Duration
VIPHotel
152days
GeneralConditions
21days
Finalizeplansanddevelopestimatewithowner,architect 20days
Signcontractandnoticetoproceed
1day
ApplyforPermits
0days
Securefoundationpermit
0days
Secureframingpermit
0days
Secureelectricalpermit
0days
Secureplumbingpermit
0days
SecureHVACpermit
0days
Securemiscellaneouspermits
0days
SiteWork
3days
Clearandgrublot
1day
Installtemporarypowerservice
1day
Installundergroundutilities
1day
Foundation
42days
Excavateforfoundations
3days
Formbasementwalls
13days
Placeconcreteforfoundations&basementwalls
12days
Curebasementwallsfor7days
7days
Stripbasementwallforms
2days
Waterproof/insulatebasementwalls
2days
Performfoundationinspection
1day
Backfillfoundation
2days
Framing
22days
Install1stfloorjoists
2days
Lay1stfloordecking
2days
Frame1stfloorwalls
4days
Frame1stfloorcorners
1day
Install2ndfloorjoists
2days
Frame2ndfloordecking
2days
Frame2ndfloorwalls
3days
Frame2ndfloorcorners
2days
Completeroofframing
3days
Conductframinginspection
1day
DryIn
22days
Install1stfloorsheathing
3days
Install2ndfloorsheathing
3days
Installroofdecking
3days
Installfelt,flashingandshingles
3days
Hang1stfloorexteriordoors
1day
Install1stfloorwindows
3days
Start
Finish
Jun22'16
Jan19'17
Jun22'16
Jun22'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul21'16
Jul21'16
Jul22'16
Jul25'16
Jul26'16
Jul26'16
Jul29'16
Aug17'16
Sep2'16
Sep13'16
Sep15'16
Sep19'16
Sep20'16
Sep22'16
Sep22'16
Sep26'16
Sep28'16
Oct4'16
Oct5'16
Oct7'16
Oct11'16
Oct14'16
Oct18'16
Oct21'16
Oct21'16
Oct24'16
Oct27'16
Oct21'16
Nov8'16
Nov11'16
Nov14'16
Jul20'16
Jul19'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul25'16
Jul21'16
Jul22'16
Jul25'16
Sep21'16
Jul28'16
Aug16'16
Sep1'16
Sep12'16
Sep14'16
Sep16'16
Sep19'16
Sep21'16
Oct21'16
Sep23'16
Sep27'16
Oct3'16
Oct4'16
Oct6'16
Oct10'16
Oct13'16
Oct17'16
Oct20'16
Oct21'16
Nov21'16
Oct26'16
Oct31'16
Oct25'16
Nov10'16
Nov11'16
Nov16'16
Predecessors
Resource Names
General
General
016
May
Jun
Qtr 3, 2016
Jul
Aug
Qtr 4, 2016
Oct
Nov
Sep
Qtr 1, 2017
Jan
Feb
Mar
Qtr 2, 20
Apr
General contractor[0.5],Architect[0.5],Owner[0.12],Mortga
General contractor,Architect,Owner,Mortgage lender
7/20
3
3
3
3
3
3
General
General
General
General
General
General
7/20
5,6,7,8,10,9
12
13
Siteexcavation
Electriccompany
Electric
14
16
17
18
19
20
21,16
22
Siteexcavation
Concrete
Concrete
23
25
26
27
28
29
30
31
32
33
Framing
Framing
Framing
Framing
Framing
Framing
Framing
Framing
Framing
Inspector
34
36
33
47
39
40
Framing
Framing
Framing
Roofing
Framing
Framing
7/20
7/20
7/20
7/20
7/20
Electric company
Electric contractor,Plumbing contractor
Site excavation contractor
Concrete contractor
Concrete contractor
Concrete contractor
Concrete
Concrete
Inspector
Siteexcavation
Concrete contractor
Inspector
Site excavation contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Inspector
Framing contractor
Framing contractor
Framing contractor
Roofing contractor
Framing contractor
Framing contractor
Task
Project Summary
Manual Task
Start-only
Deadline
Split
Inactive Task
Duration-only
Finish-only
Progress
Milestone
Inactive Milestone
External Tasks
Manual Progress
Summary
Inactive Summary
Manual Summary
External Milestone
Page 1
Dec
ID
Duration
Install2ndfloorwindows
3days
ExteriorFinishes
19days
Completeexteriorbrick
16days
Completeexteriorsiding
3days
UtilityRoughB97InsandCompleteConcrete
21days
Roughinplumbing
5days
Conductroughinplumbinginspection
1day
Placeconcreteforbasementfloor
11days
Roughinelectrical
5days
Conductroughinelectricalinspection
1day
RoughinHVAC
3days
ConductroughinHVACinspection
1day
Roughincommunicationphone,cable,computer,alarm 2days
InteriorFinishes
30days
Insulation
11days
Placewallinsulation1stfloor
1day
Placewallinsulation2ndfloor
1day
Placeceilinginsulation2ndfloor
1day
Conductinsulationinspection
1day
Drywall
9days
Installdrywall1stfloorwalls
2days
Installdrywall1stflooroverhead
2days
Installdrywall2ndfloorwalls
2days
Installdrywall2ndflooroverhead
2days
Tapeandfloat1stfloordrywall
1day
Tapeandfloat2ndfloordrywall
1day
PaintandWallpaper
17days
Textureallexceptentryandkitchen1stfloor
1day
Paintallexceptentryandkitchen1stfloor
1day
Hangwallpaperentryandkitchen1stfloor
1day
Textureall2ndfloor
1day
Paintall2ndfloor
1day
Paintexteriorsiding&trimwork
4days
Cabinets
6days
Install1stfloorkitchencabinets
2days
Install1stfloormasterbathandguestcabinets
1day
Install2ndfloorhallbathandprivatebathcabinets 1day
Installchairrails,crownmoldings,trim
2days
FinishPlumbing
6days
Complete1stfloorkitchenplumbing
1day
Complete1stfloormasterbathandguestplumbing 2days
Complete2ndfloorhallbathandprivatebath
2days
Start
Finish
Nov17'16
Nov22'16
Nov22'16
Dec14'16
Oct26'16
Nov1'16
Nov8'16
Nov9'16
Nov1'16
Nov8'16
Nov9'16
Nov14'16
Oct26'16
Nov22'16
Nov22'16
Nov22'16
Nov23'16
Dec5'16
Dec6'16
Nov23'16
Nov23'16
Nov25'16
Nov29'16
Dec1'16
Nov29'16
Dec5'16
Nov30'16
Nov30'16
Dec1'16
Dec2'16
Dec1'16
Dec2'16
Dec19'16
Dec5'16
Dec5'16
Dec7'16
Dec8'16
Dec9'16
Dec7'16
Dec7'16
Dec8'16
Dec12'16
Nov21'16
Dec16'16
Dec13'16
Dec16'16
Nov23'16
Nov7'16
Nov8'16
Nov23'16
Nov7'16
Nov8'16
Nov11'16
Nov14'16
Oct27'16
Jan2'17
Dec6'16
Nov22'16
Nov23'16
Dec5'16
Dec6'16
Dec5'16
Nov24'16
Nov28'16
Nov30'16
Dec2'16
Nov29'16
Dec5'16
Dec22'16
Nov30'16
Dec1'16
Dec2'16
Dec1'16
Dec2'16
Dec22'16
Dec12'16
Dec6'16
Dec7'16
Dec8'16
Dec12'16
Dec14'16
Dec7'16
Dec9'16
Dec13'16
Predecessors
Resource Names
016
May
Jun
Qtr 3, 2016
Jul
Aug
Sep
Qtr 1, 2017
Jan
Feb
Dec
Framing contractor
Mar
Qtr 2, 20
Apr
41
Framing
42
44
Masonry
Framing
38,37
47
48
38,37
50
51
52
38
Plumbing
Inspector
Concrete
Electriccontractor
Inspector
HeatingandAC
Inspector
Electriccontractor
36,42,54,52,50,37
57
65,58
59
Insulation
Insulation
Insulation
Inspector
Insulation contractor
57
62
63,58
64
63
65,66
Drywallcontractor
Drywallcontractor
Drywallcontractor
Drywallcontractor
Drywallcontractor
Drywallcontractor
Drywall contractor
66
69
70
69
72
45
Painting
Painting
Painting
Painting
Painting
Painting
71
76
77
78
Finishcarpentry
Finishcarpentry
Finishcarpentry
Finishcarpentry
76,48
81,77
82,78
Plumbing
Plumbing
Plumbing
Plumbing contractor
Masonry contractor
Framing contractor
Plumbing contractor
Inspector
Concrete contractor
Electric contractor
Inspector
Heating and AC contractor
Inspector
Electric contractor
Insulation contractor
Insulation contractor
Inspector
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Plumbing contractor
Plumbing contractor
Task
Project Summary
Manual Task
Start-only
Deadline
Split
Inactive Task
Duration-only
Finish-only
Progress
Milestone
Inactive Milestone
External Tasks
Manual Progress
Summary
Inactive Summary
Manual Summary
External Milestone
Page 2
Qtr 4, 2016
Oct
Nov
ID
100
101
102
103
104
105
106
107
108
Duration
Conductfinishplumbinginspection
FinishElectrical
Complete1stfloorcircuitstoservicepanel
Complete2ndfloorcircuitstoservicepanel
Conductfinishelectricalinspection
Completecommunicationswiringphone,cable,
FinishHVAC
Complete1stfloorzone1HVAC
Complete2ndfloorzone2HVAC
ConductHVACinspection
Carpet,TileandAppliances
Tileentry,kitchenandbaths
Carpet1stfloor
Carpet2ndfloor
Installappliances
LandscapingandGroundsWork
Pourconcretedrivewayandsidewalks
Installbackyardfence
Sodandcompleteplantingsfrontyard
Sodandcompleteplantingsbackyard
FinalAcceptance
Completefinalinspectionforcertificateofoccupancy
Cleanupforoccupancy
Performfinalwalkthroughinspection
Completepunchlistitems
1day
3days
1day
1day
1day
2days
3days
1day
1day
1day
8days
3days
2days
2days
1day
12days
2days
2days
2days
1day
8days
1day
1day
1day
5days
Start
Finish
Dec14'16
Dec14'16
Dec14'16
Dec15'16
Dec16'16
Dec15'16
Dec19'16
Dec19'16
Dec20'16
Dec21'16
Dec22'16
Dec22'16
Dec27'16
Dec29'16
Jan2'17
Dec23'16
Dec23'16
Jan3'17
Jan5'17
Jan9'17
Jan10'17
Jan10'17
Jan11'17
Jan12'17
Jan13'17
Dec14'16
Dec16'16
Dec14'16
Dec15'16
Dec16'16
Dec16'16
Dec21'16
Dec19'16
Dec20'16
Dec21'16
Jan2'17
Dec26'16
Dec28'16
Dec30'16
Jan2'17
Jan9'17
Dec26'16
Jan4'17
Jan6'17
Jan9'17
Jan19'17
Jan10'17
Jan11'17
Jan12'17
Jan19'17
Predecessors
Resource Names
016
May
Jun
Qtr 3, 2016
Jul
Aug
Sep
Dec
Qtr 1, 2017
Jan
Feb
Mar
Qtr 2, 20
Apr
83
Inspector
Inspector
83,51
86
87
84
Electriccontractor
Electriccontractor
Inspector
Electriccontractor
Electric contractor
89,53
91
92
HeatingandAC
HeatingandAC
Inspector
88,93
95
96
97
Flooring
Flooring
Flooring
Appliance
Flooring contractor
74
98,100
101
102
Concrete
Fencing
Landscape
Landscape
Concrete contractor
Electric contractor
Inspector
Electric contractor
Heating and AC contractor
Heating and AC contractor
Inspector
Flooring contractor
Flooring contractor
Appliance contractor
Fencing contractor
Landscape contractor
Landscape contractor
Inspector
103,93,88,84,60,79Inspector
98,105
Maidservice
106
Owner
107
General
Maid service
Owner
General contractor
Task
Project Summary
Manual Task
Start-only
Deadline
Split
Inactive Task
Duration-only
Finish-only
Progress
Milestone
Inactive Milestone
External Tasks
Manual Progress
Summary
Inactive Summary
Manual Summary
External Milestone
Page 3
Qtr 4, 2016
Oct
Nov