Sei sulla pagina 1di 3

ID

Task Mode Task Name


0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41

Project: VIP Hotel


Date: Jun 22 '16

Duration

VIPHotel

152days

GeneralConditions
21days
Finalizeplansanddevelopestimatewithowner,architect 20days
Signcontractandnoticetoproceed
1day
ApplyforPermits
0days
Securefoundationpermit
0days
Secureframingpermit
0days
Secureelectricalpermit
0days
Secureplumbingpermit
0days
SecureHVACpermit
0days
Securemiscellaneouspermits
0days
SiteWork
3days
Clearandgrublot
1day
Installtemporarypowerservice
1day
Installundergroundutilities
1day
Foundation
42days
Excavateforfoundations
3days
Formbasementwalls
13days
Placeconcreteforfoundations&basementwalls
12days
Curebasementwallsfor7days
7days
Stripbasementwallforms
2days
Waterproof/insulatebasementwalls
2days
Performfoundationinspection
1day
Backfillfoundation
2days
Framing
22days
Install1stfloorjoists
2days
Lay1stfloordecking
2days
Frame1stfloorwalls
4days
Frame1stfloorcorners
1day
Install2ndfloorjoists
2days
Frame2ndfloordecking
2days
Frame2ndfloorwalls
3days
Frame2ndfloorcorners
2days
Completeroofframing
3days
Conductframinginspection
1day
DryIn
22days
Install1stfloorsheathing
3days
Install2ndfloorsheathing
3days
Installroofdecking
3days
Installfelt,flashingandshingles
3days
Hang1stfloorexteriordoors
1day
Install1stfloorwindows
3days

Start

Finish

Jun22'16

Jan19'17

Jun22'16
Jun22'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul21'16
Jul21'16
Jul22'16
Jul25'16
Jul26'16
Jul26'16
Jul29'16
Aug17'16
Sep2'16
Sep13'16
Sep15'16
Sep19'16
Sep20'16
Sep22'16
Sep22'16
Sep26'16
Sep28'16
Oct4'16
Oct5'16
Oct7'16
Oct11'16
Oct14'16
Oct18'16
Oct21'16
Oct21'16
Oct24'16
Oct27'16
Oct21'16
Nov8'16
Nov11'16
Nov14'16

Jul20'16
Jul19'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul20'16
Jul25'16
Jul21'16
Jul22'16
Jul25'16
Sep21'16
Jul28'16
Aug16'16
Sep1'16
Sep12'16
Sep14'16
Sep16'16
Sep19'16
Sep21'16
Oct21'16
Sep23'16
Sep27'16
Oct3'16
Oct4'16
Oct6'16
Oct10'16
Oct13'16
Oct17'16
Oct20'16
Oct21'16
Nov21'16
Oct26'16
Oct31'16
Oct25'16
Nov10'16
Nov11'16
Nov16'16

Predecessors

Resource Names

General
General

016
May

Jun

Qtr 3, 2016
Jul
Aug

Qtr 4, 2016
Oct
Nov

Sep

Qtr 1, 2017
Jan
Feb

Mar

Qtr 2, 20
Apr

General contractor[0.5],Architect[0.5],Owner[0.12],Mortga
General contractor,Architect,Owner,Mortgage lender
7/20

3
3
3
3
3
3

General
General
General
General
General
General

7/20

5,6,7,8,10,9
12
13

Siteexcavation
Electriccompany
Electric

Site excavation contractor

14
16
17
18
19
20
21,16
22

Siteexcavation
Concrete
Concrete

23
25
26
27
28
29
30
31
32
33

Framing
Framing
Framing
Framing
Framing
Framing
Framing
Framing
Framing
Inspector

34
36
33
47
39
40

Framing
Framing
Framing
Roofing
Framing
Framing

7/20
7/20
7/20
7/20
7/20

Electric company
Electric contractor,Plumbing contractor
Site excavation contractor
Concrete contractor
Concrete contractor
Concrete contractor

Concrete
Concrete
Inspector
Siteexcavation

Concrete contractor
Inspector
Site excavation contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Inspector
Framing contractor
Framing contractor
Framing contractor
Roofing contractor
Framing contractor
Framing contractor

Task

Project Summary

Manual Task

Start-only

Deadline

Split

Inactive Task

Duration-only

Finish-only

Progress

Milestone

Inactive Milestone

Manual Summary Rollup

External Tasks

Manual Progress

Summary

Inactive Summary

Manual Summary

External Milestone

Page 1

Dec

ID

Task Mode Task Name


42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83

Project: VIP Hotel


Date: Jun 22 '16

Duration

Install2ndfloorwindows
3days
ExteriorFinishes
19days
Completeexteriorbrick
16days
Completeexteriorsiding
3days
UtilityRoughB97InsandCompleteConcrete
21days
Roughinplumbing
5days
Conductroughinplumbinginspection
1day
Placeconcreteforbasementfloor
11days
Roughinelectrical
5days
Conductroughinelectricalinspection
1day
RoughinHVAC
3days
ConductroughinHVACinspection
1day
Roughincommunicationphone,cable,computer,alarm 2days
InteriorFinishes
30days
Insulation
11days
Placewallinsulation1stfloor
1day
Placewallinsulation2ndfloor
1day
Placeceilinginsulation2ndfloor
1day
Conductinsulationinspection
1day
Drywall
9days
Installdrywall1stfloorwalls
2days
Installdrywall1stflooroverhead
2days
Installdrywall2ndfloorwalls
2days
Installdrywall2ndflooroverhead
2days
Tapeandfloat1stfloordrywall
1day
Tapeandfloat2ndfloordrywall
1day
PaintandWallpaper
17days
Textureallexceptentryandkitchen1stfloor
1day
Paintallexceptentryandkitchen1stfloor
1day
Hangwallpaperentryandkitchen1stfloor
1day
Textureall2ndfloor
1day
Paintall2ndfloor
1day
Paintexteriorsiding&trimwork
4days
Cabinets
6days
Install1stfloorkitchencabinets
2days
Install1stfloormasterbathandguestcabinets
1day
Install2ndfloorhallbathandprivatebathcabinets 1day
Installchairrails,crownmoldings,trim
2days
FinishPlumbing
6days
Complete1stfloorkitchenplumbing
1day
Complete1stfloormasterbathandguestplumbing 2days
Complete2ndfloorhallbathandprivatebath
2days

Start

Finish

Nov17'16
Nov22'16
Nov22'16
Dec14'16
Oct26'16
Nov1'16
Nov8'16
Nov9'16
Nov1'16
Nov8'16
Nov9'16
Nov14'16
Oct26'16
Nov22'16
Nov22'16
Nov22'16
Nov23'16
Dec5'16
Dec6'16
Nov23'16
Nov23'16
Nov25'16
Nov29'16
Dec1'16
Nov29'16
Dec5'16
Nov30'16
Nov30'16
Dec1'16
Dec2'16
Dec1'16
Dec2'16
Dec19'16
Dec5'16
Dec5'16
Dec7'16
Dec8'16
Dec9'16
Dec7'16
Dec7'16
Dec8'16
Dec12'16

Nov21'16
Dec16'16
Dec13'16
Dec16'16
Nov23'16
Nov7'16
Nov8'16
Nov23'16
Nov7'16
Nov8'16
Nov11'16
Nov14'16
Oct27'16
Jan2'17
Dec6'16
Nov22'16
Nov23'16
Dec5'16
Dec6'16
Dec5'16
Nov24'16
Nov28'16
Nov30'16
Dec2'16
Nov29'16
Dec5'16
Dec22'16
Nov30'16
Dec1'16
Dec2'16
Dec1'16
Dec2'16
Dec22'16
Dec12'16
Dec6'16
Dec7'16
Dec8'16
Dec12'16
Dec14'16
Dec7'16
Dec9'16
Dec13'16

Predecessors

Resource Names

016
May

Jun

Qtr 3, 2016
Jul
Aug

Sep

Qtr 1, 2017
Jan
Feb

Dec

Framing contractor

Mar

Qtr 2, 20
Apr

41

Framing

42
44

Masonry
Framing

38,37
47
48
38,37
50
51
52
38

Plumbing
Inspector
Concrete
Electriccontractor
Inspector
HeatingandAC
Inspector
Electriccontractor

36,42,54,52,50,37
57
65,58
59

Insulation
Insulation
Insulation
Inspector

Insulation contractor

57
62
63,58
64
63
65,66

Drywallcontractor
Drywallcontractor
Drywallcontractor
Drywallcontractor
Drywallcontractor
Drywallcontractor

Drywall contractor

66
69
70
69
72
45

Painting
Painting
Painting
Painting
Painting
Painting

71
76
77
78

Finishcarpentry
Finishcarpentry
Finishcarpentry
Finishcarpentry

Finish carpentry contractor

76,48
81,77
82,78

Plumbing
Plumbing
Plumbing

Plumbing contractor

Masonry contractor
Framing contractor
Plumbing contractor
Inspector
Concrete contractor
Electric contractor
Inspector
Heating and AC contractor
Inspector
Electric contractor

Insulation contractor
Insulation contractor
Inspector

Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor

Finish carpentry contractor


Finish carpentry contractor
Finish carpentry contractor

Plumbing contractor
Plumbing contractor

Task

Project Summary

Manual Task

Start-only

Deadline

Split

Inactive Task

Duration-only

Finish-only

Progress

Milestone

Inactive Milestone

Manual Summary Rollup

External Tasks

Manual Progress

Summary

Inactive Summary

Manual Summary

External Milestone

Page 2

Qtr 4, 2016
Oct
Nov

ID

Task Mode Task Name


84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99

100
101
102
103
104
105
106
107
108

Project: VIP Hotel


Date: Jun 22 '16

Duration

Conductfinishplumbinginspection
FinishElectrical
Complete1stfloorcircuitstoservicepanel
Complete2ndfloorcircuitstoservicepanel
Conductfinishelectricalinspection
Completecommunicationswiringphone,cable,
FinishHVAC
Complete1stfloorzone1HVAC
Complete2ndfloorzone2HVAC
ConductHVACinspection
Carpet,TileandAppliances
Tileentry,kitchenandbaths
Carpet1stfloor
Carpet2ndfloor
Installappliances
LandscapingandGroundsWork
Pourconcretedrivewayandsidewalks
Installbackyardfence
Sodandcompleteplantingsfrontyard
Sodandcompleteplantingsbackyard
FinalAcceptance
Completefinalinspectionforcertificateofoccupancy
Cleanupforoccupancy
Performfinalwalkthroughinspection
Completepunchlistitems

1day
3days
1day
1day
1day
2days
3days
1day
1day
1day
8days
3days
2days
2days
1day
12days
2days
2days
2days
1day
8days
1day
1day
1day
5days

Start

Finish

Dec14'16
Dec14'16
Dec14'16
Dec15'16
Dec16'16
Dec15'16
Dec19'16
Dec19'16
Dec20'16
Dec21'16
Dec22'16
Dec22'16
Dec27'16
Dec29'16
Jan2'17
Dec23'16
Dec23'16
Jan3'17
Jan5'17
Jan9'17
Jan10'17
Jan10'17
Jan11'17
Jan12'17
Jan13'17

Dec14'16
Dec16'16
Dec14'16
Dec15'16
Dec16'16
Dec16'16
Dec21'16
Dec19'16
Dec20'16
Dec21'16
Jan2'17
Dec26'16
Dec28'16
Dec30'16
Jan2'17
Jan9'17
Dec26'16
Jan4'17
Jan6'17
Jan9'17
Jan19'17
Jan10'17
Jan11'17
Jan12'17
Jan19'17

Predecessors

Resource Names

016
May

Jun

Qtr 3, 2016
Jul
Aug

Sep

Dec

Qtr 1, 2017
Jan
Feb

Mar

Qtr 2, 20
Apr

83

Inspector

Inspector

83,51
86
87
84

Electriccontractor
Electriccontractor
Inspector
Electriccontractor

Electric contractor

89,53
91
92

HeatingandAC
HeatingandAC
Inspector

88,93
95
96
97

Flooring
Flooring
Flooring
Appliance

Flooring contractor

74
98,100
101
102

Concrete
Fencing
Landscape
Landscape

Concrete contractor

Electric contractor
Inspector
Electric contractor
Heating and AC contractor
Heating and AC contractor
Inspector

Flooring contractor
Flooring contractor
Appliance contractor

Fencing contractor
Landscape contractor
Landscape contractor
Inspector

103,93,88,84,60,79Inspector
98,105
Maidservice
106
Owner
107
General

Maid service
Owner
General contractor

Task

Project Summary

Manual Task

Start-only

Deadline

Split

Inactive Task

Duration-only

Finish-only

Progress

Milestone

Inactive Milestone

Manual Summary Rollup

External Tasks

Manual Progress

Summary

Inactive Summary

Manual Summary

External Milestone

Page 3

Qtr 4, 2016
Oct
Nov

Potrebbero piacerti anche