of which
other activities need to be done before the given activity can be done. Figure 58.1
shows the logical dependencies as a network diagram. From the volume data it is
possible to calculate the time available. The output per day is 240 so the time available
to assemble each one is 1/240 of a day. The working day is 8 hours or 480 minutes so the
time available is 2 minutes. This means that tasks can be combined together but the
total time at a workstation must not exceed 2 minutes. The actual cycle time may be
less than this. The actual cycle time for a line is the maximum of the values of required
at its workstations. From the total work content, 9.3 minutes, it is possible to calculate
the minimum number of work stations. The value obtained is rounded up to the next
higher whole number.
Minimum no. of work stations = total work content / cycle time
(58.3)
(rounded up to an integer)
In this case the minimum number of work stations is 9.3 / 2 = 4.65 which is rounded up
to 5. This does not means that the number of work stations has to be 5 only that 5 is the
minimum number that are needed to ensure that the time required is below that needed
to achieve the required output. In some cases it may not be possible to achieve this
minimum, in other cases a larger number could be preferred. In many cases there will
not be a single feasible solution but several alternatives.
Figure 58.1
From the activity list and dependencies it is possible to draw a network showing the
sequences of activities. This is shown in Figure 58.1. By visual inspection of Figure 58.1
it can be seen that some activities can be grouped together, up to the limit of the cycle
time. Tasks 1 and 3 can be linked since when task 1 has been done it is possible to do
task 3. Tasks 2 and 4 can be linked since once task 1 has been done both tasks 2 and 4
can be done. Tasks 1 and 5 can not be grouped since task 2 is not done until after task
1 has been done. If it were possible within the time available tasks 1 and 2 and 5 could
be grouped together (but not in this case since the time available would be exceeded).
Figure 58.2 shows a possible grouping of activities for this example and Table 58.2
shows standard times for the 5 work stations.
Table 58.2 Workstations for assembly of a product
Station
Tasks
1+3
2+4
5+7
8+9
Time
1.9
1.9
1.8
1.9
1.9
This table, and Figure 58.2 show that tasks 1 and 3, 5 and 7 and 8 and 9 have been
grouped together.
Figure 58.2
Figure 58.3 shows the work load at each workstation. The balance is not perfect since
the task time at each workstation is not exactly the same. However the line is better
balanced than it would have been if each task had been done at its own workstation.
Figure 58.3
Measures of the efficiency of the line can then be made and compared for alternative
proposals
Line efficiency = 9.3 / 5 x 1.9 =
0.979
(58.4)
(58.5)
(58.6)
Task
10
Time
1.2
2.1
2.3
2.5
4.0
3.2
1.2
1.1
1.6
3.6
1+
2
5+
6
7+8+9
Dependency -
2+ 4+
3 5
58.1 Determine the number of work-stations and the activities that each
should do.