Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
TITLE OF ITP:
S.I
No.
1.
2.
3.
INSPECTION/AC
TIVITY/TEST
DESCRIPTION
FREQUENCY
OF
TEST/INSPE
CTION
ACCEPTANCE CRITERIA/
TOLERANCE
PARAMETERS
ITP No.
Date:
QUALITY
RECORD
( Forms,
Checklist,
Test
Results))
Rev. No.
RESPONSIBILITY/ACTION
T
P
L
SC
CN
S
PRELIMINARY
Shop Drawing
Project
Specification
& IFC Drawing
Material
Submittal and
Approval
Project
Specification
& Drawing
Concrete Mix
Design
Project
Specification
VOLUME II
Section 4.5
Prior to Start
the Activity
Prior to Start
the Activity
Prior to Start
the Activity
Approved Submittal
Transmittal Sheet with Code
A or Code B
Approved
Submittal
Transmittal
Sheet with
Code A or
Code B
Approved Submittal
Transmittal Sheet with Code
A or Code B
Approved
Submittal
Transmittal
Sheet with
Code A or
Code B.
Approved
Submittal
Transmittal
sheet with
code A or B
CONSTRUCTION PHASE
Page 1 of 5
S.I
No.
4.
5.
6.
INSPECTION/AC
TIVITY/TEST
DESCRIPTION
REFERENCE
DOCUMENT
(Drwg./Spec
s/Contract)
FREQUENCY
OF
TEST/INSPE
CTION
ACCEPTANCE CRITERIA/
TOLERANCE
PARAMETERS
Construction of
Form Work
Support /
Alignment
Project
Specification
VOLUME II
Section 4.32
Every pour
prior to
concreting
Reinforcement/St
eel Fixing
Project
Specification
VOLUME II
Section 4.8 to
4.11
Each
Foundation
Reinforcement shall be
placed and maintained in
the position shown in the
Contract drawings
Cleaning
Project
Specification
VOLUME II
Section 4.32
Prior to cast
concrete
Page 2 of 5
ITP No.
Date:
QUALITY
RECORD
( Forms,
Checklist,
Test
Approved IR
with Status A
or AN
Rev. No.
RESPONSIBILITY/ACTION
T
CN
P SC C
E
A
S
L
Pre-pour check
list F-003
Approved IR
with Status A
or AN
Pre-pour check
list F-003
Prepour check
list F-003
S.I
No.
INSPECTION/AC
TIVITY/TEST
DESCRIPTION
FREQUENCY
OF
TEST/INSPE
CTION
1)All
conditions of
Mix
7.
Concrete Grade
30/20 OPC+GGBS
Project
Specification
VOLUME II
Section 4.8 to
4.15
2), 3), 4)
Each Delivery
prior to
releasing the
concrete
5) Min of one
set (6 nos
cubes) per
casting day
and every 50
m
6) & 7) Each
Pour
ACCEPTANCE CRITERIA/
TOLERANCE
PARAMETERS
1) Ambient temperature is
above 40oC on a rising
thermometer
ITP No.
Date:
QUALITY
RECORD
( Forms,
Checklist,
Test
Rev. No.
RESPONSIBILITY/ACTION
T
CN
P SC C
E
A
S
L
2) C-30/20 SRC
3) Concrete temp shall not
be greater than 32C prior
to placement and
compaction
4) Slump as per approved
Trial mix approval
5) 150 x 150 mm cube
samples prepared in
accordance with BS En
12390-2, demoulded
between 16-24 hrs.
6 ) concrete shall be placed
gently and shall not have a
free fall of more than 2.0 m
7) Level layer no greater
Page 3 of 5
A Approved IR
with Status A
or AN
Concrete
Delivery note
and Test
Report
S.I
No.
8.
INSPECTION/AC
TIVITY/TEST
DESCRIPTION
REFERENCE
DOCUMENT
(Drwg./Spec
s/Contract)
Concrete pouring
Project
Specification
VOLUME II
Section 4.8 to
4.24
9.
Concrete Curing
Project
Specification
VOLUME II
Section 4.8 to
4.26
10.
Removal of Form
Work
Project
Specification
VOLUME II
Section 4.32
11.
FREQUENCY
OF
TEST/INSPE
CTION
Each
Foundation
Each
Foundation
Each
Foundation
Protective
All external
Bituminous
As per IFC
buried
Coating on
drawing
Concrete
precast
surface
foundation
ERECTION OF PRECAST FOUNDATION
ACCEPTANCE CRITERIA/
TOLERANCE
PARAMETERS
ITP No.
Date:
QUALITY
RECORD
( Forms,
Checklist,
Test
Approved IR
with Status A
or AN
RESPONSIBILITY/ACTION
T
CN
P SC C
E
A
S
L
Project Specification
VOLUME II Section 4.8 to
4.26
Approved IR
with Status A
or AN
Project Specification
VOLUME II Section 4.32
Approved IR
with Status A
or AN
Approved IR
with Status A
or AN
Page 4 of 5
Rev. No.
ITP No.
Date:
QUALITY
RECORD
( Forms,
Checklist,
Test
REFERENCE
DOCUMENT
(Drwg./Spec
s/Contract)
FREQUENCY
OF
TEST/INSPE
CTION
ACCEPTANCE CRITERIA/
TOLERANCE
PARAMETERS
Verification of
Original Ground
Level survey
Project
Specification
VOLUME II
Section 6
Clause 6.16
Prior to Start
the Activity
Approved IR
with Status A
or AN
Check evenness
and level of
surrounding
ground level
Project
Specification
VOLUME II
Section 6
Clause 6.17
Every
excavation
Approved IR
with Status A
or AN
14.
Placing of Precast
Foundation
Project
Specification
Volume II-A:
Specification
Section D
Concrete
Works ,
Clause 7.1.9
Each
Foundation
Approved IR
with Status A
or AN
15.
Blinding
Approved
Drawings
Each activity
Approved
Drawings
Each activity
As per manufacturers
instruction
S.I
No.
12.
13.
16.
INSPECTION/AC
TIVITY/TEST
DESCRIPTION
Application of
Waterproofing
Membrane
Page 5 of 5
Rev. No.
RESPONSIBILITY/ACTION
T
CN
P SC C
E
A
S
L
Approved IR
with Status A
or AN
Approved IR
with Status A
or AN
S.I
No.
INSPECTION/AC
TIVITY/TEST
DESCRIPTION
REFERENCE
DOCUMENT
(Drwg./Spec
s/Contract)
FREQUENCY
OF
TEST/INSPE
CTION
ACCEPTANCE CRITERIA/
TOLERANCE
PARAMETERS
17.
Lifting and
Placement of
Precast
Foundation
Approved
Drawings
Each activity
Project
Specification
18.
Grouting
19.
Backfilling &
Compaction
Volume II-A:
Specification
Section D
Concrete
Works, Clause
7.1.3
Project
Specification
Volume II :
Section 6
Clause 6.30
Each
Foundation
Each
Foundation
Page 6 of 5
ITP No.
Date:
QUALITY
RECORD
( Forms,
Checklist,
Test
Approved IR
with Status A
or AN
Rev. No.
RESPONSIBILITY/ACTION
T
CN
P SC C
E
A
S
L
W
Approved IR
with Status A
or AN
Approved IR
with Status A
or AN
S.I
No.
INSPECTION/AC
TIVITY/TEST
DESCRIPTION
All As-built
Records
20.
FREQUENCY
OF
TEST/INSPE
CTION
ACCEPTANCE CRITERIA/
TOLERANCE
PARAMETERS
On
completion
of the work
ITP No.
Date:
QUALITY
RECORD
( Forms,
Checklist,
Test
Approved as
built
submittals
Rev. No.
RESPONSIBILITY/ACTION
T
CN
P SC C
E
A
S
L
LEGEND
ACTION CODE:
S Surveillance
W Witness
R Review of Documents
H Hold Point
DATE
Inspection Authority:
TPL Third Party Laboratory
C Contractor
CNS Consultants
APPROVED BY
ACCEPTED BY
QAQC REPRESENTATIVE
PROJECT MANAGER
CONSULTANT REPRESENTATIVE
DATE
DATE
Page 7 of 5