Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
SINCOR, C.A.
UPSTREAM SURFACE FACILITIES PROJECT
REVISION INDEX:
This Document Consists of 74 Pages
Note: Any technical change or revision from the original Sincor document is indicated by
the right hand margin.
Rev.
Nro.
Prepared
By/ Date
F1
A. DI BELLA/
S. CUESTA
1998-07-28
A. Avila
20/05/2003
A. Avila
08/10/2003
A. Avila
17/08/2004
J.Menendez
17/10/2005
X0
X1
X2
X3
CA04-04-33-P-DC-101_X31.DOC
APPROVAL REGISTER
Checked
Project
Approved
By/ Date
Approved By/
By/ Date
Date
A. DI BELLA
1998-07-28
G.HARRIS
1998-07-28
N BAKER
1998-07-28
A. Avila
20/05/2003
A. Avila
08/10/2003
A. Avila
17/08/2004
A. Avila
17/10/2005
S. Cuesta
20/05/2003
S. Cuesta
08/10/2003
S. Cuesta
17/08/2004
S. Cuesta
17/10/2005
J. Morillo
20/05/2003
J. Morillo
08/10/2003
J. Riera
17/08/2004
J. Riera
17/10/2005
Reason for
Revision
Final
Issued/Aproved for
tender
As - Built
Update by SINCOR
Rev 2003
Update by SINCOR
Rev 2004
Update by SINCOR
Rev 2005
in
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
CONTENTS
SECTION N
PAGE
1.
SCOPE
2.
DESIGN BASIS
3.
4.
ENGINEERING DOCUMENTS
5.
6.
7.
11
8.
17
9.
21
23
25
12. SWITCHGEAR
26
30
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
34
15. ALARMS
38
16. LIGHTING
41
45
46
48
48
53
22. CONDUIT
55
23. CABLES
56
24. GROUNDING
62
68
69
69
69
69
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
69
71
74
33. INSPECTION
74
34. STANDARDIZATION
74
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
1.
SCOPE
This document covers the general requirements of the electrical design criteria for the
equipment, materials and design of the electrical installation to be used in all projects
and modifications required in SINCOR Upstream surface facilities in San Diego de
Cabrutica, Edo. Anzotegui..
2.
DESIGN BASIS
The electrical installation shall be designed to provide:
3.
Safety to personnel
Mechanical protection
Interchangeability
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Other recognized National Codes and Standards will be accepted, provided the
electrical installation and equipment based on such documents are at least equal to
those conforming to the standards listed above.
All equipment and material shall be designed, manufactured and tested by the
governing standards and regulations of the country of manufacture. In general, in case
of conflict, the recommendations of the International Electrotechnical Commission
(IEC) shall govern for equipment manufactured outside the USA, while NEMA shall
govern for equipment manufactured in the USA.
4.
ENGINEERING DOCUMENTS
A.
b)
One line diagrams for DC and AC power circuits, including metering &
protective relaying.
c)
d)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
e)
f)
g)
Load data list and load computation for different plant conditions, including
DC loads and instrument loads.
h)
i)
Voltage profile calculations for steady state and for re-acceleration, including
the starting of large motors.
j)
Cable schedule.
k)
l)
m)
n)
o)
p)
Substation layouts.
q)
r)
s)
t)
u)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
b)
Metric system and letter symbols in accordance with IEC 60027 and IEC
60164.
c)
d)
Where necessary, the phase relation of conductors and the phase shift
through transformers shall be indicated with hour numbers in accordance
with IEC 60152.
e)
f)
Other Specifications
Electrical Switchboard
CA04-04-33-P-SP-002
Power Transformers
CA04-04-33-P-SP-003
CA04-04-33-P-SP-004
CA04-04-33-P-SP-005
CA04-04-33-P-SP-006
CA04-04-33-P-SP-007
CA04-04-33-P-SP-008
CA04-04-33-P-SP-009
CA04-04-33-P-SP-010
CA04-04-33-P-SP-011
CA04-04-33-P-SP-012
CA04-04-33-P-SP-030
Electrical
Requirements
Equipment
Cathodic Protection
CA04-04-33-P-SP-015
for
Package
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
5.
CA04-04-33-P-SP-017
CA04-04-33-P-SP-018
CA04-04-33-P-SP-020
26C 1C
50% 5%
Nonetheless, all indoor equipment and devices shall withstand operation without
degradation for a period of four days continuous without air conditioning system
C. Equipment shall comply with IEC-60068 for environmental conditions specified.
D. The equipment located outdoors shall be able to operate continuously in the site
climatic conditions specified above at the rated values given in the relevant document.
E. The equipment and material shall be designed to meet the seismic requirement for
zone 3 per UBC-97 and Z = 0.15.
6.
Material, machinery and equipment with any type of protection against the hazard
of explosion, or fire, shall be designed, manufactured and tested in accordance
with the IEC. In the case that standards of the country of origin differ from the
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
C.
b)
c)
Installation
a)
E.
For installation purposes, articles including but not limited to the following
shall be applicable: IEC 60079-14 Electrical Installation in Explosive Gas
Atmosphere (other than mines) and FONDONORMA 200. In general,
electrical equipment and wiring materials shall be furnished as required by
FONDONORMA 200. Electrical equipment shall be located outside Zone 1
areas where practical.
Definitions
a)
Hazardous area
An area in which an explosive gas atmosphere is present, or may be
expected to be present, in quantities such as to require special precautions
for the construction, installation and use of electrical apparatus.
b)
Non-hazardous area
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Zones
Hazardous areas are classified in zones based upon the frequency of the
appearance and the duration of an explosive gas atmosphere as follows:
Zone 0
Zone 1
Zone 2
An area in which an explosive gas atmosphere is not likely to occur in
normal operation and if it does occur it will exist for a short period only.
7.
General
Material, equipment and machinery shall be as hereinafter specified and shall
comply with requirements dictated by the classification of the environment and of
the hazardous location in which they are to be installed. Materials shall conform
to the standards called for.
B.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
b)
IP 23
IP 55
Terminal boxes shall be with protection degree not less than IP 55 or with
the protection required for the machine itself, whichever is higher.
c)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
d)
C.
external covers shall have degree of protection not less than IP 31,
grates and wire screens for ventilation and gas venting shall have
openings not greater than 2.5 mm and shall not be located in
correspondence to live parts.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
c)
d)
e)
f)
g)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Sand filled apparatus shall comply with the requirements set forth by IEC
60079 - 5.
h)
i)
j)
Approved type apparatus are apparatus for which the suitability of safety
provisions is recognized by a testing station.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
D.
Ex-ia,b
Ex-d
Ex-e
increased safety
Ex-p
pressurized enclosure
Ex-o
oil-immersed apparatus
Ex-q
sand-filled apparatus
8.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
A.
Outdoor Installation
Low voltage equipment shall be with enclosure not less than IP 54.
c)
Indoor Installations
B.
Zone 0 locations
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Power and control equipment shall not be installed; only instrumentation circuits
may be installed with protection type Ex-ia.
b)
Zone 1 locations
In general, electrical equipment and wiring material shall be furnished, as
required by IEC, with the following specific interpretations and additions:
For protection type Ex-p, if the pressurizing medium is air, the air intake
shall be located outside of locations classified Zone 1, at a distance in
all directions of at least 3 m. Apertures provided for the control of outflow of pressurizing medium to the external atmosphere shall be
located outside of locations classified Zone 1.
The supply of the pressurizing medium to enclosures which shall
remain in service also if the prescribed overpressure falls under 5 mm
water gauge shall be by means of a dual system and shall have
pressure-measuring devices for the operation of an alarm in the control
room and trip devices whenever the pressure within the casing falls
below the permitted minimum.
If one of the two pressurizing systems fails, an alarm shall sound in the
control room; if the second system fails the equipment shall be
automatically deenergized.
c)
Three phase squirrel cage induction motors shall be type Ex-d, Ex-e, or
Ex-p, suitable for specified temperature class.
Zone 2 Locations
In general, electrical equipment and wiring materials shall conform to the
requirement of IEC, with the following specific interpretation and additions.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Three phase squirrel cage induction motors shall be type Ex-d, Ex-e,
Ex-p, or Ex-n suitable for specified temperature class.
Lighting fixtures may also be vapor tight type suitable for the specified
temperature class and with enclosure not less than IP 55.
Inverter fed motors used for variable speed applications and installed in
hazardous locations shall be tested and certified as an integral unit with
the converter. IEC 60034 Parts 17 and 25 recommendations shall be
followed.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
9.
B.
C.
Power Sources
a)
D.
The electricity power for the SINCOR UPSTREAM shall be supplied from on
site power generation.
b)
c)
d)
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
E.
Extremely large motors to be started direct on line shall be 13.2 kV, 3phase, 3-wire, connected with 34.5 kV-13.8 kV captive transformers
(See one line diagram). Motors that cannot be started direct on line due
to voltage drop constraints shall be started by means of an electronic
soft starter.
f)
Lighting and Instrument Branch Circuits - 120 Volts, single phase (High
Pressure Sodium Lighting may use 277 or 480 Volts).
g)
Motor Space Heaters - Up to 1800 Watts, 120 Volts, single phase; 1801
Watts and above, 208 Volts, single phase.
h)
Other heaters - Up to 1800 Watts, 120 Volts, single phase; 1801 to 3000
Watts, 208 Volts, single phase; above 3000 Watts, 480 Volts, 3-phase.
F.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
POWER TRANSFORMERS
A.
B.
General Requirements
a)
b)
c)
d)
For process unit substation only, one power transformer shall be fed from
one feeder circuit breaker.
Accessories
a)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
b)
c)
d)
C.
Protection
For protection, see section 14.C.
D.
Transformer Sizing
a)
b)
Transformer Impedance
Transformers having manufacturers standard impedance values shall be
used except when other values are required as follows:
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
c)
d)
E.
Transformer(s) oil shall be analyzed (tested for water and gas content, pH,
dielectric rigidity) at transformer first energization as specified in
precommissioning procedure PPR, and one year after start-up
Converter Transformer Particular Requirements
11.
Lighting
Receptacles
Instruments
Heat Tracing
Space Heaters
A.
Basic Arrangement
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
a)
b)
c)
Alternate Arrangement
The alternate to the basic arrangement, when specified, shall be the installation of
a single transformer with a capacity suitable for the complete area or unit
requirements. In general, this transformer shall be of the same type as that
specified for Power Transformer.
C.
Accessories
Transformers for the basic arrangement or the alternate arrangement shall be
provided with standard accessories for the kVA and voltage ratings, with below
rated voltage taps, where available. See ESPECIFICATION CA04-04-33-P-SP010
12.
SWITCHGEAR
A.
Circuit Breakers
a)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
b)
c)
Momentary rating shall be adequate for the maximum short circuit level and
maximum number of motors operating under normal conditions with
estimated motor load which would exist when the transformer or installed
local generating capacity is loaded to its rated capacity.
d)
e)
f)
b)
c)
When switchgear is used for motor control, the following features shall be
included:
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
d)
C.
Undervoltage protection
The Close control at the switchgear shall not be operable unless the
breaker is in the Test position.
and
The
e)
Switchgear shall be furnished with 15% spare circuit breakers fully equipped
with all protective relays and controls for future services.
f)
Switchgear shall be furnished suitable for future extension on both ends and
shall be provided with floor space for 20% future cubicles.
In general, switchgear for service at 1000 Volts and below shall be free
standing, dead-front steel structures for indoor installation and shall comply
with IEC requirements. Except where indicated otherwise, circuit breakers
shall be drawout, air type, with stored energy mechanism. When specified,
switchgear may be used for the following functions:
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
D.
Motor controllers for motors rated above 200kW which are operated at
480 Volts (only when 6.9kV is not available or when it is economical to
use 480V)
b)
The use of direct acting trips or integrally mounted static trip devices for
overcurrent protection shall be maximized. Protective relays and associated
current transformers shall be provided only in the event that a selectively
coordinated system cannot be achieved by using direct acting trips.
c)
d)
Switchgear shall be furnished with 15% spare circuit breakers fully equipped
with protection relays and controls for future services. 15% being counted
upon each typical size quantities of outgoes.
e)
Switchgear shall be furnished suitable for future extension on both ends and
shall be provided with floor space for 20% future cubicles.
Medium voltage circuit breakers close and trip circuits. Separate fuses shall
be provided for closed and trip circuits.
b)
c)
d)
125 Volts DC control power shall be supplied from two 100% capacity valveregulated nickel cadmium batteries (sealed type) and two suitably rated 100%
battery chargers.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
13.
General
a)
b)
Unless otherwise specified, motor control shall be for full voltage starting.
c)
d)
Motor control equipment shall include overcurrent and short circuit protective
devices to provide a minimum of 5 seconds delay at locked rotor currents.
This delay shall be reviewed and increased as required for motors with
extended acceleration periods.
In general, control of motor shall be as shown on Typical Diagrams for Motor
Outgoers and as described in Medium & Low Switchgear Specification
CA04-04-33-P-SP-003, Medium Voltage Motor Control Center Specification
CA04-04-33-P-SP-004 and Low Voltage Motor Control Center Specification
CA04-04-33-P-SP-005.
e)
Every motor starter shall be furnished with provisions for padlocking in the
open position. The disconnect shall always be within sight of the controller.
Unless otherwise specified, the disconnect and controller shall be
constructed as a combination motor starter unit.
f)
For motors utilized above 120 Volts, the controller shall be operated from a
480-120 Volts secondary control power transformer directly connected on
the load side of the disconnect. One side of the 120 Volts secondary shall
be fused and the other side shall be grounded.
g)
Motor starters for single-phase motors which are not automatically started
shall be of the manually operated type located within sight of the motor. The
enclosure shall be chosen to meet the area classification requirements.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
h)
When vacuum quench type magnetic controllers are used, they shall be
supplied with surge capacitors where required to keep transient
overvoltages, due to current chopping, within acceptable limits for the motor.
i)
j)
For motors rated 6.9 kV, 3000 kW and below, the motor control equipment
shall be drawout magnetic contactor type with current limiting fuses or
equivalent equipment. If economics dictate, the motor control equipment for
the kW ratings listed below may be of the drawout magnetic contactor type,
1-high construction, with current limiting fuses:
b)
c)
d)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
D.
Push-button Stations
a)
b)
c)
Control stations for multi-speed and reversing motors shall have pilot lights
to indicate their mode of operation.
d)
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Selector switch shall have provisions for padlocking in the stop position.
f)
g)
i)
j)
Emergency stop controllers on control house panels shall meet the following:
Control wiring shall run directly from the control station to the motor
controller. Wiring shall not be routed through the motor location.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
14.
General
a)
b)
c)
Relay settings and coordination curves for the protective devices furnished
shall be provided.
d)
Relay data shall be furnished for each adjustable relay or other protective
device as follows:
Data shall also include settings for auxiliary relays and devices, such as timers,
associated with each protective device.
e)
B.
Motor Protection
a)
All 3-phase motors rated 1500 kW and below shall be protected against
overloads by thermal relays in each phase. Undervoltage protection shall be
provided for motors of all voltages controlled by switchgear.
b)
Required devices for synchronous motors only, such as relays for field
application, excitation check, out-of-step, etc., shall be provided.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
c)
d)
For motors above 600 Volts rated 1500 kW and below, the following shall be
provided in addition to the above:
High temperature alarm as specified in Specification CA04-04-33-PSP-018, for motors that have air filters.
For motors rated above 1500 kW, when controlled by switchgear, the
following shall be provided (for motors, controlled by contactors equivalent
protection shall be provided):
Lockout relay (hand reset) with healthy drop pilot light shall be
provided.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
e)
C.
Power Transformers
Each transformer shall be provided with overcurrent protection set at no more
than 125% of rated current for transformers rated 600 Volts or less, or 250% for
transformers rated over 600 Volts.
The provisions for protection of power transformers shall depend upon the
distribution system arrangement, plot plan area, and voltage rating. In general,
protection shall be provided as follows:
a)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
D.
Feeder Relaying
a)
Time (short & long) and instantaneous phase overcurrent tripping shall be
provided for feeder breakers requiring relaying except that instantaneous
tripping shall be omitted if relaying exists UPSTREAM without significant
intervening impedance. If the only UPSTREAM protection with which the
feeder relaying must coordinate is fuses, instantaneous phase overcurrent
tripping shall be furnished if selectivity can be achieved. This requires that
the instantaneous trip setting be 70 percent of the peak let-through current of
the largest anticipated fuse, and that fuse be current limiting at the fault level
of the system where it is located.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
b)
15.
c)
d)
ALARMS
A.
General
a)
b)
Alarm shall be actuated by a switch sensitive to air flow and shall give
abnormal indication whenever there is no air flow from the inside to the
outside of the building or room.
Air flow switch shall be equal to Dry-Sys standard suction type switch.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
SUBSTATION
a)
Bus tie alarms shall be provided for each secondary selective substation to
give abnormal indication whenever the breaker is closed (or open).
b)
c)
Transformers rated 500 kVA and larger shall be provided with an alarm as
follows:
d)
For each motor whose automatic shutdown would jeopardize the safety of
personnel or cause major equipment damage. An alarm shall be actuated
as in paragraph 15.C.b or by thermal overload relay. The overload tripping
relay shall then be set at 120-140 percent of the rated current.
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
and energized from the main control power busses. One relay shall be
provided for each main control power bus in each switchgear
assembly.
C.
f)
g)
A single alarm shall be located in the unit control house or room to supervise
substation alarm conditions described above if applicable.
b)
Water leakage (TEWAC enclosure having double tube cooler inside the
motor enclosure).
Overspeed.
Vibration.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
16.
LIGHTING
A.
B.
Lighting Design
a)
b)
Lighting fixtures shall not be located directly over equipment with exposed
moving parts.
c)
The lighting design for outdoor facilities shall be based on the maximum use
of flood lighting.
d)
e)
Light fixtures & receptacles shall not be connected to the same circuit.
Gauge glass lights and sight glass illuminators shall be fed from the
receptacle panel.
f)
In general, circuits shall be switched from lighting panels. The use of local
switches shall be kept to a minimum.
g)
h)
Lighting Levels
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
The lighting system shall be designed for the average initial illumination values
tabulated below and per COVENIN 2249 Iluminancias recomendadas en tareas
y ambientes de trabajo, whichever is more conservative:
Illumination levels for various areas appear on next page table.
AREA TYPE
Control Rooms General
Control Rooms Rear of Panel
Control Rooms Instrumentation Panels
Electrical Switchboard Room General
Electrical Switchboard Room Rear
Electrical Switchboard Room Isle
Transformer and Outdoor Switchgear
Areas
Pump and Compressor Rooms Indoors
Pump Rows Valves and Manifolds
Outdoor
Main Operating Platforms
Ordinary Platforms
Exchanger Areas (tube bundle removal)
General Yard Area
Furnace and Boiler Area
Outdoor Operational Areas
Toilet and Locker Rooms
Workshop - Interior Generally
Workshop - Exterior
Tank Farms
Offices
Drawing Offices
Street Lighting
* Elevation from floor
LEVEL
(Lux)
500
300
500
300
300
300
100
WORK
PLANE
Floor
1200 mm*
Horizontal centerline
of vertical surface
Ground
Ground
Ground
Ground
150
100
Floor
Ground
100
30
50
20
50
50
150
300
50
5
750
750
5
Floor
Floor
Ground
Ground
Ground
Ground
Ground
Ground
Ground
Ground
760 mm*
Ground
Ground
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
C.
Lighting Fixtures
a)
b)
Where required, general lighting for open areas within hazardous and nonhazardous areas shall be by means of 400 watt high pressure sodium (HPS)
floodlight luminaries mounted on adjacent structures or on strategically
located floodlight columns. High mast floodlighting installation shall also be
used where appropriate.
c)
High bay type 250 or 400 watt high pressure sodium fixtures shall be used in
appropriate non-hazardous locations such as warehouses, workshops etc.
d)
e)
All lighting fixtures shall be approved for use in the area classifications where
they are listed.
f)
HPS fixtures shall have high power factor, constant wattage ballasts and
color-corrected lamps.
g)
h)
Pump rows
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Loading racks
i)
Fixture location shall allow safe and convenient relamping and cleaning. In
no case shall lighting fixtures be located directly over equipment having
exposed moving parts.
j)
Fixtures for grade lighting and top platforms on towers and structures shall
be equipped with reflectors while all other outdoor fixtures shall be equipped
with guards.
k)
l)
m)
n)
Lighting for instrument consoles provided with CRT displays shall be such
that glare should be avoided.
o)
Standby lighting consisting of HPS fixtures with quick restrike ballast will be
placed at the center of pipe racks in process areas and at the top, landing
and bottom of ladders and stairways of operating platform in a sufficient
number to provide adequate illumination for safe personnel egress from
operating platform and process areas.
p)
q)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
17.
Street lighting and lighting for outdoor operating areas which are not
continuously attended, shall be automatically controlled (2-wire system)
by photocell. An auto-on-off selector switch shall be located at the
controller location to permit manual control of the lighting.
r)
s)
Substations, control rooms, administration building, and all office areas shall
be provided with self-contained battery-operated emergency lighting fixtures.
LIGHTING PANELS
A.
Design Consideration
a)
b)
c)
Nominal system voltage for outdoor area, flood lighting circuits, and street
lighting shall be 277 o 480 Volts. Outdoor lighting shall be photocell
controlled. The lighting panel for outdoor areas shall have main breaker and
several 3 pole 20 A. One spare circuit shall be provided for each 5 active
circuits in the initial design. Each phase shall be equally loaded.
d)
e)
Circuit loading shall not exceed 80% of the rating of the protective device.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
18.
Enclosures
a)
Lighting panel enclosures shall be approved for use in the area classification
where they are located.
b)
Basis of Design
a)
b)
c)
LOAD-kVA
40
55
70
80
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
d)
e)
f)
Convenience outlets shall be provided to serve portable lights and tools for
maintenance of outdoor installations of equipment and facilities as follows:
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
g)
B.
19.
In office and control rooms, receptacle outlets shall be provided along the
walls, spaced no more than 4 meters apart, with a minimum of 2 receptacles
per room.
Receptacle Types
a)
b)
c)
WIRING METHODS
A.
General
All power, motor feeders, control circuits, lighting and instrument home-run
multi-conductor cables shall be installed underground via direct buried cable
trench. Branch power, lighting and instruments may be installed aboveground on
cables trays based on economics and practicability.
In case of the new modification projects in Main Station Plant or Cluster, the
cables will be installing in spare undergroung via existing direct buried cable
trench. If this installation is impossible about of operation activities or construction
issue, the cable will be installed in new undergroung via direct buried cable trench
or abovegroung on cable trays based on economics and practicability.
20.
General
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
a)
b)
The route of cable trenches or concrete duct banks shall avoid aboveground
and underground obstructions so as to maintain reasonable access to the
buried cables. A minimum clearance of 300 mm shall be maintained
between cables and parallel runs of underground piping (including
insulation). Cables should preferably cross above buried pipelines. Cables
shall not be located under parallel runs of low level aboveground piping
which could block access to the cables or close to parallel piping runs which
will be expanded over the cables in the future. Adequate segregation shall
be
maintained
between
different
services.
Power
and
instrumentation/telecommunication cables shall not be laid in the same
trench or concrete duct banks. A separation of 600 mm shall be maintained
between parallel runs of instrument and electrical cables.
c)
Low voltage cables serving as two supply feeds shall have a minimum
spacing of 300 mm between them. Control cables, associated with the
feeder cables, shall be laid adjacent to their respective feeder cables.
d)
For 6.9 kV cables and larger serving as two supply feeders, they shall have
a minimum spacing of 300 mm between them. Control cables associated
with the feeder cables shall be run separate.
e)
Cables shall normally be run in one continuous length where practical but
underground joints may be installed when necessary. Cable joints shall be
recorded and their locations marked accurately on as built drawings.
f)
g)
h)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
i)
HV cables may be laid in the same trench or concrete duct banks with LV
cables but shall be separated by means of concrete blocks placed vertically.
j)
Cable routes shall normally follow the side of a road. Wherever possible HV
and LV should follow different sides.
k)
l)
Cable routes shall be kept away from underground pipelines containing hot
liquids or gases. If this is unavoidable, the pipelines shall be insulated to
limit their outside skin temperature to 60C maximum. Cables shall then
cross underneath those lines with separation of 300 mm minimum.
m)
n)
Cable Trench
a)
b)
Burial depth from finished grade to the top surface of the largest cable in the
trench, shall be 600 mm minimum. An exception is for trenches containing
only off-site lighting feeder and branch cables operating at 600 Volts or less
between conductors for which burial depth may be reduced to 460 mm
minimum.
c)
Sand bedding and protective covering. Cable shall be laid on top of a layer
of clean sandfill 150 mm thick, and then covered with a layer of clean sandfill
150 mm deep as measured from the top of the largest cable. A 50 mm thick
protective covering of red concrete (135 kg/cm2 compressive strength),
either precast slabs (preferred) or cast-in-place concrete (alternative) shall
be provided on top of the sand and the remainder of the trenches backfilled
with soil. The sand shall be compacted to prevent air pockets from forming
beneath the trench cover.
d)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
provided in order to place heavy duty steel plates over the trenches for
purpose of "bridging" during movement of vehicles, etc.
e)
C.
D.
Within process units, sandfilled concrete lined cable duct banks with red
concrete covers shall be used.
b)
Cable duct banks shall have concrete side walls and concrete bottom.
c)
d)
Burial depth form finished grade to the top surface of the largest cable in the
concrete duct bank shall be 150 mm minimum.
E.
F.
b)
Duct banks for buried cable systems shall consist of conduits encased in
concrete in accordance with paragraph 20 C.
c)
A separate conduit sleeve shall be provided for each circuit, except one
power cable and its associated control cable, such as a motor feeder and its
associated push-button circuit, may be run in the same conduit sleeve.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
a)
G.
Sleeves are not required where cables are extended above grade
beneath elevated substations.
b)
Cables entering buildings below grade shall pass through the building
foundation in individual metal conduit sleeves or pipe sleeves. Space
between cable and sleeves shall be sealed as to be liquid tight. Sealing
compound shall be impervious to liquids that may be in the ground.
c)
Direct buried cables shall be identified by the circuit number stamped on the
band attached to each cable as follows:
b)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
c)
d)
Trenches less that 2 m in width shall be provided with markers along the
centerline of the trench.
e)
21.
Location of Splices
CABLE TRAYS
A.
General
Where cable tray is used it shall conform to the following:
a)
The design and installation of the cable tray system shall conform to
applicable IEC Standards. The installation must also comply with the cable
tray manufacturer's recommended support and loading instructions.
b)
Cable trays shall be used for power, control, and instrument wiring in plant
distribution. Separate tray systems or trays with continuous barriers shall be
used for different classes of wiring.
c)
Cable trays shall be steel, hot dipped galvanized after fabrication, the cable
tray system will be continuous and shall use vertical elbows for major
changes in elevation. Vertical adjustable splice plates may be used where
there are slight changes of elevations, and shall be supported within 600 mm
of each side of the fitting.
d)
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
f)
The requirements of IEC Standards for ventilated, metallic cable tray shall
apply wherever applicable.
g)
Cable tray systems shall be of the design of one manufacturer and shall be
designed so that there are no burrs, projections or sharp edges to damage
cable insulation.
h)
All fittings shall have the same load capacity as straight sections. Fittings
shall be of the continuous type with a 600 mm radius unless otherwise
shown on the drawing.
i)
In general, ladder type cable trays shall be 7.3 m long and shall be of the
width indicated on the drawings to provide the planned cable capacity.
j)
Ladder type cable tray with 230 mm rung spacing will be used for
multi-conductor cable, heavy loading rated.
k)
All cable tray supports shall be of the "L" or "T" type to facilitate cable
installation, utilizing pipe rack wherever possible.
l)
m)
All cable tray runs will be made electrically continuous by means of suitable
approved jumpers. Tray sections shall be connected in such a way as to
ensure electrical continuity.
n)
o)
p)
Cable tray shall have a minimum load safety factor of 1.5. It shall also be
capable of carrying a 91 kg static concentrated load located at mid-span.
Control cables shall be laid between power cables to the maximum extent
possible.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
22.
b)
There shall be no more than two layers of multi-conductor 600 Volts power
cables sized 70 mm2. Cables greater than 70 mm2 shall be in a single layer
on the cable tray.
c)
Trays carrying only 600 V control or instrument cables may have cables
arranged in more than two layers.
d)
e)
CONDUIT
A.
Conduit Type
Conduit shall conform to the following:
B.
a)
Where circuit is used, it shall be rigid hot dipped galvanized steel conduit for
aboveground and underground installations. Aluminum conduit shall not be
used.
b)
b)
c)
d)
The minimum bending radius for underground conduits shall be 1200 mm for
all horizontal bends. The minimum bending radius for stub-ups shall follow
the manufacturers recommended minimum bending radius of the cable.
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
g)
h)
23.
Rigid steel conduit, conduit elbows, couplings, and similar fittings shall
be of steel with an outer zinc protective coating and an inner protective
coating of zinc, enamel, or equivalent corrosion resistant material.
Rigid steel conduit is preferred.
CABLES
A.
b)
c)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Sub-feeders from distribution centers to load shall be sized based upon the
nameplate rating of the load for motors and shall be size based upon the
IEC 60287and COVENIN 200 the latest edition.
e)
Sub-feeders
Voltage drop calculations shall be based on the minimum short circuit level
of the supply.
g)
For circuits above 600 Volts, the minimum size cable shall be the smallest
practical size dictated by the short circuit level and the protective devices of
the electrical system
h)
For lighting and power circuits 600 Volts and below, the smallest conductor
size shall be 2.5 mm2, except that 1.5 mm2 shall be used for controls.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
B.
i)
j)
k)
For off-site and remote areas supplying non-process loads, When a feeder
supplies more than one transformer its rating shall be at least equal to the
summation of the self-cooled (forced or cooled) ratings of all secondary
selective substations plus the self-cooled rating of all radial substation
transformer supplied by the feeder. This is to be approved by Owner.
l)
Lighting feeders feeding lighting panels shall have an ampacity not less than
the adjusted maximum demand of load or trip rating of the breaker.
m)
n)
Feeders supplying welding terminal boxes and outlets shall be sized based
on a 0.4 demand factor.
Cable Construction
a)
Conductors 2.5 mm2 and larger shall be stranded. Lighting circuits only, 4
mm2 shall be solid.
b)
In general, Type TC, sunlight resistant, Power & Control tray cable shall be
installed in cable tray.
c)
All cable shall comply with applicable portions of IEC Standards, COVENIN
200 the latest edition and other applicable recognized codes (CENELEC,
UTE, VDE, BS...) when IEC Standard have not yet been issued.
d)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
480V
6.9 kV
13.8 kV
34.5 kV
e)
f)
C.
0.6/1kV
6/10 kV
8.7/15 kV
26/45 kV
Basis of Design
a)
All cables furnished with shielding shall be terminated with stress cones
and grounded in accordance with the manufacturer's recommendation.
b)
One power circuit and its associated control circuit such as a motor feeder
shall be run in separate cables.
c)
Power system control, metering, alarm, and relaying circuits associated with
a Packaged Unit or with one major electrical equipment item, such as a
motor or transformer, may be run within one conduit, duct, tubing, or cable,
provided all circuits are insulated for 600 Volts or more. Remote tripping
circuits between substations may also be run within one multi-conductor
cable, except that:
Differential and pilot wire relay circuits shall be run in separate cables.
d)
Power system control, metering and signal circuits which run indoors for
major electrical equipment in the same building, such as between switchgear
and centralized control console, may be grouped in common cable tray.
e)
Motor space heater circuits may be run in the same cable with motor pushbutton circuits -- but not with the motor power (two cables) circuit -- between
the motor starter and motor, provided:
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
The space heater circuit is not extended into the motor push-button
enclosure.
f)
g)
Design shall not permit power circuits to enter or leave a metallic enclosure
with a separate entry or exit for any phase or neutral (if any) conductors, if
this would cause overheating of the enclosure due to induction. One
acceptable solution is for all conductors of the power circuits to be passed
through an insulating wall or sheet large enough to accommodate all
conductors.
h)
Telephone and signal circuits operating at less than 65 Volts may be run in
the same cable, duct, tubing, cable tray or cable trench with each other, but
not with circuits of higher voltage.
i)
j)
Quick disconnects shall not be used with motors rated above 600 volts.
Plugs and receptacles which are not interlocked with a switching device
shall be capable of safely interrupting motor locked rotor current.
Flexible cable shall not be used for motors larger than 40 kW.
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
D.
k)
l)
Critical wiring shall not be routed closer than 3 m horizontally to potential fire
hazards such as pumps and other high risk fire equipment. Critical wiring
routed between 3 and 7.5 m horizontally from potential hazards shall be
protected from fire. Protection shall consist of 50 mm covering of mineral
wool and an overall steel jacket. Ampacity of power wiring so protected shall
be derated to account for the thermal insulating effect of the protective
covering and jacket.
m)
Color Coding
a)
208Y/120 Volts
Phase A- Brown
Phase B- Orange
Phase C- Yellow
Neutral- Gray
Ground- Green (or
yellow/green)
Phase A- Black
Phase B- Red
Phase C- Blue
Neutral- White
Ground- Green
c)
All control leads, including those for push-button stations, interlock circuits,
instrument control circuits, current and potential transformer circuits, etc.,
shall be red.
d)
Power supplies to/from instruments shall be yellow (live line) and white for
the neutral.
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
24.
GROUNDING
A.
B.
C.
b)
c)
d)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
D.
e)
f)
E.
F.
Grounding and bonding for protection of the electrical system circuits and
equipment shall be installed to minimize damage in case of ground faults by
providing low fault impedance, thereby limiting the voltage to ground and
facilitating the operation of the overcurrent devices.
b)
c)
b)
c)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
d)
G.
H.
e)
f)
g)
Grounding Conductors
a)
Grounding conductor burial depths shall be at least 450 mm. Burial depths
in switch or transformer yards graded with stone shall be at least 300 mm
below the stone.
b)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
I.
b)
c)
Enclosure Grounding
a)
Metal enclosure for wire and cable such as conduits, cable trays and
raceways shall be grounded at their supply ends by connection to the
switchgear or control center ground bus, when such equipment is used; or
by connection to the grounded metallic equipment enclosures when
switchracks are used. The metal enclosures shall be metallically connected
to utilization equipment enclosures at their load end.
b)
The electrical continuity of metal enclosures for wire and cable shall be
assured between terminations.
c)
Metallic armor and sheaths, and metallic insulation shielding of all cables
shall be bonded together and grounded at the cables supply end by
connection to the switchgear or control center ground bus, when such
equipment is used; or by connection to the grounded metal equipment
enclosures when switchracks are used.
d)
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
f)
Single-conductor cables. Bonding and grounding methods for singleconductor cables having metallic armor, sheaths or insulation shielding must
be engineered for the specific installation to avoid dangerous sheath or
shield voltages or excessive heating due to circulating currents. Generally,
single-conductor cables smaller than 250 mm2 with all three phases in the
same duct may be bonded and grounded the same as multiconductor
cables. Armor, sheaths, and shielding of larger cables may require single
point grounding with insulating joint between grounded sections.
g)
h)
i)
j)
k)
l)
m)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
J.
Plug and receptacle shall be polarized and arranged so that the ground
connection makes first and breaks last.
n)
Metal enclosures such as fences, partitions, and grill work around equipment
operating above 600 Volts between conductors, shall be grounded by
connections to grounds in their immediate vicinity.
o)
Metal fences and grills enclosing the space under elevated substation
buildings shall be grounded by connections to ground in their immediate
vicinity.
GROUND RETURNS
a)
b)
If switchgear or control centers are used, the supply ends of ground return
paths shall terminate at the switchgear or control center ground bus.
c)
If switchracks are used, the supply ends of ground return paths shall
terminate by connection to the metal enclosure of the individual control
devices.
d)
e)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
f)
Armor or sheaths of metal clad cable used in circuits not more than 45
m in length and protected by overcurrent devices having a nominal
rating of 20 amperes or less.
Metal-enclosed bus duct enclosures where bus duct length does not
exceed 7.5 m.
The combined impedance of the ground return path and the supply circuit
line conductors shall be low enough to ensure operation of the circuit
overcurrent protective device in less than 2 seconds on a single line-to
ground fault at the load end of the circuit. An arc voltage of 40 Volts in
phase with the line-to-neutral source voltage shall be assumed at the fault
point. For receptacle circuits, the impedance of the plug connected portable
cord shall be included in the combined impedance used to check operation
of the protective device. Maximum cord length of 30 m shall be assumed.
NOTES:
25.
DC DISTRIBUTION SYSTEM
DC Distribution system, when is required, shall be provided to ensure continuous
power for controls of critical process equipment, instrumentation, communications and
other items necessary to provide safe and secure plant operations and control. The DC
Distribution System shall have a minimum 30 minutes of battery backup. The The DC
Distribution System will be provided in accordance with Specification CA04-04-33-PSP-006
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
.
26.
27.
28.
CATHODIC PROTECTION
If required, cathodic protection shall be provided for all metal structures exposed to soil
or water. Appropriate application shall be made on either impressed current or
sacrificial and methods for buried or immersed structures, vessels, pipes and tank
bars, refer to Specification CA04-04-33-P-SP-030.
29.
30.
B.
The heating cable type shall be dependent upon which is most technically and
economically feasible, and shall be suitable for the area classification and
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
exposure temperatures. The cable shall be sized for the required output per
meter or foot of pipe.
C.
For use in corrosive environment, the heater shall have an outer jacketing of
fluropolymer or other corrosion resistant construction.
D.
Thermostats for lower and upper limit control, as required, shall be provided.
a)
b)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
31.
B.
b)
c)
The requirements for fresh air intake, static design, stack designs and type
of building construction shall be indicated by Mechanical Design Discipline.
Design Requirements
a)
Substation buildings shall not have windows and shall be provided with at
least 1 personnel door and 1 equipment door (double door). The equipment
doors shall accommodate the largest assembled unit of equipment, using
standard size doors with removable panels above, if required. Preferably,
doors shall be located at opposite ends of the substation building and shall
be provided with weather proof louvers.
b)
The initial layout of the substation building shall be provided with space for
the addition of 20% future equipment.
c)
The building shall be provided with cable room approximately 1.8 m high
under beam to allow for routing and termination of cable. Cable room shall
be provided with doors wide enough to move dry type transformers.
d)
Where possible, 2 exit paths shall be provided out of the work space or the
operating aisle of switchgear or motor control equipment. 2 exits are
mandatory for every room containing electrical equipment that would have
length of more than 12 m.
In addition, the following minimum clearances around equipment shall be
provided:
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
Behind Switchgear
Between equipment ends or between ends and wall
Operating Aisle (between switchgear and control
centers)
800 mm
800 mm
1500 mm
or Manufacturers
Minimum
(greater of the two)
1200mm
e)
f)
g)
Substation building floors shall be level and smooth. Floor steel provided for
the mounting of switchgear and control equipment shall be installed even
with the finished floor and shall be perfectly level.
h)
i)
j)
k)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
C.
l)
m)
n)
o)
p)
SINCOR
Project Title: SINCOR, C. A.
UPSTREAM SURFACE FACILITIES PROJECT
32.
33.
INSPECTION
For shop information requirements, refer to the applicable equipment specification.
34.
STANDARDIZATION
A.
For ease of maintenance and to limit the spare parts inventory, it is intended that
as far as is practical, each class and category of electrical equipment shall be of
the same type and supplied by the same manufacturer wherever it is used on the
SINCOR Upstream Surface facilities.
When similar cases and categories of electrical equipment are included in
packages, vendors shall be required to purchase the same standard types.