Confidentiality Level

RNC SUbrack Addition-TATA

MOP for RNC Subrack Addition

Author
Prepared by

Manish Sharma

Date

Reviewed by

2016-8-9

07-01-2016

Date

Huawei Confidential.
No Spreading Without Permission.

Page 1, Total 13

Confidentiality Level

RNC SUbrack Addition-TATA

Change Overview

INTRODUCTION:
In TATA 3G new expansion rollout is carried planned. For this purpose RNC Expansion is planned of existing
RNC. For one RNC Subrack-1 and board addition is planned.

1.1 Site Information:

Circle

RNC

Upgrade(CELL)

Activity

MPCG

BHOAL

900-1500

Sub rack Expansion

1.2 Change Objective:


1.
2.
3.
4.

To increase the network capacity


To support new rollout
Where currently only 1 subrack(subrack0 ), addition of 2nd Subrack( Subrack -1)
Where already 1 subrack , board addition is planned.

1.3 PROCEDURE:

Check the DiP Switches of Subrack2

OFF

ON

ON

ON

ON

OFF

ON

Check the Power Proper Cable connections for Subrack-2

Make proper Inter-SCUa connections between the Subracks.

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

OFF

Page 2, Total 13

RNC SUbrack Addition-TATA

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Confidentiality Level

Page 3, Total 13

RNC SUbrack Addition-TATA

Confidentiality Level

Install the Y-Shaped Clock Cables for new subrack.

Figure 1 Connecting the Y-shaped clock cables (taking the GCUa board as an example)

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 4, Total 13

RNC SUbrack Addition-TATA

Rearrange the boards as per the respective BSC layout.

Power-ON the subrack.

Confidentiality Level

Procedure - Installing a Subrack


This section describes procedures and precautions for adding a subrack.

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 5, Total 13

RNC SUbrack Addition-TATA

Confidentiality Level

Prerequisites

The required parts are all ready, including subracks and screws.

If there is space in the cabinet, add the subrack there. If there is no space for a new
subrack, add a cabinet.

Context
NOTICE:
To protect the components from electrostatic discharge, wear an ESD wrist strap properly.
Ensure that the ESD wrist strap is properly connected to the ESD connector on the cabinet. If
no ESD wrist strap or no proper grounding point is available, wear ESD gloves.
NOTICE:
Due to heavy weight, four person are required to install a subrack.

Procedure
1.

Optional: (This step is required only when floating nuts are not installed in the
mounting bar at the front side of the cabinet.) Take floating nuts out of the ESD bag at
the bottom of the cabinet and install them in the place highlighted in yellow, as shown
in Figure 1.
Figure 1 Installing floating nuts

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 6, Total 13

RNC SUbrack Addition-TATA

Confidentiality Level

NOTE:
Three holes in the mounting bar are known as 1 U space. One subrack occupies 36
holes.
One subrack is fixed by 4 pairs of floating nuts installed symmetrically. The floating nuts
are installed in the 3rd, 12th, 25th, and 34th holes above the guide rail where the
subrack will be installed.
2.

person hold the mounting ears and support the base of the subrack. Slide the
subrack along the guiding rail into the cabinet, and then fasten the screws to fix the
subrack.

3.

Set the DIP switch based on the new subrack location according to instructions in DIP
Switch on a Subrack.
NOTICE:

4.

You must set the DIP switch before powering on the subrack. The setting
after the power-on is invalid.
Different subracks must have different DIP-switch settings. If two subracks in
the share the same DIP-switch settings, services on the two subracks will be
interrupted.
If the DIP-switch setting of the new subrack is the same as that of another
subrack and services in the two subracks are consequently interrupted, set the
DIP switches of the two subracks properly and reset the two subracks to restore
services.

Install the power cables and PGND cables for the new subrack.
Install the power cables and PGND cables for the subrack, please refer to Installing
Power Cables and PGND Cables Between a BSC6900 Cabinet and the PDF

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 7, Total 13

RNC SUbrack Addition-TATA

Confidentiality Level

a. Take off the cover of the power cable connection box and unscrew the nuts on
the power ports, as shown in Figure 2.
Figure 2 Unscrewing nuts in the power cable connection box

b. Connect the power cables to the power ports in the subrack, as shown Figure 3.
Figure 3 Connecting the power cable to the power port

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 8, Total 13

RNC SUbrack Addition-TATA

c.

Confidentiality Level

Install the cover of the power cable connection box, as shown Figure 4.
Figure 4 Installing the cover of the power cable connection box

Install a board.

For details, see instructions in Installing the Inter-SCUb SFP+ High-Speed Cables
Between Different Subracks.

Install the Ethernet cables and fiber optic cables for connecting the interface boards.

Installing the Y-Shaped Clock Cables.

Attach the engineering labels to the signal cables according to instructions in Attaching
the Engineering Labels to the Signal Cables.

Install the signal cables for connecting the power distribution monitoring board and the
EMU.
2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 9, Total 13

Confidentiality Level

RNC SUbrack Addition-TATA

Check whether cables in the new subrack are correctly connected.

Turn on the power switch on the power distribution frame (PDF).

10 Turn on the power switch controlling the subrack on the power distribution box.
11 Commission the data loading and services.
For details on the commissioning methods, see Commissioning Guide.
12 Check whether alarms related to subrack failure such as Cell Setup Failure are cleared
after the subrack is replaced. Clear the alarms by referring to the online alarm
reference on the LMT. If the alarms persist, contact Huawei technical support.

1.4 SOFTWARE VERSION:

Current software version

V900R014ENGC00SPH522

M2000 Version

IManagerM2000V200R012C00SPC240

Current nodeb Software Version

V200R014C00SPC378

Change Preparation

2.1 Change Arrangement

BHOPAL
Board layout Planning

Done

IP Planning

Done

Implementation script

Done

iCare RFC

07-01-2016

Subrack Addition

09-01-2016

Subrack Power-On

09-01-2016

Board Installation
Configuration script
Implementation
Verification

09-01-2016
09-01-2016
09-01-2016

2.2 Implemetation
2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 10, Total 13

Confidentiality Level

RNC SUbrack Addition-TATA

Daytime Activities:
S. No.
1

Start Time
11.00PM

End Time
00:00 AM

Activity Description
Backup of Live BSC (BKP DB; EXP
CFGMML; EXP CFGBCP;

00:00 AM

01:00 AM

01:00 AM

Take Alarm Logs


1.

Physical Subrack Addition

2.

Inter SCU cable connections

2:00 AM
Subrack Dip Switch changes and Subrack
Power ON

2:00 AM

3:00 AM

Configuration Changes

03:00 AM

4:00 AM

Observation:
1.

Observe if newAlarms

2.

Observe 1 hr KPIs

2.2 Change Team and Responsibility


2.2.1

List of the Change Team of Customer

Name
Prasad sakpal

2.2.2

09039090505

List of the Onsite Change Team of HUAWEI

Name
Manish Sharma

2016-8-9

Tel.

Responsibility

Responsibility
Change Implementer

Tel.
+918871420712

Huawei Confidential.
No Spreading Without Permission.

Page 11, Total 13

Confidentiality Level

RNC SUbrack Addition-TATA

2.2.3

List of the Support Team of HUAWEI

Name
Shailendra Nalavade

Responsibility
Change Activity

GTAC

Technical support-

Tel.
+919920812635

2.3 Equipment Running Check

Check the Redundancy of Power provided to Subrack-2 from SMPS and PDF.

Check the current patching and Board Status of Subrack

Check the inter-subrack connectivity.

2.4 Change Risks and Mitigations

Risk Description.

o.
Risk would be
1

Possibility

Impact level

(High, Middle

High, Middle,

and Low)
High

low
High

involved if any

2.5

Mitigations

Troubleshoot Alarm/Roll Back

critical Alarm.
KPI Monitioring
Check before the change
No.
1
3
4
5

Cooperation work before the change


Hardware Check and Power
Physical Subrack Addition
Physical Board Addition
Admin Passwords arrangement and PE

2016-8-9

Owner
Huawei
Huawei
Huawei
TATA

Huawei Confidential.
No Spreading Without Permission.

Completion Time
Day of PE
Day of PE
Day of PE
Day of PE

Page 12, Total 13

RNC SUbrack Addition-TATA

Confidentiality Level

Change Operation Procedures

3.1 Change Procedures


3.1.1General Description of Change Procedures:

Physical Subrack Addition

Physicalk Card Addition and Re-arrangement

Power-ON
Run Scripts

3.2 Test Verification


1. Check Alarm
2 . KPI monitoring
3.3 Failure Roll-Back Plan
3.3.1 Roll-Back Procedures
Restore BD and Poer-off new Subrack.
3.3.2Equipment Status Check

All boards and Links status should be normal and services of BSC should be normal.

The KPI and handovers should be normal.

All test call scenarios should be successful.

2016-8-9

Huawei Confidential.
No Spreading Without Permission.

Page 13, Total 13