Sei sulla pagina 1di 17

Technical Proposal & Detail Scope

For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

1 of 17

TECHNICAL PROPOSAL & DETAIL SCOPE


FOR

PROJECT NAME
CLEAN BOILER UNIT 02 POWER PLANT (IRPC)

By :

HYDRODYNE SERVICES COMPANY LIMITED

Customer : IRPC PUBLIC COMPANY LIMITED

Bidding By : MECHANICAL MAINTENANCE STATIONARY


EQUIPMENT SECTION (MSS)

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

2 of 17

General
This document is the technical for Cleaning Boiler unit 02 power Plant of
IRPC PUBLIC COMPANY LIMITED with regard to safety in the workplace. That is
specified in the attached document bidding package. We are HYDRODYNE
SERVICES to prepare the proposal to bidding and technical step for Cleaning
Boiler unit 02 power Plant.
Summary scope:
This proposal and detail cover the requirement for the Boiler internal
cleaning, transfer oil and waste.

The contractor shall perform a detail cleaning,

Contractor shall supply all material, equipments and necessary in order to meet all
requirement of proper and workman like cleaning procedure;
1. Isolate blind.
2. Open and Close manhole.
3. Air Ventilation.
4. High Pressure water Jet/Manual cleaning inside boiler and condenser.
5. Mobilization and De- Mobilization Equipment and tool.

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

3 of 17

CONTENT
DESCRIPTION

PAGE

SECTION 1 MANPOWERS AND EQUIPMENTS/ TOOLS LOADING..........................4


SECTION 2 ORGANIZATION CHART.....................................................................5
SECTION 3 PROCEDURE OF WORK.....................................................................6
SECTION 4 SCOPE OF SUPPLY..........................................................................14
SECTION 5 SCHEDULE PLAN............................................................................15
SECTION 6 SAFETY MANAGEMENT...................................................................16

(MR.SARUNYU TONGTAJA)

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

4 of 17

Senior
Sale Engineer

HYDRODYNE SERVICES CO., LTD.

SECTION 1
MANPOWERS AND EQUIPMENT/TOOL LOADING

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

5 of 17

SECTION 2
ORGANIZATION CHART

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

6 of 17

SECTION 3
PROCEDURE OF WORK
1. Cleaning inside Boiler
1.1.

Isolate blind System

1.1.1.Prepare blind plate at least 5 mm.


1.1.2.Survey blind point around Boiler.
1.1.3.Isolate blind reference blind list from IRPC
1.1.4.Checking and inspection blind.
1.2.

Open Manhole and Ventilation system

1.2.1.Open manhole. Over all.


1.2.2.Install ventilation system.
1.2.3.Start Air for Ventilation Boiler.
1.2.4.Check gas LEL and Oxygen reference standard value.
1.3.

Cleaning inside Boiler

1.3.1.

Cleaning Penhouse and PA duct

A. Prepare PPE and Confine permit approval by IRPC.


B. Prepare Oxygen alert and other safety tool ( SCBA standby).
C. Install lighting 24 V. inside penhuose and PA duct.

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

7 of 17

D.Ventilation has running every time.


E. Remove ASH over all.
F. Manual cleaning inside penhuose and PA duct.
G.Visual inspection Cleaning by IRPC & HDS.
1.3.2.

Cleaning Super heat, Furnace and Boundary air duct zone.

A. Prepare PPE and Confine permit approval by IRPC.


B. Prepare Oxygen alert and other safety tool ( SCBA standby).
C. Install lighting 24 V. inside Super heat, Furnace and Boundary
air duct zone .
D.Ventilation has running every time.
E. Start up High pressure water jet.
F. Cleaning Super heat, Furnace and Boundary air duct zone .
G.Visual inspection Cleaning by IRPC & HDS (Approved by IRPC).
1.3.3.Cleaning Economizer.
A. Prepare PPE and Confine permit approval by IRPC.
B. Prepare Oxygen alert and other safety tool ( SCBA standby).
C. Install lighting 24 V. inside Economizer.
D.Ventilation has running every time.
E. Connect hose at station air IRPC.
F. Air cleaning Economizer.
G.Visual inspection Cleaning by IRPC & HDS.
1.4.

Final Inspection and De-mobilization


A. Final Inspection by IRPC.
B. Close manhole (a new bolt, nut, gasket and torque standard (If
any)).
C. De-blind (a new bolt, nut, gasket and torque standard).

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

8 of 17

D.Housekeeping around site.


E. De-Mobilization Equipment/Tool.

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Manual
Cleaning

High Pressure
water jet Cleaning

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

9 of 17

Penhouse Zone

Super Heat Zone

Economizer Zone

Air
Flush/Manual
Cleaning
High Pressure
water jet Cleaning

Furnace Zone

Diagram show lay out type Cleaning Boiler

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

10 of 17

2. Cleaning Electrostatic precipitator (EP).


2.1.

Isolate blind System

2.1.1.Prepare blind plate at least 5 mm.


2.1.2.Survey blind point around EP.
2.1.3.Isolate blind reference blind list from IRPC
2.1.4.Checking and inspection blind.
2.2.

Open Manhole and Ventilation system

2.2.1.Open manhole. Over all.


2.2.2.Install ventilation system (Air Ventilation inside and outside 1).
2.2.3.Start Air for Ventilation EP.
2.2.4.Check gas LEL and Oxygen reference standard value.
2.3.

Cleaning inside EP.


A. Prepare PPE and Confine permit approval by IRPC.
B. Prepare Oxygen alert and other safety tool ( SCBA standby).
C. Install lighting 24 V. inside EP.
D.Ventilation has running every time.
E. Start up High pressure water jet.
F. Cleaning Electrostatic precipitator (EP).
G.Visual inspection Cleaning by IRPC & HDS (Approved by IRPC).

2.4.

Final Inspection and De-mobilization


A. Final Inspection by IRPC.
B. Close manhole (a new bolt, nut, gasket and torque standard (If
any)).
C. De-blind (a new bolt, nut, gasket and torque standard).
D.Housekeeping around site.
E. De-Mobilization Equipment/Tool.

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

11 of 17

High Pressure
water jet Cleaning

Electrostatic precipitator
(EP).

Diagram show lay out type Cleaning Electrostatic precipitator (EP).

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

12 of 17

3. Cleaning Gas Air Heater (GAH).


3.1.

Isolate blind System

3.1.1.Prepare blind plate at least 5 mm.


3.1.2.Survey blind point around Gas Air Heater.
3.1.3.Isolate blind reference blind list from IRPC
3.1.4.Checking and inspection blind.
3.2.

Open Manhole and Ventilation system

3.2.1.Open manhole. Over all.


3.2.2.Install ventilation system
3.2.3.Start Air for Ventilation Gas Air Heater.
3.2.4.Check gas LEL and Oxygen reference standard value.
3.3.

Cleaning Gas Air Heater


A. Prepare PPE and Confine permit approval by IRPC.
B. Prepare Oxygen alert and other safety tool ( SCBA standby).
C. Install lighting 24 V. inside Gas Air Heater.
D.Ventilation has running every time.
E. Remove Gas Eliment (2 part) go to at cleaning area.
F. Start up High pressure water jet.
G.Cleaning Gas Eliment and inside Gas Air Heater.
H. Visual inspection Cleaning by IRPC & HDS (Approved by IRPC).
I. Install Gas Eliment (2 part).

3.4.

Final Inspection and De-mobilization


A. Final Inspection by IRPC.

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

13 of 17

B. Close manhole (a new bolt, nut, gasket and torque standard (If
any)).
C. De-blind (a new bolt, nut, gasket and torque standard).
D.Housekeeping around site.
E. De-Mobilization Equipment/Tool.
4. Cleaning Condenser.
4.1.

Isolate blind System

4.1.1.Prepare blind plate at least 5 mm.


4.1.2.Survey blind point around condenser.
4.1.3.Isolate blind reference blind list from IRPC
4.1.4.Checking and inspection blind.
4.2.

Open Manhole and Ventilation system

4.2.1.Open manhole. Over all.


4.2.2.Install ventilation system.
4.2.3.Start Air for Ventilation condenser.
4.2.4.Check gas LEL and Oxygen reference standard value.
4.3.

Cleaning Condenser
A. Prepare PPE and Confine permit approval by IRPC.
B. Prepare Oxygen alert and other safety tool ( SCBA standby).
C. Install lighting 220 V. outside condenser.
D.Start up High pressure water jet. (Ventilation has running every
time)
E. Cleaning inside tube and cover condenser.
F. Visual inspection Cleaning by IRPC & HDS (Approved by IRPC).
G.Replace Aluminum Catode.

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

4.4.

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

14 of 17

Final Inspection and De-mobilization


A. Final Inspection by IRPC.
B. Close Cover (a new bolt, nut, gasket and torque standard (If
any)).
C. Check leak condenser by Air PW Plant.
D.De-blind (a new bolt, nut, gasket and torque standard).
E. Housekeeping around site.
F. De-Mobilization Equipment/Tool.

5. Cleaning inside SSC pit


5.1.

Cleaning SSC pit.


A. Prepare PPE and Confine permit approval by IRPC.
B. Prepare Oxygen alert and other safety tool ( SCBA standby).
C. Ventilation has running every time)
D.Install lighting 24 V. inside SSC pit.
E. Cleaning inside SSC pit. And Remove ASH
F. Visual inspection Cleaning by IRPC & HDS (Approved by IRPC).

5.2.

Final Inspection and De-mobilization


A. Final Inspection by IRPC.
B. Housekeeping around site.
C. De-Mobilization Equipment/Tool.

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

15 of 17

SECTION 4
SCOPE OF SUPPLY

ITEM
1
2
3
4
5
6
7
8
9
10
11
12

DESCRIPTION
All Equipment and Tool for Project
Manpower for Project
Transportation Equipment and tool
Consumable
Change New Bolt, Nut, Gasket (Close system for Cleaning work)
Safety tools
Waste Disposal
N2 (If request)
Air, Electrical
Site Area
Water for Clean
Steam (If request)

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

PROVIDER
HDS
HDS
HDS
HDS
HDS
HDS
IRPC
IRPC
IRPC
IRPC
IRPC
IRPC

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

16 of 17

SECTION 5
SCHEDULE PLAN

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)

Technical Proposal & Detail Scope


For
Boiler inside cleaning unit 02 Power Plant

Customer:

Rev.

IRPC PW
Date:

0
Page:

19/09/2013

17 of 17

SECTION 6
SAFETY MANAGEMENT

HYDRODYNE SERVICES CO., LTD. (HDS)


Issue By:

Sarunyu.T

19 Watchaklukya Rd., T.Huaypong Muang,


Rayong 21150 Thailand

Approve By :
Position:
Date: 21/09/2013
Owner: MSS Section. (IRPC)