Sei sulla pagina 1di 385

Government of Telangana

T.S. Revised Standard Data


(With Schedule of Rates 2015-16)
(Effective from 01-06-2015)

Part 1
For IRRIGATION & CAD WORKS
and
LEADS & LIFTS (Common to all Departments)

BOARD OF CHIEF ENGINEERS

Office of the Engineer-in-Chief (I.W)


I&CAD Dept., Errummanzil, Hyderabad
Procs.No.ENC/IW/P&M/EE/DEE-2/AEE-5/13305/Vol-1

dt: 25.07.2015

Sub:

Telangana Revised Standard Data for I&CAD works(Part-I) for the year 2015-16
approved-Printing & communication of Standard Data Reg.,

Ref:

1)G.O.Ms.No.49,I&CAD (PW:Reforms)Dept., dt:2.3.2009


2) Minutes of BOCEs meeting for Schedule of Rates held on 25.05.2015.
3) SoR Procs.No.ENC/IW/P&M/EE/DEE-2/AEE-5/13305/Vol-1 dt:25.07.2015
*****
The Board of Chief Engineers meeting for finalization of Schedule of Rates (SoR) for I&CAD

(Part-I), Road & Bridges (Part-II), Building (Part-III) and Public Health (Part-IV) was held on
25.05.2015 @ 3.30 PM and approved the SoR. Based on the approval of BoCEs, the SoR for I&CAD
Dept(basic input required for arriving unit item rate as per Telangana Revised Standard data), I&CAD
Department,

R&B Department, PR Department and Public Health Department

items were

communicated vide this office proceedings 3rd cited.


During the BoCEs meeting held on 25-05-2015, it is observed that in some of the estimates,
Lead Charges are being added directly to the material basic rates for arriving the finished item rate. In
view of that, the BoCE has instructed to see that while arriving the finished item rate, the lead charges
are to be added to the material basic rates only after deducting the provision of Contractor's Profit and
Overhead charges"
By incorporating the items, the Telangana Revised Standard Data (unit rate for work items) for
the year 2015-16 is finalized. Any additions, modifications or deletions in the existing data must be
approved by BoCEs. One soft copy is herewith enclosed.
Encl: Soft copy of Telangana Revised Standard Data for I&CAD Department for the year 2015-16

Sd/- J.Vijaya Prakash, 25.07.2015


Engineer-in-Chief (I.W.)
Chairman, BOCE (SoR)
I) Copy communicated to the Principal Secretary to Govt., I&CAD Dept., J-Block, Telangana Secretariat
Buildings, Hyderabad.
II) Copy Communicated to the following Heads of Departments along with Enclosures for information.
1) Engineer-in-Chief (Admn & NH), Roads & Buildings Department.
2) Engineer-in-Chief (P.H.), Public Health Department.
3) Engineer-in-Chief (P.R.), Panchayath Raj Department.

4) Engineer-in-Chief (RWS) R W S, Department.


5) Chief Engineer (Buildings), R&B Department.
6) Copy of C.D containing Schedule of Rates 2015-16 & Standard data, part-1 (Irrigation & CAD
works) to all Engineers-in-Chief, Chief Engineers of Irrigation & CAD Department for favour of
information.
III) Copy to the Superintending Engineer, Irrigation Circle, Irrigation & CAD Department, Red Hill,
Hyderabad for necessary action.

Sd/- J.Vijaya Prakash, 25.07.2015


Engineer-in-Chief (I.W.)
Chairman, BOCE (SoR)

code and index for work items of standard data


Item Code

Item of the work

Proceedings for the Standard Data


Copy of the G.O.Ms.No.49, I & CAD (PW: Reforms) Dept., dt:.2-3-2009.
PREAMBLE & GUIDELINES
PART-1

Page No.

i-xiii

IRRIGATION
Abstract of Items - Irrigation

1-45

Abstract of Leads and Lifts

46-47

IRR-DAW
IRR-DAW-1

Dam And Allied Works (48-104)


EXCAVATION & FOUNDATION TREATMENT WORKS:

48-59

IRR-DAW-2
IRR-DAW-3
IRR-DAW-4
IRR-DAW-5
IRR-DAW-6

REINFORCEMENT & CEMENT CONCRETE WORKS :


MASONRY & GUNITING WORKS :
CONTRACTION JOINT WORKS:
EARTH / ROCKFILL EMBANKMENT WORKS :
FILTER & PITCHING WORKS :

59-78
78-84
84-87
87-95
96-104

IRR-TAW
IRR-TAW-1
IRR-TAW-2
IRR-TAW-3
IRR-TAW-4
IRR-TAW-5
IRR-TAW-6

Tunnel & Allied Works (105-130)


EXCAVATION :
DEWATERING & GUNITING WORKS :
TEMPORARY & PERMANENT SUPPORTS :
MASONRY WORKS :
REINFORCEMENT & CONCRETE WORKS :
DRILLING & GROUTING WORKS :

105-113
113-116
116-122
122-123
123-128
128-130

IRR-CAW
IRR-CAW-1
IRR-CAW-2
IRR-CAW-3
IRR-CAW-4
IRR-CAW-5
IRR-CAW-6
IRR-CAW-7
IRR-CAW-8

Canal And Allied Works (131-230)


EXCAVATION WORKS :
EMBANKMENT WORKS USING BORROW AREA SOIL :
EMBANKMENT WORKS USING DUMP AREA SOIL :
EMBANKMENT WORKS USING EXCAVATED SOIL :
FOUNDATION FILLING WORKS :
ROCK FILL WORKS :
CANAL LINING WORKS :
ROCK PITCHING:

131-146
146-153
153-158
158-163
163-171
171-173
173-217
217-229

IRR-CCDW
IRR-CCDW-1
IRR-CCDW-2
IRR-CCDW-3
IRR-CCDW-4
IRR-CCDW-5
IRR-CCDW-6
IRR-CCDW-7

Canal & Cross Drainage Works (229-284)


EXCAVATION & FOUNDATION TREATMENT WORKS :
STEEL AND CEMENT CONCRETE WORKS :
FOUNDATION WELL SINKING WORKS :
MASONRY WORKS :
COPING & RAILING WORKS :
HUME PIPE LAYING & JOINTING WORKS :
BACK FILLING & OTHER WORKS :

229-235
235-261
261-263
263-270
270-274
274-280
280-284

IRR_GAW

Gates/Hoists And Allied Works (285-317)


NOTES ON GATES/HOISTS AND ALLIED WORKS
RADIAL GATES
VERTICAL LIFT GATES
SAND BLASTING AND PAINTING:
PAINTING WITHOUT SAND BLASTING:

285
285-291
291-310
310-314
314-317

IRR_GAW-1
IRR_GAW-2
IRR_GAW-3
IRR_GAW-4

Item Code
IRR-PMW
IRR-PMW-1
IRR-PMW-2
IRR-PMW-3

Item of the work


Preliminary And Maintenance Works (318-354)
JUNGLE CLEARANCE :
PRELIMINARY WORKS :
MAINTENANCE WORKS :

Page No.
318-328
328-338
338-354

COMMON ITEMS TO ALL DEPARTMENTS (unless specified)


COM-MWRK
COM-LDLFT

COM-LDLFT
COM-LDLFT-1

A. Manual Works
B. Lead/Lift/Loading & Unloading Charges
(to follow MORTH standardsfor the items not covered ,as
applicable to roads and bridge works)
Notes on Lead and Lift
(Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.

COM-LDLFT-2
COM-LDLFT-3
COM-LDLFT-4

COM-LDLFT-5
COM-LDLFT-6
COM-DTL-LDLFT-1

COM-DTL-LDLFT-4

COM-DTL-LDLFT-5
COM-DTL-LDLFT-6

356-356
356-356

356-356
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (Idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
(Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.

COM-DTL-LDLFT-2
COM-DTL-LDLFT-3

355-355
356-356

356-357
357-357

357-357
357-357
358-359

359-365
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
Hire Charges

365-366
366-367

367-368
368-369
370-371

T.S. REVISED STANDARD DATA


PREAMBLE

The TS Revised Standard data for various construction items has come into
existence as per the Government orders G.O.Ms.No.49, I & CAD (PW: Reforms)
Dept., dt: 2-3-2009.

The background for adoption of Telangana Revised Standard Data is:

1. Government, in GO 7326 (GAD-GPM& AR), Dated 26-10-2005, has observed


that the age old Standard data requires revision and updation with reference
to the latest machinery and contemporary practices and has

constituted a

High Level Committee to advise on updating and revision of

standard data

and schedule of rates. The work has been taken up by CGG


irrigation. The secretary (Irrigation) is the member- convener of

and SPIUthe committee

Accordingly the data has been revised adopting the procedures and
guidelines given by CWC, Report on committee on cost control of river valley
Projects, BIS specifications, NHAI, MORTH, MORD, CPWD and Government
of Karnataka and revised data and formulated schedule of rates for all
infrastructure Departments (I&CAD, R&B, PR and PH). The team of senior
engineers interacted with the S.R Committee of Karnataka on implementation
and improvements needed. For irrigation works, the data pattern as adopted by
Karnataka has been considered and for other Departments, the data adopted
by MORTH, MORD and NHAI etc. is considered.

2. Sequence followed in revision of standard data is,


a) The first step is the revision and formulation of standard data for each
work component.

b) The second step is to work out the details of inputs. This enables to
generate the unit work item rates, by incorporating the use rates of
machinery, materials, labour charges and other supplementary parameters.
c) (c) The third step is to develop software tool to generate unit rate using the
software (completed for irrigation works by the SPI Unit of Irrigation)
3. The Detailed draft data was communicated to all the HODs and interacted
through many seminars and discussions and incorporated the relevant
features. The Board of chief engineers in their meetings have recommended for
acceptance to the data formulated and schedule of rates. It was proposed to
examine the recommendations on important parameters, to refer to high level
committee, for their specific recommendations for adoption, as they are
common to all departments.
The committee made in depth study on the methodology and systems
followed by the reputed National organizations and other States and made
detailed

deliberations

Association of India and

with

HODs

and

representatives

of

Builders

made recommendations to the Government, on

adoption of such parameters in Telangana.

4. The Chief Secretary held a detailed discussions on 04-07-2007,with the


Secretaries of the Departments and Heads of Departments.

ii

GUIDELINES

1)

The Revised Standard Data is formulated under four Parts, which are
applicable to all the Engineering Departments and other Organisations.

PART -1:

Irrigation& CAD (Dam and Allied Works, Canals and Allied Works,
Canal C.D. Works, Tunnels and Allied Works, Preliminary and
Maintenance Works, Hydraulic Gates and allied works and Leads
and Lifts applicable to all Departments

PART -2:

Roads and Bridges

PART -3:

Buildings including Electrical Works

PART -4:

Drinking Water Supply and Public Health (ONLY FOR WORKS


DONE BY MANUAL MEANS)

2) Brief description of item of work. :


Brief description of the item of work to cover all important aspects of the
work included in the in the Data. On reading the item description, the user should
be in a position to assess the various cost components involved in the work.
3) Data for assessing quantities:
The data reflects various assessments / assumptions made in arriving at
the quantities of materials, machinery, labour and other in-puts. In case of plants
and equipment the output of main plant is worked out and the requirement of all
other inputs and assessed to match the output of the main plant. Cycle time of
operations is the criteria for assessing the output of equipment. Generally the
equipment manufacturers furnish the output of machinery under ideal conditions of
working. Suitable job and management efficiency factors are considered while
working out the average output of machinery under field conditions. In case of
combination of machinery and manpower, the assessment of manpower shall
match the output of machinery.
Though cycle time of operations is the criteria for hourly / daily out-put of
machinery work-force ,the actual progress of work depends on several other

iii

factors such as power interruptions, minor break-downs, time for meals and other
needs of work-force, stray rains etc. Therefore, it is the general practice to consider
50 minutes as the actual working time per hour for working out the hourly / daily
out-put of machinery / work-force. CWC / BIS guide-lines stipulate the actual
working hours for the purpose of equipment planning and utilisation. The daily output is computed duly considering the actual available working time and feed back
from the field.

For gate and hoist works, it is the general practice to specify the quantity
of work in terms of number of sets of embedded parts / gates. The
requirement of

machinery and work-force for cutting, bending,

fabrication, erection, painting etc., is assessed to commensurate with the


task involved.

The data for gates and E.M. Parts is arrived per Ton quantity.

The data for Hoists and Gantry Cranes is worked out on the basis of
capacity in tonnage

4) The lead and lift charges provided in PART-I (B) are generally applicable
and common to all Departments. Any item is not covered in this part, the
rates as provided in the data of the relevant works may be adopted in
preparation of estimates.

5) The basic material inputs needed for all works are listed and incorporated in
the data. The requirements are analyzed and the specifications adopted shall
confirm to Standards published by the BIS.

The labour and material rates will be communicated by the Board of


Chief engineers.

Unless otherwise specified, all material rates shall be inclusive of all


taxes, duties, levies, transportation and handling costs up to project area.

For sand, gravel , murum, stones , course aggregates etc, the rates are
to be fixed for delivery at Quarry, adding loading charges by machinery /

iv

manual means and idle hire charges of machinery (as per table under
chapter conveyance or lead and lift charges), as applicable.

For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone
slabs, the rates are to be taken prevailing at major commercial centre
near project area. The lead charges, as applicable are to be added in
preparing estimates.

The specifications of the aggregates for sizes and gradation and its
adoption shall be as per IS 383.

6) The labour component in the data is mentioned for unit work.

No allowance towards labour importation and labour amenities added


extra as they are included in the recommended overheads.

On Labour Component: Certain additional allowances are added extra to


the wages of labour (,i.e. only on labour component in the work item) in
the form of percentage, as recommended by the Government/Board of
chief engineers due to statutory and other provisions.

However, If more than one area allowances, such as those for (1)
Municipalities (2) Agency / Tribal areas (3) Industrial areas are applicable
for a particular situation, only the maximum out of the allowable
percentages is to be allowed.

7) HIRE CHARGES OF MACHINERY: The machinery and /or group of machinery

for items of works and their output has been worked

based on the

availability of machinery generally in the market and working in the


field successfully, duly considering cycle time, idle time, operator
efficiency, type of work etc.

The hire charge of a machinery / equipment is worked out based on the


guidelines published by CWC and BIS codes.

For the other machinery not covered by the list, the R&B and other users
may adopt hire charges as recommended by the MORTH.
v

8) Lead Charges

The high level committee has recommended to adopt, for conveyance by


head load, a minimum lead of 50 meters and additional lead up to 150
meters in the intervals of 50 meters. Beyond 150 meters lead, only
machinery rates are to be adopted.

The basic work item rates provided in the Standard Data & Schedule of
rates include 50 m or 1 km as initial lead and no lead charges shall be
allowed where the source of material is within the initial lead specified in
item rate. Additional lead charges shall be allowed for the lead exceeding
initial lead specified in the item rate. The Guidelines may be followed
regarding adding Lead charges as given against each chapter.

The lead charges per unit quantity for conveyance of the materials are
worked out, and included in the schedule of rates in increment of 50 m for
head load and in increment of 1 km for mechanical mode.

The rates for lead charges by head load up to 150 meters and by
machinery up to 5 km, shall be cumulative and inclusive of lead charges
for preceding lead. For lead beyond 5 km, the lead charges shall be
worked out on per km basis.

9) Loading and Unloading charges for Materials


The following features are considered:
1. Loading and unloading charges are not payable for conveyance by head load.
2. Loading and unloading charges are not payable for conveyance by mechanical
means, for disposal of excavated material unless specified.
3. The rates for unloading of materials except earth, sand, gravel, coarse
aggregate, rubble, size stone and cut stone, are inclusive of stacking
wherever applicable.

vi

10) LIFT CHARGES:

The data includes initial lift charges of

3 meters ,for materials

conveyance by head load, Additional leads in the interval of 1.0 meters


are

worked out,

as additional labour input and incorporated in the

chapter on Lead and lifts .

Where the conveyance / lifting of material is done by mechanical means,


lift charges shall not be considered, as the cycle time of operation of the
machine includes lifts involved.

The data and rates for lift charges is cumulative and are inclusive of rates
for preceding lifts also.

11) Wastage of Materials


I) Cement: No wastage allowance is recommended towards the quantity of

cement used in works, as the wastage is already included in the input


and in major works , bulk quantities are used.

II) Steel: The wastage


structures.

For

of steel @ 2.5% is allowed for gates and allied


RCC

works

the

wastage

is

@2.5%

for

the

reinforcement rods above 36mm dia. and @ 5% for rods below 36mm
dia. Including overlaps, if they are not welded.
If welding is adopted for the reinforcement rods even for below 36mm
dia, 2.5% of wastage is only recommended.

12) Provision for rate of water:The Committee has recommended not to consider the water charges in
the Irrigation Project works. But, it may be considered in specific cases as per
the site conditions.

13) In respect of RCC works the rate for cement concrete for 1 cum is worked
separately for all grades based on Indian Standards. The rate for ton is
vii

calculated separately and to be added separately in the estimates of RCC works


as a separate item.

14) Soil classification: The Committee recommended to allow uniform


classification of soils for all Departments and data is worked out accordingly.
1. all soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)

15) Use of Super Plasticizers and Admixtures:

Concrete admixtures such as Air-Entraining Agent (AEA) / Water reducing agent


can be used advantageously for better quality concrete. The high level committee
has recommended to adopt for super plasticizers and admixtures at 0.4% on
cement for concrete work as per MORTH standards for batching plants.
16) Contractors overheads, profit and other provisions:

High Level Committee has recommended adding 14% towards contractor


overheads and profit including labour importation and amenities etc., as given
below which includes various items recommended in MORTH.

The provision for VAT at 5% or as fixed by the Government from time to time
should be made separately in Part-B of the estimate. In the agreements it
should be mentioned that it will be reimbursed as per actual. The provisions
allowed in G.O.Ms.No.94, I&CAD, dt: 01.07.03, need not be added separately
for the items covered in the contractor overhead charges.

The provision for labour Cess at 1% or as fixed by the Government from time to
time should be made separately in Part-B of the estimate.
viii

The overhead charges include the following elements:

Site accommodation, setting up plant, access road, water supply, electricity and
general site arrangements.

Office furniture, equipment and communications

Expenditure on:

Corporate office of contractor

site supervision

Documentation and as built drawings

Mobilisation/ de-mobilisation of resources

Labour camps with minimum amenities and transportation to work sites.

Light vehicles for site supervision including administrative and managerial


requirements.

Laboratory equipment and quality control including field and laboratory testing.

Minor T & P and survey instruments and setting outworks, including verification
of line, dimensions, trial pits and bore holes, where required.

Watch and ward

Traffic management during construction

Expenditure on safeguarding environment

Sundries

Financing Expenditure

Sales/ Turn overtax

17) EXCISE DUTY ON SUPPLIES:


In respect of gates, hoists and allied works, excise duty is applicable on
the value of fabricated components supplied to site. Excise duty is not applicable
on erection charges. Further, the excise duty shall not be considered in the rate
analysis on material component, as basic material rates are inclusive of excise
duty.
Therefore, excise duty is considered in the rate analysis only on
machinery and labour components required for fabrication of gates and hoists at

ix

the central fabrication yard. It is difficult to determine the machinery and labour
components separately for fabrication and erection.
For the purpose of computation of excise duty to be included in the rate analysis
the machinery and labour components may apportioned at 75% for central
fabrication yard and 25% for field erection and commissioning. Therefore, 75% of
the machinery and labour components may be considered for assessing the extent
of excise duty to be added in the rate analysis.
18) DEWATERING & DESILTING:
The High level committee considering the local conditions of rainfall / seepage has
recommended towards de-watering and de-silting at 3 percent on the relevant
work component for which dewatering is required.
It is also proposed as per CWC guidelines, to keep a condition in the agreements
shall be incorporated, to fix a ceiling of 5% in extreme cases, with the specific
approval of chief engineer/Government.
19) Computerization Of Data:

A software program is developed by the SPI Unit (Irrigation), which


facilitates automatic changes and generation of unit rates, based on
basic input rates of Labour, materials and capital cost of machinery.

A soft ware tool is also developed for auto preparation of estimates


based on in put quantities.

Other Departments are also advised to develop such program.

20) For each chapter separate additional details are incorporated for clarity.

USER GUIDELINES OF REVISED STANDARD DATA

1.

Please select the item of work, as given in Index Code, and view the
relevant data.

2.

The common data items like, lead, lift, conveyance and manual
excavation (without involving contracting agencies) is applicable
to all Departments (volume-1).

3.

The departments have to adopt the relevant data from other


Departments, if such works are executed by them.

4.

The unit rate /hire charges, of machinery not covered in the


Irrigation data, the MORTH data may be taken with the approval
of Board of Chief Engineers.

5.

For Drinking water Supply works(PART-IV), the data incorporated is


generally applicable only for manual means of execution. The rates
deploying machinery have to be worked out by the Board of Chief
engineers and approved for adoption.

xi

1. ROLE OF CENTRAL COMPETENT AGENCY FOR

SCHEDULE OF

RATES
(BOARD OF CHIEF ENGINEERS)

a) The Board Of Chief Engineers under the chairman ship of Engineer-inChief, (administration) I&CAD Department is the competent authority to
finalise and recommend the Schedule of Rates applicable for all engineering
Departments. The board has to assess and incorporate only the three basic
inputs required to generate unit work item rates as below.

Basic rates of labour:


Wages of labour commonly required in execution of works has to be
arrived and incorporated in the schedule of rates (Basic Input Of Labour
Wages), without adding extra towards area allowances (like municipality
allowance, tribal area and ghat road allowances etc, which shall be added to
the rates where applicable in the form of separate percentage as explained
in the preceding paras. The rates shall be the prevailing daily rates in the
State and shall not be less than the minimum wages fixed by the
Government from time to time.

Materials rates:
The basic input material rates common to all departmental works are
listed out and incorporated (in the chapter Basic inputs) The

material

specifications adopted shall confirm to Standards published by the BIS.


The Prevailing market rates for all basic input materials shall be
obtained from the major commercial centers near the project areas. Average
of the rates, ignoring freak rates, shall be reckoned as the prevailing market
rate.
Unless otherwise specified, all material rates shall be inclusive of

all

taxes, duties, levies, royalty, transportation and handling costs up to


project area.
xii

For sand, gravel, murrum, stones, aggregates etc, the rates are for
delivery at Quarry including loading charges and idle hire charges. For steel,
Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs, the rates
prevailing at major commercial centre near project area has to be adopted.
Use rate of machinery:
The third parameter for incorporation in the Basic Inputs, is the use rate
of machinery. To arrive at the use rate of machinery, the inputs to be
incorporated are

The

list and capital cost of machinery required

to be

used in the

construction activity, The rate has to be obtained from major


manufacturers and outlet sources and the rate shall be the current
market price inclusive of all taxes, duties and freight charges.

The prevailing fuel charges of petrol and diesel are ascertained and
average rate adopted

Borrow rate of interest as fixed by the Government/competent authority


be indicated.

For the other machinery not covered by the list, the R&B and other
users may adopt hire charges as recommended by the MORTH

b) The Chairman, Board of Chief Engineers or competent authority appointed


by the Government, based on the approved basic inputs, load the above
three basic parameters in the software program. The unit rate of all works
including hire charges of all machinery will be generated automatically for
adoption.

He shall communicate the uniform Schedule of rates arrived from


Standard Data, to all users for uniform and direct adoption in all
infrastructure Departments, as applicable

xiii

Abstract of work items_UNit Rates for the year 2015-16

WORK ITEM RATES


FOR THE YEAR - 2015-16
* Add Leads and Lifts, Area Allowance and VAT as applicable in the estimate
** Area Allowance includes profit component also
*** Unit Rates arrived without Seigniorage Charges
Chapterwise
item No.
1
Chapter I
IRR-DAW

S.NO

Item description

Unit

Rate

Excavation for foundation in all kinds of soil including boulders upto 0.30 m
diameter for dam, spillway, intake structure and other appurtenant works and
placing the excavated soil neatly in dump area or disposing off the same as
directed etc., complete with initial lead upto 1 km and all lifts.

cum

120.10

Labour Component (including contractor's profit and Overheads)

cum

DAM AND ALLIED WORKS

IRR-DAW-1

IRR-DAW-1-1

IRR-DAW-1-2

IRR-DAW-1-3

IRR-DAW-1-3-A
New Item 201415-1

Itemwise unit rate


for Labour
Component
6

EXCAVATION & FOUNDATION TREATMENT WORKS:

Excavation for foundation in ordinary rock (including HDR) without blasting


including boulders above 0.3 m upto 0.6 m dia for dam, spillway, intake
structure and other appurtenant works and placing the excavated material neatly
in dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation for foundation in hard rock (including F&F) requiring blasting
including boulders above 0.6 m upto 1.2 m dia. for dam, spillway, intake
structure and other appurtenant works and placing the excavated material neatly
in dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

Excavation for foundation in hard rock (including F&F rock) including


boulders above 0.6 m upto 1.2 m dia. by controlled blasting and controlling
fly rock by muffling arrangements for dam, spillway, intake structure and other
appurtenant works and other open foundation works and placing the excavated
material neatly in dump area or disposing off the same as directed etc.,
complete with initial lead upto 1 km and all leads
Labour Component (including contractor's profit and Overheads)

cum

24.10

159.10

cum

cum

31.20

241.40

cum

cum

55.70

367.20

65.40
cum

IRR-DAW-1-4(a)

IRR-DAW-1-5(b)

Excavation for foundation in hard rock of all toughness by blasting including


boulders above 1.2 m dia. for dam, spillway, intake structure and other
appurtenant works and placing the excavated rock neatly in dump area or stack
yard including levelling as directed etc., complete with initial lead upto 1 km
and all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation for foundation in hard rock of all toughness including boulders
above 1.2 m dia. by controlled blasting method and controlling fly-rock by
muffling arrangements for dam, spillway, intake structure and other appurtenant
structures etc., including placing and levelling the excavated rock neatly in dump
area or other place as directed etc., complete with lead upto upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)

cum

432.40

cum

cum

107.70

680.30

cum

118.00

Excavation for foundation in hard rock of all toughness including boulders


above 1.2 m dia. by line drilling and smooth blasting and controlling fly-rock by
muffling arrangements for dam, spillway, intake structure and other appurtenant
structures etc., including dressing sides and bed to required level / profile,
placing and levelling the excavated rock neatly in dump area or other place as
directed etc., complete with lead upto 1 km and all lifts.

IRR-DAW-1-6(c)

i ) For the purpose of payment 1 m width of excavation along boundary of


excavation shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
as the case may be.
ii ) The rate includes controlling fly-rock wherever required.
iii ) The rate under this item shall be paid only on ascertaining that the excavated
face has come off neatly as per specifications or atleast 50 percent of smooth
blast holes are visible for inspection and are spaced at specified interval.
iv ) In case, where the above criteria is not fulfilled payment shall be restricted to
rate provided for excavation by normal blasting or controlled blasting as the case
may be.
Labour Component (including contractor's profit and Overheads)

cum

cum

929.20

311.00

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

IRR-DAW-1-7

3
Preparing foundation bed for masonry or concrete by benching, stepping,
removing all loose material by wedging / chiselling and disposing off the same as
directed and cleaning the surface with air and water jet etc.,complete with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

sqm

35.60

IRR-DAW-1-8

IRR-DAW-1-9

10

Preparing foundation bed for cut-off trench filling in rock portion by removing
all loose materials by wedging / chiselling and disposing off the same as directed
etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Drilling 45 to 50 mm dia holes vertical or inclined upto 10 degrees to vertical in
rock /masonry / concrete by percussion drilling using waggon drill or any
other suitable equipment including cost of all materials, machinery, labour,
redrilling through partially set grout wherever required etc., complete for drilling
upto 6 m depth from surface.

sqm

sqm

Itemwise unit rate


for Labour
Component
6

28.30

23.90

sqm

23.90

Rm

202.80

Rm
Rm
Rm
Rm
Rm
Rm
Rm
Rm

223.10
245.40
269.90
296.90
326.60
359.30
395.20

Rm

51.50

The item rate for drilling through rock / masonry / concrete includes redrilling
through partially set grout, if any, in the portion of the hole drilled and grouted.
.

IRR-DAW-1-10

IRR-DAW-111(a)

IRR-DAW-112(b)

IRR-DAW-1-13

IRR-DAW-1-14

11

12

13

14

15

IRR-DAW-2

IRR-DAW-2-1A

Beyond 6 m upto 12 m from surface :


Beyond 12 m upto 18 m from surface :
Beyond 18 m upto 24 m from surface
Beyond 24 m upto 30 m from surface
Beyond 30 m upto 36 m from surface
Beyond 36 m upto 42 m from surface
Beyond 42 m upto 48 m from surface
Labour Component (including contractor's profit and Overheads)
Flushing grout holes of all sizes with water and air jets alternatively for an
average period of 30 minutes including water intake observations after flushing,
cost of all materials, machinery, labour etc., complete.
Labour Component (including contractor's profit and Overheads)

Rm

Consolidation grouting with neat cement grout mix of suitable consistency


under specified pressure as directed in drilled holes by stage grouting method
including cost of all materials, machinery, labour, redrilling if necessary
etc.,complete with initial lead upto 1 km and all lifts.

tonne

Labour Component (including contractor's profit and Overheads)

tonne

Curtain grouting with neat cement grout mix of suitable consistency under
specified pressure as directed in drilled holes by stage grouting method including
cost of all materials, machinery, labour, redrilling if necessary etc., complete with
initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

tonne

18.30

11093.30

2959.00

12054.50

tonne

Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel
bars with one end driven into 45 to 50 mm diameter 1.50 m deep hole drilled in
bed rock and other end provided with L-bend for embedding in concrete /
masonry of over flow / non-over flow blocks and other appertenant works
including cost of drilling and cleaning hole, filling hole with cement mortar 1 : 1
proportion, driving anchor rod, cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.

Each

Labour Component (including contractor's profit and Overheads)

Each

Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods with
one end split and driven firmly using steel wedge into 1.25 m deep 45 to 50 mm
dia. hole drilled in bed rock and other end provided with L- bend for embedding
in concrete / masonry for spillway and appurtenant works including drilling and
cleaning hole, filling hole with thick cement slurry, driving anchor rod, cost of all
materials, machinery, labour, steel wedge etc., complete with initial lead upto 1
km and all lifts.
Labour Component (including contractor's profit and Overheads)

46.90

Each

3813.80

940.30

109.60

863.90

Each

123.60

REINFORCEMENT & CEMENT CONCRETE WORKS :

16

Providing, fabricating and placing in position reinforcement steel for


RCC,below 36 dia rods overlaps and wastages wherever required, tying with
1.25 mm diameter soft annealed steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

52115.67
tonne
tonne

3522.50

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

IRR-DAW-2-1B

17

IRR-DAW-2-2

IRR-DAW-2-2A
(new Item1 201011)

IRR-DAW-2-3

IRR-DAW-2-4

IRR-DAW-2-4A
(new Item2 201011)

IRR-DAW-2-4B
(new Item3 201011)

18

19

20

21

22

23

Providing, fabricating and placing in position reinforcement steel for RCC


above 36 dia with welding and wastage at 2.5%, tying with 1.25 mm diameter
soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

53545.14
tonne
tonne

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 250
kg /cum with use of super plasticiser equla to 0.4% of cement content, CA :
0.98 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.35 cum ))

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 300
kg /cum with use of super plasticiser equla to 0.4% of cement content, CA :
0.90 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.4 cum ))

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 220
kg /cum with use of super plasticiser, CA: 0.98 cum, Blending Ratio of CA -40:30:20:10, FA: 0.37 cum )

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 310 kg / cum with use of super
plasticiser, CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 360 kg / cum with use of super
plasticiser,CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structures,
training walls, piers, abutments and such other locations with initial lead upto 1 km
and all lifts. ( Cement content : 380 kg / cum with use of super plasticiser,CA : 0.90
cum, blending ratio of CA--65:35, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

Itemwise unit rate


for Labour
Component
6

cum.

4701.30

4221.00

171.30

4584.80

171.30

3982.40

171.30

5554.00

338.00

5976.00

cum.

cum.

cum.

338.00

6124.90

338.00

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-DAW-2-5

IRR-DAW-2-6

IRR-DAW-2-7

IRR-DAW-2-8

IRR-DAW-2-9

IRR-DAW-2-10

Item description

Unit

Rate

24

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 260
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA -50:30:20, FA : 0.40 cum)

cum.

5020.50

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates with placing and sinking plums of size
150 to 80 mm upto 15 percent for gravity type structures including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete with initial
lead upto 1 km and all lifts. ( Cement content : 260 kg / cum of concrete with
use of plums and super plasticiser,, CA : 0.77 cum, Blending Ratio of CA :
50:30:20,FA : 0.34 cum, plums of size 150 to 80 mm : 0.25 cum)

cum.

Labour Component (including contractor's profit and Overheads)

cum.

25

26

27

28

29

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content 220
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA :
50:30:20, FA : 0.40 cum )
Labour Component (including contractor's profit and Overheads)

cum.

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of spillway bridge, blockouts and such other similar structures with
conjested reinforcement with initial lead upto 1 km and all lifts. ( Cement
content : 330 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA -- 65:35, FA : 0.44 cum).

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and forming porous concrete body drain of size 68.5 x 68.5 cm with 23
cm diameter central hole using cement and 20 mm down approved, clean, hard,
graded coarse aggregates in 1 : 3.50 proportion by volume including cost of all
materials, machinery, labour, formwork, curing etc., complete with initial lead
upto 1 km and all lifts.(M15 Cement content : 400kg/cum, CA : 1cum, Blending
Ratio of CA -- 65:35)
Labour Component (including contractor's profit and Overheads)

1202.30

4884.50

1173.20

4586.00

cum.

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 280
kg /cum with use of super plasticiser,CA : 0.80 cum, Blending Ratio of CA -65:35, FA : 0.44 cum)

Rm

Rm

Itemwise unit rate


for Labour
Component
6

1088.20

4959.50

1114.40

6774.50

1580.70

2617.00

543.60

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-DAW-211(a)

IRR-DAW-212(b)

IRR-DAW-2-13

IRR-DAW-2-14

IRR-DAW-2-15

IRR-DAW-2-16

IRR-DAW-2-17

IRR_DAW-3

30

31

32

33

34

35

36

Item description

Unit

Rate

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
solid parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m pillars
spaced approximately at 3.35 m c / c, 12.5 cm thick wall 80 cm height with 12.5
cm thick and 35 cm wide coping slab for wall and 12 .5 cm thick 40 cm x 40 cm
coping for pillars with top edges of kerb and coping chamferred / rounded as
directed etc., complete ( excluding cost of providing and placing
reinforcement steel and gate ) with initial lead upto 1 km and all lifts. (
Cement content 350 kg / cum with use of super plasticiser( 0.4% by wt.of
cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)

Rm

2428.60

Labour Component (including contractor's profit and Overheads)

Rm

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
ornamental parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m
pillars spaced approximately at 3.5 m apart, 20 cm x 15 cm posts 80 cm height
approximately 30 cm c / c with 12.5 cm thick and 35 cm wide coping slab for
posts and pillars with top edges of kerb and coping chamferred or rounded as
directed etc., complete ( excluding cost of providing and placing reinforcement
steel and gate ) with initial lead upto 1 km and all lifts. ( Cement content : 350
kg / cum with use of super plasticiser, CA : 0.80 cum, Blending Ratio of CA-65:35, FA : 0.44 cum)

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Providing and laying insitu M- 25 ( 28 days cube compressive strength not less
than 25 N / sq mm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing joints with
asphalt mortar etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 380 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA--65:35, FA : 0.45 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

Pre-cooling to control placement temperature of cement concrete in the range of


18 to 21 C at the concrete placement point by inundation of coarse aggregates
and adding flaked ice as part of mixing water including cost of all materials,
machinery, labour etc., complete with all leads and lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Conveying and fixing elastomeric bearing for spillway bridge including cleaning
and preparing surface, mixing and applying adhesive, fixing bearing in correct
position etc., including cost of all materials except bearings, machinery, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Each

674.50

2440.10

716.10

5846.60

1351.80

82.30

13.10

331.20

Each

Providing and constructing 150 mm dia hume pipe weep holes for concrete /
masonry walls including providing 20 x 20 x 20 cm size porous concrete block
made of cement and 20 mm down coarse aggregate in 1 : 4 proportion
including 10 cm thick sand backing at the junction of wall and soil back fill, cost of
all materials, machinery, labour etc., complete with lead upto 1 km and all lifts.

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Providing and forming expansion joint for spillway bridge consisting of 75 x


75 x 6 mm angles 2 numbers provided with 25 cm long 12 mm dia. anchors fixed
to both flanges at 15 cm c /c and 140 x 6 mm plate welded on top of one of the
angle including cost of all materials, machinery, labour, providing and fixing 38
mm thick joint filler board matching the thickness of wearing coat, painting etc.,
complete with lead upto 1 km and all lifts.

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Itemwise unit rate


for Labour
Component
6

284.00

464.30

64.40

1764.50

297.30

MASONRY & GUNITING WORKS :

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

IRR_DAW-3-1

37

3
Providing and constructing un-coursed rubble stone masonry using approved
stones in cement mortar 1 : 3 proportion including cost of all materials,
machinery, labour, scaffolding, cleaning, packing mortar, wedging stone chips,
curing etc., complete with initial lead upto 1 km and all lifts.( Cement content :
190 kg/cum of masonry, rubble stones : 0.85 cum,stone chips : 0.15 cum/cum,
FA : 0.4 cum)
Labour Component (including contractor's profit and Overheads)

cum

3218.20

IRR_DAW-3-2

IRR_DAW-3-3

38

39

Providing and constructing un-coursed rubble stone masonry using approved


stones in cement mortar 1 : 4 proportion including cost of all materials,
machinery, labour, scaffolding, cleaning, packing mortar, wedging stone chips,
curing etc., complete with initial lead upto 1 km and all lifts.( Cement content :
143 kg/cum of masonry, rubble stones : 0.85 cum, stone chips : 0.15 cum/cum,
cum
FA : 0.4 cum)
Labour Component (including contractor's profit and Overheads)
cum
Providing and constructing coursed rubble face stone masonry using approved
rubble stones in cement mortar 1 : 3 proportion including cost of all materials,
machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone
chips, curing etc., with initial lead upto 1 km and all lifts.( Thickness of the CR
face assumed: 0.75 m, Cement content : 178 kg/cum of masonry, rubble stones
: 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum, CR stones 30 x 30 x 45
cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)
Labour Component (including contractor's profit and Overheads)

IRR_DAW-3-4

IRR_DAW-3-5

40

41

IRR-DAW-3-7

IRR-DAW-3-8

42

43

44

IRR_DAW-4

IRR-DAW-4-1

1028.80

2875.70

1028.80

cum

3389.10

1146.50

cum

Providing and constructing coursed rubble face stone masonry using approved
rubble stones in cement mortar 1 : 4 proportion including cost of all materials,
machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone
cum
chips, curing etc., with initial lead upto 1 km and all lifts. ( Cement content :
134 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum,
FA : 0.375 cum, CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm :
3.25 No)
Labour Component (including contractor's profit and Overheads)
cum
Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 3 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km
and all lifts.( Cement content : 167 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)
Labour Component (including contractor's profit and Overheads)

IRR-DAW-3-6

cum

Itemwise unit rate


for Labour
Component
6

cum

3068.40

1146.50

3560.90

1410.50

cum

Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 4 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km
and all lifts.( Cement content : 125 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing cement mortar pointing to coursed rubble face stone masonry 50


mm deep in CM 1 : 2 proportion by volume including raking and cleaning joints,
pressing mortar into joints, cost of all materials, labour, scaffolding, finishing,
curing etc., complete with initial lead upto 1 km and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing cement mortar pointing to coursed rubble face stone masonry 50


mm deep in CM 1 : 3 proportion by volume including raking and cleaning joints,
pressing mortar into joints, cost of all materials, labour, scaffolding, finishing,
curing etc., complete with initial lead upto 1 km and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

3254.80

1410.50

122.10

82.40

112.40

82.40

CONTRACTION JOINT WORKS:

45

Providing 25 mm thick guniting to rock or masonry surface in cement mortar


1 : 3 proportion by weight including cost of all materials, machinery, labour,
raking-out and cleaning joints, scaffolding wherever required and all other
ancillary operations etc., complete with initial lead upto 1 km and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

515.30

163.00

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

Rm

14553.30

IRR-DAW-4-2

IRR-DAW-4-3

IRR-DAW-4-4

IRR-DAW-4-5

46

47

48

49

IRR-DAW-5

IRR-DAW-5-1

IRR-DAW-5-2

IRR-DAW-5-3

IRR-DAW-5-4

Providing and constructing contraction joints by fixing 16 SWG 60 cm wide


annealed copper sheets in two lines with 8 mm dia steel dowel rods on either side
at one metre interval, forming 125 x 125 mm size groove in between copper
strips for filling asphalt including fixing 15 mm dia two legged G.I pipe with U bend at bottom for circulation of steam at intervals and forming 150 mm dia
formed drain behind water seals including cost of all materials, machinery,
labour, filling asphalt, circulation of steam through pipes etc., complete with all
leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 310 mm wide central
bulb type approved quality PVC water stop in two lines with 8 mm diameter steel
dowel rods on either side at 1m interval, forming 125 x 125 mm size groove in
between two water stops, providing & fixing 15 mm dia two legged G.I pipe with
U-bend at bottom for circulation steam at interval, forming 150 mm diameter
formed drain behind water seals including filling groove with asphalt, circulation
of steam at intervals, cost of all materials, machinery, labour etc., complete with
all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 16 SWG 60 cm wide
annealed copper sheets in single line with 8 mm dia steel dowel rods on either
side at 1 metre interval including cost of all materials, machinery, labour etc.,
complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Rm

Rm

173.50

1753.10

Rm

Rm

114.50

7090.80

Rm

Providing and constructing contraction joints by fixing 23 cm wide central bulb


type PVC water stop in single line supported by 10 mm dia steel dowel rods on
either side at 1 metre interval including cost of all materials, machinery, labour,
valcunising joints etc., complete with all leads and lifts.

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Itemwise unit rate


for Labour
Component
6

133.50

220.80

106.50

EARTH / ROCKFILL EMBANKMENT WORKS :

50

51

52

53

Providing hearting embankment using selected impervious soil from


approved borrow areas in layers of 25 to 30 cm before compaction including
cost of all materials, machinery, labour, all operations such as excavation,
sorting out, transportation, spreading soil in layer of specified thickness,
breaking clods, sectioning, watering, compacting to density control of not less
than 95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to
10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing cut-off trench filling using selected impervious soil from approved
borrow areas in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil to specified thickness, breaking clods, sectioning,
watering, compacting to density control of not less than 95 percent using Sheep
foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing casing embankment using semi-pervious soil from approved borrow


areas in layers of 25 to 30 cm before compaction including cost of all materials,
machinery, labour, all other operations such as excavation, sorting out,
transportation, spreading soil in layers of specified thickness, breaking clods,
sectioning, watering, compacting to density control of not less than 95 percent
using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as
stipulated etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing casing embankment using semi-pervious soil available from


excavation in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all other operations such as re-excavation, sorting
out, transportation, spreading in layers of specified thickness, breaking clods,
sectioning, watering, compacting to specified density control of not less than 95
percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
as stipulated etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

138.00

20.50

148.10

22.30

148.50

22.20

124.90

18.90

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-DAW-5-4-A
(New Item1 2011-12)

IRR-DAW-5-5

IRR-DAW-5-6

IRR-DAW-5-7

IRR-DAW-5-8

IRR-DAW-5-9

54

55

56

57

58

59

IRR-DAW-5-9-A
(New Item4-2012- 60
13)

IRR-DAW-5-10

IRR-DAW-6

61

Item description

Unit

Rate

Providing casing embankment using semi-pervious soil available from


excavation in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all other operations such as re-excavation, sorting
out, transportation, spreading in layers of specified thickness, breaking clods,
sectioning, watering, compacting to specified density control of not less than 90
percent using 2Tonne Roller as stipulated etc., complete with initial lead upto
1 km and all lifts. (For Maintenance Works)

cum

85.40

Labour Component (including contractor's profit and Overheads)

cum

Providing homogeneous embankment using soil from approved borrow area in


layers of 25 to 30 cm before compaction including cost of all materials,
machinery, labour, all operations such as excavation, sorting out, transportation,
spreading soil in layer of specified thickness, breaking clods, sectioning,
watering, compacting to density control of not less than 95 percent or as
stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power
roller etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing embankment adjacent to masonry / concrete structures and filling


trial pits using impervious soil from approved borrow areas in layers of 10 to
15 cm and compacting each layer to density control of not less than 95 percent
using pneumatic tampers or by vibratory earth rammers including cost of all
materials, machinery, labour, picking previous layer, spreading soil in layer,
breaking clods, watering etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and constructing rockfill embankment with 300 mm down graded


stones and quarry spalls from approved source including cost of all materials,
machinery, labour, spreading stones and spalls in layers, hand packing,
wedging, finishing the surface to required slopes etc., complete with initial
lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing dry rubble rock-toe using rubble and stone chips
from approved source including cost of all materials, machinery, labour, hand
packing rubble and stone chips, finishing top and sides to required slopes etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

cum

Note: Useful rubble and stone chips will be issued at dump yard at the issue rate
for usefull rubble /stone chips. Sorting out and breaking charges included in rate
analysis.
Labour Component (including contractor's profit and Overheads)

cum

Providing and laying 30 cm diameter open jointed hume pipes with collars in
rock-toe for drainage including cost of all materials, machinery, labour etc.,
complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

140.30

20.90

264.30

113.20

435.00

103.30

498.60

cum

Providing and constructing dry rubble rock-toe with rubble and stone chips
from dump yard including cost of all materials, machinery, labour, hand packing
rubble and stone chips, finishing top and sides to required slopes etc., complete
with initial lead upto 1 km and all lifts.

Providing and constructing Dry rock Pitching for Groynes using Un-Coursed
rubble stone of size 300 mm thick and Un-Coursed rubble stone chips from
Quarry to site of work including cost of all materials, Machinery, Labour charge
hand packing Un-Course rubble stone &chips to the designed profile with all
leads and lifts etc
Labour Component (including contractor's profit and Overheads)

18.90

cum

cum

cum

193.00

462.10

132.70

679.40

cum

Rm
Rm

Itemwise unit rate


for Labour
Component
6

132.70

824.80
29.50

FILTER & PITCHING WORKS :

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-DAW-6-1

IRR-DAW-6-2

IRR-DAW-6-3

IRR-DAW-6-4

Item description

Unit

Rate

62

Providing and constructing 1.20 m internal diameter and average 3 m height


RCC manhole with 60 cm dia. top cover in M-15 grade cement concrete using 20
mm down graded, clean, hard coarse aggregate, 20 cm thick for bed / sides /
top slab / 1.5 m long cut-off wall and 7.5 cm thick for cover including providing 12
mm dia reinforcement bars at 30 cm c / c bothways for bed / sides / cut-off wall /
top slab / rungs and 8 mm dia bars at 15 cm c / c bothways for cover, excavation
for foundation, providing 30 cm dia hume pipe outlet, cost of all materials,
machinery, labour, formwork, scaffolding, batching, mixing, laying, vibrating,
finishing, curing etc., complete with lead upto 1 km and all lifts.( Cement
content : 300 kg/cum , CA : 0.80 cum, Blending Ratioof CA -- 65:35,FA : 0.44
cum, superplasticizer (0.4% by wt. of cement)

Each

46639.10

Labour Component (including contractor's profit and Overheads)

Each

Providing and constructing longitudinal and cross graded filter drains using
sand and 80-20 mm and 20 mm down graded aggregates satisfying specified
filter creteria in layers as per specifications including cost of all materials,
machinery, labour, laying to required slopes, compaction etc. complete with
initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and constructing 1.40 m thick vertical or inclined graded filter


media consisting of 20 cm thick sand layers, 25 cm thick 20 mm down
coarse aggregate layers and 50 cm thick 80-20 mm coarse aggregate layer
using approved materials satisfying specified filter creteria as per specifications
including cost of all materials, machinery, labour, laying to required slope,
compaction etc., complete with initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and constructing graded filter media below and behind rock-toe
consisting of 20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80 20 mm size graded coarse aggregates satisfying filter creteria as per
specifications including cost of all materials, labour, machinery, laying to required
slope, compaction etc., complete with initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

63

64

65

IRR-DAW-6-4-A
(New Item2 2011- 66
12)

IRR-DAW-6-5

IRR-DAW-6-6

IRR-DAW-6-7

IRR-DAW-6-8

67

68

69

70

Providing and constructing graded filter media below and behind rock-toe
consisting of 30 cm thick, 80 - 20 mm size graded coarse aggregates
satisfying filter creteria as per specifications including cost of all materials,
labour, machinery, laying to required slope, compaction etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing and constructing 45 cm thick chimney filter using clean approved


sand satisfying filter creteria including cost of all materials, machinery, labour,
compacting etc., complete with initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and constructing 90 cm thick transition cum filter media behind


rockfill using approved sand and 80-20 mm and 20 mm down graded aggregates
satisfying the filter creteria in layers of 30 cm thickness each as per
specifications including cost of all materials, machinery, labour, laying each layer
to required slope, compaction etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)

9978.60

1013.10

138.40

1074.00

138.40

1017.40

124.30

1133.30

cum

Providing and laying filter media consisting of 2 layers of 250 gsm polypropeline non-woven filter fabric and 400 mm thick 20 mm down graded
coarse aggregate for vertical / inclined and horizontal filter blanket for
embankment including cost of all materials, machinery, labour etc., complete
with lead upto 50 m for aggregate and all leads for fabric and all lifts.

cum

46.80

950.60

53.90

778.30
110.20

1061.80

cum

Providing and constructing 60 cm thick hand packed rough stone revetment


with 65 to 75 cm long through stones at 1.50 m c / c over a backing of 45 cm
thick graded filter media consisting of sand, 10 mm and 40 mm size approved
graded aggregates laid in layers of 15 cm thick each including cost of all
materials, machinery, labour, laying to required slopes, wedging with chips,
finishing etc. complete with initial lead upto 50 m and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Itemwise unit rate


for Labour
Component
6

145.40

893.60

162.80

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-DAW-6-9

IRR-DAW-6-10

IRR-DAW-6-11

IRR-DAW-6-12

IRR-DAW-6-13

71

72

73

74

75

sqm

1064.20

Labour Component (including contractor's profit and Overheads)

sqm

Providing and constructing 60 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each
including cost of all materials, machinery, labour, laying to required slopes,
wedging with stone chips etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)

IRR-TAW-1-3

IRR-TAW-1-4

78

79

sqm

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing and constructing 90 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each including
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips etc., complete with initial lead upto 50 m and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing and laying Hariyala or other approved quality turfing sods for the
slopes of earthen embankments over 20 mm thick sand backing including cost of
all materials, machinery, labour including preparing surface, spreading sand,
watering for 15 days etc., complete with initial lead upto 1 km and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Excavation for adit by tunnelling methods in all types of rock including cost
of all materials, machinery, labour, scaling excavated surface, ventilation,
lighting, drainage, removing and hauling the excavated muck outside adit upto
specified dump area and all other ancillary operations etc., complete with
initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Excavation for vertical / inclined shaft in all types of soft / hard rock
including cost of all materials, machinery, labour, shoring, strutting, scaling
excavated surface, ventilation, lighting, drainage, removing and hauling
excavated muck outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Excavation for tunnel by tunnelling methods in rock not requiring supports


including cost of all materials,machinery, labour, scaling excavated surface,
removing under-cuts, ventilation, lighting, drainage, removing and hauling the
excavated muck outside tunnel upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Excavation for tunnel by tunnelling methods including excavation for


supports in all types of soil / rock strata requiring supports ( excluding cost
of providing supports ) including cost of all other materials, machinery, labour,
scaling excavated surface, ventilation, lighting, drainage, removing and hauling
the excavated muck outside tunnel upto specified dump area and all other
ancillary operations etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Itemwise unit rate


for Labour
Component
6

183.90

834.40

sqm

Providing and constructing 75 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each including
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips, etc., complete with initial lead upto 50 m and all lifts.

EXCAVATION :

77

IRR-TAW-1

IRR-TAW-1-2

Rate

TUNNEL AND ALLIED WORKS

76

Unit

Providing and constructing 60 cm thick hand packed rough stone revetment


with 65 to 75 cm long through stones at 1.50 m c / c over a backing of 60 cm
thick graded filter media consisting of sand, 10 mm and 40 mm size approved
graded aggregates laid in layers of 20 cm thick each including cost of all
materials, machinery, labour, laying to required slopes, wedging with chips,
finishing etc. complete with initial lead upto 50 m and all lifts.

Chapter II
IRR-TAW

IRR-TAW-1-1

Item description

124.20

910.10

135.40

999.10

157.90

107.70

62.50

1750.60

590.50

2316.20

1177.80

1786.70

581.70

1839.00

600.60

10

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-TAW-1-5

80

Item description

Unit

Rate

cum

1887.90

Excavation for tunnel by heading and benching tunnelling methods including


excavation for supports in all types of soil / rock strata requiring supports (
excluding cost of providing supports ) for roof before benching including cost of
all other materials, machinery, labour, scaling excavated surface, ventilation,
lighting, drainage removing and hauling excavated muck outside tunnel upto
specified dump area and all other ancillary operations etc., complete with initial
lead upto 1 km and all lifts.

Itemwise unit rate


for Labour
Component
6

NOTE: Where mucking is to be carried out through shaft using winch and
mucking tub system increase the basic rates for items 3, 4 & 5 by 8 percent.
Labour Component (including contractor's profit and Overheads)

IRR-TAW-1-6

81

IRR-TAW-2

IRR-TAW-2-1

IRR-TAW-2-2

IRR-TAW-2-3
(new Item4 201011)

IRR-TAW-3-2

IRR-TAW-3-3

IRR-TAW-3-4

cum

645.70

364.90

cum

89.80

DEWATERING & GUNITING WORKS :

82

83

84

IRR-TAW-3

IRR-TAW-3-1

Removing and hauling muck overfallen due to natural causes such as


geological faults etc., out of tunnel including breaking large fragments by blasting
if necessary and disposing off the same in specified dump area or as directed
including cost of all materials, machinery, labour, ventilation, drainage, lighting
and all other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.
Labour Component (including contractor's profit and Overheads)

cum

Dewatering tunnel by pumping out water collected by natural drainage inside


tunnel including providing sump wherever necessary, cost of all materials,
machinery, labour, drainage, lighting, ventilation and all other ancillary operations
etc., complete.
Labour Component (including contractor's profit and Overheads)
Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar
1 : 3 proportion by weight including cost of all materials, machinery, labour,
ventilation, lighting, drainage and all other ancillary operations etc., complete
with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

Kwhr

23.60

Kwhr

sqm

8.30

630.00

sqm

Shortcreting in two layers (each layer+38 mm thickness) for slabs duly


fixing chain weld wire mesh 100 x 100x5 mm in between the two layers including
cost and conveyance of all materials, labour charges, all heads, lifts, centering,
scaffolding, machine mixing, laying concrete with shortcrete machine etc.
complete as per specification and as directed by Engineer-in-Charge

sqm

Labour Component (including contractor's profit and Overheads)

sqm

185.10

1524.00

185.10

TEMPORARY & PERMANENT SUPPORTS :

85

86

87

88

Providing and fixing 25 mm diameter steel rock bolts with mechanical /


wedge type anchorage including drilling 35 mm dia holes, providing 15 cm long
20 mm thick steel tapered wedge, 10 mm thick plate washers and nuts,
tightening bolt by torque wrench, cost of all materials, machinery, labour,
ventilation, lighting, drainage and all other ancillary operations etc., complete
with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 25 mm diameter steel rock bolts with resin bond cement
capsule anchorage including drilling 35 mm dia holes, inserting grout capsule,
driving bolt,fixing 10 mm thick plate washers and nuts and tightening the same
by torque wrench after hardening of cement grout, cost of all materials,
machinery, labour, ventilation, lighting, drainage and other ancillary operations
etc., complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

Rm

Rm

Rm

315.30

1020.70

Rm

Providing, fabricating and fixing in position permanent structural steel


supports as per details including cost of all materials, machinery, labour,
cutting, bending, welding, grinding, lighting, ventilation, drainage and all other
ancillary operations etc., complete with initial lead upto 1 km and all lifts.

tonne

Labour Component (including contractor's profit and Overheads)

tonne

Providing, fabricating and fixing in position temperary structural steel


supports as per details and dismantling the same before concreting including
cost of all materials, machinery, labour, cutting, bending, welding, grinding,
ventilation, lighting, drainage and all other ancillary operations etc.,complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

1063.40

tonne

tonne

290.50

88520.40

17121.30

22212.60

8555.10

11

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

IRR-TAW-3-5

89

3
Providing and fixing hard variety cut jungle wood for lagging / blocking
locations in tunnel wherever required including cost of all materials, machinery,
labour, fixing in position, lighting, ventilation, drainage etc complete with all
leads and lifts.
Labour Component (including contractor's profit and Overheads)

cum

34880.10

IRR-TAW-4

IRR-TAW-4-1

IRR-TAW-5-2

IRR-TAW-5-3

IRR-TAW-5-4

90

Providing and constructing un-coursed rubble stone masonry with approved


stones from tunnel excavated muck in cement mortar 1 : 6 proportion for
backfilling over cuts / slips on tunnel sides due to geological faults etc., including
cost of all materials, machinery, labour, cleaning,scaffolding, packing mortar,
wedging stone chips, curing, ventilation, lighting, drainage complete with lead
upto 1 km and all lifts.(cement content : 95 kg/cum of masonry, Rubble stones
: 0.83 cum, Stone chips : 0.13 cum,FA : 0.40 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

2478.30

780.40

REINFORCEMENT & CONCRETE WORKS :

91

92

93

94

IRR-TAW-6

IRR-TAW-6-1

1495.90

MASONRY WORKS :

IRR-TAW-5

IRR-TAW-5-1

cum

Itemwise unit rate


for Labour
Component
6

Providing, fabricating and placing in position reinforcement steel for tunnel


RCC works including cleaning, straightening, cutting, bending, hooking, lapping
/ welding joints wherever required, tying with 1.25 mm dia.soft annealed steel
wire, including cost of all materials, labour, machinery, ventilation, lighting,
drainage etc.,complete with initial lead upto 1 km and all lifts.

tonne

Labour Component (including contractor's profit and Overheads)

tonne

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates crushed from tunnel excavated muck
for filling and levelling over-cuts in bed due to geological faults etc., including
cost of all materials, machinery, labour, cleaning bed, batching, mixing,
conveying and laying, levelling, compacting, finishing, curing, lighting, ventilation,
drainage etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40
cum, Superplasticizer 0.4% by wt. of cement)

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for kerb and
bed lining including cost of all materials, machinery, labour, formwork, batching,
mixing, conveying upto placing point in agitator cars, placing in position,
levelling, vibrating, finishing, curing, ventilation, lighting, drainage and all other
ancillary operations etc., complete with lead upto 1 km and all lifts. ( Cement
content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for sides
and arch lining including cost of all materials, machinery, labour, formwork,
batching, mixing, conveying upto placing point in agitator cars, placing in
position, levelling, vibrating, finishing, curing, ventilation, lighting, drainage and
all other ancillary operations etc., complete with lead upto 1 km and all lifts. (
Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

65041.30

10293.50

5763.00

783.90

7107.80

976.60

7312.40

768.20

DRILLING & GROUTING WORKS :

95

Drilling 32 mm diameter grout holes in concrete / rock by percussion


drilling using jack hammer or stooper drills as directed to specified depth for
consolidation / contact grouting including cost of all materials, machinery, labour,
cleaning holes, ventilation, lighting, drainage and all other ancillary operations
etc., complete.
Labour Component (including contractor's profit and Overheads)

Rm

Rm

399.10

151.60

12

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-TAW-6-2

IRR-TAW-6-3

96

97

Chapter III
IRR-CAW

IRR-CAW-1-2

Unit

Rate

Grouting cement slurry in grout holes under specified pressure for


consolidation / contact grouting including cost of all materials, machinery,
labour, redrilling wherever necessary, ventilation,lighting, drainage and other
ancillary operations etc., complete with lead upto 1 km and all lifts.

tonne

11980.40

Labour Component (including contractor's profit and Overheads)

tonne

Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in


tunnel by percussion drilling using waggon drill or other suitable drilling
equipment including cost of all materials, machinery, labour, ventilation, lighting,
drainage etc., complete.
Labour Component (including contractor's profit and Overheads)

Rm

Itemwise unit rate


for Labour
Component
6

2318.70

365.50

Rm

62.80

CANAL AND ALLIED WORKS

IRR-CAW-1

IRR-CAW-1-1

Item description

98

99

EXCAVATION WORKS :
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal,
seating of embankment, filter drains / catch water drains etc., including dressing
bed and sides to required level and profile, cost of all materials, machinery,
labour, placing the excavated soil neatly in dump area or for the formation of
service road / embankment as directed etc., complete with initial lead upto 1
km and all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation in all kinds of soil including boulders upto 0.30 m dia for field
channels, seating of embankment for field channels etc., including dressing of
bed and sides to required profile, cost of all materials, machinery, labour, placing
the excavated stuff for formation of service road / embankment as directed etc.,
complete with lead upto 10 m and lift upto 3 m.

cum

93.90

cum

cum

23.90

50.00

(Machinery excavation and manual conveyance)


Labour Component (including contractor's profit and Overheads)

IRR-CAW-1-3

Excavation in ordinary rock (including HDR) without blasting including


boulders above 0.30 m upto 0.6 m dia. for canals, seating of embankment, filter
drain / catch water drains etc., including dressing of bed and sides to required
100
level and profile, cost of all materials, machinery, labour, placing the excavated
soft rock neatly in dump area or for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-1-4

Excavation in ordinary rock (including HDR) without blasting including


boulders above 0.3 m upto 0.60 m dia. for field channels, seating of
embankment for field channels etc., including dressing of bed and sides to
101 required profile, cost of all materials, machinery, labour, placing the excavated
stuff for formation of service road as directed etc.,complete with lead upto 10 m
and lift upto 3 m.
(Machinery excavation and manual conveyance)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-1-5

Excavation in hard rock (including F&F rock) requiring blasting including


boulders above 0.6 m upto 1.2 m dia. for canals, seating of embankment, filter
102 drain / catch water drains etc., including dressing bed and sides to required level
and profile, cost of all materials, machinery, labour, placing the excavated rock in
dump area or for formation of service road as directed etc., complete with lead
upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

cum

19.20

127.40

cum

cum

35.60

83.00

cum

cum

31.80

196.40

cum

Excavation in hard rock of all toughness by blasting including boulders above


1.2 m dia. for canals, seating of embankment, filter drain / catch water drains
etc., including levelling the bed by removing all projections by hammering /
chiselling, cost of all materials, machinery, labour, placing the excavated rock
neatly in approved dump area and levelling the same as directed etc., complete
IRR-CAW-1-6 (a) 103 with initial lead upto 1 km and all lifts.

cum

i ) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth excavation in hard
rock is less than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock
projections wherever required.
Labour Component (including contractor's profit and Overheads)

cum

64.50

486.60

139.10

13

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

3
Excavation in hard rock of all toughness including boulders above 1.2 m dia. by
approved controlled blasting methods for canals, cut-off trench of
embankment, filter / catch-water drains etc., including controlling fly-rock by
muffling arrangements such as placing 50 x 50 mm opening chain link mesh or
waste tyres and sand bags, monitoring ground vibrations at specified locations,
costof all materials, machinery, labour, placing excavated rock neatly in
IRR-CAW-1-7 (b) 104 approved dump area or other place as directed etc., complete with lead upto 1
km and all lifts.
i) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth excavation in hard
rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads)
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
for dressing canal sides neatly on either side to required profile by line drilling
and smooth blasting including removing under-cuts by chiselling / hammering,
placing the excavated rock neatly in dump area or other place as directed, cost
of all materials, machinery, labour etc., complete with lead upto 1 km and all
lifts.
i) For excavation of canal below free board level combination of normal
controlled blasting and line drilling and smooth blasting shall be adopted to
IRR-CAW-1-8( c) 105 obtain neat side slopes. For the purpose of payment 1 m width of excavation on
either side shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth of excavation in
hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated
face has come off neatly as per specifications or atleast 50 percent of smooth
Labour Component (including contractor's profit and Overheads)

Unit

Rate

cum

617.90

cum

cum

Itemwise unit rate


for Labour
Component
6

137.10

1069.20

cum

366.30

Excavation in hard rock by blasting including boulders above 1.2 m dia. for
canals, seating embankment etc., including levelling bed by removing all
projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same
as directed etc.,complete with initial lead upto 1 km and all lifts.
IRR-CAW-1-9(a)

106

cum

298.20

i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering /chiselling all rock
projections wherever required.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-110(b)

Excavation in hard rock of all toughness including boulders above 1.2 m dia.
by approved controlled blasting methods for canals, cut-off trench of
embankment etc., including controlling fly-rock by muffling arrangements such
as placing 50 x 50 mm opening chain link mesh or waste tyres and sand bags,
monitoring ground vibrations at specified locations, cost of all materials,
machinery, labour, placing excavated rock neatly in approved dump area or
107 other place as directed etc., complete with lead upto 1 km and all lifts.

cum

cum

43.90

446.90

i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads)

cum

50.20

14

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-CAW-111(c)

IRR-CAW-2

IRR-CAW-2-1

Item description

3
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
for dressing canal sides neatly on either side to required profile by line drilling
and smooth blasting including removing under-cuts by chiselling / hammering,
placing the excavated rock neatly in dump area or other place as directed, cost
of all materials, machinery, labour etc., complete with lead upto 1 km and all
lifts.
i ) For excavation of canal below free board level combination of normal
controlled blasting and line drilling and smooth blasting shall be adopted to
108 obtain neat side slopes. For the purpose of payment 1 m width of excavation on
either side shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated
face has come off neatly as per specifications or atleast 50 percent of smooth
Labour Component (including contractor's profit and Overheads)

Providing impervious hearting embankment with selected soil from approved


borrow areas in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
109 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.

Providing impervious hearting embankment with selected soil from approved


borrow areas in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
110 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-3

Providing semi-pervious / pervious casing embankment using soil from


approved borrow area in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sortingout,
111 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting to density control of not less than 98 percent
or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power
roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-4

Providing semi-pervious / pervious casing embankment using soil from


approved borrow area in layers of 25cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sortingout,
112 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting to density control of not less than 95 percent
or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power
roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-5

Rate

cum

734.30

cum

Itemwise unit rate


for Labour
Component
6

113.20

EMBANKMENT WORKS USING BORROW AREA SOIL :

Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-2

Unit

Providing semi-pervious / pervious casing embankment using soil from


approved borrow area in layers of 25cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sortingout,
113 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, compacting each layer without watering to density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)

cum

196.40

cum

cum

32.90

189.70

cum

cum

32.40

196.20

cum

cum

32.90

191.90

cum

cum

cum

34.70

178.70

30.00

15

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

169.70

IRR-CAW-2-6

Providing hearting / casing embankment with homogeneous soil from


approved borrow areas in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sorting out,
114 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-7

Providing hearting / casing embankment with homogeneous soil from


approved borrow areas in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sorting out,
115 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-8

Providing casing embankment using homogeneous soil from approved


borrow area in layers of 25 cm before compaction including cost of all materials,
machinery, labour, all operations such as excavation, sortingout, transporting,
116 spreading in layer of specified thickness, breaking clods, sectioning, compacting
each layer without watering to density control of not less than 95 percent or as
stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-3

IRR-CAW-3-1

IRR-CAW-3-2

IRR-CAW-3-3

cum

27.30

163.80

cum

cum

26.70

153.90

cum

24.50

EMBANKMENT WORKS USING DUMP AREA SOIL :


Providing impervious hearting embankment with soil from approved dump
areas in layers of 25 cm before compaction including cost of all materials,
machinery, labour, all operations such as re-excavation, sorting out,
117 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to achieve density control of not
less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc.,complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing impervious hearting embankment with soil from approved dump
areas in layers of 25 cm before compaction including cost of all materials,
machinery, labour, all operations such as re-excavation, sorting out,
118 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to achieve density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc.,complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing semi-pervious / pervious casing embankment using soil from
approved dump area in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as re-excavation, sorting out,
119 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-3-4

cum

Itemwise unit rate


for Labour
Component
6

Providing semi-pervious / pervious casing embankment using soil from


approved dump area in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as re-excavation, sorting out,
120 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

149.00

cum

cum

25.20

143.70

cum

cum

24.90

144.80

cum

cum

cum

24.40

139.30

24.00

16

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-CAW-3-5

IRR-CAW-4

IRR-CAW-4-1

Item description

3
Providing semi-pervious / pervious casing embankment using soil from
approved dump area in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as re-excavation, sorting
out, transporting, spreading in layer of specified thickness, breaking clods,
121
sectioning, compacting each layer without watering to density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)

Providing impervious hearting embankment with soil collected in


embankment area in heaps as part of disposal of excavated soil from canal
including cost of all materials,machinery, labour, all operations such as
122 sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not
less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with lead upto 1 km for water.

Providing impervious hearting embankment with soil collected in


embankment area in heaps as part of disposal of excavated soil from canal
including cost of all materials,machinery, labour, all operations such as
123 sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with lead upto 1 km for water.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-3

Providing semi-pervious / pervious casing hearting embankment using soil


collected in heaps in embankment area as part of disposal of excavated soil from
canal including cost of all materials, machinery, labour, all operations such as
124 sorting-out, spreading in layers of 25 cm before compaction, breaking clods,
sectioning, watering and compacting each layer to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with lead upto 1 km for water.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-4

Providing semi-pervious / pervious casing embankment using soil collected in


heaps in embankment area as part of disposal of excavated soil from canal
including cost of all materials, machinery, labour, all operations such as sorting125 out, spreading in layers of 25 cm before compaction, breaking clods,
sectioning, watering and compacting each layer to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with lead upto 1 km for water.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-5

Providing semi-pervious / pervious casing embankment using soil collected in


heaps in embankment area as part of disposal of excavated soil from canal
including cost of all materials, machinery, labour, all operations such as sorting126 out, spreading in layers of 25 cm before compaction, breaking clods, sectioning
and compacting each layer without watering to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-6

Rate

cum

130.60

cum

Itemwise unit rate


for Labour
Component
6

22.00

EMBANKMENT WORKS USING EXCAVATED SOIL :

Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-2

Unit

Providing compacted embankment for field irrigation channels with gravely


soil from approved borrow area including sorting out, spreading in layers of 15
cm thickness, breaking clods, watering, compacting, dressing sides to required
127
slopes etc.,complete with lead upto 50 m and all lifts.

cum

66.60

cum

cum

10.10

61.20

cum

cum

10.30

66.60

cum

cum

10.10

61.20

cum

cum

10.30

51.00

cum

cum

7.40

281.50

( manual work with water pump)


Labour Component (including contractor's profit and Overheads)
IRR-CAW-5

IRR-CAW-5-1

cum

277.30

FOUNDATION FILLING WORKS :


Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all
128 materials, machinery, labour, watering, ramming etc., complete with initial lead
upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

cum
cum

770.30
140.90

17

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

568.10

IRR-CAW-5-2

IRR-CAW-5-3

IRR-CAW-5-3-A
(New Item 3 2011-12)

IRR-CAW-5-4

IRR-CAW-5-5

IRR-CAW-5-6

Providing rubble and Murum filling in layers of 22.5 to 30 cm including cost of


129 all materials, machinery, labour, watering, ramming etc., complete with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying 25 cm thick sand blanket below embankment including
130 cost of all materials, machinery, labour, spreading to specified thickness etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying sand blanket below embankment including cost of all
131 materials, machinery, labour, spreading to specified thickness etc., complete
with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-5-8

IRR-CAW-5-9

Providing and constructing dry rubble rock-toe using rubble and stone chips
132 from approved source including cost of all materials, machinery, labour, hand
packing rubble and stone chips, finishing top and sides to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing longitudinal and cross graded filter drains using
sand and 20 mm down graded aggregates satisfying specified filter creteria in
133 layers as per specifications including cost of all materials, machinery, labour,
laying to required slopes, compaction etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm
134 in Bed and filling with 12 mm to 40 mm HG machine Crushed metal and sand in
bed including excavation of drains and Cost of procuring of all materials

Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed
135 and sides using 1.181 Kgs of cement per each using 20 mm HG metal and
placing in local filters of size 600x600x750 mm in size including excavation of
drains and Cost of procuring of all materials
Labour Component (including contractor's profit and Overheads)
Providing and constructing 0.50 m thick vertical or inclined graded filter
media consisting of 15 cm thick sand layers and 20 cm thick 20 mm down coarse
136 aggregate layer using approved materials satisfying specified filter creteria as
per specifications including cost of all materials, machinery, labour, laying to
required slope, compaction etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing graded filter media below and behind rock-toe
consisting of 20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm
down size graded coarse aggregates satisfying filter creteria behind rock-toe and
137 15 cm thick sand, 20 cm thick 20 mm down coarse aggregate and 65 cm thick 40
mm down size coarse aggregate satisfying filter creiteria below rock-toe as per
specifications including cost of all materials, machinery, labour, laying to required
slope, compaction etc., complete with initial lead upto 50 m and all lifts.

Providing and laying filter media consisting of 2 layers of poly-propeline


nonwoven filter fabric and 200 mm thick 20 mm down graded coarse aggregate
for embankment including cost of all materials, machinery, labour, forming toe
138 drain etc., complete with lead upto 50 m for aggregate and all leads for fabric
and all lifts.
Using 200 gsm filter fabric.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-511(b)

Providing and laying filter media consisting of 2 layers of poly-propeline


nonwoven filter fabric and 200 mm thick 20 mm down graded coarse aggregate
for embankment including cost of all materials, machinery, labour, forming toe
139 drain etc., complete with lead upto 50 m for aggregate and all leads for fabric
and all lifts.
Using 250 gsm filter fabric.
Labour Component (including contractor's profit and Overheads)

140.90

176.70

sqm

17.60

706.70

cum

Labour Component (including contractor's profit and Overheads)

IRR-CAW-510(a)

sqm

cum

133

IRR-CAW-5-7

cum

cum

70.40

537.60

cum

cum

100.90

916.80

cum

Rm

131.30

448.50

Rm

one plug

24.90

366.30

one plug

cum

105.70

1024.90

cum

cum

131.30

1198.60

cum

sqm

122.70

600.10

sqm

sqm

sqm

Itemwise unit rate


for Labour
Component
6

29.20

652.50

29.20

18

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.
1
IRR-CAW-6

IRR-CAW-6-1

IRR-CAW-6-2

S.NO
2

Item description

Unit

Rate

cum

489.70

ROCK FILL WORKS :


Providing and constructing rockfill casing to canal embankment with graded
stones and spalls from approved quarry including cost of all materials,
140 machinery, labour, spreading stones and spalls in layers, hand packing,
wedging, finishing surface to required slopes etc., complete with initial lead
upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing rockfill casing to canal embankment with graded
stones and spalls available in dump yard including cost of all materials,
machinery, labour, spreading stones and spalls in layers, hand packing,
141
wedging, finishing surface to required slopes etc., complete with initial lead
upto 50 m and all lifts.
Stones and spalls available in dump yard will be issued at specified issue rate.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7

IRR-CAW-7-1

IRR-CAW-7-2

IRR-CAW-7-3

IRR-CAW-7-4

Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
142 more than 15 cm, breaking clods, watering, compacting to density control of not
less than 98 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
143 more than 15 cm, breaking clods, watering, compacting to density control of not
less than 95 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing cohesive non-swelling ( CNS ) soil lining to canal using soil
collected in heaps along the edge of canal requiring CNS soil lining as part
of the disposal of excavated soil from canal excavation in CNS soil reach
144 including spreading in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 95 percent or as
stipulated, dressing to required profile etc., complete with lead upto upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal
145 bed level stones including cost of all materials, labour, excavation, fixing in
position to correct level etc., complete with lead upto 50 m and all lifts.

Providing, fabricating and placing in position reinforcement steel bars for RCC
works including cleaning, straightening, cutting, bending, hooking, lapping, tying
146 with 1.25 mm dia.soft annealed steel wire, welding wherever required including
cost of all materials, machinery, labour etc., complete with initial lead upto 50
and all lifts.(1.05 tonne/tonne of steel)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-6

cum

cum

53.40

287.80

cum

68.90

CANAL LINING WORKS :

Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-5

Itemwise unit rate


for Labour
Component
6

Providing and laying 75 mm thick in-situ M-15 ( 28 days cube compressive


strength not less than 15 N / sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using vibrating
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position,finishing, forming contraction
147 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to
other side of canal etc., complete with initial lead upto 1 km and all lifts. ( 43
Gr Cement content: (300kg /cum) 22.5 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:79.2 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Labour Component (including contractor's profit and Overheads)

cum

211.50

cum

cum

64.40

206.60

cum

cum

63.50

105.20

cum

Each

48.50

91.80

Each

kg

65.70

55.80

kg

sqm

sqm

7.30

464.10

29.70

19

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

sqm

484.80

IRR-CAW-7-7

Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive


strength not less than 15 N / sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using vibrating
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position, finishing, forming contraction
148 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to
other side of canal etc., complete with initial lead upto 1 km and all lifts. ( 43
Gr Cement content: (300kg /cum) 24 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:84.48 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-8

Providing and laying 100 mm thick in situ M-15 (28 days cube compressive
strength not less than 15 N /Sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using, vibrating,
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position, finishing, forming contraction
149 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to
othere side of canal etc., complete with initial lead upto 1 Km and all lifts. ( 43
Gr Cement content: (300kg /cum) 30 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:88 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-9

Dismantling, shifting and re-erecting mechanical concrete paver and DG set


with all accessories across canal CD work or other locations wherever shifting
and re-erecting is necessary including aligning paver correctly for continuing
canal lining work, cost of all materials, machinery, labour etc., complete with all
150 leads and lifts.
Note: Local shifting and re-erection of paver for LH and RH side lining included
in concrete lining rates under items IRR-CAW-7-7 and IRR-CAW-7-8 and
saperate rate for shifting shall not be allowed.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-10

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for bed and side lining of canal(150mm
thick) including finishing the junction of bed and sides to required curveture,
cost of all materials, machinery, labour, formwork including supports, cleaning,
151 batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( 43 Gr Cement content: 250
kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)

sqm

sqm

29.70

588.90

sqm

shifting

34.30

8830.60

shifting

cum

Itemwise unit rate


for Labour
Component
6

6428.80

4865.80

(Only forManually operated)


Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-11

Providing and laying insitu vibrated M-10 (28 days cube compressive strength
not less than 10 N/sqm) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregade for bed and side lining of canal(100
mm thick) including, finishing the junction of bed and sides to required
152 curveture, cost of all materials, machinery, labour, formwork including supports
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead up to 50 m and all lifts ( 43 Gr Cement
content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-12

Providing and laying 100mm thick insitu vibrated M-10 (28 days cube
compressive strength-not less than 10.00 N / sq mm) grade cement concrete
using 40 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver
153 including cost of all materials mechinery labour batching mixing placing in
position forming contraction joints fixing pvc joint seiling strips shifting of paver
from one side of canal to other side etc.complete with all leads & lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

cum

cum

1129.00

5005.10

cum

sqm

sqm

1162.60

556.10

34.30

20

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

4910.50

IRR-CAW-7-13

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N /sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for bed and side lining of canal
including finishing the junction of bed and sides to required curveture, cost of all
154 materials, machinery, labour, formwork including supports, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 250 kg / cum for use
of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA-65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-14

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for bed and side lining(150 mm thick)
of canal including finishing the junction of bed and sides to required curveture,
155 cost of all materials, machinery, labour, formwork including supports, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. (Cement content: 290 kg /
cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-15

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for bed and side lining(of thickness
100 mm) of canal including finishing the junction of bed and sides to required
156 curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
300 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80 cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-16

Providing and laying 150mm thick insitu vibrated M-15 (28 days cube
compressive strength-not less than 15.00 N / sq mm) grade cement concrete
using 20 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver including
cost of all materials mechinery labour batching mixing placing in position forming
157 contractiom joints fixing pvc joint seiling strips shifting of paver from one side of
canal to other side etc.complete with all leads & lifts. (Cement content: 300
kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80 cum,
Blending Ratio of CA--65:35, FA : 0.44 cum)
(Paver)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-17

Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15
grade concrete using 20 mm down size coarse aggregates and 10 kg
reinforcement steel moulded as per specifications and drawing in CM 1:4
158 proportion including cost of all materials, machinery, labour, formwork,
fabricating and placing reinforcement steel, mixing, laying, conveying and fixing
in position including necessary excavation for seating, finishing joints in CM 1:4,
curing etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-18

IRR-CAW-7-19

IRR-CAW-7-20

159

Providing and fixing 50 mm dia perforated GI pressure relief pipes 12.50 cm


long with one end closed with perforated GI plate and other end provided with
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Providing and fixing 50 mm dia perforated GI pressure relief pipes 22.50 cm


160 long with one end closed with perforated GI plate and other end provided with
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

161

Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm


long with one end closed with perforated GI plate and other end provided with
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

cum

cum

1162.60

5307.30

cum

cum

1230.20

5464.70

cum

sqm

1299.40

792.80

sqm

Rm

34.30

973.60

Rm

Each

257.10

114.20

Each

Each

44.90

160.80

Each

Each
Each

Itemwise unit rate


for Labour
Component
6

44.90

192.60
44.90

21

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

IRR-CAW-7-21

162

Each

253.90

IRR-CAW-7-22

IRR-CAW-7-23

IRR-CAW-7-24

IRR-CAW-7-25

IRR-CAW-7-26

IRR-CAW-7-27

IRR-CAW-7-28

IRR-CAW-7-29

IRR-CAW-7-30

163

Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm


long with one end closed with perforated GI plate and other end provided with
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm
long with one end closed with perforated GI plate and other end provided with
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep
164 holes including cost of all materials, labour, drilling 8 mm dia holes etc. complete
with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and
165 side lining of canal laid on rock including cost of all materials, machinery, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

166

167

170

171

Each

Each

Each

44.90

221.30
22.50

268.70

Each

Labour Component (including contractor's profit and Overheads)

Each

Providing and fixing 25 to 40 mm thick Shahabad / Talikota / other similar


stone slabs with pointing and finishing joints neatly in CM 1:3 proportion for
canal / field channel lining including cutting slabs to required size, mixing mortar,
finishing joints neatly, curing etc., complete with lead upto 50 m and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

sqm

91.80

44.90

7.70

373.30

67.10

85.90

sqm

Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion for supporting


PCC slab lining including necessary excavation, refilling, flush pointing joints in
CM 1 : 3 propn, cost of all materials ( excluding PCC lug slabs ), labour, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Providing and fixing LDPE sheet for bed and sides of canal including cost of all
materials, labour, laying, joining etc., complete with all leads and lifts.

374.40

Each

Each

Fixing 30 cm height pre-cast drops for field channels as directed including


excavation, etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

44.90

Each

Providing and forming 35 x 35 x 40 cm deep filter drain consisting of 75 mm


thick 10 mm down coarse aggregate around pressure relief pipe and 75 mm thick
sand around coarse aggregate filter including cost of all materials, labour,
excavation of pit etc., complete with lead upto 50 m and all lifts.

Fixing PCC slabs of various sizes in CM 1 : 3 proportion to the side slopes of


canal including preparing bed, flush pointing joints in CM 1 : 3 propn, cost of all
168
materials ( excluding PCC slabs ), labour, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

169

Each

Each

62.30

48.00

41.80
175.30

Each

sqm

Itemwise unit rate


for Labour
Component
6

175.30

133.70

Using 500 micron thick LDPE sheet.


Labour Component (including contractor's profit and Overheads)
If the surface on which the LDPE sheet is to be laid is too rough and undulating
provide 75 mm thick sand backing to LDPE sheet. For providing 75 mm thick
Sand for backing add
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-31

Providing and fixing LDPE sheet for bed and sides of canal including cost of all
172 materials, labour, laying, joining etc., complete with all leads and lifts.
Using 750 micron thick LDPE sheet.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-32

Providing and fixing LDPE sheet for bed and sides of canal including cost of all
173 materials, labour, laying, joining etc., complete with all leads and lifts.

sqm
sqm

12.40
56.20

sqm

sqm

8.40

188.30

sqm

sqm

16.90

259.20

Using 1000 micron thick LDPE sheet.

22

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-CAW-7-33

IRR-CAW-7-34

IRR-CAW-7-35

IRR-CAW-7-36

IRR-CAW-7-37

Item description
3
Labour Component (including contractor's profit and Overheads)

Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler
174 boards for stone masonry lining of canal including cost of all materials, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler
175 boards for cement concrete lining of canal including cost of all materials,
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler
176 boards for cement concrete lining of canal including cost of all materials,
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and forming 35 mm wide and 10 mm thick construction /
177 contraction joints for concrete lining by mastic filler including cost of all
materials, labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28
days cube compressive strength not less than 15 N /sqmm ) cement concrete
using 20 mm down graded coarse aggregate including cost of all materials,
178 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
Blending Ratio of CA : 65:35, FA : 0.45cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-38

Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N / sqmm ) cement concrete using
20 mm down graded coarse aggregate including cost of all materials,
179 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
Blending Ratio of CA : 65:35, FA : 0.45cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-39

IRR-CAW-7-40

IRR-CAW-7-41

Manufacturing 450 x 300 x 30 mm size PCC lining slabs in M-15 grade ( 28


days cube compressive strength not less than 15 N / sqmm ) cement concrete
using 10 mm down graded coarse aggregate including cost of all materials,
180 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads)
Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N / sqmm ) cement concrete using
10 mm down graded coarse aggregate including cost of all materials,
181 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement),CA : 0.68 cum, FA :
0.43cum)
Labour Component (including contractor's profit and Overheads)
Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28
days cube compressive strength not less than 15 N/Sqmm) cement concrete
using 20 mm down grades coarse aggregate including cost of all materials,
182 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content
: 300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
FA : 0.45cum, Blending Ratio of CA--65:35)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-42

Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28


days cube compressive strength not less than 15 N / sqmm )cement concrete
using 10 mm down graded coarse aggregate including cost of all materials,
183 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)

Unit

Rate

4
sqm

Rm

192.60

Rm

Rm

7.70

81.60

Rm

Rm

7.70

120.70

Rm

Rm

7.70

7.60

Rm

Each

5.70

102.20

Each

Each

24.40

70.00

Each

Each

24.40

35.50

Each

Each

15.70

26.50

Each

Each

15.70

90.10

Each

Each

Itemwise unit rate


for Labour
Component
6
22.80

15.60

38.10

23

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-CAW-7-43

IRR-CAW-7-44

Item description
3
Labour Component (including contractor's profit and Overheads)

Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N /sqmm ) cement concrete using
10 mm down graded coarse aggregate including cost of all materials,
184 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads)
Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion
for canal side lining using stones and chips from approved quarry including cost
of all materials, machinery, labour, forming weep holes at specified intervals,
185
finishing, curing etc., complete with initial lead upto 50 m and all
lifts.(Thickness of the masonry assumed: 0.3 m, rubble stones : 0.96 cum,
Stone Chips : 0.15cum,Through Stones 20 x 20 x 30cm : 1/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-45

Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for
canal side lining using stones from approved quarry including cost of all
186 materials, machinery, labour, forming weep holes at specified intervals, finishing,
curing etc., complete with initial lead upto 50m and all lifts.(with no pin
headers)(Thickness of the Masonry assumed:0.3 m, rubble stones : 1.1 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-46

IRR-CAW-7-47

Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion


for canal side lining using stones and chips from canal excavation including cost
187 of all materials, machinery, labour, forming weep holes at specified interval,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.( rubble
stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm :
1/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for
canal side lining using stones from canal excavation including cost of all
188 materials, machinery, labour, forming weep holes at specified intervals,
finishing, curing etc., complete with initial lead upto 50m and all lifts.(with no
pin headers)( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8

IRR-CAW-8-1

IRR-CAW-8-2

IRR-CAW-8-2 A (New Item5 2011-12)

Rate

4
Each

Each

25.80

Each

cum

15.70

2317.40

cum

cum

600.90

3444.70

cum

cum

1981.90

2179.10

cum

cum

Itemwise unit rate


for Labour
Component
6
15.70

678.20

3239.00

cum

1981.90

ROCK PITCHING
Providing and constructing 25 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
189
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)
If 15 cm thick murum bed is to be provided below pitching add
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-1-A
(New Item4 2011-12)

Unit

Providing and constructing 22.5 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
190 finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.207 cum/sqm, Stone Chips : 0.3375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance Works)
Labour Component (including contractor's profit and Overheads)
Providing and constructing 25 cm thick dry rubble stone pitching including
191 cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.(with no pin headers)( rubble stones : 0.33
cum/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and constructing 225 mmm thick dry rubble stone pitching
192 including cost of all materials, labour, hand packing, finishing etc., complete with
initial lead upto 50 m and all lifts.(with no pin headers)( rubble stones :
0.2475 cum/sqm) (For Maintenance Works)
Labour Component (including contractor's profit and Overheads)

sqm

200.50

sqm
sqm
sqm

37.60

sqm

190.40

46.70
14.10

sqm

sqm

46.70

213.40

sqm

sqm
sqm

110.30

153.70
99.30

24

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

sqm

220.50

IRR-CAW-8-3

Providing and constructing 30 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
193
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-4

IRR-CAW-8-5

IRR-CAW-8-6

IRR-CAW-8-7

IRR-CAW-8-8

IRR-CAW-8-9

Providing and constructing 30 cm thick dry rubble stone pitching including


194 cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.(with no pin headers)( rubble stones : 0.33
cum/sqm)
Labour Component (including contractor's profit and Overheads)

195

Labour Component (including contractor's profit and Overheads)

sqm

Providing and constructing 45 cm thick dry rubble stone pitching including


196 cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.(with no pin headers)( rubble stones : 0.495
cum/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and constructing 30 cm thick rubble stone pitching set in CM 1: 5
proportion with pin headers at 2 per sqm in including cost of all materials,
197 labour, packing chips and mortar, finishing, curing etc., complete with initial
lead upto 50 m and all lifts.( rubble stones : 0.275 cum/sqm, Stone Chips :
0.045cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and Constructing 30 cm thick rubble stone pitching set in CM 1:5
198 Proportion including cost of all materials,labour, packing chips and mortar
,finishing etc.,complete( rubble stones : 0.33 cum/sqm )
Labour Component (including contractor's profit and Overheads)
Providing and constructing 30 cm thick dry khandki stone pitching using 20
to 25 cm size khandki stones with pin headers at 2 per sqm including cost of all
199 materials, labour, hand packing, finishing etc., complete with initial lead upto
50 m and all lifts.( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone
Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

Providing and constructing 45 cm thick dry khandki stone pitching using 25


to 30 cm size khandki stones with pin headers at 2 per sqm including cost of all
200 materials, labour, hand packing, finishing etc., complete with initial lead upto
50 m and all lifts.( Khandki stones 25- 30 cm height : 1200 Nos/sqm, Stone
Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

Providing and constructing 30 cm thick khandki stone pitching using 20 to 25


cm size khandki stones with pin headers at 2 per sqm set in CM 1 : 5 proportion
with pointing joints in CM 1:3 proportion including cost of all materials, labour,
201
packing chips and mortar, finishing, curing etc.complete with initial lead upto
50 m and all lifts.( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone
Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-12

Providing and constructing 45 cm thick khandki stone pitching using 25 to 30


cm stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing
joints in CM 1 : 3 proportion including cost of all materials, labour, packing chips
202
and mortar, finishing, curing etc., complete with initial lead upto 50 m and all
lifts.( Khandki stones 25- 30 cm height : 730 Nos/sqm, Stone Chips :
0.0675cum/sqm, Pin Headers 45cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-13

Providing 10 cm thick approved type grass turfing to the side slopes of


203 canal icluding cost of all materials, labour, watering for minimum 15 days
etc.,complete with lead 50 m and all lifts.(FA : 2 cum/sqm)
Labour Component (including contractor's profit and Overheads)

46.70

256.10

sqm

sqm

Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-11

sqm

Providing and constructing 45 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-10

sqm

sqm

132.40

331.90

65.70

384.10

sqm

sqm

198.50

561.10

sqm

sqm

79.90

469.70

sqm

sqm

17.70

294.60

sqm

sqm

46.70

314.60

sqm

sqm

65.70

617.50

sqm

sqm

76.30

768.50

sqm

sqm
sqm

Itemwise unit rate


for Labour
Component
6

104.60

104.00
59.40

25

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-CAW-8-14

Item description

3
Providing 10 cm thick approved type grass turfing to the side slopes of
canal icluding cost of all materials, labour, watering for minimum 15 days
204 etc.,complete with lead 50 m and all lifts.
with no sand
Labour Component (including contractor's profit and Overheads)

Chapter IV
IRR-CCDW

sqm

66.10

sqm

Itemwise unit rate


for Labour
Component
6

34.30

EXCAVATION & FOUNDATION TREATMENT WORKS :


(manual means of excavation and conveyance)
Excavation in all kinds of soil including boulders upto 0.30 m dia. for
205 foundations of canal cross drainage and other appurtenant structures and
placing the excavated stuff neatly in specified dump area or disposing off the
same as directed etc., complete with initial lead upto 50 m and initial lift upto
3 m.
Labour Component (including contractor's profit and Overheads)
Excavation for Structures- Mechanical Means
MORTH)

IRR-CCDW-1-2

Rate

CANAL CROSS DRAINAGE WORKS

IRR-CCDW-1

IRR-CCDW-1-1

Unit

206

cum

222.70

cum

222.70

( Data adopted from

Earth work in excavation in all kinds of soils of foundation of structures as


per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing
of sides and bottom and backfilling with approved material. ( depth upto 3
meters)
Labour Component (including contractor's profit and Overheads)

cum

92.50

cum

18.60

(manual means of excavation and conveyance)


IRR-CCDW-1-3

207

Excavation in ordnary rock (including HDR) without blasting including


boulders above 0.3 m upto 0.60 m dia. for foundations of canal cross
drainage and other appurtenant structures and placing the excavated stuff
neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

327.80

cum

327.80

( Data adopted from MORTH) (manual means of excavation and conveyance)


IRR-CCDW-1-4

208

Excavation in ordnary rock (including HDR) without blasting for foundations


of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as
directed etc., complete with initial lead upto 50 m and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

119.20

cum

20.70

(manual means of excavation after blasting and conveyance)

IRR-CCDW-1-5

Excavation in hard rock requiring blasting including boulders above 0.6 m


209 upto 1.2 m dia. for foundations of canal cross drainage and other appurtenant
structures and placing the excavated stuff neatly in specified dump area or
disposing off the same as directed etc., complete with initial lead upto 50 m
and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

336.60

cum

254.40

(manual means of excavation after blasting and conveyance)

IRR-CCDW-1-6

Excavation in hard rock of all toughness by blasting including boulders


210 above 1.2 m dia. for foundations of canal cross drainage and other
appurtenant structures and placing the excavated rock neatly in specified dump
area or stack yard as directed etc., complete with initial lead upto 50 m and
initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

525.80

cum

317.80

(manual means of excavation after controlled blasting and conveyance)


Hard Rock ( blasting prohibited ) ( Data adopted from MORTH)
IRR-CCDW-1-7

211

Excavation in hard rock with blasting ( blasting prohibited )prohibited for


foundations of canal cross drainage and other appurtenant structures and
placing the excavated rock neatly in or stack yard as directed etc., complete
with specified dump area initial lead upto 50 m and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

cum

981.80

318.70

26

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

Each

846.70

IRR-CCDW-1-8

IRR-CCDW-2

IRR-CCDW-2-1

IRR-CCDW-2-2

IRR-CCDW-2-3

Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel
anchor rods with 1.25 m length driven into 32 mm dia hole drilled in bed rock
212 and remaining length embedded in concrete / masonry including cost of all
materials, machinery, labour, drilling and cleaning hole, driving anchor rod,
grouting hole with thick cement slurry etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)

Providing, fabricating and placing in position reinforcement steel bars for


RCC works including cleaning, straightening, cutting, bending, hooking, lapping,
213 welding wherever required,tying with 1.25 mm dia soft annealed steel wire,
including cost of all materials, machinery, labour etc., complete with initial lead
upto 50 and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing, fabricating and fixing in position structural steel cutting edge
consisting of 100 x 100 x 10 mm angle and 250 x 12 mm plate for sinking 4.50 m
214 outer diameter foundation wells foundation wells including cost of all materials,
machinery, labour, bending, welding, providing anchors etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
215
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
216
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 250 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA-35:30:20:15, FA : 0.35 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-5

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
217
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 220 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-6

198.60

STEEL AND CEMENT CONCRETE WORKS :

Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-4

Each

Itemwise unit rate


for Labour
Component
6

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost of
all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
218
position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 220 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA-35:30:20:15, FA : 0.35 cum)
Labour Component (including contractor's profit and Overheads)

kg

56.10

kg

kg

7.70

70.10

kg

cum

9.20

4990.20

cum

cum

1170.80

4934.70

cum

cum

1219.70

4625.40

cum

cum

cum

1118.70

4696.50

1211.70

27

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

5442.80

IRR-CCDW-2-7

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost
of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing
219
in position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 310 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-8

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
220
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-9

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
221
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-10

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
222
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-11

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
223
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-12

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for well kerb including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
224 initial lead upto 50 m and all lifts. (Cement content: 350 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA-65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

cum

cum

1231.00

5877.80

cum

cum

1226.00

5912.30

cum

cum

1302.70

5535.60

cum

cum

1305.00

4968.80

cum

cum

cum

Itemwise unit rate


for Labour
Component
6

1212.60

7164.40

1575.40

28

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

6502.70

IRR-CCDW-2-13

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for well steining including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
225 initial lead upto 50 m and all lifts. (Cement content: 320 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-14

Providing and laying insitu M-15 ( 28 days cube compressive strength not less
than 15 N / sq mm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for well bottom plug by tremie or skip box
226
method including cost of all materials, complete with initial lead upto 50 m and
all lifts.(Cement content: 350 kg / cum with use of super plasticiser(0.4% by
wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-15

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for well top plug including cost of all
materials, machinery, labour, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m
227
and all lifts. (Cement content: 280 kg / cum with use of super plasticiser(0.4%
by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

cum

cum

1439.40

5204.60

cum

cum

Itemwise unit rate


for Labour
Component
6

1130.00

4735.10

If water is to be brought from other place add only lead charges @ 500 ltrs /
cum
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-16

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for well cap including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with initial
228 lead upto 50 m and all lifts. (Cement content: 330 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-17

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for piers and abutments including
cost of all materials, labour, machinery, formwork, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
229 initial lead upto 50 m and all lifts. (Cement content: 250 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA-35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-18

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for piers and abutments including
cost of all materials, labour, machinery, formwork, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
230 initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA-35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

cum

cum

1112.60

5306.50

cum

cum

1132.40

5856.90

cum

cum

cum

1504.40

5618.70

1495.90

29

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

5534.70

IRR-CCDW-2-19

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for piers and abutments including
cost of all materials, labour, machinery, formwork, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
231 initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-20

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for cantiliver / counterfort retaining
walls including cost of all materials, machinery, labour, formwork, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
232 curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-21

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates with placing and sinking plums of
size 150 to 80 mm upto 15 percent for gravity type retaining walls / piers /
abutments etc., including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
233
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of
cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25cum )
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-22

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard,graded aggregates for cast in-situ pipes including cost of
all materials, machinery, labour, cleaning, batching, mixing, placing in position,
234 levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m
and all lifts.(Cement content: 260 kg / cum with use of super plasticiser(0.4%
by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-23

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for cast in-situ pipes including cost of
all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead
235 upto 50 m and all lifts. (Cement content: 250 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA-35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

cum

cum

1383.60

6423.10

cum

cum

1432.60

5633.00

cum

cum

1341.10

5385.60

cum

cum

cum

Itemwise unit rate


for Labour
Component
6

1267.30

5324.90

1315.40

30

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

8533.50

IRR-CCDW-2-24

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for deck slab & kerb including cost of
all materials,machinery, labour, formwork, scaffolding, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
236 with initial lead upto 50 m and all lifts. (Cement content: 330 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio
of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-25

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for columns and beams including
cost of all materials, labour, machinery, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
237 etc.,complete with initial lead upto 50 m and all lifts. (Cement content: 330 kg
/ cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-26

Providing and laying insitu M- 20 ( 28 days cube compressive strength not less
than 20 N / sqmm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing joints with
238 asphalt mortar etc., complete with initial lead upto 50 m and all lifts. (Cement
content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA
: 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-27

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for troughs including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position,levelling, vibrating, finishing, curing etc., complete with initial
239 lead upto 50 m and all lifts. (Cement content: 330 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-3

IRR-CCDW-3-1

Sinking RCC wells vertically for foundation of piers and abutments in all
kinds of soil, sand and soft rock by approved well sinking method including
cost of all materials, machinery, labour, kent - ledge arrangements, disposal of
240 excavated material as disposal of excavated material as directed etc., complete
with lead upto 50 m for disposal of excavated material.(diameter of well
6.00m) (Data adopted from MORTH)

Filling foundation wells with sand in layers of 25 to 30 cm and compacting


241 by watering, ramming as directed including cost of all materials, machinery,
labour etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4

cum

1887.40

7562.10

cum

cum

1721.70

5214.20

cum

cum

1161.70

6955.60

cum

1596.40

FOUNDATION WELL SINKING WORKS :

Labour Component (including contractor's profit and Overheads)


for 3 to 10 meters for each running meter
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-3-2

cum

Itemwise unit rate


for Labour
Component
6

*Rm

3707.60

*Rm
*Rm
*Rm

5254.90

cum

769.60

cum

1603.10
2098.10

101.50

MASONRY WORKS :

31

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

cum

2564.50

IRR-CCDW-4-1

Providing and constructing un-coursed rubble stone masonry with approved


stones in CM 1 : 4 proportion for sub-structure portions of return walls /
abutments etc., including cost of all materials, machinery, labour, scaffolding,
242
cleaning, packing cement mortar, wedging stone chips, curing etc., complete
with initial lead upto 50 m and all lifts.(Cement content: 143 kg / cum of
masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-2

Providing and constructing un-coursed rubble stone masonry with approved


stones in CM 1 : 4 proportion for super-structure portions of return walls /
abutments etc., including cost of all materials, machinery, labour, scaffolding,
243
cleaning, packing cement mortar, wedging stone chips, curing etc., complete
with initial lead upto 50 m and all lifts.(Cement content: 143 kg / cum of
masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-3

Providing and constructing coursed rubble masonry second sort in CM 1:4


proportion with stones from approved source including cost of all materials,
machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone
244 chips, finishing, curing etc., complete with initial lead upto 50 m and initial lift
upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum,
FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180
Nos, Header stones 25 x 25x 45 cm : 60 Nos)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-4

Providing and constructing coursed rubble masonry first sort in CM 1:4


proportion with stones from approved source including cost of all materials,
machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone
245 chips, finishing, curing etc., complete with initial lead upto 50 m and initial lift
upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum,
FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180
Nos, Header stones 25 x 25x 45 cm : 60 Nos)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-5

IRR-CCDW-4-6

IRR-CCDW-4-7

Providing cement mortar pointing to coursed rubble face stone masonry in


CM 1 : 2 proportion by volume including raking and cleaning joints for 50 mm
246 depth, pressing cement mortar into joints, cost of all materials, labour,
scaffolding, finishing, curing etc., complete with initial lead upto 50 m and all
lifts.
246
Providing cement mortar pointing to coursed rubble face stone masonry in
CM 1 : 3 proportion by volume including raking and cleaning joints for 50 mm
247 depth, pressing cement mortar into joints, cost of all materials, labour,
scaffolding, finishing, curing etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume
248 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-8

Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume


249 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-9

Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume


250 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-10

Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume


251 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-5

cum

cum

729.70

2626.50

cum

cum

747.90

3056.20

cum

cum

841.10

3185.50

cum

sqm

970.40

127.00

sqm

sqm

86.90

117.20

sqm

sqm

86.90

180.00

sqm

sqm

122.10

168.40

sqm

sqm

122.10

259.80

sqm

sqm
sqm

Itemwise unit rate


for Labour
Component
6

163.40

240.60
163.40

COPING & RAILING WORKS :

32

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

sqm

626.60

IRR-CCDW-5-1

Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
252 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-5-2

Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
253 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-5-3

Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
254 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-5-4

IRR-CCDW-5-5

Providing and laying insitu M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete using 20 mm down size approved
clean, hard, graded aggregates for coping slab including cost of all materials,
255 machinery, labour, formwork, cleaning surface, batching, mixing, placing in
position, levelling, compacting, finishing, curing etc., complete with initial lead
upto 50 m and initial lift upto 3 m. (Cement content: 300 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA-65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
Providing and constructing protective railing consisting of in-situ railing posts
of size 15 x 15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre
to centre in M-20 grade concrete using 20 mm down size graded aggregates and
with each post reinforced by 4 Nos. of 8 mm dia main bars embedded in kerb
256
concrete for a depth of 40 cm and 5 Nos. of 6 mm dia. stirrups including fixing 3
rows of 40 mm dia. GI pipes with one coat of red oxide primer and two coats of
synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6

IRR-CCDW-6-1

Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
257 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
258 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-3

sqm

177.20

773.20

sqm

sqm

323.80

961.80

sqm

cum

512.40

6658.50

cum

Rm

1513.50

1349.40

Rm

169.10

HUME PIPE LAYING & JOINTING WORKS :

Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-2

sqm

Itemwise unit rate


for Labour
Component
6

Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
259 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
Labour Component (including contractor's profit and Overheads)

Joint

322.10

Joint

Joint

235.20

389.10

Joint

Joint

Joint

235.20

508.50

291.40

33

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

Joint

568.40

IRR-CCDW-6-4

Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
260 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-5

Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
261 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-6

Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
262 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-7

Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
263 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-8

Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
264 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-9

Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
265 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-7

IRR-CCDW-7-1

IRR-CCDW-7-2

IRR-CCDW-7-3

IRR-CCDW-7-4

Joint

Joint

291.40

690.10

Joint

Joint

347.70

733.60

Joint

Joint

347.70

811.20

Joint

Joint

382.90

874.20

Joint

Joint

Itemwise unit rate


for Labour
Component
6

382.90

1034.90

Joint

460.10

BACK FILLING & OTHER WORKS :


Providing rubble / boulder and sand filling behind abutment and return
266 walls in layers including cost of all materials, machinery, labour, watering,
ramming etc., complete with initial lead upto 50 m and initial lift upto 3 m.

267

268

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and filling murrum / gravely soil ( CNS soil ) for foundation or
around pipes including breaking clods, spreading in layers of 10 to 15 cm,
watering, compaction by earth masters to achieve density control of not less
than 95 percent etc., complete with lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and filling murum / gravely soil ( CNS soil ) for foundation or
above pipes including breaking clods, spreading in layers of 10 to 15 cm,
watering, compaction by power roller to achieve density control of not less
than 98 percent etc., complete with lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and fixing one line dressed 111x35x25 cm thick IRC standard
kilometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 70x45x40 cm, embedding the stone
269 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.

Each

835.10
205.60

415.00

258.20

278.30

103.50

1420.20

34

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-CCDW-7-5

Chapter V
IRR-GAW

IRR-GAW-1-1

IRR-GAW-1-2

IRR-GAW-1-3

Item description
3
Labour Component (including contractor's profit and Overheads)

Providing and fixing one line dressed 65x15x10 cm thick IRC standard
hectometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 50x45x40 cm, embedding the stone
270 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-1

Rate

4
Each

Each

1055.50

Each

Itemwise unit rate


for Labour
Component
6
443.10

374.90

GATES / HOISTS AND ALLIED WORKS

SPILLWAY RADIAL GATES


E.M Parts and anchorages
fabrication, supply, erection, testing and commissioning of embedded parts
for radial gate consists of sill beam, wall plates, anchor girders , yoke girders,
271 tie flats, trunnion supports etc., including cost of all materials, machinery, labour,
welding, finishing, with leads and lifts &all accessories
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under itemsinthis chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
RADIAL GATES
fabrication, supply, erection, testing and commissioning of radial gate
consisting of skin plate, stiffeners, horizontal girders, radial arms, trunnion
assemblies, tie beam, pulley supports, bracings, rubber seals, clamps etc., with
all accessories for spillway/canals including cost of all materials, machinery,
272 labour, seal fixing etc., complete as per specifications and approved
drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under itemsinthis chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

RADIAL GATES-ROPE DRUM HOISTS WITH HOIST BRIDGES


fabrication, supply, erection, testing and commissioning of electrically
operated rope drum hoist of adequate capacity consisting of base frames,
rope drums,connecting shaft, gear system, brake system, electric motor, wire
ropes, gate position indicator, manual operation arrangement etc., with all
273 accessories for spillway radial gate including cost of all materials, machinery,
labour,, greasing, providing hand railing and approach staircase with gate to
hoist platform, , complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under itemsinthis chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-1-4

Unit

RADIAL GATES
Walk way(cat walk)
Design, fabrication, supply, erection and commissioning of 1 metre wide
walkway connecting spillway piers / abutments at trunnion platform level
274 including cost of all materials, machinery, labour, cutting, etc., complete as per
specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

VERTICAL LIFT GATES-EM PARTS


Design, fabrication, supply, erection and commissioning of embedded parts
consisting of sill beam, slide tracks, seal seats, guide rails, dogging sets for
storage of stoplog elements etc., with all accessories for spillway stop log gates
275 and other vertical lift elements including cost of all materials, machinery, labour,
etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

tonne

145343.80

tonne

tonne

43697.40

129684.80

tonne

tonne
capacity

33286.70

41988.00

tonne
capacity

Rm

2660.00

99181.90

Rm

tonne

tonne

31657.90

160796.80

51925.90

35

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-GAW-2-2

Item description
3
vertical lift gates and stop log gate elements ( SLIDING GATES)

Design, fabrication, supply, erection, testing and commissioning of vertical lift


gates and stoplog gate elements, consisting of skin plate, horizontal and
vertical girders, stiffeners, lifting pins, bronze padded slide blocks/bearings,
guide shoes, rubber seals, clamps etc., with all accessories including cost of all
276 materials, machinery, labour, seal fixing etc.,complete as per specifications
and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as perscedule of rates under items in this chapter and add as applicable
separately)2
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-3

IRR-GAW-2-4

Unit

Rate

tonne

132071.40

tonne

STOP LOGS-automatic lifting beam


fabrication, supply, erection, testing and commissioning of automatic lifting
beam with all accessories for handling, lowering and lifting of spillway stop log
gate elements including cost of all materials, machinery, labour, cutting, aligning,
277 welding, finishing, etc., complete as per specifications and drawings with all
leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

tonne

MOVING GANTRY CRANE-CLASS II


fabrication, supply, erection, testing and commissioning of adequate capacity
Class- II type moving gantry crane consisting of rail mounted gantry frame, top
platform with hand railing, long / cross travel arrangements, rope drums, gear
systems, electric motors, electro-magnetic brake system, cabin, control panel,
278 wire rope, ladder, motorised cable reeling drum etc., with all accessories for
operating spillway stop log gate elements and river sluice / canal sluice
emergency gates including cost of all materials, machinery, labour, etc.,
complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)

tonne
capacity

Labour Component (including contractor's profit and Overheads)

113865.40

19338.30

231380.80

tonne
capacity

IRR-GAW-2-5

Rm

IRR-GAW-2-6

VERTICAL LIFT GATES/STOP LOGS - ROLLER MOUNTED


Design, fabrication, supply, erection, testing and commissioning of fixed wheel
type vertical lift service gate consisting of skin plate, vertical and horizontal
girders, wheels, stiffeners, lifting brackets, guide rollers, ballast blocks, teflon
claded rubber seals etc., with all accessories for river sluice / canal sluice vent
280 including cost of all materials, machinery, labour,welding ,aligning finishing seal
fixing etc.with all leads and lifts, complete as per specifications and approved
drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

tonne

VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP. POWER


OPERATED
Design, fabrication, supply, erection, testing and commissioning of adequate
capacity rope drum hoist consisting of hoist platform, rope drum, gear system,
electric motor, electro-magnetic brake system, hand operation assembly, control
281 panel, wire rope, pulleys, ladder etc., with all accessories for operating river
sluice / canal sluice service gate including cost of all materials, machinery,
labour, , complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)

tonne
capacity

IRR-GAW-2-7

38393.90

tonne

RAIL TRACK FOR GANTRY CRANE


Design, fabrication, supply, erection and commissioning of rail track using 45
kg / m standard rails on spillway bridge for movement of gantry crane for
handling and operating spillway stoplog gate elements / river sluice / canal sluice
279 emergency gate including cost of all materials, machinery, labour, complete as
per specifications
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

Itemwise unit rate


for Labour
Component
6

19535.80

7342.50

Rm

479.80

131393.50

tonne

36338.10

70666.00

36

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

4
tonne
capacity

tonne

112880.70

Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-8

IRR-GAW-2-9

HOIST BRIDGE/ WITH TRESSELS


Design, fabrication, supply, erection and commissioning of structural steel
hoist bridge consisting of columns, beams, bracings, stiffeners, ties, chequered
plate covering, hand railing, ladder etc., with all accessories for supporting rope
282 drum hoist for operating barrage gates including cost of all materials, machinery,
labour, welding, finishing, etc., complete complete as per specifications and
drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
ROPE DRUM HOIST WITHOUT HOIST BRIDGE FOR BARRAGE GATES
Design, fabrication, supply, erection, testing and commissioning of adequate
capacity rope drum hoist consisting of rope drum, pulleys, gear system,
electric motor, electro-magnetic brake system, manual operation assembly,
position indicator, control panel, wire rope etc., with all accessories for operating
283 vertical lift roller gates for barrage including cost of all materials, machinery,
labour, cutting, bending, aligning, anchoring, welding, finishing etc., complete
with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-10

SCREW GEAR HOISTS INCLUDING PLATFORM ( UPTO 10 TON CAP)


Design, fabrication, supply, erection, testing and commissioning of adequate
capacity screw gear type hoist consisting of supporting structure, platform,
284 ladder etc., with all accessories for operating canal escape / regulator gate
including cost of all materials, machinery, labour, cutting, bending, aligning,
anchoring, welding,finishing etc.,complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-11

MANUAL OPERATED ROPE DRUM HOISTS


Design, fabrication, supply, erection, testing and commissioning of adequate
capacity manually operated rope drum hoist consisting of hoist platform, rope
drum, gear system, brake system, wire rope, ladder etc., with all accessories for
285 operating canal regulator radial gate including cost of all materials, machinery,
labour, welding, finishing, cleaning, ., complete with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-12
New Item 201415-2

OT SLUICE SHUTTERS Screw Gear Hoist Including Platform for below 5


Tons Capacity (Small Gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad
Specification drawing for Krishna Delta System
286 Fabrication, supply, erection, testing and commissioning of Embedded parts
consisting of supporting structure, platform etc. with all accessories for
operating canal escape/ regulator gate with all accessories including cost of all
materials, machinery, labour, cutting, bending, aligning, anchoring, welding,
finishing etc. complete as per Specification and approved drawings (without
painting on mechanical cleaning surfaces which are added extra as per schedule
of rates under items in this chapter and add as applicable separately)
Labour Component (including contractor's profit and Overheads)

2538.00

tonne

tonne
capacity

32801.20

34920.60

tonne
capacity

tonne
capacity

1075.80

33260.70

tonne
capacity

tonne
capacity

4866.10

74976.20

tonne
capacity

Tonne

Tonne

Itemwise unit rate


for Labour
Component
6

6515.10

121623.80

24310.00

37

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

Tonne

77152.00

IRR-GAW-2-13
New Item 201415-3

IRR-GAW-2-14
New Item 201415-4

OT SLUICE SHUTTERS EM parts for Below 5 Tons capacity (small gates)


As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad
Specification drawing for Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts
287
consisting of sil beam, slide tracks, seal seats, Guide plates etc. with all
accessories including cost of all materials, machinery, labour, etc. complete as
per specifications and approved drawings. (without painting on mechanical
cleaning surfaces which are added extra as per schedule of rates under items in
this chapter and add as applicable separately)
Labour Component (including contractor's profit and Overheads)
OT SLUICE SHUTTERS for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad
Specification drawing for Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Sluice Shutters
288 consisting of skin plate, horizontal and vertical angles, stiffeners, rubber seals,
clamps with all accessories for sluice shutters including cost of all materials,
machinery, labour, seal fixing etc., complete as per specifications and approved
drawings (without painting on mechanical cleaning surfaces which are added
extra as per schedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-3

IRR-GAW-3-1

IRR-GAW-3-2

IRR-GAW-3-4

IRR-GAW-3-5

IRR-GAW-4

Tonne

20340.30

192481.40

Tonne

10291.50

SAND BLASTING AND PAINTING


Cleaning gates / hoists / embedded parts/lifting beams etc, to expose fresh
289 metal surface for painting by sand blasting method as per specifications
including cost of all materials, labour, machinery, scaffolding, etc., complete
with initial lead for sand upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

painting of embedded metal parts and all types of gates, stoplogs,etc, on


sand blasted surfaces with one coat of inorganic zinc silicate (airless spray
preferred)70+/- 5 and two super coats with a total thickness of 300 microns
(each 150+/- 5) of solventless coaltar epoxy paint each coat 150 microns ( total
290 300 microns) cost of all materials, labour, scaffolding etc., complete with all leads
and all lifts
(Upstream surface of gates portion may be painted with solventless coaltar
epoxy brown paint instead of solventless coaltar black. The rate for
coaltar epoxy brown shall be adopted in data for Upstream side painting)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-3-3

Tonne

Itemwise unit rate


for Labour
Component
6

291

painting of Lifting beams,cat walks and other similar structures-painting


hoist machinery, on sand blasted surfaces with two coats of zinc phosphate
primer (airless spray preferred) 40microns/coat and twocoats of alkyd based
micaccous iron oxide paint , 65 microns/coat cost of all materials, labour,
scaffolding etc., complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads)

HOISTS:STRUCTURAL COMPONENTS-painting structurals on sand blasted surfaces with two coats of zinc
phosphate primer (airless spray preferred) 40microns/coat and one coat 65+/292
5 of alkyd based micaccous iron oxide paint followed by two coats of synthetic
enamel paint 25 microns/coat cost of all materials, labour, scaffolding etc.,
complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads)

293

HOISTS:machineryCOMPONENTS-painting hoist machinery, on sand blasted surfaces with one coats of zinc
phosphate primer (airless spray preferred) 50microns/coat and three coats of
aluminium paint or synthetic enamel , 25 microns/coat cost of all materials,
labour, scaffolding etc., complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads)

sqm

490.30

sqm

sqm

89.20

479.00

sqm

sqm

192.90

346.60

sqm

sqm

148.00

431.80

sqm

sqm

sqm

192.90

388.50

192.90

PAINTING WITHOUT SAND BLASTING

38

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

sqm

567.40

IRR-GAW-4-1

E.M Parts OF ALL TYPES OF GATES


Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaning,applying primary coat
with one coat of Protective Mastic to athickness of 70+5 microns ,followed by
294
finishing coats 2 coats with coal tar epoxy each coat with a DFT of 150+5
microns and total DFT of all coats including Primary coat should not be less than
350 microns with material, labour and all accessories with all leads and lifts
(in respect of Heavily rusted (30 to 40% rusted) surfaces)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-4-2

IRR-GAW-4-3

IRR-GAW-4-4

IRR-PMW-1-1

IRR-PMW-1-2

IRR-PMW-1-3

IRR-PMW-1-4

HOIST BRIDGES ,HOISTING EQUIPMENT AND CRANES,Etc,


Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaning,applying primary coat
with two coats of Zinc chromite red oxide primer , followed by finishing coats
295 3 coats with synthetic enamel paint with material, labour,and all accessories
with all leads and lifts
where surface cleaning by sand blasting is not feasible and based on specific
recommendations of designers, it is to adopt surface preperation done
manually by hand and power tool after cleaning by chemical treatment to
remove grease, rust, scaling etc., and to form phasphate coating to prevent
further rusting, before applying primer painting.
Labour Component (including contractor's profit and Overheads)
WALK WAYS( CAT WALKS), LIFTING BEAMS,etc,
Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaning,applying primary coat
296
with one coat of Zinc rich epoxy primer to a thickness of 40 microns ,followed
by finishing coats 2 coats with coal tar epoxy with material, labour, and all
accessories with all leads and lifts
Labour Component (including contractor's profit and Overheads)

JUNGLE CLEARANCE :
Clearing thin jungle growth ( more than 50 percent open space ) including
297 bushes upto 30 cm / parthenium and other weeds including burning or
disposing off the same as directed etc., complete.
Labour Component (including contractor's profit and Overheads)
Clearing thick jungle growth ( less than 50 percent open space ) including
298 bushes upto 30 cm / parthenium and other weeds including burning or
disposing off the same as directed etc., complete.
Labour Component (including contractor's profit and Overheads)
Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth
299 including excavation, stacking the materials neatly and levelling the surface etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above
300 1.50 m and upto 3.0 m including excavation, stacking the materials neatly and
levelling the area etc., complete with initial lead upto 50 m and all lifts.

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above
301 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and
levelling the area etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-1-6

IRR-PMW-1-7

sqm

410.90

sqm

sqm

192.90

474.30

sqm

130.10

PRELIMINARY AND MAINTENANCE WORKS

Labour Component (including contractor's profit and Overheads)

IRR-PMW-1-5

192.90

Deleted from the year 2014-15 onwards

Chapter VI
IRR-PMW
IRR-PMW-1

sqm

Itemwise unit rate


for Labour
Component
6

302

303

Additional rate for every 0.5 m increase in girth of tree stump/stumps of


bamboo cluster beyond 5 m
Labour Component (including contractor's profit and Overheads)
Cutting and stacking bamboos excluding removing stumps and roots etc.,
complete with initial lead upto 50 m and all lifts.

sqm

1.30

sqm

sqm

1.20

2.00

sqm

Each

2.00

45.40

Each

Each

45.40

102.30

Each

Each

102.30

327.20

Each
Each

327.20
58.30

Each
Each

58.30
13.30

39

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-PMW-1-8

IRR-PMW-1-9

IRR-PMW-1-10

IRR-PMW-1-11

IRR-PMW-1-12

IRR-PMW-1-13

IRR-PMW-1-14

Item description
3
Labour Component (including contractor's profit and Overheads)

Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal
304 of stumps and including burning or disposing off the materials as directed with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth
305 excluding removal of stumps and including burning or disposing off the materials
as directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps
306 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps
307 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps
308 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps
309 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps
310 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)

Unit

Rate

4
Each

Each

12.80

Each

Each

12.80

25.70

Each

Each

25.70

86.60

Each

Each

83.60

303.20

Each

Each

292.60

606.40

Each

Each

585.10

1212.80

Each

Each

Itemwise unit rate


for Labour
Component
6
13.30

1170.20

1959.90

Each

1874.60

For every 0.5 m increase in girth of tree beyond 3 m add


IRR-PMW-1-15

IRR-PMW-1-16

IRR-PMW-2

IRR-PMW-2-1

311

312

Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3
m.
Labour Component (including contractor's profit and Overheads)
Cutting and burning or disposing off Apu / Jondu from marshy areas as
directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-3

687.40

Each
sqm

661.80
4.70

sqm

4.70

PRELIMINARY WORKS :
Earthwork excavation for trial pits / borrow pits and other investigation works
313 in all kinds of soil including boulders upto 30 cm dia and disposing off
excavated soil as directed with lead upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-2

Each

Earthwork excavation for trial pits / borrow pits and other investigation works
314 in soft rock including disposing off the excavated rock as directed with lead
upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

Conducting geophysical investigation studies by electrical resistivity


method in stages of 5m for sub-surface details such as depth of formations,
shear zones, classification of strata, depth of water table etc., including cost of
315
all materials, equipments, labour, analysing and reporting the details of field
studies conducted etc., complete excluding cost of transportation
arrangements.
Labour Component (including contractor's profit and Overheads)

cum

234.00

cum

cum

234.00

328.90

cum

stage

stage

328.90

292.00

232.30

40

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-PMW-2-4

Item description

3
Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or
inclined upto 10 degrees to vertical as directed including cost of all materials,
machinery, labour, water charges, reaming, collection of wash samples at
suitable intervals, logging and lebelling, supplying honne wood core box, fixing
casing pipes ( excluding cost of casing pipes ) etc., complete for depth
316 upto 30 m from surface.
1. For driiling through over-burden beyond 30 m from surface increase the rate
per Rm by 10 percent.
2. For providing HDPE or light black MS casing pipe add the cost of pipe per
Rm.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-5

IRR-PMW-2-5-A
(New Item 201415)-5

Rm

1173.70

Rm

Rm

1. For driiling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For driiling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

Rm

Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
directed including cost of all materials, machinery, labour, water charges, and
318 redrilling in case of collapse of sides etc., complete for depth upto 30 m from
surface for Primary and Secondary Holes

Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
directed including cost of all materials, machinery, labour, water charges,
319 collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m
from surface for Test Holes
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-6

Rate

Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit
vertical / inclined upto 10 degree to vertical as directed including cost of all
materials, machinery, labour, water charges, collection of core samples, logging
and lebelling, supplying honne wood core box and redrilling in case of collapse of
317 sides etc., complete for depth upto 30 m from surface.

1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-5-B
(New Item 201415)-6

Unit

Rm

413.70

5976.10

1666.10

3808.20

Rm

Rm

994.10

4628.70

Rm

Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical
/ inclined upto 10 degree to vertical as directed including cost of all materials,
machinery, labour, water charges,collection of core samples,logging, lebelling,
supplying honne wood core box and redrilling in case of collapse of sides etc.,
320 complete for depth upto 30 m from surface.

Rm

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

Rm

Itemwise unit rate


for Labour
Component
6

994.60

5815.50

1666.10

41

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

Rm

3580.30

IRR-PMW-2-6-A
(New Item 201415)-7

Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing shoe)
using diamond core bit vertical / inclined upto 10 degree to vertical as directed
321 including cost of all materials, machinery, labour, water charges, and redrilling
in case of collapse of sides etc., complete for depth upto 30 m
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-7

IRR-PMW-2-8

NOTE:

IRR-PMW-2-9

Providing and fixing 20 x 20 x 75 cm size roughly dressed boundary /


322 demarcation / chainage / arrow stones including cost of all materials, labour,
engraving marks, fixing in position, murum filling etc., complete with lead upto
50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

323

IRR-PMW-3-1

IRR-PMW-3-2

IRR-PMW-3-3

Providing and fixing 20 x 20 x 75 cm size permanent bench mark stone in CC


1 :3 : 6 block of size 90 x 90 x 120 cm using 40 mm down size graded coarse
324 aggregate and providing 35 cm thick 30 cm high UCR masonry in CM 1 : 5
proportion protective wall alround the BM stone, including cost of all materials,
labour, dressing top surface of stone, engraving BM data

IRR-PMW-3-5

IRR-PMW-3-6

994.10

143.50

Each

Each

110.10

498.00
327.80
4.00

6526.60

Each

2871.60

MAINTENANCE WORKS :
Removing dry stone rock-toe / rivetment and filter layers below rock-toe/
325 rivetment including stacking all materials separately as directed with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Re-constructing 60 cm thick hand packed rough stone revetment with
through stones at 1.5 m c / c over a backing of 45 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size graded aggregates satisfying filter
326 criteria laid in layers of 15 cm thick each using sand from approved quarry and
stones and filter aggregates obtained from revetment removed for reconstruction including cost of all machinery, labour, laying filter and stones to
specified slopes, wedging with chips, finishing etc. complete with initial lead
upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Re-constructing dry rubble rock-toe and filter media for rock-toe consisting
of sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in
layers of 15 cm thick each using sand from approved quarry and stones and filter
327
aggregates obtained from rock-toe removed for re-construction including cost of
all machinery, labour, laying filter and stones to specified slopes, wedging with
chips, finishing etc. complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-4

Each

Providing and fixing 20 x 20 x 75 cm size temporary bench mark stone in CC 1


: 4 : 8 using 40 mm down size graded coarse aggregate including cost of all
Each
materials, labour, dressing top surface, engraving BM data etc.,complete with
lead upto 50 m and all lifts.
Each
Labour Component (including contractor's profit and Overheads)
For providing 30 cm thick compacted murum bed in B.C soil area including additional
excavation for thickness of murum bedding add per
Each

Labour Component (including contractor's profit and Overheads)


IRR-PMW-3

Rm

Itemwise unit rate


for Labour
Component
6

Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC /


328 Other types of slab lining set in CM 1 : 3 including flush cement mortar
pointing in CM 1 : 3 with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Removing and resetting disturbed dry rubble / khandki stone pitching 25 to
329 45 cm thick including packing, wedging, finishing etc., complete with all leads
and lifts.
Labour Component (including contractor's profit and Overheads)
Removing and refixing disturbed chainage / demarcation / hectometre /
330 guard stones including excavation, back filling etc., complete with all leads and
lifts.
Labour Component (including contractor's profit and Overheads)

cum

189.40

cum

sqm

189.40

239.10

sqm

cum

141.80

265.40

cum

sqm

203.00

58.40

sqm

sqm

49.40

50.90

sqm

Each
Each

50.90

64.40
64.40

42

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

IRR-PMW-3-7

331

Each

144.90

IRR-PMW-3-8

Removing and refixing disturbed km stone / sign board / hecto-metre stone


etc., including excavation, back filling with available stuff after refixing, forming
base platform of size 90 x 90 x 7.5 cm including watering, ramming etc complete
with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Providing impervious hearting for breached / damaged portion of


embankment with soil from approved borrow areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
332 operations such as collection of soil, sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-9

Providing pervious/semi-pervious casing for breached / damaged portion


of embankment with soil from approved borrow areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
333 operations such as collection of soil, sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-10

Providing impervious hearting for breached / damaged portion of


embankment with soil from approved dump areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
334 operations such as collection of soil,sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-11

Providing pervious /semi-pervious casing for breached /damaged portion of


embankment with soil from approved dump areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
335 operations such as collection of soil, sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-12

IRR-PMW-3-13

IRR-PMW-3-14

Repairing rain cuts / resectioning canal slopes to required lines and grades
336 as directed using available soil including dressing, clod breaking, packing,
tamping etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

337

Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing


/ brushing including chiselling and removing leached lime deposit and disposing
off all the waste material out side adits in specified location etc., complete with
all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Cleaning dam parapet inner face and top using oxalic acid and water by
338 scrubbing / brushing and washing to remove all surface coatings etc., complete
.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-15

Deleted from the year 2014-15 onwards

IRR-PMW-3-16

Deleted from the year 2014-15 onwards

IRR-PMW-3-17

Deleted from the year 2014-15 onwards

IRR-PMW-3-18

Deleted from the year 2014-15 onwards

IRR-PMW-3-19

Deleted from the year 2014-15 onwards

Each

cum

144.90

184.20

cum

cum

29.90

210.80

cum

cum

35.70

167.40

cum

cum

28.50

190.80

cum

sqm

33.70

3.30

sqm

Rm

3.30

36.90

Rm

Rm
Rm

Itemwise unit rate


for Labour
Component
6

29.50

33.00
21.10

43

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

IRR-PMW-3-20

IRR-PMW-3-21

Item description

3
Excavation and removal of silt and silt mixed with sand from canal bed in
dry condition including disposing off the same in spoil bank or on the canal
339
embankment in layers as directed etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation and removal of silt or silt mixed with sand in slussy condition
340 from canal bed including disposing off the same in spoil bank or on the canal
embankment in layers as directed etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)

Providing homogeneous embankment using soil from approved borrow area


IRR-PMW-3-22
in layers of 25 to 30 cm before compaction including cost of all materials,
(new Item5 2010341 machinery, labour, all operations such as excavation, sorting out, transportation,
11) (for Minor
spreading soil in layer of specified thickness, breaking clods,
Works)
sectioning,etc.,complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing homogeneous embankment using soil from approved borrow area
IRR-PMW-3-23
in layers of 25 to 30 cm before compaction including cost of all materials,
(new Item6 2010342 machinery, labour, all operations such as watering, compactingto density control
11) (for Minor
of not less than 95 percent or as stipulated using 8T roller etc., complete
Works)
with initial lead upto 1 km and all lifts.

Unit

Rate

cum

140.90

cum

cum

140.90

176.10

cum

cum

176.10

94.70

cum

cum

14.10

45.60

6.80

Labour Component (including contractor's profit and Overheads)


Providing homogeneous embankment using soil from approved borrow area
IRR-PMW-3-24
in layers of 25 to 30 cm before compaction including cost of all materials,
(new Item7 2010- 343 machinery, labour, all operations such as compactingto density control of not
11)
less than 90 percent or as stipulated using 2T roller etc., complete with
initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
(New Item 201213-3)
IRR-PMW-325(a)
IRR-PMW-325(b)
IRR-PMW-3-25(
c)
IRR-PMW-325(d)
IRR-PMW-325(e)
IRR-PMW-325(f)
(new Item 201213-6)

IRR-PMW-3-26
New Item 201415-8

COM-MWRK

COM-MWRK-1

Itemwise unit rate


for Labour
Component
6

cum

6.10

cum

1.10

Weed Removal by Manual Means


344
345
346
347
348

Removal of Water Hyacinth up to 30 cm thick


Removal of Water Hyacinth beyond 30 cm thick
Clearing Alchi Tilla
Removal of Jammu
Removal of Imponea, Cornea

349

Sqm

5.70

Sqm

7.80

Sqm

5.30

Sqm

4.40

Sqm

5.30

Sqm

1.70

Sqm

408.60

Removal of Natchu, goobi, thooti, etc.


PAINTING OF SLUICES FOR MAINTENANCE WORKS
Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaniong, applying primary coat
350
with one coat of Zinc rich epoxy primer to a thickness of 100 microns, followed
by finishing coats 2 coats with Coal tar epoxy with material, labour, and all
accessories with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Sqm

154.52

New extra items-- common item for all earth works using only manual labour for all other works
without involving contractors
(Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures and
placing excavated stuff neatly in specified dump area or disposing off the same
351
as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m.
(WIthout involving the contractors for specified works )
With 3 Cum per day output

cum

103.30

44

Abstract of work items_UNit Rates for the year 2015-16

Chapterwise
item No.

S.NO

Item description

Unit

Rate

COM-MWRK-2

(Manual)Excavation in all kinds of soil/HDR including boulders upto 0.30 m


dia. for foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing off the
352
same as directed etc., complete with initial lead upto 10 m and initial lift upto
1.5 m. (WIthout involving the contractors for specified works )
With 2.5 Cum per day output

cum

124

COM-MWRK-3

(Manual)Excavation in soft rock (including F&F rock) without blasting,


including boulders upto 0.30 m dia. for foundations of canal cross drainage and
other appurtenant structures and placing excavated stuff neatly in specified
353 dump area or disposing off the same as directed etc., complete with initial lead
upto 10 m and initial lift upto 1.5 m. (WIthout involving the contractors for
specified works )
Soft rock 1.33 Cum/Day

cum

233.10

COM-MWRK-4

(Manual)Excavation in hard rock, including boulders upto 0.30 m dia. for


foundations of canal cross drainage and other appurtenant structures and
placing excavated stuff neatly in specified dump area or disposing off the same
354
as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m.
(WIthout involving the contractors for specified works )
Hard rock 0.67Cum/ day

cum

462.70

Itemwise unit rate


for Labour
Component
6

45

Dam and Allied Works - Item Unit Rates 2015-16

Chapter - I
DAM AND ALLIED WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :2015-16
Index- code
IRR-DAW

DAM AND ALLIED WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges while adding Seigniorage Charges
to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added
as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total lead involved and 1 km lead charges
included in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km /cum
Rs.
208.60
Less 1 km initial lead charges /cum Rs.
31.30 (-)
Net additional lead charges / cum
Rs.
177.30

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic rate shall be deducted from total
lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km /cum
Rs.
208.60
Less 1 km initial lead charges /cum Rs.
31.30 (-)
Net additional lead charges / cum
Rs.
177.30
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For conveyance of materials, the
lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without deducting the 50 m initial lead charges
DAW - Work Items

IRR-DAW-1

EXCAVATION & FOUNDATION TREATMENT WORKS:

IRR-DAW-1-1

Excavation for foundation in all kinds of soil including boulders upto


0.30 m diameter for dam, spillway, intake structure and other appurtenant
works and placing the excavated soil neatly in dump area or disposing off
the same as directed etc., complete with initial lead upto 1 km
and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

Unit

Quantity

NIL

0.00
0.00

Total cost of Materials

Rs:

UNIT
880 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
0.00

B. MACHINERY:
Sl No
1
2

Description
Shovel 0.85 cum capacity
Fuel / Energy charges
Dumpers 5 cum capacity 6 Nos

Unit
Hour
Hour
Hour

Quantity
8.00
8.00
48.00

Rate
Amount
in Rs.
in Rs
1706.60 13652.80
893.90 7151.20
580.70 27873.60

48

Dam and Allied Works - Item Unit Rates 2015-16

Fuel / Energy charges


Hour
Tipper 5 cum capacity 1 No
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

48.00
8.00
8.00

409.60
446.70
307.20
Rs:

19660.80
3573.60
2457.60
74369.60

221.00
212.20
165.80
400.00
310.00
Rs:

Amount
in Rs
1768.00
10185.60
1326.40
400.00
4960.00
18640.00

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Quantity

Rate
in Rs.

Crew for Shovel


Crew for Dumper
Crew for Tipper
work inspector
mazdoor

Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
21.20
Add contractor's profit and overhead charges
13.615% 2.90
labour component/unit qty (including contractor's profit)
24.10

8.00
48.00
8.00
1.00
16.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
880.00
Rate per
cum (A+B+C+D)/880

IRR-DAW-1-2

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

13.615%
cum

0.00
74369.60
18640.00
93009.60
12663.26
105672.86
120.10

Excavation for foundation in ordinary rock (including HDR) without blasting including
boulders above 0.3 m upto 0.6 m dia for dam, spillway, intake structure and
other appurtenant works and placing the excavated material neatly in dump
area or disposing off the same as directed etc., complete with initial lead
upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Unit

Quantity

NIL

0.00
0.00
Total cost of Materials

UNIT :
520 cum
Rate
Amount
in Rs.
in Rs.
0.00 0.00
0.00 0.00
Rs: 0.00

B. MACHINERY:
Sl No Description
1
2
3

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Dumpers 5 cum capacity( 4 Nos)
Fuel / Energy charges
Tipper 5 cum capacity( 1 No)
Fuel / Energy charges
Total hire charges of Machinery

Quantity

Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
32.00
32.00
8.00
8.00

Rate
in Rs.
1706.60
893.90
580.70
409.60
446.70
307.20
Rs:

Amount
in Rs
13652.80
7151.20
18582.40
13107.20
3573.60
2457.60
58524.80

Rate
in Rs.
221.00
212.20
165.80
400.00
370.00
310.00
Rs.

Amount
in Rs
1768.00
6790.40
1326.40
400.00
925.00
3100.00
14309.80

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
58524.80
14309.80
72834.60
9916.43
82751.03
159.10

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Crew for Shovel


Crew for Dumper
Crew for Tipper
work inspector
Crowbarman
mazdoor

Quantity

Hour
Hour
Hour
Day
Day
Day
Total cost of Labour
labour component/unit qty
27.50
Add contractor's profit and overhead charges
13.615% 3.70
labour component/unit qty (including contractor's profit)
31.20

8.00
32.00
8.00
1.00
2.50
10.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
520.00
Rate per
cum (A+B+C+D)/520

13.615%
cum

49

Dam and Allied Works - Item Unit Rates 2015-16

IRR-DAW-1-3

DATA:

Excavation for foundation in hard rock (including F&F rock) requiring blasting including
boulders above 0.6 m upto 1.2 m dia. for dam, spillway, intake structure
and other appurtenant works and placing the excavated material neatly in
dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Description
Use rate of 1.5 m drill rod
Reconditioning charges @
Use rate of air hose 4 Nos.
Explosive small dia
Electric detonators
Fuse coil
Sundries
Total cost of Materials

Unit

UNIT :
520.00 cum.
Rate
Amount
in Rs.
in Rs
20.75 4482.00
448.20
11.56 300.63
70.00 7280.00
13.00 2002.00
11.00 3520.00
20.00 100.00
Rs. 18132.83

Quantity

Rm

216.00

10%
Hour
kg
Nos
Rm
LS

26.00
104.00
154.00
320.00
5.00

B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate
in Rs.

1
2
3
4
5

Shovel 0.85 cum capacity


Fuel / Energy charges
Dumpers 5 cum capacity 4 Nos.
Fuel / Energy charges
Tipper 5 cum capacity 1 No
Fuel / Energy charges
Air compressor 8.5 cmm ( ele ) 2 Nos
Fuel / Energy charges
Jack hammers 4 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
32.00
32.00
8.00
8.00
13.00
13.00
26.00
26.00

1706.60
893.90
580.70
409.60
446.70
307.20
170.80
433.10
19.80
0.00
Rs:

Amount
in Rs
13652.80
7151.20
18582.40
13107.20
3573.60
2457.60
2220.40
5630.30
514.80
0.00
66890.30

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11

Crew for Shovel


Crew for Dumper
Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
49.00
Add contractor's profit and overhead charges
13.615% 6.70
labour component/unit qty (including contractor's profit)
55.70

Rate
in Rs.
8.00
32.00
8.00
13.00
26.00
1.00
1.00
1.00
2.50
1.00
10.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
520.00
Rate per
cum. (A+B+C+D)/520
IRR-DAW-1-3A
New Item 2015-16-1

Total
13.615%
cum.

221.00
212.20
165.80
153.10
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs.

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Amount
in Rs
1768.00
6790.40
1326.40
1990.30
7961.20
400.00
480.00
370.00
925.00
370.00
3100.00
25481.30

18132.83
66890.30
25481.30
110504.43
15045.18
125549.61
241.40

Excavation for foundation in hard rock (including F&F rock) including


boulders above 0.6 m upto 1.2 m dia. by controlled blasting and controlling fly rock by muffling arrangements
for dam, spillway, intake structure and other appurtenant works and other open foundation works and placing the excavated
material neatly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and all leads

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Description

Use rate of 1.5 m drill rod


Reconditioning charges @

Unit
Rm

Quantity
216.00

10%

UNIT :
520.00 cum.
Rate
Amount
in Rs.
in Rs
20.75 4482.00
448.20

50

Dam and Allied Works - Item Unit Rates 2015-16

2
3
4
3
4
5
6

Use rate of air hose 4 Nos.


Use rate of chain link wire mesh
Use rate of Sand Bags
Explosive small dia
Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

Hour
Sq m
Nos.
kg
Nos
Rm
LS

26.00
500.00
190.00
104.00
154.00
320.00
5.00

11.56
67.38
81.70
70.00
23.00
11.00
20.00
Rs.

300.63
33687.50
15523.00
7280.00
3542.00
3520.00
100.00
68883.33

1706.60
893.90
1715.50
625.30
580.70
409.60
446.70
307.20
170.80
433.10
19.80
0.00
Rs:

Amount
in Rs
13652.80
7151.20
1715.50
625.30
18582.40
13107.20
3573.60
2457.60
2220.40
5630.30
514.80
0.00
69231.10

B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate
in Rs.

1
2
3
4
5
6

Shovel 0.85 cum capacity


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Dumpers 5 cum capacity 4 Nos.
Fuel / Energy charges
Tipper 5 cum capacity 1 No
Fuel / Energy charges
Air compressor 8.5 cmm ( ele ) 2 Nos
Fuel / Energy charges
Jack hammers 4 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
1.00
1.00
32.00
32.00
8.00
8.00
13.00
13.00
26.00
26.00

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11
12

Crew for Shovel


Crew for Angle dozer
Crew for Dumper
Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
57.60
Add contractor's profit and overhead charges
13.615% 7.80
labour component/unit qty (including contractor's profit)
65.40

Rate
in Rs.
8.00
1.00
32.00
8.00
13.00
26.00
3.00
1.50
2.00
2.50
2.00
18.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%
cum.

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
520.00
Rate per
cum. (A+B+C+D)/520

IRR-DAW-1-4
(a)

221.00
221.00
212.20
165.80
153.10
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs.

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Amount
in Rs
1768.00
221.00
6790.40
1326.40
1990.30
7961.20
1200.00
720.00
740.00
925.00
740.00
5580.00
29962.30

68883.33
69231.10
29962.30
168076.73
22883.65
190960.38
367.20

Excavation for foundation in hard rock of all toughness by blasting


including boulders above 1.2 m dia. for dam, spillway, intake structure and
other appurtenant works and placing the excavated rock neatly in dump area
or stack yard including levelling as directed etc., complete with
initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS

A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Use rate of drill rod 1.5 m long


Reconditioning charges @
Use rate of air hose 4 Nos.
Explosive small dia
Ordinary detonators
Electric detonators
Fuse coil
Sundries
Total cost of Materials

Unit

Quantity

Rm

310.00

10%
Hour
kg
Nos
Nos
Rm
LS

48.00
95.00
10.00
333.00
450.00
5.00

UNIT
320.00 cum
Rate
Amount
in Rs.
in Rs
27.67 8576.67
857.67
11.56 555.00
70.00 6650.00
7.00 70.00
13.00 4329.00
11.00 4950.00
20.00 100.00
Rs: 26088.34

51

Dam and Allied Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6

Shovel 0.85 cum capacity


Fuel / Energy charges
Dumpers 5 cum capacity 3 Nos.
Fuel / Energy charges
Tipper 5 cum capacity 1 No
Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Air compressor 8.5 cmm (ele) 2 Nos.
Fuel / Energy charges
Jack hammers 4 Nos.
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
24.00
24.00
4.00
4.00
1.00
1.00
24.00
24.00
48.00
48.00

Unit

Quantity

1
2
3
4
5
6
7
8
9
10
11
12

Crew for Shovel


Hour
Crew for Dumper
Hour
Crew for Tipper
Hour
Crew for Dozer
Hour
Crew for Air compressor
Hour
Crew for Jack hammer
Hour
work inspector
Day
Blaster
Day
Helper blaster
Day
Crowbarman
Day
Stone breaker
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
94.80
Add contractor's profit and overhead charges
13.615% 12.90
labour component/unit qty (including contractor's profit)
107.70

8.00
24.00
4.00
1.00
24.00
48.00
1.00
1.00
1.00
1.00
2.00
6.00

IRR-DAW-1-5
(b)

Amount
in Rs
13652.80
7151.20
13936.80
9830.40
1786.80
1228.80
1715.50
625.30
4099.20
10394.40
950.40
0.00
65371.60

Rate
in Rs.

Amount
in Rs
1768.00
5092.80
663.20
221.00
3674.40
14697.60
400.00
480.00
370.00
370.00
740.00
1860.00
30337.00

221.00
212.20
165.80
221.00
153.10
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
13.615%
cum

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
320.00
Rate per
cum (A+B+C+D)/320

Rate
in Rs.
1706.60
893.90
580.70
409.60
446.70
307.20
1715.50
625.30
170.80
433.10
19.80
0.00
Rs.

26088.34
65371.60
30337.00
121796.94
16582.65
138379.59
432.40

Excavation for foundation in hard rock of all toughness including boulders


above 1.2 m dia. by controlled blasting method and controlling fly-rock
by muffling arrangements for dam, spillway, intake structure and other
appurtenant structures etc., including placing and levelling the excavated
rock neatly in dump area or other place as directed etc., complete with
lead upto upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
8
9

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 4 Nos.
Use rate of chain link wire mesh
Use rate of sand bag
Explosive small dia.
Ordinary detonators
Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

Particulars
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Dumpers 5 cum capacity 3 Nos.

Unit

Quantity

Rm
10%
Hour
sqm
Nos
kg
Nos
Nos
Rm
LS

Unit
Hour
Hour
Hour
Hour
Hour

UNIT :
480.00 cum
Rate
Amount
in Rs.
in Rs
27.67 12837.33
1283.73
11.56 809.38
67.38 48173.13
81.70 47386.00
70.00 10430.00
7.00 161.00
23.00 11500.00
11.00 7700.00
20.00 200.00
Rs: 140480.57

464.00
70.00
715.00
580.00
149.00
23.00
500.00
700.00
10.00

Quantity

Rate
in Rs.
12.00
12.00
2.00
2.00
36.00

1706.60
893.90
1715.50
625.30
580.70

Amount
in Rs
20479.20
10726.80
3431.00
1250.60
20905.20

52

Dam and Allied Works - Item Unit Rates 2015-16

Fuel / Energy charges


Hour
Tipper 5 cum capacity 1 No
Hour
Fuel / Energy charges
Hour
5
Air compressor 8.5 cmm ( ele ) 2 Nos
Hour
Fuel / Energy charges
Hour
6
Jack hammers 4 Nos.
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit

36.00
4.00
4.00
35.00
35.00
70.00
70.00

1
2
3
4
5
6
7
8
9
10
11
13

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
103.90
Add contractor's profit and overhead charges
13.615% 14.10
labour component/unit qty (including contractor's profit)
118.00

12.00
2.00
36.00
4.00
35.00
70.00
4.50
1.50
3.00
2.50
2.50
20.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-1-6
( c)

Note :

14745.60
1786.80
1228.80
5978.00
15158.50
1386.00
0.00
97076.50

221.00
221.00
212.20
165.80
153.10
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs.

Amount
in Rs
2652.00
442.00
7639.20
663.20
5358.50
21434.00
1800.00
720.00
1110.00
925.00
925.00
6200.00
49868.90

Rate
in Rs.

Crew for Shovel


Crew for Angle dozer
Crew for Dumper
Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
13.615%
cum

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
480.00
Rate per
cum
(A+B+C+D)/480

409.60
446.70
307.20
170.80
433.10
19.80
0.00
Rs:

140480.57
97076.50
49868.90
287425.97
39133.05
326559.02
680.30

Excavation for foundation in hard rock of all toughness including boulders


above 1.2 m dia. by line drilling and smooth blasting and controlling
fly-rock by muffling arrangements for dam, spillway, intake structure and
other appurtenant structures etc., including dressing sides and bed to
required level / profile, placing and levelling the excavated rock neatly in
dump area or other place as directed etc., complete with lead upto 1 km and
all lifts.
i ) 1 m width of excavation along the face to be dressed shall be treated as
excavation by line drilling and smooth blasting.
ii) The rate includes controlling fly-rock wherever required.
iii ) The rate under this item shall be paid only on ascertaining that the
surface requiring dressing has come off neatly as per specifications or
atleast 50 percent of smooth blast holes are visible for inspection and are
spaced at specified interval.
iv ) In case, where the above criteria is not fulfilled payment shall be
restricted to the rate provided for excavation by normal or controlled blasting
as the case may be..

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 4 Nos.
Explosive small dia.
Ordinary detonators
Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4

Shovel 0.85 cum capacity


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Dumpers 5 cum capacity 3 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( ele ) 2 Nos

Unit

Quantity

Rate
in Rs.

Rm

138.00

10%
Hour
kg
Nos
Nos
Rm
LS

22.00
10.50
2.00
76.00
140.00
2.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
1.00
1.00
0.25
0.25
3.00
3.00
11.00

40.00 cum
Amount
in Rs
27.67 3818.00
381.80
11.56 254.38
70.00 735.00
7.00 14.00
23.00 1748.00
11.00 1540.00
20.00 40.00
Rs. 8531.18

Rate
in Rs.
1706.60
893.90
1715.50
625.30
580.70
409.60
170.80

Amount
in Rs
1706.60
893.90
428.88
156.33
1742.10
1228.80
1878.80

53

Dam and Allied Works - Item Unit Rates 2015-16

Fuel / Energy charges


Hour
Jack hammers 4 Nos.
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Unit

11.00
22.00
22.00

Quantity

Crew for Shovel


Hour
Crew for Angle dozer
Hour
Crew for Dumper
Hour
Crew for Air compressor
Hour
Crew for Jack hammer
Hour
work inspector
Day
Blaster
Day
Helper blaster
Day
Crowbarman
Day
Stone breaker
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
273.70
Add contractor's profit and overhead charges
13.615% 37.30
labour component/unit qty (including contractor's profit)
311.00

1.00
0.25
3.00
11.00
22.00
0.50
0.50
0.50
0.50
0.50
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-1-7

221.00
221.00
212.20
153.10
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs.

Amount
in Rs
221.00
55.25
636.60
1684.10
6736.40
200.00
240.00
185.00
185.00
185.00
620.00
10948.35

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

8531.18
13235.11
10948.35
32714.64
4454.1
37168.74
929.20

Total
13.615%
cum

Preparing foundation bed for masonry or concrete by benching,


stepping, removing all loose material by wedging / chiselling and disposing
off the same as directed and cleaning the surface with air and water jet etc.
,complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Unit

Quantity

UNIT:
100.00 sqm
Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00

Rate
in Rs.

NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( ele )


Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

Quantity

Rate
in Rs.

Hour
Hour
Hour
Hour

Unit

1
2
3
4
5

Crew for Air compressor


Hour
Crew for Pump
Hour
Stone breaker
Day
mazdoor
Day
Crowbar man
Day
Total cost of Labour
labour component/unit qty
24.90
Add contractor's profit and overhead charges
13.615% 3.40
labour component/unit qty (including contractor's profit)
28.30

1.00
1.00
1.00
1.00

Quantity

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100

170.80
433.10
3.00
38.50
Rs.

Amount
in Rs
170.80
433.10
3.00
38.50
645.40

153.10
77.70
370.00
310.00
370.00
Rs:

Amount
in Rs
153.10
77.70
740.00
775.00
740.00
2485.80

Rate
in Rs.
1.00
1.00
2.00
2.50
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-1-8

4764.10
435.60
0.00
13235.11

Rate
in Rs.

1
2
3
4
5
6
7
8
9
10
11

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
40.00
Rate per
cum
(A+B+C+D)/40

433.10
19.80
0.00
Rs:

Total
13.615%
sqm

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
645.40
2485.80
3131.20
426.31
3557.51
35.60

Preparing foundation bed for cut-off trench filling in rock portion by

54

Dam and Allied Works - Item Unit Rates 2015-16

removing all loose materials by wedging / chiselling and disposing off the
same as directed etc., complete with initial lead upto 50 m and all lifts.
DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Unit

Quantity

UNIT:
100.00 sqm
Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00

Rate
in Rs.

NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

Unit

Quantity

Rate
in Rs.

NIL

Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00

0.00
0.00
Total cost of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Crowbar man
Stone breaker
mazdoor

Unit

Quantity

Day
Day
Day

Rate
in Rs.
2.00
2.00
2.00

370.00
370.00
310.00
Rs:

Total cost of Labour


labour component/unit qty
21.00
Add contractor's profit and overhead charges
13.615% 2.90
labour component/unit qty (including contractor's profit)
23.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%
sqm

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100

IRR-DAW-1-9

NOTE:

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Amount
in Rs
740.00
740.00
620.00
2100.00

0.00
0.00
2100.00
2100.00
285.92
2385.92
23.90

Drilling 45 to 50 mm dia holes vertical or inclined upto 10 degrees to


vertical in rock /masonry/ concrete by percussion drilling using waggon
drill or any other suitable equipment including cost of all materials,
machinery, labour, redrilling through partially set grout wherever required
etc., complete.
for drilling upto 6 m depth from surface.
The item rate for drilling through rock / masonry / concrete includes redrilling
through partially set grout, if any, in the portion of hole already grouted.

Data

RATE ANALYSIS
UNIT:
A. MATERIALS:
Sl No
Particulars
1
2
3

Use rate of cross bit 50 mm dia


Use rate of 50 mm dia air hose 50 m
Use rate of extension rod 4.5 m
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Waggon drill
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Unit

Quantity

Rm
Hour
Rm

Unit

96.00
8.00
96.00

Quantity

Hour
Hour
Hour
Hour
LS

Unit

Crew for Waggon drill


Hour
Crew for Air compressor
Hour
mazdoor
Day
Total cost of Labour
labour component/unit qty
41.30
Add contractor's profit and overhead charges
13.615% 5.60
labour component/unit qty (including contractor's profit)
46.90

Rate
in Rs.

96.00 Rm
Amount
in Rs
62.50 6000.00
18.63 149.00
6.68 641.09
Rs. 6790.09

Rate
in Rs.
8.00
8.00
8.00
8.00
2.00

Quantity

188.50
0.00
170.80
433.10
20.00
Rs:

Amount
in Rs
1508.00
0.00
1366.40
3464.80
40.00
6379.20

265.20
153.10
310.00
Rs:

Amount
in Rs
2121.60
1224.80
620.00
3966.40

Rate
in Rs.
8.00
8.00
2.00

ABSTRACT:

55

Dam and Allied Works - Item Unit Rates 2015-16

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%
Rm

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
96.00
Rate per
Rm
(A+B+C+D)/96
Upto 6 m from surface
Beyond 6 m upto 12 m from surface :
Upto 6 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 6 m upto 12 m from surface
Rate / Rm
Beyond 12 m upto 18 m from surface :
For 6 m to 12 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 12 m upto 18 m from surface
Rate / Rm
Beyond 18 m upto 24 m from surface
For 12 m to 18 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 18 m upto 24 m from surface
Rate / Rm
Beyond 24 m upto 30 m from surface
For 18 m to 24 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @ :
Beyond 24 m upto 30 m from surface
Rate / Rm
Beyond 30 m upto 36 m from surface
For 24 m to 30 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 30 m upto 36 m from surface
Rate / Rm
Beyond 36 m upto 42 m from surface
For 30 m to 36 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 36 m upto 42 m from surface
Rate / Rm
Beyond 42 m upto 48 m from surface
For 36 m to 42 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 42 m upto 48 m from surface
Rate / Rm

IRR-DAW-1-10

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

6790.09
6379.20
3966.40
17135.69
2333.02
19468.71
202.80
202.80

Rs: 202.80
10%

Rs: 20.28
Rs: 223.10
Rs: 223.10

10%

Rs: 22.31
Rs: 245.40
:
Rs: 245.40

10%

Rs: 24.54
Rs: 269.90
:
Rs: 269.90

10%

Rs 26.99
Rs: 296.90
:
Rs: 296.90

10%

Rs: 29.69
Rs: 326.60
:
Rs: 326.60

10%

Rs: 32.66
Rs: 359.30
Rs: 359.30

10%

Rs: 35.93
Rs: 395.20

Flushing grout holes of all sizes with water and air jets alternatively for an
average period of 30 minutes including water intake observations after
flushing, cost of all materials, machinery, labour etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Use rate of air hose 2 Nos x 8 hrs


Use rate of water hose 2 Nos x 8 hrs
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

Hour
Hour
LS

Unit

16.00
16.00
2.00

Quantity

Air compressor 8.5 cmm ( ele )


Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

1 Crew for Air compressor


Hour
2 Crew for Pump
Hour
3 mazdoor
Day
Total cost of Labour
labour component/unit qty
16.10
Add contractor's profit and overhead charges
13.615% 2.20
labour component/unit qty (including contractor's profit)
18.30

UNIT :
192.00 Rm.
Rate
Amount
in Rs.
in Rs
11.56 184.96
11.56 184.96
20.00 40.00
Rs: 409.92

Rate
in Rs.
8.00
8.00
8.00
8.00
2.00

Quantity

170.80
433.10
3.00
38.50
20.00
Rs:

Amount
in Rs
1366.40
3464.80
24.00
308.00
40.00
5203.20

153.10
77.70
310.00
Rs:

Amount
in Rs
1224.80
621.60
1240.00
3086.40

Rate
in Rs.
8.00
8.00
4.00

56

Dam and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%
Rm.

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
192.00
Rate per
Rm.
(A+B+C+D)/192

IRR-DAW-1-11
(a)

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Consolidation grouting with neat cement grout mix of suitable


consistency under specified pressure as directed in drilled holes by stage
grouting method including cost of all materials, machinery, labour,
redrilling if necessary etc.,complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Cement
Use rate of 50 m pressure hose
Sundries ( packer assembly etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

tonne
Hour
LS

Unit

1.05
8.00
3.00

Quantity

Grouting equipment
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT :
1.05 tonne
Rate
Amount
in Rs.
in Rs
6300.00 6615.00
11.56 92.48
20.00 60.00
Rs: 6767.48

Rate
in Rs.
8.00
8.00
2.00
2.00
2.00

Quantity

1
2
3

Crew for Grout pump


Hour
Crew for Pump
Hour
mazdoor ( cement handling)
Day
Total cost of Labour
labour component/unit qty
2604.40
Add contractor's profit and overhead charges
13.615% 354.60
labour component/unit qty (including contractor's profit)
2959.00

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Cement 1.05 Tonne @ (including
Loading and Unloading Charges)
Total cost for
1.05
Rate per
tonne
(A+B+C+D)/1.05

24.90
38.50
3.00
38.50
20.00
Rs:

Amount
in Rs
199.20
308.00
6.00
77.00
40.00
630.20

244.90
77.70
310.00
Rs:

Amount
in Rs
1959.20
155.40
620.00
2734.60

Rs:
Rs:
Rs:
Rs:
Rs.

6767.48
630.20
2734.60
10132.28
1379.51

Rate
in Rs.
8.00
2.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-1-12
(b)

409.92
5203.20
3086.40
8699.52
1184.44
9883.96
51.50

Total
13.615%
129.70 Rs/Tonne
tonne

136.185
Rs: 11647.98
Rs: 11093.30

Curtain grouting with neat cement grout mix of suitable consistency


under specified pressure as directed in drilled holes by stage grouting
method including cost of all materials, machinery, labour, redrilling if
necessary etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement
Use rate of 100 m pressure hose
Use rate of 400 m GI pipe
Sundries ( packer assembly etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Grouting equipment
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges

Unit

Quantity

tonne
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour

1.05
8.00
8.00
3.00

Quantity

UNIT :
1.05 tonne
Rate
Amount
in Rs.
in Rs
6300.00 6615.00
23.13 185.04
0.72 5.76
20.00 60.00
Rs: 6865.80

Rate
in Rs.
8.00
8.00
2.00
2.00

24.90
38.50
3.00
38.50

Amount
in Rs
199.20
308.00
6.00
77.00

57

Dam and Allied Works - Item Unit Rates 2015-16

Sundries

LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

2.00

Quantity

1
2
3
4

Crew for Grout pump


Hour
Crew for Pump
Hour
Pipe fitter
Day
mazdoor ( cement handling )
Day
Total cost of Labour
labour component/unit qty
3356.80
Add contractor's profit and overhead charges
13.615% 457.00
labour component/unit qty (including contractor's profit)
3813.80

20.00 40.00
Rs: 630.20

Rate
in Rs.
8.00
2.00
1.00
3.00

244.90
77.70
480.00
310.00
Rs:

Amount
in Rs
1959.20
155.40
480.00
930.00
3524.60

Rs:
Rs:
Rs:
Rs:
Rs.

6865.80
630.20
3524.60
11020.60
1500.45

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Cement 1.05 Tonne @ (including
Loading and Unloading Charges)
Total cost for
1.05
Rate per
tonne
(A+B+C+D)/1.05

IRR-DAW-1-13

129.70 Rs/Tonne
tonne

136.185
Rs: 12657.24
Rs: 12054.50

Providing and fixing 25 mm dia 3 m long cold twisted deformed steel


dowel bars with one end driven into 45 to 50 mm diameter 1.50 m deep
hole drilled in bed rock and other end provided with L-bend for embedding in
concrete / masonry of over flow / non-over flow blocks and other appertenant
works including cost of drilling and cleaning hole, filling hole with cement
mortar 1 : 1 proportion, driving anchor rod, cost of all materials, machinery,
labour etc., complete with initial lead upto 1 km and all lifts.
Consider 25 anchor rods for analysis.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5

Use rate of drill bit 50 mm dia


Use rate of air hose 50 m
Anchor rod 25 mm dia
Cement
Sand ( screened )
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2

Unit

Quantity

Rm
Hour
kg
kg
cum

Unit

37.50
4.00
303.22
75.00
0.05

Quantity

Air compressor 8.5 cmm ( ele )


Hour
Fuel / Energy charges
Hour
Waggon drill
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT:
25 Nos.
Rate
Amount
in Rs.
in Rs
62.50 2343.75
18.63 74.52
40.00 12128.80
6.30 472.50
760.00 38.00
Rs: 15057.57
Rate
in Rs.

4.00
4.00
4.00
4.00

Quantity

1
2
3
4
5

Crew for Air compressor


Hour
Crew for Waggon drill
Hour
Bar bender
Day
Mason Cl- II
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
96.50
Add contractor's profit and overhead charges
13.615% 13.10
labour component/unit qty (including contractor's profit)
109.60

170.80
433.10
188.50
0.00
Rs:

Amount
in Rs
683.20
1732.40
754.00
0.00
3169.60

153.10
265.20
490.00
370.00
310.00
Rs:

Amount
in Rs
612.40
1060.80
245.00
185.00
310.00
2413.20

Rate
in Rs.
4.00
4.00
0.50
0.50
1.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.05
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.08
tonne @
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
0.30
tonne @
Total cost for
25.00

Rs:
Rs:
Rs:
Rs:
Rs.
31.3 Rs./Cum

15057.57
3169.60
2413.20
20640.37
2810.19
1.565

129.7 Rs./Tonne

9.7275

Total
13.615%

151.5 Rs./Tonne
Nos.

45.93783
Rs: 23507.79

58

Dam and Allied Works - Item Unit Rates 2015-16

Rate per

IRR-DAW-1-14

Each

(A+B+C+D)/25

Rs: 940.30

Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods
with one end split and driven firmly using steel wedge into 1.25 m deep 45
to 50 mm dia. hole drilled in bed rock and other end provided with L- bend
for embedding in concrete / masonry for spillway and appurtenant works
including drilling and cleaning hole, filling hole with thick cement slurry,
driving anchor rod, cost of all materials, machinery, labour, steel wedge
etc., complete with initial lead upto 1 km and all lifts.
Consider 25 anchor rods for analysis.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

1
2
3
4
5
6

Use rate of 50 mm dia drill bit


Use rate of air hose 50 m 1 Nos.
Anchor rod 25 mm dia
Cement
Gas for splitting anchor rods
Steel wedges
Total cost of Materials
B. MACHINERY:
Sl No
Description

Quantity

Rm
Hour
kg
kg
LS
LS

31.25
3.00
277.92
62.50
5.00
10.00

Unit

Quantity

Air compressor 8.5 cmm ( ele )


Hour
Fuel / Energy charges
Hour
2
Waggon drill
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit

UNIT:
25.00 Nos.
Rate
Amount
in Rs.
in Rs
62.50 1953.13
18.63 55.89
40.00 11116.80
6.30 393.75
37.50 187.50
16.00 160.00
Rs: 13867.07
Rate
in Rs.

3.00
3.00
3.00
3.00

Quantity

1
2
3
4
5
6

Crew for Air compressor


Hour
Crew for Waggon drill
Hour
Bar bender
Day
Mason Cl- II
Day
Gas cutter
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
108.80
Add contractor's profit and overhead charges
13.615% 14.80
labour component/unit qty (including contractor's profit)
123.60

170.80
433.10
188.50
0.00
Rs:

Amount
in Rs
512.40
1299.30
565.50
0.00
2377.20

153.10
265.20
490.00
370.00
415.00
310.00
Rs:

Amount
in Rs
459.30
795.60
245.00
185.00
415.00
620.00
2719.90

Rs:
Rs:
Rs:
Rs:
Rs.

13867.07
2377.20
2719.90
18964.17
2581.97

Rate
in Rs.
3.00
3.00
0.50
0.50
1.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.06
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
Total cost for
Rate per
Each

tonne @

0.28
tonne @
25.00
(A+B+C+D)/25

129.7 Rs./Tonne
151.5 Rs./Tonne
Nos.

IRR-DAW-2

REINFORCEMENT & CEMENT CONCRETE WORKS :

IRR-DAW-2-1A

Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods
overlaps and wastages wherever required, tying with 1.25 mm diameter soft
annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
overlaps and wastage
as per NHAI-data
Lap jointing considered for bars upto 36 mm diameter.

DATA:

8.10625
42.10488
Rs: 21596.35
Rs: 863.90

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Rein.Steel with 5 % wastage


Binding wire 1.25 mm dia
Total cost of Materials

B. MACHINERY:
Sl No
Description

Unit

Quantity

tonne
kg

Unit

1.05
9.00

Quantity

UNIT :
1.00 tonne
Rate
Amount
in Rs.
in Rs
40000.00 42000.00
70.00 630.00
Rs: 42630.00

Rate

Amount

59

Dam and Allied Works - Item Unit Rates 2015-16

in Rs.
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2

Bar bender
mazdoor

Unit

Quantity

Rate
in Rs.

Day
Day

2.00
6.84

Total cost of Labour


labour component/unit qty
3100.40
Add contractor's profit and overhead charges
13.615% 422.10
labour component/unit qty (including contractor's profit)
3522.50
A.MATERIAL
B.MACHINERY
C. LABOUR
Total
D.Add for contractor's profit and overheads on A+B+C
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
151.50 Rs/Tonne
Total cost for
1.00
Rate per/ TON.=(A+B+C+D) / I

13.615%

52115.67

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

welding machine
fuel charges

Unit

1.025
70.00

Quantity

hour
hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Quantity

Rein.Steel with 2.5 % wastage


tonne
Welding electrodes 5 per joint and 14 joints perOne
ton
Total cost of Materials

B. MACHINERY:
Sl No
Description

welder
Bar bender
mazdoor

Unit

6226.19

159.075
tonne 52115.67

Providing, fabricating and placing in position reinforcement steel for RCC


above 36 dia with welding and wastage at 2.5%, tying with 1.25 mm diameter soft
annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
overlaps and wastage
as per NHAI-data
welding joints considered for bars above 36 mm diameter.

1
3

UNIT :
1.00 tonne
Rate
Amount
in Rs.
in Rs
40000.00 41000.00
11.00 770.00
Rs: 41770.00

Rate
in Rs.

Amount
in Rs
16.00 160.00
92.40 924.00
Rs: 1084.00

Rate
in Rs.

Amount
in Rs
415.00 1037.50
490.00 980.00
310.00 2120.40
4137.90

10.00
10.00

Quantity

day
Day
Day

2.50
2.00
6.84

Total cost of Labour


labour component/unit qty
4137.90
Add contractor's profit and overhead charges
13.615% 563.40
labour component/unit qty (including contractor's profit)
4701.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on A+B+C
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
151.50 Rs/Tonne
Total cost for
1.00
Rate per/ TON.=(A+B+C+D) / I

IRR-DAW-2-2

DATA:

Amount
in Rs
490.00 980.00
310.00 2120.40
3100.40

42630.00
0.00
3100.40
45730.40

IRR-DAW-2-1B

Unit

in Rs
Rs: 0.00

13.615%

41770.00
1084.00
4137.90
46991.90
6397.95

155.2875
tonne 53545.14
53545.14

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 250 kg /cum with use of super plasticiser
equal to 0.4% of cement content , CA : 0.98 cum,
Blending Ratio of CA -- 40:30:20:10, FA : 0.35 cum )
RATE ANALYSIS
UNIT:

60

Dam and Allied Works - Item Unit Rates 2015-16

A. MATERIALS:
Sl No
Particulars
1
2

3
4
5

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-screened )
Super Plasticizer or AEA
Use rate of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm

Unit

60000.00
720.00
94.08
70.56
47.04
23.52
84.00
240.00
120.00

Quantity

Batching plant
Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

240.00 cum
Amount
in Rs
6.30 378000.00
6.30 4536.00
635.00 59740.80
1145.00 80791.20
1210.00 56918.40
875.00 20580.00
560.00 47040.00
95.00 22800.00
326.08 39129.60
Rs: 709536.00

Rate
in Rs.

Rate
in Rs.
518.10
423.40
131.90
346.40
446.70
307.20
867.10
200.20
15.80
0.00
6.70
77.00
9.70
11.50
20.00
Rs:

Amount
in Rs
4144.80
3387.20
1055.20
2771.20
14294.40
9830.40
13873.60
3203.20
632.00
0.00
53.60
616.00
155.20
184.00
200.00
54400.80

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

318.20
153.10
165.80
176.80
77.70
146.90
415.00
480.00

Amount
in Rs
2545.60
1224.80
5305.60
2828.80
621.60
2350.40
1660.00
960.00

2.00
2.00
2.00
6.00
2.00
120.00

310.00
310.00
310.00
310.00
310.00
119.70
Rs:

620.00
620.00
620.00
1860.00
620.00
14364.00
36200.80

8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

1
2
3
4
5
6
7
8
9

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
150.80
Add contractor's profit and overhead charges
13.615% 20.50
labour component/unit qty (including contractor's profit)
171.30

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for conveyor system @
Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
84.00
cum @
Lead Charges for 1 Km for CA
235.20 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
60.72
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-2A
New Item1-2010-11

Rs:
Rs:
Rs:
Rs:

Total
3.00%
2.5%
4.0%
Total
13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

709536.00
54400.80
36200.80
800137.60
24004.13
20003.44
32005.50
Rs: 876150.67
Rs. 119287.91
2629.2
7103.04
7875.384
Rs: 1013046.20
Rs: 4221.00

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 300 kg /cum with use of

61

Dam and Allied Works - Item Unit Rates 2015-16

0.4% of cement content super plasticiser , CA : 0.90 cum,


Blending Ratio of CA -- 40:30:20:10, FA : 0.40 cum )

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm

Unit

72000.00
720.00
86.40
64.80
43.20
21.60
96.00
288.00
120.00

Quantity

Batching plant
Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
6.30 453600.00
6.30 4536.00
635.00 54864.00
1145.00 74196.00
1210.00 52272.00
875.00 18900.00
560.00 53760.00
95.00 27360.00
326.08 39129.60
Rs: 778617.60

Rate
in Rs.
518.10
423.40
131.90
346.40
446.70
307.20
867.10
200.20
15.80
0.00
6.70
77.00
9.70
11.50
20.00
Rs:

Amount
in Rs
4144.80
3387.20
1055.20
2771.20
14294.40
9830.40
13873.60
3203.20
632.00
0.00
53.60
616.00
155.20
184.00
200.00
54400.80

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

318.20
153.10
165.80
176.80
77.70
146.90
415.00
480.00

Amount
in Rs
2545.60
1224.80
5305.60
2828.80
621.60
2350.40
1660.00
960.00

2.00
2.00
2.00
6.00
2.00
120.00

310.00
310.00
310.00
310.00
310.00
119.70
Rs:

620.00
620.00
620.00
1860.00
620.00
14364.00
36200.80

8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

1
2
3
4
5
6
7
8
9

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
150.80
Add contractor's profit and overhead charges
13.615% 20.50
labour component/unit qty (including contractor's profit)
171.30

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for conveyor system @
Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
72.72
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-3

Rs:
Rs:
Rs:
Rs:

Total
3.00%
2.5%
4.0%
Total
13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

778617.60
54400.80
36200.80
869219.20
26076.58
21730.48
34768.77
Rs: 951795.03
Rs. 129586.89
3004.8
6523.20
9431.784
Rs: 1100341.70
Rs: 4584.80

Providing and laying insitu vibrated M-10 ( 28 days cube compressive

62

Dam and Allied Works - Item Unit Rates 2015-16

strength not less than10 N / sq mm ) grade cement concrete using 80 mm


down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 220 kg /cum with use of super plasticiser,
CA: 0.98 cum, Blending Ratio of CA --40:30:20:10, FA: 0.37 cum)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm

52800
720.00
94.08
70.56
47.04
23.52
88.8
211.20
120.00

Unit

Quantity

Batching plant 2 x 1.5 cum


Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Rate
in Rs.
518.10
423.40
131.90
346.40
446.70
307.20
867.10
200.20
15.80
0.00
6.70
77.00
9.70
11.50
20.00
Rs:

Amount
in Rs
4144.80
3387.20
1055.20
2771.20
14294.40
9830.40
13873.60
3203.20
632.00
0.00
53.60
616.00
155.20
184.00
200.00
54400.80

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

318.20
153.10
165.80
176.80
77.70
146.90
415.00
480.00

Amount
in Rs
2545.60
1224.80
5305.60
2828.80
621.60
2350.40
1660.00
960.00

2.00
2.00
2.00
6.00
2.00
120.00

310.00
310.00
310.00
310.00
310.00
119.70
Rs:

620.00
620.00
620.00
1860.00
620.00
14364.00
36200.80

8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Unit

Quantity

1
2
3
4
5
6
7
8
9

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
150.80
Add contractor's profit and overhead charges
13.615% 20.50
labour component/unit qty (including contractor's profit)
171.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rate
in Rs.

Rs:
Rs:
Rs:
Total
3.00%
2.5%
4.0%
Total
13.615%

Add for conveyor system @


Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
88.80
Lead Charges for 1 Km for CA
235.20

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
6.30 332640.00
6.30 4536.00
635.00 59740.80
1145.00 80791.20
1210.00 56918.40
875.00 20580.00
560.00 49728.00
95.00 20064.00
326.08 39129.60
Rs: 664128.00

cum @
cum @

31.3 Rs./Cum
30.2 Rs./Cum

664128.00
54400.80
36200.80
Rs: 754729.60
22641.89
18868.24
30189.18
Rs: 826428.91
Rs. 112518.3
2779.44
7103.04

63

Dam and Allied Works - Item Unit Rates 2015-16

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
53.52
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240

IRR-DAW-2-4

129.7 Rs./Tonne
cum

6941.544
Rs: 955771.23
Rs: 3982.40

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 310 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Batching plant 2 x 1.5 cum


Fuel / Energy charges
Air compressor 7 cmm ( ele )
Fuel / Energy charges
Tipper
Fuel / Energy charges
Tower crane 5 t
Fuel / Energy charges
Concrete bucket
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Needle vibrator 60 mm dia ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Unit
kg
kg
cum
cum
cum
cum
kg
sqm

74400
720.00
108
64.8
43.2
96
297.60
360.00
15%

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
11 Labour cost for scaffolding @
15%
Total cost of Labour
labour component/unit qty
297.50
Add contractor's profit and overhead charges
13.615% 40.50
labour component/unit qty (including contractor's profit)
338.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Quantity

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
6.30 468720.00
6.30 4536.00
1145.00 123660.00
1210.00 78408.00
875.00 37800.00
560.00 53760.00
95.00 28272.00
326.08 117388.80
17608.32
Rs: 930153.12

Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

518.10
423.40
131.90
346.40
446.70
307.20
867.10
200.20
15.80
0.00
6.70
77.00
9.70
11.50
20.00
Rs:

Rate
in Rs.
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

318.20
153.10
165.80
176.80
77.70
146.90
415.00
480.00

2.00
2.00
2.00
6.00
2.00
360.00

310.00
310.00
310.00
310.00
310.00
119.70
Rs:

Amount
in Rs
4144.80
3387.20
1055.20
2771.20
14294.40
9830.40
13873.60
3203.20
632.00
0.00
53.60
616.00
155.20
184.00
200.00
54400.80

Amount
in Rs
2545.60
1224.80
5305.60
2828.80
621.60
2350.40
1660.00
960.00
0.00
620.00
620.00
620.00
1860.00
620.00
43092.00
6463.80
71392.60

Rs: 930153.12
Rs: 54400.80
Rs: 71392.60

64

Dam and Allied Works - Item Unit Rates 2015-16

Add for aggregate conveyor system @


Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
75.12
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-4A
new Item2-2010-11

Total
3.0%
2.50%
4.0%
Total
13.615%

Rs: 1055946.52
31678.40
26398.66
42237.86
Rs: 1156261.44
Rs. 157425
3004.8
6523.20

31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

9743.064
Rs: 1332957.50
Rs: 5554.00

Providing and laying insitu vibrated M-25 ( 28 days cube compressive


strength not less than 25 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 360 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Batching plant 2 x 1.5 cum


Fuel / Energy charges
Air compressor 7 cmm ( ele )
Fuel / Energy charges
Tipper
Fuel / Energy charges
Tower crane 5 t
Fuel / Energy charges
Concrete bucket
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Needle vibrator 60 mm dia ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Crew for Batching plant


Crew for Air compressor
Crew for Tipper ( 4 )
Crew for Tower crane ( 2 )
Crew for Pump
Crew for Needle vibrator ( 2 )
Mason Class-I
Foreman
mazdoor
for silo ( cement handling )
for batching plant
for conveyor system
for laying & vibrating
for cleaning / washing / curing
10 Labour cost for shuttering
11 Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty

Unit

Quantity

kg
kg
cum
cum
cum
cum
kg
sqm

86400
720.00
108
64.8
43.2
96
345.60
360.00
15%

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
6.30 544320.00
6.30 4536.00
1145.00 123660.00
1210.00 78408.00
875.00 37800.00
560.00 53760.00
95.00 32832.00
326.08 117388.80
17608.32
Rs: 1010313.12

Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Unit

Quantity

518.10
423.40
131.90
346.40
446.70
307.20
867.10
200.20
15.80
0.00
6.70
77.00
9.70
11.50
20.00
Rs:

Rate
in Rs.

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

318.20
153.10
165.80
176.80
77.70
146.90
415.00
480.00

Day
Day
Day
Day
Day
sqm

2.00
2.00
2.00
6.00
2.00
360.00

310.00
310.00
310.00
310.00
310.00
119.70

15%
Rs:

Amount
in Rs
4144.80
3387.20
1055.20
2771.20
14294.40
9830.40
13873.60
3203.20
632.00
0.00
53.60
616.00
155.20
184.00
200.00
54400.80

Amount
in Rs
2545.60
1224.80
5305.60
2828.80
621.60
2350.40
1660.00
960.00
0.00
620.00
620.00
620.00
1860.00
620.00
43092.00
6463.80
71392.60

297.50

65

Dam and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


13.615% 40.50
labour component/unit qty (including contractor's profit)
338.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for aggregate conveyor system @
Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
87.12
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-4B
new Item3-2010-11

Rs:
Rs:
Rs:
Rs:

Total
3.0%
2.50%
4.0%
Total
13.615%

1010313.12
54400.80
71392.60
1136106.52

34083.20
28402.66
45444.26
Rs: 1244036.64
Rs. 169375.59
3004.8
6523.20

31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

11299.464
Rs: 1434239.69
Rs: 5976.00

Providing and laying insitu vibrated M-25 ( 28 days cube compressive


strength not less than 25 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 380 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--65:35, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Batching plant 2 x 1.5 cum


Fuel / Energy charges
Air compressor 7 cmm ( ele )
Fuel / Energy charges
Tipper
Fuel / Energy charges
Tower crane 5 t
Fuel / Energy charges
Concrete bucket
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Needle vibrator 60 mm dia ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Crew for Batching plant


Crew for Air compressor
Crew for Tipper ( 4 )
Crew for Tower crane ( 2 )
Crew for Pump
Crew for Needle vibrator ( 2 )
Mason Class-I
Foreman
mazdoor
for silo ( cement handling )
for batching plant
for conveyor system

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

91200
720.00
140.4
75.6
96
364.80
360.00
15%

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
6.30 574560.00
6.30 4536.00
1210.00 169884.00
875.00 66150.00
560.00 53760.00
95.00 34656.00
326.08 117388.80
17608.32
Rs: 1038543.12

Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

518.10
423.40
131.90
346.40
446.70
307.20
867.10
200.20
15.80
0.00
6.70
77.00
9.70
11.50
20.00
Rs:

Rate
in Rs.

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

318.20
153.10
165.80
176.80
77.70
146.90
415.00
480.00

Day
Day
Day

2.00
2.00
2.00

310.00
310.00
310.00

Amount
in Rs
4144.80
3387.20
1055.20
2771.20
14294.40
9830.40
13873.60
3203.20
632.00
0.00
53.60
616.00
155.20
184.00
200.00
54400.80

Amount
in Rs
2545.60
1224.80
5305.60
2828.80
621.60
2350.40
1660.00
960.00
0.00
620.00
620.00
620.00

66

Dam and Allied Works - Item Unit Rates 2015-16

for laying & vibrating


Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
11 Labour cost for scaffolding @
15%
Total cost of Labour
labour component/unit qty
297.50
Add contractor's profit and overhead charges
13.615% 40.50
labour component/unit qty (including contractor's profit)
338.00

6.00
2.00
360.00

310.00 1860.00
310.00 620.00
119.70 43092.00
6463.80
Rs: 71392.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for aggregate conveyor system @
Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
91.92
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-5

Rs:
Rs:
Rs:
Rs:

Total
3.0%
2.50%
4.0%
Total
13.615%

1038543.12

54400.80
71392.60
1164336.52

34930.10
29108.41
46573.46
Rs: 1274948.49
Rs. 173584.24
3004.8
6523.20

31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

11922.024
Rs: 1469982.75
Rs: 6124.90

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 260 kg / cum with use of super plasticiser,
CA : 0.90 cum, Blending Ratio of CA -- 50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticizer
Use rate of shuttering
Use rate of scaffolding @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Quantity

kg
kg
cum
cum
cum
cum
kg
sqm

3640.00
42.00
6.3
3.78
2.52
5.6
14.56
14.00
15%

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5

Unit

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
mazdoor
for batching cement ( cement handling
for batching other materials
for loading mortar pans
for laying
for conveying concrete
for cleaning / washing / curing
6
Labour cost of shuttering
7
Labour cost of scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges

UNIT :
14.00 cum
Rate
Amount
in Rs.
in Rs
6.30 22932.00
6.30 264.60
1145.00 7213.50
1210.00 4573.80
875.00 2205.00
560.00 3136.00
95.00 1383.20
217.39 3043.46
456.52
Rs: 45208.08

Rate
in Rs.
8.0
8.0
1.0
1.0
8.0
8.0

Unit

Quantity

51.70
38.50
6.70
77.00
8.00
7.70
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
64.00
61.60
930.90

Amount
in Rs
1632.80
77.70
1175.20
415.00

Rate
in Rs.

Hour
Hour
Hour
Day

8.00
1.00
8.00
1.00

204.10
77.70
146.90
415.00

Day
Day
Day
Day
Day
Day
sqm

2.00
9.00
4.00
3.00
14.00
1.00
14.00

310.00
310.00
310.00
310.00
310.00
310.00
79.80

15%

620.00
2790.00
1240.00
930.00
4340.00
310.00
1117.20
167.58
Rs: 14815.48

1058.20
13.615% 144.10

67

Dam and Allied Works - Item Unit Rates 2015-16

labour component/unit qty (including contractor's profit)

1202.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.60
Lead Charges for 1 Km for CA
12.60

13.615%
cum @
cum @

31.3 Rs./Cum
30.2 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
3.68
tonne @
Total cost for
14.00
Rate per
cum
(A+B+C+D)/14

IRR-DAW-2-6

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates with placing and
sinking plums of size 150 to 80 mm upto 15 percent for gravity type
structures including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling,
vibrating, finishing, curing etc.,complete with initial lead upto 1 km and
all lifts. ( Cement content : 260 kg / cum of concrete with use of plums
and super plasticiser of 0.4% of cement quantity, CA : 0.77 cum,
Blending Ratio of CA : 50:30:20,FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6
7

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Plums of size 150 to 80 mm
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

UNIT:
Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm
15%

Unit

1
2
3
4
5
6

Unit

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for loading plums
Day
for laying concrete and plums
Day
for conveying concrete
Day
for conveying plums
Day
for cleaning / washing / curing
Day
7
Labour for shuttering
sqm
8
Labour for scaffolding @
15%
Total cost of Labour
labour component/unit qty
1032.60
Add contractor's profit and overhead charges
13.615% 140.60
labour component/unit qty (including contractor's profit)
1173.20

477.5554
Rs: 70286.77
Rs: 5020.50

16.45 cum
Amount
in Rs
6.30 26945.10
6.30 310.91
1145.00 7247.85
1210.00 4598.00
875.00 2213.75
360.00 1480.50
560.00 3132.08
95.00 1625.26
217.39 3576.07
536.41
Rs: 51665.93

Rate
in Rs.
4277
49.35
6.33
3.8
2.53
4.11
5.59
17.11
16.45

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

129.7 Rs./Tonne
cum

45208.08
930.90
14815.48
60954.46
8298.95
175.28
380.52

Rate
in Rs.
51.70
38.50
6.70
77.00
9.70
11.50
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
77.60
92.00
974.90

8.00
1.00
8.00
1.00
1.00

204.10
77.70
146.90
415.00
400.00

Amount
in Rs
1632.80
77.70
1175.20
415.00
400.00

2.00
9.00
4.00
1.00
4.00
13.99
3.00
1.00
16.45

310.00
310.00
310.00
310.00
310.00
310.00
310.00
310.00
79.80

8.00
8.00
1.00
1.00
8.00
8.00

Quantity

Rate
in Rs.

620.00
2790.00
1240.00
310.00
1240.00
4335.66
930.00
310.00
1312.71
196.91
Rs: 16985.98

ABSTRACT:

68

Dam and Allied Works - Item Unit Rates 2015-16

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.59
cum @
Lead Charges for 1 Km for CA and Plums
16.77
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
4.33
tonne @
Total cost for
16.45
Rate per
cum
(A+B+C+D)/16.45

IRR-DAW-2-7

Rs:
Rs:
Rs:
Rs:
Rs.

Total
13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

51665.93
974.90
16985.98
69626.81
9479.69
175.0609
506.53

561.1276
Rs: 80349.22
Rs: 4884.50

Providing and laying insitu vibrated M-10 ( 28 days cube compressive


strength not less than 10 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all
lifts. ( Cement content 220 kg / cum with use of super plasticiser,
CA : 0.90 cum, Blending Ratio of CA : 50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg/ cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticizer
Use rate of shuttering
Use rate of scaffolding @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
cum
kg
sqm

3636.60
49.59
7.44
4.46
2.98
6.61
14.55
16.53
15%

Unit

Quantity

51.70
38.50
6.70
77.00
8.00
7.70
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
64.00
61.60
930.90

8.00
1.00
8.00
1.00

204.10
77.70
146.90
415.00

Amount
in Rs
1632.80
77.70
1175.20
415.00

2.00
9.00
4.00
3.00
16.53
1.00
16.53

310.00
310.00
310.00
310.00
310.00
310.00
79.80

13.615%

Rs:
Rs:
Rs:
Rs:
Rs.

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
16.53 cum
Rate
Amount
in Rs.
in Rs
6.30 22910.58
6.30 312.42
1145.00 8517.08
1210.00 5400.35
875.00 2603.48
560.00 3702.72
95.00 1381.91
217.39 3593.46
539.02
Rs: 48961.02

Rate
in Rs.
8.00
8.00
1.00
1.00
8.00
8.00

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for laying
Day
for conveying concrete
Day
for cleaning / washing / curing
Day
6
Labour cost of shuttering
sqm
7
Labour cost of scaffolding @
15%
Total cost of Labour
labour component/unit qty
957.80
Add contractor's profit and overhead charges
13.615% 130.40
labour component/unit qty (including contractor's profit)
1088.20

Rate
in Rs.

620.00
2790.00
1240.00
930.00
5124.30
310.00
1319.09
197.86
Rs: 15831.95

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
6.61
Lead Charges for 1 Km for CA
14.88

cum @
cum @

31.3 Rs./Cum
30.2 Rs./Cum

48961.02
930.90
15831.95
65723.87
8948.3
206.9556
449.29

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
3.69

tonne @

129.7 Rs./Tonne

478.09884

Total

69

Dam and Allied Works - Item Unit Rates 2015-16

Total cost for


Rate per

IRR-DAW-2-8

DATA:

cum

16.53
(A+B+C+D)/16.53

cum

Rs: 75806.51
Rs: 4586.00

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all
lifts. ( Cement content : 280 kg / cum with use of super plasticiser,
CA : 0.80 cum, Blending Ratio of CA -- 65:35, FA : 0.44 cum)
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg/ cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Use rate of scaffolding @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

4443.6
47.61
8.25
4.44
6.98
17.77
15.87
15%

Unit

Quantity

51.70
38.50
6.70
77.00
8.00
7.70
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
64.00
61.60
930.90

8.00
1.00
8.00
1.00

204.10
77.70
146.90
415.00

Amount
in Rs
1632.80
77.70
1175.20
415.00

2.00
9.00
4.00
3.00
15.87
1.00
15.87

310.00
310.00
310.00
310.00
310.00
310.00
79.80

13.615%

Rs:
Rs:
Rs:
Rs:
Rs.

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
15.87 cum
Rate
Amount
in Rs.
in Rs
6.30 27994.68
6.30 299.94
1210.00 9985.40
875.00 3888.15
560.00 3910.37
95.00 1688.57
217.39 3449.98
517.50
Rs: 51734.59

Rate
in Rs.
8.00
8.00
1.00
1.00
8.00
8.00

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for laying
Day
for conveying concrete
Day
for cleaning / washing / curing
Day
6
Labour cost of shuttering
sqm
7
Labour cost of scaffolding @
15%
Total cost of Labour
labour component/unit qty
980.90
Add contractor's profit and overhead charges
13.615% 133.50
labour component/unit qty (including contractor's profit)
1114.40

Rate
in Rs.

620.00
2790.00
1240.00
930.00
4919.70
310.00
1266.43
189.96
Rs: 15566.79

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
6.98
Lead Charges for 1 Km for CA
12.70

cum @
cum @

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.49
tonne @
Total cost for
15.87
Rate per
cum
(A+B+C+D)/15.87

IRR-DAW-2-9

31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

51734.59
930.90
15566.79
68232.28
9289.82
218.56164
383.42

582.50994
Rs: 78706.59
Rs: 4959.50

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of spillway bridge, blockouts and such
other similar structures with conjested reinforcement with initial lead

70

Dam and Allied Works - Item Unit Rates 2015-16

upto 1 km and all lifts. ( Cement content : 330 kg / cum with use of
super plasticiser, CA : 0.80 cum, Blending Ratio of CA -- 65:35,
FA : 0.44 cum)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg/ cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
ltr
sqm
100%
Total cost of Materials

Unit

4445.1
40.41
7.00
3.77
5.93
17.78
33.68

Quantity

Concrete mixer 300 / 200 ltr ( ele


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT:
13.47 cum
Rate
Amount
in Rs.
in Rs
6.30 28004.13
6.30 254.58
1210.00 8475.32
875.00 3300.15
560.00 3319.01
95.00 1689.14
217.39 7320.61
7320.61
Rs: 59683.55

Rate
in Rs.
8.00
8.00
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling )
Day
for batching other materials
Day
for loading mortar pans
Day
for laying
Day
for conveying concrete
Day
for cleaning/ washing/ curing
Day
6
Labour cost of shuttering
sqm
7
Labour cost of scaffolding @
100%
Total cost of Labour
labour component/unit qty
1391.30
Add contractor's profit and overhead charges
13.615% 189.40
labour component/unit qty (including contractor's profit)
1580.70

51.70
38.50
6.70
77.00
8.00
7.70
Rs:

Rate
in Rs.
8.00
1.00
8.00
1.00

204.10
77.70
146.90
415.00

2.00
9.00
4.00
3.00
13.47
1.00
33.68

310.00
310.00
310.00
310.00
310.00
310.00
79.80
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.93
cum @
Lead Charges for 1 Km for CA
10.78
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
4.49
tonne @
Total cost for
13.47
Rate per
cum
(A+B+C+D)/13.47

IRR-DAW-2-10

Rs:
Rs:
Rs:
Rs:
Rs.

13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

Amount
in Rs
413.60
308.00
6.70
77.00
64.00
61.60
930.90

Amount
in Rs
1632.80
77.70
1175.20
415.00
0.00
620.00
2790.00
1240.00
930.00
4175.70
310.00
2687.27
2687.27
18740.94

59683.55
930.90
18740.94
79355.39
10804.24
185.50884
325.44

581.77065
Rs: 91252.34
Rs: 6774.50

Providing and forming porous concrete body drain of size 68.5 x 68.5 cm
with 23 cm diameter central hole using cement and 20 mm down
approved, clean, hard, graded coarse aggregates in 1 : 3.50 proportion by
volume including cost of all materials, machinery, labour, formwork, curing
etc., complete with initial lead upto 1 km and all lifts.
(M15 Cement content : 400kg/cum, CA : 1cum,
Blending Ratio of CA -- 65:35)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Cement
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm

Unit
kg
cum
cum

Quantity
3424
5.56
3.00

UNIT:
20.00 Rm
Rate
Amount
in Rs.
in Rs
6.30 21571.20
1210.00 6732.44
875.00 2621.50

71

Dam and Allied Works - Item Unit Rates 2015-16

Use rate of shuttering


Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

sqm

Unit

76.00

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

55.13 4189.84
Rs: 35114.98

Rate
in Rs.
8.00
8.00
0.50
0.50

Quantity

1
2
3
4

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for laying & packing concrete
Day
for conveying concrete
Day
5
Fitter shuttering
Day
Total cost of Labour
labour component/unit qty
478.50
Add contractor's profit and overhead charges
13.615% 65.10
labour component/unit qty (including contractor's profit)
543.60

51.70
38.50
6.70
77.00
Rs:

Rate
in Rs.
8.00
0.50
1.00
2.00
6.00
2.00
2.00
8.56
3.00

Amount
in Rs
204.10 1632.80
77.70 38.85
415.00 415.00
310.00
310.00
310.00
310.00
310.00
370.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for CA
8.56
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.42
tonne @
Total cost for
20.00
Rate per
Rm
(A+B+C+D)/20

IRR-DAW-2-11
(a)

Rs:
Rs:
Rs:
Rs:
Rs.

13.615%
30.2 Rs./Cum
129.7 Rs./Tonne
Rm

Amount
in Rs
413.60
308.00
3.35
38.50
763.45

620.00
1860.00
620.00
620.00
2653.60
1110.00
9570.25

35114.98
763.45
9570.25
45448.68
6187.84
258.51

444.0928
Rs: 52339.12
Rs: 2617.00

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of
all materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC solid parapet consisting of 35 cm x 20 cm kerb,
35 cm x 35 cm x 1 m pillars spaced approximately at 3.35 m c / c, 12.5 cm
thick wall 80 cm height with 12.5 cm thick and 35 cm wide coping slab for
wall and 12 .5 cm thick 40 cm x 40 cm coping for pillars with top edges of
kerb and coping chamferred / rounded as directed etc., complete
( excluding cost of providing and placing reinforcement steel and gate )
with initial lead upto 1 km and all lifts.
( Cement content 350 kg / cum with use of super plasticiser( 0.4% by wt.
of cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)

72

Dam and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Cement mix
Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

3034.5
43.35
4.51
2.43
3.81
12.14
95.00
15%

LS

Unit

2.00

Quantity

51.70
38.50
8.00
7.70
6.70
77.00
Rs:

Amount
in Rs
413.60
308.00
64.00
61.60
3.35
38.50
889.05

8.00
0.50
8.00
2.00
1.00

204.10
77.70
146.90
415.00
400.00

Amount
in Rs
1632.80
38.85
1175.20
830.00
400.00

2.00
9.00
4.00
2.00
8.67
2.00
95.00

310.00
310.00
310.00
310.00
310.00
310.00
79.80

13.615%

Rs:
Rs:
Rs:
Rs:
Rs.

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm ( ele )
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT:
36.00 Rm
Rate
Amount
in Rs.
in Rs
6.30 19117.35
6.30 273.11
1210.00 5457.10
875.00 2126.25
560.00 2133.60
95.00 1153.11
217.39 20652.05
3097.81
20.00 40.00
Rs: 54050.38

Rate
in Rs.
8.00
8.00
8.00
8.00
0.50
0.50

Quantity

1
2
3
4
5
6

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Vibrator
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling )
Day
for batching other materials
Day
for loading mortar pans
Day
for laying & packing concrete
Day
for conveying concrete
Day
for curing & miscellaneous
Day
7
Labour for shuttering
sqm
8
Labour for scaffolding @
15%
Total cost of Labour
labour component/unit qty
593.70
Add contractor's profit and overhead charges
13.615% 80.80
labour component/unit qty (including contractor's profit)
674.50

Rate
in Rs.

620.00
2790.00
1240.00
620.00
2687.70
620.00
7581.00
1137.15
Rs: 21372.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
3.81
cum @
Lead Charges for 1 Km for CA
6.94
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.08
tonne @
Total cost for
36.00
Rate per
Rm
(A+B+C+D)/36

IRR-DAW-2-12
(b)

31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
Rm

54050.38
889.05
21372.70
76312.13
10389.9
119.253
209.59

399.19715
Rs: 87430.07
Rs: 2428.60

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC ornamental parapet consisting of 35 cm x 20 cm
kerb, 35 cm x 35 cm x 1 m pillars spaced approximately at 3.5 m apart,
20 cm x 15 cm posts 80 cm height approximately 30 cm c / c with 12.5 cm
thick and 35 cm wide coping slab for posts and pillars with top edges of
kerb and coping chamferred or rounded as directed etc., complete
( excluding cost of providing and placing reinforcement steel and gate ) with
initial lead upto 1 km and all lifts.
( Cement content : 350 kg / cum with use of super plasticiser(0.4% by wt.
of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)

73

Dam and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Cement mix
Cenent for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

2450
35.00
3.64
1.96
3.08
9.80
115.00
15%

LS

Unit

2.00

Quantity

51.70
38.50
8.00
7.70
6.70
77.00
Rs:

Amount
in Rs
413.60
308.00
64.00
61.60
3.35
38.50
889.05

8.00
0.50
8.00
2.00
1.00

204.10
77.70
146.90
415.00
400.00

Amount
in Rs
1632.80
38.85
1175.20
830.00
400.00

2.00
9.00
4.00
2.00
7.00
2.00
115.00

310.00
310.00
310.00
310.00
310.00
310.00
79.80

13.615%

Rs:
Rs:
Rs:
Rs:
Rs.

Concrete mixer 300 / 200 ltr ( ele


Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm ( ele )
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT:
36.00 Rm
Rate
Amount
in Rs.
in Rs
6.30 15435.00
6.30 220.50
1210.00 4404.40
875.00 1715.00
560.00 1724.80
95.00 931.00
217.39 24999.85
3749.98
20.00 40.00
Rs: 53220.53

Rate
in Rs.
8.00
8.00
8.00
8.00
0.50
0.50

Quantity

1
2
3
4
5
6

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Vibrator
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling )
Day
for batching other materials
Day
for loading mortar pans
Day
for laying & packing concrete
Day
for conveying concrete
Day
for curing & miscellaneous
Day
7
Labour for shuttering
sqm
8
Labour for scaffolding @
15%
Total cost of Labour
labour component/unit qty
630.30
Add contractor's profit and overhead charges
13.615% 85.80
labour component/unit qty (including contractor's profit)
716.10

Rate
in Rs.

620.00
2790.00
1240.00
620.00
2170.00
620.00
9177.00
1376.55
Rs: 22690.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
3.08
cum @
Lead Charges for 1 Km for CA
5.60
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
2.49
tonne @
Total cost for
36.00
Rate per
Rm
(A+B+C+D)/36

IRR-DAW-2-13

31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
Rm

53220.53
889.05
22690.40
76799.98
10456.32
96.404
169.12

322.3045
Rs: 87844.13
Rs: 2440.10

Providing and laying insitu M- 25 ( 28 days cube compressive strength not


less than 25 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for wearing coat including cost
of all materials, machinery, labour, formwork, cleaning, batching, mixing,
placing in position in alternate panels, levelling, compacting, finishing,

74

Dam and Allied Works - Item Unit Rates 2015-16

curing, packing joints with asphalt mortar etc., complete


with initial lead upto 1 km and all lifts.
( Cement content : 380 kg / cum with use of super plasticiser(0.4% by
wt. of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of shuttering
Sundries ( asphalt mortar etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm
LS

4446
58.50
6.084
3.276
5.265
17.78
5.85
5.00

Unit

Quantity

Concrete mixer 300/200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
11.70 cum
Rate
Amount
in Rs.
in Rs
6.30
28009.80
6.30
368.55
1210.00
7361.64
875.00
2866.50
560.00
2948.40
95.00
1689.48
217.39
1271.73
20.00
100.00
Rs:
44616.10

Rate
in Rs.
51.70
38.50
6.70
77.00
Rs:

Amount
in Rs
413.60
308.00
3.35
38.50
763.45

8.00
0.50
3.00
1.00

204.10
77.70
415.00
400.00

Amount
in Rs
1632.80
38.85
1245.00
400.00

2.00
9.00
4.00
5.00
11.70
1.00
5.85

310.00
310.00
310.00
310.00
310.00
310.00
79.80
Rs:

620.00
2790.00
1240.00
1550.00
3627.00
310.00
466.83
13920.48

8.00
8.00
0.50
0.50

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling )
Day
for batching materials
Day
for loading mortar pans
Day
for laying & compacting
Day
for conveying concrete
Day
for cleaning/ washing/ curing
Day
6
Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
1189.80
Add contractor's profit and overhead charges
13.615% 162.00
labour component/unit qty (including contractor's profit)
1351.80

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
44616.10
Rs:
763.45
Rs:
13920.48
Rs:
59300.03
Rs. 8073.7
164.7945
282.67

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.27
Lead Charges for 1 Km for CA
9.36

13.615%
cum @
cum @

31.3 Rs./Cum
30.2 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.50
tonne @
Total cost for
11.70
Rate per
cum
(A+B+C+D)/11.70

IRR-DAW-2-14

DATA:

129.7 Rs./Tonne
cum

584.23365
Rs: 68405.43
Rs: 5846.60

Pre-cooling to control placement temperature of cement concrete in the


range of 18 to 21 C at the concrete placement point by inundation of coarse
aggregates and adding flaked ice as part of mixing water including cost of
all materials, machinery, labour etc., complete with all leads and lifts.
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Sundries ( amonia gas etc)

Unit

Quantity

LS

3.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Ice maker unit consisting of:

Unit
Hour

Quantity

UNIT:
500 cum
Rate
Amount
in Rs.
in Rs
20.00 60.00
0.00 0.00
Rs:
60.00

Rate
in Rs.
24.00

Amount
in Rs
170.20 4084.80

75

Dam and Allied Works - Item Unit Rates 2015-16

Compressor 125 hp - 1 No
Condenser with 30 hp motor - 1 No.
Ice makers 10 t / day each - 3 Nos.
Pump 2 hp for ice cutting - 3 Nos.
Pump 2 hp for pumping water-3 Nos.
Screw conveyor with 15 hp motor -1
Ice elevator with 5 hp motor - 1 No.
Fuel / Energy charges for system
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description

Unit

24.00

Quantity

1
2

Crew for Ice maker unit


Hour
mazdoor
for Ice chamber ( 2 x 3 )
Day
for miscellaneous works ( 1 x 3 )
Day
Total cost of Labour
labour component/unit qty
11.50
Add contractor's profit and overhead charges
13.615% 1.60
labour component/unit qty (including contractor's profit)
13.10

1097.10 26330.40
Rs: 30415.20

Rate
in Rs.
24.00
6.00
3.00

310.00 1860.00
310.00 930.00
Rs: 5730.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
500.00 cum
Rate per
cum
(A+B+C+D)/500

IRR-DAW-2-15

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

13.615%

60.00
30415.20
5730.00
36205.20
4929.34
41134.54
82.30

Conveying and fixing elastomeric bearing for spillway bridge including


cleaning and preparing surface, mixing and applying adhesive, fixing bearing
in correct position etc., including cost of all materials except bearings,
machinery, labour etc., complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Synthetic adhesive ( Resin + Hardener)


Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

Unit

Quantity

kg
LS

Unit

0.60
2.00

Quantity

Nil

UNIT:
6.00 Nos.
Rate
Amount
in Rs.
in Rs
348.00 208.80
20.00 40.00
Rs: 248.80

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
480.00
400.00
620.00
1500.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Marker / Erector
work inspector
mazdoor

Unit

Quantity

Day
Day
Day

1.00
1.00
2.00

Total cost of Labour


labour component/unit qty
250.00
Add contractor's profit and overhead charges
13.615% 34.00
labour component/unit qty (including contractor's profit)
284.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
6.00 Nos.
Rate per
Each
(A+B+C+D)/6

IRR-DAW-2-16

Amount
in Rs
122.50 2940.00

Total
13.615%

480.00
400.00
310.00
Rs:

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

248.80
0.00
1500.00
1748.80
238.1
1986.90
331.20

Providing and constructing 150 mm dia hume pipe weep holes for
concrete / masonry walls including providing 20 x 20 x 20 cm size porous
concrete block made of cement and 20 mm down coarse aggregate in
1 : 4 proportion including 10 cm thick sand backing at the junction of wall
and soil back fill, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.

76

Dam and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

150 mm dia hume pipe


Cement
20 - 10 mm coarse aggregate
Sand for filling
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

Unit

Quantity

Rm
kg
cum
cum

Unit

2.90
3.00
0.01
0.02

Quantity

Nil

UNIT:
3.00 Rm
Rate
Amount
in Rs.
in Rs
350.00 1015.00
6.30 18.90
1210.00 9.68
560.00 11.20
Rs: 1054.78

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
370.00 92.50
310.00 77.50
Rs: 170.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2

Mason Class-II
mazdoor

Unit

Quantity

Day
Day

0.25
0.25

Total cost of Labour


labour component/unit qty
56.70
Add contractor's profit and overhead charges
13.615% 7.70
labour component/unit qty (including contractor's profit)
64.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.02
cum @
Lead Charges for 1 Km for CA
0.01
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.00
tonne @
Total cost for
3.00
Rate per
Rm
(A+B+C+D)/3

IRR-DAW-2-17

Rs:
Rs:
Rs:
Rs:
Rs.

13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
Rm

1054.78
0.00
170.00
1224.78
166.75
0.626
0.24

0.3891
Rs: 1392.79
Rs: 464.30

Providing and forming expansion joint for spillway bridge consisting of


75 x 75 x 6 mm angles 2 numbers provided with 25 cm long 12 mm dia.
anchors fixed to both flanges at 15 cm c /c and 140 x 6 mm plate welded
on top of one of the angle including cost of all materials, machinery, labour,
providing and fixing 38 mm thick joint filler board matching the thickness of
wearing coat, painting etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Structural steel plate


Structural steel angle
12 dia steel anchors
Welding electrodes
Joint filler board 19 mm thick
Sundries ( cutting gas / paint etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Quantity

kg
kg
kg
Nos
sqm
LS

Unit

50.70
104.50
27.40
70.00
1.00
1.50

Quantity

Welding set
Hour
Fuel / Energy charges
Hour
Sundries (cutting torch/ welding guns etc)
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Unit

Marker / Fabricator / Erector


Gas cutter / Welder
mazdoor

Unit

UNIT:
7.50 Rm
Rate
Amount
in Rs.
in Rs
40.00 2028.00
40.00 4180.00
40.00 1096.00
11.00 770.00
650.00 650.00
20.00 30.00
Rs: 8754.00

Rate
in Rs.
8.00
8.00
2.00

Quantity

Day
Day
Day
Total cost of Labour
labour component/unit qty
261.70
Add contractor's profit and overhead charges
13.615% 35.60
labour component/unit qty (including contractor's profit)
297.30

16.00
92.40
20.00
Rs:

Amount
in Rs
128.00
739.20
40.00
907.20

480.00
415.00
310.00
Rs:

Amount
in Rs
720.00
622.50
620.00
1962.50

Rate
in Rs.
1.50
1.50
2.00

77

Dam and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
Total cost for
Rate per
Rm

0.18

tonne @
7.50
(A+B+C+D)/7.50

IRR_DAW-3

MASONRY & GUNITING WORKS :

IRR-DAW-3-1

Providing and constructing un-coursed rubble stone masonry using


approved stones in cement mortar 1 : 3 proportion including cost of all
materials, machinery, labour, scaffolding, cleaning, packing mortar, wedging
stone chips, curing etc., complete with initial lead upto 1 km and all lifts.
( Cement content : 190 kg/cum of masonry, rubble stones : 0.85 cum,
stone chips : 0.15 cum/cum, FA : 0.4 cum)

DATA:

Rs:
Rs:
Rs:
Rs:
Rs.
151.5 Rs./Tonne

Rm

27.6639
Rs: 13233.93
Rs: 1764.50

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement for mortar


Rubble stones
Stone chips
Sand (Screened )

B. MACHINERY:
Sl No
Description
1
2

Concrete mixer 300 / 200 ltr ( ele )


Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
25.00
Unit

Quantity

kg
cum
cum
cum
Total cost of Materials

Unit

4750
21.25
3.75
10

Hour
Hour
Hour
Hour

Unit

Rate
in Rs.
6.30
330.00
360.00
760.00
Rs:

Quantity

Rate
in Rs.
51.70
38.50
6.70
77.00
Rs:

8.00
1.00
1.00
2.50
4.00
16.00

204.10
77.70
400.00
415.00
370.00
370.00

Amount
in Rs
1632.80
77.70
400.00
1037.50
1480.00
5920.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

310.00
310.00
310.00
310.00
310.00
310.00
310.00
Rs:

620.00
1860.00
1240.00
3100.00
310.00
1240.00
3720.00
22638.00

Rs:
Rs:
Rs:
Rs:
Rs.

45887.50
805.30
22638.00
69330.80
9439.39
313
755.00

Quantity

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
905.50
Add contractor's profit and overhead charges
13.615% 123.30
labour component/unit qty (including contractor's profit)
1028.80

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
10.00
cum @
Lead Charges for 1 Km for Stones/Stone Chips
25.00
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
4.75
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

cum
Amount
in Rs
29925.00
7012.50
1350.00
7600.00
45887.50

Amount
in Rs
413.60
308.00
6.70
77.00
805.30

8.00
8.00
1.00
1.00

1
2
3
4
5
6
7

IRR-DAW-3-2

8754.00
907.20
1962.50
11623.70
1582.57

13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

616.075
Rs: 80454.27
Rs: 3218.20

Providing and constructing un-coursed rubble stone masonry using approved stones in
cement mortar 1 : 4 proportion including cost of all materials, machinery, labour, scaffolding,
cleaning, packing mortar, wedging stone chips, curing etc., complete with initial lead upto
1 km and all lifts.
( Cement content : 143 kg/cum of masonry, rubble stones : 0.85 cum,

78

Dam and Allied Works - Item Unit Rates 2015-16

stone chips : 0.15 cum/cum, FA : 0.4 cum)


For 1 cum masonry :DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement for mortar


Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Concrete mixer 300 / 200 ltr(ele)


Fuel / Energy charges
10 hp pump
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

Quantity

kg
cum
cum
cum

Unit

3575
21.25
3.75
10

Quantity

Hour
Hour
Hour
Hour

Unit

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
6.30 22522.50
330.00 7012.50
360.00 1350.00
760.00 7600.00
Rs:
38485.00

Rate
in Rs.
51.70
38.50
6.70
77.00
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
805.30

8.00
1.00
1.00
2.50
4.00
16.00

204.10
77.70
400.00
415.00
370.00
370.00

Amount
in Rs
1632.80
77.70
400.00
1037.50
1480.00
5920.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

310.00
310.00
310.00
310.00
310.00
310.00
310.00
Rs:

620.00
1860.00
1240.00
3100.00
310.00
1240.00
3720.00
22638.00

Rs:
Rs:
Rs:
Rs:
Rs.

38485.00
805.30
22638.00
61928.30
8431.54
313
755.00

8.00
8.00
1.00
1.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
905.50
Add contractor's profit and overhead charges
13.615% 123.30
labour component/unit qty (including contractor's profit)
1028.80

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
10.00
cum @
Lead Charges for 1 Km for Stones/Stone Chips
25.00
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.58
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-3

Total
13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

463.6775
Rs: 71891.52
Rs: 2875.70

Providing and constructing coursed rubble face stone masonry using


approved rubble stones in cement mortar 1 : 3 proportion including cost
of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc., with initial lead upto 1 km
and all lifts.
( Thickness of the CR face assumed: 0.75 m,Cement content : 178 kg/cum of masonry,
rubble stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum,
CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Unit

Cement for mortar


kg
Coursed rubble stone 30 x 30 x 45 cm
Nos
Coursed rubble stone 30 x 30 x 60 cm
Nos
Rubble stones
cum
Stone chips
cum
Sand (Screened )
cum
Total cost of Materials

Quantity
4450
244
82
8.75
3.75
9.375

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
6.30 28035.00
22.00 5368.00
28.00 2296.00
330.00 2887.50
360.00 1350.00
760.00 7125.00
Rs: 47061.50

79

Dam and Allied Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No
Description

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
2
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit

Rate
in Rs.
51.70
38.50
6.70
77.00
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
805.30

8.00
1.00
1.00
7.00
2.50
4.00
16.00

204.10
77.70
400.00
370.00
415.00
370.00
370.00

Amount
in Rs
1632.80
77.70
400.00
2590.00
1037.50
1480.00
5920.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

310.00
310.00
310.00
310.00
310.00
310.00
310.00
Rs:

620.00
1860.00
1240.00
3100.00
310.00
1240.00
3720.00
25228.00

Rs:
Rs:
Rs:
Rs:
Rs.

47061.50
805.30
25228.00
73094.80
9951.86
293.4375
809.66

8.00
8.00
1.00
1.00

Quantity

1
2
3
4
5
6
7
8

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Stone chiseller Cl -II
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
1009.10
Add contractor's profit and overhead charges
13.615% 137.40
labour component/unit qty (including contractor's profit)
1146.50

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
9.38
Lead Charges for 1 Km for Stones/Stone Chips
26.81

13.615%
cum @
cum @

31.3 Rs./Cum
30.2 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.45
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-4

129.7 Rs./Tonne
cum

577.165
Rs: 84726.92
Rs: 3389.10

Providing and constructing coursed rubble face stone masonry using


approved rubble stones in cement mortar 1 : 4 proportion including cost of
all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc., with initial lead upto 1 km and
all lifts.
( Cement content : 134 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.375 cum,
CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mortar


Coursed rubble stone 30 x 30 x 45 cm
Coursed rubble stone 30 x 30 x 60 cm
Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Quantity

kg
Nos
Nos
cum
cum
cum

Unit

3350
244
82
8.75
3.75
9.375

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1

Unit

Crew for Concrete mixer

Unit
Hour

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
6.30 21105.00
22.00 5368.00
28.00 2296.00
330.00 2887.50
360.00 1350.00
760.00 7125.00
Rs: 40131.50

Rate
in Rs.
8.00
8.00
1.00
1.00

Quantity

51.70
38.50
6.70
77.00
Rs:

Rate
in Rs.
8.00

Amount
in Rs
413.60
308.00
6.70
77.00
805.30

Amount
in Rs
204.10 1632.80

80

Dam and Allied Works - Item Unit Rates 2015-16

2
3
4
5
6
7
8

Crew for Pump


Hour
work inspector
Day
Stone chiseller Cl -II
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
1009.10
Add contractor's profit and overhead charges
13.615% 137.40
labour component/unit qty (including contractor's profit)
1146.50

1.00
1.00
7.00
2.50
4.00
16.00

77.70
400.00
370.00
415.00
370.00
370.00

77.70
400.00
2590.00
1037.50
1480.00
5920.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

310.00
310.00
310.00
310.00
310.00
310.00
310.00

620.00
1860.00
1240.00
3100.00
310.00
1240.00
3720.00
25228.00

Rs:
Rs:
Rs:
Rs:
Rs.

40131.50
805.30
25228.00
66164.80
9008.34
293.4375
809.66

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
9.38
cum @
Lead Charges for 1 Km for Stones/Stone Chips
26.81
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.35
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-5

13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

434.495
Rs: 76710.73
Rs: 3068.40

Providing and constructing chisel drafted and hammer dressed face


stone masonry with approved stones in cement mortar 1 : 3 proportion
including cost of all materials, machinery, labour, scaffolding, ramps,
cleaning, packing mortar, wedging stone chips, curing etc.,complete with
initial lead upto 1 km and all lifts.
( Cement content : 167 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.35 cum,
Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mortar


Coursed rubble stone 30 x 30 x 45 cm
Coursed rubble stone 30 x 30 x 60 cm
Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Quantity

kg
Nos
Nos
cum
cum
cum

Unit

4175
250
85
8.75
3.75
8.75

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Unit

Crew for Concrete mixer


Crew for Pump
work inspector
Stone chiseller Cl -I
Stone chiseller Cl -II
Mason Class-I
Mason Class-II
Chavali
mazdoor
for batching cement ( cement handling )
for batching sand
for loading mortar pans
for laying & packing mortar
for loading chips

Unit

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
6.30 26302.50
22.00 5500.00
28.00 2380.00
330.00 2887.50
360.00 1350.00
760.00 6650.00
Rs: 45070.00

Rate
in Rs.
8.00
8.00
1.00
1.00

Quantity

51.70
38.50
6.70
77.00
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
805.30

Rate
in Rs.

Hour
Hour
Day
Day
Day
Day
Day
Day

8.00
1.00
1.00
14.00
7.00
2.50
4.00
16.00

204.10
77.70
400.00
415.00
370.00
415.00
370.00
370.00

Amount
in Rs
1632.80
77.70
400.00
5810.00
2590.00
1037.50
1480.00
5920.00

Day
Day
Day
Day
Day

2.00
6.00
4.00
10.00
1.00

310.00
310.00
310.00
310.00
310.00

620.00
1860.00
1240.00
3100.00
310.00

81

Dam and Allied Works - Item Unit Rates 2015-16

for washing rubble / finishing / curing


Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
1241.50
Add contractor's profit and overhead charges
13.615% 169.00
labour component/unit qty (including contractor's profit)
1410.50

4.00
12.00

310.00 1240.00
310.00 3720.00
Rs: 31038.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
8.75
Lead Charges for 1 Km for Stones/Stone Chips
27.22

13.615%
cum @
cum @

31.3 Rs./Cum
30.2 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.18
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-6

129.7 Rs./Tonne
cum

45070.00
805.30
31038.00
76913.30
10471.75
273.875
821.89

541.4975
Rs: 89022.32
Rs: 3560.90

Providing and constructing chisel drafted and hammer dressed face


stone masonry with approved stones in cement mortar 1 : 4 proportion
including cost of all materials, machinery, labour, scaffolding, ramps,
cleaning, packing mortar, wedging stone chips, curing etc.,complete with
initial lead upto 1 km and all lifts.
( Cement content : 125 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.35 cum,
Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mortar


Coursed rubble stone 30 x 30 x 45 cm
Coursed rubble stone 30 x 30 x 60 cm
Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Unit

Quantity

kg
Nos
Nos
cum
cum
cum

Unit

3125
250
85
8.75
3.75
8.75

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Unit

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Stone chiseller Cl -I
Day
Stone chiseller Cl -II
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
1241.50
Add contractor's profit and overhead charges
13.615% 169.00
labour component/unit qty (including contractor's profit)
1410.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
6.30 19687.50
22.00 5500.00
28.00 2380.00
330.00 2887.50
360.00 1350.00
760.00 6650.00
Rs: 38455.00

Rate
in Rs.
51.70
38.50
6.70
77.00
Rs:

Amount
in Rs
413.60
308.00
6.70
77.00
805.30

8.00
1.00
1.00
14.00
7.00
2.50
4.00
16.00

204.10
77.70
400.00
415.00
370.00
415.00
370.00
370.00

Amount
in Rs
1632.80
77.70
400.00
5810.00
2590.00
1037.50
1480.00
5920.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

310.00
310.00
310.00
310.00
310.00
310.00
310.00
Rs:

620.00
1860.00
1240.00
3100.00
310.00
1240.00
3720.00
31038.00

8.00
8.00
1.00
1.00

Quantity

Rate
in Rs.

Rs: 38455.00
Rs: 805.30
Rs: 31038.00

82

Dam and Allied Works - Item Unit Rates 2015-16

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
8.75
cum @
Lead Charges for 1 Km for Stones/Stone Chips
27.22
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.13
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-7

Rs: 70298.30
Rs. 9571.11
273.875
821.89

13.615%
31.3 Rs./Cum
30.2 Rs./Cum
129.7 Rs./Tonne
cum

Providing cement mortar pointing to coursed rubble face stone masonry


50 mm deep in CM 1 : 2 proportion by volume including raking and cleaning
joints, pressing mortar into joints, cost of all materials, labour, scaffolding,
finishing, curing etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Cement
Sand (Screened )

Unit

Quantity

kg
cum

455.446
0.735

Total cost of Materials


B. MACHINERY:
Sl No
Description

Unit

Quantity

1 NIL
(Manual mixing )

1
2

UNIT:
100.00 sqm
Rate
Amount
in Rs.
in Rs
6.30 2869.31
760.00 558.60
Rs: 3427.91

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
415.00 4150.00
310.00 3100.00
Rs: 7250.00

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
Description
Unit
Mason Class-I
mazdoor

Quantity

Day
Day

10.00
10.00

Total cost of Labour


labour component/unit qty
72.50
Add contractor's profit and overhead charges
13.615% 9.90
labour component/unit qty (including contractor's profit)
82.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.74
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.46
tonne @
Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100

IRR-DAW-3-8

405.3125
Rs: 81370.49
Rs: 3254.80

Rs:
Rs:
Rs:
Rs:
Rs.

13.615%
31.3 Rs./Cum
129.7 Rs./Tonne
sqm

3427.91
0.00
7250.00
10677.91
1453.8
23.0055

59.071346
Rs: 12213.79
Rs: 122.10

Providing cement mortar pointing to coursed rubble face stone masonry


50 mm deep in CM 1 : 3 proportion by volume including raking and cleaning
joints, pressing mortar into joints, cost of all materials, labour, scaffolding,
finishing, curing etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Cement
Sand (Screened )

Unit

Quantity

kg
cum

321.80
0.74

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Unit

Quantity

NIL
Manual mixing )

UNIT:
100.00 sqm
Rate
Amount
in Rs.
in Rs
6.30 2027.34
760.00 558.60
Rs: 2585.94

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
415.00 4150.00
310.00 3100.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2

Mason Class-I
mazdoor

Unit
Day
Day

Quantity
10.00
10.00

83

Dam and Allied Works - Item Unit Rates 2015-16

Total cost of Labour


labour component/unit qty
72.50
Add contractor's profit and overhead charges
13.615% 9.90
labour component/unit qty (including contractor's profit)
82.40

Rs: 7250.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.74
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.32
tonne @
Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100
IRR_DAW-4

CONTRACTION JOINT WORKS:

IRR-DAW-4-1

Providing 25 mm thick guniting to rock or masonry surface in cement


mortar 1 : 3 proportion by weight including cost of all materials, machinery,
labour, raking-out and cleaning joints, scaffolding wherever required and all
other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.

DATA:

Rs:
Rs:
Rs:
Rs:
Rs.

13.615%
31.3 Rs./Cum
129.7 Rs./Tonne
sqm

2585.94
0.00
7250.00
9835.94
1339.16
23.0055

41.73746
Rs: 11239.84
Rs: 112.40

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement
Sand (Screened )
Use rate of grout hose 25 m
Use rate of water hose 25 m
Use rate of guniting nozzle
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4

Unit

Quantity

kg
cum
Hour
Hour
Hour
LS

609.90
1.09
8.00
8.00
8.00
2.00

Unit

Quantity

Guniting equipment
Hour
Fuel / Energy charges
Hour
Air compressor 8.5 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Pump 10 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT :
36.00 sqm
Rate
Amount
in Rs.
in Rs
6.30 3842.37
760.00 828.40
5.78 46.25
5.78 46.25
3.50 28.00
20.00 40.00
Rs: 4831.27

Rate
in Rs.
110.10
0.00
170.80
433.10
6.70
77.00
20.00
Rs:

Amount
in Rs
880.80
0.00
1366.40
3464.80
6.70
77.00
40.00
5835.70

8.00
8.00
1.00
1.00

204.10
153.10
77.70
370.00

Amount
in Rs
1632.80
1224.80
77.70
370.00

2.00
2.00
2.00

310.00
310.00
310.00
Rs:

620.00
620.00
620.00
5165.30

8.00
8.00
8.00
8.00
1.00
1.00
2.00

Unit

Quantity

1
2
3
4
5

Crew for Guniting equipment


Hour
Crew for Air compressor
Hour
Crew for pump
Hour
Mason Cl II
Day
mazdoor
for cement handling
Day
for sand
Day
mazdoor for other works
Day
Total cost of Labour
labour component/unit qty
143.50
Add contractor's profit and overhead charges
13.615% 19.50
labour component/unit qty (including contractor's profit)
163.00

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
Add for scaffolding

3%

D.Add for contractor's profit and overheads on (A+B+C+other


Lead Charges for 1 Km for FA
1.09
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.61
tonne @
Total cost for
36.00
Rate per
sqm
(A+B+C+D)/36

Total
13.615%
31.3 Rs./Cum
129.7 Rs./Tonne
sqm

4831.27
5835.70
5165.30
15832.27
395.81
Rs: 16228.08
Rs. 2209.45
34.117
79.10403
Rs: 18550.75
Rs: 515.30

84

Dam and Allied Works - Item Unit Rates 2015-16

IRR-DAW-4-2

DATA:

Providing and constructing contraction joints by fixing 16 SWG 60 cm


wide annealed copper sheets in two lines with 8 mm dia steel dowel
rods on either side at one metre interval, forming 125 x 125 mm size groove
in between copper strips for filling asphalt including fixing 15 mm dia two
legged G.I pipe with U - bend at bottom for circulation of steam at intervals
and forming 150 mm dia formed drain behind water seals including cost of
all materials, machinery, labour, filling asphalt, circulation of steam through
pipes etc., complete with all leads and lifts. consider 12 m height of
contraction joint for analysis.
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Copper sheet 16 SWG


Reinforcement steel 8 mm dia
GI pipe 15 mm dia
Asphalt
Elbows / Nipple / Plugs etc.,
Soldering materials
Total cost of Materials

B. MACHINERY:
Sl No
Description

Unit

Quantity

kg
kg
Rm
kg
LS
LS

Unit

215.00
30.00
24.00
192.00
5.00
40.00

Quantity

1 Steam circulation arrangement


LS
Fuel charges ( gas for heating )
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
4
5
6

Welder
Tinsmith
Bar bender
Pipe fitter
Mason Class-I
mazdoor

Unit

UNIT:
12.00 Rm
Rate
Amount
in Rs.
in Rs
680.00 146200.00
40.00 1200.00
110.00 2640.00
4.00 768.00
17.00 85.00
17.00 680.00
Rs:
151573.00

Rate
in Rs.

Amount
in Rs
17.00 136.00
17.00 170.00
Rs: 306.00

Rate
in Rs.

Amount
in Rs
415.00
415.00
245.00
240.00
207.50
310.00
1832.50

8.00
10.00

Quantity

Day
Day
Day
Day
Day
Day

1.00
1.00
0.50
0.50
0.50
1.00

415.00
415.00
490.00
480.00
415.00
310.00
Rs:

Total cost of Labour


labour component/unit qty
152.70
Add contractor's profit and overhead charges
13.615% 20.80
labour component/unit qty (including contractor's profit)
173.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
12.00 Rm
Rate per
Rm
(A+B+C+D)/12

IRR-DAW-4-3

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

151573.00
306.00
1832.50
153711.50
20927.82
174639.32
14553.30

Providing and constructing contraction joints by fixing 310 mm wide


central bulb type approved quality PVC water stop in two lines with 8 mm
diameter steel dowel rods on either side at 1m interval, forming 125 x 125
mm size groove in between two water stops, providing & fixing 15 mm dia
two legged G.I pipe with U-bend at bottom for circulation steam at interval,
forming 150 mm diameter formed drain behind water seals including filling
groove with asphalt, circulation of steam at intervals, cost of all materials,
machinery, labour etc., complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

PVC water stops 310 mm wide


Reinforcement steel 8 mm dia
GI pipe 15 mm dia
Asphalt
Elbows / Nipple / Plugs etc.,
Vulcanizing materials
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

Steam circulation arrangement


Fuel charges ( gas for heating )

Unit

Quantity

Rm
kg
Rm
kg
LS
LS

Unit
LS
LS

24.50
30.00
24.00
192.00
5.00
25.00

Quantity

UNIT:
12.00 Rm.
Rate
Amount
in Rs.
in Rs
485.00 11882.50
40.00 1200.00
110.00 2640.00
4.00 768.00
17.00 85.00
17.00 425.00
Rs: 17000.50

Rate
in Rs.
8.00
10.00

Amount
in Rs
17.00 136.00
17.00 170.00

85

Dam and Allied Works - Item Unit Rates 2015-16

Total hire charges of Machinery


C. LABOUR:
Sl No
Description
1
2
3
4
5

Welder
Bar bender
Pipe fitter
Mason Class-I
mazdoor

Unit

Rs: 306.00

Quantity

Day
Day
Day
Day
Day

Rate
in Rs.
0.50
0.50
0.50
0.50
1.00

Total cost of Labour


labour component/unit qty
100.80
Add contractor's profit and overhead charges
13.615% 13.70
labour component/unit qty (including contractor's profit)
114.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
12.00 Rm.
Rate per
Rm.
(A+B+C+D)/12

IRR-DAW-4-4

17000.50
306.00
1210.00
18516.50
2521.02
21037.52
1753.10

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Copper sheet 16 SWG


Reinforcement steel 8 mm dia
Soldering materials
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

Sundries such as soldering gun etc.,


Fuel charges ( gas )
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5

Welder
Tinsmith
Bar bender
Mason Class-I
mazdoor

Unit

Quantity

kg
kg
LS

Unit

77.00
15.00
10.00

Quantity

LS
LS

Unit

UNIT:
8.7 Rm
Rate
Amount
in Rs.
in Rs
680.00 52360.00
40.00 600.00
17.00 170.00
Rs: 53130.00

Rate
in Rs.

Amount
in Rs
20.00 60.00
17.00 85.00
Rs: 145.00

Rate
in Rs.
415.00
415.00
490.00
415.00
310.00
Rs:

Amount
in Rs
207.50
207.50
245.00
207.50
155.00
1022.50

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

53130.00
145.00
1022.50
54297.50
7392.6
61690.10
7090.80

3.00
5.00

Quantity

Day
Day
Day
Day
Day

0.5
0.5
0.5
0.5
0.5

Total cost of Labour


labour component/unit qty
117.50
Add contractor's profit and overhead charges
13.615% 16.00
labour component/unit qty (including contractor's profit)
133.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
8.70 Rm
Rate per
Rm
(A+B+C+D)/8.70

DATA:

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Providing and constructing contraction joints by fixing 16 SWG 60 cm


wide annealed copper sheets in single line with 8 mm dia steel dowel
rods on either side at 1 metre interval including cost of all materials,
machinery, labour etc., complete with all leads and lifts.

DATA:

IRR-DAW-4-5

415.00
490.00
480.00
415.00
310.00
Rs:

Amount
in Rs
207.50
245.00
240.00
207.50
310.00
1210.00

Providing and constructing contraction joints by fixing 23 cm wide central


bulb type PVC water stop in single line supported by 10 mm dia steel
dowel rods on either side at 1 metre interval including cost of all materials,
machinery, labour, valcunising joints etc., complete with all leads and
lifts.
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

Rate

UNIT:
8.70 Rm
Amount

86

Dam and Allied Works - Item Unit Rates 2015-16

in Rs.
1
2
3

PVC water seal 23 cm wide


Reinforcement steel 10 mm dia
Vulcanising materials
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

Unit

9.00
10.00
2.00

Quantity

Sundries such as heater etc.,


LS
Fuel charges for heating
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4

Rm
kg
LS

Welder
Bar bender
Mason Class-I
mazdoor

Unit

47.00
40.00
17.00
Rs:

Rate
in Rs.

Amount
in Rs
20.00 10.00
17.00 8.50
18.50

Rate
in Rs.

Amount
in Rs
207.50
245.00
207.50
155.00
815.00

0.50
0.50

Quantity

Day
Day
Day
Day

0.50
0.50
0.50
0.50

415.00
490.00
415.00
310.00
Rs:

Total cost of Labour


labour component/unit qty
93.70
Add contractor's profit and overhead charges
13.615% 12.80
labour component/unit qty (including contractor's profit)
106.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
8.70 Rm
Rate per
Rm
(A+B+C+D)/8.70
EARTH / ROCKFILL EMBANKMENT WORKS :

IRR-DAW-5-1

Providing hearting embankment using selected impervious soil from


approved borrow areas in layers of 25 to 30 cm before compaction
including cost of all materials, machinery, labour, all operations such as
excavation, sorting out, transportation, spreading soil in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density
control of not less than 95 percent or as stipulated using Sheep foot roller /
Vibratory roller/ 8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
13.615%

IRR_DAW-5

in Rs
423.00
400.00
34.00
857.00

857.00
18.50
815.00
1690.50
230.16
1920.66
220.80

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 5 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Day

5.50
5.50
8.00
8.00
40.00
40.00
4.00
4.00
8.00
8.00
6.50
6.50
2.00

Quantity
5.50
8.00
40.00
4.00
8.00
6.50
2.00

UNIT
825.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
625.30
1706.60
893.90
446.70
307.20
3.00
38.50
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs
9435.25
3439.15
13652.80
7151.20
17868.00
12288.00
12.00
154.00
3220.00
2457.60
8724.30
6866.60
40.00
85308.90

Rate
in Rs.

Amount
in Rs
1215.50
1768.00
6632.00
310.80
1326.40
1591.85
800.00

221.00
221.00
165.80
77.70
165.80
244.90
400.00

87

Dam and Allied Works - Item Unit Rates 2015-16

mazdoor

Day
Total cost of Labour
labour component/unit qty
18.00
Add contractor's profit and overhead charges
13.615% 2.50
labour component/unit qty (including contractor's profit)
20.50

4.00

310.00 1240.00
Rs: 14884.55

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
825.00 cum
Rate per
cum
(A+B+C+D)/825

IRR-DAW-5-2

0.00
85308.90
14884.55
100193.45
13641.34
113834.79
138.00

Providing cut-off trench filling using selected impervious soil from


approved borrow areas in layers of 25 to 30 cm before compaction
including cost of all materials, machinery, labour, all operations such as
excavation, sorting out, transportation, spreading soil to specified thickness,
breaking clods, sectioning, watering, compacting to density control of not
less than 95 percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No Description
1
2
3
4
5
6
7

Unit

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 6 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No Description

Unit

5.50
5.50
8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
6.50
6.50
2.00

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
19.60
Add contractor's profit and overhead charges
13.615% 2.70
labour component/unit qty (including contractor's profit)
22.30

5.50
8.00
48.00
4.00
8.00
6.50
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
825.00 cum
Rate per
cum
(A+B+C+D)/825

IRR-DAW-5-3

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
13.615%

UNIT :
825.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
625.30
1706.60
893.90
446.70
307.20
3.00
38.50
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs
9435.25
3439.15
13652.80
7151.20
21441.60
14745.60
12.00
154.00
3220.00
2457.60
8724.30
6866.60
40.00
91340.10

Rate
in Rs.
221.00
221.00
165.80
77.70
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs
1215.50
1768.00
7958.40
310.80
1326.40
1591.85
800.00
1240.00
16210.95

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
91340.10
16210.95
107551.05
14643.08
122194.13
148.10

Providing casing embankment using semi-pervious soil from approved


borrow areas in layers of 25 to 30 cm before compaction including cost of
all materials, machinery, labour, all other operations such as excavation,
sorting out, transportation, spreading soil in layers of specified thickness,

88

Dam and Allied Works - Item Unit Rates 2015-16

breaking clods, sectioning, watering, compacting to density control of not


less than 95 percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

UNIT :
630 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Unit

4.00
4.00
8.00
8.00
32.00
32.00
3.00
3.00
5.00
5.00
5.00
5.00
5.00

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
19.50
Add contractor's profit and overhead charges
13.615% 2.70
labour component/unit qty (including contractor's profit)
22.20

Rate
in Rs.
1715.50
625.30
1706.60
893.90
446.70
307.20
3.00
38.50
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs
6862.00
2501.20
13652.80
7151.20
14294.40
9830.40
9.00
115.50
2012.50
1536.00
6711.00
5282.00
100.00
70058.00

Rate
in Rs.
221.00
221.00
165.80
77.70
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs
884.00
1768.00
5305.60
233.10
829.00
1224.50
800.00
1240.00
12284.20

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
70058.00
12284.20
82342.20
11210.89
93553.09
148.50

4.00
8.00
32.00
3.00
5.00
5.00
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
630.00 cum
Rate per
cum
(A+B+C+D)/630

IRR-DAW-5-4

Total
13.615%

Providing casing embankment using semi-pervious soil available


from excavation in layers of 25 to 30 cm before compaction including cost
of all materials, machinery, labour, all other operations such as re-excavation,
sorting out, transportation, spreading in layers of specified thickness,
breaking clods, sectioning, watering, compacting to specified density
control of not less than 95 percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as
stipulated etc.,complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

Rate
in Rs.
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1
2

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour

Quantity
4.60
4.60
8.00
8.00

970.00 cum
Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
625.30
1706.60
893.90

Amount
in Rs
7891.30
2876.38
13652.80
7151.20

89

Dam and Allied Works - Item Unit Rates 2015-16

3
4
5
6
7

Tipper 5 cum
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

48.00
48.00
4.00
4.00
8.00
8.00
7.00
7.00
5.00

446.70
307.20
3.00
38.50
402.50
307.20
1342.20
1056.40
20.00
Rs:

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
16.60
Add contractor's profit and overhead charges
13.615% 2.30
labour component/unit qty (including contractor's profit)
18.90

Rate
in Rs.
4.60
8.00
48.00
4.00
8.00
7.00
2.00
4.00

221.00
221.00
165.80
77.70
165.80
244.90
400.00
310.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
970.00 cum
Rate per
cum
(A+B+C+D)/970
IRR-DAW-5-4-A
(New Item1 - 2011-12)

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

21441.60
14745.60
12.00
154.00
3220.00
2457.60
9395.40
7394.80
100.00
90492.68

Amount
in Rs
1016.60
1768.00
7958.40
310.80
1326.40
1714.30
800.00
1240.00
16134.50

0.00
90492.68
16134.50
106627.18
14517.29
121144.47
124.90

Providing casing embankment using semi-pervious soil available


from excavation in layers of 25 to 30 cm before compaction including cost
of all materials, machinery, labour, all other operations such as re-excavation,
sorting out, transportation, spreading in layers of specified thickness,
breaking clods, sectioning, watering, compacting to specified density
control of not less than 90 percent using 2 Tonne Roller as
stipulated etc.,complete with initial lead upto 1 km and all lifts.
(For Maintenance Works)

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

Rate
in Rs.
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour
Hour
Hour

4.60
4.60
8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
7.00
7.00
5.00

Quantity
4.60
8.00
48.00
4.00
8.00
7.00

970.00 cum
Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
625.30
1706.60
893.90
446.70
307.20
3.00
38.50
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs
7891.30
2876.38
13652.80
7151.20
21441.60
14745.60
12.00
154.00
3220.00
2457.60
9395.40
7394.80
100.00
90492.68

Rate
in Rs.

Amount
in Rs
1016.60
1768.00
7958.40
310.80
1326.40
1714.30

221.00
221.00
165.80
77.70
165.80
244.90

90

Dam and Allied Works - Item Unit Rates 2015-16

7
8

work inspector
mazdoor

Day
Day

2.00
4.00

400.00 800.00
310.00 1240.00
Rs: 16134.50

Total cost of Labour


labour component/unit qty
16.60
Add contractor's profit and overhead charges
13.615% 2.30
labour component/unit qty (including contractor's profit)
18.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
D.Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
970.00 cum
Rate per
cum
(A+B+C+D)/970
Deduct Rate for Proctar's density Control of 95% using 8T roller as per IRR-PMW-3-23
Add Rate for Proctor's Density control of 90% using 2T Roller as per IRR-PMW-3-24
Rate per
cum
Rs.
IRR-DAW-5-5

Providing homogeneous embankment using soil from approved borrow


area in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil in layer of specified thickness, breaking clods,
sectioning, watering, compacting to density control of not less than
95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc., complete
with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Unit

Quantity

NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Unit

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 5 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

5.40
5.40
8.00
8.00
40.00
40.00
4.00
4.00
8.00
8.00
6.40
6.40
2.00

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
18.40
Add contractor's profit and overhead charges
13.615% 2.50
labour component/unit qty (including contractor's profit)
20.90

5.40
8.00
40.00
4.00
8.00
6.40
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
807.00 cum
Rate per
cum
(A+B+C+D)/807

IRR-DAW-5-6

0.00
90492.68
16134.50
106627.18
14517.29
121144.47
124.90
45.60
6.10
85.40

Total
13.615%

UNIT :
807.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
625.30
1706.60
893.90
446.70
307.20
3.00
38.50
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs
9263.70
3376.62
13652.80
7151.20
17868.00
12288.00
12.00
154.00
3220.00
2457.60
8590.08
6760.96
40.00
84834.96

Rate
in Rs.

Amount
in Rs
1193.40
1768.00
6632.00
310.80
1326.40
1567.36
800.00
1240.00
14837.96

221.00
221.00
165.80
77.70
165.80
244.90
400.00
310.00
Rs:

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
84834.96
14837.96
99672.92
13570.47
113243.39
140.30

Providing embankment adjacent to masonry / concrete structures and filling trial pits

91

Dam and Allied Works - Item Unit Rates 2015-16

using impervious soil from approved borrow areas in layers of 10 to 15 cm and compacting
each layer to density control of not less than 95 percent using pneumatic tampers or by
vibratory earth rammers including cost of all materials, machinery, labour, picking previous
layer, spreading soil in layer, breaking clods, watering etc., complete with initial lead upto
1 km and all lifts.
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

UNIT :
Unit

1 Use rate of air hose

Quantity

Hour

Rate
in Rs.
16.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No Description
1
2
3
4
5
6
7
8

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Pneumatic tampers 2 Nos.
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No Description

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

0.15
0.15
0.80
0.80
3.00
3.00
8.00
8.00
0.40
0.40
0.80
0.80
16.00
16.00
1.00

Unit

Quantity

1
2
3
4
5
6
7
8
9

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Air compressor
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Pneumatic tamper
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
99.60
Add contractor's profit and overhead charges
13.615% 13.60
labour component/unit qty (including contractor's profit)
113.20

Rate
in Rs.
1715.50
625.30
1706.60
893.90
446.70
307.20
170.80
433.10
3.00
38.50
402.50
307.20
20.70
0.00
20.00
Rs:

Amount
in Rs
257.33
93.80
1365.28
715.12
1340.10
921.60
1366.40
3464.80
1.20
15.40
322.00
245.76
331.20
0.00
20.00
10459.98

Rate
in Rs.

Amount
in Rs
33.15
176.80
497.40
1224.80
31.08
132.64
3918.40
400.00
1550.00
7964.27

0.15
0.80
3.00
8.00
0.40
0.80
16.00
1.00
5.00

221.00
221.00
165.80
153.10
77.70
165.80
244.90
400.00
310.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
80.00 cum
Rate per
cum
(A+B+C+D)/80

IRR-DAW-5-7

80 cum
Amount
in Rs
11.56
185.00
0.00
0.00
Rs:
185.00

Rs:
185.00
Rs:
10459.98
Rs:
7964.27
Rs:
18609.25
Rs. 2533.65
Rs: 21142.90
Rs: 264.30

Total
13.615%

Providing and constructing rockfill embankment with 300 mm down graded stones and
quarry spalls from approved source including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing the surface to required slopes
etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
7

Use rate of drill rod 2.5 m long


Reconditioning charges @
Use rate of air hose 6 Nos.
Explosive small dia
Electric detonators
Detonator ordinary
Fuse coil
Sundries ( waste tyres etc )
Total cost of Materials

UNIT :
Unit

400
Quantity

Rate
in Rs.

Rm

387.00

42.67

10%
Hour
kg
Nos
Nos
Rm
LS

60.00
118.00
159.00
8.00
200.00
10.00

11.56
70.00
13.00
7.00
11.00
20.00
Rs:

cum
Amount
in Rs
16512.00
1651.20
693.75
8260.00
2067.00
56.00
2200.00
200.00
31639.95

92

Dam and Allied Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No Description
1
2
3
4
5

Unit

Quantity

Air compressor 8.5cmm( diesel )3 Nos


Hour
Fuel / Energy charges
Hour
Jack hammer 6 Nos
Hour
Fuel / Energy charges
Hour
Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No Description

Rate
in Rs.
30.00
30.00
60.00
60.00
4.00
4.00
8.00
8.00
24.00
24.00

Unit

Quantity

1
2
3
4
5
6
7
8
9
10

Crew for Air compressor


Hour
Crew for Jack hammer
Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Dozer
Hour
Blaster
Day
Helper blaster
Day
work inspector
Day
Mason Class-II
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
90.90
Add contractor's profit and overhead charges
13.615% 12.40
labour component/unit qty (including contractor's profit)
103.30

275.60
914.20
19.80
0.00
1715.50
625.30
1706.60
893.90
446.70
307.20
Rs:

Rate
in Rs.
30.00
60.00
8.00
24.00
4.00
1.00
1.00
2.00
2.00
10.00

195.90
306.20
221.00
165.80
221.00
480.00
370.00
400.00
370.00
310.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
400.00 cum
Rate per
cum
(A+B+C+D)/400

IRR-DAW-5-8

Amount
in Rs
8268.00
27426.00
1188.00
0.00
6862.00
2501.20
13652.80
7151.20
10720.80
7372.80
85142.80

Amount
in Rs
5877.00
18372.00
1768.00
3979.20
884.00
480.00
370.00
800.00
740.00
3100.00
36370.20

Rs:
31639.95
Rs:
85142.80
Rs:
36370.20
Rs: 153152.95
Rs. 20851.77
Rs: 174004.72
Rs: 435.00

Total
13.615%

Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
7

Use rate of drill rod 1.5 m long


Reconditionong charges @
Use rate of air hose
Explosive small dia
Electric detonator
Detonator ordinary
Fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description
1
2
3
4

UNIT :
Unit

Quantity

Rm

97.00

10%
Hour
kg
Nos
Nos
Rm
LS

15.00
30.00
40.00
2.00
50.00
2.00

Unit

Quantity

Air compressor 8.5 cmm ( diesel )


Hour
Fuel / Energy charges
Hour
Jack hammer
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No Description

Rate
in Rs.

Unit

Rate
in Rs.
7.50
7.50
15.00
15.00
2.00
2.00
6.00
6.00

Quantity

100 cum
Amount
in Rs
42.67
4138.67
413.87
11.56
173.44
70.00
2100.00
13.00
520.00
7.00
14.00
11.00
550.00
20.00
40.00
Rs:
7949.97

275.60
914.20
19.80
0.00
1706.60
893.90
446.70
307.20
Rs:

Rate
in Rs.

Amount
in Rs
2067.00
6856.50
297.00
0.00
3413.20
1787.80
2680.20
1843.20
18944.90

Amount
in Rs

93

Dam and Allied Works - Item Unit Rates 2015-16

1
2
3
4
5
6
7
8
9

Crew for Air compressor


Hour
Crew for Jack hammer
Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Blaster
Day
Helper blaster
Day
work inspector
Day
Mason Class-II
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
169.90
Add contractor's profit and overhead charges
13.615% 23.10
labour component/unit qty (including contractor's profit)
193.00

7.50
15.00
2.00
6.00
0.50
1.00
1.00
7.00
19.00

195.90
306.20
221.00
165.80
480.00
370.00
400.00
370.00
310.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-5-9

Note:
DATA:

1469.25
4593.00
442.00
994.80
240.00
370.00
400.00
2590.00
5890.00
16989.05

Rs:
7949.97
Rs:
18944.90
Rs:
16989.05
Rs:
43883.92
Rs. 5974.8
Rs: 49858.72
Rs: 498.60

Total
13.615%

Providing and constructing dry rubble rock-toe with rubble and stone chips from dump
yard (Spoil Bank) including cost of all materials, machinery, labour, hand packing rubble and stone chips,
finishing top and sides to required slopes etc., complete with initial lead upto 1 km and all
lifts.
Useful rubble and stone chips will be issued at dump yard at the issue rate for usefull rubble /
stone chips. Sorting out and breaking charges included in rate analysis.
RATE ANALYSIS
UNIT :
100 cum
A. MATERIALS:
Sl No Particulars
Unit
Quantity
Rate
Amount
in Rs.
in Rs
1
Useful rubble ( at dump yard )
cum
100.00
165.00
16500.00
2
Useful stone chips ( at dump yard )
cum
15.00
185.00
2775.00
Total cost of Materials
Rs:
19275.00
B. MACHINERY:
Sl No Description
1
2

Quantity

Shovel 0.85 cum


Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No Description
1
2
3
4
6
7

Unit

Crew for Shovel


Crew for Tipper
Mason Class-II
work inspector
Stone breaker
mazdoor

Unit
Hour
Hour
Day
Day
Day
Day

2.00
2.00
6.00
6.00

Quantity
2.00
6.00
7.00
1.00
2.00
21.00

Total cost of Labour


labour component/unit qty
116.80
Add contractor's profit and overhead charges
13.615% 15.90
labour component/unit qty (including contractor's profit)
132.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

Total
13.615%

Rate
in Rs.
1706.60
893.90
446.70
307.20
Rs:

Amount
in Rs
3413.20
1787.80
2680.20
1843.20
9724.40

Rate
in Rs.

Amount
in Rs
442.00
994.80
2590.00
400.00
740.00
6510.00
11676.80

221.00
165.80
370.00
400.00
370.00
310.00
Rs:

Rs:
19275.00
Rs:
9724.40
Rs:
11676.80
Rs:
40676.20
Rs. 5538.06
Rs: 46214.26
Rs: 462.10

Providing and constructing Dry rock Pitching for Groynes using Un-Coursed rubble stone of size 300 mm thick
IRR-DAW-5-9-A
(New Item 4 -2012-13) and Un-Coursed rubble stone chips from Quarry to site of work including cost of all materials, Machinery, Labour charge
hand packing Un-Course rubble stone &chips to the designed profile with all leads and lifts etc

94

Dam and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No Particulars
1
2

Unit

Un Coursed Rubble Stones at quarry


Stone Chips at Quarry

100 cum
Quantity

cum
cum

Rate
in Rs.
100.00
15.00

330.00
360.00
Rs:

Total cost of Materials


B. MACHINERY:
Sl No Description

1
2

Unit

Shovel 0.85 cum for loading tipper at the


worksite
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No Description
1
2
3
4
6
7

Quantity

2.00
2.00
6.00
6.00

Unit

Crew for Shovel


Crew for Tipper
Mason Class-II
work inspector
Stone breaker
mazdoor

Rate
in Rs.

Quantity

Hour
Hour
Day
Day
Day
Day

Rate
in Rs.
221.00
165.80
370.00
400.00
370.00
310.00
Rs:

Total cost of Labour


labour component/unit qty
116.80
Add contractor's profit and overhead charges
13.615% 15.90
labour component/unit qty (including contractor's profit)
132.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-5-10

Amount
in Rs

1706.60
893.90
446.70
307.20
Rs:

2.00
6.00
7.00
1.00
2.00
21.00

Amount
in Rs
33000.00
5400.00
38400.00

3413.20
1787.80
2680.20
1843.20
9724.40

Amount
in Rs
442.00
994.80
2590.00
400.00
740.00
6510.00
11676.80

Rs:
38400.00
Rs:
9724.40
Rs:
11676.80
Rs:
59801.20
Rs. 8141.93
Rs: 67943.13
Rs: 679.40

Total
13.615%

Providing and laying 30 cm diameter open jointed hume pipes with collars in rock-toe for
drainage including cost of all materials, machinery, labour etc., complete with lead upto 1 km
and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1

UNIT :
Unit

Hume pipe 300 mm dia.with collar

Quantity

Rm

Rate
in Rs.
100.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No Description
1

Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

Mason Cl- II
mazdoor

Unit
Day
Day

0.00
0.00
Rs:

Quantity

Rate
in Rs.
2
6

Total cost of Labour


labour component/unit qty
26.00
Add contractor's profit and overhead charges
13.615% 3.50
labour component/unit qty (including contractor's profit)
29.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100

100 Rm
Amount
in Rs
700.00
70000.00
0.00
Rs:
70000.00

Total
13.615%

370.00
310.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Amount
in Rs
740.00
1860.00
2600.00

Rs:
70000.00
Rs:
0.00
Rs:
2600.00
Rs:
72600.00
Rs. 9884.49
Rs: 82484.49
Rs: 824.80

95

Dam and Allied Works - Item Unit Rates 2015-16

IRR_DAW-6

FILTER & PITCHING WORKS :

IRR-DAW-6-1

Providing and constructing 1.20 m internal diameter and average 3 m height RCC manhole with
60 cm dia. top cover in M-15 grade cement concrete using 20 mm down graded, clean, hard
coarse aggregate, 20 cm thick for bed / sides / top slab / 1.5 m long cut-off wall and 7.5 cm
thick for cover including providing 12 mm dia reinforcement bars at 30 cm c / c bothways for
bed / sides / cut-off wall / top slab / rungs and 8 mm dia bars at 15 cm c / c bothways for cover,
excavation for foundation, providing 30 cm dia hume pipe outlet, cost of all materials, machinery,
labour, formwork, scaffolding, batching, mixing, laying, vibrating, finishing, curing etc., complete
with lead upto 1 km and all lifts.
( Cement content : 300 kg/cum , CA : 0.80 cum, Blending Ratioof CA -- 65:35,
FA : 0.44 cum, superplasticizer (0.4% by wt. of cement)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
7
8
9
10

Cement
Cement for incidentals @ 3 kg / cum
Coarse aggregate 20 to 10 mm
Coarse aggregate 10 to 4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Reinforcement steel with 5 % wastage
Binding wire
Hume pipe 300 mm dia
Use rate of shuttering
Scaffolding of shuttering @
Sundries

B. MACHINERY:
Sl No Description
1
2
3
4

Concrete mixer 300 / 200 ( ele )


Fuel / Energy charges
Needle vibrator 40 mm dia ( ele )
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No Description
1
2
3
4

UNIT
Unit
kg
kg
cum
cum
cum
kg
kg
kg
Rm
sqm

Unit

Unit

2.00

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
LS

1 Each
Amount
in Rs
6.30
8389.71
6.30
83.90
1210.00
2793.02
875.00
1087.56
560.00
1093.77
95.00
2246.34
40.00
6547.80
70.00
280.00
700.00
700.00
217.39
7826.04
391.30
20.00
40.00
Rs:
31479.43

Rate
in Rs.

1331.70
13.32
2.31
1.24
1.95
23.65
163.70
4.00
1.00
36.00

5%
LS
Total cost of Materials

Mason Cl- II
Day
Bar bender
Day
work inspector
Day
mazdoor
for excavation for foundation
Day
for bar bending
Day
for concreting
Day
for excavation for foundation
Day
for concreting
Day
for curing
Day
5
Labour for shuttering
sqm
Total cost of Labour
labour component/unit qty
8782.80
Add contractor's profit and overhead charges
13.615% 1195.80
labour component/unit qty (including contractor's profit)
9978.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Quantity

Rate
in Rs.
51.70
38.50
8.00
7.70
3.00
38.50
20.00
Rs:

Amount
in Rs
206.80
154.00
32.00
30.80
1.50
19.25
20.00
464.35

1.00
1.00
1.00

370.00
490.00
400.00

Amount
in Rs
370.00
490.00
400.00

2.00
1.00
5.00
2.00
4.00
1.00
36.00

310.00
310.00
310.00
310.00
310.00
310.00
79.80
Rs:

620.00
310.00
1550.00
620.00
1240.00
310.00
2872.80
8782.80

Rs:
Rs:
Rs:

31479.43
464.35
8782.80

4.00
4.00
4.00
4.00
0.50
0.50
1.00

Quantity

Rate
in Rs.

96

Dam and Allied Works - Item Unit Rates 2015-16

31.3 Rs./Cum
30.2 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
1.35

tonne @

129.7 Rs./Tonne

0.16

tonne @
1.00
(A+B+C+D)/1.0

151.5 Rs./Tonne
Each

174.4487
24.799793
Rs: 46639.13
Rs: 46639.10

Providing and constructing longitudinal and cross graded filter drains using sand and 80-20
mm and 20 mm down graded aggregates satisfying specified filter creteria in layers as per
specifications including cost of all materials, machinery, labour, laying to required slopes,
compaction etc. complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Fine aggregate (Un-Screened )


Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

cum
cum
cum
cum
cum

47.50
17.865
1.99
24.49
8.16

Unit

Quantity

NIL

100 cum
Amount
in Rs
560.00
26600.00
635.00
11344.28
1145.00
2272.83
1210.00
29629.88
875.00
7142.19
Rs:
76989.16

Rate
in Rs.

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

1.00
38.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

400.00
310.00
Rs:

Amount
in Rs
400.00
11780.00
12180.00

Rs:
76989.16
Rs:
0.00
Rs:
12180.00
Rs:
89169.16
Rs. 12140.38
Rs: 101309.54
Rs: 1013.10

Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Rate
in Rs.

Total cost of Labour


labour component/unit qty
121.80
Add contractor's profit and overhead charges
13.615% 16.60
labour component/unit qty (including contractor's profit)
138.40

IRR-DAW-6-3

Rs:
40726.58
Rs. 5544.92
61.133908
107.25

cum @
cum @

Lead Charges for 1Km for Steel (including Loading


and Unloading Charges)
Total cost for
Rate per
Each

IRR-DAW-6-2

Total
13.615%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1 Km for FA
1.95
Lead Charges for 1 Km for CA
3.55

Providing and constructing 1.40 m thick vertical or inclined graded filter media consisting of
20 cm thick sand layers, 25 cm thick 20 mm down coarse aggregate layers and 50 cm thick
80-20 mm coarse aggregate layer using approved materials satisfying specified filter creteria as
per specifications including cost of all materials, machinery, labour, laying to required slope,
compaction etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Fine aggregate (Un-Screened )


Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down

B. MACHINERY:
Sl No Description

Quantity

cum
cum
cum
cum
cum
Total cost of Materials

Unit

1 NIL

28.60
32.13
3.57
28.13
8.93

Quantity

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery

100 cum
Amount
in Rs
560.00
16016.00
635.00
20402.55
1145.00
4087.65
1210.00
34031.25
875.00
7809.38
Rs:
82346.83

Rate
in Rs.

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

97

Dam and Allied Works - Item Unit Rates 2015-16

C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Rate
in Rs.
1.00
38.00

400.00
310.00
Rs:

Total cost of Labour


labour component/unit qty
121.80
Add contractor's profit and overhead charges
13.615% 16.60
labour component/unit qty (including contractor's profit)
138.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-6-4

Rs:
82346.83
Rs:
0.00
Rs:
12180.00
Rs:
94526.83
Rs. 12869.83
Rs: 107396.66
Rs: 1074.00

Total
13.615%

Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT
Unit

Fine aggregate (Un-Screened )


Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

cum
cum
cum
cum
cum

23.55
42.39
4.71
22.05
7.35

Unit

Quantity

NIL

100 cum
Amount
in Rs
560.00
13188.00
635.00
26917.65
1145.00
5392.95
1210.00
26680.50
875.00
6431.25
Rs:
78610.35

Rate
in Rs.

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

1.00
34.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100
IRR-DAW-6-4-A

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

400.00
310.00
Rs:

Amount
in Rs
400.00
10540.00
10940.00

Rate
in Rs.

Total cost of Labour


labour component/unit qty
109.40
Add contractor's profit and overhead charges
13.615% 14.90
labour component/unit qty (including contractor's profit)
124.30

(New Item2- 2011-12)

Amount
in Rs
400.00
11780.00
12180.00

Rs:
78610.35
Rs:
0.00
Rs:
10940.00
Rs:
89550.35
Rs. 12192.28
Rs: 101742.63
Rs: 1017.40

Total
13.615%

Providing and constructing graded filter media below and behind rock-toe consisting of
30 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4

Coarse aggregate 80-40 mm


Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down

UNIT
Unit
cum
cum
cum
cum

Quantity

100 cum
Amount
in Rs
635.00
22225.00
1145.00
62975.00
1210.00
6050.00
875.00
4375.00

Rate
in Rs.
35.00
55.00
5.00
5.00

98

Dam and Allied Works - Item Unit Rates 2015-16

Total cost of Materials


B. MACHINERY:
Sl No Description
1

Unit

Quantity

NIL
Total hire charges of Machinery

1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
41.20
Add contractor's profit and overhead charges
13.615% 5.60
labour component/unit qty (including contractor's profit)
46.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-6-5

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

400.00
310.00
Rs:

Amount
in Rs
400.00
3720.00
4120.00

Rate
in Rs.
1.00
12.00

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

95625.00

Rate
in Rs.
0.00
0.00

C. LABOUR:
Sl No Description

Rs:

Rs:
95625.00
Rs:
0.00
Rs:
4120.00
Rs:
99745.00
Rs. 13580.28
Rs: 113325.28
Rs: 1133.30

Total
13.615%

Providing and laying filter media consisting of 2 layers of 250 gsm poly-propeline non-woven
filter fabric and 400 mm thick 20 mm down graded coarse aggregate for vertical / inclined
and horizontal filter blanket for embankment including cost of all materials, machinery, labour
etc., complete with lead upto 50 m for aggregate and all leads for fabric and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2

UNIT :
Unit

PP filter fabric 250 gsm


20 - 10 mm CA @ 75 %
10 mm down CA @ 25 %
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

sqm
cum
cum

Unit

220.00
30.00
10.00

Quantity

NIL

100 sqm
Amount
in Rs
154.00
33880.00
1210.00
36300.00
875.00
8750.00
Rs:
78930.00

Rate
in Rs.

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

work inspector
mazdoor

Unit
Day
Day

Quantity

400.00
310.00
Rs:

Amount
in Rs
400.00
4340.00
4740.00

Rate
in Rs.
1.00
14.00

Total cost of Labour


labour component/unit qty
47.40
Add contractor's profit and overhead charges
13.615% 6.50
labour component/unit qty (including contractor's profit)
53.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Total
13.615%

Rs:
78930.00
Rs:
0.00
Rs:
4740.00
Rs:
83670.00
Rs. 11391.67

99

Dam and Allied Works - Item Unit Rates 2015-16

Total cost for


Rate per

IRR-DAW-6-6

100.00 sqm
(A+B+C+D)/100

sqm

Rs: 95061.67
Rs: 950.60

Providing and constructing 45 cm thick chimney filter using clean approved sand satisfying
filter creteria including cost of all materials, machinery, labour, compacting etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1

UNIT :
Unit

Sand (Un-Screened)

Quantity

cum

Rate
in Rs.
105.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No Description
1

Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
97.00
Add contractor's profit and overhead charges
13.615% 13.20
labour component/unit qty (including contractor's profit)
110.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-6-7

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

400.00
310.00
Rs:

Amount
in Rs
400.00
9300.00
9700.00

Rate
in Rs.
1.00
30.00

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

100 cum
Amount
in Rs
560.00
58800.00
0.00
Rs:
58800.00

Rs:
58800.00
Rs:
0.00
Rs:
9700.00
Rs:
68500.00
Rs. 9326.28
Rs: 77826.28
Rs: 778.30

Total
13.615%

Providing and constructing 90 cm thick transition cum filter media behind rockfill using
approved sand and 80-20 mm and 20 mm down graded aggregates satisfying the filter creteria
in layers of 30 cm thickness each as per specifications including cost of all materials,
machinery, labour, laying each layer to required slope, compaction etc., complete with initial
lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

Sand (Un-Screened )
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

B. MACHINERY:
Sl No Description
1

UNIT :
Unit

Quantity

cum
cum
cum
cum
cum

Unit

34.00
30.60
3.40
25.50
8.50

Quantity

NIL

100 cum.
Amount
in Rs
560.00
19040.00
635.00
19431.00
1145.00
3893.00
1210.00
30855.00
875.00
7437.50
Rs:
80656.50

Rate
in Rs.

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

work inspector
mazdoor

Unit
Day
Day

Total cost of Labour


labour component/unit qty
128.00
Add contractor's profit and overhead charges
13.615% 17.40
labour component/unit qty (including contractor's profit)
145.40

Quantity

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

400.00
310.00
Rs:

Amount
in Rs
400.00
12400.00
12800.00

Rate
in Rs.
1.00
40.00

ABSTRACT:

100

Dam and Allied Works - Item Unit Rates 2015-16

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum.
Rate per
cum.
(A+B+C+D)/100

IRR-DAW-6-8

Rs:
80656.50
Rs:
0.00
Rs:
12800.00
Rs:
93456.50
Rs. 12724.1
Rs: 106180.60
Rs: 1061.80

Total
13.615%

Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to
75 cm long through stones at 1.50 m c / c over a backing of 45 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 15 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6

UNIT :
Unit

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble ) 30 to 45 cm long
Through stones 65 to 75 cm long
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

cum
cum
cum
cum
cum
Nos

15.30
15.30
15.30
9.00
57.60
44.00

Unit

Quantity

NIL

100 sqm
Amount
in Rs
560.00
8568.00
875.00
13387.50
1145.00
17518.50
360.00
3240.00
330.00
19008.00
59.00
2596.00
Rs:
64318.00

Rate
in Rs.

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
143.30
Add contractor's profit and overhead charges
13.615% 19.50
labour component/unit qty (including contractor's profit)
162.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-6-9

400.00
370.00
310.00
Rs:

Amount
in Rs
400.00
3700.00
10230.00
14330.00

Rate
in Rs.
1.00
10.00
33.00

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Rs:
64318.00
Rs:
0.00
Rs:
14330.00
Rs:
78648.00
Rs. 10707.93
Rs: 89355.93
Rs: 893.60

Total
13.615%

Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to 75
cm long through stones at 1.50 m c / c over a backing of 60 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 20 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble ) 30 to 45 cm long
Through stones 65 to 75 cm long
Total cost of Materials

B. MACHINERY:
Sl No Description
1

NIL

UNIT :
Unit

Quantity

cum
cum
cum
cum
cum
Nos

Unit

100 sqm
Amount
in Rs
560.00
11424.00
875.00
17850.00
1145.00
23358.00
360.00
3240.00
330.00
19008.00
59.00
2596.00
Rs:
77476.00

Rate
in Rs.
20.40
20.40
20.40
9.00
57.60
44.00

Quantity

Rate
in Rs.
0.00

0.00

Amount
in Rs
0.00

101

Dam and Allied Works - Item Unit Rates 2015-16

0.00
Total hire charges of Machinery
C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
161.90
Add contractor's profit and overhead charges
13.615% 22.00
labour component/unit qty (including contractor's profit)
183.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-6-10

400.00
370.00
310.00
Rs:

Amount
in Rs
400.00
3700.00
12090.00
16190.00

Rs:
77476.00
Rs:
0.00
Rs:
16190.00
Rs:
93666.00
Rs. 12752.63
Rs: 106418.63
Rs: 1064.20

Total
13.615%

Providing and constructing 60 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

cum
cum
cum
cum
cum

100 sqm.
Amount
in Rs
560.00
8568.00
875.00
13387.50
1145.00
17518.50
360.00
3240.00
330.00
19800.00
Rs:
62514.00

Rate
in Rs.
15.30
15.30
15.30
9.00
60.00

Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

1.00
5.00
28.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 sqm.
Rate per
sqm.
(A+B+C+D)/100

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

400.00
370.00
310.00
Rs:

Amount
in Rs
400.00
1850.00
8680.00
10930.00

Rate
in Rs.

Total cost of Labour


labour component/unit qty
109.30
Add contractor's profit and overhead charges
13.615% 14.90
labour component/unit qty (including contractor's profit)
124.20

IRR-DAW-6-11

0.00
0.00

Rate
in Rs.
1.00
10.00
39.00

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

0.00
Rs:

Rs:
62514.00
Rs:
0.00
Rs:
10930.00
Rs:
73444.00
Rs. 9999.4
Rs: 83443.40
Rs: 834.40

Total
13.615%

Providing and constructing 75 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour,
laying to required slopes, wedging with stone chips, etc., complete with initial lead upto 50 m
and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

UNIT :
Unit

Quantity

Rate

100 sqm
Amount

102

Dam and Allied Works - Item Unit Rates 2015-16

in Rs.
1
2
3
4
5

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )

cum
cum
cum
cum
cum
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Unit

15.30
15.30
15.30
11.00
75.00

Quantity

NIL

560.00
875.00
1145.00
360.00
330.00
Rs:

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
119.20
Add contractor's profit and overhead charges
13.615% 16.20
labour component/unit qty (including contractor's profit)
135.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

IRR-DAW-6-12

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

400.00
370.00
310.00
Rs:

Amount
in Rs
400.00
2220.00
9300.00
11920.00

Rate
in Rs.
1.00
6.00
30.00

in Rs
8568.00
13387.50
17518.50
3960.00
24750.00
68184.00

Rs:
68184.00
Rs:
0.00
Rs:
11920.00
Rs:
80104.00
Rs. 10906.16
Rs: 91010.16
Rs: 910.10

Total
13.615%

Providing and constructing 90 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )

B. MACHINERY:
Sl No Description
1

Quantity

cum
cum
cum
cum
cum
Total cost of Materials

Unit

15.30
15.30
15.30
13.50
90.00

Quantity

NIL

100 sqm
Amount
in Rs
560.00
8568.00
875.00
13387.50
1145.00
17518.50
360.00
4860.00
330.00
29700.00
Rs:
74034.00

Rate
in Rs.

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

work inspector
Mason Class-II
mazdoor

Unit
Day
Day
Day

Quantity

400.00
370.00
310.00
Rs:

Amount
in Rs
400.00
2960.00
10540.00
13900.00

Rate
in Rs.
1.00
8.00
34.00

Total cost of Labour


labour component/unit qty
139.00
Add contractor's profit and overhead charges
13.615% 18.90
labour component/unit qty (including contractor's profit)
157.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Total
13.615%

Rs:
74034.00
Rs:
0.00
Rs:
13900.00
Rs:
87934.00
Rs. 11972.21
Rs: 99906.21
Rs: 999.10

103

Dam and Allied Works - Item Unit Rates 2015-16

IRR-DAW-6-13

Providing and laying Hariyala or other approved quality turfing sods for the slopes of earthen
embankments over 20 mm thick sand backing including cost of all materials, machinery,
labour including preparing surface, spreading sand, watering for 15 days etc., complete with
initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2

UNIT :
Unit

Sand for filling


Hariyala turfing sods
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

cum
sqm

Unit

Rate
in Rs.
2.00
100.00

Quantity

NIL

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description

Unit

1
2

Cartman with double bullock cart


Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
55.00
Add contractor's profit and overhead charges
13.615% 7.50
labour component/unit qty (including contractor's profit)
62.50

Quantity

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

425.00
310.00
Rs:

Amount
in Rs
850.00
4650.00
5500.00

Rate
in Rs.
2.00
15.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
2.00
cum @
Total cost for
100.00 sqm.
Rate per
sqm.
(A+B+C+D)/100

100 sqm.
Amount
in Rs
560.00
1120.00
28.00
2800.00
Rs:
3920.00

Total
13.615%
31.3 Rs./Cum

Rs:
3920.00
Rs:
0.00
Rs:
5500.00
Rs:
9420.00
Rs. 1282.53
62.6
Rs: 10765.13
Rs: 107.70

104

Tunnel and Allied Works - Item Unit Rates 2015-16

Chapter - II
TUNNEL AND ALLIED WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :2015-16
Index- code
TUNNEL AND ALLIED WORKS - DATA RATES
IRR-TAW

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing the estimate.
(i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total lead involved
and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be
allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate and
hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km /cum
Rs.
208.60
Less 1 km initial lead charges /cum
Rs.
31.30 (-)
Net additional lead charges / cum
Rs.
177.30

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added
as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic
rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km /cum
Rs.
208.60
Less 1 km initial lead charges /cum
Rs.
31.30 (-)
Net additional lead charges / cum
Rs.
177.30
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
TAW -Work Items
IRR-TAW-1

EXCAVATION :

IRR-TAW-1-1 Excavation for adit by tunnelling methods in all types of rock including cost of all materials,
machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and
hauling the excavated muck outside adit upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1km and all lifts.

105

Tunnel and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Small dia explosive


Delay detonators
Electric detonators
Detonating fuse coil
Use rate of drill rod 2.5 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9

Description

Unit

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 1 x 6.5 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
14

UNIT :

Description

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for ventilation fans
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting
Hammerman
work inspector 1 in each shift

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day

Quantity

38.50 cum

40.00
54.00
5.00
50.00
119.00

70.00
23.00
13.00
11.00
42.67

20.00
20.00
2.00

5.78
5.78
20.00
Rs:

Amount
in Rs.
2800.00
1242.00
65.00
550.00
5077.33
507.73
115.63
115.63
40.00
10513.32

Rate
in Rs.
368.40
43.90
138.80
962.30
19.80
0.00
12.70
0.00
822.80
267.90
580.70
409.60
6.70
77.00
11.50
154.00
20.00
Rs:

Amount
in Rs.
2947.20
351.20
694.00
4811.50
396.00
0.00
254.00
0.00
5348.20
1741.35
3774.55
2662.40
33.50
385.00
11.50
154.00
40.00
23604.40

Rate
in Rs.
163.30
163.30
306.20
163.30
212.20
77.70
26.80
590.00
480.00
415.00
480.00
370.00
370.00
400.00

Amount
in Rs.
1306.40
816.50
6124.00
1061.45
1379.30
388.50
26.80
295.00
480.00
830.00
480.00
740.00
740.00
1200.00

Quantity
8.00
8.00
5.00
5.00
20.00
20.00
20.00
20.00
6.50
6.50
6.50
6.50
5.00
5.00
1.00
1.00
2.00

Quantity
8.00
5.00
20.00
6.50
6.50
5.00
1.00
0.50
1.00
2.00
1.00
2.00
2.00
3.00

Rate
in Rs.

106

Tunnel and Allied Works - Item Unit Rates 2015-16

15
16

Khalasi for mucking shift 4 Nos


mazdoor
for mucking shift 4 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Day

4.00

415.00

1660.00

Day
Day
Day

4.00
2.00
2.00

310.00
310.00
310.00
Rs:

1240.00
620.00
620.00
20007.95

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

10513.32
23604.40
20007.95
54125.67
541.26
2435.66
866.01
1353.14
59321.73

Rs:
Rs:
Rs:

8076.65
67398.38
1750.60

519.70
13.615% 70.80
590.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
38.50 cum
Rate per cum
(A+B+C+D)/38.50

IRR-TAW-1-2 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of all
materials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting,
drainage, removing and hauling excavated muck outside shaft upto specified dump area and
all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10

Particulars

Unit

Small dia explosive


Electric detonator
Detonating fuse coil
Use rate of drill rod 1.6 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Use rate of rail track
Use rate of mucking bucket
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Rm
Rm
10%
Hour
Hour
Shift
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Unit

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Jack hammer ( 4 x 4 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Pump 20 hp electric
Fuel / Energy charges
Winch 35 hp electric
Fuel / Energy charges
Tipping tub 1.5 cum
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2

UNIT :

Description

Crew for Air compressor


Crew for Jack hammer

Unit
Hour
Hour

Quantity

30.00 cum

32.00
65.00
50.00
95.00

70.00
13.00
11.00
27.67

18.00
16.00
3.00
24.00
2.00

23.13
23.13
130.01
22.20
20.00
Rs:

Amount
in Rs.
2240.00
845.00
550.00
2628.33
262.83
416.25
370.00
390.04
532.68
40.00
8275.14

Rate
in Rs.
138.80
962.30
19.80
0.00
6.70
77.00
12.30
154.00
129.40
188.60
64.20
0.00
20.00
Rs:

Amount
in Rs.
624.60
4330.35
316.80
0.00
26.80
308.00
24.60
308.00
3623.20
5280.80
1540.80
0.00
40.00
16423.95

Rate
in Rs.
163.30
306.20

Amount
in Rs.
734.85
4899.20

Quantity
4.50
4.50
16.00
16.00
4.00
4.00
2.00
2.00
28.00
28.00
24.00
24.00
2.00

Quantity
4.50
16.00

Rate
in Rs.

107

Tunnel and Allied Works - Item Unit Rates 2015-16

3
4
5
6
7
8
9
10
11
12
13
14

Crew for Pump 10 hp


Hour
4.00
Crew for Pump 20 hp
Hour
2.00
Crew for Winch
Hour
28.00
Surveyor
Day
0.50
Foreman
Day
4.00
Fitter / Mechanic
Day
2.00
Blaster ( Licensed )
Day
1.00
Helper blasting
Day
2.00
Hammerman 1 No. in each shift
Day
3.00
work inspector 1 in each shift
Day
4.00
Khalasi for mucking 2 Nos in each shift
Day
6.00
mazdoor
for mucking 8 Nos in each shift
Day
24.00
for other 2 shifts 1 No / shift
Day
2.00
for cleaning & miscellaneous
Day
2.00
Total cost of Labour
labour component/unit qty
1036.70
Add contractor's profit and overhead charges
13.615% 141.10
labour component/unit qty (including contractor's profit)
1177.80

77.70
77.70
244.90
590.00
480.00
415.00
480.00
370.00
370.00
400.00
415.00

310.80
155.40
6857.20
295.00
1920.00
830.00
480.00
740.00
1110.00
1600.00
2490.00

310.00
310.00
310.00
Rs:

7440.00
620.00
620.00
31102.45

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

8275.14
16423.95
31102.45
55801.54
558.02
2511.07
892.82
1395.04
61158.48

Rs:
Rs:
Rs:

8326.73
69485.21
2316.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
30.00 cum
Rate per cum
(A+B+C+D)/30.0

IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring supports including cost
of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation,
lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.
DATA:

Size of tunnel assumed ( finished section )


Shape of tunnel assumed for excavation
Height of tunnel assumed ( finished section )
Length of tunnel assumed
Thickness of CC lining
Pay-line margin assumed
Diameter of tunnel upto pay line for excavation
Distance of dump yard from face
Haulage of excavated muck

DATA:

:
:
:
:
:
:
:
:within
:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Small dia explosive


Delay detonators
Electric detonators
Detonating fuse coil

4.50 m dia
D - shape
4.50
1000
0.30
0.20
5.50
500
By dumpers

UNIT :
Unit
kg
Nos
Nos
Rm

Quantity
54.00
68.00
10.00
50.00

m
m
m
m
m
m

48.60 cum
Rate
in Rs.
70.00
23.00
13.00
11.00

Amount
in Rs.
3780.00
1564.00
130.00
550.00

108

Tunnel and Allied Works - Item Unit Rates 2015-16

5
6
7
8

Use rate of drill rod 2.5 m long


Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9

Rm
10%
Hour
Hour
LS

Description

Unit

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 6.5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for ventilation fans
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting
Hammerman
work inspector 1 in each shift
Khalasi for mucking shift 4 Nos
mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

150.00

42.67

24.00
24.00
2.00

5.78
5.78
20.00
Rs:

6400.00
640.00
138.75
138.75
40.00
13381.50

Rate
in Rs.
368.40
43.90
138.80
962.30
19.80
0.00
12.70
0.00
822.80
267.90
580.70
409.60
6.70
77.00
11.50
154.00
20.00
Rs:

Amount
in Rs.
3684.00
439.00
902.20
6254.95
514.80
0.00
330.20
0.00
4936.80
1607.40
6968.40
4915.20
43.55
500.50
23.00
308.00
40.00
31468.00

Rate
in Rs.
163.30
163.30
306.20
163.30
212.20
77.70
26.80
590.00
480.00
415.00
480.00
370.00
370.00
400.00
415.00

Amount
in Rs.
1633.00
1061.45
7961.20
979.80
2546.40
505.05
53.60
295.00
480.00
830.00
480.00
740.00
740.00
1200.00
1660.00

310.00
310.00
310.00
Rs:

2480.00
620.00
620.00
24885.50

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

13381.50
31468.00
24885.50
69735.00
697.35
3138.08
1115.76
1743.38
76429.56

Rs:
Rs:
Rs:

10405.88
86835.44
1786.70

Quantity
10.00
10.00
6.50
6.50
26.00
26.00
26.00
26.00
6.00
6.00
12.00
12.00
6.50
6.50
2.00
2.00
2.00

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
Day

10.00
6.50
26.00
6.00
12.00
6.50
2.00
0.50
1.00
2.00
1.00
2.00
2.00
3.00
4.00

Day
Day
Day

8.00
2.00
2.00

512.00
13.615% 69.70
581.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
48.60 cum
Rate per cum
(A+B+C+D)/48.60

109

Tunnel and Allied Works - Item Unit Rates 2015-16

IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports in all types of
soil / rock strata requiring supports ( excluding cost of providing supports ) including cost of
all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage,
removing and hauling the excavated muck outside tunnel upto specified dump area and all
other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Small dia explosive


Delay detonators
Electric detonators
Detonating fuse coil
Use rate of drill rod 2.5 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9

Description

Unit

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 6 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

UNIT :

Description

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for ventilation fans
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting
Hammerman 2 Nos
work inspector 1 in each shift
Khalasi for mucking shift 4 Nos
mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges

Unit

Quantity

46.00 cum

41.00
77.00
10.00
50.00
144.00

70.00
23.00
13.00
11.00
42.67

24.00
24.00
2.00

5.78
5.78
20.00
Rs:

Amount
in Rs.
2870.00
1771.00
130.00
550.00
6144.00
614.40
138.75
138.75
40.00
12396.90

Rate
in Rs.
368.40
43.90
138.80
962.30
19.80
0.00
12.70
0.00
822.80
267.90
580.70
409.60
6.70
77.00
11.50
154.00
20.00
Rs:

Amount
in Rs.
4052.40
482.90
832.80
5773.80
475.20
0.00
304.80
0.00
4936.80
1607.40
6968.40
4915.20
40.20
462.00
23.00
308.00
40.00
31222.90

Rate
in Rs.
163.30
163.30
306.20
163.30
212.20
77.70
26.80
590.00
480.00
415.00
480.00
370.00
370.00
400.00
415.00

Amount
in Rs.
1796.30
979.80
7348.80
979.80
2546.40
466.20
53.60
295.00
480.00
830.00
480.00
740.00
740.00
1200.00
1660.00

310.00
310.00
310.00
Rs:

2480.00
620.00
620.00
24315.90

Quantity
11.00
11.00
6.00
6.00
24.00
24.00
24.00
24.00
6.00
6.00
12.00
12.00
6.00
6.00
2.00
2.00
2.00

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
Day

11.00
6.00
24.00
6.00
12.00
6.00
2.00
0.50
1.00
2.00
1.00
2.00
2.00
3.00
4.00

Day
Day
Day

8.00
2.00
2.00

Rate
in Rs.

528.60
13.615% 72.00

110

Tunnel and Allied Works - Item Unit Rates 2015-16

labour component/unit qty (including contractor's profit)

600.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
46.00 cum
Rate per cum
(A+B+C+D)/46.0

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

12396.90
31222.90
24315.90
67935.70
679.36
3057.11
1086.97
1698.39
74457.53

Rs:
Rs:
Rs:

10137.39
84594.92
1839.00

IRR-TAW-1-5 Excavation for tunnel by heading and benching tunnelling methods including excavation
for supports in all types of soil / rock strata requiring supports ( excluding cost of providing
supports ) for roof before benching including cost of all other materials, machinery, labour,
scaling excavated surface, ventilation, lighting, drainage removing and hauling excavated muck
outside tunnel upto specified dump area and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Small dia explosive


Delay detonators
Electric detonator
Detonating fuse coil
Use rate of drill rod 2.5 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

UNIT :

Description

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 6.5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6.5 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity

50.00 cum

44.00
84.00
10.00
50.00
157.00

70.00
23.00
13.00
11.00
42.67

26.00
26.00
2.00

5.78
5.78
20.00
Rs:

Amount
in Rs.
3080.00
1932.00
130.00
550.00
6698.67
669.87
150.31
150.31
40.00
13401.16

Rate
in Rs.
368.40
43.90
138.80
962.30
19.80
0.00
12.70
0.00
822.80
267.90
580.70
409.60
6.70
77.00

Amount
in Rs.
4420.80
526.80
902.20
6254.95
514.80
0.00
330.20
0.00
5348.20
1741.35
7549.10
5324.80
43.55
500.50

Quantity
12.00
12.00
6.50
6.50
26.00
26.00
26.00
26.00
6.50
6.50
13.00
13.00
6.50
6.50

Rate
in Rs.

111

Tunnel and Allied Works - Item Unit Rates 2015-16

8
9

Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for Ventilation fan
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting
Hammerman 2 Nos
work inspector 1 in each shift
Khalasi
for pushing muck in heading portion
for mucking shift 4 Nos
16
mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning &miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Hour
Hour
LS

Unit

3.00
3.00
2.00

Quantity

11.50
154.00
20.00
Rs:

34.50
462.00
40.00
33993.75

Amount
in Rs.
1959.60
1061.45
7961.20
1061.45
2758.60
505.05
80.40
295.00
480.00
830.00
960.00
1480.00
740.00
1200.00

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day

12.00
6.50
26.00
6.50
13.00
6.50
3.00
0.50
1.00
2.00
2.00
4.00
2.00
3.00

Rate
in Rs.
163.30
163.30
306.20
163.30
212.20
77.70
26.80
590.00
480.00
415.00
480.00
370.00
370.00
400.00

Day
Day

4.00
4.00

415.00
415.00

1660.00
1660.00

Day
Day
Day

8.00
2.00
2.00

310.00
310.00
310.00
Rs:

2480.00
620.00
620.00
28412.75

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

13401.16
33993.75
28412.75
75807.66
758.08
3411.34
1212.92
1895.19
83085.19

Rs:
Rs:
Rs:

11312.05
94397.24
1887.90

568.30
13.615% 77.40
645.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
50.00 cum
Rate per cum
(A+B+C+D)/50.0

NOTE: Where mucking is to be carried out through shaft using winch and mucking tub system
increase the basic rates for items IRR-TAW-1-3, IRR-TAW-1-4 & IRR-TAW-1-5 by 8 percent.

IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geological faults
etc., out of tunnel including breaking large fragments by blasting if necessary and disposing off
the same in specified dump area or as directed including cost of all materials, machinery,
labour, ventilation, drainage, lighting and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

Particulars

Use rate of drill rod


Reconditioning charges @
Explosive small dia.
Detonator ( ele )
Detonating fuse coil
Use rate of air hose

UNIT :
Unit
Rm
10%
kg
Nos.
Rm
Hour

Quantity

100.00 cum
Rate
in Rs.

15.00

27.67

8.00
30.00
20.00
4.00

70.00
13.00
11.00
5.78

Amount
in Rs.
415.00
41.50
560.00
390.00
220.00
23.13

112

Tunnel and Allied Works - Item Unit Rates 2015-16

6
7

Use rate of water hose


Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4
5
6

Hour
LS

Description

Unit

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper 4.5 cum
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8

Crew for Air compressor


Crew for Jack hammer
Crew for Pump
Crew for Convey mucker
Crew for Dumper
Blaster ( Licensed )
Helper blasting
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit
Hour
Hour
Hour
Hour
Hour
Day
Day
Day

4.00
1.00

Quantity
1.00
1.00
4.00
4.00
1.00
1.00
6.00
6.00
12.00
12.00
1.00

Quantity
1.00
4.00
1.00
6.00
12.00
0.50
0.50
8.00

5.78
20.00
Rs:

23.13
20.00
1692.75

Rate
in Rs.
138.80
962.30
19.80
0.00
6.70
77.00
822.80
267.90
580.70
409.60
20.00
Rs:

Amount
in Rs.
138.80
962.30
79.20
0.00
6.70
77.00
4936.80
1607.40
6968.40
4915.20
20.00
19711.80

Rate
in Rs.
163.30
306.20
77.70
163.30
212.20
480.00
370.00
310.00
Rs:

Amount
in Rs.
163.30
1224.80
77.70
979.80
2546.40
240.00
185.00
2480.00
7897.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1692.75
19711.80
7897.00
29301.55
293.02
1318.57
468.82
732.54
32114.50

Rs:
Rs:
Rs:

4372.39
36486.89
364.90

79.00
13.615% 10.80
89.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
100.00 cum
Rate per cum
(A+B+C+D)/100.0
IRR_TAW-2 DEWATERING & GUNITING WORKS :

IRR-TAW-2-1 Dewatering tunnel by pumping out water collected by natural drainage inside tunnel including
providing sump wherever necessary, cost of all materials, machinery, labour, drainage, lighting,
ventilation and all other ancillary operations etc., complete.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Unit

Use rate of G.I.pipe 100 mm dia


Sundries
Total cost of Materials

Hour
LS

B. MACHINERY:
Sl No
1
2

UNIT :

Description

Electric pump 20 hp
Fuel / Energy charges

Unit
Hour
Hour

Quantity

15.00 Kwhr
Rate
in Rs.
4.67
20.00
Rs:

Amount
in Rs.
4.67
2.00
6.67

12.30
154.00

Amount
in Rs.
12.30
154.00

1.00
0.10

Quantity
1.00
1.00

Rate
in Rs.

113

Tunnel and Allied Works - Item Unit Rates 2015-16

Sundries(Starter/Switches ete)
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

LS

Unit

0.10

Quantity

20.00
Rs:

2.00
168.30

77.70
20.00
310.00
Rs:

Amount
in Rs.
77.70
1.00
31.00
109.70

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

6.67
168.30
109.70
284.67
2.85
12.81
4.55
7.12
311.99

Rs:
Rs:
Rs:

42.48
354.47
23.60

Rate
in Rs.

1
2
3

Crew charges for Pump


Hour
1.00
Laying & dismantling pipe
LS
0.05
mazdoor
Day
0.10
Total cost of Labour
labour component/unit qty
7.30
Add contractor's profit and overhead charges
13.615% 1.00
labour component/unit qty (including contractor's profit)
8.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
15.00 Kwhr
Rate per Kwhr
(A+B+C+D)/15.0

IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar 1 : 3 proportion
by weight including cost of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement
Sand (Screened)
Use rate of grout hose 20 m
Use rate of water hose 20 m
Use rate of guniting nozzle
Sundries
Total cost of Materials

kg
cum
Hour
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5

Description

Unit

Guniting equipment
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Crew for Guniting equipment


Crew for Air compressor
Crew for pump
Crew for Drilling jumbo
Mason Cl I
mazdoor

Unit
Hour
Hour
Hour
Hour
Day
Day

Quantity
600.00
1.10
8.00
8.00
8.00
2.00

Quantity
8.00
8.00
8.00
8.00
1.00
1.00
4.00
4.00
2.00

Quantity
8.00
8.00
1.00
4.00
1.00
6.00

36.00 sqm
Rate
in Rs.
6.30
760.00
5.78
5.78
3.50
20.00
Rs:

Amount
in Rs.
3780.00
836.00
46.25
46.25
28.00
40.00
4776.50

Rate
in Rs.
110.10
0.00
170.80
433.10
6.70
77.00
368.40
43.90
20.00
Rs:

Amount
in Rs.
880.80
0.00
1366.40
3464.80
6.70
77.00
1473.60
175.60
40.00
7484.90

Rate
in Rs.
204.10
153.10
77.70
163.30
415.00
310.00

Amount
in Rs.
1632.80
1224.80
77.70
653.20
415.00
1860.00

114

Tunnel and Allied Works - Item Unit Rates 2015-16

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rs:

5863.50

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

4776.50
7484.90
5863.50
18124.90
181.25
815.62
290.00
453.12
19864.89

13.615%
Rs:
cum @
31.3 Rs./Cum

2704.60
34.43

162.90
13.615% 22.20
185.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1 Km for FA
1.10
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per sqm

0.60

tonne @
36.00 sqm
(A+B+C+D)/36.0

129.7 Rs./Tonne
Rs:
Rs:

77.82
22681.75
630.00

IRR-TAW-2-3 Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing chain weld wire mesh
(new4 - 2011-12) 100 x 100x5 mm in between the two layers including cost and conveyance of all materials,

labour charges, all heads, lifts, centering, scaffolding, machine mixing,


laying concrete with shortcrete machine etc. complete as per specification and as
directed by Engineer-in-Charge

Data

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Cement
Sand (Screened)
Coarse aggregate 10-4.75 mm size
Use rate of grout hose 20 m
Use rate of water hose 20 m
Use rate of guniting nozzle
Welded steel wire fabric 100 x 100 x 5 mm
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4
5

Unit
kg
cum
cum
Hour
Hour
Hour
kg
LS

Description

Unit

Guniting equipment
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4
5
6

Particulars

UNIT :

Description

Crew for Guniting equipment


Crew for Air compressor
Crew for pump
Crew for Drilling jumbo
Mason Cl I
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges

Unit
Hour
Hour
Hour
Hour
Day
Day

Quantity
1548.00
2.41
1.03
8.00
8.00
8.00
108.00
2.00

Quantity
8.00
8.00
8.00
8.00
1.00
1.00
4.00
4.00
2.00

Quantity
8.00
8.00
1.00
4.00
1.00
6.00

36.00 sqm
Rate
in Rs.
6.30
760.00
875.00
5.78
5.78
3.50
165.00
20.00
Rs:

Amount
in Rs.
9752.40
1831.60
901.25
46.25
46.25
28.00
17820.00
40.00
30465.75

Rate
in Rs.
110.10
0.00
170.80
433.10
6.70
77.00
368.40
43.90
20.00
Rs:

Amount
in Rs.
880.80
0.00
1366.40
3464.80
6.70
77.00
1473.60
175.60
40.00
7484.90

Rate
in Rs.
204.10
153.10
77.70
163.30
415.00
310.00
Rs:

Amount
in Rs.
1632.80
1224.80
77.70
653.20
415.00
1860.00
5863.50

162.90
13.615% 22.20

115

Tunnel and Allied Works - Item Unit Rates 2015-16

labour component/unit qty (including contractor's profit)

185.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

30465.75
7484.90
5863.50
43814.15
438.14
1971.64
701.03
1095.35
48020.31

Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
13.615%
Rs:
Lead Charges for 1 Km for FA
2.41
cum @
31.3 Rs./Cum
Lead Charges for 1 Km for CA
1.03
cum @
30.2 Rs./Cum
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
1.55
tonne @ 129.7 Rs./Tonne
Total cost for
36.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/36.0
Rs:

6537.96
75.433
31.106
200.7756
54865.59
1524.00

IRR_TAW-3 TEMPORARY & PERMANENT SUPPORTS :


IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type
anchorage including drilling 35 mm dia holes, providing 15 cm long 20 mm thick steel tapered
wedge, 10 mm thick plate washers and nuts, tightening bolt by torque wrench, cost of all
materials, machinery, labour, ventilation, lighting, drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Particulars

Unit

Rein.Steel with 5 % wastage


Steel plate for washers
Steel plate for wedges
M S Nuts for bolts
Use rate of drill rod
Reconditioning charges @
Use rate of air hose 4 Nos
Use rate of water hose 4 Nos
Sundries ( gas for cutting / heating etc )
Total cost of Materials

kg
kg
kg
kg
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Unit

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries ( lathe, blower etc )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Crew for Air compressor


Crew for pump
Crew for Jack hammer
Crew for Drilling jumbo
Fitter
Gas cutter

Unit
Hour
Hour
Hour
Hour
Day
Day

Quantity

20.00 Rm

86.91
65.94
6.18
4.00
20.00

40.00
40.00
40.00
90.00
42.67

6.00
6.00
5.00

5.78
5.78
20.00
Rs:

Amount
in Rs.
3476.55
2637.60
247.28
360.00
853.33
85.33
34.69
34.69
100.00
7829.47

Rate
in Rs.
138.80
962.30
6.70
77.00
19.80
0.00
12.70
0.00
368.40
43.90
20.00
Rs:

Amount
in Rs.
208.20
1443.45
6.70
77.00
118.80
0.00
76.20
0.00
1473.60
175.60
100.00
3679.55

Rate
in Rs.
163.30
77.70
306.20
163.30
415.00
415.00

Amount
in Rs.
244.95
77.70
1837.20
653.20
207.50
415.00

Quantity
1.50
1.50
1.00
1.00
6.00
6.00
6.00
6.00
4.00
4.00
5.00

Quantity
1.50
1.00
6.00
4.00
0.50
1.00

Rate
in Rs.

116

Tunnel and Allied Works - Item Unit Rates 2015-16

7
8
9
10
11

Turner
Blacksmith
Khalasi ( 2 x 0.5 )
Hammerman
mazdoor

Day
Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1.00
1.00
1.00
0.50
2.00

480.00
415.00
415.00
370.00
310.00
Rs:

480.00
415.00
415.00
185.00
620.00
5550.55

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

7829.47
3679.55
5550.55
17059.57
170.60
767.68
272.95
426.49
18697.29

277.50
13.615% 37.80
315.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%

Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
13.615%
Rs:
2545.64
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges)
0.16
tonne @ 151.5 Rs./Tonne 24.09389719
Total cost for
20.00 Rm
Rs:
21267.01
Rate per Rm
(A+B+C+D)/20.0
Rs:
1063.40

IRR-TAW-3-2 Providing and fixing 25 mm diameter steel rock bolts with resin bond cement capsule
anchorage including drilling 35 mm dia holes, inserting grout capsule, driving bolt,fixing 10 mm
thick plate washers and nuts and tightening the same by torque wrench after hardening of
cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and other
ancillary operations etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Rein.Steel with 5 % wastage


Steel plate for washers
Resin bond cement grout capsule
M S Nuts for bolts
Use rate of drill rod
Reconditioning charges @
Use rate of air hose 4 Nos
Use rate of water hose 4 Nos
Sundries(gas for cutting etc)
Total cost of Materials

kg
kg
Nos.
kg
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Unit

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries ( lathe, etc )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1

UNIT :

Description

Crew for Air compressor

Unit
Hour

Quantity

20.00 Rm

86.91
65.94
2.00
4.00
20.00

40.00
40.00
40.00
90.00
42.67

6.00
6.00
3.00

5.78
5.78
20.00
Rs:

Amount
in Rs.
3476.55
2637.60
80.00
360.00
853.33
85.33
34.69
34.69
60.00
7622.19

Rate
in Rs.
138.80
962.30
6.70
77.00
19.80
0.00
12.70
0.00
368.40
43.90
20.00
Rs:

Amount
in Rs.
208.20
1443.45
6.70
77.00
118.80
0.00
76.20
0.00
1473.60
175.60
60.00
3639.55

Rate
in Rs.
163.30

Amount
in Rs.
244.95

Quantity
1.50
1.50
1.00
1.00
6.00
6.00
6.00
6.00
4.00
4.00
3.00

Quantity
1.50

Rate
in Rs.

117

Tunnel and Allied Works - Item Unit Rates 2015-16

2
3
4
5
6
7
8
9
10

Crew for pump


Hour
1.00
Crew for Jack hammer
Hour
6.00
Crew for Drilling jumbo
Hour
4.00
Fitter
Day
0.50
Gas cutter
Day
1.00
Turner
Day
1.00
Khalasi ( 2 x 0.5 )
Day
1.00
Hammerman
Day
0.50
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
255.70
Add contractor's profit and overhead charges
13.615% 34.80
labour component/unit qty (including contractor's profit)
290.50

77.70
306.20
163.30
370.00
415.00
480.00
415.00
370.00
310.00
Rs:

77.70
1837.20
653.20
185.00
415.00
480.00
415.00
185.00
620.00
5113.05

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

7622.19
3639.55
5113.05
16374.79
163.75
736.87
262.00
409.37
17946.77

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%

Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
13.615%
Rs:
2443.45
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges)
0.15
tonne @ 151.5 Rs./Tonne 23.15734313
Total cost for
20.00 Rm
Rs:
20413.38
Rate per Rm
(A+B+C+D)/20.0
Rs:
1020.70

IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel supports as per details
including cost of all materials, machinery, labour, cutting, bending, welding, grinding, lighting,
ventilation, drainage and all other ancillary operations etc., complete with initial lead upto
1 km and all lifts.

Data

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

5
6
7

Particulars

Unit

Structural steel beams


Structural steel plates
Steel bars for tie rods & anchors
For cutting sections:
Oxygen gas @ 2.4 cum / t
Acetylene gas @ 0.8 cum / t
For welding sections:
Electrodes 4 x 300 mm @ 125 Nos / t
For field connections:
M.S.Bolts / Nuts & Washers
Sundries
Total cost of Materials

kg
kg
kg

B. MACHINERY:
Sl No
1
2

UNIT :

Description

Bending machine
Fuel / Energy charges
Welding set

760.00
115.00
150.00

40.00
40.00
40.00

Amount
in Rs.
30400.00
4600.00
6000.00

cum
cum

2.40
0.80

45.00
330.00

108.00
264.00

Nos.

125.00

11.00

1375.00

kg
LS

50.00
5.00

90.00
20.00
Rs:

4500.00
100.00
47347.00

42.60
115.50
16.00

Amount
in Rs.
340.80
924.00
256.00

Unit
Hour
Hour
Hour

Quantity

1.00 tonne

Quantity
8.00
8.00
16.00

Rate
in Rs.

Rate
in Rs.

118

Tunnel and Allied Works - Item Unit Rates 2015-16

3
4

Fuel / Energy charges


Drilling Jumbo
Fuel / Energy charges
Sundries ( lathe / drilling / grinder )
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Hour
Hour
Hour
LS

Unit

16.00
12.00
12.00
30.00

Quantity

1
2
3

Crew for Drilling Jumbo


Hour
12.00
Crew fir Bending machine
Hour
8.00
For cutting & preparing sections:
Structural steel Marker
Day
1.00
Gas cutter
Day
2.00
Fitter
Day
2.00
Turner / Driller
Day
3.00
Khalasi
Day
2.00
Helper fabrication
Day
4.00
4
For welding sections:
Welder
Day
2.00
Helper fabrication
Day
2.00
Khalasi
Day
2.00
5
For erection of supports:
Foreman
Day
1.00
Structural steel Erector
Day
2.00
Helper erector
Day
2.00
Khalasi
Day
4.00
Total cost of Labour
labour component/unit qty
15069.60
Add contractor's profit and overhead charges
13.615% 2051.70
labour component/unit qty (including contractor's profit)
17121.30

92.40
368.40
43.90
20.00
Rs:

1478.40
4420.80
526.80
600.00
8546.80

Rate
in Rs.
163.30
122.50

Amount
in Rs.
1959.60
980.00

480.00
415.00
415.00
480.00
415.00
370.00

480.00
830.00
830.00
1440.00
830.00
1480.00

415.00
370.00
415.00

830.00
740.00
830.00

480.00
480.00
370.00
415.00
Rs:

480.00
960.00
740.00
1660.00
15069.60

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

47347.00
8546.80
15069.60
70963.40
709.63
3193.35
1135.41
1774.09
77775.89

Rs:

10589.19

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges)
1.03
Total cost for
Rate per tonne

13.615%
tonne @

151.5 Rs./Tonne

1.00 tonne
(A+B+C+D)/1.0

Rs:
Rs:

155.2875
88520.36
88520.40

IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel supports as per details
and dismantling the same before concreting including cost of all materials, machinery, labour,
cutting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillary
operations etc.,complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS (for 20 uses):
Sl No
Particulars
1
2
3
4

5
6

Structural steel beams


Structural steel plates
Tie rods & anchors
For cutting sections:
Oxygen gas @ 2.40 cum / t
Acetylene @ 0.8 cum / t
For welding sections:
Electrodes @ 125 Nos / t
For field connections:
M.S.Bolts / Nuts / Washers

UNIT :
Unit

760.00
115.00
150.00

40.00
40.00
40.00

Amount
in Rs.
30400.00
4600.00
6000.00

cum
cum

2.40
0.80

45.00
330.00

108.00
264.00

Nos.

125.00

11.00

1375.00

kg

50.00

90.00

4500.00

kg
kg
kg

Quantity

1.00 tonne
Rate
in Rs.

119

Tunnel and Allied Works - Item Unit Rates 2015-16

7
Sundries
Total cost of Materials for 20 uses of supports
Cost per use considering
B. MACHINERY (for fabrication):
Sl No
Description
1
2
3

Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Cost per use considering

B. MACHINERY (for erection and dismantling):


Sl No
Description
1
2

Drilling Jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR ( for fabrication ):


Sl No
Description
1
2

Crew for Bending machine


For cutting & preparing sections:
Structural steel Marker
Gas cutter
Fitter
Turner / Driller
Khalasi
Helper fabrication
For welding sections:
Welder
Helper fabrication
Khalasi
Total cost of Labour
Cost per use considering

C. LABOUR ( for erection ):


Sl No
Description

LS

20.00

20.00
Rs:
Rs:

400.00
47647.00
2382.35

42.60
115.50
16.00
92.40
20.00
Rs:
Rs:

Amount
in Rs.
340.80
924.00
256.00
1478.40
600.00
3599.20
179.96

Rate
in Rs.
368.40
43.90
20.00
Rs:

Amount
in Rs.
6631.20
790.20
200.00
7621.40

Amount
in Rs.
980.00

20 uses

Unit

Quantity

Hour
Hour
Hour
Hour
LS

Rate
in Rs.

8.00
8.00
16.00
16.00
30.00
20 uses

Unit

Quantity

Hour
Hour
LS

Unit

18.00
18.00
10.00

Quantity

Hour

8.00

Rate
in Rs.
122.50

Day
Day
Day
Day
Day
Day

1.00
2.00
2.00
3.00
2.00
4.00

480.00
415.00
415.00
480.00
415.00
370.00

480.00
830.00
830.00
1440.00
830.00
1480.00

Day
Day
Day

2.00
2.00
2.00

415.00
370.00
415.00
Rs:
Rs:

830.00
740.00
830.00
9270.00
463.50

Rate
in Rs.
163.30

Amount
in Rs.
1306.40

480.00
480.00
370.00
415.00

480.00
960.00
740.00
1660.00

480.00
480.00
370.00
415.00
Rs:

240.00
480.00
370.00
830.00
7066.40

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

2382.35
179.96
7621.40
463.50
7066.40
17713.61
177.14
797.11
283.42
442.84

20 uses

Unit

Quantity

1
2

Crew for Drilling jumbo


Hour
8.00
For erection of supports:
Foreman
Day
1.00
Structural steel Erector
Day
2.00
Helper erector
Day
2.00
Khalasi
Day
4.00
3
For dismantling of supports:
Foreman
Day
0.50
Structural steel Erector
Day
1.00
Helper erector
Day
1.00
Khalasi
Day
2.00
Total cost of Labour
labour component/unit qty
7529.90
Add contractor's profit and overhead charges
13.615% 1025.20
labour component/unit qty (including contractor's profit)
8555.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery for fabrication
C. Hire charges of Machinery for erection and dismantling
D. Cost of Labour for fabrication
E. Cost of Labour for erection and dismantling

Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%

120

Tunnel and Allied Works - Item Unit Rates 2015-16

Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges)
Total cost for
Rate per tonne

Rs:

19414.12

Rs:

2643.23

151.5 Rs./Tonne
Rs:
Rs:

155.2875
22212.64
22212.60

13.615%

1.03

tonne @
1.00 tonne
(A+B+C+D)/1.0

IRR-TAW-3-5 Providing and fixing hard variety cut jungle wood for lagging / blocking locations in tunnel
wherever required including cost of all materials, machinery, labour, fixing in position, lighting,
ventilation, drainage etc complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cut jungle wood


Sundries

UNIT :
Unit
cum
LS

Quantity
1.05
2.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Drilling jumbo
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

C. LABOUR:
Sl No

Description

Unit

Quantity
2.00
2.00

Quantity

1
2
3

Crew for Drilling jumbo


Hour
2.00
Carpenter Cl II
Day
1.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
1316.60
Add contractor's profit and overhead charges
13.615% 179.30
labour component/unit qty (including contractor's profit)
1495.90

1.00 cum
Rate
in Rs.
24600.00
20.00
Rs:

Amount
in Rs.
25830.00
40.00
25870.00

Rate
in Rs.
368.40
43.90
Rs:

Amount
in Rs.
736.80
87.80
824.60

Rate
in Rs.
163.30
370.00
310.00
Rs:

Amount
in Rs.
326.60
370.00
620.00
1316.60

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

25870.00
824.60
1316.60
28011.20
280.11
1260.50
448.18
700.28
30700.28

Rs:
Rs:
Rs:

4179.84
34880.12
34880.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
1.00 cum
Rate per cum
(A+B+C+D)/1.0

IRR_TAW-4 MASONRY WORKS :


IRR-TAW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones from
tunnel excavated muck in cement mortar 1 : 6 proportion for backfilling over cuts / slips on
tunnel sides due to geological faults etc., including cost of all materials, machinery, labour,
cleaning,scaffolding, packing mortar, wedging stone chips, curing, ventilation, lighting, drainage
complete with lead upto 1 km and all lifts.
(cement content : 95 kg/cum of masonry, Rubble stones : 0.83 cum, Stone chips : 0.13 cum,
FA : 0.40 cum)
DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

UNIT :
Unit

Quantity

10.00 cum
Rate
in Rs.

Amount
in Rs.

121

Tunnel and Allied Works - Item Unit Rates 2015-16

1
2
3
4

Cement
Rubble stones
Stone chips
Sand (Screened)

kg
cum
cum
cum

Add for scaffolding @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Unit

10 hp pump ( ele )
Fuel / energy charges
Total hire charges of Machinery

Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Crew for Pump


work inspector
Mason Class-I
Mason Class-II
mazdoor
for sorting out rubble in dump yard
for conveying rubble
for preparing mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

950.00
8.30
1.25
4.00
TOTAL
2.5%

Quantity

6.30
330.00
360.00
760.00
Rs:
Rs:
Rs:

Rate
in Rs.

1.00
1.00

Quantity

6.70
77.00
Rs:

Amount
in Rs.
6.70
77.00
83.70

Rate
in Rs.

Hour
Day
Day
Day

1.00
1.00
1.00
2.00

77.70
400.00
415.00
370.00

Amount
in Rs.
77.70
400.00
415.00
740.00

Day
Day
Day
Day
Day
Day
Day

1.00
2.00
2.00
1.00
4.00
1.00
3.00
TOTAL
15.0%

310.00
310.00
310.00
310.00
310.00
310.00
310.00
Rs:
Rs:
Rs:

310.00
620.00
620.00
310.00
1240.00
310.00
930.00
5972.70
895.91
6868.61

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

12519.35
83.70
6868.61
19471.66
194.72
876.22
311.55
486.79
21340.93

13.615%
Rs:
cum @
31.3 Rs./Cum
cum @
30.2 Rs./Cum

2905.57
125.2
288.41

686.86
13.615% 93.50
780.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1 Km for FA
4.00
Lead Charges for 1 Km for Stones and Stone Chips9.55
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per cum

5985.00
2739.00
450.00
3040.00
12214.00
305.35
12519.35

0.95

tonne @
10.00 cum
(A+B+C+D)/10.0

129.7 Rs./Tonne
Rs:
Rs:

123.215
24783.33
2478.30

IRR_TAW-5 REINFORCEMENT & CONCRETE WORKS :


IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RCC works
including cleaning, straightening, cutting, bending, hooking, lapping / welding joints wherever
required, tying with 1.25 mm dia.soft annealed steel wire, including cost of all materials, labour,
machinery, ventilation, lighting, drainage etc.,complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Rein.Steel with 5 % wastage

UNIT :
Unit
tonne

Quantity
1.05

1.00 tonne
Rate
in Rs.
40000.00

Amount
in Rs.
42000.00

122

Tunnel and Allied Works - Item Unit Rates 2015-16

2
3

Binding wire 1.25 mm dia


Sundries ( chairs / spacers etc )
Total cost of Materials

B. MACHINERY:
Sl No

Description

kg
LS

Unit

Nil

13.50
5.00

Quantity

70.00
20.00
Rs:

945.00
100.00
43045.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
490.00
310.00
Rs:

Amount
in Rs.
4410.00
4650.00
9060.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

43045.00
0.00
9060.00
52105.00
521.05
2344.73
833.68
1302.63
57107.08

Rate
in Rs.

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description

Bar bender
mazdoor

Unit
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
9.00
15.00

9060.00
13.615% 1233.50
10293.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Rs:
Lead Charges for 1Km for Steel (including
Loading and Unloading Charges)
1.05
tonne @ 151.5 Rs./Tonne
Total cost for
1.00 tonne
Rs:
Rate per tonne
(A+B+C+D)/1.0
Rs:

7775.13
159.075
65041.28
65041.30

IRR-TAW-5-2 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates crushed from tunnel excavated muck for filling and levelling over-cuts
in bed due to geological faults etc., including cost of all materials, machinery, labour, cleaning
bed, batching, mixing, conveying and laying, levelling, compacting, finishing, curing, lighting,
ventilation, drainage etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum,
Superplasticizer 0.4% by wt. of cement)
DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5

Particulars

Unit

Cement for mix


Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Sundries
Total cost of Materials

kg
cum
cum
cum
cum
kg
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Batching plant 2 x 1 cum


Fuel / Energy charges
Agitator car 2 cum
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
6160.00
12.60
7.56
5.04
11.20
24.64
2.00

Quantity
8.00
8.00
16.00
16.00
8.00
8.00

28.00 cum
Rate
in Rs.
6.30
1145.00
1210.00
875.00
560.00
95.00
20.00
Rs:

Amount
in Rs.
38808.00
14427.00
9147.60
4410.00
6272.00
2340.80
40.00
75445.40

Rate
in Rs.
405.40
346.40
758.40
893.90
6.70
77.00

Amount
in Rs.
3243.20
2771.20
12134.40
14302.40
53.60
616.00

123

Tunnel and Allied Works - Item Unit Rates 2015-16

4
5

Needle vibrator 40 mm dia


Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Hour
Hour
LS

Description

Unit

1
2
3
4
5
6
7

Crew for Batching plant


Crew for Agitator car
Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for cleaning bed
for loading material bin ( Cement )
for miscellaneous works at BP
for laying concrete
for conveying laying concrete
for cleaning bed
for washing CA / curing
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

8.00
8.00
2.00

8.00
7.70
20.00
Rs:

64.00
61.60
40.00
33286.40

Rate
in Rs.
318.20
265.20
77.70
146.90
415.00
400.00

Amount
in Rs.
2545.60
4243.20
621.60
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
310.00
310.00
Rs:

620.00
930.00
620.00
2170.00
4340.00
620.00
620.00
19320.60

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

75445.40
33286.40
19320.60
128052.40
1280.52
5762.36
2048.84
3201.31
140345.43

13.615%
Rs:
cum @
31.3 Rs./Cum
cum @
30.2 Rs./Cum

19108.03
350.56
761.04

Quantity

Hour
Hour
Hour
Hour
Day
Day

8.00
16.00
8.00
8.00
1.00
1.00

Day
Day
Day
Day
Day
Day
Day

2.00
3.00
2.00
7.00
14.00
2.00
2.00

690.00
13.615% 93.90
783.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1 Km for FA
11.20
Lead Charges for 1 Km for CA
25.20
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per cum

6.16

tonne @
28.00 cum
(A+B+C+D)/28.0

129.7 Rs./Tonne
Rs:
Rs:

798.952
161364.01
5763.00

IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for kerb and bed lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

4
5

Particulars

Cement 43 Gr
Cement for incidentals @ 1 kg / cum
Fine aggregate (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Super plasticiser
Use rate of shuttering for kerb / bed

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm

Quantity
9240.00
28.00
11.20
12.60
7.56
5.04
36.96
28.00

28.00 cum
Rate
in Rs.
6.30
6.30
560.00
1145.00
1210.00
875.00
95.00
155.53

Amount
in Rs.
58212.00
176.40
6272.00
14427.00
9147.60
4410.00
3511.20
4354.81

124

Tunnel and Allied Works - Item Unit Rates 2015-16

Sundries

LS

2.00

20.00
Rs:

40.00
100551.01

Rate
in Rs.
405.40
346.40
758.40
893.90
8.00
7.70
6.70
77.00
20.00
Rs:

Amount
in Rs.
3243.20
2771.20
12134.40
14302.40
64.00
61.60
53.60
616.00
100.00
33346.40

Rate
in Rs.
318.20
265.20
146.90
77.70

Amount
in Rs.
2545.60
4243.20
1175.20
621.60

370.00
310.00

740.00
1860.00

310.00

930.00

310.00

620.00

310.00

620.00

415.00
370.00
310.00
400.00
79.80
Rs:

830.00
740.00
6510.00
400.00
2234.40
24070.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

100551.01
33346.40
24070.00
157967.41
1579.67
7108.53
2527.48
3949.19
173132.28

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

Description

Batching plant 2 x 1.00 cum


Fuel / Energy charges
Agitator car 2 cum ( 2 Nos )
Fuel / Energy charges
Needle Vibrator
Fuel / Energy charges
Pump 10 hp ( Ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
8.00
8.00
16.00
16.00
8.00
8.00
8.00
8.00
5.00

Quantity

1
2
3
4
5

Crew for Batching plant


Hour
8.00
Crew for Agitator car
Hour
16.00
Crew for vibrator
Hour
8.00
Crew for pump
Hour
8.00
For scaling & cleaning bed
Hammerman
Day
2.00
mazdoor
Day
6.00
6
For loading cement to BP bin
mazdoor
Day
3.00
7
For miscellaneous work at BP
mazdoor
Day
2.00
8
For wetting C.A & curing
mazdoor
Day
2.00
9
Laying concrete for kerb/ invert
Mason Cl I
Day
2.00
Mason Cl II
Day
2.00
mazdoor
Day
21.00
work inspector
Day
1.00
10 Labour charges for shuttering
sqm
28.00
Total cost of Labour
labour component/unit qty
859.60
Add contractor's profit and overhead charges
13.615% 117.00
labour component/unit qty (including contractor's profit)
976.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%

Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
13.615%
Rs:
Lead Charges for 1 Km for FA
11.20
cum @
31.3 Rs./Cum
Lead Charges for 1 Km for CA
25.20
cum @
30.2 Rs./Cum
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
9.27
tonne @ 129.7 Rs./Tonne
Total cost for
28.00 cum
Rs:
Rate per cum
(A+B+C+D)/28.0
Rs:

23571.96
350.56
761.04
1202.0596
199017.90
7107.80

IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for sides and arch lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),

125

Tunnel and Allied Works - Item Unit Rates 2015-16

CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

4
5
6
7

Cement 43 Gr
Cement for incidentals @ 1 kg / cum
Fine aggregate (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Super plasticiser
Use rate of end shuttering
Use rate of steel gantry
Sundries ( placer pipe etc )
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Air compressor ( Ele ) 8.5 cmm


Fuel / Energy charges @ 75 % load
Batching plant 2 x 1.00 cum
Fuel / Energy charges
Agitator car 2 cum ( 2 Nos )
Fuel / Energy charges
Concrete placer pump
Fuel / Energy charges
Needle Vibrator / Shutter vibrator
Fuel / Energy charges
Pump 10 hp ( Ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7

Particulars

Description

Crew charges for Air compressor


Crew charges for Batching plant
Crew charges for Agitator car
Crew charges for placer pump
Crew charges for vibrator
Crew charges for Pump
For scaling & cleaning
Stone chiseller Cl II
mazdoor
For dismantling / Laying track
Surveyer
Fitter shuttering
Helper shuttering 2 x 0.5
Khalasi 6 x 0.5
mazdoor 2 x 0.5
For Moving / Positioning gantry
Surveyer
Foreman
Fitter shuttering

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
sqm
LS

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
15840.00
48.00
19.20
21.60
12.96
8.64
63.36
6.00
100.00
5.00

Quantity
16.00
12.00
12.00
12.00
32.00
32.00
16.00
16.00
8.00
8.00
8.00
8.00
5.00

Quantity

48.00 cum
Rate
in Rs.
6.30
6.30
560.00
1145.00
1210.00
875.00
95.00
155.53
79.80
20.00
Rs:

Amount
in Rs.
99792.00
302.40
10752.00
24732.00
15681.60
7560.00
6019.20
933.17
7980.00
100.00
173852.37

Rate
in Rs.
170.80
433.10
405.40
346.40
758.40
893.90
102.00
2.00
8.00
7.70
6.70
77.00
20.00
Rs:

Amount
in Rs.
2732.80
5197.20
4864.80
4156.80
24268.80
28604.80
1632.00
32.00
64.00
61.60
53.60
616.00
100.00
72384.40

Amount
in Rs.
2449.60
5091.20
8486.40
268.80
1175.20
621.60

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
32.00
16.00
8.00
8.00

Rate
in Rs.
153.10
318.20
265.20
16.80
146.90
77.70

Day
Day

0.50
1.00

370.00
310.00

185.00
310.00

Day
Day
Day
Day
Day

0.50
0.50
1.00
3.00
1.00

590.00
370.00
370.00
415.00
310.00

295.00
185.00
370.00
1245.00
310.00

Day
Day
Day

0.50
0.50
0.50

590.00
480.00
370.00

295.00
240.00
185.00

126

Tunnel and Allied Works - Item Unit Rates 2015-16

Helper shuttering 2 x 0.5


Day
1.00
Khalasi 6 x 0.5
Day
3.00
mazdoor 2 x 0.5
Day
1.00
10
For loading cement to BP bin
mazdoor
Day
5.00
11
For miscellaneous works of BP
mazdoor
Day
2.00
12
For Erection/Dismantling bulk head
sqm
6.00
13
For Laying concrete by placer
Masom Cl I
Day
3.00
mazdoor
Day
9.00
work inspector
Day
3.00
14
For wetting C.A / Curing etc
mazdoor
Day
3.00
Total cost of Labour
labour component/unit qty
676.10
Add contractor's profit and overhead charges
13.615% 92.10
labour component/unit qty (including contractor's profit)
768.20

370.00
415.00
310.00

370.00
1245.00
310.00

310.00

1550.00

310.00
79.80

620.00
478.80

415.00
310.00
400.00

1245.00
2790.00
1200.00

310.00
Rs:

930.00
32451.60

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

173852.37
72384.40
32451.60
278688.37
2786.88
12540.98
4459.01
6967.21
305442.46

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%

Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
13.615%
Rs:
Lead Charges for 1 Km for FA
19.20
cum @
31.3 Rs./Cum
Lead Charges for 1 Km for CA
43.20
cum @
30.2 Rs./Cum
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
15.89
tonne @ 129.7 Rs./Tonne
Total cost for
48.00 cum
Rs:
Rate per cum
(A+B+C+D)/48.0
Rs:
IRR-TAW-6

41585.99
600.96
1304.64
2060.6736
350994.72
7312.40

DRILLING & GROUTING WORKS :

IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jack
hammer or stooper drills as directed to specified depth for consolidation / contact grouting
including cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage
and all other ancillary operations etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

1
2
3
4
5
6

Particulars

Use rate of drill rod


Reconditioning charges @
Use rate of air hose 4 Nos
Use rate of water hose 4 Nos
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

UNIT :

Description

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries

Unit

Quantity

Rm

100.00 Rm
Rate
in Rs.

100.00

42.67

32.00
32.00
3.00

5.78
5.78
20.00
Rs:

Amount
in Rs.
4266.67
426.67
185.00
185.00
60.00
5123.33

Rate
in Rs.
138.80
962.30
6.70
77.00
19.80
0.00
12.70
0.00
368.40
43.90
20.00

Amount
in Rs.
1110.40
7698.40
26.80
308.00
633.60
0.00
406.40
0.00
2947.20
351.20
100.00

10%
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Quantity
8.00
8.00
4.00
4.00
32.00
32.00
32.00
32.00
8.00
8.00
5.00

127

Tunnel and Allied Works - Item Unit Rates 2015-16

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

1
2
3
4
5

Crew charges for Air compressor


Hour
8.00
Crew charges for Pump
Hour
4.00
Crew charges for Jack Hammer
Hour
32.00
Crew charges for Drilling Jumbo
Hour
8.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
133.40
Add contractor's profit and overhead charges
13.615% 18.20
labour component/unit qty (including contractor's profit)
151.60

Rs:

13582.00

Rate
in Rs.
163.30
77.70
306.20
163.30
310.00
Rs:

Amount
in Rs.
1306.40
310.80
9798.40
1306.40
620.00
13342.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

5123.33
13582.00
13342.00
32047.33
320.47
1442.13
512.76
801.18
35123.88

Rs:
Rs:
Rs:

4782.12
39905.99
399.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
100.00 Rm
Rate per Rm
(A+B+C+D)/100.0

IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for consolidation / contact
grouting including cost of all materials, machinery, labour, redrilling wherever necessary,
ventilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km
and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Cement
Use rate of grouting hose 50 m
Use rate of water hose 50 m
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

Description

Grouting machine
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

Particulars

Description

UNIT :
Unit
tonne
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
1.50
8.00
8.00
2.00

Quantity
8.00
8.00
2.00
2.00
2.00
2.00
2.00

Quantity

Crew for Grout pump


Hour
8.00
Crew for pump
Hour
2.00
Crew for Drilling jumbo
Hour
2.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
2040.80
Add contractor's profit and overhead charges
13.615% 277.90
labour component/unit qty (including contractor's profit)
2318.70

1.50 tonne
Rate
in Rs.
6300.00
11.56
11.56
20.00
Rs:

Amount
in Rs.
9450.00
92.50
92.50
40.00
9675.00

Rate
in Rs.
24.90
38.50
6.70
77.00
368.40
43.90
20.00
Rs:

Amount
in Rs.
199.20
308.00
13.40
154.00
736.80
87.80
40.00
1539.20

Rate
in Rs.
244.90
77.70
163.30
310.00
Rs:

Amount
in Rs.
1959.20
155.40
326.60
620.00
3061.20

128

Tunnel and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

9675.00
1539.20
3061.20
14275.40
142.75
642.39
228.41
356.89
15645.84

Rs:

2130.18

129.7 Rs./Tonne
Rs:
Rs:

194.55
17970.57
11980.40

Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per tonne

13.615%

1.50

tonne @
1.50 tonne
(A+B+C+D)/1.50

IRR-TAW-6-3 Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel by
percussion drilling using waggon drill or other suitable drilling equipment including cost of all
materials, machinery, labour, ventilation, lighting, drainage etc., complete.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Use rate of cross bit 75 mm dia


Use rate of air hose 20 m
Use rate of water hose 20 m
Use rate of extension rods
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

Particulars

Description

Waggon drill
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

UNIT :
Unit
Rm
Hour
Hour
Rm

Unit
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
120.00
16.00
16.00
120.00

Quantity
16.00
16.00
8.00
8.00
6.00
6.00
2.00

Quantity

1
2
3
4

Crew for Waggon drill


Hour
16.00
Crew for Air compressor
Hour
8.00
Crew for Pump
Hour
6.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
55.30
Add contractor's profit and overhead charges
13.615% 7.50
labour component/unit qty (including contractor's profit)
62.80

120.00 Rm
Rate
in Rs.
125.00
4.63
4.63
8.90
Rs:

Amount
in Rs.
15000.00
74.00
74.00
1068.48
16216.48

Rate
in Rs.
188.50
0.00
138.80
962.30
6.70
77.00
20.00
Rs:

Amount
in Rs.
3016.00
0.00
1110.40
7698.40
40.20
462.00
40.00
12367.00

Rate
in Rs.
265.20
163.30
77.70
310.00
Rs:

Amount
in Rs.
4243.20
1306.40
466.20
620.00
6635.80

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

16216.48
12367.00
6635.80
35219.28
352.19
1584.87
563.51
880.48
38600.33

Rs:
Rs:

5255.44
43855.77

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
13.615%
Total cost for
120.00 Rm

129

Tunnel and Allied Works - Item Unit Rates 2015-16

Rate per Rm

(A+B+C+D)/120.0

Rs:

365.50

130

Canal and Allied Works - Item Unit Rates 2015-16

Chapter III
CANAL AND ALLIED WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR : 2015-16
Index- code
IRR-CAW

CANAL AND ALLIED WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing
the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total
lead involved and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and
unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate
and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges for 5 km
Rs.
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km /cum
Rs.
208.60
Less 1 km initial lead charges /cum
Rs.
31.30 (-)
Net additional lead charges / cum
Rs.
177.30

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges for 5 km
Rs.
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km /cum
Rs.
208.60
Less 1 km initial lead charges /cum
Rs.
31.30 (-)
Net additional lead charges / cum
Rs.
177.30
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
CAW-Work Items
IRR-CAW-1

EXCAVATION WORKS :

IRR-CAW-1-1

Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated soil
neatly in dump area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts.

131

Canal and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
893.90
446.70
307.20
Rs:

Amount
in Rs.
13652.80
7151.20
21441.60
14745.60
56991.20

Rate
in Rs.
221.00
165.80
400.00
310.00
Rs:

Amount
in Rs.
1768.00
7958.40
400.00
9300.00
19426.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

Rs:
Rs:
Rs:
Rs:

0.00
56991.20
19426.40
76417.60

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
925.00 cum
Rate per
cum
(A+B+C+D)/925

Rs:
Rs:
Rs.

10404.26
86821.86
93.90

Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Tippers 5 cum capacity 6 Nos
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

Description

Unit

C. LABOUR:
Sl No
1
2
3
4

Crew for Shovel


Crew for Tipper
work inspector
mazdoor

Hour
Hour
Day
Day

Quantity
8.00
8.00
48.00
48.00

Quantity
8.00
48.00
1.00
30.00

Total cost of Labour


labour component/unit qty
21.00
Add contractor's profit and overhead charges
13.615% 2.90
labour component/unit qty (including contractor's profit)
23.90

IRR-CAW-1-2

925.00 cum

1706.60

Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seating
of embankment for field channels etc., including dressing of bed and sides to required profile,
cost of all materials, machinery, labour, placing the excavated stuff for formation of service
road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

NIL

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No
1
2
3

Description

Unit

Shovel 0.50 cum capacity


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Crew for Shovel


work inspector
mazdoor

Hour
Day
Day

Quantity
8.00
8.00

Quantity
8.00
1.00
17.00

440.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
487.60
Rs:

Amount
in Rs.
8024.80
3900.80
11925.60

Rate
in Rs.
221.00
400.00
310.00

Amount
in Rs.
1768.00
400.00
5270.00

1003.10

132

Canal and Allied Works - Item Unit Rates 2015-16

Total cost of Labour


labour component/unit qty
16.90
Add contractor's profit and overhead charges
13.615% 2.30
labour component/unit qty (including contractor's profit)
19.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
440.00 cum
Rate per
cum
(A+B+C+D)/440

IRR-CAW-1-3

7438.00

Rs:
Rs:
Rs:
Rs:

0.00
11925.60
7438.00
19363.60

Rs:
Rs:
Rs.

2636.35
21999.95
50.00

Excavation in ordinary rock (including HDR) without blasting including boulders above 0.30 m upto 0.6 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including dressing of
bed and sides to required level and profile, cost of all materials, machinery, labour, placing the
excavated soft rock neatly in dump area or for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Tippers 5 cum capacity 5 Nos
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

Description

Unit

Crew for Shovel


Crew for Tipper
work inspector
Crowbarman
mazdoor

Hour
Hour
Day
Day
Day

Quantity

630.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
893.90
446.70
307.20
Rs:

Amount
in Rs.
13652.80
7151.20
17868.00
12288.00
50960.00

Rate
in Rs.
221.00
165.80
400.00
370.00
310.00
Rs:

Amount
in Rs.
1768.00
6632.00
400.00
4070.00
6820.00
19690.00

Rs:
Rs:
Rs:
Rs:

0.00
50960.00
19690.00
70650.00

Rs:
Rs:
Rs.

9619
80269.00
127.40

8.00
8.00
40.00
40.00

Quantity
8.00
40.00
1.00
11.00
22.00

Total cost of Labour


labour component/unit qty
31.30
Add contractor's profit and overhead charges
13.615% 4.30
labour component/unit qty (including contractor's profit)
35.60

1706.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
630.00 cum
Rate per
cum
(A+B+C+D)/630

IRR-CAW-1-4

Rs:

Excavation in ordinary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia. for
field channels, seating of embankment for field channels etc., including dressing of bed and
sides to required profile, cost of all materials, machinery, labour, placing the excavated stuff

133

Canal and Allied Works - Item Unit Rates 2015-16

for formation of service road as directed etc.,complete with lead upto 10 m and lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Shovel 0.50 cum capacity


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No
1
2
3
4

Crew for Shovel


work inspector
Crowbarman
mazdoor

Hour
Day
Day
Day

Quantity

265.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
487.60
Rs:

Amount
in Rs.
8024.80
3900.80
11925.60

Rate
in Rs.
221.00
400.00
370.00
310.00
Rs:

Amount
in Rs.
1768.00
400.00
1850.00
3410.00
7428.00

Rs:
Rs:
Rs:
Rs:

0.00
11925.60
7428.00
19353.60

Rs:
Rs:
Rs.

2634.99
21988.59
83.00

8.00
8.00

Quantity
8.00
1.00
5.00
11.00

Total cost of Labour


labour component/unit qty
28.00
Add contractor's profit and overhead charges
13.615% 3.80
labour component/unit qty (including contractor's profit)
31.80

1003.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
265.00 cum
Rate per
cum
(A+B+C+D)/265

IRR-CAW-1-5

Excavation in hard rock (including F&F rock) requiring blasting including boulders
above 0.6 m upto 1.2 m dia. for canals, seating of embankment, filter drain / catch water drains
etc., including dressing bed and sides to required level and profile, cost of all materials,
machinery, labour, placing the excavated rock in dump area or for formation of service
road as directed etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos

Rm
10%
Hour

316.00
24.00

11.56

Amount
in Rs.
6557.00
655.70
277.50

Explosive small dia ( Kelvex-220 )


Ordinary detonators
Electric detonators
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Nos
Rm
LS

161.00
12.00
215.00
520.00
5.00

70.00
7.00
13.00
11.00
20.00
Rs:

11270.00
84.00
2795.00
5720.00
100.00
27459.20

Description

Shovel 0.85 cum capacity

Unit

Unit
Hour

Quantity

805.00 cum
Rate
in Rs.
20.75

B. MACHINERY:
Sl No

particulars

UNIT :

Quantity
8.00

Rate
in Rs.
1706.60

Amount
in Rs.
13652.80

134

Canal and Allied Works - Item Unit Rates 2015-16

3
4

C. LABOUR:
Sl No

Fuel / Energy charges


Tippers 5 cum capacity 5 Nos.
Fuel / Energy charges

Hour
Hour
Hour

8.00
40.00
40.00

893.90
446.70
307.20

7151.20
17868.00
12288.00

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammers 3 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

12.00
12.00
39.00
39.00

275.60
914.20
19.80
0.00
Rs:

3307.20
10970.40
772.20
0.00
66009.80

Description

Unit

Rate
in Rs.
221.00
165.80
195.90
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
1768.00
6632.00
2350.80
11941.80
400.00
480.00
370.00
5920.00
5920.00
9920.00
45702.60

Quantity

1
2
3
4
5
6
7
8
9
10

Crew for Shovel


Hour
8.00
Crew for Tipper
Hour
40.00
Crew for Air compressor
Hour
12.00
Crew for Jack hammer
Hour
39.00
work inspector
Day
1.00
Blaster
Day
1.00
Helper blaster
Day
1.00
Crowbarman
Day
16.00
Stone breaker
Day
16.00
mazdoor
Day
32.00
Total cost of Labour
labour component/unit qty
56.80
Add contractor's profit and overhead charges
13.615% 7.70
labour component/unit qty (including contractor's profit)
64.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
805.00 cum
Rate per
cum
(A+B+C+D)/805

IRR-CAW-1-6
(a)

Note:

Rs: 27459.20
Rs: 66009.80
Rs: 45702.60
Rs: 139171.60
Rs: 18948.21
Rs: 158119.81
Rs.
196.40

Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including levelling the bed
by removing all projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same as directed
etc., complete with initial lead upto 1 km and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.

135

Canal and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

1
2
3

4
5

C. LABOUR:
Sl No

Unit

Quantity

68.00 cum

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos.

Rm
10%
Hour

85.00

Rate
in Rs.
27.67

13.00

11.56

Amount
in Rs.
2351.67
235.17
150.31

Explosive small dia. (Kelvex-220 )


Ordinary detonators
Electric detonators
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Nos
Rm
LS

21.20
4.00
59.00
90.00
2.00

70.00
7.00
13.00
11.00
20.00
Rs:

1484.00
28.00
767.00
990.00
40.00
6046.15

B. MACHINERY:
Sl No

particulars

UNIT :

Description

Unit

Shovel 0.85 cum capacity


Fuel / energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tippers 5 cum capacity 4 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( diesel ) 1
Nos
Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

1.10
1.10
0.25
0.25
4.40
4.40

Hour
Hour
Hour
Hour

6.50
6.50
13.00
13.00

Description

Unit

1
2
3
4
5
6
7
8
9
10
11

Quantity

Quantity

Crew for Shovel


Hour
1.10
Crew for Dozer
Hour
0.25
Crew for Tipper
Hour
4.40
Crew for Air compressor
Hour
6.50
Crew for Jack hammer
Hour
13.00
work inspector
Day
0.50
Blaster
Day
1.00
Helper blaster
Day
1.00
Crowbarman
Day
0.50
Stone breaker
Day
0.50
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
122.40
Add contractor's profit and overhead charges
13.615% 16.70
labour component/unit qty (including contractor's profit)
139.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

Rate
in Rs.

625.30
446.70
307.20

Amount
in Rs.
1877.26
983.29
428.88
156.33
1965.48
1351.68

275.60
914.20
19.80
0.00
Rs:

1791.40
5942.30
257.40
0.00
14754.01

Rate
in Rs.
221.00
221.00
165.80
195.90
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
243.10
55.25
729.52
1273.35
3980.60
200.00
480.00
370.00
185.00
185.00
620.00
8321.82

Rs:
Rs:

6046.15
14754.01

1706.60

893.90
1715.50

136

Canal and Allied Works - Item Unit Rates 2015-16

C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
68.00 cum
Rate per
cum
(A+B+C+D)/68

IRR-CAW-1-7
(b)

Note:

Rs:
Rs:

8321.82
29121.98

Rs:
Rs:
Rs.

3964.96
33086.94
486.60

Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
controlled blasting methods for canals, cut-off trench of embankment, filter / catch-water
drains etc., including controlling fly-rock by muffling arrangements such as placing
50 x 50 mm opening chain link mesh or waste tyres and sand bags, monitoring ground
vibrations at specified locations, costof all materials, machinery, labour, placing excavated rock
neatly in approved dump area or other place as directed etc., complete with lead upto 1 km
and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

Unit

Quantity

68.00 cum

Rm
10%
Hour
sqm
Nos

85.00

2
3
4

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos.
Use rate of wire mesh
Use rate of sand bag

Rate
in Rs.
27.67

13.00
94.00
98.00

11.56
55.13
20.62

Amount
in Rs.
2351.67
235.17
150.31
5182.22
2020.76

5
6
7

Explosive small dia. (Kelvex-220 )


Ordinary detonators
Electric delay detonators

kg
Nos
Nos

21.20
4.00
59.00

70.00
7.00
23.00

1484.00
28.00
1357.00

particulars

UNIT :

137

Canal and Allied Works - Item Unit Rates 2015-16

8
9

Fuse coil
Sundries

Rm
LS

90.00
2.00

11.00
20.00
Rs:

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3

4
5

C. LABOUR:
Sl No

Description

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tippers 5 cum capacity 3 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( diesel ) 1
No
Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

1.10
1.10
0.25
0.25
4.40
4.40

Hour
Hour
Hour
Hour

6.50
6.50
13.00
13.00

Description

Unit

1
2
3
4
5
6
7
8
9
10
11

Quantity

Quantity

Crew for Shovel


Hour
1.10
Crew for Angle dozer
Hour
0.25
Crew for Tipper
Hour
4.40
Crew for Air compressor
Hour
6.50
Crew for Jack hammer
Hour
13.00
work inspector
Day
0.50
Blaster
Day
0.50
Helper blaster
Day
0.50
Stone chiseller Cl - II
Day
0.50
Stone breaker
Day
0.50
mazdoor
Day
3.00
Total cost of Labour
labour component/unit qty
120.70
Add contractor's profit and overhead charges
13.615% 16.40
labour component/unit qty (including contractor's profit)
137.10

Rate
in Rs.

625.30
446.70
307.20

Amount
in Rs.
1877.26
983.29
428.88
156.33
1965.48
1351.68

275.60
914.20
19.80
0.00
Rs:

1791.40
5942.30
257.40
0.00
14754.01

Rate
in Rs.
221.00
221.00
165.80
195.90
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
243.10
55.25
729.52
1273.35
3980.60
200.00
240.00
185.00
185.00
185.00
930.00
8206.82

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

13839.13
14754.01
8206.82
36799.96
184.00
36983.96
5035.37
42019.33
617.90

1706.60

893.90
1715.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for blasting studies & monitoring vibrations etc
D. Add for contractor's profit and overheads on
Total cost for
Rate per
cum

IRR-CAW-1-8
( c)

Note:

990.00
40.00
13839.13

Total
0.50%
Total
13.615%
68.00 cum
(A+B+C+D)/68

Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
canal sides neatly on either side to required profile by line drilling and smooth blasting
including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
i) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for

138

Canal and Allied Works - Item Unit Rates 2015-16

inspection and are spaced at specified interval.


v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided
for excavation by normal blasting or controlled blasting as the case may be.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

3
4

Unit

UNIT :
Quantity

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos.

Rm
10%
Hour

63.00

Explosive small dia. (Kelvex-220 )


Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Rm
LS

3.50
22.00
20.00
1.00

B. MACHINERY:
Sl No
1

particulars

10.00

Description

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Tippers 5 cum capacity 4 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( diesel ) 1
Nos
Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

0.28
0.28
1.12
1.12

Hour
Hour
Hour
Hour

5.00
5.00
10.00
10.00

Description

Unit

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10

Quantity

Quantity

Crew for Shovel


Hour
0.50
Crew for Tipper
Hour
1.12
Crew for Air compressor
Hour
5.00
Crew for Jack hammer
Hour
10.00
work inspector
Day
0.50
Blaster
Day
0.50
Helper blaster
Day
0.50
Stone breaker
Day
0.50
Stone chiseller Cl - II
Day
0.50
mazdoor
Day
1.00
Total cost of Labour
labour component/unit qty
322.40
Add contractor's profit and overhead charges
13.615% 43.90
labour component/unit qty (including contractor's profit)
366.30
ABSTRACT:
A. Cost of Materials

17.50 cum
Rate
Amount
in Rs.
in Rs.
27.67
1743.00
174.30
11.56
115.63
70.00
23.00
11.00
20.00
Rs:

Rate
in Rs.

245.00
506.00
220.00
20.00
3023.93

893.90
446.70
307.20

Amount
in Rs.
477.85
250.29
500.30
344.06

275.60
914.20
19.80
0.00
Rs:

1378.00
4571.00
198.00
0.00
7719.51

Rate
in Rs.
221.00
165.80
195.90
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
110.50
185.70
979.50
3062.00
200.00
240.00
185.00
185.00
185.00
310.00
5642.70

Rs:

3023.93

1706.60

139

Canal and Allied Works - Item Unit Rates 2015-16

B. Hire charges of Machinery


C. Cost of Labour
Add for blasting studies & monitoring vibrations etc
D. Add for contractor's profit and overheads on
Total cost for
Rate per
cum

IRR-CAW-1-9
(a)

Note:

Total
0.50%
Total
13.615%
17.50 cum
(A+B+C+D)/17.50

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

7719.51
5642.70
16386.13
81.93
16468.06
2242.13
18710.19
1069.20

Excavation in hard rock by blasting including boulders above 1.2 m dia. for canals, seating
embankment etc., including levelling bed by removing all projections by hammering / chiselling,
cost of all materials, machinery, labour, placing the excavated rock neatly in approved dump
area and levelling the same as directed etc.,complete with initial lead upto 1 km and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Use rate of T.C bit 100 mm dia


Use rate of Extension rod with
coupling sleeve
Use rate of Jack hammer drill rod
1.5 m
reconditioning charges @
Use rate of 50 m air hose for
waggon drill
Use rate of 25 m air hose for JH 2
Nos
High strength ANFO booster

Unit:
Unit
Rm

104.00

Rate
in Rs.
150.00

Rm

104.00

6.68

694.51

12.00

27.67

332.00
33.20

Hour

10.50

18.63

195.56

Hour
kg

1.00
38.00

11.56
68.00

11.56
2584.00

Rm
10%

Quantity

386.00 Cum
Amount
in Rs.
15600.00

140

Canal and Allied Works - Item Unit Rates 2015-16

6
7

ANFO
Diesel oil

8
9
10
11
12

Explosive small dia ( Kelvex-220 )


Ordinary detonators
D-cord
Detonating fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

4
5
6

C. LABOUR:
Sl No

Description

kg
ltr

155.00
35.00

48.00
59.10

7440.00
2068.50

kg
Nos
Rm
Rm
LS

4.00
20.00
145.00
20.00
5.00

70.00
7.00
10.00
11.00
20.00
Rs:

280.00
140.00
1450.00
220.00
100.00
31149.34

Rate
in Rs.
446.70
307.20

625.30

Amount
in Rs.
11096.03
7630.85
10597.99
5551.12
3431.00
1250.60

275.60
914.20
188.50
0.00
19.80
0.00
Rs:

3169.40
10513.30
1979.25
0.00
39.60
0.00
55259.13

Rate
in Rs.
165.80
221.00
221.00
195.90
265.20
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
4118.47
1372.41
442.00
2252.85
2784.60
612.40
800.00
480.00
370.00
370.00
370.00
930.00
14902.73

Unit

Quantity

Tippers 5 cum capacity


Fuel / Energy charges
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

24.84
24.84
6.21
6.21
2.00
2.00

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Waggon drill
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

11.50
11.50
10.50
10.50
2.00
2.00

Description

Unit

Quantity

1
2
3
4
5
6
7
8
9
10
11
12

Crew for Tipper


Hour
24.84
Crew for Shovel
Hour
6.21
Crew for Dozer
Hour
2.00
Crew for Air compressor
Hour
11.50
Crew for Waggon drill
Hour
10.50
Crew for Jack hammer
Hour
2.00
work inspector
Day
2.00
Blaster
Day
1.00
Helper blaster
Day
1.00
Stone chiseller Cl - II
Day
1.00
Stone breaker
Day
1.00
mazdoor
Day
3.00
Total cost of Labour
labour component/unit qty
38.60
Add contractor's profit and overhead charges
13.615% 5.30
labour component/unit qty (including contractor's profit)
43.90

1706.60

893.90
1715.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
386.00 Cum
Rate per
Cum
(A+B+C+D)/386

Rs: 31149.34
Rs: 55259.13
Rs: 14902.73
Rs: 101311.20
Rs: 13793.52
Rs: 115104.72
Rs.
298.20

IRR-CAW-1-10 Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
(b)
controlled blasting methods for canals, cut-off trench of embankment etc., including
controlling fly-rock by muffling arrangements such as placing 50 x 50 mm opening
chain link mesh or waste tyres and sand bags, monitoring ground vibrations at specified
locations, cost of all materials, machinery, labour, placing excavated rock neatly in approved
dump area or other place as directed etc., complete with lead upto 1 km and all lifts.

141

Canal and Allied Works - Item Unit Rates 2015-16

Note:

i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Rm

104.00

Rm

104.00

6.68

694.51

Rm
10%

12.00

27.67

332.00
33.20

Hour

10.50

18.63

195.56

Use rate of 25 mm air hose 2 Nos


High strength ANFO booster
ANFO
Diesel oil

Hour
kg
kg
ltr

2.00
38.00
155.00
35.00

11.56
68.00
48.00
59.10

23.13
2584.00
7440.00
2068.50

Explosive small dia ( Kelvex-220 )


Ordinary detonators
Shock tube detonators
Noiseless trunk line delays
Detonating fuse coil
Use rate of chain link wire mesh
Use rate of sand bag
Sundries
Total cost of Materials

kg
Nos
Rm
Nos
Rm
sqm
Nos
LS

4.00
20.00
120.00
12.00
20.00
132.00
110.00
20.00

70.00
7.00
45.00
21.00
11.00
198.00
16.62
20.00
Rs:

280.00
140.00
5400.00
252.00
220.00
26136.00
1828.20
400.00
63627.10

Rate

Amount

5
6
7

8
9
10
11
12
13
14
15

B. MACHINERY:
Sl No

Description

Unit

Unit

Quantity

386.00 cum
Rate
in Rs.
150.00

Use rate of T.C bit 100 mm dia


Use rate of Extension rod with
coupling sleeve
Use rate of Jack hammer drill rod
1.6 m
reconditioning charges @
Use rate of 50 m air hose 50 mm 1
No.

UNIT :

Quantity

Amount
in Rs.
15600.00

142

Canal and Allied Works - Item Unit Rates 2015-16

1
2
3

4
5
6

C. LABOUR:
Sl No

Tippers 5 cum capacity


Fuel / Energy charges
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

30.00
30.00
10.00
10.00
2.00
2.00

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Waggon drill
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

12.50
12.50
11.50
11.50
2.00
2.00

Description

Unit

1
2
3
4
5
6
7
8
9
10
11
12

Quantity

Crew for Tipper


Hour
30.00
Crew for Shovel
Hour
10.00
Crew for Dozer
Hour
2.00
Crew for Air compressor
Hour
12.50
Crew for Waggon drill
Hour
11.50
Crew for Jack hammer
Hour
2.00
work inspector
Day
1.50
Blaster
Day
0.50
Helper blaster
Day
0.50
Stone chiseller Cl - II
Day
1.00
Stone breaker
Day
1.00
mazdoor
Day
5.00
Total cost of Labour
labour component/unit qty
44.20
Add contractor's profit and overhead charges
13.615% 6.00
labour component/unit qty (including contractor's profit)
50.20

in Rs.
446.70
307.20

625.30

in Rs.
13401.00
9216.00
17066.00
8939.00
3431.00
1250.60

275.60
914.20
188.50
0.00
19.80
0.00
Rs:

3445.00
11427.50
2167.75
0.00
39.60
0.00
70383.45

Rate
in Rs.
165.80
221.00
221.00
195.90
265.20
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
4974.00
2210.00
442.00
2448.75
3049.80
612.40
600.00
240.00
185.00
370.00
370.00
1550.00
17051.95

1706.60

893.90
1715.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for blasting studies & monitoring vibrations etc
D. Add for contractor's profit and overheads on
Total cost for
Rate per
cum

Total
0.50%
Total
13.615%
386.00 cum
(A+B+C+D)/386

Rs: 63627.10
Rs: 70383.45
Rs: 17051.95
Rs: 151062.50
Rs:
755.31
Rs: 151817.81
Rs:
20670
Rs: 172487.81
Rs.
446.90

IRR-CAW-1-11 Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
( c)
canal sides neatly on either side to required profile by line drilling and smooth blasting
including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
Note:

i ) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for
inspection and are spaced at specified interval.
v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided

143

Canal and Allied Works - Item Unit Rates 2015-16

for excavation by normal blasting or controlled blasting as the case may be.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Rm

121.00

Rm

121.00

6.68

808.04

Rm
10%

3.00

27.67

83.00
8.30

Hour

12.00

18.63

223.50

Use rate of 25 mm air hose 2 Nos


High strength ANFO booster
ANFO
Diesel oil

Hour
kg
kg
ltr

0.50
5.00
19.00
4.50

11.56
68.00
48.00
59.10

5.78
340.00
912.00
265.95

Explosive small dia ( Kelvex-220 )


Ordinary detonators
Detonating shock tube
Noiseless trunk line delays
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Rm
Nos
Rm
LS

1.00
5.00
70.00
4.00
10.00
2.00

70.00
7.00
45.00
21.00
11.00
20.00
Rs:

70.00
35.00
3150.00
84.00
110.00
40.00
24285.57

Rate
in Rs.
446.70
307.20

625.30

Amount
in Rs.
2787.41
1916.93
2662.30
1394.48
857.75
312.65

275.60
914.20
188.50
0.00
19.80
0.00
Rs:

3706.82
12295.99
2488.20
0.00
9.90
0.00
28432.43

Rate
in Rs.
165.80
221.00

Amount
in Rs.
868.79
344.76

5
6
7

8
9
10
11
12
13

B. MACHINERY:
Sl No
1
2
3

4
5
6

C. LABOUR:
Sl No
1
2

Description

Unit

Unit

Quantity

97.00 cum
Rate
in Rs.
150.00

Use rate of T.C bit 100 mm dia


Use rate of Extension rod with
coupling sleeve
Use rate of Jack hammer drill rod
1.6 m
reconditioning charges @
Use rate of 50 m air hose 50 mm 1
No.

UNIT :

Quantity

Tippers 5 cum capacity


Fuel / Energy charges
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

6.24
6.24
1.56
1.56
0.50
0.50

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Waggon drill
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

13.45
13.45
13.20
13.20
0.50
0.50

Description

Unit

Crew for Tipper


Crew for Shovel

Hour
Hour

Quantity
5.24
1.56

1706.60

893.90
1715.50

Amount
in Rs.
18150.00

144

Canal and Allied Works - Item Unit Rates 2015-16

3
4
5
6
7
8
9
10
11
12

Crew for Dozer


Hour
0.50
Crew for Air compressor
Hour
13.45
Crew for Waggon drill
Hour
13.45
Crew for Jack hammer
Hour
0.50
work inspector
Day
0.50
Blaster
Day
0.50
Helper blaster
Day
0.50
Stone breaker
Day
1.00
Stone chiseller Cl- II
Day
1.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
99.60
Add contractor's profit and overhead charges
13.615% 13.60
labour component/unit qty (including contractor's profit)
113.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for blasting studies & monitoring vibrations etc
D. Add for contractor's profit and overheads on
Total cost for
Rate per
cum

Total
0.50%
Total
13.615%
97.00 cum
(A+B+C+D)/97

221.00
195.90
265.20
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

110.50
2634.86
3566.94
153.10
200.00
240.00
185.00
370.00
370.00
620.00
9663.95

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

24285.57
28432.43
9663.95
62381.94
311.91
62693.85
8535.77
71229.62
734.30

IRR-CAW-2

EMBANKMENT WORKS USING BORROW AREA SOIL :

IRR-CAW-2-1

Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No
1
2

Description

Unit

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel

Hour
Hour

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
5.10
5.10
5.00

Quantity
3.40
8.00

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

20.00
Rs:

Amount
in Rs.
5832.70
2126.02
8024.80
3900.80
14294.40
9830.40
20.40
162.60
1610.00
1228.80
6845.22
5387.64
100.00
59363.78

Rate
in Rs.
221.00
221.00

Amount
in Rs.
751.40
1768.00

1715.50

625.30
1003.10

487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40

145

Canal and Allied Works - Item Unit Rates 2015-16

3
4
5
6
7
8

Crew for Tipper


Hour
32.00
Crew for Pump
Hour
2.00
Crew for Water tanker
Hour
4.00
Crew for Roller
Hour
5.10
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
29.00
Add contractor's profit and overhead charges
13.615% 3.90
labour component/unit qty (including contractor's profit)
32.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
412.80 cum
Rate per
cum
(A+B+C+D)/412.80

IRR-CAW-2-2

165.80
103.60
165.80
244.90
400.00
310.00
Rs:

5305.60
207.20
663.20
1248.99
800.00
1240.00
11984.39

Rs:
Rs:
Rs:
Rs:

0.00
59363.78
11984.39
71348.17

Rs:
Rs:
Rs.

9714.05
81062.22
196.40

Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No
1
2
3
4
5
6
7

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector

Hour
Hour
Hour
Hour
Hour
Hour
Day

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
4.18
4.18
5.00

Quantity
3.40
8.00
32.00
2.00
4.00
4.18
2.00

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
5832.70
2126.02
8024.80
3900.80
14294.40
9830.40
20.40
162.60
1610.00
1228.80
5610.40
4415.75
100.00
57157.07

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00

Amount
in Rs.
751.40
1768.00
5305.60
207.20
663.20
1023.68
800.00

146

Canal and Allied Works - Item Unit Rates 2015-16

mazdoor

Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

4.00

310.00
Rs:
28.50
13.615% 3.90
32.40

1240.00
11759.08

Rs:
Rs:
Rs:
Rs:

0.00
57157.07
11759.08
68916.15

Rs:
Rs:
Rs.

9382.93
78299.08
189.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
412.80 cum
Rate per
cum
(A+B+C+D)/412.80

IRR-CAW-2-3

Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
5.10
5.10
2.00

Quantity
3.40
8.00
32.00
2.00
4.00
5.10
2.00
4.00

13.615%

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
5832.70
2126.02
8024.80
3900.80
14294.40
9830.40
20.40
162.60
1610.00
1228.80
6845.22
5387.64
40.00
59303.78

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:
29.00
3.90
32.90

Amount
in Rs.
751.40
1768.00
5305.60
207.20
663.20
1248.99
800.00
1240.00
11984.39

147

Canal and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
412.80 cum
Rate per
cum
(A+B+C+D)/412.80

IRR-CAW-2-4

Rs:
Rs:
Rs:
Rs:

0.00
59303.78
11984.39
71288.17

Rs:
Rs:
Rs.

9705.88
80994.05
196.20

Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

1
2
3
4
5
6
7
8

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
4.17
4.17
5.00

Quantity

Crew for Dozer


Hour
3.40
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
32.00
Crew for Pump
Hour
2.00
Crew for Water tanker
Hour
4.00
Crew for Roller
Hour
4.00
work inspector
Day
4.17
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
30.50
Add contractor's profit and overhead charges
13.615% 4.20
labour component/unit qty (including contractor's profit)
34.70

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
5832.70
2126.02
8024.80
3900.80
14294.40
9830.40
20.40
162.60
1610.00
1228.80
5596.97
4405.19
100.00
57133.08

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
751.40
1768.00
5305.60
207.20
663.20
979.60
1668.00
1240.00
12583.00

Rs:
Rs:
Rs:
Rs:

0.00
57133.08
12583.00
69716.08

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

148

Canal and Allied Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
412.80 cum
Rate per
cum
(A+B+C+D)/412.80

IRR-CAW-2-5

Rs:
Rs:
Rs.

Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Nill

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Day
Day

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
4.17
4.17
2.00

Quantity
3.40
8.00
32.00
4.17
2.00
4.00

Total cost of Labour


labour component/unit qty
26.40
Add contractor's profit and overhead charges
13.615% 3.60
labour component/unit qty (including contractor's profit)
30.00

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
5832.70
2126.02
8024.80
3900.80
14294.40
9830.40
5596.97
4405.19
40.00
54051.28

Rate
in Rs.
221.00
221.00
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
751.40
1768.00
5305.60
1021.23
800.00
1240.00
10886.23

Rs:
Rs:
Rs:
Rs:

0.00
54051.28
10886.23
64937.52

Rs:
Rs:
Rs.

8841.24
73778.76
178.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
412.80 cum
Rate per
cum
(A+B+C+D)/412.80

IRR-CAW-2-6

9491.84
79207.92
191.90

Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

149

Canal and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Unit

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
6.06
6.06
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.53
7.53
2.00

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
6.06
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
7.53
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
24.00
Add contractor's profit and overhead charges
13.615% 3.30
labour component/unit qty (including contractor's profit)
27.30

677.28 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
10395.93
3789.32
8024.80
3900.80
21441.60
14745.60
30.60
243.90
2415.00
1843.20
10106.77
7954.69
40.00
84932.21

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
1339.26
1768.00
7958.40
310.80
994.80
1844.10
800.00
1240.00
16255.36

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
677.28 cum
Rate per
cum
(A+B+C+D)/677.28

IRR-CAW-2-7

Rs:
0.00
Rs: 84932.21
Rs: 16255.36
Rs: 101187.56
Rs: 13776.69
Rs: 114964.25
Rs.
169.70

Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

677.28 cum
Rate
in Rs.

Amount
in Rs.

150

Canal and Allied Works - Item Unit Rates 2015-16

Nill

0.00
0.00

0.00
0.00
Rs:

0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
10395.93
3789.32
8024.80
3900.80
21441.60
14745.60
30.60
243.90
2415.00
1843.20
8267.95
6507.42
100.00
81706.12

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
1339.26
1768.00
7958.40
310.80
994.80
1508.58
800.00
1240.00
15919.84

Rs:
Rs:
Rs:
Rs:

0.00
81706.12
15919.84
97625.97

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum 3 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
6.06
6.06
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.16
6.16
5.00

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
6.06
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
6.16
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
23.50
Add contractor's profit and overhead charges
13.615% 3.20
labour component/unit qty (including contractor's profit)
26.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
677.28 cum
Rate per
cum
(A+B+C+D)/677.28
IRR-CAW-2-8

Rs: 13291.78
Rs: 110917.75
Rs.
163.80

Providing casing embankment using homogeneous soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

677.28 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

151

Canal and Allied Works - Item Unit Rates 2015-16

1
2
3
4
5

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No
1
2
3
4
5
6

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Day
Day

6.06
6.06
8.00
8.00
48.00
48.00
6.16
6.16
2.00

Quantity
6.06
8.00
48.00
6.16
2.00
4.00

Total cost of Labour


labour component/unit qty
21.60
Add contractor's profit and overhead charges
13.615% 2.90
labour component/unit qty (including contractor's profit)
24.50

1715.50
625.30
1003.10
487.60
446.70
307.20
1342.20
1056.40
20.00
Rs:

10395.93
3789.32
8024.80
3900.80
21441.60
14745.60
8267.95
6507.42
40.00
77113.42

Rate
in Rs.
221.00
221.00
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
1339.26
1768.00
7958.40
1508.58
800.00
1240.00
14614.24

Rs:
Rs:
Rs:
Rs:

0.00
77113.42
14614.24
91727.67

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
677.28 cum
Rate per
cum
(A+B+C+D)/677.28

Rs: 12488.72
Rs: 104216.39
Rs.
153.90

IRR-CAW-3

EMBANKMENT WORKS USING DUMP AREA SOIL :

IRR-CAW-3-1

Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density
control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
4.04
4.04
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.50

735.36 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20

Amount
in Rs.
6930.62
2526.21
8024.80
3900.80
21441.60
14745.60
30.60
243.90
2415.00
1843.20
10066.50

152

Canal and Allied Works - Item Unit Rates 2015-16

Fuel / Energy charges


Sundries
Total hire charges of Machinery

Hour
LS

Description

Unit

C. LABOUR:
Sl No

7.50 1056.40
2.00
20.00
Rs:

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
3.58
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
7.50
work inspector
Day
2.00
mazdoor
Day
6.00
Total cost of Labour
labour component/unit qty
22.20
Add contractor's profit and overhead charges
13.615% 3.00
labour component/unit qty (including contractor's profit)
25.20

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
791.18
1768.00
7958.40
310.80
994.80
1836.75
800.00
1860.00
16319.93

Rs:
Rs:
Rs:
Rs:

0.00
80131.83
16319.93
96451.76

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
735.36 cum
Rate per
cum
(A+B+C+D)/735.36

IRR-CAW-3-2

7923.00
40.00
80131.83

Rs: 13131.91
Rs: 109583.67
Rs.
149.00

Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Quantity
4.04
4.04
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.13
6.13
5.00

Quantity

735.36 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
6930.62
2526.21
8024.80
3900.80
21441.60
14745.60
30.60
243.90
2415.00
1843.20
8227.69
6475.73
100.00
76905.75

Rate

Amount

153

Canal and Allied Works - Item Unit Rates 2015-16

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
4.04
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
6.13
work inspector
Day
2.00
mazdoor
Day
6.00
Total cost of Labour
labour component/unit qty
21.90
Add contractor's profit and overhead charges
13.615% 3.00
labour component/unit qty (including contractor's profit)
24.90

in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

in Rs.
892.84
1768.00
7958.40
310.80
994.80
1501.24
800.00
1860.00
16086.08

Rs:
Rs:
Rs:
Rs:

0.00
76905.75
16086.08
92991.83

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
735.36 cum
Rate per
cum
(A+B+C+D)/735.36

IRR-CAW-3-3

Rs: 12660.84
Rs: 105652.67
Rs.
143.70

Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker

Hour
Hour
Hour
Hour
Hour

Quantity
4.22
4.22
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.82
7.82
2.00

Quantity
4.22
8.00
48.00
3.00
6.00

768.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
7239.41
2638.77
8024.80
3900.80
21441.60
14745.60
30.60
243.90
2415.00
1843.20
10496.00
8261.05
40.00
81320.73

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80

Amount
in Rs.
932.62
1768.00
7958.40
310.80
994.80

154

Canal and Allied Works - Item Unit Rates 2015-16

6
7
8

Crew for Roller


work inspector
mazdoor

Hour
Day
Day

7.82
2.00
6.00

Total cost of Labour


labour component/unit qty
21.50
Add contractor's profit and overhead charges
13.615% 2.90
labour component/unit qty (including contractor's profit)
24.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
768.00 cum
Rate per
cum
(A+B+C+D)/768

IRR-CAW-3-4

244.90
400.00
310.00
Rs:

1915.12
800.00
1860.00
16539.74

Rs:
Rs:
Rs:
Rs:

0.00
81320.73
16539.74
97860.47

Rs:
13323.7
Rs: 111184.17
Rs.
144.80

Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum of 6 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor
Total cost of Labour
labour component/unit qty

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day

Quantity
4.22
4.22
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.40
6.40
5.00

Quantity
4.22
8.00
48.00
3.00
6.00
6.40
2.00
6.00

768.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
7239.41
2638.77
8024.80
3900.80
21441.60
14745.60
30.60
243.90
2415.00
1843.20
8590.08
6760.96
100.00
77974.72

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:
21.10

Amount
in Rs.
932.62
1768.00
7958.40
310.80
994.80
1567.36
800.00
1860.00
16191.98

155

Canal and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


labour component/unit qty (including contractor's profit)

13.615% 2.90
24.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
768.00 cum
Rate per
cum
(A+B+C+D)/768
IRR-CAW-3-5

Rs:
Rs:
Rs:
Rs:

0.00
77974.72
16191.98
94166.70

Rs:
12820.8
Rs: 106987.50
Rs.
139.30

Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Nill

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos.
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Day
Day

Quantity
4.22
4.22
8.00
8.00
48.00
48.00
6.40
6.40
2.00

Quantity
4.22
8.00
48.00
6.40
2.00
6.00

Total cost of Labour


labour component/unit qty
19.40
Add contractor's profit and overhead charges
13.615% 2.60
labour component/unit qty (including contractor's profit)
22.00

768.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
7239.41
2638.77
8024.80
3900.80
21441.60
14745.60
8590.08
6760.96
40.00
73382.02

Rate
in Rs.
221.00
221.00
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
932.62
1768.00
7958.40
1567.36
800.00
1860.00
14886.38

Rs:
Rs:
Rs:
Rs:

0.00
73382.02
14886.38
88268.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
768.00 cum
Rate per
cum
(A+B+C+D)/768

Rs: 12017.74
Rs: 100286.14
Rs.
130.60

156

Canal and Allied Works - Item Unit Rates 2015-16

IRR-CAW-4

EMBANKMENT WORKS USING EXCAVATED SOIL :

IRR-CAW-4-1

Providing impervious hearting embankment with soil collected in embankment area in


heaps as part of disposal of excavated soil from canal including cost of all materials,machinery,
labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,
breaking clods,sectioning, watering and compacting each layer to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
3.60
3.60
3.00
3.00
5.00
5.00
7.30
7.30
2.00

Quantity

1
2
3
4
5
6

Crew for Dozer


Hour
3.60
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
5.00
Crew for Roller
Hour
7.30
work inspector
Day
1.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
8.90
Add contractor's profit and overhead charges
13.615% 1.20
labour component/unit qty (including contractor's profit)
10.10

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
6175.80
2251.08
30.60
243.90
2012.50
1536.00
9798.06
7711.72
40.00
29799.66

Rate
in Rs.
221.00
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
795.60
310.80
829.00
1787.77
400.00
1240.00
5363.17

Rs:
Rs:
Rs:
Rs:

0.00
29799.66
5363.17
35162.83

Rs:
Rs:
Rs.

4787.42
39950.25
66.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
600.00 cum
Rate per
cum
(A+B+C+D)/600

IRR-CAW-4-2

Providing impervious hearting embankment with soil collected in embankment area in


heaps as part of disposal of excavated soil from canal including cost of all materials,machinery,
labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,
breaking clods,sectioning, watering and compacting each layer to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

600.00 cum
Rate

Amount

157

Canal and Allied Works - Item Unit Rates 2015-16

Nill

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
3.60
3.60
3.00
3.00
5.00
5.00
6.06
6.06
5.00

Quantity

1
2
3
4
5
6

Crew for Dozer


Hour
3.60
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
5.00
Crew for Roller
Hour
6.06
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
9.10
Add contractor's profit and overhead charges
13.615% 1.20
labour component/unit qty (including contractor's profit)
10.30

in Rs.
0.00
0.00
Rs:

in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
6175.80
2251.08
30.60
243.90
2012.50
1536.00
8133.73
6401.78
100.00
26885.40

Rate
in Rs.
221.00
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
795.60
310.80
829.00
1484.09
800.00
1240.00
5459.49

Rs:
Rs:
Rs:
Rs:

0.00
26885.40
5459.49
32344.89

Rs:
Rs:
Rs.

4403.76
36748.65
61.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
600.00 cum
Rate per
cum
(A+B+C+D)/600

IRR-CAW-4-3

Providing semi-pervious / pervious casing hearting embankment using soil collected in


heaps in embankment area as part of disposal of excavated soil from canal including cost of
all materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning, watering and compacting each layer
to density control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour

Quantity
3.60
3.60
3.00
3.00

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
10.20
81.30

Amount
in Rs.
6175.80
2251.08
30.60
243.90

158

Canal and Allied Works - Item Unit Rates 2015-16

3
4
5

Water tanker 8000 ltr


Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

5.00 402.50
5.00 307.20
7.30 1342.20
7.30 1056.40
2.00
20.00
Rs:

Quantity

1
2
3
4
5
6

Crew for Dozer


Hour
3.60
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
5.00
Crew for Roller
Hour
7.30
work inspector
Day
1.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
8.90
Add contractor's profit and overhead charges
13.615% 1.20
labour component/unit qty (including contractor's profit)
10.10

Rate
in Rs.
221.00
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
795.60
310.80
829.00
1787.77
400.00
1240.00
5363.17

Rs:
Rs:
Rs:
Rs:

0.00
29799.66
5363.17
35162.83

Rs:
Rs:
Rs.

4787.42
39950.25
66.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
600.00 cum
Rate per
cum
(A+B+C+D)/600

IRR-CAW-4-4

2012.50
1536.00
9798.06
7711.72
40.00
29799.66

Providing semi-pervious / pervious casing embankment using soil collected in heaps in


embankment area as part of disposal of excavated soil from canal including cost of all
materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning, watering and compacting each layer
to density control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No
1
2

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Pump

Hour
Hour

Quantity
3.60
3.60
3.00
3.00
5.00
5.00
6.1
6.1
5.00

Quantity
3.60
3.00

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
6175.80
2251.08
30.60
243.90
2012.50
1536.00
8133.73
6401.78
100.00
26885.40

Rate
in Rs.
221.00
103.60

Amount
in Rs.
795.60
310.80

159

Canal and Allied Works - Item Unit Rates 2015-16

3
4
5
6

Crew for Water tanker


Hour
5.00
Crew for Roller
Hour
6.1
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
9.10
Add contractor's profit and overhead charges
13.615% 1.20
labour component/unit qty (including contractor's profit)
10.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
600.00 cum
Rate per
cum
(A+B+C+D)/600

IRR-CAW-4-5

165.80
244.90
400.00
310.00
Rs:

829.00
1484.09
800.00
1240.00
5459.49

Rs:
Rs:
Rs:
Rs:

0.00
26885.40
5459.49
32344.89

Rs:
Rs:
Rs.

4403.76
36748.65
61.20

Providing semi-pervious / pervious casing embankment using soil collected in heaps in


embankment area as part of disposal of excavated soil from canal including cost of all
materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning and compacting each layer without
watering to density control of not less than 95 percent or as stipulated by Sheep foot roller /
Vibratory roller/ 8 to 10 tonne power roller etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Nill

0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3

C. LABOUR:
Sl No
1
2
3
4

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Roller
work inspector
mazdoor

Quantity
3.60
3.60
6.06
6.06
2.00

Quantity

Hour
Hour
Day
Day

3.60
6.06
1.00
4.00

Total cost of Labour


labour component/unit qty
6.50
Add contractor's profit and overhead charges
13.615% 0.90
labour component/unit qty (including contractor's profit)
7.40

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

0.00

Rate
in Rs.
1715.50
625.30
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
6175.80
2251.08
8133.73
6401.78
40.00
23002.40

Rate
in Rs.
221.00
244.90
400.00
310.00
Rs:

Amount
in Rs.
795.60
1484.09
400.00
1240.00
3919.69

Rs:
Rs:
Rs:
Rs:

0.00
23002.40
3919.69
26922.09

Rs:
Rs:
Rs.

3665.44
30587.53
51.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
600.00 cum
Rate per
cum
(A+B+C+D)/600

Amount
in Rs.

160

Canal and Allied Works - Item Unit Rates 2015-16

IRR-CAW-4-6

Providing compacted embankment for field irrigation channels with gravely soil from
approved borrow area including sorting out, spreading in layers of 15 cm thickness, breaking
clods, watering, compacting, dressing sides to required slopes etc.,complete with lead upto
50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

Quantity
1.00
1.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
10.20
81.30
91.50

Amount
in Rs.
103.60
400.00
925.00

0.00

Crew for pump


work inspector
Crowbarman for loosening soil
mazdoor
For excavation at borrow area

Hour
Day
Day

1.00
1.00
2.50

Rate
in Rs.
103.60
400.00
370.00

Day

5.00

310.00

1550.00

For spreading / levelling / sectioning


for loading soil

Day
Day

2.50
5.00

310.00
310.00

775.00
1550.00

Cartman with Bullock cart for water


Day
1.00
Bullock drawn roller for rolling
Day
1.00
Total cost of Labour
labour component/unit qty
244.10
Add contractor's profit and overhead charges
13.615% 33.20
labour component/unit qty (including contractor's profit)
277.30

400.00
400.00
Rs:

400.00
400.00
6103.60

Rs:
Rs:
Rs:
Rs:

0.00
91.50
6103.60
6195.10

Rs:
Rs:
Rs.

843.46
7038.56
281.50

1
2
3
4

Quantity

25.00 cum

5
6

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
25.00 cum
Rate per
cum
(A+B+C+D)/25
IRR-CAW-5

FOUNDATION FILLING WORKS :

IRR-CAW-5-1

Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Rubble stones at quarry


Sand for filling
Total cost of Materials

cum
cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
10.00
4.00

Quantity

10.00 cum
Rate
in Rs.
330.00
560.00
Rs:

Amount
in Rs.
3300.00
2240.00
5540.00

Rate

Amount

161

Canal and Allied Works - Item Unit Rates 2015-16

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit
Day

Quantity
4.00

Total cost of Labour

in Rs.
0.00
0.00
Rs:

in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1240.00
1240.00

Rs:
Rs:
Rs:
Rs:

5540.00
0.00
1240.00
6780.00

Rs:
Rs:
Rs.

923.1
7703.10
770.30

labour component/unit qty


124.00
Add contractor's profit and overhead charges
13.615% 16.90
labour component/unit qty (including contractor's profit)
140.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 cum
Rate per
cum
(A+B+C+D)/10

IRR-CAW-5-2

Providing rubble and Murum filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Rubble stones at quarry


Murum
Total cost of Materials

cum
cum

B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
10.00
4.00

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit
Day

Quantity
4.00

Total cost of Labour

10.00 cum
Rate
in Rs.
330.00
115.00
Rs:

Amount
in Rs.
3300.00
460.00
3760.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1240.00
1240.00

Rs:
Rs:
Rs:
Rs:

3760.00
0.00
1240.00
5000.00

Rs:
Rs:
Rs.

680.75
5680.75
568.10

labour component/unit qty


124.00
Add contractor's profit and overhead charges
13.615% 16.90
labour component/unit qty (including contractor's profit)
140.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 cum
Rate per
cum
(A+B+C+D)/10

IRR-CAW-5-3

Providing and laying 25 cm thick sand blanket below embankment including cost of all
materials, machinery, labour, spreading to specified thickness etc., complete with initial lead
upto 50 m and all lifts.

162

Canal and Allied Works - Item Unit Rates 2015-16

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Sand for Filling

UNIT :
Unit
cum

Quantity
25.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit

Quantity

Day

5.00

Total cost of Labour

100.00 sqm
Rate
in Rs.
560.00
0.00
Rs:

Amount
in Rs.
14000.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1550.00
1550.00

Rs:
Rs:
Rs:
Rs:

14000.00
0.00
1550.00
15550.00

Rs:
Rs:
Rs.

2117.13
17667.13
176.70

14000.00

labour component/unit qty


15.50
Add contractor's profit and overhead charges
13.615% 2.10
labour component/unit qty (including contractor's profit)
17.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

IRR-CAW-5-3-A Providing and laying sand blanket below embankment including cost of all
(New Item3- 2011-12)
materials, machinery, labour, spreading to specified thickness etc., complete with initial lead

upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Sand for Filling

UNIT :
Unit
cum

Quantity
100.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit
Day

Quantity
20.00

Total cost of Labour

100.00 cum
Rate
in Rs.
560.00
0.00
Rs:

Amount
in Rs.
56000.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
6200.00
6200.00

56000.00

labour component/unit qty


62.00
Add contractor's profit and overhead charges
13.615% 8.40
labour component/unit qty (including contractor's profit)
70.40

163

Canal and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100
IRR-CAW-5-4

56000.00
0.00
6200.00
62200.00

Rs:
Rs:
Rs.

8468.53
70668.53
706.70

Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Rubble
Stone chips
Sundries

UNIT :
Unit
cum
cum
LS

Quantity
100.00
15.00
2.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class-II
mazdoor

Unit
Day
Day
Day

Quantity
1.00
7.00
19.00

Total cost of Labour


labour component/unit qty
88.80
Add contractor's profit and overhead charges
13.615% 12.10
labour component/unit qty (including contractor's profit)
100.90

100.00 cum
Rate
in Rs.
330.00
360.00
20.00
Rs:

Amount
in Rs.
33000.00
5400.00
40.00
38440.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
2590.00
5890.00
8880.00

Rs:
Rs:
Rs:
Rs:

38440.00
0.00
8880.00
47320.00

Rs:
Rs:
Rs.

6442.62
53762.62
537.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-CAW-5-5

Rs:
Rs:
Rs:
Rs:

0.00

Providing and constructing longitudinal and cross graded filter drains using sand and
20 mm down graded aggregates satisfying specified filter creteria in layers as per specifications
including cost of all materials, machinery, labour, laying to required slopes, compaction etc.,
complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 cum
Rate
in Rs.
560.00

Amount
in Rs.
43008.00
21054.00

Sand (Un-Screened )

cum

76.80

Coarse aggregate 20-10 mm 75 %

cum

17.40 1210.00

164

Canal and Allied Works - Item Unit Rates 2015-16

Coarse aggregate 10 mm down 25


%
Total cost of Materials

B. MACHINERY:
Sl No

Description

cum

Unit

5.80

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoor

Unit

Quantity

Day
Day

1.00
36.00

Total cost of Labour


labour component/unit qty
115.60
Add contractor's profit and overhead charges
13.615% 15.70
labour component/unit qty (including contractor's profit)
131.30

875.00
Rs:

5075.00
69137.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
11160.00
11560.00

Rs:
Rs:
Rs:
Rs:

69137.00
0.00
11560.00
80697.00

Rs:
Rs:
Rs.

10986.9
91683.90
916.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-CAW-5-6

DATA:

0.00

Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm in Bed and
filling with 12 mm to 40 mm HG machine Crushed metal and sand in bed including
Excavation of drains and Cost of procuring of all materials including 50 m lead and for all lifts.
RATE ANALYSIS
A. MATERIALS:
Sl.No
Particulars
1
12 mm to 40 mm metal
2
Sand (Un-Screened )
Total cost of Materials
B. MACHINERY
Sl.No
Description
1

Excavation of drain with Excavator


Total hire charges of Machinery

C. LABOUR
Sl.No
1
2

Unit
Cum
cum

Unit

100 mt
Rate in RsAmount in Rs.
13.5 1145.00 15457.50
36 560.00 20160.00
Rs.
35617.5

Quantity

Cum

Particulars
Unit
Labour for Sand laying
Cum
Labour for Metal laying
Cum
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
13.615%
labour component/unit qty (including contractor's profit)
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Unit:
Qty

45

Qty
5.14
1.93

Rate in Rs.
Amount in Rs.
37.00
Total Rs.

1665.00
1665

Rate in RsAmount in Rs.


310.00
1593.40
310.00
598.30
Rs.
2191.7

21.90
3.00
24.90

Rs.
Rs.
Rs.
Total
Rs:

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
100.00 mt
Rate per
mt
(A+B+C+D)/100

Rs:
Rs:
Rs.

35617.5
1665
2191.7
39474.20
5374.41
44848.61
448.50

165

Canal and Allied Works - Item Unit Rates 2015-16

IRR-CAW-5-7

Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed and sides
using 1.181 Kgs of cement per each using 20 mm HG metal and placing in local filters of size
600x600x750 mm in size including Excavation of drains and Cost of procuring of all materials
including 50 m lead and for all lifts.

DATA

Rate Analysis

Unit

1 Plug

A. MATERIALS:
Sl.No
1
2
3

Particulars
Coarse aggregate
Sand (Un-Screened )
Cement
Total cost of Materials

Unit
Cum
cum
Kg

Rate in Amount in
Qty
Rs
Rs.
0.08 1210.00
97.28
0.203 560.00
113.68
1.181
6.30
7.44
Rs.
218.40

B. MACHINERY
Sl.No
1
2

Description
Excavation of drain with Excavator
Machine mixing Charges
Total hire charges of Machinery

Unit
Cum
Cum

Quantity
0.27
0.003

Rate in
Rs.

Amount in
Rs.

37.00
338.90
Total Rs.

9.99
1.02
11.01

C. LABOUR
Sl.No
1

Particulars

Unit
Day

Qty
0.30

Mazdoor
Total cost of Labour
labour component/unit qty
93.00
Add contractor's profit and overhead charges
13.615% 12.70
labour component/unit qty (including contractor's profit)
105.70
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
Rs.
Rs.
Total
Rs:

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
1.00 Plug
Rate per
each plug
(A+B+C+D)/1.0

IRR-CAW-5-8

Rate in Amount in
Rs
Rs.
310.00
93.00
Rs.
93.00

218.40
11.01
93.00
322.41

Rs:
Rs:
Rs.

43.9
366.31
366.30

Providing and constructing 0.50 m thick vertical or inclined graded filter media consisting of
15 cm thick sand layers and 20 cm thick 20 mm down coarse aggregate layer using approved
materials satisfying specified filter creteria as per specifications including cost of all materials,
machinery, labour, laying to required slope, compaction etc., complete with initial lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 cum
Rate
in Rs.
560.00

Amount
in Rs.
33600.00

Sand (Un-Screened )

cum

60.00

Coarse aggregate 20-10 mm 75 %


Coarse aggregate 10 mm down 25
%
Total cost of Materials

cum

30.00 1210.00

36300.00

cum

10.00

875.00
Rs:

8750.00
78650.00

Rate
in Rs.
0.00
0.00

Amount
in Rs.
0.00
0.00

B. MACHINERY:
Sl No
1

Description
Nil

Unit

Quantity
0.00
0.00

166

Canal and Allied Works - Item Unit Rates 2015-16

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoor

Unit
Day
Day

Quantity
1.00
36.00

Total cost of Labour


labour component/unit qty
115.60
Add contractor's profit and overhead charges
13.615% 15.70
labour component/unit qty (including contractor's profit)
131.30

Rs:

0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
11160.00
11560.00

Rs:
Rs:
Rs:
Rs:

78650.00
0.00
11560.00
90210.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100.0

IRR-CAW-5-9

Rs: 12282.09
Rs: 102492.09
Rs.
1024.90

Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm down size graded coarse
aggregates satisfying filter creteria behind rock-toe and 15 cm thick sand, 20 cm thick 20 mm
down coarse aggregate and 65 cm thick 40 mm down size coarse aggregate satisfying filter
creiteria below rock-toe as per specifications including cost of all materials, machinery, labour,
laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

UNIT :

particulars

Unit

Sand (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

cum
cum
cum
cum

B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
58.77
52.70
50.70
13.80

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoors

Unit
Day
Day

Quantity
1.00
60.00

Total cost of Labour


labour component/unit qty
108.00
Add contractor's profit and overhead charges
13.615% 14.70
labour component/unit qty (including contractor's profit)
122.70

176.00 cum
Rate
Amount
in Rs.
in Rs.
560.00 32911.20
1145.00 60341.50
1210.00 61347.00
875.00 12075.00
Rs: 166674.70

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
18600.00
19000.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
176.00 cum
Rate per
cum
(A+B+C+D)/176.0

Rs: 166674.70
Rs:
0.00
Rs: 19000.00
Rs: 185674.70
Rs: 25279.61
Rs: 210954.31
Rs.
1198.60

167

Canal and Allied Works - Item Unit Rates 2015-16

IRR-CAW-5-10 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(a)
fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
a. for aggregate and all leads for fabric and all lifts.
Using 200 gsm filter fabric.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

PP filter fabric 200 gsm


20 - 10 mm CA @ 75 %
10 mm down CA @ 25 %
Total Cost of materials

B. MACHINERY:
Sl No

Description

UNIT :
Unit
sqm
cum
cum

Unit

Quantity

Rate
in Rs.
210.00 132.00
15.00 1210.00
5.00 875.00
Rs:

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoor

Unit

100.00 sqm

Quantity

Day
Day

1.00
7.00

Total cost of Labour


labour component/unit qty
25.70
Add contractor's profit and overhead charges
13.615% 3.50
labour component/unit qty (including contractor's profit)
29.20

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
2170.00
2570.00

Rs:
Rs:
Rs:
Rs:

50245.00
0.00
2570.00
52815.00

Rs:
Rs:
Rs.

7190.76
60005.76
600.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0

Amount
in Rs.
27720.00
18150.00
4375.00
50245.00

IRR-CAW-5-11 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(b)
fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
for aggregate and all leads for fabric and all lifts.
b. Using 250 gsm filter fabric.

168

Canal and Allied Works - Item Unit Rates 2015-16

Data

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

PP filter fabric 250 gsm


20 - 10 mm CA @ 75 %
10 mm down CA @ 25 %
Total cost of Materials

sqm
cum
cum

B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate
in Rs.
210.00 154.00
15.00 1210.00
5.00 875.00
Rs:

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoor

Unit

100.00 sqm

Quantity

Day
Day

1.00
7.00

Total cost of Labour


labour component/unit qty
25.70
Add contractor's profit and overhead charges
13.615% 3.50
labour component/unit qty (including contractor's profit)
29.20

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
2170.00
2570.00

Rs:
Rs:
Rs:
Rs:

54865.00
0.00
2570.00
57435.00

Rs:
Rs:
Rs.

7819.78
65254.78
652.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0

Amount
in Rs.
32340.00
18150.00
4375.00
54865.00

IRR-CAW-6

ROCK FILL WORKS :

IRR-CAW-6-1

Providing and constructing rockfill casing to canal embankment with graded stones and
spalls from approved quarry including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Rubble stones ( at quarry )


Stone chips / spalls ( at quarry )
Total cost of Materials

cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
100.00
15.00

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Mason Cl- II
mazdoor

Unit

Quantity

Day
Day

6.00
8.00

Total cost of Labour


labour component/unit qty

100.00 cum
Rate
in Rs.
330.00
360.00
Rs:

Amount
in Rs.
33000.00
5400.00
38400.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
310.00
Rs:

Amount
in Rs.
2220.00
2480.00
4700.00

47.00

169

Canal and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


13.615% 6.40
labour component/unit qty (including contractor's profit)
53.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100.0

IRR-CAW-6-2

Note:

Rs:
Rs:
Rs:
Rs:

38400.00
0.00
4700.00
43100.00

Rs:
Rs:
Rs.

5868.07
48968.07
489.70

Providing and constructing rockfill casing to canal embankment with graded stones and
spalls available in dump yard (spoil bank) including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
Stones and spalls available in dump yard shall be issued at specified issue rate.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Rubble stones at dump yard

Stone chips ( spalls ) at dump yard


Total cost of Materials

B. MACHINERY:
Sl No

Description

UNIT :
Unit
cum

Quantity
100.00

Unit

Quantity
0.00
0.00

Total hire charges of Machinery

1
2
3

Description
Mason Cl- II
Crowbarman
mazdoor

Rate
in Rs.
165.00

Amount
in Rs.
16500.00

185.00
Rs:

2775.00
19275.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
370.00
310.00
Rs:

Amount
in Rs.
2220.00
740.00
3100.00
6060.00

Rs:
Rs:
Rs:
Rs:

19275.00
0.00
6060.00
25335.00

Rs:
Rs:
Rs.

3449.36
28784.36
287.80

15.00

Nil

C. LABOUR:
Sl No

100.00 cum

Unit
Day
Day
Day

Quantity
6.00
2.00
10.00

Total cost of Labour


labour component/unit qty
60.60
Add contractor's profit and overhead charges
13.615% 8.30
labour component/unit qty (including contractor's profit)
68.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100.0
IRR-CAW-7

CANAL LINING WORKS :

IRR-CAW-7-1

Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 98 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.

DATA:

Capacity of shovel bucket

0.50 cum

170

Canal and Allied Works - Item Unit Rates 2015-16

Capacity of shovel bucket under heaped condition


Capacity of tipper
Lead for conveyance of soil
Speed for loaded tipper under haul road condition
Speed for empty tipper under haul road condition
Turning and unloading time
Shovel digging and loading cycle per bucket
In-situ qty / bucket for 15 % bulkage of soil ( 0.58 /1.15 )
In-situ quantity per load for 20 % bulkage of soil ( 5.0 /1.2 )
Number of buckets per load ( 4.00 / 0.50 )
Cycle time for loading 8 buckets ( 8 x 32 / 60 )
Round trip cycle time for tipper:
Ideal cycle time of shovel for digging & loading
Time for 1km haulage under load ( 60 / 20 )
Time for turning and un-loading
Time for 1 km return trip ( 60 / 25 )
Time for turning and spotting

:
:
:
:
:
:
:
:
say :
say :
say :

0.58
5.00
1
20
25
2.00
32
0.50
4.00
8
4.30

:
:
:
:
:
:
:
:
say :

4.30
3.00
2.00
2.40
0.50
12.20
3
16.40
394

cum
cum
km
km / hr
km / hr
min
sec
cum
cum
buckets
min
min
min
min
min
min
min
Nos
cum
cum

Total
No. of tippers to match corrected cycle time of shovel ( 12.60 / 4.00 )
Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 12.20 )
Output for 3 tippers per day ( 3 x 16.40 x 8 )
Stripping of borrow area :
Generally borrow area is stripped once in a week for 6 days requirement of soil.
Area to be stripped assuming 2.0 m depth of cut ( 394 x 6 / 2.0 )
:
1182 sqm
Depth of stripping
:
0.2 m
Quantity of stripping considering 5 % extra area ( 1182x1.05x0.20 )
:
248 cum
Output of dozer per hr with 50 min / hr working for stripping
:
72 cum
Time required for stripping 248 cum
:
3.5 hours
Consider 5 hours including time for levelling stripped siol / shifting time.
Requirement of dozer for one day work of 394 cum
say :
1.00 hours
Collection of soil for embankment:
Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil.
Deploy 3 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.
Spreading soil in 15 cm layer:
In view of narrow width spreading soil by dozer is generally not be possible.
Soil collected in heaps along the edge of the canal can be pushed down by dozer to the extent
required and further spreading in layers of specified thickness has to be carried out by manual
labour. Deploy dozer for 2.00 hour for pushing soil.
Output of mazdoor for levelling per day
:
20 cum
Consider 27 mazdoors for levelling 551.6 cum soil including extra soil to be laid for roller
margin.
Watering;
Generally soil in the borrow area will be in moist condition. In the beginning of the season no
watering may be necessary and in summer months about 8 to 10 percent watering may be
needed to maintain soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal
average of 5 % watering by weight, the daily requirement of water for 394 cum of embankment
will be about 4 tanker loads of 8000 ltrs each.
Deploy 8000 ltr capacity water tanker for 4 hours daily for watering before rolling.
Consider 2 mazdoors for spraying water.
Compaction:
Since dozer is not considered for spreading soil about 25 percent extra roller passes needed.
Generally about 10 to 12 passes of diesel road roller is adequate for achieving 98 percent density
control for 25 cm thick loose layer.
Effective length of roller drum
:
1.50 m
Speed of roller per hour
:
3.00 km
Thickness of layer
:
0.15 m
Number of roller passes to achieve specified density control
:
12 Nos
Output of roller / hr with 50 min /hr working and 75 % effenciancy
50 / 60 ( 1.5 x 3000 x 0.15 x 0.75 / 12 )
35.15625 say :
35.15 cum/hour
Time for rolling 394 cum spread soil
11.2091 say :
11.5 hours
Sorting out/ sectioning etc :
Assume 4 mazdoors for sorting out.
No extra labour required for sectioning as trimming roller margin forms part of the soil collection
for bed lining.However 5 mazdoors considered for finishing to required slopes.

DATA:

RATE ANALYSIS

UNIT :

394.00 cum

A. MATERIALS:

171

Canal and Allied Works - Item Unit Rates 2015-16

Sl No

particulars

Nil

Unit

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Unit

Shovel 0.5 cum


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Diesel road roller 8-10 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
8.00
8.00
3.00
3.00
24.00
24.00
4.00
4.00
4.00
4.00
11.50
11.50
5.00

Quantity

1
2
3
4
5
6
7
8

Crew for Shovel


Hour
8.00
Crew for Dozer
Hour
3.00
Crew for Tipper
Hour
24.00
Crew for Pump
Hour
4.00
Crew for Water tanker
Hour
4.00
Crew for Road roller
Hour
11.50
work inspector
Day
2.00
mazdoor
Day
38.00
Total cost of Labour
labour component/unit qty
56.70
Add contractor's profit and overhead charges
13.615% 7.70
labour component/unit qty (including contractor's profit)
64.40

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1003.10
487.60
1715.50
625.30
446.70
307.20
10.20
81.30
402.50
307.20
197.20
731.40
20.00
Rs:

Amount
in Rs.
8024.80
3900.80
5146.50
1875.90
10720.80
7372.80
40.80
325.20
1610.00
1228.80
2267.80
8411.10
100.00
51025.30

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
195.90
400.00
310.00
Rs:

Amount
in Rs.
1768.00
663.00
3979.20
414.40
663.20
2252.85
800.00
11780.00
22320.65

Rs:
Rs:
Rs:
Rs:

0.00
51025.30
22320.65
73345.95

Rs:
Rs:
Rs.

9986.05
83332.00
211.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
394.00 cum
Rate per
cum
(A+B+C+D)/394.0

IRR-CAW-7-2

Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 95 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars
Nil
Total cost of Materials

UNIT :
Unit

Quantity
0.00
0.00

394.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

B. MACHINERY:

172

Canal and Allied Works - Item Unit Rates 2015-16

Sl No

Description

Unit

Shovel 0.5 cum


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Diesel road roller 8-10 tonnes
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

2
3
4
5
6
7

C. LABOUR:
Sl No

Quantity
8.00
8.00
3.00
3.00
24.00
24.00
4.00
4.00
4.00
4.00
10.00
10.00
5.00

Quantity

1
2
3
4
5
6
7
8

Crew for Shovel


Hour
8.00
Crew for Dozer
Hour
3.00
Crew for Tipper
Hour
24.00
Crew for Pump
Hour
4.00
Crew for Water tanker
Hour
4.00
Crew for Road roller
Hour
10.00
work inspector
Day
2.00
mazdoor
Day
38.00
Total cost of Labour
labour component/unit qty
55.90
Add contractor's profit and overhead charges
13.615% 7.60
labour component/unit qty (including contractor's profit)
63.50

Rate
in Rs.
1003.10
487.60
1715.50
625.30
446.70
307.20
10.20
81.30
402.50
307.20
197.20
731.40
20.00
Rs:

Amount
in Rs.
8024.80
3900.80
5146.50
1875.90
10720.80
7372.80
40.80
325.20
1610.00
1228.80
1972.00
7314.00
100.00
49632.40

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
195.90
400.00
310.00
Rs:

Amount
in Rs.
1768.00
663.00
3979.20
414.40
663.20
1959.00
800.00
11780.00
22026.80

Rs:
Rs:
Rs:
Rs:

0.00
49632.40
22026.80
71659.20

Rs:
Rs:
Rs.

9756.4
81415.60
206.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
394.00 cum
Rate per
cum
(A+B+C+D)/394.0

IRR-CAW-7-3

Providing cohesive non-swelling ( CNS ) soil lining to canal using soil collected in heaps
along the edge of canal requiring CNS soil lining as part of the disposal of excavated soil from
canal excavation in CNS soil reach including spreading in layers of thickness not more than
15 cm, breaking clods, watering, compacting to density control of not less than 95 percent
or as stipulated, dressing to required profile etc., complete with lead upto upto 50 m and all
lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nil

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Angle Dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour

Quantity
1.50
1.50
5.00
5.00

394.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
10.20
81.30

Amount
in Rs.
2573.25
937.95
51.00
406.50

173

Canal and Allied Works - Item Unit Rates 2015-16

3
4
5

Water tanker 8000 ltr


Fuel / Energy charges
Diesel road roller 8-10 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

5.00
5.00
13.00
13.00
5.00

Quantity

1
2
3
4
5
6

Crew for Dozer


Hour
1.50
Crew for Pump
Hour
5.00
Crew for Water tanker
Hour
5.00
Crew for Road roller
Hour
13.00
work inspector
Day
2.00
mazdoor
Day
38.00
Total cost of Labour
labour component/unit qty
42.70
Add contractor's profit and overhead charges
13.615% 5.80
labour component/unit qty (including contractor's profit)
48.50

402.50
307.20
197.20
731.40
20.00
Rs:

2012.50
1536.00
2563.60
9508.20
100.00
19689.00

Rate
in Rs.
221.00
103.60
165.80
195.90
400.00
310.00
Rs:

Amount
in Rs.
331.50
518.00
829.00
2546.70
800.00
11780.00
16805.20

Rs:
Rs:
Rs:
Rs:

0.00
19689.00
16805.20
36494.20

Rs:
Rs:
Rs.

4968.69
41462.89
105.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
394.00 cum
Rate per
cum
(A+B+C+D)/394.0

IRR-CAW-7-4

Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal bed level
stones including cost of all materials, labour, excavation, fixing in position to correct level etc.,
complete with lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Rough stone 20x20x75 cm

UNIT :
Unit
Each

Quantity
32.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

1
2
3

Unit

Quantity

work inspector
Day
1.00
Stone chiseller Cl- I
Day
2.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
57.80
Add contractor's profit and overhead charges
13.615% 7.90
labour component/unit qty (including contractor's profit)
65.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

32 Nos.
Rate
in Rs.
23.00
0.00
Rs:

Amount
in Rs.
736.00
0.00
736.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
400.00
415.00
310.00
Rs:

Amount
in Rs.
400.00
830.00
620.00
1850.00

Rs:
Rs:
Rs:

736.00
0.00
1850.00

0.00

174

Canal and Allied Works - Item Unit Rates 2015-16

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
32.00 Nos.
Rate per
each
(A+B+C+D)/32.0

IRR-CAW-7-5

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Rs:
Rs:
Rs.

352.08
2938.08
91.80

UNIT : 1000.00 kg

particulars

Unit

Rein.Steel with 5 % wastage


Binding wire 1.25 mm dia
Sundries ( chairs / spacers etc )
Total cost of Materials

kg
kg
LS

B. MACHINERY:
Sl No

Description

Unit

Quantity
1050.00
8.00
10.00

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Bar bender
mazdoor

Unit

Quantity

Day
Day

6.00
11.00

Total cost of Labour


labour component/unit qty
6.40
Add contractor's profit and overhead charges
13.615% 0.90
labour component/unit qty (including contractor's profit)
7.30

Rate
in Rs.
40.00
70.00
20.00
Rs:

Amount
in Rs.
42000.00
560.00
200.00
42760.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
490.00
310.00
Rs:

Amount
in Rs.
2940.00
3410.00
6350.00

Rs:
Rs:
Rs:
Rs:

42760.00
0.00
6350.00
49110.00

Rs:
Rs:
Rs.

6686.33
55796.33
55.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
1000.00 kg
Rate per
kg
(A+B+C+D)/1000.0

DATA:

2586.00

Providing, fabricating and placing in position reinforcement steel bars for RCC works
including cleaning, straightening, cutting, bending, hooking, lapping, tying with 1.25 mm dia.
soft annealed steel wire, welding wherever required including cost of all materials, machinery,
labour etc., complete with initial lead upto 50 and all lifts.

DATA

IRR-CAW-7-6

Rs:

Providing and laying 75 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,
finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (22.5 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:79.2 cum including the extra quantity of
concrete for curvatures and bends etc.,)
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
1
2

Cement 43 Gr
Coarse aggregate 20-10 mm

UNIT :
Unit
kg
cum

960 sqm

Quantity

Rate
Amount
in Rs.
in Rs.
23760.00
6.30 149688.00
41.18 1210.00 49832.64

175

Canal and Allied Works - Item Unit Rates 2015-16

3
4
5
6
7

Coarse aggregate 10-4.75 mm


Fine aggregate (Un-Screened )
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Sundries
Total cost of Materials

cum
cum
kg
Rm
sqm
LS

22.18
35.64
95.04
640.00
960.00
5.00

Unit

Quantity

Batching plant
Lubricants etc @ 5 %
Transit mixer 3 Nos
Fuel / Energy charges
Mechanical paver
Lubricants etc @ 5 %
DG set for batching plant 50 KVA
Fuel / Energy charges
DG set for paver 30 KVA
Fuel / Energy charges
Shovel 0.5 cum / Loader
Fuel / Energy charges
Water tanker
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
24.00
24.00
8.00
8.00
8.00
8.00
8.00
8.00
2.00
2.00
8.00
8.00

Pump 5 hp(diesel) 2 Nos. 4 hrs each


Fuel / Energy charges
Sundries ( power line etc )
Total hire charges of Machinery

Hour
Hour
LS

8.00
8.00
5.00

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

8
9

C. LABOUR:
Sl No
Description

Unit

Quantity

1
2
3
4
5
6
7
8
9
10
11
12
13
14

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8.00
Crew for Pump
Hour
16
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
26.10
Add contractor's profit and overhead charges
13.615% 3.60
labour component/unit qty (including contractor's profit)
29.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for shifting & re-erection of BP @
Add for LH / RH shifting & erection of Paver @
Add for ledge cutting / erection of tracks etc @

2%
0.5%
1%

875.00 19404.00
560.00 19958.40
95.00
9028.80
47.00 30080.00
0.88
842.40
20.00
100.00
Rs: 278934.24

Rate
in Rs.
405.40
20.27
758.40
893.90
356.50
17.83
85.10
975.20
65.80
650.10
1003.10
487.60
402.50
307.20

Amount
in Rs.
3243.20
162.16
18201.60
21453.60
2852.00
142.60
680.80
7801.60
526.40
5200.80
2006.20
975.20
3220.00
2457.60

10.20
81.30
20.00
Rs:

81.60
650.40
100.00
69755.76

Rate
Amount
in Rs.
in Rs.
318.20
2545.60
265.20
6364.80
391.90
3135.20
122.50
1960.00
221.00
442.00
165.80
1326.40
103.60
1657.60
415.00
830.00
415.00
415.00
415.00
415.00
480.00
480.00
400.00
800.00
310.00
1550.00
310.00
3100.00
Rs:
25021.60

Rs:
278934.24
Rs:
69755.76
Rs:
25021.6
Total
Rs:373711.6
Rs:
7474.232
Rs:
1868.558
Rs:
3737.116
Total
Rs: 386791.51
13.615%
Rs: 52661.66
cum @
31.3 Rs./Cum
1115.532
cum @
30.2 Rs./Cum1913.47

D. Add for contractor's profit and overheads on (A+B+C+other


Lead Charges for 1 Km for FA
35.64
Lead Charges for 1 Km for CA
63.36
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
23.76
tonne @

129.7 Rs./Tonne
3081.672

176

Canal and Allied Works - Item Unit Rates 2015-16

Total cost for


Rate per
sqm

IRR-CAW-7-7

DATA:

960.00 sqm
(A+B+C+D)/960.0

Rs: 445563.84
Rs.
464.10

Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,
finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (24 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:84.48 cum including the extra quantity of
concrete for curvatures and bends etc.,)

RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
1
2
3
4
5
6
7

Unit

Quantity

kg
cum
cum
cum
kg
Rm
sqm
LS

25344.00
43.93
23.65
38.02
101.38
640.00
960.00
5.00

Unit

Quantity

Batching plant
Lubricants etc @ 5 %
Transit mixer 3 Nos
Fuel / Energy charges
Mechanical paver
Lubricants etc @ 5 %
DG set for batching plant 50 KVA
Fuel / Energy charges
DG set for paver 30 KVA
Fuel / Energy charges
Shovel 0.5 cum / Loader
Fuel / Energy charges
Water tanker
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
24.00
24.00
8.00
8.00
8.00
8.00
8.00
8.00
2.00
2.00
8.00
8.00

Pump 5 hp(diesel) 2 Nos. 4 hrs each


Fuel / Energy charges
Sundries ( power line etc )
Total hire charges of Machinery

Hour
Hour
LS

8.00
8.00
5.00

Cement 43 Gr
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

8
9

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
10
11

UNIT :

Crew for Batching plant


Crew for Transit mixer
Crew for Concrete paver
Crew for DG set
Crew for Shovel
Crew for Water tanker
Crew for Pump
Mason Class I
Mechanic
Fitter
Electrician

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day

Quantity
8.00
24.00
8.00
16.00
2.00
8.00
16
2
1
1
1

960 sqm
Rate
Amount
in Rs.
in Rs.
6.30 159667.20
1210.00 53154.82
875.00 20697.60
560.00 21288.96
95.00
9630.72
47.00 30080.00
0.88
842.40
20.00
100.00
Rs: 295461.70

Rate
in Rs.
405.40
20.27
758.40
893.90
356.50
17.83
85.10
975.20
65.80
650.10
1003.10
487.60
402.50
307.20

Amount
in Rs.
3243.20
162.16
18201.60
21453.60
2852.00
142.60
680.80
7801.60
526.40
5200.80
2006.20
975.20
3220.00
2457.60

10.20
81.30
20.00
Rs:

81.60
650.40
100.00
69755.76

Rate
Amount
in Rs.
in Rs.
318.20
2545.60
265.20
6364.80
391.90
3135.20
122.50
1960.00
221.00
442.00
165.80
1326.40
103.60
1657.60
415.00
830.00
415.00
415.00
415.00
415.00
480.00
480.00

177

Canal and Allied Works - Item Unit Rates 2015-16

12
13
14

work inspector
Day
2 400.00
mazdoor ( BP site )
Day
5 310.00
mazdoor ( Paver site )
Day
10 310.00
Total cost of Labour
Rs:
labour component/unit qty
26.10
Add contractor's profit and overhead charges
13.615% 3.60
labour component/unit qty (including contractor's profit)
29.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for shifting & re-erection of BP @
Add for LH / RH shifting & erection of Paver @
Add for ledge cutting / erection of tracks etc @

2%
0.5%
1%

Rs:
295461.70
Rs:
69755.76
Rs:
25021.6
Total
Rs:
390239.06
Rs:
7804.7811
Rs:
1951.1953
Rs:
3902.3906
Total
Rs: 403897.42
13.615%
Rs: 54990.63
cum @
31.3 Rs./Cum
1189.9008
cum @
30.2 Rs./Cum2041.04

D. Add for contractor's profit and overheads on (A+B+C+other


Lead Charges for 1 Km for FA
38.02
Lead Charges for 1 Km for CA
67.58
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
25.34
tonne @
Total cost for
960.00 sqm
Rate per
sqm
(A+B+C+D)/960.0

IRR-CAW-7-8

DATA:

800.00
1550.00
3100.00
25021.60

129.7 Rs./Tonne
3287.1168
Rs: 465406.11
Rs.
484.80

Providing and laying 100 mm thick in situ M-15 (28 days cube compressive strength not less than
15 N /Sqmm ) grade cement concrete with 20 mm down size approved, clean, hard, graded
aggregates for canal lining using, vibrating, cylinder type mechanical paver including cost of all
materials, machinery, labour, cleaning, batching, mixing, placing in position, finishing, forming
contraction joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to othere
side of canal etc., complete with initial lead upto 1 Km and all lifts.
(43 Gr Cement content: 300 kg /cum (30 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:88 cum including the extra quantity of
concrete for curvatures and bends etc.,)

RATE ANALYSIS
A. MATERIALS:
Sl.No
Particulars
1
Cement 43 Gr
2
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
3
Fine aggregate (Un-Screened)
4
Super plasticiser
5
PVC sealing strip
6
Use rate of paving cylinder
Total cost of Materials
B. MACHINERY:
Sl.No
Particulars
1
Batching plant
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
7
Water tanker
Fuel / Energy charges
Pump 5 hp (diesel) 2 Nos. 4 hrs
8
each

UNIT

Unit
Kg
cum
cum
cum
kg
Rm
sqm

Qty

Rate in Rs.
Amount
26400
6.30 166320.00
45.76 1210.00 55369.60
24.64 875.00 21560.00
39.6 560.00 22176.00
105.6
95.00 10032.00
533
47.00 25051.00
800 0.8775
702.00
Rs.
301210.6

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Qty

Rate in Rs.
Amount
8 405.40
3243.20
24 758.40 18201.60
24 893.90 21453.60
8 356.50
2852.00
8
17.83
142.60
8
85.10
680.80
8 975.20
7801.60
8
65.80
526.40
8 650.10
5200.80
2.00 1003.10
2006.20
2.00 487.60
975.20
8 402.50
3220.00
8 307.20
2457.60

Hour

800 Sqm

10.20

81.60

178

Canal and Allied Works - Item Unit Rates 2015-16

Fuel / Energy charges


Total hire charges of Machinery
C. LABOUR:
Sl No
Description

Unit

Quantity

1
2
3
4
5
6
7
8
9
10
11
12
13
14

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8
Crew for Pump
Hour
8
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
30.20
Add contractor's profit and overhead charges
13.615% 4.10
labour component/unit qty (including contractor's profit)
34.30

81.30
Rs.

650.40
69493.6

Rate
Amount
in Rs.
in Rs.
318.20
2545.60
265.20
6364.80
391.90
3135.20
122.50
1960.00
221.00
442.00
165.80
1326.40
103.60
828.80
415.00
830.00
415.00
415.00
415.00
415.00
480.00
480.00
400.00
800.00
310.00
1550.00
310.00
3100.00
Rs:
24192.80

ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
301210.6
Rs.
69493.6
Rs.
24192.80
TOTAL Rs. 394897
Add for shifting & re-erection of BP @
2% Rs.
7897.94
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
1974.485
Add for ledge cutting / erection of tracks etc @
1% Rs.
3948.97
Total
Rs: 408718.40
D. Add for contractor's profit and overheads on (A+B+C+other 13.615%
Rs: 55647.01
Lead Charges for 1 Km for FA
39.60
cum @
31.3 Rs./Cum1239.48
Lead Charges for 1 Km for CA
70.40
cum @
30.2 Rs./Cum2126.08
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
26.40
tonne @ 129.7 Rs./Tonne
3424.08
Total cost for
800.00 Sqm
Rs: 471155.05
Rate per
Sqm
(A+B+C+D)/800.0
Rs.
588.90

IRR-CAW-7-9

Note:

Dismantling, shifting and re-erecting mechanical concrete paver and DG set with all
accessories across canal CD work or other locations wherever shifting and re-erecting is
necessary including aligning paver correctly for continuing canal lining work, cost of all
materials, machinery, labour etc., complete with all leads and lifts.
Local shifting and re-erection of paver for LH and RH side lining included in concrete lining rates
under items IRR-CAW-7-7 and IRR-CAW-7-8 and saperate rate for shifting shall not be allowed.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Tipper
Fuel / Energy charges
Sundries (ropes / rails etc)

Unit
Hour
Hour
LS

Quantity
4.00
1.00
1.00

1.00 Shifting
Rate
in Rs.
0.00

Amount
in Rs.

Rs:

0.00

Rate
in Rs.
446.70
307.20
20.00

Amount
in Rs.
1786.8
307.2
20

179

Canal and Allied Works - Item Unit Rates 2015-16

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
Crew for Tipper
Crew for Paver
mazdoor

Unit
Hour
Hour
Day

Quantity
4.00
8.00
6.00

Total cost of Labour


labour component/unit qty
5658.40
Add contractor's profit and overhead charges
13.615% 770.40
labour component/unit qty (including contractor's profit)
6428.80

Rs:

2114.00

Rate
in Rs.
165.80
391.90
310.00
Rs:

Amount
in Rs.
663.2
3135.2
1860
5658.40

Rs:
Rs:
Rs:
Rs:

0.00
2114.00
5658.40
7772.40

Rs:
Rs:
Rs.

1058.21
8830.61
8830.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
1.00 Shifting
Rate per
Shifting
(A+B+C+D)/1.0

IRR-CAW-7-10 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

3
4
6
7

particulars

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

Description

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS

Unit

Quantity
7042.5

28.17 cum
Rate
in Rs.
6.30

Amount
in Rs.
44367.75

140.85
6.30
887.355
12.68 1145.00 14514.593
7.61 1210.00 9203.139
5.07 875.00 4436.775
11.27 560.00
6310.08
28.17
95.00
2676.15
180
27.37
4925.94
2
20.00
40
Rs: 87361.78

Quantity

Rate
in Rs.

Amount
in Rs.

180

Canal and Allied Works - Item Unit Rates 2015-16

1
2
3

C. LABOUR:
Sl No

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
162.50
10.20
81.30
402.50
307.20

1483.2
2600
5.1
40.65
402.5
307.2

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
20.60
Rs:

121.6
329.6
5289.85

Description

Unit

Rate
in Rs.
204.10
103.60
165.80
146.90
400.00
415.00
415.00

Amount
in Rs.
3265.6
51.8
165.8
2350.4
400
830
415

310.00
310.00
310.00
310.00
310.00
Rs:

6820
2480
1860
8732.7
620
27991.30

Quantity

1
2
3
4
5
6
7
8

Crew for Concrete mixer


Hour
16.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Needle vibrator
Hour
16.00
work inspector
Day
1.00
Mason Class-I
Day
2.00
Fitter
Day
1.00
mazdoor
for batching materials
Day
22.00
for loading mortar pans
Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
28.17
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
993.70
Add contractor's profit and overhead charges
13.615% 135.30
labour component/unit qty (including contractor's profit)
1129.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
28.17 cum
Rate per
cum
(A+B+C+D)/28.17

Rs: 87361.78
Rs:
5289.85
Rs: 27991.30
Rs: 120642.93
Rs: 16425.54
Rs: 137068.47
Rs.
4865.80

IRR-CAW-7-11 Providing and laying insitu vibrated M-10 (28 days cube compressive strength not less than
10 N/sqm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregade for bed and side lining of canal(100 mm thick) including, finishing the junction of bed and sides
to required curvature, cost of all materials, machinery, labour, formwork including supports
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead up to 50 m and all lifts (Cement content: 250 kg/cum)
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl.No
Particulars
1
Cement for mix

3
4

Cement for incidentals @ 5 Kg / cum


Coarse aggregate 40mm
Coarse aggregate 20 mm .
Coarse aggregate 10 mm .
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT:

Unit
kg
kg
cum
cum
cum
cum
kg

27 cum

Qty Rate in Rs. Amount


6750
6.30 42525.00
135
6.30
12.15 1145.00
7.29 1210.00
4.86 875.00
10.8 560.00
27
95.00

850.50
13911.75
8820.90
4252.50
6048.00
2565.00

181

Canal and Allied Works - Item Unit Rates 2015-16

Use rate of manual paver

sqm

270

Total cost of Materials


B. MACHINERY:
Sl.No
1
2
3

C. LABOUR:
Sl No

Particulars

Unit

Qty

27.37
Total Rs.
Rs.

7388.91
86362.56
86362.56

Rate in Rs. Amount

Concrete mixer 600/400 ltr (diesel)


Fuel / Energy charges
5 hp pump (diesl)
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
162.50
10.20
81.30
402.50
307.20

1483.20
2600.00
5.10
40.65
402.50
307.20

Needle vibrator 40 mm die (petrol)


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

4.00
4.00

7.60
20.60
Rs.

30.40
82.40
4951.45

Rate
in Rs.
204.10
103.60
165.80
146.90
400.00
415.00
415.00

Amount
in Rs.
3265.6
51.8
165.8
2350.4
400
830
415

310.00
310.00
310.00
310.00
310.00
Rs:

6820
2480
1860
8370
620
27628.60

Description

Unit

Quantity

1
2
3
4
5
6
7
8

Crew for Concrete mixer


Hour
16.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Needle vibrator
Hour
16.00
work inspector
Day
1.00
Mason Class-I
Day
2.00
Fitter
Day
1.00
mazdoor
for batching materials
Day
22.00
for loading mortar pans
Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
27.00
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
1023.30
Add contractor's profit and overhead charges
13.615% 139.30
labour component/unit qty (including contractor's profit)
1162.60
ABSTRACT:
A. Cost of Materials including royalty charges
B. Hire charges of Machinery
C. Cost of Labour

Rs.
86362.56
Rs.
4951.45
Rs.
27628.60
Total Rs. 118942.61

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
27.00 cum
Rate per
cum
(A+B+C+D)/27.0

Rs: 16194.04
Rs: 135136.65
Rs.
5005.10

IRR-CAW-7-12 Providing and laying100mm thick insitu vibrated M-10 (28 days cube compressive strength-not less than
10.00 N / sq mm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contraction joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1 km lead & all lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl.No
Particulars
1
Cement 43 Gr
2
Coarse aggregate 40 mm
Coarse aggregate 20 mm

UNIT
Unit
Kg
cum
cum

800 Sqm
Qty Rate in Rs. Amount
22000.00
6.30
138600
39.60 1145.00
45342
23.76 1210.00
28749.6

182

Canal and Allied Works - Item Unit Rates 2015-16

3
4
5
6

Coarse aggregate 10 mm
Fine aggregate (Un-Screened)
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Total cost of Materials

B. MACHINERY:
Sl.No
Particulars
1
Batching plant
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
7
Water tanker
Fuel / Energy charges
Pump 5 hp (diesel) 2 Nos. 4 hrs
8
each
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

cum
cum
kg
Rm
sqm

15.84
35.20
88.00
533.00
800.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Qty Rate in Rs. Amount


8.00 405.40
3243.2
24.00 758.40
18201.6
24.00 893.90
21453.6
5.00 356.50
1782.5
5.00
17.83
89.125
8.00
85.10
680.8
8.00 975.20
7801.6
8.00
65.80
526.4
8.00 650.10
5200.8
2.00 1003.10
2006.20
2.00 487.60
975.20
8.00 402.50
3220
8.00 307.20
2457.6

Hour
Hour

Unit

8.00
8.00

Quantity

1
2
3
4
5
6
7
8
9
10
11
12
13
14

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8
Crew for Pump
Hour
8
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
30.20
Add contractor's profit and overhead charges
13.615% 4.10
labour component/unit qty (including contractor's profit)
34.30

875.00
13860
560.00
19712
95.00
8360
47.00
25051
0.878
702
Rs.
280376.60

10.20
81.30
Rs.

81.6
650.4
68370.63

Rate
Amount
in Rs.
in Rs.
318.20
2545.60
265.20
6364.80
391.90
3135.20
122.50
1960.00
221.00
442.00
165.80
1326.40
103.60
828.80
415.00
830.00
415.00
415.00
415.00
415.00
480.00
480.00
400.00
800.00
310.00
1550.00
310.00
3100.00
Rs:
24192.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
280376.60
Rs.
68370.63
Rs.
24192.80
TOTAL Rs.372940.03
Add for shifting & re-erection of BP @
2% Rs.
7458.8
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
1864.7
Add for ledge cutting / erection of tracks etc @
1% Rs.
3729.4
Total
Rs: 385992.93
D. Add for contractor's profit and overheads on (A+B+C+other 13.615%
Rs: 52552.94
Lead Charges for 1 Km for FA
35.20
cum @
31.3 Rs./Cum1101.76
Lead Charges for 1 Km for CA
79.20
cum @
30.2 Rs./Cum2391.84
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per
Sqm

22.00
tonne @
800.00 Sqm
(A+B+C+D)/800.0

129.7 Rs./Tonne
2853.4
Rs: 444892.87
Rs.
556.10

183

Canal and Allied Works - Item Unit Rates 2015-16

IRR-CAW-7-13 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

1
2
3

C. LABOUR:
Sl No

particulars

UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
LS

Quantity

27.00 cum
Rate
in Rs.
6.30

Amount
in Rs.
42525

135
6.30
14.04 1210.00
7.56 875.00
12.15 560.00
27
95.00
270
27.37
2
20.00
Rs:

850.5
16988.4
6615
6804
2565
7388.91
40
83776.81

6750

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
162.50
10.20
81.30
402.50
307.20

1483.2
2600
5.1
40.65
402.5
307.2

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
20.60
Rs:

121.6
329.6
5289.85

Description

Unit

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00
415.00

Amount
in Rs.
3265.6
51.8
165.8
2350.40
830
400
415

310.00
310.00
310.00
310.00
310.00
Rs:

6820
2480
1860
8370
620
27628.60

Rs:
Rs:
Rs:

83776.81
5289.85
27628.60

1
2
3
4
5
6
7
8

Quantity

Quantity

Crew for Concrete mixer


Hour
16.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
16.00
Mason Class-I
Day
2.00
work inspector
Day
1.00
Fitter
Day
1.00
mazdoor
for batching materials
Day
22.00
for loading mortar pans
Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
27.00
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
1023.30
Add contractor's profit and overhead charges
13.615% 139.30
labour component/unit qty (including contractor's profit)
1162.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rate
in Rs.

Amount
in Rs.

184

Canal and Allied Works - Item Unit Rates 2015-16

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
27.00 cum
Rate per
cum
(A+B+C+D)/27.0

Rs: 116695.26
Rs: 15888.06
Rs: 132583.32
Rs.
4910.50

IRR-CAW-7-14 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 290 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

1
2
3

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

particulars

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS

Quantity

24.92 cum
Rate
in Rs.
6.30

Amount
in Rs.
45528.84

124.6
6.30
11.21 1145.00
6.73 1210.00
4.49 875.00
9.97 560.00
28.91
95.00
166.14
27.37
2
20.00
Rs:

784.98
12840.03
8141.364
3924.90
5582.08
2746.18
4546.64
40.00
84135.02

7226.8

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
162.50
10.20
81.30
402.50
307.20

1483.20
2600.00
5.10
40.65
402.50
307.20

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
20.60
Rs:

121.60
329.60
5289.85

Description

Unit

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00
415.00

Amount
in Rs.
3265.6
51.80
165.8
2350.40
830
400
415

310.00
310.00
310.00
310.00
310.00
Rs:

6820
2480
1860
7725.2
620
26983.80

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
Fitter
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Total cost of Labour
labour component/unit qty

Quantity

Quantity

Hour
Hour
Hour
Hour
Day
Day
Day

16.00
0.50
1.00
16.00
2.00
1.00
1.00

Day
Day
Day
Day
Day

22.00
8.00
6.00
24.92
2.00

Rate
in Rs.

Amount
in Rs.

1082.80

185

Canal and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


13.615% 147.40
labour component/unit qty (including contractor's profit)
1230.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
24.92 cum
Rate per
cum
(A+B+C+D)/24.92

Rs: 84135.02
Rs:
5289.85
Rs: 26983.80
Rs: 116408.67
Rs: 15849.04
Rs: 132257.71
Rs.
5307.30

IRR-CAW-7-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(100 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 300 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
6
7

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

1
2
3

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

particulars

UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
LS

Quantity

23.10 cum
Rate
in Rs.
6.30

Amount
in Rs.
43659

115.5
6.30
12.01 1210.00
6.47 875.00
10.40 560.00
27.72
95.00
231
27.37
2
20.00
Rs:

727.65
14534.52
5659.5
5821.2
2633.40
6321.62
40
79396.89

6930

Description

Unit

Quantity

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
162.50
10.20
81.30
402.50
307.20

1483.2
2600
5.1
40.65
402.5
307.2

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
20.60
Rs:

121.6
329.6
5289.85

Description

Unit

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
Fitter
mazdoor
for batching materials

Hour
Hour
Hour
Hour
Day
Day
Day

16.00
0.50
1.00
16.00
2.00
1.00
1.00

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00
415.00

Amount
in Rs.
3265.6
51.8
165.8
2350.4
830
400
415

Day

22.00

310.00

6820

Quantity

Rate
in Rs.

Amount
in Rs.

186

Canal and Allied Works - Item Unit Rates 2015-16

for loading mortar pans


Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
23.10
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
1143.70
Add contractor's profit and overhead charges
13.615% 155.70
labour component/unit qty (including contractor's profit)
1299.40

310.00
310.00
310.00
310.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
23.10 cum
Rate per
cum
(A+B+C+D)/23.10

2480
1860
7161
620
26419.60

Rs: 79396.89
Rs:
5289.85
Rs: 26419.60
Rs: 111106.34
Rs: 15127.13
Rs: 126233.47
Rs.
5464.70

IRR-CAW-7-16 Providing and laying150mm thick insitu vibrated M-15 (28 days cube compressive strength-not less than
15.00 N / sq mm) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contractiom joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1km lead & all lifts.
(43 Gr Cement content: 300 kg /cum (45 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.44 cum equivalent concrete volume:132 cum including the extra quantity of
concrete for curvatures and bends etc.,)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl.No
Particulars
1
Cement 43 Gr
2
Coarse aggregate 20 mm
Coarse aggregate 10 mm
3
Fine aggregate (Un-Screened)
4
Super plasticiser
5
PVC sealing strip
6
Use rate of paving cylinder
Total cost of Materials
B. MACHINERY:
Sl.No
Particulars
1
Batching plant
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
7
Water tanker
Fuel / Energy charges
Pump 5 hp (diesel) 2 Nos. 4 hrs
8
each
Fuel / Energy charges
Total hire charges of Machinery

UNIT

800 Sqm

Unit
Kg
cum
cum
cum
kg
Rm
sqm

Qty Rate in Rs. Amount


39600.00
6.30
249480
68.64 1210.00
83054.4
36.96 875.00
32340
58.08 560.00
32524.8
158.40
95.00
15048
533.00
47.00
25051
800.00
0.878
702
Rs.
438200.20

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Qty Rate in Rs. Amount


8.00 405.40
3243.2
24.00 758.40
18201.6
24.00 893.90
21453.6
5.00 356.50
1782.5
5.00
17.83
89.125
8.00
85.10
680.8
8.00 975.20
7801.6
8.00
65.80
526.4
8.00 650.10
5200.8
2.00 1003.10
2006.20
2.00 487.60
975.20
8.00 402.50
3220
8.00 307.20
2457.6

Hour
Hour

8.00
8.00

10.20
81.30
Rs.

81.6
650.4
68370.63

C. LABOUR:

187

Canal and Allied Works - Item Unit Rates 2015-16

Sl No

Description

Unit

Quantity

1
2
3
4
5
6
7
8
9
10
11
12
13
14

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8
Crew for Pump
Hour
8
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
30.20
Add contractor's profit and overhead charges
13.615% 4.10
labour component/unit qty (including contractor's profit)
34.30

Rate
Amount
in Rs.
in Rs.
318.20
2545.60
265.20
6364.80
391.90
3135.20
122.50
1960.00
221.00
442.00
165.80
1326.40
103.60
828.80
415.00
830.00
415.00
415.00
415.00
415.00
480.00
480.00
400.00
800.00
310.00
1550.00
310.00
3100.00
Rs:
24192.80

ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
438200.20
Rs.
68370.63
Rs.
24192.80
TOTAL Rs.530763.63
Add for shifting & re-erection of BP @
2% Rs.
10615.27
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
2653.82
Add for ledge cutting / erection of tracks etc @
1% Rs.
5307.64
Total
Rs: 549340.36
D. Add for contractor's profit and overheads on (A+B+C+other 13.615%
Rs: 74792.69
Lead Charges for 1 Km for FA
58.08
cum @
31.3 Rs./Cum
1817.904
Lead Charges for 1 Km for CA
105.60
cum @
30.2 Rs./Cum3189.12
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
39.60
tonne @ 129.7 Rs./Tonne
5136.12
Total cost for
800.00 Sqm
Rs: 634276.19
Rate per
Sqm
(A+B+C+D)/800.0
Rs.
792.80

IRR-CAW-7-17 Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15 grade
concrete using 20 mm down size coarse aggregates and 10 kg reinforcement steel moulded
as per specifications and drawing in CM 1:4 proportion including cost of all materials,
machinery, labour, formwork, fabricating and placing reinforcement steel, mixing, laying,
conveying and fixing in position including necessary excavation for seating, finishing joints in
CM 1:4, curing etc., complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

particulars

Cement 43 Gr
Sand (Un-Screened )
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Reinforcement steel
Binding wire

UNIT :
Unit
kg
cum
cum
cum
kg
kg

Quantity
310.00
0.50
0.50
0.30
200.00
3.00

20.00 templete
Rate
in Rs.
6.30
560.00
1210.00
875.00
40.00
70.00

Amount
in Rs.
1953
280
605
262.5
8000
210

188

Canal and Allied Works - Item Unit Rates 2015-16

6
7

Use rate of mould


Sundries( water charges & misc. )
Total cost of Materials

B. MACHINERY:
Sl No
1

Description

Hand mixer

set
LS

Unit
Hour

20.00
1.00

Quantity
8.00
8.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

1
2
3
4
5

work inspector
Day
1.00
Mason Class I for fixing
Day
1.00
Mason Class II for casting
Day
2.00
Bar bender
Day
1.00
mazdoor ( casting yard )
Day
4.00
mazdoor ( for fixing )
Day
2.00
mazdoor for conveying
Day
2.00
Total cost of Labour
labour component/unit qty
226.30
Add contractor's profit and overhead charges
13.615% 30.80
labour component/unit qty (including contractor's profit)
257.10
ABSTRACT:
A. Cost of Materials including serignorage charges
B. Hire charges of Machinery
C. Cost of Labour

57.09 1141.7956
20.00
20
Rs: 12472.30

Rate
in Rs.
5.50
0.00
Rs:

Amount
in Rs.
44
0
44.00

Rate
in Rs.
400.00
415.00
370.00
490.00
310.00
310.00
310.00
Rs:

Amount
in Rs.
400
415
740
490
1240
620
620
4525.00

Rs: 12472.30
Rs:
44.00
Rs:
4525.00
Total
Rs: 17041.30
13.615%
Rs:
2320.17
cum @
31.3 Rs./Cum 15.65
cum @
30.2 Rs./Cum 24.16

D. Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1 Km for FA
0.50
Lead Charges for 1 Km for CA
0.80
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
0.31
tonne @
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
0.20
tonne @
Total cost for
20.00 templete
Rate per
templete
(A+B+C+D)/20.0

129.7 Rs./Tonne
40.207
151.5 Rs./Tonne 30.3
Rs: 19471.78
Rs.
973.60

IRR-CAW-7-18 Providing and fixing 50 mm dia perforated GI pressure relief pipes 12.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia 10 Nos

Rm

1.25

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes


Total hire charges of Machinery

Unit
LS

Quantity
0.50
0.00

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
400

20.00
Rs:

200
600.00

Rate
in Rs.
20.00

Amount
in Rs.
10

Rs:

10.00

C. LABOUR:

189

Canal and Allied Works - Item Unit Rates 2015-16

Sl No
1

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
39.50
Add contractor's profit and overhead charges
13.615% 5.40
labour component/unit qty (including contractor's profit)
44.90

Rate
in Rs.
480.00
310.00
Rs:

Amount
in Rs.
240
155
395.00

Rs:
Rs:
Rs:
Rs:

600.00
10.00
395.00
1005.00

Rs:
Rs:
Rs.

136.83
1141.83
114.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Nos.
Rate per
each
(A+B+C+D)/10.0

IRR-CAW-7-19 Providing and fixing 50 mm dia perforated GI pressure relief pipes 22.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia 10 Nos

Rm

2.25

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit

Quantity

LS

5.00
0.00

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
720

20.00
Rs:

200
920.00

Rate
in Rs.
20.00

Amount
in Rs.
100

Rs:

100.00

Rate
in Rs.
480.00
310.00
Rs:

Amount
in Rs.
240
155
395.00

Rs:
Rs:
Rs:
Rs:

920.00
100.00
395.00
1415.00

Rs:
Rs:
Rs.

192.65
1607.65
160.80

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
39.50
Add contractor's profit and overhead charges
13.615% 5.40
labour component/unit qty (including contractor's profit)
44.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Nos.
Rate per
No.
(A+B+C+D)/10.0

IRR-CAW-7-20 Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged

190

Canal and Allied Works - Item Unit Rates 2015-16

to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia 10 Nos

Rm

3.00

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit

Quantity

LS

7.00
0.00

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
960.00

20.00
Rs:

200.00
1160.00

Rate
in Rs.
20.00

Amount
in Rs.
140.00

Rs:

140.00

Rate
in Rs.
480.00
310.00
Rs:

Amount
in Rs.
240.00
155.00
395.00

Rs:
Rs:
Rs:
Rs:

1160.00
140.00
395.00
1695.00

Rs:
Rs:
Rs.

230.77
1925.77
192.60

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
39.50
Add contractor's profit and overhead charges
13.615% 5.40
labour component/unit qty (including contractor's profit)
44.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Nos.
Rate per
No.
(A+B+C+D)/10.0

IRR-CAW-7-21 Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia 10 Nos

Rm

4.50

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit
LS

Quantity
10.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
1440.00

20.00
Rs:

200.00
1640.00

Rate
in Rs.
20.00

Amount
in Rs.
200.00

Rs:

200.00

Rate
in Rs.

Amount
in Rs.

191

Canal and Allied Works - Item Unit Rates 2015-16

Pipe fitter
mazdoor

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
39.50
Add contractor's profit and overhead charges
13.615% 5.40
labour component/unit qty (including contractor's profit)
44.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Nos.
Rate per
No.
(A+B+C+D)/10.0

480.00
310.00
Rs:

240.00
155.00
395.00

Rs:
Rs:
Rs:
Rs:

1640.00
200.00
395.00
2235.00

Rs:
Rs:
Rs.

304.3
2539.30
253.90

IRR-CAW-7-22 Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia

Rm

7.50

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit
LS

Quantity
15.00
0.00

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
2400.00

20.00
Rs:

200.00
2600.00

Rate
in Rs.
20.00

Amount
in Rs.
300.00

Rs:

300.00

Rate
in Rs.
480.00
310.00
Rs:

Amount
in Rs.
240.00
155.00
395.00

Rs:
Rs:
Rs:
Rs:

2600.00
300.00
395.00
3295.00

Rs:
Rs:
Rs.

448.61
3743.61
374.40

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
39.50
Add contractor's profit and overhead charges
13.615% 5.40
labour component/unit qty (including contractor's profit)
44.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Nos.
Rate per
No.
(A+B+C+D)/10.0

IRR-CAW-7-23 Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep holes
including cost of all materials, labour, drilling 8 mm dia holes etc. complete with all
leads and lifts.

192

Canal and Allied Works - Item Unit Rates 2015-16

DATA

RATE ANALYSIS

UNIT:

10 Nos.

A. MATERIALS:
Sl.No
1

Particulars
PVC pipe 100 mm dia 10 Nos
Total cost of Materials

Unit
Rm

Qty
10.00

Rate in Amount in
Rs
Rs.
175.00
1750.00
Rs.
1750.00

B. MACHINERY
Sl.No
1

Description

Unit

Rate in Amount in
Rs.
Rs.
0.00
0.00
0.00
0.00
Rs.
0.00

Quantity

Nill
Total hire chargs of Machinery

C. LABOUR
Sl.No
1
2

Particulars

Unit
Day
Day

Qty
0.25
0.25

Pipe fitter
Mazdoor
Total cost of Labour
labour component/unit qty
19.80
Add contractor's profit and overhead charges
13.615% 2.70
labour component/unit qty (including contractor's profit)
22.50
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rate in Amount in
Rs
Rs.
480.00
120.00
310.00
77.50
Rs.
197.50

Rs.
Rs.
Rs.
Total
Rs:

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
10.00 Nos.
Rate per
No.
(A+B+C+D)/10.0

Rs:
Rs:
Rs.

1750.00
0.00
197.50
1947.50
265.15
2212.65
221.30

IRR-CAW-7-24 Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and side lining of
canal laid on rock including cost of all materials, machinery, labour etc., complete with all
leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Unit

Use rate of drill rod 1.6 m long


Reconditioning charges @
Use rate of air hose 2 Nos.
Total cost of Materials

Rm

B. MACHINERY:
Sl No
1
2

C. LABOUR:
Sl No
1
2

UNIT :

Hour

Description

Unit

Air compressor 8.5 cmm diesel


Fuel / Energy charges
Jack hammer 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

Description

Unit

Crew for Air compressor


Crew for Jack hammer
Total cost of Labour
labour component/unit qty

Quantity
10.00
10%
2.00

Quantity
1.00
1.00
2.00
2.00

Quantity

Hour
Hour

1.00
2.00

10 Nos.
Rate
in Rs.
27.67
11.56
Rs:

Amount
in Rs.
276.67
27.67
23.13
327.46

Rate
in Rs.
275.60
914.20
19.80
0.00
Rs:

Amount
in Rs.
275.60
914.20
39.60
0.00
1229.40

Rate
in Rs.
195.90
306.20
Rs:

Amount
in Rs.
195.90
612.40
808.30

80.80

193

Canal and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


13.615% 11.00
labour component/unit qty (including contractor's profit)
91.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Nos.
Rate per
No.
(A+B+C+D)/10.0

Rs:
Rs:
Rs:
Rs:

327.46
1229.40
808.30
2365.16

Rs:
Rs:
Rs.

322.02
2687.18
268.70

IRR-CAW-7-25 Providing and forming 35 x 35 x 40 cm deep filter drain consisting of 75 mm thick 10 mm


down coarse aggregate around pressure relief pipe and 75 mm thick sand around coarse
aggregate filter including cost of all materials, labour, excavation of pit etc., complete with
lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Coarse aggregate 10-4.75 mm


Sand (Un-Screened )
Total cost of Materials

cum
cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
0.15
0.35

Quantity

Nil

0.00

10 Nos.
Rate
in Rs.
875.00
560.00
Rs:

Amount
in Rs.
131.25
196.00
327.25

Rate
in Rs.
0.00

Amount
in Rs.

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Mason Cl- II
mazdoor

Unit

Quantity

Day
Day

0.10
0.10

Total cost of Labour


labour component/unit qty
6.80
Add contractor's profit and overhead charges
13.615% 0.90
labour component/unit qty (including contractor's profit)
7.70

Rs:

0.00

Rate
in Rs.
370.00
310.00
Rs:

Amount
in Rs.
37.00
31.00
68.00

Rs:
Rs:
Rs:
Rs:

327.25
0.00
68.00
395.25

Rs:
Rs:
Rs.

53.81
449.06
44.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Nos.
Rate per
No.
(A+B+C+D)/10.0

IRR-CAW-7-26 Providing and fixing 25 to 40 mm thick Shahabad / Talikota / other similar stone slabs
with pointing and finishing joints neatly in CM 1:3 proportion for canal / field channel lining
including cutting slabs to required size, mixing mortar, finishing joints neatly, curing etc.,
complete with lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate

Amount

194

Canal and Allied Works - Item Unit Rates 2015-16

1
2
3

Shahabad Stone slabs


Cement 43 Gr
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
1

sqm
kg
cum

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

105.00
200.00
0.40

Quantity
2.00
2.00

Quantity

1
2
3
4
5

Operator pump
Hour
2.00
work inspector
Day
1.00
Mason Class I
Day
4.00
Mason Class II
Day
2.00
mazdoor
Day
8.00
Cartman with Double Bullock cart for
6
water
Day
1.00
Total cost of Labour
labour component/unit qty
59.10
Add contractor's profit and overhead charges
13.615% 8.00
labour component/unit qty (including contractor's profit)
67.10

in Rs.
240.00
6.30
760.00
Rs:

in Rs.
25200.00
1260.00
304.00
26764.00

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
20.40
162.60
183.00

Rate
in Rs.
103.60
400.00
415.00
370.00
310.00

Amount
in Rs.
207.20
400.00
1660.00
740.00
2480.00

425.00
Rs:

425.00
5912.20

Rs:
Rs:
Rs:
Rs:

26764.00
183.00
5912.20
32859.20

Rs:
Rs:
Rs.

4473.78
37332.98
373.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0

IRR-CAW-7-27 Fixing PCC slabs of various sizes in CM 1 : 3 proportion to the side slopes of canal
including preparing bed, flush pointing joints in CM 1 : 3 propn, cost of all materials ( excluding
PCC slabs ), labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Unit

Cement 43 Gr
Sand (Screened)
Total cost of Materials

kg
cum

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Operator pump
work inspector
Mason Class I
mazdoor

Hour
Day
Day
Day

Quantity
240.00
0.50

Quantity
2.00
2.00

Quantity
2.00
1.00
4.00
9.00

100.00 sqm
Rate
in Rs.
6.30
760.00
Rs:

Amount
in Rs.
1512.00
380.00
1892.00

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
20.40
162.60
183.00

Rate
in Rs.
103.60
400.00
415.00
310.00

Amount
in Rs.
207.20
400.00
1660.00
2790.00

195

Canal and Allied Works - Item Unit Rates 2015-16

Cartman with Double Bullock cart for


water
Day
1.00
Total cost of Labour
labour component/unit qty
54.80
Add contractor's profit and overhead charges
13.615% 7.50
labour component/unit qty (including contractor's profit)
62.30
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0

425.00
Rs:

425.00
5482.20

Rs:
Rs:
Rs:
Rs:

1892.00
183.00
5482.20
7557.20

Rs:
Rs:
Rs.

1028.91
8586.11
85.90

IRR-CAW-7-28 Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion for supporting PCC slab lining
including necessary excavation, refilling, flush pointing joints in CM 1 : 3 propn, cost of all
materials ( excluding PCC lug slabs ), labour, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Unit

Cement 43 Gr
Sand ( Screened)
Total cost of Materials

kg
cum

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

UNIT :

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Quantity
58.00
0.12

Quantity
1.00
1.00

Quantity

1
2
3
4
5

Operator pump
Hour
1.00
work inspector
Day
1.00
Mason Class I
Day
2.00
Mason Class II
Day
1.00
mazdoor
Day
5.00
Cartman with Double Bullock cart for
6
water
Day
1.00
Total cost of Labour
labour component/unit qty
36.80
Add contractor's profit and overhead charges
13.615% 5.00
labour component/unit qty (including contractor's profit)
41.80

100.00 Rm
Rate
in Rs.
6.30
760.00
Rs:

Amount
in Rs.
365.40
91.20
456.60

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
10.20
81.30
91.50

Rate
in Rs.
103.60
400.00
415.00
370.00
310.00

Amount
in Rs.
103.60
400.00
830.00
370.00
1550.00

425.00
Rs:

425.00
3678.60

Rs:
Rs:
Rs:
Rs:

456.60
91.50
3678.60
4226.70

Rs:
Rs:
Rs.

575.47
4802.17
48.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100.0

196

Canal and Allied Works - Item Unit Rates 2015-16

IRR-CAW-7-29 Fixing 30 cm height pre-cast drops for field channels as directed including excavation, etc.,
complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Nill

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Cl- II
mazdoor

Unit
Day
Day
Day

Quantity
1.00
1.00
1.00

Total cost of Labour


labour component/unit qty
154.30
Add contractor's profit and overhead charges
13.615% 21.00
labour component/unit qty (including contractor's profit)
175.30

7 Nos.
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
370.00
310.00
1080.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1080.00
1080.00

Rs:
Rs:
Rs.

147.04
1227.04
175.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
7.00 Nos.
Rate per
No.
(A+B+C+D)/7.00

0.00

0.00

IRR-CAW-7-30 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
a. Using 500 micron thick LDPE sheet.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

250.00 sqm
Rate

Amount

197

Canal and Allied Works - Item Unit Rates 2015-16

1
2

LDPE sheet 500 micron thick


Bitumen 85 / 25 and 80 / 100 Gr
Total cost of Materials

B. MACHINERY:
Sl No

Description

sqm
kg

Unit

275.00
4.00

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

in Rs.
97.00
4.00
Rs:

in Rs.
26675.00
16.00
26691.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

Joining & laying @ 10 % of sheet


cost
sqm
250.00
mazdoor
Day
1.00
Total cost of Labour
labour component/unit qty
10.90
Add contractor's profit and overhead charges
13.615% 1.50
labour component/unit qty (including contractor's profit)
12.40
1
2

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
250.00 sqm
Rate per
sqm
(A+B+C+D)/250.0
Note :

9.70
310.00
Rs:

2425.00
310.00
2735.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

26691.00
0.00
2735.00
29426.00
4006.35
33432.35
133.70

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick sand backing to LDPE sheet.
For providing average 75 mm thick sand backing :

DATA:

Quantity of sand ( unscreened )


2 mazdoors for laying 6 cum per day.

( 250 x 0.075 )

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Sand for filling

18.75 cum

UNIT :
Unit

Quantity

cum

18.75
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit

Quantity

Day
Total cost of Labour

6.00

250.00 sqm
Rate
in Rs.
560.00
0.00
Rs:

Amount
in Rs.
10500.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1860.00
1860.00

Rs:
Rs:

10500.00
0.00

10500.00

labour component/unit qty


7.40
Add contractor's profit and overhead charges
13.615% 1.00
labour component/unit qty (including contractor's profit)
8.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

198

Canal and Allied Works - Item Unit Rates 2015-16

C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
250.00 sqm
Rate per
sqm
(A+B+C+D)/250.0

Rs:
Rs:

1860.00
12360.00

Rs:
Rs:
Rs.

1682.81
14042.81
56.20

IRR-CAW-7-31 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
b. Using 750 micron thick LDPE sheet.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

UNIT :
Unit

LDPE sheet 750 micron thick


Bitumen 85 / 25 and 80 / 100 Gr
Total cost of Materials

B. MACHINERY:
Sl No

Description

Quantity
275.00
4.00

Unit

Nill

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

250.00 sqm
Rate
in Rs.
137.00
4.00
Rs:

Amount
in Rs.
37675.00
16.00
37691.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.

Amount
in Rs.

Joining & laying @ 10 % of sheet


cost
sqm
250.00
mazdoor
Day
1.00
Total cost of Labour
labour component/unit qty
14.90
Add contractor's profit and overhead charges
13.615% 2.00
labour component/unit qty (including contractor's profit)
16.90
1
2

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
250.00 sqm
Rate per
sqm
(A+B+C+D)/250.0
Note :

0.00

13.70
310.00
Rs:

3425.00
310.00
3735.00

Rs:
Rs:
Rs:
Rs:

37691.00
0.00
3735.00
41426.00

Rs:
Rs:
Rs.

5640.15
47066.15
188.30

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing add
per sqm
Rs:
56.20

IRR-CAW-7-32 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
c. Using 1000 micron thick LDPE sheet.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

LDPE sheet 1000 micron thick


Bitumen 85 / 25 and 80 / 100 Gr

UNIT :
Unit

Quantity
275.00
4.00

250.00 sqm
Rate
in Rs.
189.00
4.00

Amount
in Rs.
51975.00
16.00

199

Canal and Allied Works - Item Unit Rates 2015-16

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

Rs:

51991.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

Joining & laying @ 10 % of sheet


cost
sqm
250.00
mazdoor
Day
1.00
Total cost of Labour
labour component/unit qty
20.10
Add contractor's profit and overhead charges
13.615% 2.70
labour component/unit qty (including contractor's profit)
22.80
1
2

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
250.00 sqm
Rate per
sqm
(A+B+C+D)/250.0
Note :

18.90
310.00
Rs:

4725.00
310.00
5035.00

Rs:
Rs:
Rs:
Rs:

51991.00
0.00
5035.00
57026.00

Rs:
Rs:
Rs.

7764.09
64790.09
259.20

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing add
per sqm
Rs:
56.20

IRR-CAW-7-33 Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler boards for
stone masonry lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Tarfelt joint filler board 12 mm thick

UNIT :
Unit

Quantity

sqm

38.75
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Carpenter Cl- II
mazdoor

Unit

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
6.80
Add contractor's profit and overhead charges
13.615% 0.90
labour component/unit qty (including contractor's profit)
7.70

1.00
1.00

100.00 Rm
Rate
in Rs.

Amount
in Rs.

420.00
0.00
Rs:

16275.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
370.00
310.00
Rs:

Amount
in Rs.
370.00
310.00
680.00

16275.00

0.00

200

Canal and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100.00

Rs:
Rs:
Rs:
Rs:

16275.00
0.00
680.00
16955.00

Rs:
Rs:
Rs.

2308.42
19263.42
192.60

IRR-CAW-7-34 Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Tarfelt joint filler board 20 mm thick

UNIT :
Unit

Quantity

sqm

100.00 Rm
Rate
in Rs.

10.00
0.00

650.00
0.00
Rs:

0.00
6500.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
310.00
Rs:

Amount
in Rs.
370.00
310.00
680.00

Rs:
Rs:
Rs:
Rs:

6500.00
0.00
680.00
7180.00

Rs:
Rs:
Rs.

977.56
8157.56
81.60

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Carpenter Cl- II
mazdoor

Unit

Quantity

Day
Day

1.00
1.00

Total cost of Labour


labour component/unit qty
6.80
Add contractor's profit and overhead charges
13.615% 0.90
labour component/unit qty (including contractor's profit)
7.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100.00

Amount
in Rs.
6500.00

IRR-CAW-7-35 Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Tarfelt joint filler board 20 mm thick

UNIT :
Unit

sqm

Quantity

15.30
0.00

100.00 Rm
Rate
in Rs.

Amount
in Rs.
9945.00

650.00
0.00

201

Canal and Allied Works - Item Unit Rates 2015-16

Total cost of Materials


B. MACHINERY:
Sl No

Description

Rs:

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Carpenter Cl- II
mazdoor

Unit

Quantity

Day
Day

1.00
1.00

Total cost of Labour


labour component/unit qty
6.80
Add contractor's profit and overhead charges
13.615% 0.90
labour component/unit qty (including contractor's profit)
7.70

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
370.00
310.00
Rs:

Amount
in Rs.
370.00
310.00
680.00

Rs:
Rs:
Rs:
Rs:

9945.00
0.00
680.00
10625.00

Rs:
Rs:
Rs.

1446.59
12071.59
120.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100.00

9945.00

0.00

IRR-CAW-7-36 Providing and forming 35 mm wide and 10 mm thick construction / contraction joints
for concrete lining by mastic filler including cost of all materials, labour etc., complete with
all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Unit

Asphalt 80/100 Gr
Sand (Screened )
Total cost of Materials

kg
cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
35.00
0.04

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Mason Cl- II
mazdoor

Unit

Quantity

Day
Day

0.50
1.00

Total cost of Labour


labour component/unit qty
5.00
Add contractor's profit and overhead charges
13.615% 0.70
labour component/unit qty (including contractor's profit)
5.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

100.00 Rm
Rate
in Rs.
4.00
760.00
Rs:

Amount
in Rs.
140.00
30.40
170.40

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
310.00
Rs:

Amount
in Rs.
185.00
310.00
495.00

Rs:
Rs:
Rs:
Rs:

170.40
0.00
495.00
665.40

202

Canal and Allied Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100.00

Rs:
Rs:
Rs.

90.59
755.99
7.60

IRR-CAW-7-37 Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum
equivalent concrete volume: 3.74 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5

2
3

Unit

Cement for mix

kg

Cement for incidentals @ 1 kg / slab


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 500 uses
Total cost of Materials

kg
cum
cum
cum
kg
No.

B. MACHINERY:
Sl No

particulars

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel)


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lining slab

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

C. LABOUR:
Sl No
1
2
3
4
5
6

Quantity
1122.00

Rate
in Rs.
6.30

225.00
6.30
1.94 1210.00
1.05 875.00
1.68 560.00
4.49
95.00
225.00
5.19
Rs:

Quantity

Rate
in Rs.

Amount
in Rs.
7068.60
1417.50
2353.21
916.30
942.48
426.36
1167.34
14291.78

Amount
in Rs.
428.00

8.00
8.00
0.10
0.10
0.20
0.20

53.50
81.30
10.20
81.30
402.50
307.20
Rs:

650.40
1.02
8.13
80.50
61.44
1229.49

90%

Rs:

1106.54

Rate
in Rs.
204.10
103.60
165.80
415.00
400.00

Amount
in Rs.
1632.80
10.36
33.16
830.00
400.00

310.00
310.00
310.00
310.00
310.00
Rs:

930.00
620.00
310.00
310.00
310.00
5386.32

Rs:

4847.69

Rs:

14291.78

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching materials / laying CC
Day
3.00
for demoulding / oiling / laying
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lining
slabs
90%
labour component/unit qty
21.50
Add contractor's profit and overhead charges
13.615% 2.90
labour component/unit qty (including contractor's profit)
24.40
ABSTRACT:
A. Cost of Materials

225 Nos.

203

Canal and Allied Works - Item Unit Rates 2015-16

B. Hire charges of Machinery


C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
225.00 Nos.
Rate per
each
(A+B+C+D)/225.0

Rs:
Rs:
Rs:

1106.54
4847.69
20246.01

Rs:
Rs:
Rs.

2756.49
23002.50
102.20

IRR-CAW-7-38 Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum,
equivalent concrete volume: 0.23 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5

2
3

C. LABOUR:
Sl No
1
2
3
4
5
6

Unit

Quantity

25 Nos.
Rate
in Rs.
6.30

Cement for mix

kg

69.00

Cement for incidentals @ 0.5 kg/slab


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 500 uses
Total cost of Materials

kg
cum
cum
cum
kg
No.

12.50
6.30
0.12 1210.00
0.06 875.00
0.10 560.00
0.28
95.00
25.00
3.23
Rs:

B. MACHINERY:
Sl No

particulars

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel)


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lug slabs

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Quantity

Rate
in Rs.

Amount
in Rs.
434.70
78.75
144.72
56.35
57.96
26.22
80.79
879.49

Amount
in Rs.
428.00

8.00
8.00
0.10
0.10
0.20
0.20

53.50
81.30
10.20
81.30
402.50
307.20
Rs:

650.40
1.02
8.13
80.50
61.44
1229.49

10%

Rs:

122.95

Rate
in Rs.
204.10
103.60
165.80
415.00
400.00

Amount
in Rs.
1632.80
10.36
33.16
830.00
400.00

310.00
310.00
310.00
310.00
310.00
Rs:

930.00
620.00
310.00
310.00
310.00
5386.32

Rs:

538.63

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching materials / laying CC
Day
3.00
for demoulding / oiling / laying
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labourfor lug
slabs
10%
labour component/unit qty
21.50
Add contractor's profit and overhead charges
13.615% 2.90
labour component/unit qty (including contractor's profit)
24.40

204

Canal and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
25.00 Nos.
Rate per
each
(A+B+C+D)/25.0

Rs:
Rs:
Rs:
Rs:

879.49
122.95
538.63
1541.07

Rs:
Rs:
Rs.

209.82
1750.89
70.00

IRR-CAW-7-39 Manufacturing 450 x 300 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Cement for mix

kg

270.00

2
3
4
5

Cement for incidentals @ 0.5 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses
Total cost of Materials

kg
cum
cum
kg
No.

112.50
0.61
0.39
1.08
225.00

B. MACHINERY:
Sl No
1
2
3

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lining slab

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

90%

Quantity

Crew for Pump


Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching / mixing / laying
Day
2.00
for demoulding / cleaning / oiling
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lining
slabs
90%
labour component/unit qty
13.80
Add contractor's profit and overhead charges
13.615% 1.90
labour component/unit qty (including contractor's profit)
15.70

225 Nos.
Rate
in Rs.
6.30

Amount
in Rs.
1701.00
708.75

6.30
875.00
560.00
95.00
2.15
Rs:

535.50
216.72
102.60
483.83
3748.40

Rate
in Rs.
5.50
0.00
10.20
81.30
402.50
307.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.13
80.50
61.44
195.09

Rs:

175.58

Rate
in Rs.
103.60
165.80
415.00
400.00

Amount
in Rs.
10.36
33.16
830.00
400.00

310.00
310.00
310.00
310.00
310.00
Rs:

620.00
620.00
310.00
310.00
310.00
3443.52

Rs:

3099.17

205

Canal and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
225.00 Nos.
Rate per
each
(A+B+C+D)/225.0

Rs:
Rs:
Rs:
Rs:

3748.40
175.58
3099.17
7023.14

Rs:
Rs:
Rs.

956.2
7979.34
35.50

IRR-CAW-7-40 Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Cement for mix

kg

15.00

2
3
4
5

Cement for incidentals @ 0.3 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses
Total cost of Materials

kg
cum
cum
kg
No.

7.50
0.03
0.02
0.06
25.00

B. MACHINERY:
Sl No
1
2
3

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lug slabs

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

10%

Quantity

Crew for Pump


Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching / mixing / laying
Day
2.00
for demoulding / cleaning / oiling
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lug
slabs
10%
labour component/unit qty
13.80
Add contractor's profit and overhead charges
13.615% 1.90
labour component/unit qty (including contractor's profit)
15.70

25 Nos.
Rate
in Rs.
6.30

Amount
in Rs.
94.50
47.25

6.30
875.00
560.00
95.00
1.18
Rs:

29.75
12.04
5.70
29.54
218.78

Rate
in Rs.
5.50
0.00
10.20
81.30
402.50
307.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.13
80.50
61.44
195.09

Rs:

19.51

Rate
in Rs.
103.60
165.80
415.00
400.00

Amount
in Rs.
10.36
33.16
830.00
400.00

310.00
310.00
310.00
310.00
310.00
Rs:

620.00
620.00
310.00
310.00
310.00
3443.52

Rs:

344.35

206

Canal and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
25.00 Nos.
Rate per
each
(A+B+C+D)/25.0

Rs:
Rs:
Rs:
Rs:

218.78
19.51
344.35
582.64

Rs:
Rs:
Rs.

79.33
661.97
26.50

IRR-CAW-7-41 Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28 days cube
compressive strength not less than 15 N/Sqmm) cement concrete using 20mm down
grades coarse aggregate including cost of all materials, machinery, labour, batching,
mixing, laying, compacting, formwork, finishing, curing etc., complete with initial lead upto 50 m
and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, FA : 0.45cum, Blending Ratio of CA--65:35)

DATA:

RATE ANALYSIS

UNIT:

225

Nos.

A. MATERIALS :
Sl. No
1
2
3
4
5
6
7

Particulars
Cement for mix

Unit
Kg
Kg

Quantity
1215
112.5

Cement for incidentals @ 0.5kg/slab


Cum
Coarse aggregate 20 mm below
Cum
Coarse aggregate 10 mm below
Cum
Fine aggregate (Un-Screened)
kg
Super Plasticizer
No.
Use rate of moulds for 250 uses
Total Cost of Materials Rs.

2.11
1.13
1.82
4.86
225

Rate
Amount in
Rs.
in Rs.
7654.50
6.30
708.75
6.30
2548.26
1210.00
992.25
875.00
1020.60
560.00
461.70
95.00
1.23
276.75
13662.81

B. MACHINERY :
Sl. No
1
2
3

C. LABOUR :
Sl. No
1
2
3
4
5

Particulars

Unit

Hour
Diesel mixer 300/200
Hour
Fuel/Energy charges
Hour
5 hp pump (diesel)
Hour
Fuel/Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel/Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery @ 90% for lining slab
Rs.

Particulars
Crew for Pump
Crew for water tanker
Mason Class-I
Class II Mason
Mazdoor
For batching materials/laying
For demoulding/cleaning/oiling
For shifting slabs to curing pond
For stacking after curing
For cleaning & miscellaneous

Unit

Quantity
8
8
0.1
0.1
0.2
0.2
Rs.
90%

Quantity

Hour
Hour
Day
Day

0.1
0.2
2
1

Day

2
2
1
1
1

Day

Rate
Amount in
Rs.
in Rs.
428.00
53.50
650.40
81.30
1.02
10.20
8.13
81.30
80.50
402.50
61.44
307.20
1229.49
1106.54

Rate
Amount in
Rs.
in Rs.
10.36
103.60
33.16
165.80
830.00
415.00
370.00
370.00
310.00
310.00
310.00
310.00
310.00

620.00
620.00
310.00
310.00
310.00

207

Canal and Allied Works - Item Unit Rates 2015-16

Total Cost of Labour Rs.


Aportioned cost of labour for lining
90%
slabs Rs.
labour component/unit qty
13.70
Add contractor's profit and overhead charges
13.615% 1.90
labour component/unit qty (including contractor's profit)
15.60

ABSTRACT :
A. Cost of Materials
B. Hire Charges of machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
225.00 Nos.
Rate per
each
(A+B+C+D)/225.0

3413.52
3072.17

Rs.
Rs.
Rs.
Rs:

13662.81
1106.54
3072.17
17841.52

Rs:
Rs:
Rs.

2429.12
20270.64
90.10

IRR-CAW-7-42 Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm )cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Cement for mix

kg

324.00

2
3
4
5

Cement for incidentals @ 0.5 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses
Total cost of Materials

kg
cum
cum
kg
No.

112.50
0.73
0.46
1.30
225.00

B. MACHINERY:
Sl No
1
2
3

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lining slab

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Crew for Pump


Crew for Water tanker
Mason Class-I
work inspector
mazdoor
for batching / mixing / laying
for demoulding / cleaning / oiling
for shifting slabs to curing pond
for stacking after curing
for cleaning & miscellaneous

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

90%

Quantity

225 Nos.
Rate
in Rs.
6.30

Amount
in Rs.
2041.20
708.75

6.30
875.00
560.00
95.00
2.18
Rs:

642.60
260.06
123.12
489.46
4265.19

Rate
in Rs.
5.50
0.00
10.20
81.30
402.50
307.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.13
80.50
61.44
195.09

Rs:

175.58

Amount
in Rs.
10.36
33.16
830.00
400.00
620.00
620.00
310.00
310.00
310.00

Hour
Hour
Day
Day

0.10
0.20
2.00
1.00

Rate
in Rs.
103.60
165.80
415.00
400.00

Day
Day
Day
Day
Day

2.00
2.00
1.00
1.00
1.00

310.00
310.00
310.00
310.00
310.00

208

Canal and Allied Works - Item Unit Rates 2015-16

Total cost of Labour


Aportioned cost of labour for lining
slabs
90%
labour component/unit qty
13.80
Add contractor's profit and overhead charges
13.615% 1.90
labour component/unit qty (including contractor's profit)
15.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
225.00 Nos.
Rate per
each
(A+B+C+D)/225.0

Rs:

3443.52

Rs:

3099.17

Rs:
Rs:
Rs:
Rs:

4265.19
175.58
3099.17
7539.94

Rs:
Rs:
Rs.

1026.56
8566.50
38.10

IRR-CAW-7-43 Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Cement for mix

kg

13.50

2
3
4
5

Cement for incidentals @ 0.3 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses
Total cost of Materials

kg
cum
cum
kg
No.

7.50
0.03
0.02
0.05
25.00

B. MACHINERY:
Sl No
1
2
3

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lug slabs

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Crew for Pump


Crew for Water tanker
Mason Class-I
work inspector
mazdoor
for batching / mixing / laying
for demoulding / cleaning / oiling
for shifting slabs to curing pond
for stacking after curing
for cleaning & miscellaneous

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

10%

Quantity

25 Nos.
Rate
in Rs.
6.30

Amount
in Rs.
85.05
47.25

6.30
875.00
560.00
95.00
1.15
Rs:

26.78
10.84
5.13
28.76
203.80

Rate
in Rs.
5.50
0.00
10.20
81.30
402.50
307.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.13
80.50
61.44
195.09

Rs:

19.51

Amount
in Rs.
10.36
33.16
830.00
400.00
620.00
620.00
310.00
310.00
310.00

Hour
Hour
Day
Day

0.10
0.20
2.00
1.00

Rate
in Rs.
103.60
165.80
415.00
400.00

Day
Day
Day
Day
Day

2.00
2.00
1.00
1.00
1.00

310.00
310.00
310.00
310.00
310.00

209

Canal and Allied Works - Item Unit Rates 2015-16

Total cost of Labour


Aportioned cost of labour for lug
slabs
10%
labour component/unit qty
13.80
Add contractor's profit and overhead charges
13.615% 1.90
labour component/unit qty (including contractor's profit)
15.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
25.00 Nos.
Rate per
each
(A+B+C+D)/25.0

Rs:

3443.52

Rs:

344.35

Rs:
Rs:
Rs:
Rs:

203.80
19.51
344.35
567.66

Rs:
Rs:
Rs.

77.29
644.95
25.80

IRR-CAW-7-44 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from approved quarry including cost of all materials,
machinery, labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
(Thickness of the masonry assumed: 0.3 m, rubble stones : 0.96 cum, Stone Chips : 0.15cum,
Through Stones 20 x 20 x 30cm : 1/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

1
2

Cement 43 Gr
Sand (Screened )

kg
cum

1152.00
4.00

3
4
5

Uncoursed rubble stones at quarry


Through stones 20x20x30 cm
Stone chips at quarry
Total cost of Materials

cum
Nos
cum

9.60
32.00
1.50

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Quantity
4.00
4.00

Quantity

1
2
3
4
5

Operator pump
Hour
4.00
work inspector
Day
1.00
Mason Class I
Day
2.00
Mason Class II
Day
2.00
mazdoor
Day
8.00
Cartman with Double Bullock cart for
6
water
Day
1.00
Total cost of Labour
labour component/unit qty
528.90
Add contractor's profit and overhead charges
13.615% 72.00
labour component/unit qty (including contractor's profit)
600.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

10.00 cum
Rate
in Rs.
6.30
760.00

Amount
in Rs.
7257.60
3040.00
3168.00

330.00
23.00
360.00
Rs:

736.00
540.00
14741.60

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
40.80
325.20
366.00

Rate
in Rs.
103.60
400.00
415.00
370.00
310.00

Amount
in Rs.
414.40
400.00
830.00
740.00
2480.00
425.00

425.00
Rs:

5289.40

Rs:
Rs:
Rs:
Rs:

14741.60
366.00
5289.40
20397.00

210

Canal and Allied Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Total cost for
10.00 cum
Rate per
cum
(A+B+C+D)/10.0

Rs:
Rs:
Rs.

2777.05
23174.05
2317.40

IRR-CAW-7-45 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side
lining using stones from approved quarry including cost of all materials, machinery,
labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50m and all lifts.(without pin headers) : 1.1 cum)
(Thickness of the Masonry assumed: 0.3 m , rubble stones

DATA:

RATE ANALYSIS

UNIT:

10

Cum

A.
MATERIALS
:
Sl. No
1
2
3

Particulars
Cement 43 Gr
Sand (Screened)
Uncoursed rubble stones at quarry

Unit
Kg
Cum
Cum

Quantity
979.2
3.4
11

Total Cost of Materials Rs.

Rate
Amount in
Rs.
in Rs.
6168.96
6.30
2584.00
760.00
3630.00
330.00
12382.96

B. MACHINERY :
Sl. No
1
2

Particulars

Unit

Hand Mixing Charges


Hour
5 hp pump (diesel)
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

Quantity
8
4
5
Rs.

Rate
Amount in
Rs.
in Rs.
5.50
44.00
40.80
10.20
406.50
81.30
491.30

C. LABOUR :
Sl. No

Particulars

Unit

Quantity

1
2
3
4
5

Operator pump
Hour
4
Mason Class I
Day
13
Mason Class II
Day
6
Mazdoor
Day
29
Cartman with Double Bullock cart for
Day
1
water
Total Cost of Labour Rs.
labour component/unit qty
1744.40
Add contractor's profit and overhead charges
13.615% 237.50
labour component/unit qty (including contractor's profit)
1981.90

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Cum
Rate per
Cum
(A+B+C+D)/10.0

Rate
Amount in
Rs.
in Rs.
414.40
103.60
5395.00
415.00
2220.00
370.00
310.00
8990.00
425.00
425.00
17444.40

Rs.
Rs.
Rs.
Rs:

12382.96
491.3
17444.40
30318.66

Rs:
Rs:
Rs.

4127.89
34446.55
3444.70

IRR-CAW-7-46 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from canal excavation including cost of all materials,

211

Canal and Allied Works - Item Unit Rates 2015-16

machinery, labour, forming weep holes at specified interval, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
( rubble stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm : 1/sqm)
Note:

Stones and chips will be issued from dump yard at specified issue rate.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

Cement 43 Gr
Sand (Screened )
Uncoursed rubble at dump yard
Through stones 20x20x30 cm
Stone chips at dump yard
Total cost of Materials

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

particulars

UNIT :
Unit
kg
cum
cum
Nos
cum

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Quantity
1144.00
4.00
9.60
32.00
1.50

Quantity
4.00
4.00

Quantity

1
2
3
4
5
6

Operator pump
Hour
4.00
work inspector
Day
1.00
Mason Class I
Day
2.00
Mason Class II
Day
2.00
Crowbarman
Day
1.00
mazdoor
Day
9.00
Cartman with Double Bullock cart for
7
water
Day
1.00
Total cost of Labour
labour component/unit qty
596.90
Add contractor's profit and overhead charges
13.615% 81.30
labour component/unit qty (including contractor's profit)
678.20

10.00 cum
Rate
in Rs.
6.30
760.00
165.00
23.00
185.00
Rs:

Amount
in Rs.
7207.20
3040.00
1584.00
736.00
277.50
12844.70

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
40.80
325.20
366.00

Rate
in Rs.
103.60
400.00
415.00
370.00
370.00
310.00

Amount
in Rs.
414.40
400.00
830.00
740.00
370.00
2790.00
425.00

425.00
Rs:

5969.40

Rs:
Rs:
Rs:
Rs:

12844.70
366.00
5969.40
19180.10

Rs:
Rs:
Rs.

2611.37
21791.47
2179.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 cum
Rate per
cum
(A+B+C+D)/10.0

IRR-CAW-7-47 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side lining
using stones from canal excavation including cost of all materials, machinery, labour, forming weep holes at
specified intervals, finishing, curing etc., complete with initial lead upto 50m and all lifts.
( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum)

DATA:

RATE ANALYSIS

UNIT:

10

Cum

A.
MATERIALS
:
Sl. No
1
2

Particulars
Cement 43 Gr
Sand (Screened)

Unit
Kg
Cum

Quantity
980
3.4

Rate
Amount in
Rs.
in Rs.
6174.00
6.30
2584.00
760.00

212

Canal and Allied Works - Item Unit Rates 2015-16

Uncoursed rubble at dump yard


Cum
Total Cost of Materials Rs.

11

165.00

1815.00
10573

B. MACHINERY :
Sl. No
1
2

Particulars

Unit

Hand Mixing Charges


Hour
5 hp pump (diesel)
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

Quantity
8
4
5
Rs.

Rate
Amount in
Rs.
in Rs.
5.50
44.00
40.80
10.20
406.50
81.30
491.30

C. LABOUR :
Sl. No

Particulars

Unit

Quantity

1
2
3
4
5

Operator pump
Hour
4
Mason Class I
Day
13
Mason Class II
Day
6
Mazdoor
Day
29
Cartman with double bullock cart
Day
1
Total Cost of Labour Rs.
labour component/unit qty
1744.40
Add contractor's profit and overhead charges
13.615% 237.50
labour component/unit qty (including contractor's profit)
1981.90

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
10.00 Cum
Rate per
Cum
(A+B+C+D)/10.0

Rate
Amount in
Rs.
in Rs.
414.40
103.60
5395.00
415.00
2220.00
370.00
310.00
8990.00
425.00
425.00
17444.40

Rs.
Rs.
Rs.
Rs:

10573
491.3
17444.40
28508.70

Rs:
Rs:
Rs.

3881.46
32390.16
3239.00

IRR-CAW-8

ROCK PITCHING:

IRR-CAW-8-1

Providing and constructing 25 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate
in Rs.

Amount
in Rs.
7590.00

Uncoursed rubble stones at quarry

cum

23.00

330.00

2
3

Pin header (Through stone) 30 cm


Stone chips at quarry
Total cost of Materials

Nos
cum

200.00
3.75

23.00
360.00
Rs:

1350.00
13540.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

4600.00

B. MACHINERY:
Sl No
1

Description

Unit

Nill

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

213

Canal and Allied Works - Item Unit Rates 2015-16

1
2
3

work inspector
Mason Class II
mazdoor

Day
Day
Day

1.00
5.00
6.00

Total cost of Labour


labour component/unit qty
41.10
Add contractor's profit and overhead charges
13.615% 5.60
labour component/unit qty (including contractor's profit)
46.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
Note:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Murum

UNIT :
Unit
cum

Quantity
18.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

400.00
1850.00
1860.00
4110.00

Rs:
Rs:
Rs:
Rs:

13540.00
0.00
4110.00
17650.00

Rs:
Rs:
Rs.

2403.05
20053.05
200.50

If 15 cm thick murum bed is to be provided below pitching


(Murum : 0.18 cum/sqm)

DATA:

400.00
370.00
310.00
Rs:

Description
mazdoor

Unit

Quantity

Day

4.00

Total cost of Labour

100.00 sqm
Rate
in Rs.
115.00
0.00
Rs:

Amount
in Rs.
2070.00
0.00
2070.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1240.00
1240.00

Rs:
Rs:
Rs:
Rs:

2070.00
0.00
1240.00
3310.00

Rs:
Rs:
Rs.

450.66
3760.66
37.60

labour component/unit qty


12.40
Add contractor's profit and overhead charges
13.615% 1.70
labour component/unit qty (including contractor's profit)
14.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0

IRR-CAW-8-1-A Providing and constructing 22.5 cm thick dry rubble stone pitching with pin headers at 2 per
(New Item4 - 201112)
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial

lead upto 50 m and all lifts.


( rubble stones : 0.207 cum/sqm, Stone Chips : 0.03375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance works)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate

Amount

214

Canal and Allied Works - Item Unit Rates 2015-16

in Rs.

in Rs.
6831.00

Uncoursed rubble stones at quarry

cum

20.70

330.00

2
3

Pin header (Through stone) 30 cm


Stone chips at quarry
Total cost of Materials

Nos
cum

200.00
3.375

23.00
360.00
Rs:

1215.00
12646.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
1850.00
1860.00
4110.00

Rs:
Rs:
Rs:
Rs:

12646.00
0.00
4110.00
16756.00

Rs:
Rs:
Rs.

2281.33
19037.33
190.40

4600.00

B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
5.00
6.00

Total cost of Labour


labour component/unit qty
41.10
Add contractor's profit and overhead charges
13.615% 5.60
labour component/unit qty (including contractor's profit)
46.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
IRR-CAW-8-2

Providing and constructing 25 cm thick dry rubble stone pitching including cost of all materials, labour,
hand packing, finishing etc., complete
( rubble stones : 0.275 cum/sqm)

DATA:

RATE ANALYSIS

UNIT:

100

Sqm.

A. MATERIALS :
Sl. No
1

Particulars
Uncoursed rubble stones at quarry

Unit
Cum

Quantity

Rate
in Rs.

Amount in
Rs.
9075.00

27.50
330.00

Total Cost of Materials Rs.

9075

B. MACHINERY :
Sl. No

Particulars

Nil

Unit

Quantity
0
0

Total hire charges of Machinery

Rs.

Rate
in Rs.

Amount in
Rs.
0
0
0

C. LABOUR :
Sl. No
1
2

Particulars
Mason Class II
Mazdoor

labour component/unit qty

Unit

Day
Day
Total Cost of Labour Rs.

Quantity
5.50
24.75

Rate
Amount in
Rs.
in Rs.
2035.00
370.00
310.00
7672.50
9707.50

97.10

215

Canal and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


13.615% 13.20
labour component/unit qty (including contractor's profit)
110.30

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour

Rs.
Rs.
Rs.
Rs:

9075
0
9707.50
18782.50

D. Add for contractor's profit and overheads on (A+B+C)


13.615%
Rs:
Total cost for
100.00 Sqm.
Rs:
Rate per
Sqm.
(A+B+C+D)/100.0
Rs.
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
in Rs.
( As per rate analysis under item IRR-CAW-8-1- Note )

2557.24
21339.74
213.40

Total

37.60

IRR-CAW-8-2-A Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour,
(New Item5 - 2011hand packing, finishing etc., complete
12)

( rubble stones : 0.2475 cum/sqm) (For Maintenance Works)

DATA:

RATE ANALYSIS

UNIT:

100

Sqm.

A. MATERIALS :
Sl. No
1
2

Particulars

Unit

Rough Stone for Revetment


Cum
Stone Chips at Quarry
Cum
Total Cost of Materials Rs.

Quantity
24.75
3.40

Rate
Amount in
Rs.
in Rs.
3564.00
144.00
1224.00
360.00
4788

B. MACHINERY :
Sl. No

Particulars

Nil

Unit

Quantity
0
0

Total hire charges of Machinery

Rate
in Rs.

Amount in
Rs.
0
0

Rs.

C. LABOUR :
Sl. No
1
2

Particulars
Mason Class II
Mazdoor

Unit

Day
Day
Total Cost of Labour Rs.

Quantity
4.95
22.28

Rate
Amount in
Rs.
in Rs.
1831.50
370.00
310.00
6905.25
8736.75

labour component/unit qty


87.40
Add contractor's profit and overhead charges
13.615% 11.90
labour component/unit qty (including contractor's profit)
99.30

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 Sqm.
Rate per
Sqm.
(A+B+C+D)/100.0
IRR-CAW-8-3

Rs.
Rs.
Rs.
Rs:

4788
0
8736.75
13524.75

Rs:
Rs:
Rs.

1841.39
15366.14
153.70

Providing and constructing 30 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.

216

Canal and Allied Works - Item Unit Rates 2015-16

( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate
in Rs.

Uncoursed rubble stones at quarry

cum

27.50

330.00

2
3

Pin header (Through stone) 30 cm


Stone chips at quarry
Total cost of Materials

Nos
cum

200.00
4.50

23.00
360.00
Rs:

Amount
in Rs.
9075.00
4600.00

B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
5.00
6.00

Total cost of Labour


labour component/unit qty
41.10
Add contractor's profit and overhead charges
13.615% 5.60
labour component/unit qty (including contractor's profit)
46.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item
IRR-CAW-8-1- Note )

IRR-CAW-8-4

DATA:

1620.00
15295.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
1850.00
1860.00
4110.00

Rs:
Rs:
Rs:
Rs:

15295.00
0.00
4110.00
19405.00

Rs:
Rs:
Rs.

2641.99
22046.99
220.50

0.00

37.60

Providing and Constructing 30 cm thick dry rubble stone pitching


including cost of all materials,labour,hand packing,finishing etc.,complete
( rubble stones : 0.33 cum/sqm)

RATE ANALYSIS
A. MATERIALS :
Sl No

Particulars

Uncoursed rubble stones at Quarry

UNIT :
Unit

Cum

Quantity

33.00

100.00 sqm
Rate
in Rs

Amount
in Rs
10890.00

330.00

( Included in material Rate)


Total Cost of materials
Rs :

10890.00

B.MACHINERY :
Sl No

Description

Unit

Quantity

Rate
in Rs

Amount
in Rs

217

Canal and Allied Works - Item Unit Rates 2015-16

Nill

0.00
0.00

0.00
0.00

Total hire charges of machinery


Rs :

0.00

C.LABOUR :
Sl No

Description

Unit

Quantity

1
2

Mason Class II
Day
6.60
Mazdoor
Day
29.70
Total cost of labour
Rs :
labour component/unit qty
116.50
Add contractor's profit and overhead charges
13.615% 15.90
labour component/unit qty (including contractor's profit)
132.40
ABSTRACT
A.Cost of Materials including ryolty charges
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under
item IRR-CAW-8-1 - Note)

IRR-CAW-8-5

Rate
in Rs
370.00
310.00

Amount
in Rs
2442.00
9207.00
11649.00

Rs:
Rs:
Rs:
Rs:

10890.00
0.00
11649.00
22539.00

Rs:
Rs:
Rs.

3068.68
25607.68
256.10

Rs :

37.60

Providing and constructing 45 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate
in Rs.

Uncoursed rubble stones at quarry

cum

40.00

330.00

2
3

Pin header (Through stone) 45 cm


Stone chips at quarry
Total cost of Materials

Nos
cum

200.00
6.75

39.00
360.00
Rs:

Amount
in Rs.
13200.00
7800.00

B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
57.80
Add contractor's profit and overhead charges
13.615% 7.90
labour component/unit qty (including contractor's profit)
65.70

1.00
7.00
9.00

2430.00
23430.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
2590.00
2790.00
5780.00

0.00

218

Canal and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item
IRR-CAW-8-1 - Note )

IRR-CAW-8-6

DATA:

Rs:
Rs:
Rs:
Rs:

23430.00
0.00
5780.00
29210.00

Rs:
Rs:
Rs.

3976.94
33186.94
331.90
37.60

Providing and Constructing 45 cm thick dry rubble stone pitching


including cost of all materials,labour,hand packing,finishing etc.,complete
( rubble stones : 0.495 cum/sqm)

RATE ANALYSIS
A. MATERIALS :
Sl No

Particulars

Uncoursed rubble stones at Quarry

UNIT :
Unit

Cum

Quantity

49.50

100.00 sqm
Rate
in Rs

Amount
in Rs
16335.00

330.00

( Included in material Rate)


Total Cost of materials
Rs :

16335.00

B.MACHINERY :
Sl No

Description

Nill

Unit

Quantity
0.00
0.00

Rate
in Rs
0.00
0.00

Total hire charges of machinery


Rs :

Amount
in Rs
0.00
0.00
0.00

C.LABOUR :
Sl No

Description

Unit

Quantity

1
2

Mason Class II
Day
9.90
Mazdoor
Day
44.55
Total cost of labour
Rs :
labour component/unit qty
174.70
Add contractor's profit and overhead charges
13.615% 23.80
labour component/unit qty (including contractor's profit)
198.50
ABSTRACT
A.Cost of Materials including ryolty charges
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under
item IRR-CAW-8-1 - Note)

Rate
in Rs

Amount
in Rs

370.00
310.00

3663.00
13810.50
17473.50

Rs:
Rs:
Rs:
Rs:

16335.00
0.00
17473.50
33808.50

Rs:
Rs:
Rs.

4603.03
38411.53
384.10

Rs :

37.60

219

Canal and Allied Works - Item Unit Rates 2015-16

IRR-CAW-8-7

Providing and constructing 30 cm thick rubble stone pitching set in CM 1: 5 proportion with
pin headers at 2 per sqm in including cost of all materials, labour, packing chips and mortar,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.
( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate
in Rs.

Amount
in Rs.
9075.00

Uncoursed rubble stones at quarry

cum

27.50

330.00

2
3
4
5

Pin header (Through stone) 30 cm


Stone chips @ 15 % at quarry
Cement
Sand (Screened )
Total cost of Materials

Nos
cum
kg
cum

200.00
4.50
3000.00
10.50

23.00
360.00
6.30
760.00
Rs:

1620.00
18900.00
7980.00
42175.00

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
20.40
162.60
183.00

Rate
in Rs.
103.60
400.00
370.00
310.00
425.00
Rs:

Amount
in Rs.
207.20
400.00
1850.00
3720.00
850.00
7027.20

Rs:
Rs:
Rs:
Rs:

42175.00
183.00
7027.20
49385.20

Rs:
Rs:
Rs.

6723.79
56108.99
561.10

4600.00

B. MACHINERY:
Sl No
1

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Quantity
2.00
2.00

Unit

Quantity

1
2
3
4
5

Crew for Pump


Hour
2.00
work inspector
Day
1.00
Mason Class II
Day
5.00
mazdoor
Day
12.00
Catrman with double bullock cart
Day
2.00
Total cost of Labour
labour component/unit qty
70.30
Add contractor's profit and overhead charges
13.615% 9.60
labour component/unit qty (including contractor's profit)
79.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item
IRR-CAW-8-1 - Note )

IRR-CAW-8-8

37.60

Providing and Constructing 30 cm thick rubble stone pitching set in CM 1:5 Proportion
including cost of all materials,labour, packing chips and mortar ,finishing etc.,complete
( rubble stones : 0.33 cum/sqm )

DATA:

RATE ANALYSIS

UNIT :

100.00 Sqm

A. MATERIALS :
Sl No

Particulars

Uncoursed rubble stones at Quarry

Unit

Cum

Quantity

33.00

Rate
in Rs

Amount
in Rs
10890.00

330.00

220

Canal and Allied Works - Item Unit Rates 2015-16

2
3

Cement
Sand (Screened)
Total Cost of materials

Kg
Cum

3232.00
11.22

6.30
760.00

20361.60
8527.20
39778.80

Rate
in Rs

Amount
in Rs

Rs :

B.MACHINERY :
Sl No

Description

Nill

Unit

Quantity
0.00

0.00

0.00

Total hire charges of machinery


Rs :

0.00

C.LABOUR :
Sl No

Description

Unit

Quantity

1
2
3

Mason Class I
Day
0.54
Mason Class II
Day
1.26
Mazdoor
Day
2.80
Total cost of labour
Rs :
labour component/unit qty
15.60
Add contractor's profit and overhead charges
13.615% 2.10
labour component/unit qty (including contractor's profit)
17.70
ABSTRACT
A.Cost of Materials
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 Sqm
Rate per
Sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under
item IRR-CAW-8-1 - Note)

IRR-CAW-8-9

Rate
in Rs

Amount
in Rs
224.10
466.20
868.00

415.00
370.00
310.00

1558.30

Rs:
Rs:
Rs:
Rs:

39778.80
0.00
1558.30
41337.10

Rs:
Rs:
Rs.

5628.05
46965.15
469.70

Rs :

37.60

Providing and constructing 30 cm thick dry khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm,
Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Khandki stones 20-25 cm height

Nos

1200.00

2
3

Pin header (Through stone) 30 cm


Stone chips
Total cost of Materials

Nos
cum

200.00
4.50

B. MACHINERY:
Sl No
1

Description

Unit

Nil

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

100.00 sqm
Rate
in Rs.
13.00

Amount
in Rs.
15600.00
4600.00

23.00
360.00
Rs:

1620.00
21820.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

221

Canal and Allied Works - Item Unit Rates 2015-16

1
2
3

work inspector
Mason Class II
mazdoor

Day
Day
Day

1.00
5.00
6.00

Total cost of Labour


labour component/unit qty
41.10
Add contractor's profit and overhead charges
13.615% 5.60
labour component/unit qty (including contractor's profit)
46.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item
IRR-CAW-8-1 - Note )

400.00
370.00
310.00
Rs:

400.00
1850.00
1860.00
4110.00

Rs:
Rs:
Rs:
Rs:

21820.00
0.00
4110.00
25930.00

Rs:
Rs:
Rs.

3530.37
29460.37
294.60
37.60

IRR-CAW-8-10 Providing and constructing 45 cm thick dry khandki stone pitching using 25 to 30 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 1200 Nos/sqm, Stone Chips : 0.0675cum/sqm,
Pin Headers 45cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Khandki stones 25-30 cm height


Pin headers 45 cm
Stone chips
Total cost of Materials

B. MACHINERY:
Sl No

Description

UNIT :
Unit
Nos
Nos
cum

Unit

Quantity
730.00
200.00
6.75

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
7.00
9.00

Total cost of Labour


labour component/unit qty
57.80
Add contractor's profit and overhead charges
13.615% 7.90
labour component/unit qty (including contractor's profit)
65.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0

100.00 sqm
Rate
in Rs.
16.00
39.00
360.00
Rs:

Amount
in Rs.
11680.00
7800.00
2430.00
21910.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
2590.00
2790.00
5780.00

Rs:
Rs:
Rs:
Rs:

21910.00
0.00
5780.00
27690.00

Rs:
Rs:
Rs.

3769.99
31459.99
314.60

222

Canal and Allied Works - Item Unit Rates 2015-16

NOTE:

If 15 cm thick murum bed is to be


provided below pitching add
( As per rate analysis under item
IRR-CAW-8-1 - Note )

37.60

IRR-CAW-8-11 Providing and constructing 30 cm thick khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in
CM 1:3 proportion including cost of all materials, labour, packing chips and mortar, finishing,
curing etc.complete with initial lead upto 50 m and all lifts.
( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm,
Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

Khandki stones 20-25 cm height


Pin headers 30 cm long
Stone chips @ 15 % at quarry
Cement
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

particulars

UNIT :
Unit
Nos
Nos
cum
kg
cum

Description

Unit

5 hp diesel pump
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Quantity
1200.00
200.00
4.50
2902.00
9.67

Quantity
2.00
2.00

Quantity

1
2
3
4
5

Crew for Pump


Hour
2.00
work inspector
Day
1.00
Cartman with double bullock cart
Day
2.00
Mason Class II
Day
5.00
mazdoor
Day
11.00
Total cost of Labour
labour component/unit qty
67.20
Add contractor's profit and overhead charges
13.615% 9.10
labour component/unit qty (including contractor's profit)
76.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item
IRR-CAW-8-1 - Note )

100.00 sqm
Rate
in Rs.
13.00
23.00
360.00
6.30
760.00
Rs:

Amount
in Rs.
15600.00
4600.00
1620.00
18282.60
7349.20
47451.80

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
20.40
162.60
183.00

Rate
in Rs.
103.60
400.00
425.00
370.00
310.00
Rs:

Amount
in Rs.
207.20
400.00
850.00
1850.00
3410.00
6717.20

Rs:
Rs:
Rs:
Rs:

47451.80
183.00
6717.20
54352.00

Rs:
Rs:
Rs.

7400.02
61752.02
617.50
37.60

IRR-CAW-8-12 Providing and constructing 45 cm thick khandki stone pitching using 25 to 30 cm stones
with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in CM 1 : 3
proportion including cost of all materials, labour, packing chips and mortar, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 730 Nos/sqm, Stone Chips : 0.0675cum/sqm,

223

Canal and Allied Works - Item Unit Rates 2015-16

Pin Headers 45cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

Khandki stones 25-30 cm height


Pin headers 45 cm
Stone chips @ 15 % at quarry
Cement
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :
Unit
Nos
Nos
cum
kg
cum

Description

Unit

5 hp diesel pump
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

Quantity
730.00
200.00
6.75
4050.00
13.99

Quantity
4.00
4.00

Quantity

1
2
3
4
5

Crew for Pump


Hour
4.00
work inspector
Day
1.00
Cartman with double bullock cart
Day
2.00
Mason Class II
Day
7.00
mazdoor
Day
16.00
Total cost of Labour
labour component/unit qty
92.10
Add contractor's profit and overhead charges
13.615% 12.50
labour component/unit qty (including contractor's profit)
104.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item
IRR-CAW-8-1 - Note )

100.00 sqm
Rate
in Rs.
16.00
39.00
360.00
6.30
760.00
Rs:

Amount
in Rs.
11680.00
7800.00
2430.00
25515.00
10632.40
58057.40

Rate
in Rs.
10.20
81.30
Rs:

Amount
in Rs.
40.80
325.20
366.00

Rate
in Rs.
103.60
400.00
425.00
370.00
310.00
Rs:

Amount
in Rs.
414.40
400.00
850.00
2590.00
4960.00
9214.40

Rs:
Rs:
Rs:
Rs:

58057.40
366.00
9214.40
67637.80

Rs:
Rs:
Rs.

9208.89
76846.69
768.50
37.60

IRR-CAW-8-13 Providing 10 cm thick approved type grass turfing to the side slopes of canal including cost of
all materials, labour, watering for minimum 15 days etc.,complete with lead 50 m and all lifts.
(FA : 2 cum/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Turfing sods
Sand for filling

UNIT :
Unit
sqm
cum

Quantity
100.00
2.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description
Nill

Unit

Quantity
0.00

100.00 sqm
Rate
in Rs.
28.00
560.00
Rs:

Amount
in Rs.
2800.00
1120.00
3920.00

Rate
in Rs.
0.00

Amount
in Rs.
0.00

224

Canal and Allied Works - Item Unit Rates 2015-16

0.00
Total hire charges of Machinery
C. LABOUR:
Sl No

Description

Unit

Quantity

1
2
3

work inspector
Day
0.10
Cartman with double bullock cart
Day
2.00
mazdoor
Day
14.00
Total cost of Labour
labour component/unit qty
52.30
Add contractor's profit and overhead charges
13.615% 7.10
labour component/unit qty (including contractor's profit)
59.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100.0

0.00
Rs:

0.00
0.00

Rate
in Rs.
400.00
425.00
310.00
Rs:

Amount
in Rs.
40.00
850.00
4340.00
5230.00

Rs:
Rs:
Rs:
Rs:

3920.00
0.00
5230.00
9150.00

Rs:
Rs:
Rs.

1245.77
10395.77
104.00

IRR-CAW-8-14 Providing 10 cm Thick approved type gross turfing to the side slopes of canal including cost of
all materials ,labour,watering for minimum 15 days etc.,,complete.
with initial lead upto 50 m and all lifts ( WITHOUT USING SAND)

DATA:

RATE ANALYSIS

UNIT :

100.00 Sqm

A. MATERIALS :
Sl No
1

Particulars
Turfing Sods
Total Cost of materials

Unit
Sqm

Quantity
100.00

Rate
in Rs
28.00

Rs :

Amount
in Rs
2800.00
2800.00

B.MACHINERY :
Sl No

Description

Nill

Unit

Quantity
0.00
0.00

Rate
in Rs
0.00
0.00

Total hire charges of machinery


Rs :

Amount
in Rs
0.00
0.00
0.00

C.LABOUR :
Sl No

Description

Unit

Quantity

1
2

Mazdoor
Day
7.00
Cart men with double bullock cart
Day
2.00
Total cost of labour
Rs :
labour component/unit qty
30.20
Add contractor's profit and overhead charges
13.615% 4.10
labour component/unit qty (including contractor's profit)
34.30
ABSTRACT
A.Cost of Materials including ryolty charges
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)

13.615%

Rate
in Rs
310.00
425.00

Amount
in Rs
2170.00
850.00
3020.00

Rs:
Rs:
Rs:
Rs:

2800.00
0.00
3020.00
5820.00

Rs:

792.39

225

Canal and Allied Works - Item Unit Rates 2015-16

Total cost for


Rate per
Sqm

100.00 Sqm
(A+B+C+D)/100.0

Rs:
Rs.

6612.39
66.10

226

Canal Cross Drainage Works - Item Unit Rates 2015-16

CHAPTER-IV
CANAL CROSS DRAINAGE WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :2015-16
Index- code
IRR-CCDW

CANAL CROSS DRAINAGE WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing
the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead
as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total
lead involved and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and
unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate
and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges forRs.
5 km
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km
Rs.
/cum
208.60
Less 1 km initial lead charges
Rs./cum
31.30 (-)
Net additional lead chargesRs.
/ cum
177.30

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be
added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges forRs.
5 km
83.60
Lead charges for next 10 km
Rs.
125
Total lead charges for 15 km
Rs.
/cum
208.60
Less 1 km initial lead charges
Rs./cum
31.30 (-)
Net additional lead chargesRs.
/ cum
177.30
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
CCDW - Work Items
IRR-CCDW-1

EXCAVATION & FOUNDATION TREATMENT WORKS :

IRR-CCDW-1-1

Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal
cross drainage and other appurtenant structures and placing the excavated stuff neatly in
specified dump area or disposing off the same as directed etc., complete with initial lead upto
50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS

UNIT :

10.00 cum

230

Canal Cross Drainage Works - Item Unit Rates 2015-16

A. MATERIALS:
Sl No
Particulars
1

Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Unit

Quantity

NIL

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
Description

Unit

1
2

Day
Day

work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
0.25
6.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
100.00
1860.00
1960.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1960.00
1960.00
266.85
2226.85
222.70

196.00
13.615% 26.70
222.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

IRR-CCDW-1-2

DATA:

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

Excavation for Structures- Mechanical Means


( Data adopted from MORTH)
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and
technical specification, including setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and backfilling with approved material.
Depth upto 3 m
Unit = cum
Taking output = 240 cum
cum
Unit
240.00
A. Materials:
Sl No
Description
Unit
Quantity
Rate
Amount
in Rs.
in Rs.
NIL
0.00
0.00
0.00
B. Machinery:
Sl No
Description

Unit

hour
hour

Hydraulic excavator 1.0 cum bucket


capacity
Fuel/ Energy charges
Total in Rs.

C. Labour:
Sl No
Description

Unit

1
2
3

day
day
hour

work inspector
Mazdoor
crew for excavator
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Abstract
a) Material
b) Machinery
c) Labour
Total

Quantity
6.00

Rate
in Rs.
1706.60

Amount
in Rs.
10239.60

6.00

893.90

5363.40
15603.00

Rate
in Rs.
400.00
310.00
221.00

Amount
in Rs.
128.00
2480.00
1326.00
3934.00

Quantity
0.32
8.00
6.00

16.40
13.615% 2.20
18.60

Rs
Rs
Rs
Rs

0.00
15603.00
3934.00
19537.00

231

Canal Cross Drainage Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per cum

13.615% Rs:
240.00 cum
Rs:
(A+B+C+D)/240.0
Rs.

2659.96
22196.96
92.50

IRR-CCDW-1-3

Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.
for foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

UNIT :
Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Unit

Quantity

NIL

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
Description

Unit

1
2
3
4

Day
Day
Day
Day

Crowbarman
Stone breaker
work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
1.25
1.25
0.25
6.00

10.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
370.00
400.00
310.00
Rs:

Amount
in Rs.
462.50
462.50
100.00
1860.00
2885.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
2885.00
2885.00
392.79
3277.79
327.80

288.50
13.615% 39.30
327.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

IRR-CCDW-1-4

DATA:

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

Excavation in ordnary rock without blasting for foundations of canal cross drainage
and other appurtenant structures and placing the excavated stuff neatly in specified dump
area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
( Data adopted from MORTH)
Mechanical Means
Unit = cum
Taking output = 180 cum
Unit:
180.00
A. Materials:
Sl No
Description
Unit
Quantity
Rate
in Rs.
NIL
0.00
0.00
B. Machinery:
Sl No
Description

Unit

1.0

Hydraulic excavator 1.0 cum bucket capacity

hour

Fuel/ Energy charges


Total in Rs.

hour

C. Labour:
Sl No
Description

Unit

Quantity

cum
Amount
in Rs.
0.00

6.00

Rate
in Rs.
1706.60

Amount
in Rs.
10239.60

6.00

893.90

5363.40
15603.00

Rate

Amount

Quantity

232

Canal Cross Drainage Works - Item Unit Rates 2015-16

1
2
3

work inspector
Mazdoor
crew for excavator
Total in Rs.

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

day
day
hour

0.24
6.00
6.00

Rs
Rs
Rs
Rs
13.615% Rs:
180.00 cum
Rs:
(A+B+C+D)/180.0
Rs.

Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

2
3
4
5
6

Use rate of drill rod 1.6 m length


Reconditioning charges @
Use rate of air hose 2 Nos.
Explosive small dia ( Kelvex-220 )
Electric detonators
Detonating fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

UNIT :
Unit

Quantity

Rm
10%
Hour
kg
Nos
Rm
LS

Unit

43.50

Quantity

Unit

1
2
3
4
5
6
7
8

Hour
Hour
Day
Day
Day
Day
Day
Day

3.00
3.00
6.00
6.00

Quantity
3.00
6.00
1.00
0.50
0.50
6.00
3.00
51.00

Rate
in Rs.
20.75
0.23
70.00
13.00
11.00
20.00
Rs:

Amount
in Rs.
902.63
90.26
1.39
1400.00
377.00
770.00
10.00
3551.28

Rate
in Rs.
275.60
914.20
19.80
0.00
Rs:

Amount
in Rs.
826.80
2742.60
118.80
0.00
3688.20

Rate
in Rs.
195.90
306.20
400.00
480.00
370.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
587.70
1837.20
400.00
240.00
185.00
2220.00
1110.00
15810.00
22389.90

Rs:
Rs:
Rs:
Rs:

3551.28
3688.20
22389.90
29629.38
4034.04

223.90
13.615% 30.50
254.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)

0.00
15603.00
3282.00
18885.00
2571.19
21456.19
119.20

100 cum

6.00
20.00
29.00
70.00
0.50

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
Description
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

in Rs.
96.00
1860.00
1326.00
3282.00

18.20
13.615% 2.50
20.70

IRR-CCDW-1-5

in Rs.
400.00
310.00
221.00

Total
13.615% Rs:

233

Canal Cross Drainage Works - Item Unit Rates 2015-16

Total cost for


Rate per cum

100.00 cum
(A+B+C+D)/100.0

Rs:
Rs.

33663.415
336.60

IRR-CCDW-1-6

Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated rock neatly in specified dump area or stack yard as directed etc., complete with
initial lead upto 50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Explosive small dia ( Kelvex-220 )


Ordinary detonator
Electric detonator
Detonating fuse coil
Use rate of air hose 2 Nos.
Use rate of drill rod
Reconditioning charges @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammer 2 Nos
Fuel / Energy charges
Total hire charges of Machinery

UNIT :
Unit
kg
No.
No.
Rm
Hour
Rm
10%

Unit

32.00
8.00
104.00
150.00
16.00
98.30

Quantity

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
Description

Unit

1
2
3
4
5
6
7
8

Hour
Hour
Day
Day
Day
Day
Day
Day

Crew for Air compressor


Crew for Jack hammer
Blaster licensed
Helper blasting
work inspector
Crowbarman
Stone breaker
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity

8.00
8.00
16.00
16.00

Quantity
8.00
16.00
1.00
1.00
1.00
6.00
6.00
51.00

100.00 cum
Rate
in Rs.
70.00
7.00
13.00
11.00
11.56
27.67
Rs:

Amount
in Rs.
2240.00
56.00
1352.00
1650.00
185.00
2719.63
271.96
8474.60

Rate
in Rs.
275.60
914.20
19.80
0.00
Rs:

Amount
in Rs.
2204.80
7313.60
316.80
0.00
9835.20

Rate
in Rs.
195.90
306.20
480.00
370.00
400.00
370.00
370.00
310.00
Rs:

Amount
in Rs.
1567.20
4899.20
480.00
370.00
400.00
2220.00
2220.00
15810.00
27966.40

Rs:
Rs:
Rs:
Rs:

8474.60
9835.20
27966.40
46276.20
6300.5
52576.70
525.80

279.70
13.615% 38.10
317.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

IRR-CCDW-1-7

DATA:

Total
13.615% Rs:
100.00 cum
Rs:
(A+B+C+D)/100.0
Rs.

Excavation in hard rock with blasting prohibited for foundations of canal cross drainage
and other appurtenant structures and placing the excavated rock neatly in
or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and
initial lift upto 3 m.
Hard Rock ( blasting prohibited )
( Data adopted from MORTH)
Unit = cum
Taking output = 10 cum
Mechanical Means
10.00
A.Materials:
Sl No
Description

Unit

Quantity

Rate
in Rs.

cum

Amount
in Rs.

234

Canal Cross Drainage Works - Item Unit Rates 2015-16

NIL

0.00

0.00

0.00

Amount
in Rs.
1447.80

b)
Machinery
Sl No
Description

Unit

1.0

hour

6.00

Rate
in Rs.
241.30

hour

6.00

731.40

4388.40
5836.20

Rate
in Rs.
400.00
310.00
195.90

Amount
in Rs.
80.00
1550.00
1175.40
2805.40

Air Compressor 250 cft with 2 leads of


pneumatic breaker
Fuel/ Energy charges
Total in Rs.

c) Labour
Sl No
Description

Unit

1
2
3

day
day
hour

work inspector
Mazdoor
crew for compressor
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Quantity

Quantity
0.20
5.00
6.00

280.50
13.615% 38.20
318.70

Rs
Rs
Rs
Rs
10.00 cum
(A+B+C+D)/10.0

13.615% Rs:
Rs:
Rs.

IRR-CCDW-1-8

Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with
1.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded in
concrete / masonry including cost of all materials, machinery, labour, drilling and cleaning
hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead
upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement for grouting


25 mm dia steel
Use rate of 32 mm dia drill rod
Reconditioning charges @
Use rate of air hose
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammer 2 Nos
Fuel / Energy charges
Total hire charges of Machinery

UNIT :
Unit
kg
kg
Rm
10%
Hour

Unit

5.00
101.00
12.50
2.00

Quantity

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
Description

Unit

1
2
3
4
5
6

Hour
Hour
Day
Day
Day
Day

Crew for Air compressor


Crew for Jack hammer
Mason Class-II
Bar bender
work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges

Quantity

1.00
1.00
2.00
2.00

Quantity
1.00
2.00
0.50
0.50
0.50
1.00

0.00
5836.20
2805.40
8641.60
1176.55
9818.15
981.80

10.00 Nos.
Rate
in Rs.
6.30
40.00
27.67
11.56
Rs:

Amount
in Rs.
31.50
4040.00
345.83
34.58
23.13
4475.04

Rate
in Rs.
275.60
914.20
19.80
0.00
Rs:

Amount
in Rs.
275.60
914.20
39.60
0.00
1229.40

Rate
in Rs.
195.90
306.20
370.00
490.00
400.00
310.00
Rs:

Amount
in Rs.
195.90
612.40
185.00
245.00
200.00
310.00
1748.30

174.80
13.615% 23.80

235

Canal Cross Drainage Works - Item Unit Rates 2015-16

labour component/unit qty (including contractor's profit)

198.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per each

Total
13.615% Rs:
10.00 Nos.
Rs:
(A+B+C+D)/10.0
Rs.

Rs:
Rs:
Rs:
Rs:

IRR-CCDW-2

STEEL AND CEMENT CONCRETE WORKS :

IRR-CCDW-2-1

Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

1
2
3

kg
kg
LS

Rein.Steel with 5 % wastage


Binding wire 1.25 mm dia
Sundries ( chairs / spacers etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

UNIT :

Unit

Quantity
1050.00
8.00
3.00

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
Description

Unit

1
2
3

Day
Day
Day

work inspector
Bar bender
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
1.00
6.00
11.00

1000.00 kg
Rate
in Rs.
40.00
70.00
20.00
Rs:

Amount
in Rs.
42000.00
560.00
60.00
42620.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
490.00
310.00
Rs:

Amount
in Rs.
400.00
2940.00
3410.00
6750.00

Rs:
Rs:
Rs:
Rs:

42620.00
0.00
6750.00
49370.00
6721.73
56091.73
56.10

6.80
13.615% 0.90
7.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per kg

IRR-CCDW-2-2

4475.04
1229.40
1748.30
7452.74
1014.69
8467.43
846.70

Total
13.615% Rs:
1000.00 kg
Rs:
(A+B+C+D)/1000.0
Rs.

Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x
100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter
foundation wells foundation wells including cost of all materials, machinery, labour, bending,
welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.

DETAILS OF FOUNDATION WELL CUTTING EDGE

236

Canal Cross Drainage Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Particulars

Unit

Str.Steel angle with 2.5 % wastage


Str.Steel plate with 2.5 % wastage
Steel for anchors
Acetyline gas
Oxygen gas
Welding electrodes
Sundries
Total cost of Materials

kg
kg
kg
cum
cum
Nos
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Unit

Str. Steel fabricator


Welder / Gas cutter
work inspector
mazdoor

Quantity
216.10
342.30
56.60
0.50
1.50
300.00
5.00

Quantity
8.00
8.00
30.00
30.00
10.00

Quantity

Day
Day
Day
Day

2.00
5.00
1.00
5.00

Total cost of Labour


labour component/unit qty
8.10
Add contractor's profit and overhead charges
13.615% 1.10
labour component/unit qty (including contractor's profit)
9.20

615.00 kg
Rate
in Rs.
40.00
40.00
40.00
330.00
45.00
11.00
20.00
Rs:

Amount
in Rs.
8644.00
13692.00
2264.00
165.00
67.50
3300.00
100.00
28232.50

Rate
in Rs.
42.60
115.50
16.00
92.40
20.00
Rs:

Amount
in Rs.
340.80
924.00
480.00
2772.00
200.00
4716.80

Rate
in Rs.
480.00
415.00
400.00
310.00
Rs:

Amount
in Rs.
960.00
2075.00
400.00
1550.00
4985.00

Rs:
Rs:
Rs:
Rs:

28232.50
4716.80
4985.00
37934.30
5164.75
43099.05
70.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per kg

Total
13.615% Rs:
615.00 kg
Rs:
(A+B+C+D)/615.0
Rs.

IRR-CCDW-2-3 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Data

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5

Particulars

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm

Quantity
3998.80
46.14
6.92
4.15
2.77
6.15
16.00
15.38

15.38 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00
225.53

Amount
in Rs.
25192.44
290.68
7924.55
5024.65
2422.35
3445.12
1519.54
3468.64

237

Canal Cross Drainage Works - Item Unit Rates 2015-16

Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

10%
LS

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

20.00
Rs:

346.86
10.00
49644.83

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
60.80
164.80
2059.45

Rate
in Rs.
204.10
103.60
165.80
146.90
400.00
415.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
400.00
415.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
930.00
4767.80
310.00
1227.32
122.73
15848.46

0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Needle vibrator
Hour
8.00
work inspector
Day
1.00
Mason Class-I
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
15.38
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
15.38
Labour cost for scaffolding @
10%
Total cost of Labour
labour component/unit qty
1030.50
Add contractor's profit and overhead charges
13.615% 140.30
labour component/unit qty (including contractor's profit)
1170.80

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
15.38 cum
Rs:
(A+B+C+D)/15.38
Rs.

49644.83
2059.45
15848.46
67552.73
9197.3
76750.03
4990.20

IRR-CCDW-2-4 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4

Particulars

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT :
Unit
kg
kg
cum
cum
cum
cum
cum
kg

Quantity
3600.00
43.20
4.94
4.23
2.82
2.12
5.04
14.40

14.40 cum
Rate
in Rs.
6.30
6.30
635.00
1145.00
1210.00
875.00
560.00
95.00

Amount
in Rs.
22680.00
272.16
3136.39
4847.47
3415.10
1852.20
2822.40
1368.00

238

Canal Cross Drainage Works - Item Unit Rates 2015-16

5
6

Use rate of shuttering for 40 uses


Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

sqm
10%
LS

Description

Unit

Concrete mixer 600/400 ltr ( diesel)


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol)
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

14.40

225.53

0.50

20.00
Rs:

3247.62
324.76
10.00
43976.11

Rate
in Rs.
92.70
162.50
10.20
81.30
402.50
307.20
8.20
30.80
Rs:

Amount
in Rs.
741.60
1300.00
5.10
40.65
402.50
307.20
65.60
246.40
3109.05

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
930.00
4464.00
310.00
1149.12
114.91
15458.63

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
14.40
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
14.40
Labour cost for scaffolding @
10%
Total cost of Labour
labour component/unit qty
1073.50
Add contractor's profit and overhead charges
13.615% 146.20
labour component/unit qty (including contractor's profit)
1219.70

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.

43976.11
3109.05
15458.63
62543.79
8515.34
71059.13
4934.70

IRR-CCDW-2-5 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4

Particulars

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg

Quantity
3599.20
49.08
7.36
4.42
2.94
6.54
14.40

16.36 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00

Amount
in Rs.
22674.96
309.20
8429.49
5344.81
2576.70
3664.64
1367.70

239

Canal Cross Drainage Works - Item Unit Rates 2015-16

5
6

Use rate of shuttering for 40 uses


Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

sqm
10%
LS

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

16.36

225.53

0.50

20.00
Rs:

3689.65
368.97
10.00
48436.12

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
60.80
164.80
2059.45

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
930.00
5071.60
310.00
1305.53
16107.73

Rs:
Rs:
Rs:
Rs:

48436.12
2059.45
16107.73
66603.30
9068.04
75671.34
4625.40

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
16.36
8
for cleaning/ washing/ curing
Day
1.00
9
Labour cost for shuttering
sqm
16.36
Total cost of Labour
labour component/unit qty
984.60
Add contractor's profit and overhead charges
13.615% 134.10
labour component/unit qty (including contractor's profit)
1118.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
16.36 cum
Rs:
(A+B+C+D)/16.36
Rs.

IRR-CCDW-2-6 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4

Particulars

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT :
Unit
kg
kg
cum
cum
cum
cum
cum
kg

Quantity
3201.00
43.65
4.99
4.28
2.85
2.14
5.09
12.80

14.55 cum
Rate
in Rs.
6.30
6.30
635.00
1145.00
1210.00
875.00
560.00
95.00

Amount
in Rs.
20166.30
275.00
3169.06
4897.97
3450.68
1871.49
2851.80
1216.38

240

Canal Cross Drainage Works - Item Unit Rates 2015-16

5
6

Use rate of shuttering for 40 uses


Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

sqm
10%
LS

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

14.55

225.53

0.50

20.00
Rs:

3281.45
328.14
10.00
41518.27

Rate
in Rs.
92.70
162.50
10.20
81.30
402.50
307.20
8.20
30.80
Rs:

Amount
in Rs.
741.60
1300.00
5.10
40.65
402.50
307.20
65.60
246.40
3109.05

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
930.00
4510.50
310.00
1161.09
116.11
15518.30

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
14.55
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
14.55
Labour cost for scaffolding @
10%
Total cost of Labour
labour component/unit qty
1066.50
Add contractor's profit and overhead charges
13.615% 145.20
labour component/unit qty (including contractor's profit)
1211.70

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
14.55 cum
Rs:
(A+B+C+D)/14.55
Rs.

41518.27
3109.05
15518.30
60145.62
8188.83
68334.45
4696.50

IRR-CCDW-2-7 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )
(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4

Particulars

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg

Quantity
4398.90
42.57
6.39
3.83
2.55
5.68
17.60

14.19 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00

Amount
in Rs.
27713.07
268.19
7311.40
4635.87
2234.93
3178.56
1671.58

241

Canal Cross Drainage Works - Item Unit Rates 2015-16

5
6

Use rate of shuttering for 40 uses


Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

sqm
10%
LS

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

14.19

225.53

0.50

20.00
Rs:

3200.26
320.03
10.00
50543.88

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
60.80
164.80
2059.45

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
930.00
4398.90
310.00
1132.36
113.24
15375.10

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
14.19
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
14.19
Labour cost for scaffolding @
10%
Total cost of Labour
labour component/unit qty
1083.50
Add contractor's profit and overhead charges
13.615% 147.50
labour component/unit qty (including contractor's profit)
1231.00

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
14.19 cum
Rs:
(A+B+C+D)/14.19
Rs.

50543.88
2059.45
15375.10
67978.43
9255.26
77233.69
5442.80

IRR-CCDW-2-8 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4

Particulars

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg

Quantity
4800.00
75.00
6.75
4.05
2.70
6.00
19.20

15.00 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00

Amount
in Rs.
30240.00
472.50
7728.75
4900.50
2362.50
3360.00
1824.00

242

Canal Cross Drainage Works - Item Unit Rates 2015-16

5
6

Use rate of shuttering


Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

sqm
25%
LS

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

30.00

225.53

0.50

20.00
Rs:

6765.87
1691.47
10.00
59355.59

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
60.80
164.80
2059.45

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1240.00
4650.00
310.00
1197.00
299.25
16186.85

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying including lifting
Day
4.00
for conveying concrete
Day
15.00
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
15.00
Labour cost for scaffolding @
25%
Total cost of Labour
labour component/unit qty
1079.10
Add contractor's profit and overhead charges
13.615% 146.90
labour component/unit qty (including contractor's profit)
1226.00

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
15.00 cum
Rs:
(A+B+C+D)/15.0
Rs.

59355.59
2059.45
16186.85
77601.89
10565.5
88167.39
5877.80

IRR-CCDW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

Particulars

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering

UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
31.52

15.76 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53

Amount
in Rs.
32765.04
496.44
9916.19
3861.20
3971.52
1976.30
7108.67

243

Canal Cross Drainage Works - Item Unit Rates 2015-16

Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

25%
LS

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

20.00
Rs:

1777.17
10.00
61882.54

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
60.80
164.80
2059.45

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1240.00
4885.60
310.00
2515.30
628.82
18070.32

0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
4.00
for conveying concrete
Day
15.76
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
31.52
Labour cost for scaffolding @
25%
Total cost of Labour
labour component/unit qty
1146.60
Add contractor's profit and overhead charges
13.615% 156.10
labour component/unit qty (including contractor's profit)
1302.70

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

61882.54
2059.45
18070.32
82012.31
11165.98
93178.289
5912.30

IRR-CCDW-2-10 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

Particulars

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering

UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
25%

Quantity
4398.80
78.55
8.17
4.40
7.07
17.60
31.42

15.71 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53

Amount
in Rs.
27712.44
494.87
9884.73
3848.95
3958.92
1671.54
7086.12
1771.53

244

Canal Cross Drainage Works - Item Unit Rates 2015-16

Sundries

LS

0.50

20.00
Rs:

10.00
56439.10

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
60.80
164.80
2059.45

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1240.00
4870.10
310.00
2507.32
626.83
18044.85

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
4.00
for conveying concrete
Day
15.71
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
31.42
Labour cost for scaffolding @
25%
Total cost of Labour
labour component/unit qty
1148.60
Add contractor's profit and overhead charges
13.615% 156.40
labour component/unit qty (including contractor's profit)
1305.00

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
15.71 cum
Rs:
(A+B+C+D)/15.71
Rs.

56439.10
2059.45
18044.85
76543.40
10421.38
86964.777
5535.60

IRR-CCDW-2-11 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries

UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
25%
LS

Quantity

18.00 cum

3960.00
90.00
9.36
5.04
8.10
15.84
36.00

Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53

0.50

20.00

Amount
in Rs.
24948.00
567.00
11325.60
4410.00
4536.00
1504.80
8119.04
2029.76
10.00

245

Canal Cross Drainage Works - Item Unit Rates 2015-16

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
4.00
for conveying concrete
Day
18.00
for cleaning/ washing/ curing
Day
1.00
8
Labour cost for shuttering
sqm
36.00
Labour cost for scaffolding @
25%
Total cost of Labour
labour component/unit qty
1067.30
Add contractor's profit and overhead charges
13.615% 145.30
labour component/unit qty (including contractor's profit)
1212.60

Rs:

57450.21

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
60.80
164.80
2059.45

Rate
in Rs.
204.10
103.60
165.80
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
165.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1240.00
5580.00
310.00
2872.80
718.20
19211.60

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
18.00 cum
Rs:
(A+B+C+D)/18.0
Rs.

57450.21
2059.45
19211.60
78721.26
10717.9
89439.155
4968.80

IRR-CCDW-2-12 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well kerb including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

UNIT :

Particulars

Unit

Cement for mix


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of curved shutter (40 uses)
Sundries
Total cost of Materials

kg
cum
cum
cum
kg
sqm
LS

Quantity
5250.00
7.80
4.20
6.75
21.00
82.50
0.50

15.00 cum
Rate
in Rs.
6.30
1210.00
875.00
560.00
95.00
248.08
20.00
Rs:

Amount
in Rs.
33075.00
9438.00
3675.00
3780.00
1995.00
20466.76
10.00
72439.76

246

Canal Cross Drainage Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

1
2
3
4
5
6

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
15.00
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
82.50
Total cost of Labour
labour component/unit qty
1386.60
Add contractor's profit and overhead charges
13.615% 188.80
labour component/unit qty (including contractor's profit)
1575.40

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
930.00
4650.00
310.00
6583.50
20798.30

Rs:
Rs:
Rs:
Rs:

72439.76
1349.75
20798.30
94587.81
12878.13
107465.94
7164.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
15.00 cum
Rs:
(A+B+C+D)/15.0
Rs.

IRR-CCDW-2-13 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well steining including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 2 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of curved shutter (40 uses)
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
LS

B. MACHINERY:
Sl No
1

UNIT :

Description

Concrete mixer 300/200 ltr ( diesel )

Unit
Hour

Quantity
4800.00
30.00
6.75
4.05
2.70
6.00
19.20
60.00
0.50

Quantity
8.00

15.00 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00
248.08
20.00
Rs:

Amount
in Rs.
30240.00
189.00
7728.75
4900.50
2362.50
3360.00
1824.00
14884.91
10.00
65499.66

Rate
in Rs.
53.50

Amount
in Rs.
428.00

247

Canal Cross Drainage Works - Item Unit Rates 2015-16

2
3

Fuel / Energy charges


5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Hour
Hour
Hour
Hour
Hour

Unit

8.00
0.50
0.50
8.00
8.00

Quantity

1
2
3
4
5
6

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
15.00
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
60.00
Total cost of Labour
labour component/unit qty
1266.90
Add contractor's profit and overhead charges
13.615% 172.50
labour component/unit qty (including contractor's profit)
1439.40

81.30
10.20
81.30
7.60
20.60
Rs:

650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
930.00
4650.00
310.00
4788.00
19002.80

Rs:
Rs:
Rs:
Rs:

65499.66
1349.75
19002.80
85852.21
11688.78
97540.99
6502.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
15.00 cum
Rs:
(A+B+C+D)/15.0
Rs.

IRR-CCDW-2-14 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sq
mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well bottom plug by tremie or skip box method including cost of all materials,
machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Cement for mix


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT :
Unit
kg
cum
cum
cum
kg

Add for tremie arrangement @


Total cost of Materials
B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Sundries( Hopper etc. )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

Quantity
4900.00
7.28
3.92
6.30
19.60
TOTAL
1%

Quantity
8.00
8.00
0.50
0.50
5.00

14.00 cum
Rate
in Rs.
6.30
1210.00
875.00
560.00
95.00
Rs:
Rs:
Rs:

Amount
in Rs.
30870.00
8808.80
3430.00
3528.00
1862.00
48498.80
484.99
48983.79

Rate
in Rs.
53.50
81.30
10.20
81.30
20.00
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
100.00
1224.15

C. LABOUR:

248

Canal Cross Drainage Works - Item Unit Rates 2015-16

Sl No

Description

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Fitter shuttering
Day
1.00
work inspector
Day
1.00
mazdoor
for erecting/ dismantling tremie
Day
4.00
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for feeding tremie hopper
Day
2.00
for conveying concrete
Day
16.00
Total cost of Labour
labour component/unit qty
994.60
Add contractor's profit and overhead charges
13.615% 135.40
labour component/unit qty (including contractor's profit)
1130.00

Rate
in Rs.
204.10
103.60
370.00
400.00

Amount
in Rs.
1632.80
51.80
370.00
400.00

310.00
310.00
310.00
310.00
310.00
Rs:

1240.00
3410.00
1240.00
620.00
4960.00
13924.60

Rs:
Rs:
Rs:
Rs:

48983.79
1224.15
13924.60
64132.54
8731.65
72864.19
5204.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
14.00 cum
Rs:
(A+B+C+D)/14.0
Rs.

IRR-CCDW-2-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well top plug including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4

Particulars

Unit

Cement for mix


Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Total cost of Materials

kg
cum
cum
cum
cum
kg

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials

Unit

Quantity
4001.20
6.43
3.86
2.57
5.72
16.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

14.29 cum
Rate
in Rs.
6.30
1145.00
1210.00
875.00
560.00
95.00
Rs:

Amount
in Rs.
25207.56
7362.92
4668.54
2250.68
3200.96
1520.46
44211.12

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00
3410.00

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Day

11.00

310.00

249

Canal Cross Drainage Works - Item Unit Rates 2015-16

for loading mortar pans


Day
4.00
for laying
Day
3.00
for conveying concrete
Day
14.29
for cleaning/ washing/ curing
Day
1.00
Total cost of Labour
labour component/unit qty
979.30
Add contractor's profit and overhead charges
13.615% 133.30
labour component/unit qty (including contractor's profit)
1112.60

310.00
310.00
310.00
310.00
Rs:

1240.00
930.00
4429.90
310.00
13994.70

Rs:
Rs:
Rs:
Rs:

44211.12
1349.75
13994.70
59555.57
8108.49
67664.06
4735.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
14.29 cum
Rs:
(A+B+C+D)/14.29
Rs.

IRR-CCDW-2-16 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well cap including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of curved shutter (40 uses)
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
15.76
0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Description

Unit

Quantity

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Labour cost for shuttering
Total cost of Labour

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Day
Day
Day
Day
Day
sqm

11.00
4.00
3.00
15.76
1.00
15.76

15.76 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53
20.00
Rs:

Amount
in Rs.
32765.04
496.44
9916.19
3861.20
3971.52
1976.30
3554.34
10.00
56551.03

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
930.00
4885.60
310.00
1257.65
15708.05

250

Canal Cross Drainage Works - Item Unit Rates 2015-16

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

996.70
13.615% 135.70
1132.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

56551.03
1349.75
15708.05
73608.83
10021.84
83630.67
5306.50

IRR-CCDW-2-17 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Unit

Quantity
3600.00
72.00
4.94
4.23
2.82
2.12
5.04
14.40
39.60

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
6.00
for conveying concrete
Day
14.40
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
39.60
Labour cost for scaffolding @
30%
Total cost of Labour
labour component/unit qty
1324.10
Add contractor's profit and overhead charges
13.615% 180.30

14.40 cum
Rate
in Rs.
6.30
6.30
635.00
1145.00
1210.00
875.00
560.00
95.00
236.81
Rs:

Amount
in Rs.
22680.00
453.60
3136.39
4847.47
3415.10
1852.20
2822.40
1368.00
9377.50
2813.25
52765.91

Rate
in Rs.
92.70
162.50
10.20
81.30
8.20
30.80
Rs:

Amount
in Rs.
741.60
1300.00
5.10
40.65
65.60
246.40
2399.35

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1860.00
4464.00
310.00
3160.08
948.02
19066.90

Rs:

251

Canal Cross Drainage Works - Item Unit Rates 2015-16

labour component/unit qty (including contractor's profit)

1504.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.

52765.91
2399.35
19066.90
74232.17
10106.71
84338.877
5856.90

IRR-CCDW-2-18 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate ofshuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Unit

Quantity
3201.00
72.75
4.99
4.28
2.85
2.14
5.09
12.80
40.01

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
6.00
for conveying concrete
Day
14.55
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
40.01
Labour cost for scaffolding @
30%
Total cost of Labour
labour component/unit qty
1316.60
Add contractor's profit and overhead charges
13.615% 179.30
labour component/unit qty (including contractor's profit)
1495.90

14.55 cum
Rate
in Rs.
6.30
6.30
635.00
1145.00
1210.00
875.00
560.00
95.00
236.81
Rs:

Amount
in Rs.
20166.30
458.33
3169.06
4897.97
3450.68
1871.49
2851.80
1216.38
9475.18
2842.55
50399.74

Rate
in Rs.
92.70
162.50
10.20
81.30
8.20
30.80
Rs:

Amount
in Rs.
741.60
1300.00
5.10
40.65
65.60
246.40
2399.35

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1860.00
4510.50
310.00
3193.00
957.90
19156.20

Rs:

252

Canal Cross Drainage Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
14.55 cum
Rs:
(A+B+C+D)/14.55
Rs.

50399.74
2399.35
19156.20
71955.28
9796.71
81751.99
5618.70

IRR-CCDW-2-19 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
30%

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Quantity
3599.20
81.80
7.36
4.42
2.94
6.54
14.40
44.99

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
5.00
for conveying concrete
Day
16.36
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
44.99
Labour cost for scaffolding @
30%
Total cost of Labour
labour component/unit qty
1217.80
Add contractor's profit and overhead charges
13.615% 165.80
labour component/unit qty (including contractor's profit)
1383.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

16.36 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00
236.81
Rs:

Amount
in Rs.
22674.96
515.34
8429.49
5344.81
2576.70
3664.64
1367.70
10653.88
3196.16
58423.68

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
1550.00
5071.60
310.00
3590.20
1077.06
19923.66

Rs:
Rs:

58423.68
1349.75

253

Canal Cross Drainage Works - Item Unit Rates 2015-16

C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:

Total
13.615% Rs:
16.36 cum
Rs:
(A+B+C+D)/16.36
Rs.

19923.66
79697.09
10850.76
90547.85
5534.70

IRR-CCDW-2-20 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for cantiliver / counterfort retaining walls including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Note:

If water is to be brought from other place add only lead charges @ 500 ltr / cum.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
25%
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Quantity
5200.00
81.25
7.31
4.39
2.93
6.50
20.80
52.81
0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
5.00
for conveying concrete
Day
16.25
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
52.81
Labour cost for scaffolding @
25%
Total cost of Labour
labour component/unit qty
1260.90
Add contractor's profit and overhead charges
13.615% 171.70
labour component/unit qty (including contractor's profit)
1432.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

16.25 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00
225.53
20.00
Rs:

Amount
in Rs.
32760.00
511.88
8372.81
5308.88
2559.38
3640.00
1976.00
11910.75
2977.69
10.00
70027.38

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
1550.00
5037.50
310.00
4214.44
1053.61
20490.35

Rs:
Rs:
Rs:

70027.38
1349.75
20490.35

254

Canal Cross Drainage Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per cum

Total
13.615% Rs:
16.25 cum
Rs:
(A+B+C+D)/16.25
Rs.

Rs:

91867.47
12507.76
104375.23
6423.10

IRR-CCDW-2-21 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity
type retaining walls / piers / abutments etc., including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25cum )

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 4 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Plums of size 150 to 80 mm
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Quantity
4703.40
72.36
6.92
4.15
2.77
4.52
6.15
18.81
49.75

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
5.00
for placing plums
Day
2.00
for conveying concrete
Day
15.38
for conveying plums
Day
2.00
for cleaning/ washing/ curing
Day
1.00
7
Labour for shuttering
sqm
49.75
Labour for scaffolding @
30%
Total cost of Labour
labour component/unit qty
1180.40
Add contractor's profit and overhead charges
13.615% 160.70
labour component/unit qty (including contractor's profit)
1341.10
ABSTRACT:
A. Cost of Materials

18.09 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
360.00
560.00
95.00
225.53
Rs:

Amount
in Rs.
29631.42
455.87
7922.74
5023.50
2421.80
1628.10
3444.34
1787.29
11219.50
3365.85
66900.41

Rate
in Rs.
53.50
81.30
10.20
81.30
8.20
30.80
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
65.60
246.40
1436.15

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
1550.00
620.00
4767.80
620.00
310.00
3969.85
1190.96
21353.41

Rs:

66900.41

255

Canal Cross Drainage Works - Item Unit Rates 2015-16

B. Hire charges of Machinery


C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:

Total
13.615% Rs:
18.09 cum
Rs:
(A+B+C+D)/18.09
Rs.

1436.15
21353.41
89689.97
12211.29
101901.26
5633.00

IRR-CCDW-2-22 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,graded
aggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
15%
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Quantity
3998.80
76.90
6.92
4.15
2.77
6.15
16.00
30.76
0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
15.38
for cleaning/ washing/ curing
Day
1.00
7
Labour for shuttering
sqm
30.76
Labour for scaffolding @
15%
Total cost of Labour
labour component/unit qty
1115.40
Add contractor's profit and overhead charges
13.615% 151.90
labour component/unit qty (including contractor's profit)
1267.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

15.38 cum
Rate
in Rs.
6.30
6.30
1145.00
1210.00
875.00
560.00
95.00
236.81
20.00
Rs:

Amount
in Rs.
25192.44
484.47
7924.55
5024.65
2422.35
3445.12
1519.54
7284.14
1092.62
10.00
54399.87

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
930.00
4767.80
310.00
2454.65
368.20
17155.45

Rs:
Rs:
Rs:

54399.87
1349.75
17155.45

256

Canal Cross Drainage Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per cum

Total
13.615% Rs:
15.38 cum
Rs:
(A+B+C+D)/15.38
Rs.

Rs:

72905.07
9926.02
82831.09
5385.60

IRR-CCDW-2-23 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
15%

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Unit

Quantity
3600.00
72.00
4.94
4.23
2.82
2.12
5.04
14.40
28.80

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
14.40
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
28.80
Labour cost for scaffolding @
15%
Total cost of Labour
labour component/unit qty
1157.80
Add contractor's profit and overhead charges
13.615% 157.60
labour component/unit qty (including contractor's profit)
1315.40

14.40 cum
Rate
in Rs.
6.30
6.30
635.00
1145.00
1210.00
875.00
560.00
95.00
236.81
Rs:

Amount
in Rs.
22680.00
453.60
3136.39
4847.47
3415.10
1852.20
2822.40
1368.00
6820.00
1023.00
48418.16

Rate
in Rs.
92.70
162.50
10.20
81.30
8.20
30.80
Rs:

Amount
in Rs.
741.60
1300.00
5.10
40.65
65.60
246.40
2399.35

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
930.00
4464.00
310.00
2298.24
344.74
16671.78

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)

Total
13.615% Rs:

Rs:

Rs:
Rs:
Rs:
Rs:

48418.16
2399.35
16671.78
67489.29
9188.67

257

Canal Cross Drainage Works - Item Unit Rates 2015-16

Total cost for


Rate per cum

14.40 cum
(A+B+C+D)/14.40

Rs:
Rs.

76677.96
5324.90

IRR-CCDW-2-24 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 30 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
250%
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
39.40

15.76 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
274.37
20.00
Rs:

Amount
in Rs.
32765.04
496.44
9916.19
3861.20
3971.52
1976.30
10810.26
27025.64
20.00
90842.59

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
830.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1240.00
4885.60
310.00
3144.12
7860.30
26179.82

1.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
4.00
for conveying concrete
Day
15.76
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
39.40
Labour cost for scaffolding @
250%
Total cost of Labour
labour component/unit qty
1661.20
Add contractor's profit and overhead charges
13.615% 226.20
labour component/unit qty (including contractor's profit)
1887.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

Rs:

Rs:
Rs:
Rs:
Rs:

90842.59
1349.75
26179.82
118372.16
16116.37
134488.53
8533.50

258

Canal Cross Drainage Works - Item Unit Rates 2015-16

IRR-CCDW-2-25 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for columns and beams including cost of all materials, labour, machinery,
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note:

If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
50%
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
78.80

15.76 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53
20.00
Rs:

Amount
in Rs.
32765.04
496.44
9916.19
3861.20
3971.52
1976.30
17771.69
8885.84
20.00
79664.22

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
930.00
4885.60
310.00
6288.24
3144.12
23882.76

1.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
3.00
for conveying concrete
Day
15.76
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
78.80
Labour cost for scaffolding @
50%
Total cost of Labour
labour component/unit qty
1515.40
Add contractor's profit and overhead charges
13.615% 206.30
labour component/unit qty (including contractor's profit)
1721.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

Rs:

Rs:
Rs:
Rs:
Rs:

79664.22
1349.75
23882.76
104896.73
14281.69
119178.42
7562.10

IRR-CCDW-2-26 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /

259

Canal Cross Drainage Works - Item Unit Rates 2015-16

Note:

sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for wearing coat including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
and all lifts.
If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Sundries ( asphalt mortar etc )
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
7.88
5.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
4.00
for conveying concrete
Day
15.76
for cleaning/ washing/ curing
Day
2.00
7
Labour cost for shuttering
sqm
7.88
Total cost of Labour
labour component/unit qty
1022.50
Add contractor's profit and overhead charges
13.615% 139.20
labour component/unit qty (including contractor's profit)
1161.70

15.76 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53
20.00
Rs:

Amount
in Rs.
32765.04
496.44
9916.19
3861.20
3971.52
1976.30
1777.17
100.00
54863.86

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
830.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
1240.00
4885.60
620.00
628.82
16114.22

Rs:
Rs:
Rs:
Rs:

54863.86
1349.75
16114.22
72327.84
9847.44
82175.28
5214.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for troughs including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.

260

Canal Cross Drainage Works - Item Unit Rates 2015-16

Note:

If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
25%
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
70.92

15.76 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53
20.00
Rs:

Amount
in Rs.
32765.04
496.44
9916.19
3861.20
3971.52
1976.30
15994.52
3998.63
10.00
72989.84

Rate
in Rs.
53.50
81.30
10.20
81.30
7.60
20.60
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Rate
in Rs.
204.10
103.60
146.90
415.00
400.00

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80

3410.00
1240.00
1550.00
4885.60
310.00
5659.42
1414.85
22144.67

0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.50
Crew for Needle vibrator
Hour
8.00
Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying
Day
5.00
for conveying concrete
Day
15.76
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering
sqm
70.92
Labour cost for scaffolding @
25%
Total cost of Labour
labour component/unit qty
1405.10
Add contractor's profit and overhead charges
13.615% 191.30
labour component/unit qty (including contractor's profit)
1596.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-3

Total
13.615% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

Rs:

Rs:
Rs:
Rs:
Rs:

72989.84
1349.75
22144.67
96484.26
13136.33
109620.59
6955.60

FOUNDATION WELL SINKING WORKS :

IRR-CCDW-3-1 Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil,
DATA:
Unit = Running meter
Taking output = 1m
diameter of well = 6.00m
(i)
Depth below bed level upto 3.0m
Rate of sinking = 0.50 m /hour
a) Labour

261

Canal Cross Drainage Works - Item Unit Rates 2015-16

0.12
1.00
2.00

Mate (Mason Cl- ll )


Sinker ( skilled)
Sinking helper ( Semi skilled)

370.00 day
415.00 day
310.00 day

44.40
415.00
620.00
1079.40

sub total (a)


b) Machinery
2.00
Hire & running charges of crane with grab
519.70 hour
bucket of 0.75 cum capacity and accessories.
Fuel Charges
307.20 hour
Crew Charges
165.80 hour
Consumables in sinking @ 10% of machinery charges
sub total (b)
sub total (a+b)
c) Add for Contractor's profit and overhead
charges on (A+B)
13.615%
Rate per metre = (a+b+c)/1.0
or say ( Rate upto 3.0m for 6.0 m well sinking )
labour component/unit qty
Contractor's profit and overhead charges
13.615%
labour component/unit qty(including contractor's profit)
(ii)

1039.40
614.40
331.60
198.54
2183.94
3263.34
444.30
3707.64
3707.60
1411.00
192.10
1603.10

Beyond 3m and upto 10m depth


Rate of sinking = 0.33 m per hour.

a) Labour
0.15
1.25
2.50

Mate (Mason Cl- ll )


Sinker ( skilled)
Sinking helper ( Semi skilled)

370.00 day
415.00 day
310.00 day

55.50
518.75
775.00
1349.25

sub total (a)


b) Machinery
3.00
Hire & running charges of crane with grab
519.70 hour
bucket of 0.75 cum capacity and accessories.
Fuel Charges
307.20 hour
Crew Charges
165.80 hour
Consumables in sinking @ 10% of machinery charges
sub total (b)
sub total (a+b)
c) Add for Contractor's profit and overhead
charges on (A+B)
13.615%
Rate per metre = (a+b+c)
or say ( Rate for 3.0m to 10m well sinking )

1559.10
921.60
497.40
297.81
3275.91
4625.16
629.72
5254.88
5254.90

labour component/unit qty


Contractor's profit and overhead charges
13.615%
labour component/unit qty(including contractor's profit)

1846.70
251.40
2098.10

IRR-CCDW-3-2 Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,
ramming as directed including cost of all materials, machinery, labour etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Sand for filling

UNIT :
Unit
cum

Quantity
15.75

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Nill

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

15.00 cum
Rate
in Rs.
560.00
0.00
Rs:

Amount
in Rs.
8820.00
0.00
8820.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

262

Canal Cross Drainage Works - Item Unit Rates 2015-16

1
2

work inspector
mazdoor

Day
Day

0.25
4.00

Total cost of Labour


labour component/unit qty
89.30
Add contractor's profit and overhead charges
13.615% 12.20
labour component/unit qty (including contractor's profit)
101.50

400.00
310.00
Rs:

100.00
1240.00
1340.00

Rs:
Rs:
Rs:
Rs:

8820.00
0.00
1340.00
10160.00
1383.28
11543.28
769.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-4

Total
13.615% Rs:
15.00 cum
Rs:
(A+B+C+D)/15.0
Rs.

MASONRY WORKS :

IRR-CCDW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Cement
Rubble stones
Stone chips
Sand (Screened)

UNIT :
Unit

Quantity

kg
cum
cum
cum

1430.00
8.50
1.50
4.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Quantity
1.00
1.00
0.50
0.50

Quantity

Crew for Water tanker


Hour
Crew for Pump
Hour
work inspector
Day
Mason Class-I
Day
Mason Class-II
Day
mazdoor
for conveying rubble stones
Day
for preparing mortar
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
642.30
Add contractor's profit and overhead charges
13.615% 87.40
labour component/unit qty (including contractor's profit)
729.70

1.00
0.50
1.00
1.00
2.00

10.00 cum
Rate
in Rs.
6.30
330.00
360.00
760.00
Rs:

Amount
in Rs.
9009.00
2805.00
540.00
3040.00
15394.00

Rate
in Rs.
402.50
307.20
10.20
81.30
Rs:

Amount
in Rs.
402.50
307.20
5.10
40.65
755.45

Rate
in Rs.
165.80
103.60
400.00
415.00
370.00

Amount
in Rs.
165.80
51.80
400.00
415.00
740.00

310.00
310.00
310.00
310.00
310.00
310.00
Rs:

1240.00
620.00
310.00
930.00
310.00
1240.00
6422.60

Rs:
Rs:
Rs:
Rs:

15394.00
755.45
6422.60
22572.05

4.00
2.00
1.00
3.00
1.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

263

Canal Cross Drainage Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per cum

10.00 cum
(A+B+C+D)/10.0

13.615% Rs:
Rs:
Rs.

3073.18
25645.23
2564.50

IRR-CCDW-4-2 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Cement
Rubble stones
Stone chips
Sand (Screened)

UNIT :
Unit

Quantity

kg
cum
cum
cum

1430.00
8.50
1.50
4.00
TOTAL
2.5%

Add for scaffolding @


Total cost of Materials
B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Crew for Water tanker


Crew for Pump
work inspector
Mason Class-I
Mason Class-II
mazdoor
for conveying rubble stones
for preparing mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Unit

Quantity
1.00
1.00
0.50
0.50

Quantity

Hour
Hour
Day
Day
Day

1.00
0.50
1.00
1.00
2.00

Day
Day
Day
Day
Day
Day

4.00
2.00
1.00
3.00
1.00
4.00
TOTAL
2.5%

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
658.30
Add contractor's profit and overhead charges
13.615% 89.60
labour component/unit qty (including contractor's profit)
747.90

10.00 cum
Rate
in Rs.
6.30
330.00
360.00
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
9009.00
2805.00
540.00
3040.00
15394.00
384.85
15778.85

Rate
in Rs.
402.50
307.20
10.20
81.30
Rs:

Amount
in Rs.
402.50
307.20
5.10
40.65
755.45

Rate
in Rs.
165.80
103.60
400.00
415.00
370.00

Amount
in Rs.
165.80
51.80
400.00
415.00
740.00

310.00
310.00
310.00
310.00
310.00
310.00
Rs:
Rs:
Rs:

1240.00
620.00
310.00
930.00
310.00
1240.00
6422.60
160.57
6583.17

Rs:
Rs:
Rs:
Rs:

15778.85
755.45
6583.17
23117.47
3147.44
26264.91
2626.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-4-3 Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
initial lead upto 50 m and initial lift upto 3m.

264

Canal Cross Drainage Works - Item Unit Rates 2015-16

(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,
Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
25 x 25x 45 cm : 60 Nos)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

UNIT :

Particulars

Unit

Cement
Header stones 25x25x45 cm
Khandki stones 25x25x30 cm
Rubble stones
Stone chips
Sand (Screened)

kg
Nos
Nos
cum
cum
cum

Quantity
1330.00
60.00
180.00
4.50
1.50
3.50
TOTAL
2.5%

Add for scaffolding materials @


Total cost of Materials
B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6
7

Description

Unit

Crew for Water tanker


Crew for Pump
work inspector
Stone chiseller Cl -II
Mason Class-I
Mason Class-II
mazdoor
for conveying stones / rubble
for preparation of mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Quantity
1.00
1.00
0.50
0.50

Quantity

Hour
Hour
Day
Day
Day
Day

1.00
0.50
1.00
3.00
1.00
2.00

Day
Day
Day
Day
Day
Day

4.00
3.00
1.00
3.00
1.00
2.00
TOTAL
2.5%

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
740.30
Add contractor's profit and overhead charges
13.615% 100.80
labour component/unit qty (including contractor's profit)
841.10

10.00 cum
Rate
in Rs.
6.30
39.00
16.00
330.00
360.00
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
8379.00
2340.00
2880.00
1485.00
540.00
2660.00
18284.00
457.10
18741.10

Rate
in Rs.
402.50
307.20
10.20
81.30
Rs:

Amount
in Rs.
402.50
307.20
5.10
40.65
755.45

Rate
in Rs.
165.80
103.60
400.00
370.00
415.00
370.00

Amount
in Rs.
165.80
51.80
400.00
1110.00
415.00
740.00

310.00
310.00
310.00
310.00
310.00
310.00
Rs:
Rs:
Rs:

1240.00
930.00
310.00
930.00
310.00
620.00
7222.60
180.57
7403.17

Rs:
Rs:
Rs:
Rs:

18741.10
755.45
7403.17
26899.72
3662.4
30562.12
3056.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,
Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
25 x 25x 45 cm : 60 Nos)
DATA:

RATE ANALYSIS

UNIT :

10.00 cum

A. MATERIALS:

265

Canal Cross Drainage Works - Item Unit Rates 2015-16

Sl No
1
2
3
4
5
6

Particulars

Unit

Cement
Header stones 25x25x45 cm
Khandki stones 25x25x30 cm
Rubble stones
Stone chips
Sand (Screened)

kg
Nos
Nos
cum
cum
cum

Quantity
1330.00
60.00
180.00
4.50
1.50
3.50
TOTAL
2.5%

Add for scaffolding materials @


Total cost of Materials
B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Unit

Crew for Water tanker


Crew for Pump
work inspector
Stone chiseller Cl -II
Mason Class-I
Mason Class-II
mazdoor
for conveying rubble/ stones
for preparation of mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Quantity
1.00
1.00
0.50
0.50

Quantity

Hour
Hour
Day
Day
Day
Day

1.00
0.50
1.00
6.00
1.00
2.00

Day
Day
Day
Day
Day
Day

4.00
3.00
1.00
3.00
1.00
2.00
TOTAL
2.5%

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
854.10
Add contractor's profit and overhead charges
13.615% 116.30
labour component/unit qty (including contractor's profit)
970.40

Rate
in Rs.
6.30
39.00
16.00
330.00
360.00
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
8379.00
2340.00
2880.00
1485.00
540.00
2660.00
18284.00
457.10
18741.10

Rate
in Rs.
402.50
307.20
10.20
81.30
Rs:

Amount
in Rs.
402.50
307.20
5.10
40.65
755.45

Rate
in Rs.
165.80
103.60
400.00
370.00
415.00
370.00

Amount
in Rs.
165.80
51.80
400.00
2220.00
415.00
740.00

310.00
310.00
310.00
310.00
310.00
310.00
Rs:
Rs:
Rs:

1240.00
930.00
310.00
930.00
310.00
620.00
8332.60
208.32
8540.92

Rs:
Rs:
Rs:
Rs:

18741.10
755.45
8540.92
28037.47
3817.3
31854.77
3185.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-4-5 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cement
Sand (Screened)
Add for scaffolding / ramps etc @
Total cost of Materials

UNIT :
Unit
kg
cum

Quantity
456.00
0.75
TOTAL
2.5%

100.00 sqm
Rate
in Rs.
6.30
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
2872.80
570.00
3442.80
86.07
3528.87

266

Canal Cross Drainage Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

10.00
1.00
10.00

Total cost of Labour


labour component/unit qty
76.50
Add contractor's profit and overhead charges
13.615% 10.40
labour component/unit qty (including contractor's profit)
86.90

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
415.00
400.00
310.00
Rs:

Amount
in Rs.
4150.00
400.00
3100.00
7650.00

Rs:
Rs:
Rs:
Rs:

3528.87
0.00
7650.00
11178.87
1522
12700.87
127.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
13.615% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-4-6 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cement
Sand (Screened)

UNIT :
Unit

Quantity

kg
cum

322.00
0.75
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

Mason Cl- I
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
76.50
Add contractor's profit and overhead charges
13.615% 10.40
labour component/unit qty (including contractor's profit)
86.90

10.00
1.00
10.00

100.00 sqm
Rate
in Rs.
6.30
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
2028.60
570.00
2598.60
64.97
2663.57

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
415.00
400.00
310.00
Rs:

Amount
in Rs.
4150.00
400.00
3100.00
7650.00

Rs:
Rs:
Rs:
Rs:

2663.57
0.00
7650.00
10313.57
1404.19
11717.76
117.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
13.615% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

267

Canal Cross Drainage Works - Item Unit Rates 2015-16

IRR-CCDW-4-7 Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

UNIT :
Unit

Cement
Sand (Screened)

Quantity

kg
cum

629.00
1.32
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

10.00
1.00
20.00

Total cost of Labour


labour component/unit qty
107.50
Add contractor's profit and overhead charges
13.615% 14.60
labour component/unit qty (including contractor's profit)
122.10

100.00 sqm
Rate
in Rs.
6.30
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
3962.70
1003.20
4965.90
124.15
5090.05

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
415.00
400.00
310.00
Rs:

Amount
in Rs.
4150.00
400.00
6200.00
10750.00

Rs:
Rs:
Rs:
Rs:

5090.05
0.00
10750.00
15840.05
2156.62
17996.67
180.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
13.615% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-4-8 Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cement
Sand (Screened)

UNIT :
Unit
kg
cum

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

Description

Unit

Nil
( Manual mixing)
Total hire charges of Machinery

Description

Quantity
472.00
1.32
TOTAL
2.5%

Quantity
0.00
0.00

Unit

Quantity

100.00 sqm
Rate
in Rs.
6.30
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
2973.60
1003.20
3976.80
99.42
4076.22

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

268

Canal Cross Drainage Works - Item Unit Rates 2015-16

1
2
3

Mason Cl- I
work inspector
mazdoor

Day
Day
Day

10.00
1.00
20.00

Total cost of Labour


labour component/unit qty
107.50
Add contractor's profit and overhead charges
13.615% 14.60
labour component/unit qty (including contractor's profit)
122.10

415.00
400.00
310.00
Rs:

4150.00
400.00
6200.00
10750.00

Rs:
Rs:
Rs:
Rs:

4076.22
0.00
10750.00
14826.22
2018.59
16844.81
168.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
13.615% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-4-9 Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

UNIT :
Unit

Cement
Sand (Screened)

Quantity

kg
cum

1050.00
2.20
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

15.00
1.00
25.00

Total cost of Labour


labour component/unit qty
143.80
Add contractor's profit and overhead charges
13.615% 19.60
labour component/unit qty (including contractor's profit)
163.40

100.00 sqm
Rate
in Rs.
6.30
760.00
Rs:
Rs:
Rs:

Amount
in Rs.
6615.00
1672.00
8287.00
207.18
8494.18

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
415.00
400.00
310.00
Rs:

Amount
in Rs.
6225.00
400.00
7750.00
14375.00

Rs:
Rs:
Rs:
Rs:

8494.18
0.00
14375.00
22869.18
3113.64
25982.82
259.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
13.615% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-4-10 Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate
in Rs.

Amount
in Rs.

269

Canal Cross Drainage Works - Item Unit Rates 2015-16

1
2

Cement
Sand (Screened)

kg
cum

788.00
2.20
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

15.00
1.00
25.00

Total cost of Labour


labour component/unit qty
143.80
Add contractor's profit and overhead charges
13.615% 19.60
labour component/unit qty (including contractor's profit)
163.40

6.30
760.00
Rs:
Rs:
Rs:

4964.40
1672.00
6636.40
165.91
6802.31

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
415.00
400.00
310.00
Rs:

Amount
in Rs.
6225.00
400.00
7750.00
14375.00

Rs:
Rs:
Rs:
Rs:

6802.31
0.00
14375.00
21177.31
2883.29
24060.6
240.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
IRR-CCDW-5

Total
13.615% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

COPING & RAILING WORKS :

IRR-CCDW-5-1 Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm,
Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Unit

Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials

kg
cum
sqm

B. MACHINERY:
Sl No
1

Description

Unit

Quantity
75.00
0.30
10.50

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Mason Cl- II
Stone chiseller Cl- II
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
156.00
Add contractor's profit and overhead charges
13.615% 21.20
labour component/unit qty (including contractor's profit)
177.20

1.00
1.00
0.50
2.00

10.00 sqm
Rate
in Rs.
6.30
760.00
310.00
Rs:

Amount
in Rs.
472.50
228.00
3255.00
3955.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
370.00
400.00
310.00
Rs:

Amount
in Rs.
370.00
370.00
200.00
620.00
1560.00

270

Canal Cross Drainage Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Rs:
Rs:
Rs:
Rs:

Total
13.615% Rs:
10.00 sqm
Rs:
(A+B+C+D)/10.0
Rs.

3955.50
0.00
1560.00
5515.50
750.94
6266.44
626.60

IRR-CCDW-5-2 Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Unit

Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials

kg
cum
sqm

B. MACHINERY:
Sl No
1

Description

Unit

Quantity
75.00
0.30
10.50

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

0.00
0.00

Unit

Mason Cl- II
Stone chiseller Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day
Day

1.00
4.00
0.50
2.00

Total cost of Labour


labour component/unit qty
285.00
Add contractor's profit and overhead charges
13.615% 38.80
labour component/unit qty (including contractor's profit)
323.80

10.00 sqm
Rate
in Rs.
6.30
760.00
310.00
Rs:

Amount
in Rs.
472.50
228.00
3255.00
3955.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
415.00
400.00
310.00
Rs:

Amount
in Rs.
370.00
1660.00
200.00
620.00
2850.00

Rs:
Rs:
Rs:
Rs:

3955.50
0.00
2850.00
6805.50
926.57
7732.07
773.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
13.615% Rs:
10.00 sqm
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-5-3 Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

UNIT :

Particulars

Unit

Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials

kg
cum
sqm

Quantity
75.00
0.30
10.50

10.00 sqm
Rate
in Rs.
6.30
760.00
310.00
Rs:

Amount
in Rs.
472.50
228.00
3255.00
3955.50

271

Canal Cross Drainage Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

Unit

Description

0.00
0.00

Unit

Mason Cl- II
Stone chiseller Cl-I
work inspector
mazdoor

Quantity

Day
Day
Day
Day

1.00
8.00
0.50
2.00

Total cost of Labour


labour component/unit qty
451.00
Add contractor's profit and overhead charges
13.615% 61.40
labour component/unit qty (including contractor's profit)
512.40

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
415.00
400.00
310.00
Rs:

Amount
in Rs.
370.00
3320.00
200.00
620.00
4510.00

Rs:
Rs:
Rs:
Rs:

3955.50
0.00
4510.00
8465.50
1152.58
9618.08
961.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
13.615% Rs:
10.00 sqm
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-5-4 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /
sqmm ) grade cement concrete using 20 mm down size approved clean, hard, graded
aggregates for coping slab including cost of all materials, machinery, labour, formwork,
cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing
etc., complete with initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
sqm

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3

UNIT :

Description

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker

Unit
Hour
Hour
Hour

Quantity
4401.00
73.35
7.63
4.11
6.60
17.60
80.69
1.00

Quantity
8.00
8.00
0.50
0.50
1.00
1.00

Quantity
8.00
0.50
1.00

14.67 cum
Rate
in Rs.
6.30
6.30
1210.00
875.00
560.00
95.00
225.53
20.00
Rs:

Amount
in Rs.
27726.30
462.11
9230.36
3594.15
3696.84
1672.38
18196.81
20.00
64598.95

Rate
in Rs.
53.50
81.30
10.20
81.30
402.50
307.20
Rs:

Amount
in Rs.
428.00
650.40
5.10
40.65
402.50
307.20
1833.85

Rate
in Rs.
204.10
103.60
165.80

Amount
in Rs.
1632.80
51.80
165.80

272

Canal Cross Drainage Works - Item Unit Rates 2015-16

4
5
6

Mason Class-I
Day
1.00
work inspector
Day
1.00
mazdoor
for batching materials
Day
11.00
for loading mortar pans
Day
4.00
for laying and tamping
Day
3.00
for conveying concrete
Day
14.67
for cleaning/ washing/ curing
Day
1.00
7
Labour cost for shuttering/scaffolding
sqm
80.69
Total cost of Labour
labour component/unit qty
1332.10
Add contractor's profit and overhead charges
13.615% 181.40
labour component/unit qty (including contractor's profit)
1513.50

415.00
400.00

415.00
400.00

310.00
310.00
310.00
310.00
310.00
79.80
Rs:

3410.00
1240.00
930.00
4547.70
310.00
6438.66
19541.76

Rs:
Rs:
Rs:
Rs:

64598.95
1833.85
19541.76
85974.56
11705.44
97680.00
6658.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
14.67 cum
Rs:
(A+B+C+D)/14.67
Rs.

IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x
15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 grade
concrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.
of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mm
dia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primer
and two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

UNIT :

Particulars

Unit

Cement
20-10 mm coarse aggregate
10-4.75 mm coarse aggregate
Fine aggregate (Un-Screened)
Reinforcement steel
40 mm dia GI pipes B class
Use rate of shuttering
Sundries ( paints/ binding wire etc )
Total cost of Materials

kg
cum
cum
cum
kg
Rm
sqm
LS

B. MACHINERY:
Sl No
1

Description

Unit

Quantity
30.00
0.04
0.02
0.04
16.39
30.00
3.00
4.00

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3
4
5
6

Mason Class I
Bar bender
work inspector
mazdoor
Painter Cl- II
Fitter shuttering

Description

Unit

Quantity

Day
Day
Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
148.80
Add contractor's profit and overhead charges
13.615% 20.30
labour component/unit qty (including contractor's profit)
169.10
ABSTRACT:
A. Cost of Materials

0.50
0.50
0.50
1.50
0.50
0.50

10.00 Rm
Rate
in Rs.
6.30
1210.00
875.00
560.00
40.00
290.00
225.53
20.00
Rs:

Amount
in Rs.
189.00
48.40
17.50
22.40
655.60
8700.00
676.59
80.00
10389.49

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
415.00
490.00
400.00
310.00
370.00
370.00
Rs:

Amount
in Rs.
207.50
245.00
200.00
465.00
185.00
185.00
1487.50

Rs:

10389.49

273

Canal Cross Drainage Works - Item Unit Rates 2015-16

B. Hire charges of Machinery


C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per Rm
IRR-CCDW-6

Rs:
Rs:
Rs:

Total
13.615% Rs:
10.00 Rm
Rs:
(A+B+C+D)/10.0
Rs.

0.00
1487.50
11876.99
1617.05
13494.04
1349.40

HUME PIPE LAYING & JOINTING WORKS :

IRR-CCDW-6-1 Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

UNIT :
Unit

Cement
Sand (Screened)
Hemp yarn

Quantity

kg
cum
kg

99.00
0.10
0.91

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

2.00
1.00
3.00

Total cost of Labour


labour component/unit qty
207.00
Add contractor's profit and overhead charges
13.615% 28.20
labour component/unit qty (including contractor's profit)
235.20

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00
Rs:

Amount
in Rs.
623.70
76.00
65.52
765.22

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
740.00
400.00
930.00
2070.00

Rs:
Rs:
Rs:
Rs:

765.22
0.00
2070.00
2835.22
386.02
3221.24
322.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-2 Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Cement
Sand (Screened)

Particulars

UNIT :
Unit
kg
cum

Quantity
174.00
0.22

10.00 Joints
Rate
in Rs.
6.30
760.00

Amount
in Rs.
1096.20
167.20

274

Canal Cross Drainage Works - Item Unit Rates 2015-16

Hemp yarn

kg

1.27

72.00
Rs:

91.44
1354.84

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
740.00
400.00
930.00
2070.00

Rs:
Rs:
Rs:
Rs:

1354.84
0.00
2070.00
3424.84
466.29
3891.13
389.10

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

2.00
1.00
3.00

Total cost of Labour


labour component/unit qty
207.00
Add contractor's profit and overhead charges
13.615% 28.20
labour component/unit qty (including contractor's profit)
235.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-3 Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit

Quantity

kg
cum
kg

248.00
0.25
2.20

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Mason Cl- II
work inspector
mazdoor

Description

0.00
0.00

Unit

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
256.50
Add contractor's profit and overhead charges
13.615% 34.90
labour component/unit qty (including contractor's profit)
291.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

2.50
1.00
4.00

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00
Rs:

Amount
in Rs.
1562.40
190.00
158.40
1910.80

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
925.00
400.00
1240.00
2565.00

Rs:
Rs:

1910.80
0.00

275

Canal Cross Drainage Works - Item Unit Rates 2015-16

C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Rs:
Rs:

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

2565.00
4475.80
609.38
5085.18
508.50

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-4 Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

UNIT :
Unit

Cement
Sand (Screened)
Hemp yarn

Quantity

kg
cum
kg

321.00
0.31
2.50

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

2.50
1.00
4.00

Total cost of Labour


labour component/unit qty
256.50
Add contractor's profit and overhead charges
13.615% 34.90
labour component/unit qty (including contractor's profit)
291.40

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00
Rs:

Amount
in Rs.
2022.30
235.60
180.00
2437.90

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
925.00
400.00
1240.00
2565.00

Rs:
Rs:
Rs:
Rs:

2437.90
0.00
2565.00
5002.90
681.14
5684.04
568.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-5 Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Cement
Sand (Screened)
Hemp yarn

Particulars

UNIT :
Unit
kg
cum
kg

Quantity
396.00
0.39
3.10

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00

Amount
in Rs.
2494.80
296.40
223.20

276

Canal Cross Drainage Works - Item Unit Rates 2015-16

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

3.00
1.00
5.00

Total cost of Labour


labour component/unit qty
306.00
Add contractor's profit and overhead charges
13.615% 41.70
labour component/unit qty (including contractor's profit)
347.70

Rs:

3014.40

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
1110.00
400.00
1550.00
3060.00

Rs:
Rs:
Rs:
Rs:

3014.40
0.00
3060.00
6074.40
827.03
6901.43
690.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-6 Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit

Quantity

kg
cum
kg

446.00
0.45
3.40

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Mason Cl- II
work inspector
mazdoor

Description

0.00
0.00

Unit

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
306.00
Add contractor's profit and overhead charges
13.615% 41.70
labour component/unit qty (including contractor's profit)
347.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

3.00
1.00
5.00

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00
Rs:

Amount
in Rs.
2809.80
342.00
244.80
3396.60

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
1110.00
400.00
1550.00
3060.00

Rs:
Rs:
Rs:

3396.60
0.00
3060.00

277

Canal Cross Drainage Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per joint

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

Rs:

6456.60
879.07
7335.67
733.60

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-7 Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

UNIT :
Unit

Cement
Sand (Screened)
Hemp yarn

Quantity

kg
cum
kg

495.00
0.50
3.77

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

3.00
1.00
6.00

Total cost of Labour


labour component/unit qty
337.00
Add contractor's profit and overhead charges
13.615% 45.90
labour component/unit qty (including contractor's profit)
382.90

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00
Rs:

Amount
in Rs.
3118.50
380.00
271.44
3769.94

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
1110.00
400.00
1860.00
3370.00

Rs:
Rs:
Rs:
Rs:

3769.94
0.00
3370.00
7139.94
972.1
8112.04
811.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-8 Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit
kg
cum
kg

Total cost of Materials

Quantity
569.00
0.58
4.15

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00
Rs:

Amount
in Rs.
3584.70
440.80
298.80
4324.30

278

Canal Cross Drainage Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

3.00
1.00
6.00

Total cost of Labour


labour component/unit qty
337.00
Add contractor's profit and overhead charges
13.615% 45.90
labour component/unit qty (including contractor's profit)
382.90

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
1110.00
400.00
1860.00
3370.00

Rs:
Rs:
Rs:
Rs:

4324.30
0.00
3370.00
7694.30
1047.58
8741.88
874.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
13.615% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-9 Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit

Quantity

kg
cum
kg

668.00
0.69
4.53

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Mason Cl- II
work inspector
mazdoor

Description

0.00
0.00

Unit

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
405.00
Add contractor's profit and overhead charges
13.615% 55.10
labour component/unit qty (including contractor's profit)
460.10

4.00
1.00
7.00

10.00 Joints
Rate
in Rs.
6.30
760.00
72.00
Rs:

Amount
in Rs.
4208.40
524.40
326.16
5058.96

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
Rs:

Amount
in Rs.
1480.00
400.00
2170.00
4050.00

Rs:
Rs:
Rs:
Rs:

5058.96
0.00
4050.00
9108.96

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

279

Canal Cross Drainage Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per joint

10.00 Joints
(A+B+C+D)/10.0

13.615% Rs:
Rs:
Rs.

1240.18
10349.14
1034.90

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-7

BACK FILLING & OTHER WORKS :

IRR-CCDW-7-1 Providing rubble / boulder and sand filling behind abutment and return walls in layers
including cost of all materials, machinery, labour, watering, ramming etc., complete with initial
lead upto 50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

UNIT :
Unit

Rubble / Boulder
Sand for filling

Quantity

cum
cum

10.00
4.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

work inspector
Mason Cl II
mazdoor

Quantity

Day
Day
Day

0.50
1.00
4.00

Total cost of Labour


labour component/unit qty
181.00
Add contractor's profit and overhead charges
13.615% 24.60
labour component/unit qty (including contractor's profit)
205.60

10.00 cum
Rate
in Rs.
330.00
560.00
Rs:

Amount
in Rs.
3300.00
2240.00
5540.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
200.00
370.00
1240.00
1810.00

Rs:
Rs:
Rs:
Rs:

5540.00
0.00
1810.00
7350.00
1000.7
8350.7
835.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-7-2 Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
masters to achieve density control of not less than 95 percent etc., complete with lead
upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Murum

UNIT :
Unit
cum

Quantity
12.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description
Nill
Total hire charges of Machinery

Unit

Quantity
0.00
0.00

10.00 cum
Rate
in Rs.
115.00
0.00
Rs:

Amount
in Rs.
1380.00
0.00
1380.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

280

Canal Cross Drainage Works - Item Unit Rates 2015-16

C. LABOUR:
Sl No

Description

Unit

Quantity

1
2
3

Cartman with double bullock cart


Day
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
227.30
Add contractor's profit and overhead charges
13.615% 30.90
labour component/unit qty (including contractor's profit)
258.20

0.50
0.50
6.00

Rate
in Rs.
425.00
400.00
310.00
Rs:

Amount
in Rs.
212.50
200.00
1860.00
2272.50

Rs:
Rs:
Rs:
Rs:

1380.00
0.00
2272.50
3652.50
497.29
4149.79
415.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-7-3 Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power
roller to achieve density control of not less than 98 percent etc., complete with lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Murum

UNIT :
Unit

Quantity

cum

12.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Diesel road roller 8-10 tonne


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4

Unit

Quantity
0.17
0.17

Quantity

Operator road roller


Hour
Cartman with double bullock cart
Day
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
91.10
Add contractor's profit and overhead charges
13.615% 12.40
labour component/unit qty (including contractor's profit)
103.50

0.17
0.50
0.50
1.50

10.00 cum
Rate
in Rs.
115.00
0.00
Rs:

Amount
in Rs.
1380.00
0.00
1380.00

Rate
in Rs.
197.20
731.40
Rs:

Amount
in Rs.
33.65
124.81
158.46

Rate
in Rs.
195.90
425.00
400.00
310.00
Rs:

Amount
in Rs.
33.43
212.50
200.00
465.00
910.93

Rs:
Rs:
Rs:
Rs:

1380.00
158.46
910.93
2449.39
333.49
2782.88
278.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
13.615% Rs:
10.00 cum
Rs:
(A+B+C+D)/10.0
Rs.

IRR-CCDW-7-4 Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

281

Canal Cross Drainage Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

One line dressed Km stone


40-20 mm coarse aggregate
20-10 mm coarse aggregate
10-4.75 mm coarse aggregate
Sand (Un-Screened)
Cement
Synthetic enamel paint I st quality
Sundries ( brush / oil etc )
Total cost of Materials

No.
cum
cum
cum
cum
kg
ltr
LS

B. MACHINERY:
Sl No
1

Description

Unit

Quantity
4.00
0.20
0.15
0.10
0.20
100.00
1.00
4.00

Quantity

NIL
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor
Painter Cl- I

Quantity

Day
Day
Day
Day

1.00
1.00
1.00
1.00

Total cost of Labour


labour component/unit qty
390.00
Add contractor's profit and overhead charges
13.615% 53.10
labour component/unit qty (including contractor's profit)
443.10

4 Nos.
Rate
in Rs.
470.00
1145.00
1210.00
875.00
560.00
6.30
240.00
20.00
Rs:

Amount
in Rs.
1880.00
229.00
181.50
87.50
112.00
630.00
240.00
80.00
3440.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
400.00
310.00
480.00
Rs:

Amount
in Rs.
370.00
400.00
310.00
480.00
1560.00

Rs:
Rs:
Rs:
Rs:

3440.00
0.00
1560.00
5000.00
680.75
5680.75
1420.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per No.

Total
13.615% Rs:
4.00 Nos.
Rs:
(A+B+C+D)/4.0
Rs.

IRR-CCDW-7-5 Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

1
2
3
4
5
6
7
8

One line dressed hectometre stone


40-20 mm coarse aggregate
20-10 mm coarse aggregate
10-4.75 mm coarse aggregate
Sand (Un-Screened)
Cement
Synthetic enamel paint I st quality
Sundries ( brush / oil etc )
Total cost of Materials
B. MACHINERY:
Sl No
Description
1

NIL
( Manual mixing )
Total hire charges of Machinery

UNIT :
Unit
No.
cum
cum
cum
cum
kg
ltr
LS

Unit

Quantity
4.00
0.20
0.15
0.10
0.20
100.00
0.40
1.00

Quantity
0.00
0.00

4 Nos.
Rate
in Rs.
260.00
1145.00
1210.00
875.00
560.00
6.30
240.00
20.00
Rs:

Amount
in Rs.
1040.00
229.00
181.50
87.50
112.00
630.00
96.00
20.00
2396.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

C. LABOUR:

282

Canal Cross Drainage Works - Item Unit Rates 2015-16

Sl No
1
2
3
4

Description
Mason Cl- II
work inspector
mazdoor
Painter Cl- I

Unit

Quantity

Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
330.00
Add contractor's profit and overhead charges
13.615% 44.90
labour component/unit qty (including contractor's profit)
374.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per No.

1.00
1.00
1.00
0.50

Rate
in Rs.
370.00
400.00
310.00
480.00
Rs:

Amount
in Rs.
370.00
400.00
310.00
240.00
1320.00

Rs:
Rs:
Rs:
Rs:

2396.00
0.00
1320.00
3716.00
505.93
4221.93
1055.50

Total
13.615% Rs:
4.00 Nos.
Rs:
(A+B+C+D)/4.0
Rs.

283

Gates and Allied Works - Item Unit Rates 2015-16

CHAPTER-V
HYDRAULIC GATES AND ALLIED EQUIPMENT - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :
IRR-GAW

2015-16

GATE HOIST AND ALLIED WORKS - DATA RATES

All materials / bought out components for embedded parts, gates, hoists and allied works
shall conform to relevant Indian standards / technical specifications and approved drawings.

The basic rates are EXCLUSIVEof preparation of designs / drawings / material schedules etc.,
as per specifications and other technical data including revisions.
If designs &drawings are to be done by private agency 2% of estimated cost be added

The basic rates are inclusive of cost of all materials, machinery, labour, fabrication, erection,
commissioning and testing of gates, hoists and other related components as per technical
specifications.

The basic rates are inclusive of finishing, wastage of materials , incidental works, temperary
supports, all enabling works, profit, overheads, small tools / plants, hidden cost
on labour etc.

The basic rates are inclusive of taxes, duties (excise ), levies and all other incidental charges including
turn over tax/sales tax on works contract. Separate provision shall be made in the estimate towards such
tax on works contract at the rate prevailing at the time of preparation of estimate.

The basic rates are inclusive of all leads and lifts including rehandling.

no provision is made for stitch welding and it is part of welding work

The basic rates are inclusive of preparatory works such as rectification of damages, repairing
shop painting, cleaning, positioning and anchoring first stage embedments,

The basic rates are not inclusive of painting with or without sand blasting,and are to be added to the rate as
perschedule rates formulated in the same chapter as per applicability and specifications

10

The basic rates are exclusive of cost of river diversion arrangements, dewatering, desilting ,secondary concreting
of EM parts etc., which form part of civil works.

11

DESIGNS AND DRAWING CHARGES AT 2% BE ADDED EXTRA TO THE ESTIMATES, IF CONTRACTOR'S


SCOPE OF WORK INVOLVES DESIGNS COMPONENT ALSO

12

Add AREA ALLOWANCES AS APPLICABLE ON LABOUR COMPONENT ONLY ( SHOWN UNDER EACH ITEM)

13

Add contractors profit and overheads at 14% to all items

14

Painting Charges added extra to the data items as per applicability wherver necessary

15

HOIST EQUIPMENT1.-where sand blasting is not possible, hand and power tool cleaning be
adopted - Guidance may be taken from Mechanical workshop in this regard
2. Machined surfaces should not be painted
3. for maintenance unless sand blasting is essential hand and power tool cleaning be adopted
Painting of Hoast Gates is to be done as per IS 14177:1994

16

DATA and RATES

---GATE / HOIST AND ALLIED WORKS -

(STORED WITH E-N-C &TO INCORPORATE CHANGES YEARLY/AS NEEDED)


GAW - Work Items
Index- code
IRR-GAW

TYPES OF GATES:

IRR-GAW-1
A. SPILLWAY RADIAL GATES
IRR-GAW-1-1 E.M Parts and anchorages
fabrication, supply, erection, testing and commissioning of Embedded parts for radial gate
consists of sill beam, wall plates, anchor girders , yoke girders, tie flats, trunnion supports etc., including
cost of all materials, machinery, labour, welding, finishing, with leads and lifts &all accessories
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra

285

Gates and Allied Works - Item Unit Rates 2015-16

as perscedule of rates under itemsinthis chapter and add as applicable separately)


Drawing no. MD/CDO/VRSP/90-92/85-86 (Vengalaraya Sagar - Gomukhi Project)
Vent Size:

DATA:

RATE ANALYSIS
Sl No
1
2
3
4
5
6
7
8
9
10
11
12

A. MATERIALS:
particulars
Str steel angle / beam / channel / bars
Structural steel plate / flats
Stainless steel plate / flats
MS bolts and nuts
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Welding electrodes ( stainless steel )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1

2
3
4
5
6
7
8
9
10
11

Welding transformer
Fuel / Energy charges
Tower crane/heavy duty tyre
mounted crane
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 16 Tonnes
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Planing machine
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Description

Description

Crew for Tower crane


Crew for Mobile crane 16 T
Crew for Shearing machine
Crew for Planing machine
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )
Khalasi
Helper fabrication / erection
Electrician

Unit

UNIT :
Quantity

kg
3467.00
kg
11261.00
kg
515.00
kg
48.00
cum
158.00
cum
53.00
Nos
11520.00
Nos
2880.00
Nos
1160.00
Hour
1945.00
Hour
158.00
LS
100.00
Total cost of Materials

Unit

Quantity

Hour
Hour

1945.00
1945.00

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

16.00
16.00
16.00
16.00
76.00
76.00
22.00
22.00
64.00
64.00
30.00
30.00
30.00
30.00
100.00
100.00
30.00
30.00
100.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour

Quantity

16.00
22.00
16.00
100.00
30.00
30.00
30.00
Day
15.00
Day
75.00
Day
20.00
Day
212.00
Day
48.00
Day
345.00
Day
255.00
Day
5.00
Total cost of Labour

12.00 X 6.6 Mtrs

15.300 tonne
Rate
in Rs.
40.00
40.00
275.00
90.00
45.00
330.00
11.00
18.00
27.00
7.65
2.08
20.00
Rs:

Amount
in Rs.
138680.00
450440.00
141625.00
4320.00
7110.00
17490.00
126720.00
51840.00
31320.00
14879.25
329.17
2000.00
986753.42

Rate
in Rs.
16.00
92.40

Amount
in Rs.
31120.00
179718.00

867.10
200.20
41.90
154.00
6.40
3.80
2278.10
75.00
86.10
0.00
22.50
38.50
22.50
38.50
117.80
115.50
42.60
115.50
20.00
Rs:

13873.60
3203.20
670.40
2464.00
486.40
288.80
50118.20
1650.00
5510.40
0.00
675.00
1155.00
675.00
1155.00
11780.00
11550.00
1278.00
3465.00
2000.00
322836.00

Rate
in Rs.
176.80
489.20
132.60
195.90
187.20
187.20
122.50
480.00
480.00
415.00
415.00
480.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
2828.80
10762.40
2121.60
19590.00
5616.00
5616.00
3675.00
7200.00
36000.00
8300.00
87980.00
23040.00
143175.00
94350.00
2400.00
452654.80

286

Gates and Allied Works - Item Unit Rates 2015-16

Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

135796.44
588451.24

labour component/unit qty


38460.90
Add contractor's profit and overhead charges
13.615% 5236.50
labour component/unit qty (including contractor's profit)
43697.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D.Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

986753.42
322836.00
588451.24
1898040.66
0.00
1898040.66
56941.22
1954981.88

Rs:

266170.78

578.34
2028.78
Rs:
2223759.78
Rs:
145343.80

15.300 tonne
Rate per tonne

RADIAL GATES
A-2
Gates
IRR-GAW-1-2 fabrication, supply, erection, testing and commissioning of radial gate consisting
of skin plate, stiffeners, horizontal girders, radial arms, trunnion assemblies, tie beam, pulley
supports, bracings, rubber seals, clamps etc., with all accessories for spillway/canals including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)
Drawing no. MD/CDO/VRSP/170-172/85-86(Vengalaraya Sagar - Gomukhi Project)
Vent Size: 12 X 6.6 Mtr
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

3
4
5
6

7
8
9
10
11
12
13

Structural steel :
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Trunnion hubs / Guide rollers
Alluminium / Bronze alloy
components :
Bush for Trunnion / Guide roller
Bolt / Nut / Washer :
GI bolts / nuts / washers
Zinc/Babbit Metal
Rubber seals :
Bottom seal
Side seals ( Z - type )
Oxygen gas
Acetyline gas
Welding electrodes ( std )
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1

particulars

Description

Welding transformer
Fuel / Energy charges

UNIT :
Unit

Quantity

29.000 tonne
Rate
in Rs.

Amount
in Rs.

kg
kg

9700.00
16850.00

40.00
40.00

388000.00
674000.00

kg

2100.00

180.00

378000.00

kg

350.00

920.00

322000.00

kg
kg

250.00
50.00

120.00
180.00

30000.00
9000.00

Rm
12.00
Rm
14.00
cum
228.00
cum
76.00
Nos
1000.00
Nos
250.00
Hour
156.00
Hour
228.00
LS
500.00
Total cost of Materials

780.00
1600.00
45.00
330.00
11.00
18.00
7.65
2.08
20.00
Rs:

9360.00
22400.00
10260.00
25080.00
11000.00
4500.00
1193.40
475.00
10000.00
1895268.40

Rate
in Rs.
16.00
92.40

Amount
in Rs.
2496.00
14414.40

Unit
Hour
Hour

Quantity
156.00
156.00

287

Gates and Allied Works - Item Unit Rates 2015-16

2
3
4
5
6
7
8
9
10
11

Plate shearing machine


Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Bending machine
Fuel / Energy charges
Tower crane 5 t cpacity
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Mobile Crane 30 T
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13

Description

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

29.00
29.00
114.00
114.00
116.00
116.00
29.00
29.00
58.00
58.00
58.00
58.00
58.00
58.00
58.00
58.00
100.00
100.00
500.00

Quantity

Crew for Mobile crane 30T


Crew for Tower crane
Crew for Bending machine
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )
Khalasi
Helper fabrication / erection
Electrician

Hour
100.00
Hour
29.00
Hour
116.00
Hour
58.00
Hour
58.00
Day
29.00
Day
145.00
Day
29.00
Day
17.00
Day
5.00
Day
493.00
Day
667.00
Day
15.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

41.90
154.00
6.40
3.80
42.60
115.50
867.10
200.20
519.70
307.20
86.10
0.00
22.50
38.50
22.50
38.50
3096.80
118.80
20.00
Rs:

1215.10
4466.00
729.60
433.20
4941.60
13398.00
25145.90
5805.80
30142.60
17817.60
4993.80
0.00
1305.00
2233.00
1305.00
2233.00
309680.00
11880.00
10000.00
464635.60

Rate
in Rs.
489.20
176.80
122.50
187.20
187.20
480.00
480.00
415.00
415.00
480.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
48920.00
5127.20
14210.00
10857.60
10857.60
13920.00
69600.00
12035.00
7055.00
2400.00
204595.00
246790.00
7200.00
653567.40
196070.22
849637.62

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1895268.40
464635.60
849637.62
3209541.62
0.00
3209541.62
96286.25
3305827.87

Rs:

450088.46

labour component/unit qty


29297.80
Add contractor's profit and overhead charges
13.615% 3988.90
labour component/unit qty (including contractor's profit)
33286.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

IRR-GAW-1-3 RADIAL GATES-ROPE DRUM HOISTS

13.615%
Rs.

18.90 per tonne


66.30 per tonne

29.000 tonne
Rate per
tonne

1096.2
3845.4
Rs:
3760857.93
Rs.
129684.80

WITH HOIST BRIDGES

fabrication, supply, erection, testing and commissioning of electrically operated rope


drum hoist of adequate capacity consisting of base frames, rope drums,connecting shaft, gear
system, brake system, electric motor, wire ropes, gate position indicator, manual operation
arrangement etc., with all accessories for spillway radial gate including cost of all materials,
machinery, labour,, greasing, providing hand railing and approach staircase with gate to hoist platform,
, complete as per specifications and approved drawings

288

Gates and Allied Works - Item Unit Rates 2015-16

(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21

2
3
4
5
6
7

6
7

Description

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5

Unit

Quantity

Structural steel
Angles / beams / channels / bars
kg
2571.00
Plates / flats
kg
3632.00
Cast steel components :
Rope drums 2 Nos / Gears 4 Nos
kg
3680.00
Pinions
kg
218.00
Pulleys 720 PCD 6 Nos
kg
1080.00
Plummer blocks / Hubs
kg
322.00
Alloy steel components
Shafts
kg
557.00
Pins
kg
546.00
Bronze alloy components :
Bronze bearings / bush
kg
144.00
Wire rope 36 mm dia 6/37
construction
kg
448.00
MS Bolt / Nut / Washer
kg
85.00
Worm reducers
No.
1.00
Electric motor 20 hp
No.
1.00
Floating shaft 300 mm dia
kg
1000.00
Manual operating system
No.
1.00
Gate position indicator
No.
1.00
Ele-magnetic brake
No.
1.00
Electric cable / switch / control panel
etc
LS
1.00
Oxygen gas
cum
213.00
Acetyline gas
cum
71.00
Welding electrodes
Nos
530.00
Welding electrodes ( LH )
Nos
4776.00
Grease
kg
50.00
Use rate welding holder set
Hour
566.00
Use rate gas cutting torch set
Hour
90.00
Sundries ( hand rail /staircase / gate etc ) LS
200.00
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector /
Mechanic
Gas cutter

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
566.00
353.00
4.00
4.00
53.00
53.00
50.00
50.00
8.00
8.00
16.00
16.00
100.00

Quantity

15.440 tonne wt
90.00 t capacity
Rate
Amount
in Rs.
in Rs.
40.00
40.00

102840.00
145280.00

220.00
210.00
180.00
180.00

809600.00
45780.00
194400.00
57960.00

230.00
420.00

128110.00
229320.00

920.00

132480.00

200.00
90.00
224400.00
121000.00
180.00
28820.00
195800.00
35200.00

89600.00
7650.00
224400.00
121000.00
180000.00
28820.00
195800.00
35200.00

50380.00
45.00
330.00
11.00
18.00
260.00
7.65
2.08
20.00
Rs:

50380.00
9585.00
23430.00
5830.00
85968.00
13000.00
4329.90
187.50
4000.00
2924950.40

Rate
in Rs.
16.00
92.40
867.10
200.20
6.40
3.80
519.70
307.20
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
9056.00
32617.20
3468.40
800.80
339.20
201.40
25985.00
15360.00
180.00
308.00
360.00
616.00
2000.00
91292.00

Amount
in Rs.
8290.00
707.20
2995.20
1497.60
16800.00
27840.00
7470.00

Hour
Hour
Hour
Hour
Day

50.00
4.00
16.00
8.00
35.00

Rate
in Rs.
165.80
176.80
187.20
187.20
480.00

Day
Day

58.00
18.00

480.00
415.00

289

Gates and Allied Works - Item Unit Rates 2015-16

8
9
10
11

Welder ( General )
Khalasi
Helper fabrication / erection
Electrician

Day
53.00
Day
20.00
Day
175.00
Day
3.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

415.00
415.00
370.00
480.00
Rs:

21995.00
8300.00
64750.00
1440.00
162085.00
48625.50
210710.50

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

2924950.40
91292.00
210710.50
3226952.90
0.00
3226952.90
96808.59
3323761.49

Rs:

452530.13

labour component/unit qty


2341.20
Add contractor's profit and overhead charges
13.615% 318.80
labour component/unit qty (including contractor's profit)
2660.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for
Total cost for

13.615%
Rs.

18.90 per tonne


583.632
66.30 per tonne
2047.344
15.440 tonne wt
Rs:
3778922.59
90.00 t capacity
Rs:
Rate per tonne wt
Rs:
244748.90
Rate per tonne capacity of hoist
41988.00

IRR-GAW-1-4 Walk way(cat walk)


fabrication, supply, erection and commissioning of 1 metre wide walkway connecting
spillway piers / abutments at trunnion platform level including cost of all materials,
machinery, labour, cutting, welding etc, complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6
7
8

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plates
MS bolts / nuts / washers
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5

particulars

Description

Welding transformer
Fuel / Energy charges
Tower crane
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile CRANE 16T
Fuel / Energy charges
Grinding machine
Fuel / Energy charges

UNIT :
Unit

Quantity

kg
4258.00
kg
98.00
kg
856.00
kg
8.00
cum
51.00
cum
17.00
Nos
1195.00
Hour
150.00
Hour
30.00
LS
10.00
Total cost of Materials

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
150.00
150.00
6.00
6.00
12.00
12.00
8.00
8.00
12.00
12.00

5.22 MT
Rate
in Rs.

Amount
in Rs.

40.00
40.00
63.00
90.00
45.00
330.00
11.00
7.65
2.08
20.00
Rs:

170320.00
3920.00
53928.00
720.00
2295.00
5610.00
13145.00
1147.50
62.50
200.00
251348.00

Rate
in Rs.
16.00
92.40
867.10
200.20
6.40
3.80
2278.10
75.00
22.50
38.50

Amount
in Rs.
2400.00
13860.00
5202.60
1201.20
76.80
45.60
18224.80
600.00
270.00
462.00

290

Gates and Allied Works - Item Unit Rates 2015-16

6
7
8

Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

Description

Hour
Hour
Hour
Hour
LS

Unit

12.00
12.00
10.00
10.00
10.00

Quantity

Crew for Mobile crane 16T


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
10.00
Hour
6.00
Hour
12.00
Hour
12.00
Hour
10.00
Day
6.00
Day
25.00
Day
5.00
Day
20.00
Day
200.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

22.50
38.50
42.60
115.50
20.00
Rs:

270.00
462.00
426.00
1155.00
200.00
44856.00

Rate
in Rs.
489.20
176.80
187.20
187.20
122.50
480.00
480.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
4892.00
1060.80
2246.40
2246.40
1225.00
2880.00
12000.00
2075.00
8300.00
74000.00
960.00
111885.60
33565.68
145451.28

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

251348.00
44856.00
145451.28
441655.28
0.00
441655.28
13249.66
454904.94

Rs:

61935.31

labour component/unit qty


27864.20
Add contractor's profit and overhead charges
13.615% 3793.70
labour component/unit qty (including contractor's profit)
31657.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne

5.22 MT
Rate per MT

197.316
692.172
Rs:
517729.73
Rs:
99181.90

IRR-GAW-2
VERTICAL LIFT GATES-EM PARTS
IRR-GAW-2-1 Design, fabrication, supply, erection and commissioning of embedded parts consisting of
sill beam, slide tracks, seal seats, guide rails, dogging sets for storage of stoplog elements
etc., with all accessories for spillway stop log gates and other vertical lift elements including cost of all materials,
machinery, labour, etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing No. MD/CDO/GNCP/HR/1759,1760/94 (GNSS Project)
Vent Size:
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9

particulars

Str steel angle / beam / channel / bars


Structural steel plate / flats
Stainless steel plate / flats
MS bolts and nuts
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Welding electrodes ( stainless steel )

UNIT :
Unit
kg
kg
kg
kg
cum
cum
Nos
Nos
Nos

Quantity
1885.00
3890.00
271.00
50.00
225.00
75.00
1410.00
350.00
1320.00

3.6 X 6.1 Mtr


6.300 tonne
Rate
in Rs.
40.00
40.00
275.00
90.00
45.00
330.00
11.00
18.00
27.00

Amount
in Rs.
75400.00
155600.00
74525.00
4500.00
10125.00
24750.00
15510.00
6300.00
35640.00

291

Gates and Allied Works - Item Unit Rates 2015-16

10
11
12

Use rate welding holder set


Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
10

Welding transformer
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Planing machine
Fuel / Energy charges
Mobile Crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12

Description

Description

Hour
385.00
Hour
225.00
LS
40.00
Total cost of Materials

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

385.00
385.00
8.00
8.00
110.00
110.00
270.00
270.00
24.00
24.00
14.00
14.00
14.00
14.00
21.00
21.00
14.00
14.00
40.00

Quantity

Crew for Mobile crane 16 T


Crew for Planing machine
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )
Helper fabrication / erection
Electrician

Hour
24.00
Hour
270.00
Hour
21.00
Hour
14.00
Hour
14.00
Day
32.00
Day
35.00
Day
9.00
Day
46.00
Day
6.00
Day
240.00
Day
4.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

7.65
2.08
20.00
Rs:

2945.25
468.75
800.00
406564.00

Rate
in Rs.
16.00
92.40
41.90
154.00
6.40
3.80
117.80
115.50
2278.10
75.00
86.10
0.00
22.50
38.50
22.50
38.50
42.60
115.50
20.00
Rs:

Amount
in Rs.
6160.00
35574.00
335.20
1232.00
704.00
418.00
31806.00
31185.00
54674.40
1800.00
1205.40
0.00
315.00
539.00
472.50
808.50
596.40
1617.00
800.00
170242.40

Rate
in Rs.
489.20
195.90
187.20
187.20
122.50
480.00
480.00
415.00
415.00
480.00
370.00
480.00
Rs:

Amount
in Rs.
11740.80
52893.00
3931.20
2620.80
1715.00
15360.00
16800.00
3735.00
19090.00
2880.00
88800.00
1920.00
221485.80
66445.74
287931.54

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

406564.00
170242.40
287931.54
864737.94
0.00
864737.94
25942.14
890680.08

Rs:

121266.09

labour component/unit qty


45703.40
Add contractor's profit and overhead charges
13.615% 6222.50
labour component/unit qty (including contractor's profit)
51925.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.
6.30 tonne
Rate per tonne

18.90 per tonne


66.30 per tonne

238.14
835.38
Rs:
1013019.69
Rs:
160796.80

vertical lift gates and stop log gate elements ( SLIDING GATES)

292

Gates and Allied Works - Item Unit Rates 2015-16

IRR-GAW-2-2 Design, fabrication, supply, erection, testing and commissioning of vertical lift gates and
stoplog gate elements, consisting of skin plate,
horizontal and vertical girders, stiffeners, lifting pins, bronze padded slide blocks/bearings, guide shoes,
rubber seals, clamps etc., with all accessories including cost of all materials,
machinery, labour, seal fixing etc.,complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing NO. CE/CDO/CL3/MRP/783/2002 (Spillway Stop log gate Elements of Madduvalasa Project)
Vent Size: 12.624 X 0.50 M 16 Elements

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Structural steel
Angles / beams / channels / bars
Plates / flats
Alloy steel components
Lifting pins
Bolt / Nut / Washer
GI bolts / nuts / washers
Rubber seals
Bottom seal
Side seals
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

2
3
4

5
6
7
8
9
10
11

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12

particulars

Description

Crew for Mobile crane 16T


Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )
Khalasi
Helper fabrication / erection
Electrician

UNIT :

119.000 tonne

Unit

Quantity

kg
kg

5280.00
112880.00

40.00
40.00

211200.00
4515200.00

kg

520.00

420.00

218400.00

kg

600.00

120.00

72000.00

Rm
210.00
Rm
18.00
cum
2714.00
cum
905.00
Nos
86554.00
Nos
16486.00
Hour
12880.00
Hour
2714.00
LS
400.00
Total cost of Materials

780.00
1210.00
45.00
330.00
11.00
18.00
7.65
2.08
20.00
Rs:

163800.00
21780.00
122130.00
298650.00
952094.00
296748.00
98532.00
5654.17
8000.00
6984188.17

Rate
in Rs.
16.00
92.40
6.40
3.80
2278.10
75.00
86.10
0.00
22.50
38.50
22.50
38.50
42.60
115.50
20.00
Rs:

Amount
in Rs.
206080.00
1190112.00
41216.00
24472.00
820116.00
27000.00
20491.80
0.00
5355.00
9163.00
8032.50
13744.50
10224.00
27720.00
3600.00
2407326.80

Rate
in Rs.
489.20
187.20
187.20
122.50
480.00
480.00
415.00
415.00
480.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
176112.00
66830.40
44553.60
29400.00
57600.00
93600.00
41500.00
598430.00
132000.00
839545.00
1008990.00
4800.00
3093361.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
12880.00
12880.00
6440.00
6440.00
360.00
360.00
238.00
238.00
238.00
238.00
357.00
357.00
240.00
240.00
180.00

Quantity

Hour
360.00
Hour
357.00
Hour
238.00
Hour
240.00
Day
120.00
Day
195.00
Day
100.00
Day
1442.00
Day
275.00
Day
2023.00
Day
2727.00
Day
10.00
Total cost of Labour

Rate
in Rs.

Amount
in Rs.

293

Gates and Allied Works - Item Unit Rates 2015-16

Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

928008.30
4021369.30

labour component/unit qty


33793.00
Add contractor's profit and overhead charges
13.615% 4600.90
labour component/unit qty (including contractor's profit)
38393.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

IRR-GAW-2-3

13.615%
Rs.

18.90 per tonne


66.30 per tonne

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

6984188.17
2407326.80
4021369.30
13412884.27
0.00
13412884.27
402386.53
13815270.79

Rs:

1880949.12

4498.200
15779.4
Rs:
15716497.51
Rs:
132071.40

119.00 tonne
Rate per tonne

STOP LOGS-automatic lifting beam


fabrication, supply, erection, testing and commissioning of automatic lifting beam
with all accessories for handling, lowering and lifting of spillway stop log gate elements
including cost of all materials, machinery, labour, cutting, aligning, welding, finishing,
etc., complete as per specifications and drawings with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6
7
8
9
10
11
12
13

Structural steel
Angles / beams / channels / bars
Plates / flats
Alloy steel components
Lifting pins
Bronze alloy components :
Bronze bush
Forged steel components :
Lifting hooks
MS pipe 100 mm dia
Bolt / Nut / Washer
MS bolts / nuts / washers
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5

particulars

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine

UNIT :
Unit

Quantity

3.528 tonne
Rate
in Rs.

Amount
in Rs.

kg
kg

13.00
3389.00

40.00
40.00

520.00
135560.00

kg

101.00

420.00

42420.00

kg

5.00

920.00

4600.00

kg
kg

103.00
11.00

260.00
175.00

26780.00
1925.00

kg
3.00
cum
126.00
cum
42.00
Nos
175.00
Nos
1575.00
Hour
187.00
Hour
24.00
LS
25.00
Total cost of Materials

90.00
45.00
330.00
11.00
18.00
7.65
2.08
20.00
Rs:

270.00
5670.00
13860.00
1925.00
28350.00
1430.55
50.00
500.00
263860.55

Rate
in Rs.
16.00
92.40
6.40
3.80
519.70
307.20
86.10
0.00
22.50

Amount
in Rs.
2992.00
10810.80
384.00
228.00
2078.80
1228.80
688.80
0.00
45.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
187.00
117.00
60.00
60.00
4.00
4.00
8.00
8.00
2.00

294

Gates and Allied Works - Item Unit Rates 2015-16

6
7

Fuel / Energy charges


Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9

Description

Hour
Hour
Hour
LS

Unit

2.00
2.00
2.00
10.00

Quantity

Crew for Mobile crane


Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
4.00
Hour
2.00
Hour
2.00
Day
10.00
Day
18.00
Day
10.00
Day
18.00
Day
52.00
Day
1.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

38.50
22.50
38.50
20.00
Rs:

77.00
45.00
77.00
200.00
18855.20

Rate
in Rs.
165.80
187.20
187.20
480.00
480.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
663.20
374.40
374.40
4800.00
8640.00
4150.00
7470.00
19240.00
480.00
46192.00
13857.60
60049.60

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

263860.55
18855.20
60049.60
342765.35
0.00
342765.35
10282.96
353048.31

Rs:

48067.53

labour component/unit qty


17020.90
Add contractor's profit and overhead charges
13.615% 2317.40
labour component/unit qty (including contractor's profit)
19338.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

IRR-GAW-2-4

13.615%
Rs.

18.90 per tonne


66.30 per tonne

3.528 tonne
Rate per tonne

133.358
467.812
Rs:
401717.01
Rs:
113865.40

MOVING GANTRY CRANE-CLASS II


fabrication, supply, erection, testing and commissioning of adequate capacity Class- II
type moving gantry crane consisting of rail mounted gantry frame, top platform with hand
railing, long / cross travel arrangements, rope drums, gear systems, electric motors, electromagnetic brake system, cabin, control panel, wire rope, ladder, motorised cable reeling drum
etc., with all accessories for operating spillway stop log gate elements and river sluice /
canal sluice emergency gates including cost of all materials, machinery, labour,
etc., complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plates
Cast steel components :
Rope drums 2 Nos/Gears
pinions
Wheels / Pulleys
Plummer blocks / Couplings
Forged steel components

UNIT :
Unit

Quantity

30.856 tonne
25 t capacity
Rate
Amount
in Rs.
in Rs.

kg
kg
kg

1743.00
19700.00
820.00

40.00
40.00
63.00

69720.00
788000.00
51660.00

kg
kg
kg
kg

1320.00
1165.00
2255.00
817.00

220.00
210.00
180.00
180.00

290400.00
244650.00
405900.00
147060.00

295

Gates and Allied Works - Item Unit Rates 2015-16

5
6
7
8
9
10

11
12
13
14
15
16
17
18
19
20

Hook / Shackle
kg
127.00
Alloy steel components
Shafts
kg
556.00
Pins
kg
524.00
Bronze alloy components :
Bronze bearings / bush
kg
181.00
Wire rope 28 mm dia 6/37 construction
kg
406.00
MS Bolt / Nut / Washer
kg
63.00
MS pipe 32 mm dia for railing
Rm
50.00
Worm reducers
Nos.
4.00
Electric motor 17.5 hp
No.
1.00
Electric motor 5 hp
Nos.
2.00
Electric motor 3 hp
No.
1.00
Ele-magnetic / Thruster brakes
Nos.
4.00
Electric cable / switch / control panel
etc
LS
3.00
Oxygen gas
cum
579.00
Acetyline gas
cum
193.00
Welding electrodes
Nos
1123.00
Welding electrodes ( LH )
Nos
10110.00
Grease
kg
50.00
Use rate welding holder set
Hour
1197.00
Use rate gas cutting torch set
Hour
150.00
Sundries
LS
200.00
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

Description

Description

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
1197.00
748.00
6.00
6.00
235.00
235.00
100.00
100.00
32.00
32.00
16.00
16.00
500.00

Quantity

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Khalasi
Helper fabrication / erection
Electrician

Hour
100.00
Hour
6.00
Hour
16.00
Hour
32.00
Day
74.00
Day
124.00
Day
48.00
Day
112.00
Day
20.00
Day
350.00
Day
10.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

260.00

33020.00

230.00
420.00

127880.00
220080.00

920.00
200.00
90.00
185.00
224400.00
85800.00
33000.00
23100.00
35200.00

166520.00
81200.00
5670.00
9250.00
897600.00
85800.00
66000.00
23100.00
140800.00

50380.00
45.00
330.00
11.00
18.00
260.00
7.65
2.08
20.00
Rs:

151140.00
26055.00
63690.00
12353.00
181980.00
13000.00
9157.05
312.50
4000.00
4315997.55

Rate
in Rs.
16.00
92.40
867.10
200.20
6.40
3.80
519.70
307.20
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
19152.00
69115.20
5202.60
1201.20
1504.00
893.00
51970.00
30720.00
720.00
1232.00
360.00
616.00
10000.00
192686.00

Rate
in Rs.
165.80
176.80
187.20
187.20
480.00
480.00
415.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
16580.00
1060.80
2995.20
5990.40
35520.00
59520.00
19920.00
46480.00
8300.00
129500.00
4800.00
330666.40
99199.92
429866.32

Rs:
Rs:
Rs:
Rs:

4315997.55
192686.00
429866.32
4938549.87

labour component/unit qty


17194.70
Add contractor's profit and overhead charges
13.615% 2341.10
labour component/unit qty (including contractor's profit)
19535.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

296

Gates and Allied Works - Item Unit Rates 2015-16

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

0.00%
Total
3%
Total

F. Add for contractor's profit and overheads on


(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne

30.856 tonne
25.000 t capacity
Rate per tonne
Rate per

tonne capacity

Rs:
Rs:
Rs:
Rs:

0.00
4938549.87
148156.50
5086706.37

Rs:

692555.07

1166.356
4091.506
Rs:
5784519.30
Rs:
Rs:
187468.20
Rs:
231380.80

RAIL TRACK FOR GANTRY CRANE


IRR-GAW-2-5 Design, fabrication, supply, erection and commissioning of rail track using 45 kg / m standard
rails on spillway bridge for movement of gantry crane for handling and operating spillway
stoplog gate elements / river sluice / canal sluice emergency gate including cost of all materials,
machinery, labour, complete as per specifications
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

1
2
3
4
5
6
7
8
9
10

Str steel angle / beam / channel /


bars
Structural steel plate / flats
Rails
MS bolts and nuts
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5

Description

Welding transformer
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9

particulars

Description

UNIT :
Unit

Quantity

kg
1570.00
kg
975.00
kg
18450.00
kg
246.00
cum
201.00
cum
67.00
Nos
1805.00
Hour
193.00
Hour
133.00
LS
10.00
Total cost of Materials

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
193.00
121.00
4.00
4.00
8.00
8.00
50.00
50.00
10.00

Quantity

Crew for Mobile crane


Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
4.00
Hour
50.00
Hour
8.00
Day
8.00
Day
32.00
Day
17.00
Day
18.00
Day
52.00
Day
1.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty

200.000 Rm
Rate
in Rs.

Amount
in Rs.

40.00
40.00
52.53
90.00
45.00
330.00
11.00
7.65
2.08
20.00
Rs:

62800.00
39000.00
969178.50
22140.00
9045.00
22110.00
19855.00
1476.45
277.08
200.00
1146082.03

Rate
in Rs.
16.00
92.40
519.70
307.20
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
3088.00
11180.40
2078.80
1228.80
180.00
308.00
1125.00
1925.00
200.00
21314.00

Rate
in Rs.
165.80
187.20
187.20
480.00
480.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
663.20
9360.00
1497.60
3840.00
15360.00
7055.00
7470.00
19240.00
480.00
64965.80
19489.74
84455.54

422.30

297

Gates and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


13.615% 57.50
labour component/unit qty (including contractor's profit)
479.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1146082.03
21314.00
84455.54
1251851.57
0.00
1251851.57
37555.55
1289407.12

Rs:

175552.78

783.292
2747.738
Rs:
1468490.93
Rs:
7342.50

200.000 Rm
Rate per Rm

VERTICAL LIFT GATES/STOP LOGS - ROLLER MOUNTED


IRR-GAW-2-6 Design, fabrication, supply, erection, testing and commissioning of fixed wheel type vertical
lift service gate consisting of skin plate, vertical and horizontal girders, wheels, stiffeners, lifting
brackets, guide rollers, ballast blocks, teflon claded rubber seals etc., with all accessories for
river sluice / canal sluice vent including cost of all materials, machinery, labour,welding ,aligning finishing
seal fixing etc.with allleads and lifts, complete as per specifications andvapproved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing No. CE/CDO/DEE/DEE4/GNC/HR/2150/96,2137/98 (GNSS Project)
Gate Size: 3.66 X 6.1 Mtr
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3

4
5

7
8
9
10
11
12
13

Structural steel
Plates / flats
Beams/Channels
Alloy steel components
Wheel axles / Pins
Cast steel components
Wheels / Guide rollers
Alluminium / Bronze alloy
components
Bearings
Bolt / Nut / Washer
GI bolts / nuts / washers
MS bolts / nuts / washers
Rubber seals
Bottom seal ( flat uncladed )
Side seals ( bulb teflon claded )
Top seal ( bulb teflon claded )
Corner seals ( bulb teflon claded )
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2

particulars

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges

UNIT :
Unit

Quantity

10.000 tonne
Rate
in Rs.

Amount
in Rs.

kg
kg

7103.00
2727.00

40.00
40.00

284120.00
109080.00

kg

108.00

420.00

45360.00

kg

504.00

180.00

90720.00

kg

12.00

920.00

11040.00

kg
kg

36.00
6.00

106.00
90.00

3816.00
540.00

Rm
3.72
Rm
12.30
Rm
3.72
Nos
2.00
cum
170.00
cum
56.00
Nos
3200.00
Nos
800.00
Hour
500.00
Hour
40.00
LS
60.00
Total cost of Materials

780.00
1670.00
1670.00
1630.00
45.00
330.00
11.00
18.00
7.65
2.08
20.00
Rs:

2901.60
20541.00
6212.40
3260.00
7650.00
18480.00
35200.00
14400.00
3825.00
83.33
1200.00
658429.33

Rate
in Rs.
16.00
92.40
6.40
3.80

Amount
in Rs.
8000.00
46200.00
544.00
323.00

Unit
Hour
Hour
Hour
Hour

Quantity
500.00
500.00
85.00
85.00

298

Gates and Allied Works - Item Unit Rates 2015-16

3
4
5
6
7
8
9

Tower crane
Fuel / Energy charges
Mobile crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13

Description

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

10.00
10.00
30.00
30.00
20.00
20.00
10.00
10.00
30.00
30.00
10.00
10.00
50.00

Quantity

Crew for Mobile crane 16 T


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray grade )
Khalasi
Helper fabrication / erection
Electrician

Hour
30.00
Hour
10.00
Hour
30.00
Hour
10.00
Hour
10.00
Day
16.00
Day
50.00
Day
8.00
Day
52.00
Day
14.00
Day
170.00
Day
230.00
Day
4.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

867.10
200.20
2278.10
75.00
86.10
0.00
22.50
38.50
22.50
38.50
42.60
115.50
20.00
Rs:

8671.00
2002.00
68343.00
2250.00
1722.00
0.00
225.00
385.00
675.00
1155.00
426.00
1155.00
1000.00
143076.00

Rate
in Rs.
489.20
176.80
187.20
187.20
122.50
480.00
480.00
415.00
415.00
480.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
14676.00
1768.00
5616.00
1872.00
1225.00
7680.00
24000.00
3320.00
21580.00
6720.00
70550.00
85100.00
1920.00
246027.00
73808.10
319835.10

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

658429.33
143076.00
319835.10
1121340.43
0.00
1121340.43
33640.21
1154980.65

Rs:

157250.61

labour component/unit qty


31983.50
Add contractor's profit and overhead charges
13.615% 4354.60
labour component/unit qty (including contractor's profit)
36338.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne

10.000 tonne
Rate per tonne

378
1326
Rs:
1313935.26
Rs:
131393.50

VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP. POWER OPERATED
IRR-GAW-2-7 Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of hoist platform, rope drum, gear system, electric motor, electromagnetic brake system, hand operation assembly, control panel, wire rope, pulleys, ladder etc.,
with all accessories for operating river sluice / canal sluice service gate including cost of
all materials, machinery, labour, , complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

6.243 tonne wt
25 t capacity
Rate
Amount
in Rs.
in Rs.

299

Gates and Allied Works - Item Unit Rates 2015-16

5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 3 Nos / Couplings 2 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 28 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers
Electric motor 5 hp
Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

Description

Description

kg
kg
kg

1487.00
402.00
290.00

40.00
40.00
63.00

59480.00
16080.00
18270.00

kg
kg
kg
kg

1926.00
79.00
306.00
72.00

220.00
210.00
180.00
180.00

423720.00
16590.00
55080.00
12960.00

kg
kg

346.00
73.00

230.00
420.00

79580.00
30660.00

kg

57.00

920.00

52440.00

kg
kg
No.
No.
No.
No.
No.

325.00
32.00
1.00
1.00
1.00
1.00
1.00

200.00
90.00
224400.00
33000.00
28820.00
195800.00
35200.00

65000.00
2880.00
224400.00
33000.00
28820.00
195800.00
35200.00

LS
1.00
cum
45.00
cum
15.00
Nos
80.00
Nos
720.00
kg
50.00
Hour
85.00
Hour
16.00
LS
25.00
Total cost of Materials

50380.00
45.00
330.00
11.00
18.00
260.00
7.65
2.08
20.00
Rs:

50380.00
2025.00
4950.00
880.00
12960.00
13000.00
650.25
33.33
500.00
1435338.58

Rate
in Rs.
16.00
92.40
867.10
200.20
6.40
3.80
519.70
307.20
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
1360.00
4897.20
1734.20
400.40
96.00
57.00
5197.00
3072.00
45.00
77.00
45.00
77.00
500.00
17557.80

Rate
in Rs.
165.80
176.80
187.20
187.20
480.00
480.00
415.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
1658.00
353.60
374.40
374.40
7200.00
9120.00
1660.00
3320.00
1660.00
16280.00
960.00
42960.40
12888.12
55848.52

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
85.00
53.00
2.00
2.00
15.00
15.00
10.00
10.00
2.00
2.00
2.00
2.00
25.00

Quantity

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Khalasi
Helper fabrication / erection
Electrician

Hour
10.00
Hour
2.00
Hour
2.00
Hour
2.00
Day
15.00
Day
19.00
Day
4.00
Day
8.00
Day
4.00
Day
44.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty

2233.90

300

Gates and Allied Works - Item Unit Rates 2015-16

Add contractor's profit and overhead charges


13.615% 304.10
labour component/unit qty (including contractor's profit)
2538.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne
6.243 tonne wt
25.000 t capacity
Rate per tonne wt
Rate per tonne capacity of hoist

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1435338.58
17557.80
55848.52
1508744.90
0.00
1508744.90
45262.35
1554007.25

Rs:

211578.09

235.986
827.822
Rs:
1766649.15
Rs:
Rs:
282980.80
Rs:
70666.00

HOIST BRIDGE/ WITH TRESSELS


IRR-GAW-2-8 Design, fabrication, supply, erection and commissioning of structural steel hoist bridge
consisting of columns, beams, bracings, stiffeners, ties, chequered plate covering, hand railing,
ladder etc., with all accessories for supporting rope drum hoist for operating barrage
gates including cost of all materials, machinery, labour, welding, finishing, etc., complete
complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing No. CE/CDO/VRSP/215,216/86-87 (Vengalaraya Sagar - Gomukhi Project)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Structural steel angles/ beams /


channels
Structural steel plates / flats
Chequered plate
MS pipe 25 mm dia
Bolt / Nut / Washers
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set
Use rate gas cutting torch set
Sundries

2
3
4
5
6
7
8
9

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8

particulars

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 30 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Tower Crane
Fuel / Energy charges
Sundries
Total hire charges of Machinery

UNIT :
Unit

Quantity

kg
1494.00
kg
6564.00
kg
2442.00
Rm
60.00
kg
18.00
cum
105.00
cum
35.00
Nos
3150.00
Hour
394.00
Hour
105.00
LS
50.00
Total cost of Materials

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Quantity
394.00
394.00
52.00
52.00
30.00
30.00
20.00
20.00
20.00
20.00
20.00
20.00
20.00
20.00
50.00

Vent Size: 12 X 6.6 Mtr


10.500 tonne
Rate
in Rs.

Amount
in Rs.

40.00
40.00
63.00
150.00
90.00
45.00
330.00
11.00
7.65
2.08
20.00
Rs:

59760.00
262560.00
153846.00
9000.00
1620.00
4725.00
11550.00
34650.00
3014.10
218.75
1000.00
541943.85

Rate
in Rs.
16.00
92.40
6.40
3.80
3096.80
118.80
86.10
0.00
22.50
38.50
22.50
38.50
867.10
200.20
20.00
Rs:

Amount
in Rs.
6304.00
36405.60
332.80
197.60
92904.00
3564.00
1722.00
0.00
450.00
770.00
450.00
770.00
17342.00
4004.00
1000.00
166216.00

301

Gates and Allied Works - Item Unit Rates 2015-16

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10

Description

Unit

Quantity

Crew for Mobile crane 30 T


Crew for Drilling machine
Crew for Grinding machine
Crew for Tower Crane
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
30.00
Hour
20.00
Hour
20.00
Hour
20.00
Day
10.00
Day
50.00
Day
14.00
Day
53.00
Day
400.00
Day
6.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

Rate
in Rs.
489.20
187.20
187.20
176.80
480.00
480.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
14676.00
3744.00
3744.00
3536.00
4800.00
24000.00
5810.00
21995.00
148000.00
2880.00
233185.00
69955.50
303140.50

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

541943.85
166216.00
303140.50
1011300.35
0.00
1011300.35
30339.01
1041639.36

Rs:

141819.20

labour component/unit qty


28870.50
Add contractor's profit and overhead charges
13.615% 3930.70
labour component/unit qty (including contractor's profit)
32801.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne

10.500 tonne
Rate per tonne

396.9
1392.3
Rs:
1185247.76
Rs:
112880.70

ROPE DRUM HOIST WITHOUT HOIST BRIDGE FOR BARRAGE GATES


IRR-GAW-2-9 Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of rope drum, pulleys, gear system, electri c motor,
electro-magnetic brake system, manual operation assembly, position indicator, control panel,
wire rope etc., with all accessories for operating vertical lift roller gates for barrage
including cost of all materials, machinery, labour, cutting, bending, aligning, anchoring, welding,
finishing etc., complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

5
6
7

particulars

Structural steel
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 3 Nos / Couplings 2 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts / Keys
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 28 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers

UNIT :
Unit

Quantity

5.069 tonne wt
50.00 t capacity
Rate
Amount
in Rs.
in Rs.

kg
kg

420.00
225.00

40.00
40.00

16800.00
9000.00

kg
kg
kg
kg

1290.00
98.00
650.00
250.00

220.00
210.00
180.00
180.00

283800.00
20580.00
117000.00
45000.00

kg
kg

350.00
96.00

230.00
420.00

80500.00
40320.00

kg

100.00

920.00

92000.00

kg
kg
No.

435.00
26.00
1.00

200.00
90.00
224400.00

87000.00
2340.00
224400.00

302

Gates and Allied Works - Item Unit Rates 2015-16

8
9
10
11
12
13
14
15
16
17
18
19
20

Electric motor 12.5 hp


Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

Description

Description

No.
No.
No.
No.

1.00
1.00
1.00
1.00

72600.00
28820.00
195800.00
35200.00

72600.00
28820.00
195800.00
35200.00

LS
1.00
cum
30.00
cum
10.00
Nos
44.00
Nos
392.00
kg
50.00
Hour
47.00
Hour
12.00
LS
25.00
Total cost of Materials

50380.00
45.00
330.00
11.00
18.00
260.00
7.65
2.08
20.00
Rs:

50380.00
1350.00
3300.00
484.00
7056.00
13000.00
359.55
25.00
500.00
1427614.55

Rate
in Rs.
16.00
92.40
867.10
200.20
6.40
3.80
519.70
307.20
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
752.00
4342.80
1734.20
400.40
57.60
34.20
5197.00
3072.00
45.00
77.00
45.00
77.00
500.00
16334.20

Rate
in Rs.
165.80
176.80
187.20
187.20
480.00
480.00
415.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
1658.00
353.60
374.40
374.40
6240.00
8160.00
1245.00
2075.00
1660.00
13320.00
960.00
36420.40
10926.12
47346.52

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1427614.55
16334.20
47346.52
1491295.27
0.00
1491295.27
44738.86
1536034.13

Rs:

209131.05

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

47.00
47.00
2.00
2.00
9.00
9.00
10.00
10.00
2.00
2.00
2.00
2.00
25.00

Quantity

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Khalasi
Helper fabrication / erection
Electrician

Hour
10.00
Hour
2.00
Hour
2.00
Hour
2.00
Day
13.00
Day
17.00
Day
3.00
Day
5.00
Day
4.00
Day
36.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
946.90
Add contractor's profit and overhead charges
13.615% 128.90
labour component/unit qty (including contractor's profit)
1075.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne
5.069 tonne wt

191.608
672.15
Rs:
1746028.93

303

Gates and Allied Works - Item Unit Rates 2015-16

50.000 t capacity
Rate per tonne wt
Rate per tonne capacity of hoist

Rs:
Rs:
Rs:

344452.30
34920.60

SCREW GEAR HOISTS including plat form( UPTO 10 TON CAP)


IRR-GAW-2-10
Design, fabrication, supply, erection, testing and commissioning of adequate capacity screw gear
type hoist consisting of supporting structure, platform, ladder etc., with all accessories for
operating canal escape / regulator gate including cost of all materials, machinery, labour,
cutting, bending, aligning, anchoring, welding,finishing etc.,complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6
7
8
9
10
11
12
13

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast iron components :
Hoist body / Lock nut / Main nut
Alloy steel components
Hoist stem
Bronze alloy components :
Thrust bearings
MS Bolt / Nut / Washer
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4

Description

Welding transformer
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

particulars

Description

UNIT :
Unit

Quantity

0.871 tonne
3.00 t capacity
Rate
Amount
in Rs.
in Rs.

kg
kg
kg

402.00
145.00
176.00

40.00
40.00
63.00

16080.00
5800.00
11088.00

kg

55.00

220.00

12100.00

kg

75.00

230.00

17250.00

kg
4.00
kg
8.00
cum
18.00
cum
6.00
Nos
7.00
Nos
66.00
kg
2.00
Hour
8.00
Hour
11.00
LS
2.00
Total cost of Materials

920.00
90.00
45.00
330.00
11.00
18.00
260.00
7.65
2.08
20.00
Rs:

3680.00
720.00
810.00
1980.00
77.00
1188.00
520.00
61.20
22.92
40.00
71417.12

Rate
in Rs.
16.00
92.40
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
128.00
462.00
45.00
77.00
45.00
77.00
40.00
874.00

Rate
in Rs.
187.20
187.20
480.00
480.00
415.00
415.00
370.00
480.00
Rs:

Amount
in Rs.
374.40
374.40
1920.00
2400.00
830.00
415.00
3330.00
240.00
9883.80
2965.14
12848.94

Unit
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
8.00
5.00
2.00
2.00
2.00
2.00
2.00

Quantity

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
2.00
Hour
2.00
Day
4.00
Day
5.00
Day
2.00
Day
1.00
Day
9.00
Day
0.50
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
4283.00
Add contractor's profit and overhead charges
13.615% 583.10
labour component/unit qty (including contractor's profit)
4866.10

304

Gates and Allied Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

13.615%
Rs.

18.90 per tonne


66.30 per tonne

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

71417.12
874.00
12848.94
85140.06
0.00
85140.06
2554.20
87694.26

Rs:

11939.57

32.924
115.494
Rs:
99782.25
Rs:
Rs:
114560.60
Rs:
33260.70

0.871 tonne
3.000 t capacity
Rate per tonne
Rate per tonne capacity

MANUAL OPERATED ROPE DRUM HOISTS


IRR-GAW-2-11
Design, fabrication, supply, erection, testing and commissioning of adequate capacity
manually operated rope drum hoist consisting of hoist platform, rope drum, gear system,
brake system, wire rope, ladder etc., with all accessories for operating canal regulator
radial gate including cost of all materials, machinery, labour, welding, finishing, cleaning,
., complete with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:

RATE ANALYSIS

UNIT :

A. MATERIALS:
Sl No
particulars
1

5
6
7
8
9
10
11
12
13
14
15
16
17
18

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 6 Nos
Plummer blocks / Couplings
Alloy steel components
Shafts
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 12 mm dia 6/36
construction
MS Bolt / Nut / Washer
Worm reducers
Manual operating system
Brake
Wire rope sockets
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
Description
1
2

Welding transformer
Fuel / Energy charges
Pug cutting machine

2.804
10.00
Rate
in Rs.

tonne
t capacity
Amount
in Rs.

Unit

Quantity

kg
kg
kg

1229.00
453.00
195.00

40.00
40.00
63.00

49160.00
18120.00
12285.00

kg
kg
kg
kg

384.00
14.00
108.00
47.00

220.00
210.00
180.00
180.00

84480.00
2940.00
19440.00
8460.00

kg
kg

75.00
24.00

230.00
420.00

17250.00
10080.00

kg

11.00

920.00

10120.00

kg
42.00
kg
64.00
No.
1.00
No.
1.00
No.
1.00
No
2.00
cum
75.00
cum
25.00
Nos
69.00
Nos
622.00
kg
10.00
Hour
73.00
Hour
42.00
LS
25.00
Total cost of Materials

200.00
90.00
224400.00
28820.00
35200.00
4620.00
45.00
330.00
11.00
18.00
260.00
7.65
2.08
20.00
Rs:

8400.00
5760.00
224400.00
28820.00
35200.00
9240.00
3375.00
8250.00
759.00
11196.00
2600.00
558.45
87.50
500.00
571480.95

Unit
Hour
Hour
Hour

Quantity
73.00
46.00
8.00

Rate Amount
in Rs. in Rs.
16.00
1168.00
92.40
4250.40
6.40
51.20

305

Gates and Allied Works - Item Unit Rates 2015-16

3
4
5
6
7

Fuel / Energy charges


Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

8.00
4.00
4.00
8.00
8.00
8.00
8.00
16.00
16.00
25.00

Quantity

Crew for Mobile crane


Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

3.80
519.70
307.20
86.10
0.00
22.50
38.50
22.50
38.50
20.00
Rs:

Rate
in Rs.

Hour
4.00
Hour
16.00
Hour
8.00
Day
14.00
Day
20.00
Day
6.00
Day
7.00
Day
44.00
Day
2.00
Total cost of Labour
Rs:
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

30.40
2078.80
1228.80
688.80
0.00
180.00
308.00
360.00
616.00
500.00
11460.40

Amount
in Rs.
165.80
187.20
187.20
480.00
480.00
415.00
415.00
370.00
480.00

663.20
2995.20
1497.60
6720.00
9600.00
2490.00
2905.00
16280.00
960.00
44111.00
13233.30
57344.30

labour component/unit qty


5734.40
Add contractor's profit and overhead charges
13.615% 780.70
labour component/unit qty (including contractor's profit)
6515.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for
Rate per

IRR-GAW-212
New Item
2014-15-2

13.615%
Rs.

18.90 per tonne


66.30 per tonne

2.804 tonne
10.000 t capacity
tonne
Rate per
tonne
capacity of hoist

Rs:
Rs:
Rs:
Rs:
Rs:

571480.95
11460.40
57344.30
640285.65
0.00
640285.65
19208.57
659494.22

Rs:

89790.14

105.992
371.81
Rs:
749762.16
Rs:
Rs:

267390.20
74976.20

OT SLUICE SHUTTERS Screw Gear Hoist Including Platform for below 5 Tons Capacity (Small Gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of supporting structure,
platform etc. with all accessories for operating canal escape/ regulator gate with all accessories including cost of all
materials, machinery, labour, cutting, bending, aligning, anchoring, welding, finishing etc. complete
as per Specification and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

0.869 tonne
Rate
in Rs.

Amount
in Rs.

306

Gates and Allied Works - Item Unit Rates 2015-16

1
2
3
4
5
6
7
8
9
10
11
12
13

Structural steel angles/ beams / channels kg


445.78
Structural steel plates / flats
kg
28.00
Chequered plate
kg
144.80
Cast iron Components
Hoist Body/lock nut/Main Nut etc.
Kg
83.00
Bronze Alloy Steel Components
Thrust Bearings
kg
3.00
MS Bolt/Nut/ Washer
kg
16.00
Oxygen gas
cum
21.00
Acetyline gas
cum
7.00
Welding electrodes
Nos
200.00
Welding electrodes (LH)
Nos
40.00
Use rate welding holder set
Hour
72.00
Use rate gas cutting torch set
Hour
36.00
Sundries
LS
20.00
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4
5
6

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Lathe machine (Screw Rod M/C)
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Description

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

30.00
30.00
12.00
12.00
8.00
8.00
36.00
36.00
16.00
10.00

Quantity

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Mazdoors
Helper fabrication / erection

Hour
8.00
Hour
36.00
Day
2.00
Day
10.00
Day
4.00
Day
4.00
Day
6.00
Day
6.00
Total cost of Labour
labour component/unit qty
21396.80
Add contractor's profit and overhead charges
13.615% 2913.20
labour component/unit qty (including contractor's profit)
24310.00

40.00
40.00
63.00

17831.20
1120.00
9122.40

220.00

18260.00

920.00
90.00
45.00
330.00
11.00
18.00
7.65
2.08
20.00
Rs:

2760.00
1440.00
945.00
2310.00
2200.00
720.00
550.80
75.00
400.00
57734.40

Rate
in Rs.
16.00
92.40
6.40
3.80
22.50
38.50
22.50
38.50
300.00
20.00
Rs:

Amount
in Rs.
480.00
2772.00
76.80
45.60
180.00
308.00
810.00
1386.00
4800.00
200.00
11058.40

Rate
in Rs.
187.20
187.20
480.00
480.00
415.00
415.00
310.00
370.00
Rs:

Amount
in Rs.
1497.60
6739.20
960.00
4800.00
1660.00
1660.00
1860.00
2220.00
21396.80

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

57734.40
11058.40
21396.80
90189.60
0.00
90189.60
2705.69
92895.29

Rs:

12647.69

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

IRR-GAW-213
New Item
2014-15-3

13.615%
Rs.
0.869 tonne
Rate per tonne

18.90 per tonne


66.30 per tonne

32.848
115.23
Rs:
105691.06
Rs:
121623.80

OT SLUICE SHUTTERS EM parts for Below 5 Tons capacity (small gates)


As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for

307

Gates and Allied Works - Item Unit Rates 2015-16

Krishna Delta System


Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of sil beam, slide tracks,
seal seats, Guide plates etc. with all accessories including cost of all materials, machinery, labour, etc.
complete as per specifications and approved drawings.
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
Height of EM parts: 5.4 M

Gate Size:

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10

2
3
4
5

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

UNIT :
Unit

Quantity

Structural steel angles/ beams / channels kg


440.57
Structural steel plates / flats
kg
869.00
Stainless Steel Flats
kg
25.12
Oxygen gas
cum
12.00
Acetyline gas
cum
4.00
Welding electrodes
Nos
210.00
Welding electrodes (Stainless Steel)
Nos
30.00
Use rate welding holder set
Hour
62.00
Use rate gas cutting torch set
Hour
32.00
Sundries
LS
3.00
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

Description

0.99 X 0.875 M

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

30.00
30.00
20.00
20.00
4.00
4.00
20.00
20.00
3.00

Quantity

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Mazdoors
Helper fabrication / erection

Hour
4.00
Hour
20.00
Day
8.00
Day
6.00
Day
2.00
Day
4.00
Day
4.00
Day
8.00
Total cost of Labour
labour component/unit qty
17902.80
Add contractor's profit and overhead charges
13.615% 2437.50
labour component/unit qty (including contractor's profit)
20340.30

1.334 tonne
Rate
in Rs.
40.00
40.00
275.00
45.00
330.00
11.00
27.00
7.65
2.08
20.00
Rs:

Amount
in Rs.
17622.80
34760.00
6908.00
540.00
1320.00
2310.00
810.00
474.30
66.67
60.00
64871.77

Rate
in Rs.
16.00
92.40
6.40
3.80
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
480.00
2772.00
128.00
76.00
90.00
154.00
450.00
770.00
60.00
4980.00

Rate
in Rs.
187.20
187.20
480.00
480.00
415.00
415.00
310.00
370.00
Rs:

Amount
in Rs.
748.80
3744.00
3840.00
2880.00
830.00
1660.00
1240.00
2960.00
17902.80

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

64871.77
4980.00
17902.80
87754.57
0.00
87754.57
2632.64
90387.20

Rs:

12306.22

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs

13.615%
Rs.

18.90 per tonne


66.30 per tonne

50.426
176.888

308

Gates and Allied Works - Item Unit Rates 2015-16

Total cost for

IRR-GAW-214
New Item
2014-15 -4

1.334 tonne
Rate per tonne

Rs:
Rs:

102920.74
77152.00

OT SLUICE SHUTTERS for Below 5 Tons capacity (small gates)


As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Sluice Shutters consisting of skin plate, horizontal
and vertical angles, stiffeners, rubber seals, clamps with all accessories for sluice shutters including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
Gate Size: 0.99 X 0.875 M

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11

2
3
4
5

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Unit

Quantity

Structural steel angles/ beams / channels kg


63.72
Structural steel plates / flats
kg
96.50
GI Bolts/Nut/Washer
kg
20.00
Rubber Seals
Bottom Seal
Rm
0.82
Side Seal/ Top Seal
Rm
1.75
Oxygen gas
cum
15.00
Acetyline gas
cum
5.00
Welding electrodes
Nos
110.00
Use rate welding holder set
Hour
30.00
Use rate gas cutting torch set
Hour
12.00
Sundries
LS
3.00
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
14.00
14.00
4.00
4.00
2.00
2.00
4.00
4.00
3.00

Quantity

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Mazdoors
Helper fabrication / erection

Hour
2.00
Hour
4.00
Day
2.00
Day
3.00
Day
1.00
Day
4.00
Day
4.00
Day
6.00
Total cost of Labour
labour component/unit qty
9058.20
Add contractor's profit and overhead charges
13.615% 1233.30
labour component/unit qty (including contractor's profit)
10291.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

0.161 tonne
Rate
in Rs.
40.00
40.00
120.00

Amount
in Rs.
2548.80
3860.00
2400.00

780.00
1210.00
45.00
330.00
11.00
7.65
2.08
20.00
Rs:

639.60
2117.50
675.00
1650.00
1210.00
229.50
25.00
60.00
15415.40

Rate
in Rs.
16.00
92.40
6.40
3.80
22.50
38.50
22.50
38.50
20.00
Rs:

Amount
in Rs.
224.00
1293.60
25.60
15.20
45.00
77.00
90.00
154.00
60.00
1984.40

Rate
in Rs.
187.20
187.20
480.00
480.00
415.00
415.00
310.00
370.00
Rs:

Amount
in Rs.
374.40
748.80
960.00
1440.00
415.00
1660.00
1240.00
2220.00
9058.20

Rs:
Rs:
Rs:
Rs:

15415.40
1984.40
9058.20
26458.00

309

Gates and Allied Works - Item Unit Rates 2015-16

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

0.00%
Total
3%
Total

F. Add for contractor's profit and overheads on


(A+B+C+D+E)
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

IRR-GAW-3

13.615%
Rs.

Rs:
Rs:
Rs:
Rs:

0.00
26458.00
793.74
27251.74

Rs:

3710.32

18.90 per tonne


66.30 per tonne

0.161 tonne
Rate per tonne

6.086
21.348
Rs:
Rs:

30989.50
192481.40

SAND BLASTING AND PAINTING AS PER IS:14177-1994

IRR-GAW-3-1 Cleaning gates / hoists / embedded parts/lifting beams etc, to expose fresh metal surface
for painting by sand blasting method as per specifications including cost of all materials, l
abour, machinery, scaffolding, etc., complete with initial lead for sand upto 1 km and all lifts.
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

particulars

UNIT : 100
Unit

Quantity

cum
30.00
Hour
8.00
Hour
8.00
LS
5.00
Total
Add 10% towards scaffolding/laddor @
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
1
2

Sand (Screened)
Use rate of air hose
Use rate of sand blast gun nozzle
Sundries( Rust inhibitive, seive etc )

Air compressor 7 cmm diesel


Fuel / Energy charges
Sand blasting equipment
Fuel / Energy charges

C. LABOUR:
Sl No
1
2
3

Description

Rate
in Rs.
760.00
18.63
3.50
20.00
0.10

Rate
in Rs.
Hour
8.00
241.30
Hour
8.00
731.40
Hour
8.00
110.10
Hour
8.00
0.00
Total hire charges of Machinery
Unit

Quantity

Crew for Air compressor


Crew for Sand blasting equipment
mazdoor

Hour
8.00
Hour
8.00
Day
15.00
Total cost of Labour
labour component/unit qty
78.50
Add contractor's profit and overhead charges
13.615% 10.70
labour component/unit qty (including contractor's profit)
89.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Total cost for

sqm

13.615%
100.00 sqm
Rate per sqm

Amount
in Rs.
22800.00
149.00
28.00
100.00
23077.00
2307.70
25384.70
Amount
in Rs.
1930.40
5851.20
880.80
0.00
8662.40

Rate
in Rs.
195.90
204.10
310.00

Amount
in Rs.
1567.20
1632.80
4650.00
7850.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

25384.70
8662.40
7850.00
41897.10
0.00
41897.10
1256.91
43154.01

Rs:
Rs:
Rs:

5875.42
49029.43
490.30

IRR-GAW-3-2 painting of embedded metal parts and all types of gates, stoplogs,etc, on sand blasted
surfaces with one coat of inorganic zinc silicate (airless spray preferred)70+/- 5
and two super coats with a total thickness of 300 microns
(each 150+/- 5) of solventless coaltar epoxy paint each coat 150 microns ( total 300 microns)
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts

310

Gates and Allied Works - Item Unit Rates 2015-16

(Upstream surface of gates portion may be painted with solventless coaltar epoxy brown paint
instead of solventless coaltar black. The rate for coaltar epoxy brown shall be adopted in data
for Upstream side painting)
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

1
2
3

UNIT :

particulars

Unit

Quantity

inorganic zinc silicate


Thinner @ 10%
Solventless Coal tar epoxy paint
Thinner @ 10%
Sundries ( brushes,ladders,platforms
etc )

ltr
ltr
ltr
ltr

12.00
1.20
40.00
4.00

B. MACHINERY:
Sl No

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

Sqm/Hr

3.00
Total cost of Materials
Unit

Quantity

Hr
Hr
Hr

100 sqm
Rate
in Rs.
550.00
140.00
250.00
140.00
20.00
Rs:

1
2
3

Description

Unit

6.00

Amount
in Rs.
728.40

6.00
6.00

241.30
731.40

1447.80
4388.40

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
169.80
Add contractor's profit and overhead charges
13.615% 23.10
labour component/unit qty (including contractor's profit)
192.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for excise duty
(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
13.615%
Total cost for
100.00 sqm
Rate per sqm

60
17388.00

Rate
in Rs.
121.40

Total cost of Machinery


C. LABOUR:
Sl No

Amount
in Rs.
6600
168
10000
560

Total
0
Total
0.03
Total

Rs:

6564.60

Rs:

Amount
in Rs.
1175.40
9600.00
6200.00
16975.40

Rate
in Rs.
195.90
480.00
310.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

17388.00
6564.60
16975.40
40928.00
0.00
40928.00
1227.84
42155.84

Rs:
Rs:
Rs:

5739.52
47895.36
479.00

IRR-GAW-3-3
painting of Lifting beams,cat walks and other similar structures-painting hoist machinery,
on sand blasted surfaces with two coats of zinc phosphate primer (airless spray preferred)
40microns/coat and twocoats of alkyd based micaccous iron oxide paint , 65 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
DATA:

Consider 100 sqm area for painting:


Requirement of materials :

311

Gates and Allied Works - Item Unit Rates 2015-16

Theoretical spreading rate per one Coat of Paint


25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

UNIT :

particulars

B. MACHINERY:
Sl No

28.00
2.80

Amount
in Rs.
5600
392

20.00
2.00

185.00
140.00

3700
280

3.00
Total cost of Materials

20.00

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
2
Cmm (diesel)
3
Fuel Charges of Air Compressor
Total cost of machinery
C. LABOUR:
Sl No
Description
1
2
3

Unit

Quantity

ltr
ltr
ltr
ltr

100 sqm
Rate
in Rs.
200.00
140.00

zinc phosphate primer


Thinner@10%
alkyd based micaccous iron oxide
paint
Thinner@10%
Sundries ( brushes,ladders,platforms
etc )

Sqm/Hr

Unit

Quantity

Hr
Hr
Hr

Unit

Rs:

6.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

6.00
6.00

241.30
731.40
RS:

1447.80
4388.40
6564.60

Rs:

Amount
in Rs.
1175.40
7200.00
4650.00
13025.40

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
15.00
Day
15.00
Total cost of Labour
labour component/unit qty
130.30
Add contractor's profit and overhead charges
13.615% 17.70
labour component/unit qty (including contractor's profit)
148.00

Rate
in Rs.
195.90
480.00
310.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0
Total
0.03
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Total cost for

IRR-GAW-3-4

.
DATA:

60
10032.00

13.615%
100.00 sqm
Rate per sqm

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

10032.00
6564.60
13025.40
29622.00
0.00
29622.00
888.66
30510.66

Rs:
Rs:
Rs:

4154.03
34664.69
346.60

HOISTS:STRUCTURAL COMPONENTS--painting structurals on sand blasted surfaces with


two coats of zinc phosphate primer (airless spray preferred) 40microns/coat
and one coat 65+/-5 of alkyd based micaccous iron oxide paint
followed by two coats of synthetic enamel paint 25 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
Consider 100 sqm area for painting:
Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area
Say

Sqm/Hr

17.50 Sqm/Hr
5.71
Hr
6
Hr

312

Gates and Allied Works - Item Unit Rates 2015-16

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

particulars

Unit

Quantity

zinc phosphate primer


Thinner@10%
alkyd based micaccous iron oxide
paint
Thinner@10%
synthetic enamel paint
Thinner@10%
Sundries ( brushes,ladders,platforms
etc )

ltr
ltr
ltr
ltr
ltr
ltr

B. MACHINERY:
Sl No
1
2
3

100 sqm

28.00
2.80

Rate
in Rs.
200.00
140.00

Amount
in Rs.
5600
392

15.00
1.50
17.00
1.70

185.00
140.00
240.00
140.00

2775
210
4080
238

3.00
Total cost of Materials

20.00

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

C. LABOUR:
Sl No
1
2
3

UNIT :

Unit

Quantity

Hr

6.00

Hr
6.00
Hr
6.00
Total cost of Machinery

Description

Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
169.80
Add contractor's profit and overhead charges
13.615% 23.10
labour component/unit qty (including contractor's profit)
192.90

Rs:
Rate
in Rs.
121.40

Amount
in Rs.
728.40

241.30
731.40
Rs:

1447.80
4388.40
6564.60

Rs:

Amount
in Rs.
1175.40
9600.00
6200.00
16975.40

Rate
in Rs.
195.90
480.00
310.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0
Total
0.03
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Total cost for

IRR-GAW-3-5

DATA:

60
13355.00

13.615%
100.00 sqm
Rate per sqm

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

13355.00
6564.60
16975.40
36895.00
0.00
36895.00
1106.85
38001.85

Rs:
Rs:
Rs:

5173.95
43175.80
431.80

HOISTS:machineryCOMPONENTS--painting hoist machinery, on sand blasted surfaces with


one coats of zinc phosphate primer (airless spray preferred) 50microns/coat
and three coats of aluminium paint or synthetic enamel , 25 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
Consider 100 sqm area for painting:
Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

zinc phosphate primer


Thinner@10%

Sqm/Hr

UNIT :
Unit

Quantity

ltr
ltr

14.00
1.40

100 sqm
Rate
in Rs.
200.00
140.00

Amount
in Rs.
2800
196

313

Gates and Allied Works - Item Unit Rates 2015-16

3
4
5

aluminium paint or synthetic enamel


per coat
Thinner@10%
Sundries ( brushes,ladders,platforms
etc )

B. MACHINERY:
Sl No
1
2
3

1
2
3

26.00
2.60

240.00
140.00

6240
364

3.00
Total cost of Materials

20.00
Rs:

60
9660.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

241.30
731.40

1447.80
4388.40
6564.60

Rate
in Rs.
195.90
480.00
310.00

Amount
in Rs.
1175.40
9600.00
6200.00
16975.40

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

C. LABOUR:
Sl No

ltr
ltr

Unit

Quantity

Hr

6.00

Hr
6.00
Hr
6.00
Total cost of Machinery

Description

Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
169.80
Add contractor's profit and overhead charges
13.615% 23.10
labour component/unit qty (including contractor's profit)
192.90

Rs:

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0
Total
0.03
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Total cost for

IRR-GAW-4

13.615%
100.00 sqm
Rate per sqm

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

9660.00
6564.60
16975.40
33200.00
0.00
33200.00
996.00
34196.00

Rs:
Rs:
Rs:

4655.79
38851.79
388.50

PAINTING WITHOUT SAND BLASTING

IRR-GAW-4-1 E.M Parts OF ALL TYPES OF GATES


Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners and removing
dust. After cleaning,applying primary coat with one coat of Protective Mastic to athickness of 70+5 microns
,followed by finishing coats 2 coats with Solventless Coal tar epoxy each coat with a DFT of 150+5 microns
and total DFT of all coats including Primary coat should not be less than 350 microns with material, labour and all
accessories with all leads and lifts
(in respect of Heavily rusted (30 to 40% rusted) surfaces)
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

particulars

Rust cleaner / inhibitor


Protective Mastic
Thinner@10%
Solventless Coal tar epoxy paint
Thinner@10%
Wire brush
Sundries

Sqm/Hr

UNIT :
Unit
ltr
ltr
ltr
ltr
ltr
Nos
LS

Quantity
13
25
2.5
40.00
4
2
3.00

100.000 Sq.m
Rate
in Rs.
140
483
140.00
250.00
140.00
41.00
20.00

Amount
in Rs.
1820.00
12075.00
350.00
10000.00
560.00
82.00
60.00

314

Gates and Allied Works - Item Unit Rates 2015-16

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor
Total cost of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Description

Unit

Quantity

Hr

Rs:

6.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

Hr
Hr

6.00
6.00

241.30
731.40

1447.80
4388.40
6564.60

Unit

Quantity

Rate
in Rs.
195.90
480.00
310.00

Amount
in Rs.
1175.40
9600.00
6200.00
16975.40

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
169.80
Add contractor's profit and overhead charges
13.615% 23.10
labour component/unit qty (including contractor's profit)
192.90

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on
(A+B+C+D+E)
Total cost for

24947.00

13.615%
100.00 sqm
Rate per sq.meter

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

24947.00
6564.60
16975.40
48487.00
0.00
48487.00
1454.61
49941.61

Rs:
Rs:
Rs:

6799.55
56741.16
567.40

IRR-GAW-4-3 HOIST BRIDGES ,HOISTING EQUIPMENT AND CRANES,Etc,


Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners
and removing dust. After cleaning,applying primary coat with two coats of Zinc chromite red oxide primer ,
followed by finishing coats 3 coats with synthetic enamel paint with material, labour,and all accessories
with all leads and lifts where surface cleaning by sand blasting is not feasible and based on specific
recommendations of designers, it is to adopt surface preperation done manually by hand and power tool
after cleaning by chemical treatment to remove grease, rust, scaling etc., and to form phasphate coating
to prevent further rusting, before applying primer painting.
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

particulars

Rust cleaner / inhibitor


Zinc Chromite Red Oxide Primer
Thinner@10%
Synthetic enamel Paint
Thinner@10%
Wire brush
Sundries

Sqm/Hr

UNIT :
Unit

Quantity

ltr
13
ltr
28
ltr
2.8
ltr
17.00
ltr
1.7
Nos
2
LS
3.00
Total cost of Materials

100.000 Sq.m
Rate
in Rs.
140
175
140.00
240.00
140.00
41.00
20.00

Amount
in Rs.
1820.00
4900.00
392.00
4080.00
238.00
82.00
60.00
11572.00

315

Gates and Allied Works - Item Unit Rates 2015-16

B. MACHINERY:
Sl No
1
2
3

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

C. LABOUR
Sl No
1
2
3

Description

Unit

Quantity

Hr

6.00

Hr
6.00
Hr
6.00
Total cost of Machinery

Description

Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
169.80
Add contractor's profit and overhead charges
13.615% 23.10
labour component/unit qty (including contractor's profit)
192.90

Rate
in Rs.
121.40

Amount
in Rs.
728.40

241.30
731.40

1447.80
4388.40
6564.60

Rate
in Rs.
195.90
480.00
310.00

Amount
in Rs.
1175.40
9600.00
6200.00
16975.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
Rs.
Rs.
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

Total
0.00%
Total
3%
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on (A+B+C+D+E)


13.615%
Total cost for
100.00 sqm
Rate per sq.meter

11572.00
6564.60
16975.40
35112.00
0.00
35112.00
1053.36
36165.36
4923.91
41089.27
410.90

WALK WAYS( CAT WALKS), LIFTING BEAMS,etc,


IRR-GAW-4-4 Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners
and removing dust. After cleaning,applying primary coat with one coat of Zinc rich epoxy primer to
a thickness of 40 microns ,followed by finishing coats 2 coats with Solventless Coal tar epoxy with material,
labour and all accessories with all leads and lifts
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Rust cleaner / inhibitor


Zinc rich epoxy primer
Thinner@10%
Solvetnless Coal tar epoxy paint
Thinner@10%
Wire brush
Sundries

B. MACHINERY:
Sl No
1
2
3

particulars

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

Sqm/Hr

UNIT :
Unit

Quantity

ltr
13
ltr
14
ltr
1.4
ltr
40
ltr
4
Nos
2
LS
3
Total cost of Materials

Unit

Quantity

Hr
Hr
Hr

100.000 Sq.m
Rate
in Rs.
140
700
140.00
250
140.00
41
20
Rs:

Amount
in Rs.
1820.00
9800.00
196.00
10000.00
560.00
82.00
60.00
22518.00

6.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

6.00
6.00

241.30
731.40

1447.80
4388.40

316

Gates and Allied Works - Item Unit Rates 2015-16

Total cost of Machinery


C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
13.00
Day
13.00
Total cost of Labour
labour component/unit qty
114.50
Add contractor's profit and overhead charges
13.615% 15.60
labour component/unit qty (including contractor's profit)
130.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for excise duty
(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

Total
0.00%
Total
3%
Total

F. Add for contractor's profit and overheads on (A+B+C+D+E)


13.615%
Total cost for
100.00 sqm
Rate per sq.meter

Rs:

6564.60

Rs:

Amount
in Rs.
1175.40
6240.00
4030.00
11445.40

Rate
in Rs.
195.90
480.00
310.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

22518.00
6564.60
11445.40
40528.00
0.00
40528.00
1215.84
41743.84
5683.42
47427.26
474.30

317

Preliminary and Maintenance Works - Item Unit Rates 2015-16

CHAPTER-VI

PRELIMINARY AND MAINTENANCE WORKS - Standard Data


(STORED WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
For the Year:2015-16
Index- code
IRR-PMW

PRELIMINARY & MAINTENANCE WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing
the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate,
the additional lead as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total
lead involved and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and
unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate
and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges
Rs. for 5 km
83.60
Lead charges for next 10Rs.
km
125
Total lead charges for 15Rs.
km /cum
208.60
Less 1 km initial lead charges
Rs. /cum
31.30 (-)
Net additional lead charges
Rs./ cum
177.30

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges
Rs. for 5 km
83.60
Lead charges for next 10Rs.
km
125
Total lead charges for 15Rs.
km /cum
208.60
Less 1 km initial lead charges
Rs. /cum
31.30 (-)
Net additional lead charges
Rs./ cum
177.30
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area.
For conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the
data without deducting the 50 m initial lead charges

PMW - Work Items


IRR-PMW-1
IRR-PMW-1-1

JUNGLE CLEARANCE :
Clearing thin jungle growth ( more than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same
as directed etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

1000 sqm
Rate
in Rs.

Amount
in Rs.

318

Preliminary and Maintenance Works - Item Unit Rates 2015-16

NIL

0.00
0.00

0.00
0.00
Rs:

0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
200.00
930.00
1130.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
1.10
Add contractor's profit and overhead charges
13.615% 0.10
labour component/unit qty (including contractor's profit)
1.20

0.50
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per
sqm
(A+B+C+D)/1000.0
Rs.

IRR-PMW-1-2

0.00
0.00
1130.00
1130.00
153.85
1283.85
1.30

Clearing thick jungle growth ( less than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same as
directed etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

1000 sqm
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
200.00
1550.00
1750.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
1.80
Add contractor's profit and overhead charges
13.615% 0.20
labour component/unit qty (including contractor's profit)
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

Quantity
0.50
5.00

Rs:
Rs:
Rs:
Rs:

Rate
in Rs.

0.00
0.00
1750.00
1750.00

319

Preliminary and Maintenance Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on


(A+B+C)
13.615% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per
sqm
(A+B+C+D)/1000.0
Rs.

IRR-PMW-1-3

238.26
1988.26
2.00

Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth
including excavation, stacking the materials neatly and levelling the surface etc., complete with
initial lead upto 50 m and all lifts.

DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

18 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
100.00
620.00
720.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
40.00
Add contractor's profit and overhead charges
13.615% 5.40
labour component/unit qty (including contractor's profit)
45.40

0.25
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
18.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.

IRR-PMW-1-4

0.00
0.00
720.00
720.00
98.028
818.03
45.40

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 1.50 m
and upto 3.0 m including excavation, stacking the materials neatly and levelling the area etc.,
complete with initial lead upto 50 m and all lifts.

DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :

Unit

Quantity

NIL

8 Nos.

Rate
in Rs.

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1

Description

Unit

Quantity

NIL

Description

0.00
0.00

Unit

Quantity

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Total hire charges of Machinery


C. LABOUR:
Sl No

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate

Amount

320

Preliminary and Maintenance Works - Item Unit Rates 2015-16

1
2

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
90.00
Add contractor's profit and overhead charges
13.615% 12.25
labour component/unit qty (including contractor's profit)
102.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
8.00 Nos.
Rs:
Rate per each
(A+B+C+D)/8.0
Rs.

IRR-PMW-1-5

0.25
2.00

in Rs.
400.00
310.00
Rs:

Rs:
Rs:
Rs:
Rs:

0.00
0.00
720.00
720.00
98.03
818.00
102.30

Removing stumps, tree roots, roots of bamboo cluster etc., with girth
above 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and levelling
the area etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

5 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
200.00
1240.00
1440.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Day
Day
Total cost of Labour
labour component/unit qty
288.00
Add contractor's profit and overhead charges
13.615% 39.20
labour component/unit qty (including contractor's profit)
327.20

work inspector
mazdoor

0.50
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
5.00 Nos.
Rs:
Rate per each
(A+B+C+D)/5.0
Rs.

IRR-PMW-1-6

in Rs.
100.00
620.00
720.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1440.00
1440.00
196.06
1636.06
327.20

Additional rate for every 0.5 m increase in girth of tree stump / stumps of bamboo cluster
beyond 5 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

7 Nos.

Rate

Amount

321

Preliminary and Maintenance Works - Item Unit Rates 2015-16

in Rs.

NIL

0.00
0.00
Rs:

in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
88.00
271.25
359.25

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
51.30
Add contractor's profit and overhead charges
13.615% 7.00
labour component/unit qty (including contractor's profit)
58.30

0.22
0.88

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

0.00
0.00
359.25
359.25

D. Add for contractor's profit and overheads on


(A+B+C)
13.615% Rs:
Total cost for
7.00 Nos.
Rs:
Rate per each
(A+B+C+D)/7.0
Rs.

IRR-PMW-1-7

48.91
408.16
58.30

Cutting and stacking bamboos excluding removing stumps and roots etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

150 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
200.00
1550.00
1750.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
11.67
Add contractor's profit and overhead charges
13.615% 1.59
labour component/unit qty (including contractor's profit)
13.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

Quantity
0.50
5.00

Rs:
Rs:
Rs:
Rs:

Rate
in Rs.

0.00
0.00
1750.00
1750.00

322

Preliminary and Maintenance Works - Item Unit Rates 2015-16

D. Add for contractor's profit and overheads on


(A+B+C)
13.615% Rs:
Total cost for
150.00 Nos.
Rs:
Rate per each
(A+B+C+D)/150.0
Rs.

IRR-PMW-1-8

238.26
1988.26
13.30

Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal of stumps and
including burning or disposing off the materials as directed with initial lead upto 50 m and all
lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

100 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
200.00
930.00
1130.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
11.30
Add contractor's profit and overhead charges
13.615% 1.50
labour component/unit qty (including contractor's profit)
12.80

0.50
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
100.00 Nos
Rs:
Rate per each
(A+B+C+D)/100.0
Rs.

IRR-PMW-1-9

0.00
0.00
1130.00
1130.00
153.85
1283.85
12.80

Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth excluding
removal of stumps and including burning or disposing off the materials as directed
with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :

Unit

Quantity

NIL

50 Nos

Rate
in Rs.

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1

Description

Unit

Quantity

NIL

Description

0.00
0.00

Unit

Quantity

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Total hire charges of Machinery


C. LABOUR:
Sl No

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate

Amount

323

Preliminary and Maintenance Works - Item Unit Rates 2015-16

1
2

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
22.60
Add contractor's profit and overhead charges
13.615% 3.10
labour component/unit qty (including contractor's profit)
25.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

0.50
3.00

in Rs.
400.00
310.00
Rs:

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1130.00
1130.00

D. Add for contractor's profit and overheads on


(A+B+C)
13.615% Rs:
Total cost for
50.00 Nos
Rs:
Rate per each
(A+B+C+D)/50.0
Rs.

IRR-PMW-1-10

153.85
1283.85
25.70

Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.25
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

14 Nos.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
37.50
0.00
37.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
100.00
930.00
1030.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Day
Day
Total cost of Labour
labour component/unit qty
73.60
Add contractor's profit and overhead charges
13.615% 10.00
labour component/unit qty (including contractor's profit)
83.60

work inspector
mazdoor

0.25
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
14.00 Nos.
Rs:
Rate per each
(A+B+C+D)/14.0
Rs.

IRR-PMW-1-11

in Rs.
200.00
930.00
1130.00

Rs:
Rs:
Rs:
Rs:

37.50
0.00
1030.00
1067.50
145.34
1212.84
86.60

Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit
LS

Quantity
0.25

4 Nos.

Rate
in Rs.
150.00

Amount
in Rs.
37.50

324

Preliminary and Maintenance Works - Item Unit Rates 2015-16

0.00

0.00
Rs:

0.00
37.50

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
100.00
930.00
1030.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
257.50
Add contractor's profit and overhead charges
13.615% 35.10
labour component/unit qty (including contractor's profit)
292.60

0.25
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
4.00 Nos.
Rs:
Rate per each
(A+B+C+D)/4.0
Rs.

IRR-PMW-1-12

37.50
0.00
1030.00
1067.50
145.34
1212.84
303.20

Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.25
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
515.00
Add contractor's profit and overhead charges
13.615% 70.10
labour component/unit qty (including contractor's profit)
585.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
2.00 Nos.
Rs:
Rate per each
(A+B+C+D)/2.0
Rs.

0.25
3.00

Rs:
Rs:
Rs:
Rs:

2 Nos.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
37.50
0.00
37.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
100.00
930.00
1030.00

37.50
0.00
1030.00
1067.50
145.34
1212.84
606.40

325

Preliminary and Maintenance Works - Item Unit Rates 2015-16

IRR-PMW-1-13

Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.25
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

1 No.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
37.50
0.00
37.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
100.00
930.00
1030.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
1030.00
Add contractor's profit and overhead charges
13.615% 140.20
labour component/unit qty (including contractor's profit)
1170.20

0.25
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
1.00 No.
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.

IRR-PMW-1-14

37.50
0.00
1030.00
1067.50
145.34
1212.84
1212.80

Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.50
0.00

Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

work inspector
mazdoor

Unit
Day
Day

Quantity
0.25
5.00

1 Nos.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
75.00
0.00
75.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00

Amount
in Rs.
100.00
1550.00

326

Total cost of Labour


labour component/unit qty
1650.00
Add contractor's profit and overhead charges
13.615% 224.60
labour component/unit qty (including contractor's profit)
1874.60

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
1.00 Nos.
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.

IRR-PMW-1-15

75.00
0.00
1650.00
1725.00
234.86
1959.86
1959.90

Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.15
0.00

Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

1 No

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
22.50
0.00
22.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
40.00
542.50
582.50

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Day
Day
Total cost of Labour
labour component/unit qty
582.50
Add contractor's profit and overhead charges
13.615% 79.30
labour component/unit qty (including contractor's profit)
661.80

work inspector
mazdoor

0.10
1.75

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
1.00 No
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.

IRR-PMW-1-16

1650.00

Rs:
Rs:
Rs:
Rs:

22.50
0.00
582.50
605.00
82.37
687.37
687.40

Cutting and burning or disposing off Apu / Jondu from marshy areas as directed with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :

Unit

NIL

Quantity
0.00
0.00

Total cost of Materials

1000 sqm

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

327

B. MACHINERY:
Sl No

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Description

Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
3720.00
4120.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
4.10
Add contractor's profit and overhead charges
13.615% 0.60
labour component/unit qty (including contractor's profit)
4.70

1.00
12.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/1000.0
Rs.

IRR-PMW-2
IRR-PMW-2-1

0.00
0.00
4120.00
4120.00
560.94
4680.94
4.70

PRELIMINARY WORKS :
Earthwork excavation for trial pits / borrow pits and other investigation works in all kinds of
soil including boulders upto 30 cm dia and disposing off excavated soil as directed with lead
upto 10 m and lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

10 cum

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
200.00
1860.00
2060.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
206.00
Add contractor's profit and overhead charges
13.615% 28.05
labour component/unit qty (including contractor's profit)
234.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/100.0
Rs.

0.50
6.00

Rs:
Rs:
Rs:
Rs:

Rate
in Rs.

0.00
0.00
2060.00
2060.00
280.47
2340.47
234.00

328

Preliminary and Maintenance Works - Item Unit Rates 2015-16

IRR-PMW-2-2

Earthwork excavation for trial pits / borrow pits and other investigation works in soft
rock including disposing off the excavated rock as directed with lead upto 10 m and lift
upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

10 cum

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
200.00
370.00
2325.00
2895.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Crowbarman
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
289.50
Add contractor's profit and overhead charges
13.615% 39.40
labour component/unit qty (including contractor's profit)
328.90

0.50
1.00
7.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/10.0
Rs.
IRR-PMW-2-3

0.00
0.00
2895.00
2895.00
394.15
3289.15
328.90

Conducting geophysical investigation studies by electrical resistivity method in


stages of 5m for sub-surface details such as depth of formations, shear zones, classification
of strata, depth of water table etc., including cost of all materials, equipments, labour,
analysing and reporting the details of field studies conducted etc., complete excluding cost of
transportation arrangements.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Quantity

Sundries ( misc. consumables )

5.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1

Electric resistivity meter


Battery / charging cost etc @

C. LABOUR:
Sl No
1
2

Description

Description

Geophysist / Geologist
Graduate Engineer

Unit

Quantity

Hour

8.00

20%
Total hire charges of Machinery

Unit
Day
Day

Quantity
2.00
1.00

20 Stages
Rate
in Rs.
20.00
0.00
Rs:

Amount
in Rs.
100.00
0.00
100.00

Rate
in Rs.
99.00
Rs:

Amount
in Rs.
792.00
158.40
950.40

Rate
in Rs.
790.00
790.00

Amount
in Rs.
1580.00
790.00

329

3
4

Lab Assistant
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
204.50
Add contractor's profit and overhead charges
13.615% 27.80
labour component/unit qty (including contractor's profit)
232.30

Preliminary and Maintenance Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
20.00 Stages
Rs:
Rate per stage
(A+B+C+D)/20.0
Rs.

IRR-PMW-2-4

480.00
310.00
Rs:

Rs:
Rs:
Rs:
Rs:

100.00
950.40
4090.00
5140.40

480.00
1240.00
4090.00

699.87
5840.27
292.00

Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or inclined
upto 10 degrees to vertical as directed including cost of all materials, machinery, labour, water
charges, reaming, collection of wash samples at suitable intervals, logging and lebelling,
supplying honne wood core box, fixing casing pipes ( excluding cost of casing pipes ) etc.,
complete for depth upto 30 m from surface.
Note: 1. For drilling through over-burden beyond 30 m from surface increase the basic rate per
Rm by 10 percent.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

1
2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries ( samplers etc )

C. LABOUR:
Sl No
1
2
3

particulars

UNIT :
Unit

Quantity

Use rate of casing shoe bit


Rm
Use rate of reamer shell
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

3.00
3.00
3.00
3.00

Quantity

Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

1.00
1.00
2.00
2.00
2.00

Quantity

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
364.10
Add contractor's profit and overhead charges
13.615% 49.60
labour component/unit qty (including contractor's profit)
413.70

Crew for Core drilling machine


Crew for Pump
mazdoor

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.

IRR-PMW-2-5

1.00
4.00

1.00
2.00
2.00

Rs:
Rs:
Rs:
Rs:

3.00 Rm
Rate
in Rs.
116.67
28.61
1.84
259.88
Rs:

Amount
in Rs.
350.00
85.83
5.51
779.63
1220.97

Rate
in Rs.
319.00
243.80
10.20
81.30
20.00
Rs:

Amount
in Rs.
319.00
243.80
20.40
162.60
40.00
785.80

Rate
in Rs.
265.20
103.60
310.00
Rs:

Amount
in Rs.
265.20
207.20
620.00
1092.40

1220.97
785.80
1092.40
3099.17
421.95
3521.12
1173.70

Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit vertical / inclined
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water

330

Preliminary and Maintenance Works - Item Unit Rates 2015-16

charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

Unit

Quantity

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of double tube core barrel
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Unit

3.00
3.00
3.00
3.00
3.00

Quantity

Hour
8.00
Hour
8.00
Hour
16.00
Hour
16.00
LS
5.00
Total hire charges of Machinery

Unit

Quantity

Crew for Core drilling machine


Crew for Pump
mazdoor

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
1466.40
Add contractor's profit and overhead charges
13.615% 199.70
labour component/unit qty (including contractor's profit)
1666.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

8.00
16.00
2.00

Rs:
Rs:
Rs:
Rs:

3.00 Rm

Rate
in Rs.
848.00
85.83
228.40
24.49
584.72
Rs:

Amount
in Rs.
2544.00
257.50
685.20
73.46
1754.16
5314.31

Rate
in Rs.
319.00
243.80
10.20
81.30
20.00
Rs:

Amount
in Rs.
2552.00
1950.40
163.20
1300.80
100.00
6066.40

Rate
in Rs.
265.20
103.60
310.00
Rs:

Amount
in Rs.
2121.60
1657.60
620.00
4399.20

5314.31
6066.40
4399.20
15779.91
2148.44
17928.35
5976.10

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic
rate per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate per Rm by 40 percent.

IRR-PMW-2-5-A
New Item 2014-155
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m from
surface for Primary and Secondary Holes
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Har
DATA:

For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @
Rs:
12720.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each

Rs:
10.57
Rs:
Rs:

12720.00
m
1203.41
5150.00

331

Life of reamer shell in all types of rock (other than hard rock)
Use rate of reamer shell per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2226.00 / Rm
Life of extension rods
Use rate of 16.5 m length extension rods
( cost / life )
Data:

Preliminary and Maintenance Works - Item Unit Rates 2015-16

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
4

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

UNIT :

Unit

Quantity

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of extension rod set 16.5 m
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

Description

Unit

3.00
3.00
3.00

Quantity

Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

4.78
4.78
9.55
9.55
2.99

Quantity

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
875.00
Add contractor's profit and overhead charges
13.615% 119.10
labour component/unit qty (including contractor's profit)
994.10

Crew for Core drilling machine


Crew for Pump
mazdoor

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
13.615% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

100
Rs:
Rs:
2500
Rs:

4.78
9.55
1.19

Rs:
Rs:
Rs:
Rs:

m
51.50
36729.00
m
14.69

3.00 Rm

Rate
in Rs.
1203.41
51.50
14.69
Rs:

Amount
in Rs.
3610.22
154.50
44.07
3808.79

Rate
in Rs.
319.00
243.80
10.20
81.30
20.00
Rs:

Amount
in Rs.
1523.54
1164.39
97.43
776.58
59.80
3621.74

Rate
in Rs.
265.20
103.60
310.00
Rs:

Amount
in Rs.
1266.60
989.38
368.90
2624.88

3808.79
3621.74
2624.88
10055.41
1369.04
11424.45
3808.20

1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.

IRR-PMW-2-5-B
New Item 2014-156
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface
for Test Holes
DATA:

For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @
Rs:
12720.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:

Rs:
10.57
Rs:
Rs:
100

12720.00
m
1203.41
5150.00
m

332

Use rate of reamer shell per m drilling


Cost of double core barrel @
Rs:
Life of double tube core barrel
Use rate of double tube core barrel per m drilling
Cost of 16.5 m extension rod @
Rs:
Life of extension rods
Use rate of 16.5 m length extension rods
Honne wood core box 1.5 x 0.32 x 0.12 m
Honne wood 0.033 cum @
Rs:
Add for fixtures and painting @
Add for labour charges @
Cost of one box for storing
Use rate of core box per m drilling
Data:

( cost / life )
13704.00 / Each

Preliminary and Maintenance Works - Item Unit Rates 2015-16

:
( cost / life )
2226.00 / Rm
:
( cost / life )
56700.00 / cum
10%
15%
4 m samples

1
2
3
4
5

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

UNIT :

Unit

Quantity

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of double tube core barrel
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

Description

Unit

3.00
3.00
3.00
3.00
3.00

Quantity

Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

Crew for Core drilling machine


Crew for Pump
mazdoor

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
13.615% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.

IRR-PMW-2-6

4.78
4.78
9.55
9.55
2.99

Quantity

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
875.40
Add contractor's profit and overhead charges
13.615% 119.20
labour component/unit qty (including contractor's profit)
994.60

NOTE:

51.50
13704.00
m
137.04
36729.00
m
14.69

Rs:
Rs:
Rs:
Rs:
Rs:

RATE ANALYSIS
A. MATERIALS:
Sl No

Rs:
Rs:
100
Rs:
Rs:
2500
Rs:

4.78
9.55
1.19

Rs:
Rs:
Rs:
Rs:

1871.10
187.11
280.67
2338.88
584.72

3.00 Rm

Rate
in Rs.
1203.41
51.50
137.04
14.69
584.72
Rs:

Amount
in Rs.
3610.22
154.50
411.12
44.07
1754.16
5974.07

Rate
in Rs.
319.00
243.80
10.20
81.30
20.00
Rs:

Amount
in Rs.
1523.54
1164.39
97.43
776.58
59.80
3621.74

Rate
in Rs.
265.20
103.60
310.00
Rs:

Amount
in Rs.
1266.60
989.59
370.14
2626.32

5974.07
3621.74
2626.32
12222.13
1664.04
13886.18
4628.70

1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.

Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical / inclined
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water
charges,collection of core samples,logging, lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.

Data:

RATE ANALYSIS

UNIT :

3.00 Rm

A. MATERIALS:

333

Sl No
1
2
3
4
5

particulars

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Quantity

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of double tube core barrel
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

Unit

Description

Unit

3.00
3.00
3.00
3.00
3.00

Quantity

Hour
8.00
Hour
8.00
Hour
16.00
Hour
16.00
LS
5.00
Total hire charges of Machinery

Unit

Quantity

Crew for Core drilling machine


Crew for Pump
mazdoor

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
1466.40
Add contractor's profit and overhead charges
13.615% 199.70
labour component/unit qty (including contractor's profit)
1666.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

8.00
16.00
2.00

Rate
in Rs.
706.67
85.83
228.40
24.49
584.72
Rs:

Amount
in Rs.
2120.00
257.50
685.20
73.46
1754.16
4890.31

Rate
in Rs.
319.00
243.80
10.20
81.30
20.00
Rs:

Amount
in Rs.
2552.00
1950.40
163.20
1300.80
100.00
6066.40

Rate
in Rs.
265.20
103.60
310.00
Rs:

Amount
in Rs.
2121.60
1657.60
620.00
4399.20

Rs:
Rs:
Rs:
Rs:

D. Add for contractor's profit and overheads on


(A+B+C)
13.615% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

4890.31
6066.40
4399.20
15355.91
2090.71
17446.62
5815.50

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the
basic rate for drilling upto 30 m from surface by 25 percent per Rm.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate for drilling upto 30 m from surface by 40 percent per Rm.

IRR-PMW-2-6-A
New Item 2014-157
Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m

DATA:

Data:

For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of BX diamond core bit @
Rs:
10600.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:
Use rate of reamer shell per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2226.00 / Rm
Life of extension rods
:
Use rate of 16.5 m length extension rods
( cost / life )
RATE ANALYSIS

UNIT :

Rs:
10.57
Rs:
Rs:
100
Rs:
Rs:
2500
Rs:

10600.00
m
1002.84
5150.00
m
51.50
36729.00
m
14.69

3.00 Rm

334

Preliminary and Maintenance Works - Item Unit Rates 2015-16

A. MATERIALS:
Sl No
1
2
4

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

Unit

Quantity

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of extension rod set 16.5 m
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

Description

Unit

3.00
3.00
3.00

Quantity

Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

Quantity

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
875.00
Add contractor's profit and overhead charges
13.615% 119.10
labour component/unit qty (including contractor's profit)
994.10

Crew for Core drilling machine


Crew for Pump
mazdoor

4.78
9.55
1.19

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
13.615% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

IRR-PMW-2-7

4.78
4.78
9.55
9.55
2.99

Rate
in Rs.
1002.84
51.50
14.69
Rs:

Amount
in Rs.
3008.51
154.50
44.07
3207.09

Rate
in Rs.
319.00
243.80
10.20
81.30
20.00
Rs:

Amount
in Rs.
1523.54
1164.39
97.43
776.58
59.80
3621.74

Rate
in Rs.
265.20
103.60
310.00
Rs:

Amount
in Rs.
1266.60
989.38
368.90
2624.88

3207.09
3621.74
2624.88
9453.71
1287.12
10740.83
3580.30

1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.

Providing and fixing 20 x 20 x 75 cm size roughly dressed boundary / demarcation /


chainage / arrow stones including cost of all materials, labour, engraving marks, fixing in
position, murum filling etc., complete with lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Rough stone 20x20x75 cm


Murrum

B. MACHINERY:
Sl No
1

Description

UNIT :
Unit
Each
cum
Total cost of Materials

Unit

Quantity
18.00
1.00

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

work inspector
Stone chiseller Cl- I
mazdoor

Unit
Day
Day
Day

Quantity
1.00
1.00
3.00

18 Nos.
Rate
in Rs.
23.00
115.00
Rs:

Amount
in Rs.
414.00
115.00
529.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
415.00
310.00

Amount
in Rs.
400.00
415.00
930.00

335

Total cost of Labour


labour component/unit qty
96.90
Add contractor's profit and overhead charges
13.615% 13.20
labour component/unit qty (including contractor's profit)
110.10

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
18.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.

IRR-PMW-2-8

529.00
0.00
1745.00
2274.00
309.61
2583.61
143.50

Providing and fixing 20 x 20 x 75 cm size temporary bench mark stone in CC 1 : 4 : 8


using 40 mm down size graded coarse aggregate including cost of all materials, labour,
dressing top surface, engraving BM data etc.,complete with lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Rough stone 20x20x75 cm


Cement for CC & top finishing
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Sand (Un-Screened )

B. MACHINERY:
Sl No
1

Description

UNIT :
Unit
Each
kg
cum
cum
cum
cum
Total cost of Materials

Unit

Quantity
10.00
91.00
0.25
0.15
0.10
0.25

Quantity

NIL

10 Nos.
Rate
in Rs.
23.00
6.30
1145.00
1210.00
875.00
560.00
Rs:

Amount
in Rs.
230.00
573.30
286.25
181.50
87.50
140.00
1498.55

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
415.00
310.00
Rs:

Amount
in Rs.
400.00
1245.00
1240.00
2885.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

work inspector
Stone chiseller Cl- I
mazdoor

Unit

Day
Day
Day
Total cost of Labour
labour component/unit qty
288.50
Add contractor's profit and overhead charges
13.615% 39.30
labour component/unit qty (including contractor's profit)
327.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Quantity
1.00
3.00
4.00

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
10.00 Nos.
Rs:
Rate per each
(A+B+C+D)/10.0
Rs.
NOTE: For providing 30 cm thick compacted murum bed in B.C soil area including
additional excavation for thickness of murum bedding add per
Each

IRR-PMW-2-9

1745.00

1498.55
0.00
2885.00
4383.55
596.82
4980.37
498.00
Rs:

4.00

Providing and fixing 20 x 20 x 75 cm size permanent bench mark stone in CC 1 :3 : 6


block of size 90 x 90 x 120 cm using 40 mm down size graded coarse aggregate and providing
35 cm thick 30 cm high UCR masonry in CM 1 : 5 proportion protective wall alround the BM
stone, including cost of all materials, labour, dressing top surface of stone, engraving BM data
on top surface, excavation, finishing, curing etc., complete with lead upto 50 m and all lifts.

336

Data:

Preliminary and Maintenance Works - Item Unit Rates 2015-16

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

4
5
6

particulars

Rough stone 20x20x75 cm


Cement
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Rubble stone at quarry
Stone chips at quarry
Sand (Un-Screened )

B. MACHINERY:
Sl No

Description

UNIT :

Unit

Quantity

Each
kg
cum
cum
cum
cum
cum
cum
Total cost of Materials

Unit

1.00
262.00
0.50
0.30
0.20
0.25
0.04
0.60

Quantity

NIL

1 No.

Rate
in Rs.
23.00
6.30
1145.00
1210.00
875.00
330.00
360.00
560.00
Rs:

Amount
in Rs.
23.00
1650.60
572.50
363.00
175.00
82.50
14.40
336.00
3217.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
415.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
207.50
370.00
1550.00
2527.50

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

Description

Unit

Quantity

work inspector
Stone chiseller Cl- I
Mason Cl- II
mazdoor

Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
2527.50
Add contractor's profit and overhead charges
13.615% 344.10
labour component/unit qty (including contractor's profit)
2871.60

1.00
0.50
1.00
5.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
1.00 No.
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.
IRR-PMW-3
IRR-PMW-3-1

3217.00
0.00
2527.50
5744.50
782.11
6526.61
6526.60

MAINTENANCE WORKS :
Removing dry stone rock-toe / rivetment and filter layers below rock-toe/ rivetment
including stacking all materials separately as directed with initial lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

105 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00

Amount
in Rs.
400.00
2220.00
14880.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

work inspector
Mason Cl- II
mazdoor

Unit
Day
Day
Day

Quantity
1.00
6.00
48.00

Rate
in Rs.

337

Total cost of Labour


labour component/unit qty
166.70
Add contractor's profit and overhead charges
13.615% 22.70
labour component/unit qty (including contractor's profit)
189.40

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
105.00 cum
Rs:
Rate per cum
(A+B+C+D)/105.0
Rs.

IRR-PMW-3-2

0.00
0.00
17500.00
17500.00
2382.63
19882.63
189.40

Re-constructing 60 cm thick hand packed rough stone revetment with through


stones at 1.5 m c / c over a backing of 45 cm thick graded filter media consisting of sand,
10 mm and 40 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm thick
each using sand from approved quarry and stones and filter aggregates obtained from
revetment removed for re-construction including cost of all machinery, labour, laying filter and
stones to specified slopes, wedging with chips, finishing etc. complete with initial
lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

particulars

UNIT :
Unit

Quantity

Sand (Un-Screened ) ( from quarry)


cum
Coarse aggregate 10 mm (available)
cum
Coarse aggr. 40-20 mm ( available)
cum
Stone chips ( available )
cum
Rough stones ( available )
cum
Through stones ( available )
Nos
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

15.30
15.30
15.30
9.00
57.60
44.00

Quantity

NIL

100 sqm
Rate
in Rs.
560.00
0.00
0.00
0.00
0.00
0.00
Rs:

Amount
in Rs.
8568.00
0.00
0.00
0.00
0.00
0.00
8568.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
1850.00
10230.00
12480.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

Day
Day
Day
Total cost of Labour
labour component/unit qty
124.80
Add contractor's profit and overhead charges
13.615% 17.00
labour component/unit qty (including contractor's profit)
141.80

work inspector
Mason Cl- II
mazdoor

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
100.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-3

17500.00

1.00
5.00
33.00

Rs:
Rs:
Rs:
Rs:

8568.00
0.00
12480.00
21048.00
2865.69
23913.69
239.10

Re-constructing dry rubble rock-toe and filter media for rock-toe consisting of
sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm
thick each using sand from approved quarry and stones and filter aggregates obtained from
rock-toe removed for re-construction including cost of all machinery, labour, laying filter and

338

Preliminary and Maintenance Works - Item Unit Rates 2015-16

stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto
50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

particulars

UNIT :
Unit

Quantity

Rubble ( available )
cum
Stone chips ( available )
cum
80-20 mm filter ( available )
cum
20 mm down filter ( available )
cum
Sand (Un-Screened) ( fresh from quarry )
cum
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

100 cum
Rate
in Rs.

58.20
8.70
19.40
12.10
9.80

Quantity

NIL

0.00
0.00
0.00
0.00
560.00
Rs:

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
2590.00
14880.00
17870.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Mason Cl- II
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
178.70
Add contractor's profit and overhead charges
13.615% 24.30
labour component/unit qty (including contractor's profit)
203.00

1.00
7.00
48.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
100.00 cum
Rs:
Rate per cum
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-4

Amount
in Rs.
0.00
0.00
0.00
0.00
5488.00
5488.00

5488.00
0.00
17870.00
23358.00
3180.19
26538.19
265.40

Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC / Other types
of slab lining set in CM 1 : 3 including flush cement mortar pointing in CM 1 : 3 with
lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Cement 43 Gr
Sand (Screened )

B. MACHINERY:
Sl No

Description

UNIT :
Unit
kg
cum
Total cost of Materials

Unit

Quantity
101.00
0.21

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

work inspector
Mason Class I
mazdoor

Unit
Day
Day
Day

Quantity
1.00
4.00
6.00

100 sqm
Rate
in Rs.
6.30
760.00
Rs:

Rate
in Rs.

Amount
in Rs.
636.30
159.60
795.90

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
415.00
310.00

Amount
in Rs.
400.00
1660.00
1860.00

339

Cartman with Double Bullock cart for water


Day
Total cost of Labour
labour component/unit qty
43.50
Add contractor's profit and overhead charges
13.615% 5.90
labour component/unit qty (including contractor's profit)
49.40

Preliminary and Maintenance Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
100.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-5

1.00

425.00
Rs:

Rs:
Rs:
Rs:
Rs:

795.90
0.00
4345.00
5140.90
699.93
5840.83
58.40

Removing and resetting disturbed dry rubble / khandki stone pitching 25 to 45 cm


thick including packing, wedging, finishing etc., complete with all leads and lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

100 sqm
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
370.00
310.00
Rs:

Amount
in Rs.
400.00
2220.00
1860.00
4480.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

Day
Day
Day
Total cost of Labour
labour component/unit qty
44.80
Add contractor's profit and overhead charges
13.615% 6.10
labour component/unit qty (including contractor's profit)
50.90

work inspector
Mason Class II
mazdoor

1.00
6.00
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
100.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-6

425.00
4345.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
4480.00
4480.00
609.95
5089.95
50.90

Removing and refixing disturbed chainage / demarcation / hectometre / guard stones


including excavation, back filling etc., complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00
0.00

Total cost of Materials

18 Nos.
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

340

B. MACHINERY:
Sl No

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Description

Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
620.00
1020.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
56.67
Add contractor's profit and overhead charges
13.615% 7.72
labour component/unit qty (including contractor's profit)
64.40

1.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
18.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.

IRR-PMW-3-7

0.00
0.00
1020.00
1020.00
138.87
1158.87
64.40

Removing and refixing disturbed km stone / sign board / hecto-metre stone etc., including
excavation, back filling with available stuff after refixing, forming base platform of size 90 x 90 x
7.5 cm including watering, ramming etc complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

8 Nos.
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
620.00
1020.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
127.50
Add contractor's profit and overhead charges
13.615% 17.36
labour component/unit qty (including contractor's profit)
144.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
8.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.
IRR-PMW-3-8

1.00
2.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1020.00
1020.00
138.87
1158.87
144.90

Providing impervious hearting for breached / damaged portion of embankment


with soil from approved borrow areas in layers of 10 to 15 cm before compaction including

341

Preliminary and Maintenance Works - Item Unit Rates 2015-16

cost of all materials, machinery, labour, all operations such as collection of soil, sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or
by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Quantity

NIL

480 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
8577.50
3126.50
8024.80
3900.80
14294.40
9830.40
20.40
162.60
1610.00
1228.80
8053.20
6338.40
40.00
65207.80

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
884.00
1768.00
5305.60
310.80
829.00
1469.40
800.00
1240.00
12606.80

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Description

Unit

Quantity

Hour
5.00
Hour
5.00
Hour
8.00
Hour
8.00
Hour
32.00
Hour
32.00
Hour
2.00
Hour
2.00
Hour
4.00
Hour
4.00
Hour
6.00
Hour
6.00
LS
2.00
Total hire charges of Machinery

Unit

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
26.30
Add contractor's profit and overhead charges
13.615% 3.60
labour component/unit qty (including contractor's profit)
29.90

4.00
8.00
32.00
3.00
5.00
6.00
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
480.00 cum
Rs:
Rate per cum
(A+B+C+D)/480.0
Rs.

IRR-PMW-3-9

Rs:
Rs:
Rs:
Rs:

0.00
65207.80
12606.80
77814.60
10594.46
88409.06
184.20

Providing pervious/semi-pervious casing for breached / damaged portion of


embankment with soil from approved borrow areas in layers of 10 to 15 cm before
compaction including cost of all materials, machinery, labour, all operations such as collection
of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering,
compacting each layer to density control of not less than 98 percent or as stipulated by rolling
or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

325 cum
Rate
in Rs.

Amount
in Rs.

342

Preliminary and Maintenance Works - Item Unit Rates 2015-16

NIL

0.00
0.00

0.00
0.00
Rs:

0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs.
6004.25
2188.55
8024.80
3900.80
10720.80
7372.80
15.30
121.95
1207.50
921.60
5368.80
4225.60
40.00
50112.75

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
773.50
1768.00
3979.20
155.40
497.40
979.60
800.00
1240.00
10193.10

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Description

Unit

Quantity

Hour
3.50
Hour
3.50
Hour
8.00
Hour
8.00
Hour
24.00
Hour
24.00
Hour
1.50
Hour
1.50
Hour
3.00
Hour
3.00
Hour
4.00
Hour
4.00
LS
2.00
Total hire charges of Machinery

Unit

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
31.40
Add contractor's profit and overhead charges
13.615% 4.30
labour component/unit qty (including contractor's profit)
35.70

3.50
8.00
24.00
1.50
3.00
4.00
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
325.00 cum
Rs:
Rate per cum
(A+B+C+D)/325.0
Rs.

IRR-PMW-3-10

0.00
50112.75
10193.10
60305.85
8210.64
68516.49
210.80

Providing impervious hearting for breached / damaged portion of embankment with


soil from approved dump areas in layers of 10 to 15 cm before compaction including cost
of all materials, machinery, labour, all operations such as collection of soil,sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Angle dozer
Fuel / Energy charges

Unit
Hour
Hour

Quantity
4.00
4.00

612 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30

Amount
in Rs.
6862.00
2501.20

343

2
3
4
5
6
7

Shovel 0.50 cum capacity


Fuel / Energy charges
Tippers 5.00 cum capacity 5 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Hour
8.00
Hour
8.00
Hour
40.00
Hour
40.00
Hour
4.00
Hour
4.00
Hour
7.00
Hour
7.00
Hour
7.50
Hour
7.50
LS
2.00
Total hire charges of Machinery

Unit

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
25.10
Add contractor's profit and overhead charges
13.615% 3.40
labour component/unit qty (including contractor's profit)
28.50

4.00
8.00
40.00
4.00
7.00
7.50
2.00
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
612.00 cum
Rs:
Rate per cum
(A+B+C+D)/612.0
Rs.

IRR-PMW-3-11

Rs:
Rs:
Rs:
Rs:

1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20
1056.40
20.00
Rs:

8024.80
3900.80
17868.00
12288.00
40.80
325.20
2817.50
2150.40
10066.50
7923.00
40.00
74808.20

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
884.00
1768.00
6632.00
414.40
1160.60
1836.75
800.00
1860.00
15355.75

0.00
74808.20
15355.75
90163.95
12275.82
102439.77
167.40

Providing pervious /semi-pervious casing for breached /damaged portion of embankment


with soil from approved dump areas in layers of 10 to 15 cm before compaction including
cost of all materials, machinery, labour, all operations such as collection of soil, sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
3.00
3.00
8.00
8.00
32.00
32.00
3.00
3.00
6.00
6.00
5.50

440 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1003.10
487.60
446.70
307.20
10.20
81.30
402.50
307.20
1342.20

Amount
in Rs.
5146.50
1875.90
8024.80
3900.80
14294.40
9830.40
30.60
243.90
2415.00
1843.20
7382.10

344

Fuel / Energy charges


Sundries

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Hour
5.50
LS
2.00
Total hire charges of Machinery

Unit

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
29.70
Add contractor's profit and overhead charges
13.615% 4.00
labour component/unit qty (including contractor's profit)
33.70

3.00
8.00
32.00
3.00
6.00
5.50
2.00
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
440.00 cum
Rs:
Rate per cum
(A+B+C+D)/440.0
Rs.

IRR-PMW-3-12

1056.40
20.00
Rs:

5810.20
40.00
60837.80

Rate
in Rs.
221.00
221.00
165.80
103.60
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs.
663.00
1768.00
5305.60
310.80
994.80
1346.95
800.00
1860.00
13049.15

0.00
60837.80
13049.15
73886.95
10059.71
83946.66
190.80

Repairing rain cuts / resectioning canal slopes to required lines and grades as directed
using available soil including dressing, clod breaking, packing, tamping etc., complete with
all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

1000 sqm
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
400.00
310.00
Rs:

Amount
in Rs.
400.00
2480.00
2880.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
2.88
Add contractor's profit and overhead charges
13.615% 0.39
labour component/unit qty (including contractor's profit)
3.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/1000.0
Rs.

1.00
8.00

Rs:
Rs:
Rs:
Rs:

Rate
in Rs.

0.00
0.00
2880.00
2880.00
392.11
3272.11
3.30

345

Preliminary and Maintenance Works - Item Unit Rates 2015-16

IRR-PMW-3-13

Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing / brushing


including chiselling and removing leached lime deposit and disposing off all the waste material
out side adits in specified location etc., complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Wire brush
Coir brush
Sundries ( brooms, gloves etc )

B. MACHINERY:
Sl No

Description

UNIT :
Unit

Quantity

Each
Each
LS
Total cost of Materials

Unit

5.00
10.00
2.00

Quantity

NIL

100 Rm
Rate
in Rs.
41.00
40.00
20.00
Rs:

Amount
in Rs.
205.00
400.00
40.00
645.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
310.00
Rs:

Amount
in Rs.
740.00
1860.00
2600.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Chiseller Cl II
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
26.00
Add contractor's profit and overhead charges
13.615% 3.50
labour component/unit qty (including contractor's profit)
29.50

2.00
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
100.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-14

645.00
0.00
2600.00
3245.00
441.81
3686.81
36.90

Cleaning dam parapet inner face and top using oxalic acid and water by scrubbing /
brushing and washing to remove all surface coatings etc., complete .

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

particulars

Oxalic acid
Wire brush
Coir brush
Sundries ( brooms, gloves etc )

B. MACHINERY:
Sl No
1

Description

UNIT :
Unit
ltr
Each
Each
LS
Total cost of Materials

Unit

Quantity
5.00
5.00
10.00
2.00

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1

mazdoor

Description

Unit
Day
Total cost of Labour

Quantity
6.00

100 Rm
Rate
in Rs.
80.00
41.00
40.00
20.00
Rs:

Amount
in Rs.
400.00
205.00
400.00
40.00
1045.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1860.00
1860.00

346

labour component/unit qty


18.60
Add contractor's profit and overhead charges
13.615% 2.50
labour component/unit qty (including contractor's profit)
21.10

Preliminary and Maintenance Works - Item Unit Rates 2015-16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
100.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-20

1045.00
0.00
1860.00
2905.00
395.52
3300.52
33.00

Excavation and removal of silt and silt mixed with sand from canal bed in dry condition
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Quantity

NIL

10 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1240.00
1240.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1

Description

Unit

Quantity

mazdoor

Day
Total cost of Labour
labour component/unit qty
124.00
Add contractor's profit and overhead charges
13.615% 16.90
labour component/unit qty (including contractor's profit)
140.90

4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/10.0
Rs.

IRR-PMW-3-21

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1240.00
1240.00
168.83
1408.83
140.90

Excavation and removal of silt or silt mixed with sand in slussy condition from canal bed
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity

12 cum
Rate
in Rs.

0.00
0.00

0.00
0.00
Rs:

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate

Amount
in Rs.
0.00
0.00
0.00

Amount

347

Preliminary and Maintenance Works - Item Unit Rates 2015-16

in Rs.

NIL

0.00
0.00
Rs:

in Rs.
0.00
0.00
0.00

Rate
in Rs.
310.00
Rs:

Amount
in Rs.
1860.00
1860.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1

Description

Unit

Quantity

mazdoor

Day
Total cost of Labour
labour component/unit qty
155.00
Add contractor's profit and overhead charges
13.615% 21.10
labour component/unit qty (including contractor's profit)
176.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
13.615% Rs:
Total cost for
12.00 cum
Rs:
Rate per cum
(A+B+C+D)/12.0
Rs.

6.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1860.00
1860.00
253.24
2113.24
176.10

Providing homogeneous embankment using soil from approved borrow


area in layers of 25 to 30 cm before compaction including cost of all
(For Minor Works) materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil in layer of specified thickness, breaking clods,
sectioning,etc.,complete with initial lead upto 1 km and all lifts.
IRR-PMW-3-22

New Item5 - 2010-11

A. MATERIALS:
Sl No
Particulars
1

NIL

Total cost of Materials


B. MACHINERY:
Sl No
Description
1
2
3

RATE ANALYSIS
Unit:
Unit
Quantity

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 5 Nos.
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

0.00
0.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour

Unit

Quantity
2.70
2.70
8.00
8.00
40.00
40.00

Quantity

1
2
3
4
5

Crew for Dozer


Hour
2.70
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
40.00
work inspector
Day
1.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
12.40
Add contractor's profit and overhead charges
13.615% 1.70
labour component/unit qty (including contractor's profit)
14.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost for
807.00 cum
Rate per cum
(A+B+C+D)/807

807.00
Rate
in Rs.
0.00
0.00
Rs:

cum
Amount
in Rs
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
1706.60
893.90
446.70
307.20
Rs:

Amount
in Rs
4631.85
1688.31
13652.80
7151.20
17868.00
12288.00
57280.16

Rate
in Rs.
221.00
221.00
165.80
400.00
310.00
Rs:

Amount
in Rs
596.70
1768.00
6632.00
400.00
620.00
10016.70

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
57280.16
10016.70
67296.86
9162.47
76459.33
94.70

348

Providing homogeneous embankment using soil from approved borrow


New Item6 - 2010-11 area in layers of 25 to 30 cm before compaction including cost of all
(For Minor Works) materials, machinery, labour, all operations such as watering, compacting
to density control of not less than 95 percent or as stipulated using
8T roller etc., complete with initial lead upto 1 km and all lifts.
IRR-PMW-3-23

A. MATERIALS:
Sl No
Particulars
1

NIL

Total cost of Materials


B. MACHINERY:
Sl No
Description
1
2
3
4
5

RATE ANALYSIS
UNIT :
Unit
Quantity

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

0.00
0.00

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

1
4
5
6
7
8

2.70
2.70
4.00
4.00
8.00
8.00
6.40
6.40
2.00

Quantity

Crew for Dozer


Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
6.00
Add contractor's profit and overhead charges
13.615% 0.80
labour component/unit qty (including contractor's profit)
6.80

2.70
4.00
8.00
6.40
1.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
13.615%
Total cost
for
807.00 cum
Rate per cum
(A+B+C+D)/807
IRR-PMW-3-24

Preliminary and Maintenance Works - Item Unit Rates 2015-16

807.00
Rate
in Rs.
0.00
0.00
Rs:

cum
Amount
in Rs
0.00
0.00
0.00

Rate
in Rs.
1715.50
625.30
3.00
38.50
402.50
307.20
1342.20
1056.40
20.00
Rs:

Amount
in Rs
4631.85
1688.31
12.00
154.00
3220.00
2457.60
8590.08
6760.96
40.00
27554.80

Rate
in Rs.
221.00
77.70
165.80
244.90
400.00
310.00
Rs:

Amount
in Rs
596.70
310.80
1326.40
1567.36
400.00
620.00
4821.26

Rs:
Rs:
Rs:
Rs:
Rs.

0.00
27554.80
4821.26
32376.06
4408

Rs: 36784.06
Rs: 45.60

Providing homogeneous embankment using soil from approved borrow

New Item 7 - 2010-11 area in layers of 25 to 30 cm before compaction including cost of all

materials, machinery, labour, all operations such as compacting


to density control of not less than 90 percent or as stipulated using
2T roller etc., complete with initial lead upto 1 km and all lifts.

A. MATERIALS:
Sl No
Particulars
1

NIL

Total cost of Materials


B. MACHINERY:
Sl No
Description
1
2

Tractor with 2T Roller


Sundries
Total hire charges of Machinery

RATE ANALYSIS
UNIT :
807.00 cum
Unit
Quantity
Rate
Amount
in Rs.
in Rs
0.00
0.00 0.00
0.00
0.00 0.00
Rs: 0.00
Unit
Hour
LS

Quantity
10.00
2.00

Rate
Amount
in Rs.
in Rs
345.00 3450.00
20.00 40.00
Rs: 3490.00

349

Preliminary and Maintenance Works - Item Unit Rates 2015-16

C. LABOUR:
Sl No
Description

Unit

Quantity

Rate
Amount
in Rs.
in Rs
400.00 200.00
310.00 620.00
Rs: 820.00

1
2

work inspector
Day
0.50
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
1.00
Add contractor's profit and overhead charges
13.615% 0.10
labour component/unit qty (including contractor's profit)
1.10
ABSTRAC
T:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on
13.615%
Total cost for
807.00 cum
Rate per cum
(A+B+C+D)/807
IRR-PMW-3-25

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
3490.00
820.00
4310.00
586.8065
4896.81
6.10

Weed Removal by Manual Means

(New Item 2012-13-3)

IRR-PMW-3-25(a) Removal of Water Hyacinth up to 30 cm thick


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit

Quantity
0

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Total Cost of Materials


B. MACHINERY
Sl. No.
1

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity Rate in Rs. Amount in Rs.


3.5
400.00
1400
28
310.00
8680
Rs.
10080.00

C. LABOUR
Sl. No.
1
2

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
10080.00
10080.00
1372.39
11452.39
5.7

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm

13.615%
2000 Sqm
(A+B+C+D)/2000

IRR-PMW-3-25(b) Removal of Water Hyacinth beyond 30 cm thick


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit

Quantity
0

Total Cost of Materials

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

B. MACHINERY
Sl. No.
1

Description
NIL

Unit

Quantity
0

Rate in Rs. Amount in Rs.


0
0

350

Preliminary and Maintenance Works - Item Unit Rates 2015-16

Total hire charges of Machinery

Rs.

0.00

C. LABOUR
Sl. No.
1
2

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity
5
38

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rate in Rs. Amount in Rs.


400.00
2000
310.00
11780
Rs.
13780.00

Rs.
Rs.
Rs.

0.00
0.00
13780.00
13780.00
1876.15
15656.15
7.8

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(c)

13.615%
2000 Sqm
(A+B+C+D)/2000

Clearing Alchi Tilla


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit

Quantity
0

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

3
26

Rate in Rs. Amount in Rs.


400.00
1200
310.00
8060
Rs.
9260.00

Total Cost of Materials


B. MACHINERY
Sl. No.
1

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity

C. LABOUR
Sl. No.
1
2

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
9260.00
9260.00
1260.75
10520.75
5.3

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm

13.615%
2000 Sqm
(A+B+C+D)/2000

IRR-PMW-3-25(d) Removal of Jammu


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit

Quantity
0

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Total Cost of Materials


B. MACHINERY
Sl. No.
1

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Description
Work Inspector

Quantity Rate in Rs. Amount in Rs.


2.5
400.00
1000

C. LABOUR
Sl. No.
1

Unit
Day

351

Mazdoor

Day

22

Total Cost of Labour

Preliminary and Maintenance Works - Item Unit Rates 2015-16

310.00

Rs.

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
7820.00
7820.00
1064.69
8884.69
4.4

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm

6820
7820.00

13.615%
2000 Sqm
(A+B+C+D)/2000

IRR-PMW-3-25(e) Removal of Imponea, Cornea


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit

Quantity
0

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

3
26

Rate in Rs. Amount in Rs.


400.00
1200
310.00
8060
Rs.
9260.00

Total Cost of Materials


B. MACHINERY
Sl. No.
1

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity

C. LABOUR
Sl. No.
1
2

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
9260.00
9260.00
1260.75
10520.75
5.3

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(f)

13.615%
2000 Sqm
(A+B+C+D)/2000

Removal of Natchu, goobi, thooti, etc.


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit

Quantity
0

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Rate in Rs. Amount in Rs.


0
0
Rs.
0.00

Total Cost of Materials


B. MACHINERY
Sl. No.
1

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity Rate in Rs. Amount in Rs.


1.2
400.00
480
8
310.00
2480
Rs.
2960.00

C. LABOUR
Sl. No.
1
2

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY

Rs.
Rs.

0.00
0.00

352

Preliminary and Maintenance Works - Item Unit Rates 2015-16

C.COST OF LABOUR

Rs.

2960.00
2960.00
403.00
3363.00
1.7

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm

13.615%
2000 Sqm
(A+B+C+D)/2000

IRR-PMW-3-26
New Item 2014-158
PAINTING OF SLUICES FOR MAINTENANCE WORKS
Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners

and removing dust. After cleaniong, applying primary coat with one coat of Zinc rich
epoxy primer to a thickness of 100 microns, followed by finishing coats 2 coats with
Coal tar epoxy with material, labour, and all accessories with all leads and lifts.
Data:
A. Materials

Rate Analysis
Sl. No.
1
2
3
4
5
6
7

Particulars
Rust Cleaner/ Inhibitor
Zinc rich epoxy primer
Thinner@10%
Coal Tar epoxy paint
Thinner@10%
Wire Brush
Sundries (brushes, Ladders,
platforms)

Unit:
Unit
ltr
ltr
ltr
ltr
ltr
ltr

Quantity
13
14
1.4
40
4
2

LS
3
Total Cost of Materials

100 Sqm
Rate in Rs. Amount in Rs.
140.00
1820
700.00
9800
140.00
196
220
8800
140.00
560
41
82
20

60
21318

B. Machinery
Sl. No.

Particulars

Unit

Quantity

Rate in Rs. Amount in Rs.

NIL
Total Cost of Machinery

C. Labour
Sl. No.
1
2

Particulars
Painter Class-II
Helper

Unit
Quantity Rate in Rs. Amount in Rs.
Day
20
370.00
7400
Day
20
310.00
6200
Total Cost of Machinery
13600
Labour Component/ Unit Qty.
136
Add Contractor's Profit and and Overhead Charges @
13.615%
18.52
Labour Component/ Unit Qty (including contractor' profit)
154.52
ABSTRACT:
A. Cost of Materials:
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for Excise Duty on 75% cost excluding cost of materials)
0%
Total
E. Add for transportation Charges upto worksite @
3%
Total
F. Add for Contractor's Profit and Overhead Charges @ 14% 13.615%
Total Cost per
100 Sqm
Rate per
Sqm

21318
0
13600
34918
0
34918
1047.54
35965.54
4896.71
40862.248
408.6

353

Manual works - 2015-16

(Common to all Departments)


Index_code
COM_MWRK

COM_MWRK-1

COM_MWRK-2

A. Manual Works
New extra items-- common item for all earth works using only manual labour
for all other works without involving contractors
(Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
With 3 Cum per day output
(Manual)Excavation in all kinds of soil/ HDR including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
With 2.5 Cum per day output

103.30

124.00

COM_MWRK-3

(Manual)Excavation in soft rock (including F&F) without blasting, including boulders upto 0.30 m dia.
for foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
233.10
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Soft rock 1.33 Cum/Day

COM_MWRK-4

(Manual)Excavation in hard rock, including boulders upto 0.30 m dia. for


foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Hard rock 0.67Cum/ day

462.70

355

COM-LDLFT-2015-16
COM-LDLFT

Chapter VII
LEAD/LIFT/LOADING & UNLOADING CHARGES
(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
FOR THE YEAR : 2015-16

LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS

COM-LDLFT

COM-LDLFT-1

1. For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be
adopted irrespective of mode of conveyance.
2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted
irrespective of mode of conveyance.
3. The rates for loading at quarry including idle hire charges of trucks and hire charges per for
each kilometer and upto 5 km are cumulative and inclusive of total charges for preceding lead.
4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones
are for loose volume and not for compacted or in-situ volume.
5. The rates for lift charges,lead charges, hire charges are cumulative and inclusive of
rates for preceding lift,lead and hire charges
6. Lift charges are not payable where conveyance of materials is by mechanical means to
final placing point.
7. Loading and unloading charges are not payable for conveyance by head load.
8. Loading charges are not payable for conveyance by mechanical means for disposal of
excavated materials beyond initial lead of 50 m wherever specified.
9. Loading and unloading charges are not payable for conveyance by mechanical means for
disposal of excavated materials beyond initial lead of 1 km wherever specified.
10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble,
size stone and cut stone are inclusive of stacking.
11. Hire charges are per 1KM for tippers and trucks for tranport of materials from work site to dump
yard and other places are cumulative& includes previous km upto 5 kms
12. The lead & lift charges are inclusive of contractor's profit and overhead charges of
14%
FOR THE YEAR: 2015-16
A. (Lead) Conveyance Charges for materials by head load
Earth / Sand
/Gravel / Murrum/ Cement /
Total distance
Lime/ Surki/ Size ReinforceSl No. ( Total lead includes initial stone / Cut stone ment steel
lead )
Rubble / Coarse Str steel
aggregate Rs/ Rs / tonne
Cum
1
2
3
4
Total lead upto 50 m
1
(covered by item rate)
initial lead
initial lead
2
Total lead upto 100 m
50.30
29.40
3
Total lead upto 150 m
100.60
58.70

PCC slab/ Shahbad


slab / CC block/ BS
slab/ Late-rite / Wood
Rs / cum
5
initial lead
64.00
128.10

Notes: 1. No loading or unloading charges are admissible for conveyance by head load.
2. For total lead exceeding 150 m conveyance charges by mechanical means only shall
be adopted irrespective of mode of conveyance.
3. The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

COM-LDLFT-2

B.( Lead) Conveyance charges for machinery per kilometer for transporting materials
by tippers and trucks excluding loading, unloading and idle hire charges of machinery.
FOR THE YEAR: 2015-16
( No loading and unloading charges allowed for machinery loading and unloading )

Sl No.

Distance

1
1
2
3
4
5

2
Lead upto 1 km
Lead upto 2 km
Lead upto 3 km
Lead upto 4 km
Lead upto 5 km
for Every km beyond 5 km
upto 30 km

(Lead)
charges for
(Lead) charges
(Lead) charges trucks and
for trucks and
(Lead) charges for
(Lead)
(Lead)
for trucks and
tippers for
tippers per
trucks and tippers for
charges charges
tippers for Earth Rubble/Size
cu.meter for
Cement/ Steel/ RCC
for per
for trucks
/ Sand /Gravel / stones/ Cut
PCC slabs/
poles/ AC & GI sheets/
cu.meter per 1000
Murrum/ Lime/
Stones/
Shahabad
Packed
for water/ Nos. of
Surki/ per
Coarse
slabs/ CC &
materials/tonne
1000 litres Bricks
cu.meter
aggregate
Laterite blocks/
per
Wood/ cum
cu.meter
3
31.30
43.90
58.50
71.10
83.60

4
30.20
42.30
58.50
71.10
83.60

5
18.90
26.50
36.60
44.40
52.20

6
44.50
62.30
86.10
104.50
122.90

7
18.70
26.10
34.80
42.30
49.70

8
50.40
70.60
94.10
114.20
134.40

12.50

12.50

7.80

18.40

7.50

20.20

15.40

6.20

16.80

7
for Every km beyond 30 km
10.50
10.50
6.50
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

356

COM-LDLFT-2015-16
COM-LDLFT-3

C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
Rubble/ size
Earth / Sand
stone/ cut
/Gravel
stone/
brick work
steel in
Sl No.
Description of item
Murrum/ / Surki/
Coarse
cement in Rs/tonne
Rs/1000
Rs./tonne
aggregate,Li
No
Rs / cum
me in
Rs/cum
1
2
3
4
5
6
7
1
Loading
16.80
33.50
55.40
66.30
46.10
2
Unloading
8.40
16.75
55.40
66.30
46.10
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

COM-LDLFT-4

D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
Rubble/ size
Earth / Sand
stone/ cut
/Gravel
stone/
steel in
Sl No.
Description of item
Murrum/ / Surki/
Coarse
cement in Rs/tonne
Rs./tonne
aggregate,Li
Rs / cum
me in
Rs/cum
1
2
3
4
5
6
1
Loading
108.40
125.20
156.10
167.10
2
Unloading
38.80
62.60
156.10
167.10
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

COM-LDLFT-5

brick work
Rs/1000
No

7
212.40
212.40

E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
Rubble/ size
Earth / Sand
stone/ cut
/Gravel
stone/
Sl No.
Description of item
Murrum/ / Surki/
Coarse
aggregate,Li
Rs / cum
me in
Rs/cum
1
2
3
4
1
Loading
52.00
103.90
2
Unloading
15.80
15.80
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges
F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

COM-LDLFT-6

Sl No.

1
1
2

Earth / Sand
/Gravel
Murrum/ Lime/
Total lift
Surki/
( Total lift includes initial lift Size stone / Cut
)
stone
Rubble / Coarse
aggregate
Rs / cum
2
Total lift upto 3 m (covered
by item rate)
For Every 1.00 Lift beyond
initial lift of 3 meters

Cement /
Reinforcement steel
Str steel
Rs / tonne

PCC slab/
Shahbad
slab / CC
block/ BS
slab / Laterite
/ Wood
Rs / cum

Initial lift
5.90

Initial lift
4.20

Initial lift
7.80

DETAILED DATA
LEAD / LIFT / LOADING & UNLOADING CHARGES - DATA RATES
Note: The Lead Charges are inclusive of 13.615% Contractor Profit and Overhead charges

I. GENERAL DATA FOR LEAD / LIFT / LOADING & UNLOADING:


A . DATA FOR LEAD CHARGES BY HEAD LOAD :
For the purpose of working out conveyance charges by head load the category of materials as
classified in ( I ) above are grouped together as under :
CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut stone
In this group materials which are comperatively lighter and generally conveyed by head load
by light / heavy mazdoor are included. Method of conveyance, approximate weight per load
and time required to cover specified additional distance will be generally same
Therefore common data is considered for conveyance by head load for materials under this category.
CATEGORY : Cement in bag / Reinforcement steel / Structural steel sections
In this group the materials in packed / rolled / fabricated condition which are heavier per load
compared to the materials under Category above and which can not be split into small
quantities for the purpose of conveyance are included. The unit of measurement for these
materials is per tonne.
CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
In this group the materials in moulded condition / cut to standard size which are heavier per
load compared to materials under Category above are included.

357

COM-LDLFT-2015-16
COM-DTL-LDLFT-1

A. (Lead) Conveyance Charges for materials by head load


CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate / Rubble stone
/ Size stone / Cut stone
Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
Lead: Upto 100 m :
Average distance to be covered beyond initial lead of 50 m
Average speed of conveyance by head load
Round trip cycle time for 25 m considering 50 min/ hr working
( 2 x 25 x 60 / 50 / 60 )
No. of trips per day for additional lead ( 8 x 60 / 1 )
Quantity of material by head load per load
Quantity of material by head load per day ( 480 x 0.015 ) say
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit:
Sl No.
1

Description
Mazdoor

Contractor's profit and


overhead charges
Total for materials under this Category

Unit
Day

13.615%
7
Rate per

Lead: Upto 150 m :


Average distance to be covered beyond initial of 50 m :
Deploy two mazdoors for conveyance beyond initial lead.

Sl No.
1

Description
Mazdoor

Contractor's profit and


overhead charges
Total for materials under this Category

Unit
Day

13.615%
7
Rate per

Quantity
1
Total Rs:

25
60

m
m / minute

1
480
0.015
7

min

7
Rate
in Rs.
310

cum

cum
cum

Rs:
Rs:

50

Unit:

7
Rate
in Rs.
310

Quantity
2
Total Rs:

cum
cum

cum
cum

Amount in Rs.
310
310
42.21
352.21
50.30

cum
Amount in Rs.
620
620
84.41
704.41
100.60

Rs:
Rs:

CATEGORY : Cement in bag / Reinforcement steel / Structural steel sections


Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
Lead: Upto 100 m :
Average distance to be covered beyond initial lead of 50 m
Average speed of conveyance by head load
Round trip cycle time for 25 m considering 50 min/ hr working
( 2 x 25 x 60 / 50 / 30 )
No. of trips per day for lead upto 100 m ( 8 x 60 / 2 )
Quantity of material by head load per load
Quantity of material by head load per day ( 240 x 50 / 1000 )
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit:
Sl No.
Description
Unit
Quantity
Cement /steel handling
1
mazdoor
Day
1
Total Rs:
Contractor's profit and
overhead charges
13.615%
Total for materials under this Category 12.00
tonne
Rate per
tonne
Lead: Upto 150 m :
Average distance to be covered beyond initial of 50 m :
Deploy two mazdoors for conveyance beyond initial lead.
Sl No.
1

Description
Cement /steel handling
Mazdoor

Unit
Day

Contractor's profit and


overhead charges
13.615%
Total for materials under this Category 12.00
Rate per
tonne

25
30

m
m / minute

2
240
50
12

min
kg
tonne

12
Rate in Rs.

tonne
Amount in Rs.

310

310
310
42.21
352.21
29.40

Rs:
Rs:

50

Unit:
Quantity

12
Rate in Rs.

tonne
Amount in Rs.

2
Total Rs:

310

620
620

tonne
Rs:

Rs:

84.41
704.41
58.70

CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
Lead: Upto 100 m :
Average distance to be covered beyond initial lead of 50 m
Average speed of conveyance by head load
Round trip cycle time for 25 m considering 50 min/ hr working
( 2 x 25 x 60 / 50 / 40 )

25
40

m
m / minute

1.5

min

358

COM-LDLFT-2015-16
No. of trips per day for lead upto 100 m ( 8 x 60 / 1.5 )
Quantity of material by head load per load
Quantity of material by head load per day ( 320 x 0.017 ) say
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit:
Sl No.
Description
Unit
Quantity
1
Mazdoor
Day
1
Total Rs:
Contractor's profit and
overhead charges
13.615%
Total for materials under this Category 5.5
cum
Rate per
cum

Description
Mazdoor

Unit
Day

Contractor's profit and


overhead charges
13.615%
Total for materials under this Category 5.5
Rate per

COM-DTL-LDLFT-2

5.5
Rate in Rs.
310

cum
cum
cum
Amount in Rs.
310
310

Rs:
Rs:

42.21
352.21
64.00

50

Unit:
Quantity
2
Total Rs:

5.5
Rate in Rs.
310

cum
Amount in Rs.
620
620

cum
cum

Rs:
Rs:

Lead: Upto 150 m :


Average distance to be covered beyond initial of 50 m :
Deploy two mazdoors for conveyance beyond initial lead.
Sl No.
1

320
0.017
5.5

84.41
704.41
128.10

B.( Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks
excluding loading, unloading and idle hire charges of machinery.
CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki /
For total lead upto 1 km
Sl No.
Description
1
Tipper hire charges
Fuel charges
2
Crew charges
Contractor's profit and
overhead charges
Total for
Rate per cum
For total lead more than 1 km upto 2 km
Sl No.
Description
1
Tipper hire charges
Fuel charges
2
Crew charges
Contractor's profit and
overhead charges
Total for
Rate per cum

Unit
Hour
Hour
Hour

13.615%
5

Unit
Hour
Hour
Hour

13.615%
5

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For total lead more than 4 km upto 5 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Unit:
Quantity
0.15
0.15
0.15
Total Rs:

5
Rate in Rs.
446.70
307.20
165.80

cum

Rs:

Unit:
Quantity
0.21
0.21
0.21
Total Rs:

5
Rate in Rs.
446.70
307.20
165.80

cum

Rs:

Unit:

Quantity
0.28
0.28
0.28
Total Rs:

Rate in Rs.
446.70
307.20
165.80

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.34
0.34
0.34
Total Rs:

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.4
0.4
0.4
Total Rs:

cum
Amount in Rs.
67.01
46.08
24.87
137.96
18.78
156.74
31.30
cum
Amount in Rs.
93.81
64.51
34.82
193.14
26.30
219.44
43.90
cum
Amount
in Rs.
125.08
86.02
46.42
257.52
35.06
292.58
58.50
cum
Amount
in Rs.
151.88
104.45
56.37
312.70
42.57
355.27
71.10
cum
Amount
in Rs.
178.68
122.88
66.32
367.88

359

COM-LDLFT-2015-16
Contractor's profit and
overhead charges
Total for
Rate per cum

13.615%
5

cum

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

5
Rate
in Rs.
446.70
307.20
165.80

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.05
0.05
0.05
Total Rs:

cum

Rs:

50.09
417.97
83.60
cum
Amount
in Rs.
26.80
18.43
9.95
55.18
7.51
62.69
12.50
cum
Amount
in Rs.
22.34
15.36
8.29
45.99
6.26
52.25
10.50

CATEGORY : Coarse aggregate / Rubble stone / Size stone / Cut stone


For total lead upto 1 km
Sl No.
1
2

Unit:

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For total lead more than 4 km upto 5 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Quantity
0.15
0.15
0.15
Total Rs:

5
Rate
in Rs.
414.10
307.20
165.80

cum

Rs:

Unit:

5
Rate
in Rs.
414.10
307.20
165.80

Quantity
0.21
0.21
0.21
Total Rs:

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.28
0.28
0.28
Total Rs:

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.34
0.34
0.34
Total Rs:

cum
Amount
in Rs.
62.12
46.08
24.87
133.07
18.12
151.19
30.20
cum
Amount
in Rs.
86.96
64.51
34.82
186.29
25.36
211.65
42.30
cum
Amount
in Rs.
125.08
86.02
46.42
257.52
35.06
292.58
58.50
cum
Amount
in Rs.
151.88
104.45
56.37
312.70

cum

Rs:

42.57
355.27
71.10

Unit:

5
Rate
in Rs.
446.70
307.20
165.80

cum
Amount
in Rs.
178.68
122.88
66.32

Quantity
0.4
0.4
0.4

360

COM-LDLFT-2015-16
Total Rs:

0.00

367.88

cum

Rs:

50.09
417.97
83.60

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

5
Rate
in Rs.
446.70
307.20
165.80

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
5

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.05
0.05
0.05
Total Rs:

cum

Rs:

cum
Amount
in Rs.
26.80
18.43
9.95
55.18
7.51
62.69
12.50
cum
Amount
in Rs.
22.34
15.36
8.29
45.99
6.26
52.25
10.50

CATEGORY : Cement/ Steel/ Pipes/ RCC poles/ AC & GI sheets/ Packed materials
For total lead upto 1 km
Sl No.
1
2

Unit:

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

13.615%
8

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

13.615%
8

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

13.615%
8

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

13.615%
8

For total lead more than 4 km upto 5 km


Sl No.
1

Description
Tipper hire charges
Fuel charges

Unit
Hour
Hour

Quantity
0.15
0.15
0.15
Total Rs:

8
Rate
in Rs.
414.10
307.20
165.80

tonne

Rs:

Unit:

8
Rate
in Rs.
414.10
307.20
165.80

Quantity
0.21
0.21
0.21
Total Rs:

tonne

Rs:

Unit:

8
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.28
0.28
0.28
Total Rs:

tonne

Rs:

Unit:

8
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.34
0.34
0.34
Total Rs:

tonne
Amount
in Rs.
62.12
46.08
24.87
133.07
18.12
151.19
18.90
tonne
Amount
in Rs.
86.96
64.51
34.82
186.29
25.36
211.65
26.50
tonne
Amount
in Rs.
125.08
86.02
46.42
257.52
35.06
292.58
36.60
tonne
Amount
in Rs.
151.88
104.45
56.37
312.70

tonne

Rs:

42.57
355.27
44.40

Unit:

8
Rate
in Rs.
446.70
307.20

tonne
Amount
in Rs.
178.68
122.88

Quantity
0.4
0.4

361

COM-LDLFT-2015-16
2

0.4
Total Rs:

165.80

tonne

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

8
Rate
in Rs.
446.70
307.20
165.80

Crew charges

Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

13.615%
8

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

13.615%
8

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

13.615%
8

tonne

Rs:

Unit:

8
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.05
0.05
0.05
Total Rs:

tonne

Rs:

66.32
367.88
50.09
417.97
52.20
tonne
Amount
in Rs.
26.80
18.43
9.95
55.18
7.51
62.69
7.80
tonne
Amount
in Rs.
22.34
15.36
8.29
45.99
6.26
52.25
6.50

CATEGORY : PCC slabs/ Shahabad slabs/ BS slabs/ CC & Laterite blocks/ Wood
For total lead upto 1 km
Sl No.
1
2

Unit:

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
3.4

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
3.4

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
3.4

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
3.4

For total lead more than 4 km upto 5 km


Sl No.
1

Description
Tipper hire charges

Unit
Hour

Quantity
0.15
0.15
0.15
Total Rs:

3.4
Rate
in Rs.
414.10
307.20
165.80

cum

Rs:

Unit:

3.4
Rate
in Rs.
414.10
307.20
165.80

Quantity
0.21
0.21
0.21
Total Rs:

cum

Rs:

Unit:

3.4
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.28
0.28
0.28
Total Rs:

cum

Rs:

Unit:

3.4
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.34
0.34
0.34
Total Rs:

cum
Amount
in Rs.
62.12
46.08
24.87
133.07
18.12
151.19
44.50
cum
Amount
in Rs.
86.96
64.51
34.82
186.29
25.36
211.65
62.30
cum
Amount
in Rs.
125.08
86.02
46.42
257.52
35.06
292.58
86.10
cum
Amount
in Rs.
151.88
104.45
56.37
312.70

cum

Rs:

42.57
355.27
104.50

Unit:

3.4
Rate
in Rs.
446.70

cum
Amount
in Rs.
178.68

Quantity
0.4

362

COM-LDLFT-2015-16
0.4
0.4
Total Rs:

307.20
165.80

cum

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

3.4
Rate
in Rs.
446.70
307.20
165.80

Fuel charges
Crew charges

Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
3.4

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
3.4

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

13.615%
3.4

cum

Rs:

Unit:

3.4
Rate
in Rs.
446.70
307.20
165.80

Quantity
0.05
0.05
0.05
Total Rs:

cum

Rs:

Unit:

8000
Rate
in Rs.
402.50
307.20
165.80

122.88
66.32
367.88
50.09
417.97
122.90
cum
Amount
in Rs.
26.80
18.43
9.95
55.18
7.51
62.69
18.40
cum
Amount
in Rs.
22.34
15.36
8.29
45.99
6.26
52.25
15.40

CATEGORY : water
For total lead upto 1 km
Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
8000

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
8000

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
8000

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
8000

For total lead more than 4 km upto 5 km


Sl No.

Description

Unit

Quantity
0.15
0.15
0.15
Total Rs:

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
307.20
165.80

Quantity
0.21
0.21
0.21
Total Rs:

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
307.20
165.80

Quantity
0.28
0.28
0.28
Total Rs:

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
307.20
165.80

Quantity
0.34
0.34
0.34
Total Rs:

litres
Amount
in Rs.
60.38
46.08
24.87
131.33
17.88
149.21
18.70
litres
Amount
in Rs.
84.53
64.51
34.82
183.86
25.03
208.89
26.10
litres
Amount
in Rs.
112.70
86.02
46.42
245.14
33.38
278.52
34.80
litres
Amount
in Rs.
136.85
104.45
56.37
297.67

litres

Rs:

40.53
338.20
42.30

Unit:

8000
Rate
in Rs.

litres
Amount
in Rs.

Quantity

363

COM-LDLFT-2015-16
1

0.4
0.4
0.4
Total Rs:

402.50
307.20
165.80

litres

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

8000
Rate
in Rs.
402.50
307.20
165.80

Water tanker hire charges


Fuel charges
Crew charges

Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
8000

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
8000

For lead beyond 30 km for every km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
8000

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
307.20
165.80

Quantity
0.05
0.05
0.05
Total Rs:

litres

Rs:

Unit:

3000
Rate
in Rs.
414.10
307.20
165.80

161.00
122.88
66.32
350.20
47.68
397.88
49.70
litres
Amount
in Rs.
24.15
18.43
9.95
52.53
7.15
59.68
7.50
litres
Amount
in Rs.
20.13
15.36
8.29
43.78
5.96
49.74
6.20

CATEGORY : Bricks (as adopted by R&B(Buildings))


For total lead upto 1 km
Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

13.615%
3000

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

13.615%
3000

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

13.615%
3000

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

13.615%
3000

For total lead more than 4 km upto 5 km

Quantity
0.15
0.15
0.15
Total Rs:

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
307.20
165.80

Quantity
0.21
0.21
0.21
Total Rs:

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
307.20
165.80

Quantity
0.28
0.28
0.28
Total Rs:

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
307.20
165.80

Quantity
0.34
0.34
0.34
Total Rs:

bricks
Amount
in Rs.
62.12
46.08
24.87
133.07
18.12
151.19
50.40
bricks
Amount
in Rs.
86.96
64.51
34.82
186.29
25.36
211.65
70.60
bricks
Amount
in Rs.
115.95
86.02
46.42
248.39
33.82
282.21
94.10
bricks
Amount
in Rs.
140.79
104.45
56.37
301.61

bricks

Rs:

41.06
342.67
114.20

Unit:

3000

bricks

364

COM-LDLFT-2015-16

Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

13.615%
3000

Rate
in Rs.
414.10
307.20
165.80

bricks

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

3000
Rate
in Rs.
414.10
307.20
165.80

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

13.615%
3000

For lead beyond 30 km for every km


Sl No.
1
2

COM-DTL-LDLFT-3

Quantity
0.4
0.4
0.4
Total Rs:

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

13.615%
3000

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
307.20
165.80

Quantity
0.05
0.05
0.05
Total Rs:

bricks

Amount
in Rs.
165.64
122.88
66.32
354.84
48.31
403.15
134.40
bricks
Amount
in Rs.
24.85
18.43
9.95
53.23
7.25
60.48
20.20
bricks
Amount
in Rs.
20.71
15.36
8.29
44.36
6.04
50.40
16.80

Rs:

C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
MORD -data
1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Unit
Quantity
Rate Rs.
Building Rubbish, Crushed Slag, Stone for Masonry
Work by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
0.02
370.00
Mazdoor
day
0.5
310
Total in Rs.
contractor's profit and
overhead charges
13.615%
Rate per cum =
Rs.

Amount Rs.

7.40
155.00
162.40
22.11
33.50

b) Unloading50% of the loading charges i.e.,


16.75

2
Loading of Earth, Sand, Moorum, Manure, Flyash Unit
a) Loading by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
0.01
Mazdoor
day
0.25
Total in Rs.
contractor's profit and
overhead charges
13.615%
Rate per cum =

Quantity

Rate Rs.

370.00
310

Amount
Rs.

3.70
77.50
81.20
11.06
16.80

Rs.

b) Unloading50% of the loading charges i.e.,


8.40
Loading of Bricks by manual means
3
a) Loading including a lead upto 30 m
Unit = 1000 Nos.
Taking output = 2000 Nos
a) Labour
Head Mazdoor
Mazdoor
Cost for 2000 Nos. =
contractor's profit and
overhead charges
13.615%
Rate per cum =
100% of loading charges
b) Unloadingi.e.,
+ stacking
Rs.
4

Unit

day
day

Quantity

0.01
0.25

Rate Rs.

370.00
310

Amount Rs.

3.70
77.50
81.20
11.06
46.10

Rs.

46.10

Loading of Cement by manual means

Unit

Quantity

Rate Rs.

Amount Rs.

365

COM-LDLFT-2015-16
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
Head mazdoor
Mazdoor
Cost for 10 t =
contractor's profit and
overhead charges
13.615%
Rate per 1 tonne =

day
day

0.06
1.5

370.00
310

22.20
465.00
487.20
66.33
55.40

Rs.

b) Unloading100%
+ stacking
of loading charges I.e.,55.40
Rs.
Loading of Structural Steel, Steel Bars by manual means
5
Unit
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
head Mazdoor
day
Mazdoor
day
Cost for 10 t =
contractor's profit and
overhead charges
13.615%
Rate per 1 tonne =
100% of loading charges
b) UnloadingI.e.,
+ stacking
Rs.

COM-DTL-LDLFT-4

0.07
1.8

Rate Rs.

370.00
310

Amount Rs.

25.9
558.00
583.90
79.50
66.30

Rs.

66.30

6
Unit
Loading of Bricks - 1000 Nos (Regular sizes a) Loading 225x140x70 mm) by manual means including
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
head Mazdoor
day
Mazdoor
day
Cost for 2000 Nos. =
contractor's profit and
overhead charges
13.615%
Rate per 1000 Nos. =
100% of loading charges
b) UnloadingI.e.,
+ stacking
Rs.

Quantity

Quantity

0.01
0.25

Rate Rs.

370.00
310.00

Amount Rs.

3.7
77.50
81.20
11.06
46.10

Rs.

46.10

D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Building Rubbish, Crushed Slag, Stone for Masonry Unit
Work by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Head Mazdoor
day
Mazdoor
day
b) Machinery
Truck 10t
hour
Cost for 5.5 cum =
contractor's profit and
overhead charges
13.615%
Rate per cum =
b) Unloading50% of the loading charges i.e.,

Quantity

Rate Rs.

Amount Rs.

0.02
0.5

370.00
310

7.40
155.00

0.5

887.10

443.55
605.95
82.50
125.20

Rs.

62.6

2
Loading of Earth, Sand, Moorum, Manure, Flyash Unit
a) Loading by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
Mazdoor
day
b) Machinery
Truck 10t
hour
Cost for 5.5 cum =
contractor's profit and
overhead charges
13.615%
Rate per cum =
b) UnloadingUnloading of Earth, Sand, Moorum, Manure, FlyashUnit
by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
day
Mazdoor(unskilled)
day

Quantity

Rate Rs.

Amount Rs.

0.01
0.25

370.00
310

3.70
77.50

0.5

887.10

443.55
524.75
71.44
108.40

Rs.
Quantity

0.005
0.125

Rate Rs.

370.00
310

Amount Rs.

1.85
38.75

366

COM-LDLFT-2015-16
b) Machinery
Truck 10t
Cost for 5.5 cum =
contractor's profit and
overhead charges
Rate per cum =

hour

0.166

887.10

13.615%

25.58
38.80

Rs.

Loading of Bricks by manual means


3
a) Loading including a lead upto 30 m
Unit = 1000 Nos.
Taking output = 2000 Nos
a) Labour
Mate
Mazdoor(unskilled)
b) Machinery
Truck 10t
Cost for 2000 Nos. =
contractor's profit and
overhead charges
13.615%
Rate per 1000 bricks =

Unit

Quantity

147.26
187.86

Rate Rs.

Total

day
day

0.01
0.25

370.00
310

3.70
77.50

hour

0.33

887.10

292.74
373.94
50.91
212.40

Rs.

b) Unloading100%
+ stacking
of loading charges i.e.,212.40
Rs.
Loading of Cement by manual means
4
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
Mate
Mazdoor(unskilled)
b) Machinery
Truck 10t
Cost for 10 t =
contractor's profit and
overhead charges
13.615%
Rate per 1 tonne =

Unit

Quantity

Rate Rs.

Total

day
day

0.06
1.5

370.00
310

22.20
465.00

hour

887.10

887.10
1374.30
187.11
156.10

Rs.

b) Unloading100%
+ stacking
of loading charges i.e.,156.10
Rs.
Loading of Structural Steel, Steel Bars by manual means
5
Unit
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
Mate
day
Mazdoor(unskilled)
day
b) Machinery
Truck 10t
hour
Cost for 10 t =
contractor's profit and
overhead charges
13.615%
Rate per 1 tonne =

Quantity

Rate Rs.

Total

0.07
1.8

370.00
310

25.90
558.00

887.10

887.10
1471.00
200.28
167.10

Rs.

b) Unloading100%
+ stacking
of loading charges i.e.,167.10
Rs.
COM-DTL-LDLFT-5

E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)

COM-DTL-LDLFT-5-A

1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Crushed Slag, Stone for Masonry work by
mechanical means including a lead upto 30 m
Placing tipper at loading point, loading with front end
loader excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity
@ 45 / 25 cum per hour
iii) Manoevouring, reversing, dumping and turning
for return
iv) Waiting time, unforeseen contingencies, etc.
Total

a) Machinery
Tipper 10 t capacity
Front end-loader 1 cum bucket capacity @ 45 cum

per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5

Unit

Quantity

Min
Min

1
7.33

Min

Min
Min

2
10.33

hour
hour

0.17
0.12

Rate Rs.

919.70
2821.50

Total

158.34
344.69
503.03

13.615%
Rs.

68.49
103.90

b) Unloadingsee below. COM-LDLFT-5-B

367

COM-LDLFT-2015-16
COM-DTL-LDLFT-5-B

2
Loading of Earth, sand, Moorum, Manure, Flyash,
a) Loading by mechanical means including a lead upto 30 m
Placing tipper at loading point, loading with front
end loader excluding time for haulage and return trip.
Unit
Placing tipper at loading point, loading with front
end loader excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket capacity
Min
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen contingencies, etc.Min
Total
Min
a) Machinery
Tipper 10 t capacity
hour
Front end-loader 1 cum bucket capacity @ 45 cum
hour
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
13.615%
Rate per cum = (a+b)/5.5

Quantity

COM-DTL-LDLFT-6

hour

Total

1
3.3
2
6.3
0.105
0.055

919.70 96.57
2821.50 155.18
251.75
34.28
52.00

Rs.

b) Unloading Unloading of Earth, sand, Moorum, Manure, Flyash,


lime, Aggregate, Stone boulder, Brick aggregate,
Kankar, Building rubbish, Manure, Crushed Slag,
Unit
Flyash, Stone for Masonry work by Mechaniccal
means including a lead upto 30 m
Placing tipper at unloading point, excluding time
for haulage and return trip.
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket capacity Min
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen contingencies, etc.
Min
Total

a) Machinery
Tipper 10 t capacity
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5

Rate Rs.

Quantity

Rate Rs.

Total

1
2
2
5
0.08

919.70 76.64
76.64

13.615%

10.43
15.80

F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD


FOR CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut stone
Lift : Upto 3.00 m
This is the initial lift and forms integral part of the activities in the basic rate of work item.
Lift charges are admissible only lifting effort beyond initial lift specified in the work item.
Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
Round trip cycle time for 1.00 m considering 50 min/ hr working
1 x6x 60 / 50 / 60 )
No. of trips per day for lift 1.0 m above 3 m ( 8 x 60 / 0..12)
Quantity of material by head load
Quantity of material by head load per day ( 4000x 0.015 )
Deploy 1 mazdoor for every additional lift of 1.0 m beyond initial lift.
Lift : Upto 3.00 m for materials under this Category
Unit:
Sl No.
1

Description
2
Mazdoor
contractor's profit and
overhead charges

Unit
3
Day

Quantity
4
1.00

60 m/minute
0.12
4000
0.015
60

min
cum
cum

60
Rate
in Rs.
5
310.00

13.615%
Total Rs: for 60
cum

cum
Amount
in Rs.
6
310.00
42.21

Rate per cum


FOR CATEGORY: Cement bag / Reinforcement steel / Structural steel sections
Lift : Upto 3.00 m
This is the initial lift and forms integral part of the activities in the basic rate of work item.
Lift charges are admissible only lifting effort beyond initial lift specified in the work item.

352.21
5.90

Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
Round trip cycle time for 1.00 m considering 50 min/ hr working

25 m/minute

368

COM-LDLFT-2015-16
1 x6x 60 / 50 / 25 )
0.29
No. of trips per day foradditional lift 1.0 m above 3 m ( 8 x 60 / 0.29)
1655
Quantity of material by head load
50
Quantity of material by head load per day ( 1655x50x 0.015 )
83
Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor
Lift : Upto 3.00 m for materials under this Category
Unit:
83
Sl No.
1

Description
2
Mazdoor
contractor's profit and
overhead charges

Unit
3
Day

Quantity
4
1.00

Rate
in Rs.
5
310.00

13.615%
Total Rs: for 83
Tonnes

min
kgs
tons
TONS
Amount
in Rs.
6
310.00
42.21

352.21
Rate per tonne
4.20
FOR CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
Lift : Upto 3.00 m
This is the initial lift and forms integral part of the activities in the basic rate of work item.
Lift charges are admissible only lifting effort beyond initial lift specified in the work item.
Lift : ADDITIONAL LIFT CHARGES FOR EACH 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
40 m/minute
Round trip cycle time for 1.00 m considering 50 min/ hr working
1 x6x 60 / 50 / 40 )
0.18
No. of trips per day for lift 1.0 m ( 8 x 60 / 0.18 )
2667
Quantity of material by head load
0.017
Quantity of material by head load per day ( 1667x 0.018 )
45
Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor
Lift : Upto 3.00 m for materials under Category
Sl No.
1

Description
2
Mazdoor
contractor's profit and
overhead charges

Rate per cum

Unit:
Unit
3

Day
13.615%
Total Rs: for 45
cum

Quantity
4
1.00

45
Rate
in Rs.
5
310.00

min
cum
cum

cum
Amount
in Rs.
6
310.00
42.21
352.21
7.80

369

Hire Charges- for the year 2015-16

HIRE CHARGES OF MACHINERY


FOR THE YEAR : 2015-16
S.No

1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51

Description of machinery

2
Agitator car / Transit mixer 2 cum
Air compressor 5 cmm ( electric )
Air compressor 7 cmm ( diesel )
Air compressor 7 cmm ( electric )
Air compressor 8.5 cmm ( diesel
Air compressor 8.5 cmm ( electric)
Air compressor 15 cmm ( electric)
Angle Dozer 90 hp
Batching plant 0.5 cum( 6 cum/hr)
Batching plant 2 x 1.00 cum(15 cum/hr)
Batching plant 2 x 1.50 cum(50 cum/hr)
Bending machine 3000 x 12 mm
Clamp shell and hoisting ropes
Concrete bucket 1.5 cum
Concrete hand mixer 45 / 30 ltr
Concrete mixer 300 / 200 ( diesel)
Concrete mixer 300 / 200 ltr ( electric)
Concrete mixer 600 / 400 ( diesel)
Concrete mixer 600 / 400 ltr ( electric
Concrete paver 100 sqm / hr
Convey mucker
Core drilling machine
Diesel generating set 30 KVA
Diesel generating set 50 KVA
Diesel Loco 45 hp
Dewatering pump 5 hp ( diesel )
Dewatering pump 5 hp ( electric )
Dewatering pump 10 hp ( diesel )
Dewatering pump 10 hp ( electric
Dewatering pump 20 hp ( diesel )
Dewatering pump 20 hp ( electric
Drifter
Drilling jumbo
Dumper 4.5 cum
Geophysical Electric resistivity meter
Grouting pump
Guniting / sand blast equipment
Ice plant & accessories 30 t / day
Jack hammer
Needle vibrator 40 mm ( petrol )
Needle vibrator 40 mm ( electric )
Needle vibrator 60 mm ( petrol )
Needle vibrator 60 mm ( electric )
Planing machine 4 m stroke
Plate shearing machine upto 12 mm
Pneumatic placer 0.5 cum
Pneumatic tamper
Pug cutting machine
Pusher leg
Road roller diesel 10 t
Shovel 0.50 cum 75 hp

Unit

3
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Hire
charge in
Rs
4
758.40
108.30
241.30
131.90
275.60
170.80
138.80
1715.50
114.60
405.40
518.10
42.60
5.40
15.80
5.50
53.50
51.70
92.70
91.00
356.50
822.80
319.00
65.80
85.10
381.60
10.20
3.00
15.20
6.70
48.30
12.30
322.70
368.40
580.70
99.00
24.90
110.10
170.20
19.80
7.60
8.00
8.20
9.70
117.80
41.90
171.10
20.70
6.40
12.70
197.20
1003.10

Fuel
Crew
charge in Charge
Rs
in Rs.
5
893.90
259.80
731.40
346.40
914.20
433.10
962.30
625.30
115.50
346.40
423.40
115.50
0.00
0.00
0.00
81.30
38.50
162.50
77.00
0.00
267.90
243.80
650.10
975.20
548.50
81.30
38.50
162.50
77.00
325.10
154.00
0.00
43.90
409.60
0.00
38.50
0.00
1097.10
0.00
20.60
7.70
30.80
11.50
115.50
154.00
0.00
0.00
3.80
0.00
731.40
487.60

6
265.20
153.10
195.90
153.10
195.90
153.10
163.30
221.00
318.20
318.20
318.20
122.50
0.00
0.00
0.00
204.10
204.10
204.10
204.10
391.90
163.30
265.20
122.50
122.50
153.10
103.60
77.70
103.60
77.70
103.60
77.70
331.50
163.30
212.20
0.00
244.90
204.10
122.50
306.20
146.90
146.90
146.90
146.90
195.90
132.60
80.90
244.90
0.00
0.00
195.90
221.00

Total in Rs
7
1917.50
521.20
1168.60
631.40
1385.70
757.00
1264.40
2561.80
548.30
1070.00
1259.70
280.60
5.40
15.80
5.50
338.90
294.30
459.30
372.10
748.40
1254.00
828.00
838.40
1182.80
1083.20
195.10
119.20
281.30
161.40
477.00
244.00
654.20
575.60
1202.50
99.00
308.30
314.20
1389.80
326.00
175.10
162.60
185.90
168.10
429.20
328.50
252.00
265.60
10.20
12.70
1124.50
1711.70

370

Hire Charges- for the year 2015-16

HIRE CHARGES OF MACHINERY


FOR THE YEAR : 2015-16
S.No

1
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70

Description of machinery

2
Shovel 0.85 cum 110 hp
Stationery derric crane
Tipper 5 cum
Tipping tub 1.5 cum
Tower crane 5 tonne
Transformer 250 KVA
Truck 10 t
Truck mounted derric crane 5 t
Upright drilling machine/Grinder
Ventilation fan 20 hp
Vibratory pad foot roller 8 t
Wagon drill
Water tanker 8000 ltr
Welding set
Winch 35 hp ( electric )
Tractor with 2T roller
Hydraulic Truck Crane 30T
Hydraulic Truck Crane 16T
Heavy Duty Airless Spray Painting
Equipment

Unit

Hire
charge in
Rs

Fuel
Crew
charge in Charge
Rs
in Rs.

3
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

4
1706.60
86.10
446.70
64.20
867.10
5041.00
414.10
519.70
22.50
11.50
1342.20
188.50
402.50
16.00
129.40

5
893.90
0.00
307.20
0.00
200.20
0.00
307.20
307.20
38.50
154.00
1056.40
0.00
307.20
92.40
188.60

6
221.00
0.00
165.80
0.00
176.80
0.00
165.80
165.80
187.20
26.80
244.90
265.20
165.80
0.00
244.90

3096.80
2278.10

118.80
75.00

489.20
489.20

Hour

121.40

Total in Rs
7
2821.50
86.10
919.70
64.20
1244.10
5041.00
887.10
992.70
248.20
192.30
2643.50
453.70
875.50
108.40
562.90
345.00
3704.80
2842.30
121.40

371

Potrebbero piacerti anche