Sei sulla pagina 1di 3

Sl.No.

Running Inspection
Check Point Details

Frequency

1 Physical condition of drive panel

6M

2 Ambient Room Temp

Daily

3 Exhaust Fan

4 Output Current and Voltage Trace

During Shutdown
1 Cleaning Of Door Filters

3M

2 Drive Module Tightness and Cleaning

3 Inspection of Connectors and Cards

4 VRAM and MPU Backup

5 LV discharge Test

5Y

How to Check

Criteria

Visual

Panel doors must be


closed.Idication should be
Healthy.

Sensors

Temp should be 25 - 28
deg.Humidity <90

Visual

MCB should be ON.Fan


Running Sound OK.Flow
Indicating Flap must be Lifted

Use Mtools

Should match the previous


shape.

Visual

NA

To be checked using Torque


Wrench

As per OEM instructions.

Visual and Manual

NA

Mtools

NA

Mtools and CRO

Check the output waveform


for proper Firing angle and
correct Time shift.

Action

To Be Investigated
Check AHU sysytem

Check the Fan.


Check the Drive VRAM

Inspect and Replace


Tightness to be done
accordingly.
Check individual connector
with hands and press top
lock it.
Keep the Latest Backup for
any emergency.

Investigate and chenge


IGBT,Contro card.