Sei sulla pagina 1di 93

1

Project Report 2012

Mini Civil Station at Chittur

1. INTRODUCTION
The urban society lures people with better job opportunities and better
standard of living resulting in population explosion and scarcity of habitable
space. The construction of multi-storied building will help to incorporate
various building of some nature under the same shelter to serve a common
purpose. The vertical growth of buildings also helps to save a large area of
land also the various offices which come under the Taluk Office, Chittur are
situated in different parts of the taluk. There are many other govt. offices in
Chittur which functioned in rented buildings, so all these officer can be
incorporated in a single building called Mini Civil Station Chittur, so that the
public an avail all the services from a common civic centre.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Mini Civil Station at Chittur

2. LOCATION
The proposed site is situated in near the existing sub-court Chittur. It is near
by the Chittur-Gopalapuram-Pollachiroad, 15KM away from the Palakkad
town. The proposed office complex has a north orientation facing the ChitturGopalapuram-Pollachi highway.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

Mini Civil Station at Chittur

Govt Polytechnic

Project Report 2012

Mini Civil Station at Chittur

TOPOGRAPHY
The site is having a plane topography.

SOIL CHARACTERISTICS
Soil stratum in the region is uniform.

FUTURE NEEDS
The mini civil station Chittur is in order to incorporate all the govt.
offices in Chittur under one shelter. So this will help the people of Chittur to
get things done easily and speedily.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Mini Civil Station at Chittur

3. DATA COLLECTION
GENERAL
The information regarding the proposed building was obtained
from the Executive Engineer-P.W.D-Palakkad. And Assistant-Executive
Engineer, Palakkad surveyand got rough idea about the site and
surroundings. Then for getting the detailed site plan filed survey were
conducted. Along with this to get information regarding soil characteristics,
soil investigation is done.

RECONNAISSANCE SURVEY
It is process the preliminary inspection of area to be surveyed. In
this we should not the boundaries, the position of building, road etc.
After completion of the reconnaissance a rough sketch is prepared
which is known as index sketch or key plan. The key plan shows the position
of salient features on the ground such as buildings, roads, boundaries with
respect to north direction.

PREPARATION OF SITE PLAN


After completing the key plan, the process chain survey is done
and the site plan is prepared.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Mini Civil Station at Chittur

ORIENTATION
The planning of the building with respect to the geographical
direction of wind and azimuth, of sun is known as orientation of building.
The building should be placed to attain maximum benefit from same air and
nature and the same time it is protected from their harmful effect. In towns
orientation of building is decided on various factor like the position and
direction of steeds and position of gardens and parks, the shape and size of
the plot of land etc. in such cases the orientation should be fixed with respect
to the frontage of building only.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Mini Civil Station at Chittur

4. DATA SURVEY
Total number of offices to be provided

= 9 Nos. 3EF

Total number of staff calculated

= 145 Nos.

Gazette Officers

= 13 Nos.

Non Gazette Officers

= 132 Nos.

Canteen

= 1 No.

Toilet and A/c

= 3 sets/E

Area required for G.O


Office

= 14.86 m2

Toilet

= 1.5 m2

Area required for N.G.O


Office

= 3.72 m2 /E

Records

= 0.37 m2

Dining

= 0.46m2/Each Office

Toilet
Male

= 1.5 m2

Female

= 1.5 m2

Urinal
Male

= 1.5 m2

Female

= 1.5 m2

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Mini Civil Station at Chittur

5. SPACE REQUIREMENTS
Sl. No.

Name of office

Space required

Space provided

1.

Taluk Industries

40.05 m2

47.50 m2

2.

Taluk Supply Office

90.14 m2

99.75 m2

76.47 m2

80.75 m2

3.
4.

Town Employment Exchange

44.61 m2

47.50 m2

5.

Taluk Statical

90.14 m2

99.75 m2

6.

A.R.CO.OP (G) Chittur

76.47 m2

80.75 m2

7.

Sub R.T.O, Chittur

71.92 m2

79.75 m2

8.

Asst.Director-Agricultural

44.61 m2

47.50 m2

9.

Soil Conservation

94.68 m2

99.75 m2

10.

Food Inspector

35.50 m2

49.75 m2

11.

A.R.CO.OP (A), Chittur

80.01 m2

80.75 m2

12.

A.E.O, Chittur

71.92 m2

79.75 m2

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Mini Civil Station at Chittur

6. STRUCTURAL DESIGN

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

10

Mini Civil Station at Chittur

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

11

Mini Civil Station at Chittur

Govt Polytechnic

12

Project Report 2012

Mini Civil Station at Chittur

A. ABBREVIATIONS USED
A

= Area

= Overall depth of beam or slab

= Effective depth of beam or slab

Ld

= Development length

Ix

= Length of shorter side of slab

Iy

= Length of longer side of slab

= Bending moment

= Modular ratio

= Spacing of stirrups

= Torsional moment

= Shear force

cbc

= Permissible stress in concrete

st

= Permissible stress in steel

Ast

= Area of tension steel

= Leverarm constant

bf

= Effective width of flange

bw

= Breadth of web

Df

= Thickness of flange

= Total load

= Modulus of section

= Shear stress in concrete

c max

= Maximum shear stress in concrete

= Normal shear stress

= Diameter of the bar

B. ROOF SLAB S1
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

13

Project Report 2012

Mini Civil Station at Chittur

Wall thickness

= 24 cm

Size of room

= 9.5 x 5.00 m

Height of room

= 3.60 m

Grade of concrete

= M20

Grade of steel

= Fe415

PROPERTIES OF THE SECTION


cbc

= 7 N/mm2

st

= 230 N/mm2

= 13.3

= 0.904 d

= 0.914 bd2

Basic value of l/d ratio

= 32

Assume a modification factor

= 1.6

Approximate effective depth required

= 4870 / (32 x 1.6)


= 95.20

Provide an effective depth of 105mm and an overall depth of 125mm


EFFECTIVE SPAN
C/C distance of supports

= 4.87 & 5.24 m

Width of support

= 0.24 m

Clear span

= 4.87 0.24

= 4.63 m

= 5.24 0.24

= 5.00 m

lx

= 4.63 + 0.105

= 4.735 m

Ly

= 5.00 + 0.105

= 5.105 m

= 5.105/4.735

= 1.10 <2

Effective span,
Ly / lx ratio

Hence two way slab

LOADS
Live load

= 1.5 KN/m2

Weight of weathering course

= 1.5 KN/m2

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

14

Project Report 2012

Mini Civil Station at Chittur

Self weight of slab

= 1x 0.125 x 25

Total load, W

= 6.125 KN/m2

= 3.125 KN/m2

DESIGN OF PANEL-1
In panel 1, three edges are continuous and one short edge
is discontinuous
Bending moment :Consider 1m width of middle strips
+mx

= x x W x lx2

= 0.032 x 6.125 x 4.7352

= 4.39 KNm

-my

= x x W x lx2

= 0.043 x 6.125 x 4.7352

= 5.90 KNm

+mx

= y x W x lx2

= 0.028 x 6.125 x 4.7352

= 3.84 KNm

-my

= y x W x lx2

= 0.037 x 6.125 x 4.7352

= 5.08 KNm

Depth required for strength :Z

= 0.904d

M.R

Effective depth required

= 0.914bd2
5.90 x 106

0.914 x 1000
Eff depth, d provide

= 80.34mm

= 105mm > 80.34 mm

Hence O.K

Middle strip reinforcement :Using 8mm bars with a clear cover of 16mm,
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

Project Report 2012

15

Mini Civil Station at Chittur

Effective depth available in longer span

= 125-16-4

= 105mm

Effective depth available in shorter span

= 105-8

= 97mm

Width of middle strip in longer span

= x 5.24

= 3.93m

Width of middle strip in shorter span

= x 4.87

= 3.65m

Longer span:
Ast required at midspan

= 3.84 x 106
_____________

230 x 0.904 x 97
Ast required at support

= 190.39mm2

= 5.08 x 106
_____________

230 x 0.904 x 97

= 251.88mm2

Shorter span:
Ast required at midspan

= 4.39 x 106
_____________

230 x 0.904 x 105


Ast required at support

= 201.08mm2

= 5.90 x 106
_____________

230 x 0.904 x 105


Minimum area of steel to be provided

= 270.25mm2

= 0.12/100 x 1000 x 125


= 150 mm2

Spacing:Longer span:
Spacing at middle

= 50 x 1000 x 190.39

= 262.60mm

= Say 260mm
Spacing at support

= 50 x 1000/251.88

= 198.49mm

= Say 195mm
Shorter span:
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

Project Report 2012


Spacing at middle

16

Mini Civil Station at Chittur

= 50 x 1000/201.08

= 248.60mm

= Say 245mm
Spacing support

= 50 x 1000/270

= 185.18mm

= Say 185mm
Edge strip reinforcement:Area of steel required for edge strip

= 150 mm2

Spacing of 8mm bars

= 50 x 1000/150
= 333mm
= Say 330mm

Maximum permitted spacing

= 450mm

DESIGN OF PANEL 2
In panel-2, two adjacent sides are discontinuous.
Bending moment:Consider 1m width of middle strips
+mx

= x x W x lx2 = 0.040 x 6.125 x 4.7352

= 5.49 KNm

-my

= x x W x lx2 = 0.053 x 6.125 x 4.7352

= 7.23 KNm

+mx

= y x W x lx2 = 0.035 x 6.125 x 4.7352

= 4.81 KNm

-my

= y x W x lx2 = 0.047 x 6.125 x 4.7352

= 6.45 KNm

Middle strip reinforcement :Longer span:


Ast required at midspan
Dept of Civil Engineering
College, Palakkad

= 4.81 x 106
Govt Polytechnic

Project Report 2012

17

Mini Civil Station at Chittur

_____________

230 x 0.904 x 97
Ast required at support

= 238.49mm2

= 6.45 x 106
_____________

230 x 0.904 x 97

= 319.86mm2

Shorter span:
Ast required at midspan

= 5.49 x 106
_____________

230 x 0.904 x 105


Ast required at support

= 251.47mm2

= 7.23 x 106
_____________

230 x 0.904 x 105


Minimum area of steel to be provided

= 331.17mm2

= 0.12/100 x 1000 x 125


= 150 mm2

Spacing:Longer span:
Spacing at middle

= 50 x 1000 x 238.49

= 209.65mm

= Say 205mm
Spacing at support

= 50 x 1000/319.81

= 156.3mm

= Say 155mm

Shorter span:
Spacing at middle

= 50 x 1000 x 51.47

= 209.65mm

= Say 205mm
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

18

Project Report 2012


Spacing at support

Mini Civil Station at Chittur

= 50 x 1000/331.17

= 154.96mm

= Say 150mm
Edge strip reinforcement:Area of steel required for edge strip

= 150 mm2

Spacing of 8mm bars

= 50 x 1000/150
= 333mm
= Say 330mm

Torsion reinforcement :Corners having two discontinuous edges,


Size of reinforcement mesh

= 0.2 lx
= 0.2 x 4.735 = 0.947m

Area of steel req. at midspan of middle strip

= 251.47mm2

Area of steel req./ one layer of torsion reinforcement 75%


= x 251.47 x 0.947
Number of 6mm bars/layer

= 178.60mm2
= 178.60/28

= 7 Nos.

Provide 4 layers of 6Nos x 6mm bars at corners having two discontinuous edges.
Check for stiffness :Area of steel provided at midspan of shorter span.

% of steel

= 195
_______
50 x 1000

= 256.41mm2

= 256.41 x 100

= 0.24%

_____________
1000 x 105
M.F

= 1.50

Effective depth required

B.V = 32
= 4735/ (32 x 1.5)
= 98.64mm

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

19

Project Report 2012


Effective depth provided, d

Mini Civil Station at Chittur

= 105mm>98.64mm, Hence O.K

Wall thickness

= 24 cm

Size of room

= 10.4 x 9.50 m

Height of room

= 3.60 m

Grade of concrete

= M20

Grade of steel

= Fe415

PROPERTIES OF THE SECTION


cbc

= 7 N/mm2

st

= 230 N/mm2

= 13.3

= 0.904 d

= 0.914 bd2

SIDE RATIO
The side ratio of each panel

= 9.5/3.467

= 2.74>2

This slab is designed as continuous one way slab


DEPTH REQUIRED FOR STIFFNESS
C/C distance of supports

= 3.467m

Basic value

= 26

M.F

= 1.4

Approx. effective depth req. = 3467/ (26 x 1.4) = 95.24mm


Provide overall depth of 125mm and effective depth 105mm
EFFECTIVE SPAN
Width of supports

= 240mm

Clear span/12

= 268.9mm

Width of support < clearspan/12


240 <268.9mm
Effective span is the least of,
1. Clear span + effective depth
Dept of Civil Engineering
College, Palakkad

= 3.467 + 0.015

= 3.572m
Govt Polytechnic

20

Project Report 2012


2. C/C distance of supports

Mini Civil Station at Chittur

= 3.467 + 0.24

= 3.707m

Effective span

= 3.57m

LOADS
Consider 1m width of slab,
Live load

= 1.5 KN/m2

Weight of weathering course

= 1.5 KN/m2

Self weight of slab

= 1 x 0.125 x 25

Total load, W

= 6.125 KN/m2

= 3.125 kN/m2

MAXIMUM B.M
WL2 /10 WL2/9

= 1.5 X 3.572/10 4.625 X 3.572/9


= 8.45 KNm

DEPTH REQUIRED FOR STRENGTH


Z

= 0.904d

Effective depth required

M.R

= 0.914bd2

8.45 x 106

0.914 x 1000 = 96.15mm


Eff depth , d provided

= 105mm > 96.15


Hence O.K

DESIGN BENDING MOMENT


1.B.M near middle of end span

= M1

= 4.625 x 3.572/12 + 1.5 x 3.572/10


= 6.82 KNm

2. B.M at middle of interior span

= M2

= 4.625 x 3.572/24 + 1.5 x 3.572/12


= 4.04 KNm

3. B.M at support next to end support

= M3

= 1.5 x 3.572/10-4.625 x 3.572/9


= 8.45 KNm

2. B.M at interior support

= M4

= 4.625 x 3.572/24 - 1.5 x 3.572/9


= 7.03 KNm

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

21

Project Report 2012

Mini Civil Station at Chittur

MAIN REINFORCEMENT
Minimum area of steel provided

= 0.15 x 1000 x 125


____
100
= 187.5mm2

Area of steel Ast1

= 6.82 x 106
_________
230 x 0.904 x 105

Area of steel Ast2

4.04 x 106
_________
230 x 0.904 x 105

Area of steel Ast3

= 387.05mm2

7.03 x 106
_________
230 x 0.904 x 105

Area of steel Ast5

= 185.05mm2

8.45 x 106
_________
230 x 0.904 x 105

Area of steel Ast4

= 312.39mm2

= 322.01mm2

3.25 x 106
_________
230 x 0.904 x 105

= 148.98mm2

S1

= 50 X 1000/312.39

= 160mm c/c

S2

= 50 X 1000/185.05

= 270mm c/c

S3

= 50 X 1000/387.05

= 125mm c/c

S4

= 50 X 1000/322.01

= 155mm c/c

S5

= 50 X 1000/148.98

= 315mm c/c

SPACING OF MAIN BARS

DISTRIBUTORS
Area of steel required (0.12%)

Dept of Civil Engineering


College, Palakkad

= 0.12 x 1000 x 125


_____
100
= 150 mm2
Govt Polytechnic

22

Project Report 2012

Mini Civil Station at Chittur

Spacing of 8mm bars = 50 x 1000/150


Maximum permitted spacing

= 333.33
= 5d or 450mm

Provide 8mm Fe415 distributors at 330mm c/c


CHECK FOR SHEAR
Maximum S.F at the outer side of support next to end support,
V = 0.6 Wdl + 0.6Wsl
= 0.6 x 3.57 (3125+3000)
= 13119.75KN
Nominal stress, v

= 13119.75
_________
1000 x 105

Minimum value of v

= 0.24

= 0.17

Hence O.K
CHECK FOR STIFFNESS
% Steel
= 100As
______
bd

13119.75
_________
1000 x 105

M.F

= 1..42

Mid span Ast

= 50 x 1000/160

Effective depth req. for stiffness

= 0.29%

= 312.5mm2
= 3.57
______
26 x 1.42

= 96.69 mm2

Effective depth provided 105> 96.69mm


Hence O.K

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

23

Mini Civil Station at Chittur

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

24

Mini Civil Station at Chittur

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

25

Mini Civil Station at Chittur

Govt Polytechnic

26

Project Report 2012

Mini Civil Station at Chittur

C. T BEAM UNDER ROOF SLAB


SIZE OF BEAM
Clear span

= 5000mm

Span/12

= 5000/12

= 416.67mm

Span/15

= 5000/15

= 333.33mm

The overall depth may be assumed as 410mm and


effective depth 370mm
Thickness of slab, Df

= 125mm

Depth of web

= 410 125

Assume, Breadth of the web

= 205mm

= 285mm

LOAD / METRE LENGTH OF BEAM


Since the beam are spaced at 4.87m centre. One metre length
Of beam carries load transferred from 4.87 m2 area of slab
Live load from slab

= 1.5 x 4.87

= 7.305KN

Weight of slab

= 4.87 x 0.125 x 25

= 15.22KN

Weight of weathering coarse

= 1.5 x 4.87

= 7.305KN

Self weight of web

= 0.205 x 0.285 x s 25= 1.710KN

Total

= 31.54KN/m

EFFECTIVE SPAN
Effective depth of beam is greater than the width of supports,
Effective span of the beam is

= C/C distance of supports


= 5.00 + 0.24

= 5.24m

DESIGN B.M
Maximum B.M midspan = Wl2/8
M = 31.54 x 5.242/8

= 108.25 x 106 Nmm

APPROXIMATE LEVER ARM


Z = Assume

= 0.9d

Z = 0.9 x 370

= 333mm

APPROXIMATE AREA OF STEEL


Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

27

Project Report 2012


Approximate tension steel required

Mini Civil Station at Chittur


=

M
st x Zapp

= 108.25 x 106
230 x 333
= 1413.36 mm2
= 1570 mm2

Provide 5 Nos of 20mm bar


EFFECTIVE WIDTH OF FLANGE
bf

= 10/ 6+bw + 6Df

= 5240/6 + 205 + 6 x 125


= 1828.33mm

ACTUAL N.A
Moment of flange area about its bottom

= 1828.33 x 125 x125/2


= 14.28 x 106

Modular ratio, m

= 13.3

Moment of equivalent steel area about the bottom of flange,


= 13.3 x 1570 x 45
= 5.11 x 106 KNm
The moment of flange area is more the neutral axis lies with in the flange.
Taking moments of area about the N.A
= 1828.33/2 x2a

= 13.3 x 1570 (370-xa)

= 914 x2a

= 7725970 20881 xa

= xa

= 81.22mm

ACTUAL LEVER ARM


Lever arm,

= 370 81.22/3

= 342.43mm

STRESS IN CONCRETE
Actual compressive stress in concrete and tensile stress in steel cbc
And st respectively.
= bf.xa/2 . cbc .z

=M

= 1828.33/2 x 81.22 x cbc x 342.93


= cbc
Dept of Civil Engineering
College, Palakkad

= 108.25 x 106

= 2 x 108.25 x106
1828.33 x 81.22 x 342.93
Govt Polytechnic

28

Project Report 2012

Mini Civil Station at Chittur

= cbc

= 4.25N/mm2

cbc = 4.25 < 7 N/mm2 ,

Hence O.K

STRESS IN STEEL
= Ast . st . z = M
= st

=M
Ast . z
= 108.25 x 106
1570 x 342.93

= st

= 201.1N/mm2

st = 201.1 < 230 N/ mm2

CHECK FOR STIFFNESS


B.V

= 20

% Tension reinforcement

= 1570 x 100
1828.33 x 370

M.F

= 1.85

Web width /Flange width

= 205 / 1828.33

Reduction factor

= 0.76

Effective depth required for stiffness

= 5240
20 x 1.85 x 0.76

Provide effective depth, d

= 370> 186.34mm,

= 0.23%
= 0.112

= 186.34mm
Hence O.K

D. T- BEAM UNDER FLOOR SLAB


Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

29

Project Report 2012

Mini Civil Station at Chittur

SIZE OF BEAM
Clear span

= 5240mm

Span/12

= 5000/12

= 436mm

Span/15

= 5000/15

= 349mm

The overall depth may be assumed as 435mm and


effective depth 395mm
Thickness of slab Df

= 135mm

Depth of web

=435 135

Assume, Breadth of the web

= 300mm

= 240mm

LOAD / METRE LENGTH OF BEAM


Since the beam are spaced at 4.87m centre. One metre length
of beam carries load transferred from 4.87 x 1

= 4.87m2 area of slab

Live load from slab

= 3.0 x 4.87

= 14.61KN

Weight of slab

= 4.87 x 0.135 x 25

= 16.44KN

Weight of floor finish

= 1.0 x 4.87

= 4.870KN

Self weight of web

= 0.300 x 0.240 x 25 = 1.800KN

Total

= 37.72KN/m

EFFECTIVE SPAN
Effective depth of beam is greater than the width of supports,
Effective span of the beam is

= C/C distance of supports


= 5.24 + 0.24

= 5.48m

DESIGN B.M
Maximum B.M at midspan

= Wl2 / 8

M = 37.72 x 5.482 /8

= 141.59 x 106 Nmm

APPROXIMATE LEVER ARM


Z = Assume

= 0.9d

Z = 0.9 x 395

= 355.50mm

APPROXIMATE AREA OF STEEL


Approximate tension steel required

M
st x Zapp

= 141.59 x 106
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

30

Project Report 2012

Mini Civil Station at Chittur


230 x 355.5
= 1835 mm2
= 1884mm2

Provide 6 Nos of 20mm bar


EFFECTIVE WIDTH OF FLANGE
bf

= 10 /6+bw + 6Df

= 5480 / 6 +240 +6 x 135


= 1963mm

ACTUAL N.A
Moment of flange area about its bottom = 1963 x 135 x135 /2
= 17.89 x 106
Modular ratio, m

= 13.3

Moment of equivalent steel area about the bottom of flange,


= 13.3 x 1884 x 260
= 6.51 x 106 KNm
The moment of flange area is more the neutral axis lies with in the flange.
Taking moments of area about the N.A
= 1963/2 x2 a

= 13.3 x 1884 (395-xa)

= 981.5 x2 a

= 9897594 25057.2 xa

= xa

= 88.46mm

ACTUAL LEVER ARM


Lever arm,

= 395 88.46/3

= 365.51mm

STRESS IN CONCRETE
Actual compressive stress in concrete and tensile stress in steel cbc
And st respectively.
= bf . xa/2 . cbc . z

=M

= 1963/2 x 88.46 x cbc x 365.51


= cbc

= 141.59 x 106

= 2 x 141.59 x 106
1963 x 88.46 x 365.51

= cbc

= 4.46 N/mm2

cbc = 4.46 < 7 N/ mm2, Hence O.K


Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

31

Project Report 2012

Mini Civil Station at Chittur

STRESS IN STEEL
= Ast . st. z = M
= st

= M
Ast.z
= 141.59 x 106
1884 x 365.51
= 205.61 N/mm2

= st
CHECK FOR STIFFNESS
B.V

= 20

% Tension reinforcement

= 1884 x 100
1963 x 370

M.F

= 1.55

Web width ? Flange width

= 240 / 1963

Reduction factor

= 0.76

Effective depth required for stiffness

= 5480

= 0.26%
= 0.12

20 x 1.55 x 0.76
Provide effective depth, d

Dept of Civil Engineering


College, Palakkad

= 395> 232.60mm ,

= 232.60mm

Hence O.K

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

32

Mini Civil Station at Chittur

Govt Polytechnic

Project Report 2012

33

Mini Civil Station at Chittur

E. DESIGN OF STAIR
Assume width of flight

= 1.50m

Height up to middle landing

= 1.80m

Rise

= 150mm

Tread

= 300mm

No. of riser

= 1800/150

No. of tread

= 12 1 = 11 Nos

Assume support beams

= 300 x 300mm

= 12 Nos

EFFECTIVE SPAN
Horizontal distance c/c of beams

= 11 300 300

= 3.00m

Effective width of waist slab,


Since on of the edge of the slab is embedded in to the wall for a
length of 120mm.
Effective width of waist slab

= 1500 + 75

= 1575mm

Width of loaded area

= 1500 150

= 1350mm

Live load

= 5000 x 1.35 x 1

= 6750 N/m

Weight of step

= 1000/30 x 1/12 x 0.3 x 0.15 x 19000

LOADS
Consider full width of slab,

= 2137.5 N/m
Assume the thickness of waist as span in metres 50mm,
i.e,

= 3.00 x 50

= 150mm

Weight of waist slab,metre inclined length = 1.5 x 0.15 x 1 x 25000


= 5625 N
Weight of waist slab /metre horizontal length = 5625 3002 + 1502
300
= 6525 N/m
Weight of finish

= 800 x 1.5 x 1

Total load

= 6750 + 2137.5 + 6525 + 1200

Dept of Civil Engineering


College, Palakkad

= 1200 N/m

Govt Polytechnic

34

Project Report 2012

Mini Civil Station at Chittur

= 16612.5 N/m
B.M & S.F
Maximum B.M at midspan

= 16612.5 x 32 / 8

= 18.689 KNm

Maximum S.F at support

= 16612.5 x 3 / 2

= 24.918 KN

DEPTH REQUIRED
M20 , Fe415 grade concrete and steel are used,
Z

= 0.904d

M.R

= 18.689 x 103
0.914 x 1575

= 0.914bd2
= 113.95

= Say 115mm

= 115 + 15 + 10/2

= 135mm

Providing 10mm bar with 15mm clear cover,


Total thickness required

Provide 135mm thick slab with an effective depth of 115mm


MAIN REINFORCEMENT
Area of steel required

= 18689.1 103
= 781.61mm2

230 x 0.904 x 115


Number of 10mm bar required

= 781.61/78.5

= 9.95
= Say 10 Nos

DISTRIBUTORS
Area of steel required

= 0.12/100 x 1000 x 135


= 162mm2

Spacing of 8mm bars

= 50 x 1000/162

= 308.64mm

Provide 8mm bars distributor at 300mm c/c


CHECK FOR SHEAR
Nominal shear stress

= 24918.75
1575 x 115

= 0.14 N/mm2

Minimum value of permissible shear stress

= 0.22 N/mm2

Hence the slab is safe against shear.


CHECK FOR STIFFNESS
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

Project Report 2012


B.V

35

Mini Civil Station at Chittur

= 20

% of tension reinforcement

= 10 x 78.5 x 100
1575 x 115

M.F

= 0.43%

= 1.34

Effective depth required for stiffness

= 3000
20 x 1.34

= 111.94mm

d provided 115mm>111.94mm, Hence O.K

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

36

Project Report 2012

Mini Civil Station at Chittur

F. DESIGN OF FOUNDATION
Thickness of brick wall

= 240mm

Angle of repose

= 300

Weight of brick masonry

= 19 KN/m3

Safe bearing capacity of soil

= 150KN/m3

Specific weight of soil

= 16 KN/m3

Ultimate crushing strength of c.c foundation

= 15N/mm2

LOADS
Weight from wall

= 1 x 10.8 x 0.24 x 19

= 49.25KN/m

Weight of slab
Ground floor

= Dead + Live + Weathering coarse or Floor finish


= (3.125 +3 +1) 4.47

= 31.85KN/m

First floor

= (3.125 +3 +1) 4.47

= 31.85KN/m

Roof

= (3.125 +1.5 +1) 4.47

= 25.14KN/m

Total

= 138.1 KN

Add 10% for foundation design


Total load

= 13.8 KN
= 138.1 + 13.8
= 151.9KN

WIDTH OF FOUNDATION
= Total load/ Bearing capacity of soil
= 151.9 / 150 = 1.01m
DEPTH REQUIRED
Rankines formula

= D1

= po

r
D1

= 150

16
Depth required

Dept of Civil Engineering


College, Palakkad

[ 1-sin ]2
1-sin

[ 1-sin 30 ]2
1-sin 30

= 1.04 m

Govt Polytechnic

37

Project Report 2012

Mini Civil Station at Chittur

G. DESIGN

OF LINTEL CUM
SUNSHADE OVER 100 x
150mm WINDOW

DESIGN OF SUNSHADE
Effective span

= 600mm,

Clear projection

Assume uniform thickness of 60mm with an effective depth of 42mm


= 60 15 6/2 = 42mm
Considering one metre length of sunshade,
Self weight of sunshade

= 10.6 x 0.06 x 25000


= 900N

Live load of sunshade

= 450N

Total

= 1350N

Maximum B.M at support

= 1350 x 600 / 2
= 405000Nmm

Using M20 and Fe415 grade concrete and steel,


Z=

0.904d

Effective depth required

0.914bd2

M.R =
=

405000
0.914 x 1000

= 21.61m

d provide = 42mm> 21.61mm. Hence O.K


Area of steel required

405000
230 x 0.914 x 42 = 50.74mm2

Minimum area of steel to be provided

= 0.10/100 x 1000 x 60
= 60mm2

Spacing of 6mm bars

= 28 x 1000/60

= 466mm
= Say 200mm c/c

Provide 4 Nos of 6mm bars as distributor

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

38

Project Report 2012

Mini Civil Station at Chittur

DESIGN OF LINTEL
Assume size of lintel

= 240 x 150mm

Using 6mm bars,

cover

= 20mm

Effective depth available

= 150 20 6/2

= 127mm

1. C/C of bearings

= 1.0 + 0.15

= 1.150m

2. Opening + Effective depth

= 1.0 + 0.127

= 1.127m

Effective span

Effective span, l
Height of triangle

= 1.127m
= 0.866l

Height of wall above opening

= 0.976m
= 1.50m

Height of wall above the lintel

= 1.50 0.15

= 1.35m

The height of wall above the lintel is greater than 0.866l, triangular
Loading has to be assumed on the lintel.
Weight of triangular portion of masonry,
W1

= x 1.127 x 0.976 x 0.24 x 19000


= 2507.89N

Weight of sunshade

= 1.127 x 0.6 x 0.06 x 25000


= 1014.3N

Self weight of lintel

= 0.24 x 0.15 x 1.127 x 25000


= 1014.3N

Live load on sunshade


Total UDL

= 1.127 x 0.6 x 50
W2

= 507.15N

= 1014.3 + 507.15 + 1014.3


= 2535.75N

Maximum B.M
Maximum B.M at midspan

= W1l / 6 + W2 l/ 8

= 2507.89 1.127 + 2535.75 1.127


6

Dept of Civil Engineering


College, Palakkad

= 828.3Nm

Govt Polytechnic

39

Project Report 2012

Mini Civil Station at Chittur

DESIGN OF LINTEL CUM


SUNSHADE OVER 150 x 150mm
WINDOW
DESIGN OF SUNSHADE
Effective span

= 600mm,

Clear projection

Assume uniform thickness of 60mm with an effective depth of 42mm


= 60 15 6/2 = 42mm
Considering one metre length of sunshade,
Self weight of sunshade

= 10.6 x 0.06 x 25000


= 900N

Live load of sunshade

= 450N

Total

= 1350N

Maximum B.M at support

= 1350 x 600 / 2
= 405000Nmm

Using M20 and Fe415 grade concrete and steel,


Z=

0.904d

Effective depth required

0.914bd2

M.R =
=

405000
0.914 x 1000

= 21.61m

d provide = 42mm> 21.61mm. Hence O.K


Area of steel required

405000
230 x 0.914 x 42 = 50.74mm2

Minimum area of steel to be provided

= 0.10/100 x 1000 x 60
= 60mm2

Spacing of 6mm bars

= 28 x 1000/60

= 466mm
= Say 200mm c/c

Provide 4 Nos of 6mm bars as distributor

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

40

Project Report 2012

Mini Civil Station at Chittur

DESIGN OF LINTEL
Assume size of lintel

= 240 x 150mm

Using 6mm bars,

cover

Effective depth available

= 20mm
= 150 20 6/2

= 127mm

1. C/C of bearings

= 1.5 + 0.15

= 1.650m

2. Opening + Effective depth

= 1.5 + 0.127

= 1.627m

Effective span

Effective span, l
Height of triangle

= 1.627m
= 0.866l

Height of wall above opening


Height of wall above the lintel

= 1.627m
= 1.50m

= 1.50 0.15

= 1.35m

The height of wall above the lintel is less than 0.866l, the total rectangular
Portion of the masonry above the lintel is considered
Weight of triangular portion of masonry,
= 1.627 x 1.35 x 0.24 x 19
= 9.27 KN
Self weight of lintel

= 0.24 x 0.15 x 1.627 x 25


= 1046 KN

Total UDL

= 10.73 KN

Maximum B.M
Maximum B.M at midspan

= 10.73 x 1.6272 / 8

Effective depth required

3.50 x 106
0.914 240

= 3.5 KNm
= 126.87mm

Effective depth provided

= 127mm> 126.87 Hence O.K

Area of tension steel required

= 3.5 x 106
230 x 0.904 x 127

Provide 5 numbers of 6mm bars at bottom

= 31.36mm2
= 140 mm2

Provide 2 numbers of 6mm bars at top as hangers

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

41

Mini Civil Station at Chittur

Govt Polytechnic

Project Report 2012

Dept of Civil Engineering


College, Palakkad

42

Mini Civil Station at Chittur

Govt Polytechnic

Project Report 2012

43

Mini Civil Station at Chittur

7. DETAILED SPECIFICATION
1.EARTH WORK EXCAVATION IN FOUNDATION.
Foundation trenches shall be dug out to the exact width of foundation
concrete and the side be vertical, the sides should be stopped back of
protected with timber shoring. Excavation earth shall not be placed within in
of edge of the trench.
Bottom of the foundation trenches shall be perfectly leveled both
longitudinally and transversely and the side of the trench shall be dress
perfectly vertical from bottom up to the least thickness of loose concrete so
that concrete may be laid to the exact width as per design. The bed of the
trench shall be slightly watered and well rammed. Excess deigning done
through shall be filled with concrete at the expense of contractor. If the rocks
of builders are in foundation during excavation, these should be removed.
The measurements of excavation trench shall be taken in cubic meter as for
rectangular trench bottom width of concrete multiplied by the vertical depth
of foundation from ground level and multiplied by the length of trenches.
The measurement shall be taken separately every 50m lead and 1.5m lift.
2. CEMENT CONCRETE 1:4:8 FOR FOUNDATION
Fine aggregate should be clean, hard sand and durable, course aggregated
should be of hard broken stone of granite of similar stone. Free from dust or
other matter. Size of course aggregate shall be 40mm, cement shall be fresh
Portland cement of I S I specification. The proportion of concrete shall be
1:4:8 as cement : sand course aggregate by volume centering shuttering shall
be provided as required as per specification. Concrete shall be laid gently in
layer of 15mm thick and compacted by roads and tempering with wooden
timbers after about 2 hours layering in concrete the surfaces should be kept
we with water.
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

Project Report 2012

44

Mini Civil Station at Chittur

3. RANDOM RUBBLE MASONRY FOR FOUNDATION AND


BASEMENT.
The stones shall be of hard, sound and durable of provoked quarry stone
shall be hammer dressed to secure close joint. So the stones when laid will
come in to close proximity. Stones shall be fairly equally in size, mortar shall
be of cement mortar 1:5 materials of mortar shall be standard specification
and joint shall not be thicker than 20mm the masonry shall be kept wet for
10 days. The measurement shall be taken in cubic metre.
4. BRICK WORK FOR SUPER STRUCTURE.
All bricks shall be first class for standard specifications made of good
brick, earth thoroughly burnt and shall be deep every red or copper colour.
Brick shall be regular in shape and their edge should be square and shall emit
clear ringing sound on being stuck and shall be free from cracks, chips flows
and lumps any kind. Bricks shall not absorb water more than sixth of their
weight. After one hour of snaking by immersing in water bricks shall have a
minimum crushing strength of 150 kg/cm2 mortar shall be specified be
bonded and laid in English bond wall shall be truly in plump. Vertical joints
of consecutive courses not come over one another. Brick shall be kept wet
for a period of 10 days after lay. Measurement taken in cubic meter.
5. CENTERING AND SHUTTERING OF R.C.C. WORK.
Shuttering shall be either of hard wooden plant 30mm thick or the steel
plates shifted by angle iron. The shuttering shall be supported on batten,
beams etc to make a rigid form work. Beam for centering shall be carried out
and supported on the walls with double wedges underneath and supported at
interval with props, prop shall consist of brick pillars. The shuttering shall
have smooth uneven surfaces and joints shall close tight centering and
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

Project Report 2012

45

Mini Civil Station at Chittur

shuttering shall not be removed before 14 days in general and shall be


removed slowly and carefully without any snack. Centering and shuttering
shall be measured in square meters.
6. REINFORCED CEMENT CONCRETE FOR ROOF SLAB, FLOOR
SLAB, BEAM, LINTEL ETC.
Steel reinforcement bars shall be of mild seal of standard specifications
and shall be free from corrosion, rose rust scales, oils, grease, paints etc. The
steel bars shall be round and capable of being bend without fracture. Bars
shall be looked and bend accurately and placed in position as for design and
drawing. Cement concrete shall be 1:2:4 proportion by volume for slabs,
beams, lintels and column. Sand and broken stone shall be of standard
specifications. Mixing done by means of machine or manually. Laying of
concrete is done after the steel reinforcement placed in position. The
concrete shall be compacted by mechanical vibrating machine. Laying the
concrete surfaces should be kept wet with water. Measurement is done in
cubic metres.
7. DOORS AND WINDOWS.
Timber shall be of the kind specified may be teak, sal, anjaly, decodar etc.
The timber shall be best qualities, well seasoned and free from raps, knots,
warps, cracks and other defects. All wood work shall be planed and neatly
and correctly finished to the exact dimensions. All joints shall be neat and
strong and truly and accurately filled and glould before filled together.
The shutters may be parallel as specified the thickness of shuutte shall be
3cms 5cms as specified. All doors have handless on inner slab. The
necessary linges and bolts shall be provided. The chock lots shall be
measured in cubic metres and the shuttering shall be measured in square
metre.
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

Project Report 2012

46

Mini Civil Station at Chittur

8. GLASS FOR SHUTTERS.


Glass shall be of the best quality and free from the defects. The thickness
of glass shall be of 3mm or as specified. The rebate shall be painted be for
glass is fixed.
9. CEMENT MORTAR.
The proportion of cement and sand shall be as specified may be 1:3 to
1:6 the materials shall be done first dryb on an platform and them mixed
with water, cement and shall be measured with boxes to have the required
proportion. First sand is spread on the platform and the required quantity of
cement is spread on the top of the sand and the whole mixed dry. The
mixture shall be then formed roughly in to a cone shape and water is added
slowly and then the hole mixed thoroughly to have a uniform colour and
consistency.
10. POINTING.
The joint of brick work shall be rocked out to a depth of 20mm and the
surface of the wall washed and cleaned and kept wet for 2 day before
pointing. The materials of mortar shall be of standard specification. Mortar
shall be applied in the joints slightly in excess and pressed by a proper tool
of the required shape. Extra mortar of any is removed and surface is finished.
The measurements shall be taken in the square meters.
11. WHITE WASHING.
Fresh white lime should be mixed with sufficient water to make a thin
cream, the quantity of water shall be 5 liters of water percent Kg of lime, the
surface should be clean from dust and dirt. After cleaning white wash shall
be applied two coats. For final coat, base pigment powder should be mixed
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

Project Report 2012

47

Mini Civil Station at Chittur

to give bright white surface. The measurement shall be kept in square


meters.
12. PAINTING.
The branch of paint shall be an readymade of the required colours should
be coated. For new work are primary coated and two coats of paint shall be
used. The paint shall be applied with brushes. The measurement shall be
taken in square metres. Each coat should be perfectly dry before next coat is
applied.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

48

Mini Civil Station at Chittur

8. DESIGN OF SEPTIC TANK


Number of user

= 100

Assume rate of water supply

= 1000ml / head / day

Assume detention period as 24 hours and twice of cleaning the


Sludge as 24 hours.
Space required for setting

= 100 x 100/ 1000

= 10m2

Space required for dig stone

= 100 x 0.425

= 4.25 m2

Space required for storage of sludge

= 100 x 0.085

= 8.5 m2

Total space required

= 10 + 4.25 + 8.5

= 22.75m3

Assume liquid depth

= 2m

Plan area of septic tank

= 22.75 / 2

Assume length

= 4.5m

Breadth

= 11.375 / 4.5

Provide free board

= 50cm

Total depth

= 2 + 0.50

Size of tank

= 4.5 x 2.5 x 2.5m

= 11.375 m2
= 2.5m
= 2.50m

9. DESIGN OF SOAKPIT
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

49

Project Report 2012

Mini Civil Station at Chittur

Sewage to soak pit

= 100 x 60

Assume the depth of soak pit as

= 2.5 m

= 6000 liters = 6m3

= d2 x 2.5 = 6
4
d2

= 6 x 4/2.5 = 3.05

= 1.75m

Design of c.c projection,


Assume overall depth, D

= 100mm
D

= 100 15 8/2

= 81mm

Effective span

= 1000 mm

Load
Live load

= 1.5KN/m

Need load

= 1 x 0.1 x 25

= 2.5 KN/m

Total

= 4 KN/m

B.M & S.F


Maximum B.M at support

= Wl /2

=4x

= 2 KN/m

Shear force

= Wl

=4x1

= 4KN

Maximum B.M at support

= Wl /2

=4x

= 2 KN/m

Shear force

= Wl

=4x1

= 4KN

Check for effective depth


D req.

= M

Rb

2 x 106

0.914 x 100

= 46.77mm

46.77 <81 mm, Hence O.K


Assuming 8mm bars
Ast =

M
st x jd

Spacing

2 x 106

230 x 0.904 x 100


= 50 x 1000 /120

= 96.19mm2
= 416.6mm
= Say 40s0mmc/c

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

Item

Description

Dept of Civil Engineering


College, Palakkad

50

No Length

Mini Civil Station at Chittur

Breadth

Height

Quantity

Remarks

Govt Polytechnic

51

Project Report 2012


No.

Mini Civil Station at Chittur

.
SEPTIC

TANK

1.

Earth work excavation

5.40

3.40

2.70

49.57m3

2.

P.C.C 1:3:6

5.40

3.40

0.20

3.672m3

3.

First class brick work


First footing

15.20

0.30

1.50

6.84m3

Second footing

14.80

0.20

1.00

2.96m3

Cover slab

4.90

2.90

0.10

1.421

Buffle wall

2.60

0.05

0.60

0.078

(3.14/4x

0.502)

0.01

0.02

4.

R.C.C work

Deduction
Manhole

1.479m3
5.

20 mm thick plastering

6.

50 cm dia cast iron

14.00

2.45

@ 56 kg

34.3m2

manhole cover with frame

56 kg

7.

100 mm dia S.W.Tee

2 Nos

8.

A.C ventilation cowl

1 No.

9.

100 mm dia S.W pipe

2 Nos.
SOAKPIT

1.

Earth work

( x 2.752

/4)

2.875

17.85m3

2.

P.C.C

( x 1.752

/4)

0.30

0.72m3

3.

Brick work

( x 2.152

/4)

2.80

10.17m3

4.

Brick aggregate

( x 2.452

/4)

2.00

9.43m3

5.

Course sand

( x 2.752

/4)

0.075

11.88m3

6.

R.C.C 1:2:4

( x 2.152 /4)

0.27m3

7.

Plastering

( x 1.75

13.74m2

Sl no.

Quantity

Dept of Civil Engineering


College, Palakkad

Description of work

x 2.5)

Unit

Rate

Amount

Govt Polytechnic

52

Project Report 2012

Mini Civil Station at Chittur

SEPTIC TANK
1

49.57m3

Earth work excavation

10 m3

2125.20

10534.62

4.297m3

P.C.C 1:4:8 for foundation

m3

4009.61

17229.29

980m3

Brick work in cm 1:5

m3

2695.37

36214.63

103.293

R.C.C work

10d m3

59.11

6088.33

34.30m3

Plastering

10 dm3

1590.89

5456.75

56 kg

6588.98

3688.70

Nos.

170

140.00

Total =

79352.32

50mm dia cast iron man hole


cover

2 Nos

100 mm S.W pipe

SOAK PIT
1

17.03 m3

Earth work excavation

10 m3

2125.20

3619.21

0.72 m3

Plain cement concrete

m3

4009.61

2886.91

10.17 m3

Brick work

m3

3695.37

7581.92

9.43 m3

Brick aggregate

m3

591.00

5573.13

11.88 m3

Coarse sand

m3

1860.00

22096.80

0.273 m3

R.C.C 1:2:4

10d m3

59.11

1613.70

13.74 m2

Plastering

10 m2

1590.89

2185.88

Total =

75557.85

10. DETAILED ESTIMATE


GROUND FLOOR
Item

Description

Dept of Civil Engineering


College, Palakkad

No.

Length

Breadth

Height

Quantity

Remarks

Govt Polytechnic

53

Project Report 2012

Mini Civil Station at Chittur

No
1.

2.

3.

4.

Item

Clearing and leveling


the site including
uprooting of trees up
to 30 cm grith etc.
Earth work excavation
in hard soil and
deposited on bank
with initial lead up to
50m and lift up to
1.5m including
breaking clouds water
remaining etc.
complete.
For
foundations(walls)
for pillars
Plain cement concrete
1:4:8 using nominal
size broken stone for
base concrete
for walls
For pillars
R.R masonry in c.m
1:6 for foundation and
basement for
foundation
Foundation
for walls
for pillars
Basement
For walls
For pillars

Description

L.S

45.00

25.00

1125
=1125m2

1
11

205.24
1.20

1.20
1.20

1.20
1.20

295.65
19.01
=314.56m3

1
11

205.24
1.20

1.20
1.20

0.20
0.20

49.26
3.168
=52.43m3

1
11

210.34
0.90

0.90
0.90

1.00
1.00

189.306
8.91

1
11

217.14
0.50

0.50
0.50

0.50
0.50

54.285
1.375
=253.93m3

No.

Length

Breadth

Height

Quantity

Remarks

No
5.

Earth filling inside


the basement.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

54

Project Report 2012

6.

Taluk industry
Taluk supply
Computer room
Rest room
A.R Co-op (A)
Verandah
Toilet verandah

1
1
1
1
1
1
1

8.98
10.14
5.50
5.22
9.24
36.18
9.48

4.74
9.24
2.74
3.24
8.24
2.24
2.74

0.50
0.50
0.50
0.50
0.50
0.50
0.50

21.28
46.84
7.535
8.456
38.06
40.52
12.98
=175.67m3

First class brick work


c.m 1:6 for
superstructure and
steps
24 cm walls
10 cm wall
for pillars
Steps
1st
2nd
3rd

1
1
11

180.10
43.0
0.45

0.24
0.10
0.45

3.60
3.60
3.60

155.60
15.48
8.019

1
1
1

4.00
4.00
4.00

0.30
0.30
0.30

0.17
0.34
0.50

0.20
0.408
0.60
=180.23

2.50

0.24

3.10

4.32

7
3
8
13
11
3

1.00
0.90
0.80
1.50
1.00
0.50

0.24
0.10
0.10
0.24
0.24
0.24

2.10
2.00
2.00
1.50
1.50
0.50

3.52
0.54
1.28
7.02
3.96
0.48

92.34

0.24

0.15

3.34

Length

Breadth

Height

Quantity

Deduction
For opening
(Balcony)
Doors & windows
D
D1
D2
W
W1
W3
Lintels
All round

Item

Mini Civil Station at Chittur

Description

No.

Remarks

No
Above doors and
windows (inside)
Above D1
Dept of Civil Engineering
College, Palakkad

1
3

30.96
1.20

0.24
0.10

0.15
0.10

1.114
0.036
Govt Polytechnic

55

Project Report 2012


Above W1
Above D2
Opening
Portico entrance
open
7.

Item

Mini Civil Station at Chittur

4
8
9
1

1.30
1.10
5.46 (are
4.50

0.10
0.10
a)
0.24

0.10
0.10
0.24
3.00

0.052
0.088
11.79
3.24
=41.988
=138.75m3

1
1
1
Qua
1

36.92
11.60
62.36
ntity sa
4.97

12.72
10.4
0.60
me as th
4.48

0.135
0.135
0.060
at for ite
0.11

63.39
16.28
2.24
m no.6 4.63
2.44

Stair case
Landing slab
Waist slab
Steps

1
2
22

3.24
3.76
(1/2x0.1

1.74
1.62
5x0.3)

0.110
0.110
1.20

0.620
1.340
0.594

Beams
Beam 1
Beam 2
Beam 3
Beam 4
Beam 5
Beam 6
Beam 7
Under portico slab 1
2
Above pillar

1
2
1
2
9
1
1
1
1
3
3

5.00
9.52
8.50
3.00
2.50
4.58
5.34
4.97
4.60
11.36
10.18

0.24
0.24
0.24
0.24
0.24
0.24
0.24
0.30
0.30
0.40
0.40

0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.40
0.40

0.36
1.368
0.612
0.43
1.62
0.329
0.384
0.447
0.36
5.45
4.88

R.C.C 1:2:4 using


20mm broken stone
for slab, lintel
sunshade etc.
Slab
Main all round
Above pillars
Sunshade
Lintel
Portico slab

Description

No.

Length

Breadth

Height

Quantity

Rise=0.15
Tread=0.3

=105.34

Remarks

No
Deduction
Landing slab
opening in
stair area
Dept of Civil Engineering
College, Palakkad

4.92

3.10

0.135

2.05
=20.05
=103.25m3
Govt Polytechnic

56

Project Report 2012

8.

9.

DPC 2.5cm with c.c


24cm wall
12 cm wall

1
1

Reinforcement tie
and place in position
etc. complete at
0.85% by volume of
concrete

Mini Civil Station at Chittur

217.66
70.14

0.50
0.50

0.85/100

x 103.25

108.83
35.07
=143.90m2

x 78.5

68.12
=68.92 q

1
99.28
14x4 0.45

3.60
3.60

357.41
90.72

3
3
2

4.00
4.00
0.303

0.17
0.3

2.04
3.60
0.61

2x2
2x1

4.97
4.97

0.30
0.30

5.964
5.964

1x3

4.00

0.30

3.60

No.

Length

Breadth

Beam 3
Beam 4

9
9

11.36
10.18

0.40
0.40

40.896
36.452

Sunshade
Top & bottom

62.36

0.60

37.42

10.
Plastering with c.m
1:5
12mm thick on
exposed surface of
wall and inside
surface of wall and
steps.
Out side plastering
Main wall all round
Pillar
Steps
Face
Tread
Sides
Beams
Beam 1 side
Face

(area)

Beam 2

Item

Description

Height

Quantity

Remarks

No

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

57

Project Report 2012

Mini Civil Station at Chittur

Face

62.36

0.06

3.74
=635.23

Deduction
Balcony open
Opening

2
9

2.50
5.46(area)

3.60

18.00
49.14
=67.14
=568.09m2

1
1
1
1
1
1
1
1
1X2

29.00
39.8
17.52
17.48
36.00
68.04
17.52
7.76
44.1

3.60
3.60
3.60
3.60
3.60
3.60
3.60
3.60
3.60

104.4
143.25
63.07
62.93
129.60
244.94
63.07
27.94
317.52

1X2
1X1
1

70.92
70.92
16.12

0.30
0.24
16.12

42.55
17.02

Inside plastering
Taluk industry
Taluk supply
Stair room
Rest room
Toilet verandah
Verandah
Computer room
Wall
10 cm wall
Beams
Side
Bottom
Stair

=1313.08
Deduction
D

1.00

2.10

14.70

D1

0.90

2.00

5.40

D2

0.80

2.00

12.8

No.

Length

Breadth

13

1.50

1.50

29.25

11

1.00

1.50

16.50

0.50

0.50

2.00

Item

Description

Height

Quantity

Remarks

No
W
W1
V

=80.65
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

58

Project Report 2012

Mini Civil Station at Chittur


=1232.42m2

11.

Wood work for the


frames of doors and
windows
Doors
D

6.20

0.07

0.10

0.303

D1

6.00

0.07

0.10

0.126

D2

5.80

0.07

0.10

0.32

13

9.00

0.07

0.10

0.819

W1

11

7.50

0.07

0.10

0.577

2.00

0.07

0.10

0.112

Windows

12.

13.

Item

=2.257m3

Wood work for the


shutters of fully
paneled doors
D

1.98

0.88

12.19

D1

1.88

0.78

4.39

D2

1.88

0.68

10.22
=26.80m2

13X3

0.427

1.38

W1

11X2

0.415

1.38

8X1

0.38

0.38

22.98
12.60
1.155
=36.73m2

Length

Breadth

Shutters of fully
glazed windows

Description

No.

Height

Quantity

Remarks

No
14.

Painting for doors


and windows two
coats over one coat
wooden primer used
over approved quality

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

59

Project Report 2012

15.

in cement paint
D

1.00

2.10

2.25

33.07

D1

0.90

2.00

2.25

12.15

D2

0.80

2.00

2.25

28.8

13

1.50

1.50

1.00

29.25

W1

11

1.00

1.50

1.00

16.50

0.50

0.50

1.00

2.00

Flooring c.c 1:3:6,


75mm thick using
40mm nominal
broken stone and
plastered over with
12mm thick c.m 1:3
one coat
Taluk industry
Taluk supply office
Stair room
Computer room
Rest room
A.R.CO.OP
Verandah (toilet side)
Verandah
Deduction
10 cm wall inside the
office

Item

Mini Civil Station at Chittur

Description

=121.77m2

1
1
1
1
1
1
1
1

5.00
10.40
3.10
5.24
3.50
8.50
3.00
2.50

9.50
9.50
9.50
5.76
5.24
9.50
9.70
36.44

47.50
98.8
29.45
30.18
18.34
80.75
29.10
91.10
=425.22

44.10

0.10

4.41
=420.81m2

No.

Length

Breadth

1
11

100.22
2.00

Height

Quantity

0.50
0.50

50.11
11.00
=61.11m2

Remarks

No

16.

Pointing the
exposed faces of
basement using c.m
1:3
Main wall all round
Pillar basement

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

60

Project Report 2012

17.

18.

White washing 2
coats only on out
side wall and
ceilings
Outside area
Ceiling area
Ceiling plastering
in c.m 1:3 12mm
thick under side of
slab
Taluk industries
Taluk supply office
Stair room
Rest room
Computer room
A.R.CO.
Verandah (Toilet)
Verandah

19.

Colour washing
two coats only on
inside walls
Inside area

Item

Description

Same
Same

as item
as item

1
1
1
1
1
1
1
1

5.00
10.40
4.82
3.50
5.24
8.50
3.00
36.44

area

same as

Mini Civil Station at Chittur

no. 10
no. 18

582.49
410.74
993.20m2

9.50
9.50
3.10
5.24
5.76
9.50
9.70
2.50

47.50
98.80
14.94
18.34
30.18
80.75
29.10
91.10
=410.74m2

that of it

em no.10

1232.42
=1232.42m2

No.

Length

Breadth

Height

Quantity

Supplying and fixing


10mm iron hinges
For doors

18

4 Nos/

1 door

72

For windows W

13

9 Nos/

1 window

117

11

6 Nos

Remarks

No

20.

W1
Dept of Civil Engineering
College, Palakkad

66
Govt Polytechnic

61

Project Report 2012


V
21.

22.

23.

Mini Civil Station at Chittur

2 Nos

16
=271Nos

Supplying and fixing


75mm iron tower bolt
Doors

18

3 Nos/

54

1 door

= 54Nos

Fixing 75mm iron


hookes
For windows W

13

6 Nos/

78

W1

11

4 Nos

44

1 Nos

1 window

=130Nos

Providing 150 mm
aluminium door
handle

24.

Doors

18

2 Nos/

36
=36 Nos

Providing flat iron


hold fast size
350x50x6 for doors
windows etc.
Doors

18

4 Nos/

Windows

24

2 Nos

48

Ventilators

2 Nos

16

1 door

72

1 door

=136Nos

FIRST FLOOR
Item

Description

No.

Length

Breadth

Height

Quantity

First class brick


work c.m 1:6 for
super structure and
steps
24 cm walls
10 cm walls

1
1

217.66
70.14

0.24
0.10

3.60
3.60

188.06
25.25
=213.31

Remarks

No
1.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

62

Project Report 2012


Deductions
For opening
(Balcony)

Opening
Doors & Windows
D
D1
D2
W
W1
W3
Lintels
All round
24 cm wall
D1
D2
W1

3
8

2.50
5.46(area)

0.24

3.10
0.24

6.48
10.48

1.00

0.24

2.10

4.03

0.90

0.10

2.00

1.08

10

0.80

0.10

2.00

1.60

19

1.50

0.24

1.50

10.26

12

1.00

0.24

1.50

3.06

10

0.50

0.24

0.50

0.60

121.52

0.24

0.15

4.37

31.90

0.24

0.15

1.15

1.20

0.10

0.10

0.072

10

1.10

0.10

0.10

0.11

1.30

0.10

0.10

0.078
=43.38

R.C.C 1:2:4 using


20 mm broken
stone for slab,
lintel sunshade etc.
Slab
Main all round
Above pillars
Sunshade
Lintel

Item

Mini Civil Station at Chittur

Description

=169.93m3

1
36.92
1
11.60
1
76.70
Quan tity same

No.

Length

12.72
10.4
0.60

0.135
0.135
0.060

as that for

item no.1

Breadth

63.39
16.28
2.76
5.76

Height

Quantity

0.110
0.110
1.20

0.620
1.340
0.594

0.30

0.36

Remarks

No
Stair case
Landing slab
Waist slab
Steps

1
2
22

3.24
1.74
3.76
1.62
(1/2x0.15 x0.3)

Beams
Beam 1
Dept of Civil Engineering
College, Palakkad

5.00

0.24

Govt Polytechnic

63

Project Report 2012

Mini Civil Station at Chittur

Beam 2

9.52

0.24

0.30

1.368

Beam 3

8.50

0.24

0.30

0.612

Beam 4

5.24

0.24

0.30

0.377

Beam 5

3.00

0.24

0.30

0.22

Beam 6

2.5

0.24

0.30

0.18

Beam 7

2.50

0.24

0.30

1.62

Beam 8

3.10

0.24

0.30

0.22

Beam 9

2.50

0.24

0.30

0.36

Beam 10

7.18

0.24

0.30

1.033
=97.12

Landing slab opening

4.92

3.10

0.135

2.06
=2.06

3.

=95.06m3

Reinforcement tie and


place in position etc.
complete at 0.85% by
volume of concrete

0.85/100

x95.06x

63.43
=63.43 q

4.

Plastering with c.m


1:5 12mm thick on
exposed surface of
wall and inside
surface of wall and
steps.
Out side plastering

122.48

3.60

440.93

Main wall all round

Item

Description

No.

Length

Breadth

Height

Quantity

Sunshade
Top & bottom
Face

1
1

76.50
76.70

0.60
0.06

46.02
4.60
=491.55

Deduction
Balcony open
Opening

3
8

2.50
5.46(area)

3.60

27.00
43.68
=70.68
=420.87m2

Remarks

No

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

64

Project Report 2012


Inside plastering
Town employment
Soil conservation
Stair room
A.E.NH
Food inspector
Verandah
10 cm wall
Beams
Side
Bottom
Stair

1
1
1
1
1
1
1X2

29.00
39.8
17.52
36.00
29.48
68.04
71.64

88.92
1X2
88.92
1X1
1
16.12(area)

Deduction
D

D1

D2

10

19

W1

12

10

1.00
0.90
0.80
1.50
1.50
0.50

Mini Civil Station at Chittur

3.60
3.60
3.60
3.60
3.60
3.60
3.60

104.4
143.25
63.07
129.60
106.13
244.94
555.82

0.30

52.95

0.24

21.17
16.12

2.10

=1478.08
16.80

2.00

10.80

2.00

16.00

1.50

42.75

1.50

18.00

0.50

2.50
=106.85
=1371.23m2

Item

Description

No.

Length

Breadth

Height

Quantity

6.20

0.07

0.10

0.347

D1

6.00

0.07

0.10

0.252

Remarks

No
5.

Wood work for the


frames of doors and
windows
Doors

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

65

Project Report 2012


D2

Mini Civil Station at Chittur

10

5.80

0.07

0.10

0.406

19

9.00

0.07

0.10

1.970

W1

12

7.50

0.07

0.10

0.630

10

2.00

0.07

0.10

0.140

Windows

6.

=2.972m3

Wood work for the


shutters of fully
paneled doors
D

1.98

0.88

13.94

D1

1.88

0.78

8.79

D2

10

1.88

0.68

12.78
=35.51m2

Shutters of fully
7.

8.

glazed window
W

19X3

0.427

1.38

33.59

W1

12X2

0.415

1.38

13.74

10X1

0.38

0.38

1.44

Painting for goods


and window two
coats over one coat
wooden primer used
over approved
quality in cement
paint
D

=44.77m2

1.00

2.10

2.25

37.80

0.90

2.00

2.25

24.30

No.

Length

Breadth

Height

Quantity

D2

10

0.80

2.00

2.25

36.00

19

1.50

1.50

1.00

42.75

W1

12

1.00

1.50

1.00

18.00

10

0.50

0.50

1.00

2.50

D1

Item

Description

Remarks

No

=161.35m2
9.

White washing 2

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

66

Project Report 2012

Mini Civil Station at Chittur

coats only on out


side walls and
ceiling

same

as item

no.4

420.87

Out side area

same

as item

no.11

493.65
=914.52m2

Ceiling area
10.

Ceiling plastering in
c.m 1:3 12mm thick
under side of slab
Town employment

5.00

9.50

47.50

Soil conservation

10.40

9.50

98.80

Stair room

4.82

3.10

14.94

Food inspector

5.24

9.50

49.78

A.E

8.50

9.50

80.75

Verandah (Toilet)

3.00

9.70

29.10

Verandah

36.44

2.50

91.10

A.E.O

7.18

11.36

81.56
=493.65m2

11.

Colour washing two


coats only on inside
walls
Inside area

area

same as th

at of item

no.4

1126.29
=1126.29m2

Item

Description

No.

Length

Breadth

Height

Quantity

For doors

24

4Nos/

1 door

96

For windows W

19

9Nos/ 1

window

171

12

6Nos

Remarks

No
12.

Supplying and fixing


10mm iron hinges

W1
Dept of Civil Engineering
College, Palakkad

72
Govt Polytechnic

67

Project Report 2012


V

10

Mini Civil Station at Chittur

2Nos

20
=359Nos

13.

Supplying and fixing


75mm iron tower bolt
Doors

24

3Nos/

1 door

72
=72Nos

14.

Fixing 75 mm iron
hookes
For windows W

19

6Nos/1

window

114

W1

12

4Nos

48

10

1Nos

10
=172Nos

15.

Providing 150 mm
aluminium door
handle
Doors

16.

24

2Nos/

1 door

48

Providing flat iron


hold fast size
350x50x6 for doors
widows etc.
Doors

=48Nos

24

4Nos/

Windows

31

2Nos

62

Ventilators

10

2Nos

20

1 door

46

=178Nos

SECOND FLOOR
Item

Description

No.

Length

Breadth

Height

Quantity

First class brick work


c.m 1:6 for
superstructure and
steps
24 cm walls
10 cm wall
Parapet wall

1
1
1

217.66
47.74
124.10

0.24
0.10
0.10

3.60
3.60
0.60

188.06
25.25
7.45

Remarks

No
1.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

68

Project Report 2012

Mini Civil Station at Chittur

Head room

16.00

0.24

3.00

Deductions
For opening

18.84
=231.51

2.50

0.24

3.10

6.48

(Balcony)

5.46(area)

0.24

10.48

8
4
8
19
13
8

1.00
0.90
0.80
1.50
1.00
0.50

0.24
0.10
0.10
0.24
0.24
0.24

2.10
2.00
2.00
1.50
1.50
0.50

4.03
0.72
1.28
10.26
3.31
0.48

121.52

0.24

0.15

4.37

31.90

0.24

0.15

1.15

1.20

0.10

0.10

0.048

1.10

0.10

0.10

0.088

1.30

0.10

0.10

0.078

Opening
Doors & windows
D
D1
D2
W
W1
W3
Lintels
All round
24 cm wall
D1
D2
W1
R.C.C 1:2:4 using 20
mm broken stone for
slab, lintel sunshade
etc.
Slab

=42.78
=188.74m3

Main all round


Front portion

Item

Description

37.32

13.32

0.125

62.14

11.60

10.80

0.125

15.66

No

Length

Breadth

Height

Quantity

Remarks

No
Sunshade
Lintel
Stair case
Landing slab
Waist slab
Steps
Beams
Beam 1
Dept of Civil Engineering
College, Palakkad

76.70

0.60

0.060

Qu
an

tity same a

s that for
it

em no.1

2.76
5.76

0.110
0.110
1.20

0.620
1.340
0.594

0.30

0.36

1
2
22
1

3.24
3.76
(1/2x0.15
5.00

1.74
1.62
x0.3)
0.24

Rise=0.15
Tread=0.3

Govt Polytechnic

69

Project Report 2012

Mini Civil Station at Chittur

Beam 2

9.52

0.24

0.30

1.368

Beam 3

8.50

0.24

0.30

0.612

Beam 4

5.24

0.24

0.30

0.377

Beam 5

3.00

0.24

0.30

0.22

Beam 6

2.50

0.24

0.30

0.18

Beam 7

2.50

0.24

0.30

1.62

Beam 8

3.10

0.24

0.30

0.22

Beam 9

2.50

0.24

0.30

0.36

Beam 10

7.18

0.24

0.30

1.033
=103.97

Landing slab opening

4.92

3.10

0.135

2.06
=2.06

3.

4.

=101.91m3

Reinforcement tie
and place in position
etc. complete at
0.85% by volume of
concrete
Plastering with c.m
1:5 12mm thick on
exposed surface of
wall and inside
surface of wall and
steps.
Out side plastering

x101.91
0.85/100

Description

67.99
=67.99 q

Main wall allaround

Item

x78.5

122.48

3.60

Height

440.93

No.

Length

Breadth

Quantity

Sunshade
Top & bottom
Face

1
1

76.70
76.70

0.60
0.06

46.02
4.60
=491.55

Deduction
Balcony open
Opening

3
8

2.50
5.46(area)

3.60

27.00
43.68
=70.68
=420.87m2

Inside plastering
Town employment

29.00

3.60

104.4

Remarks

No

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

70

Project Report 2012

Mini Civil Station at Chittur

Soil conservation
Stair room
A.E NH
Food inspector
Verandah
10 cm wall

1
1
1
1
1
1X2

39.8
17.52
36.00
29.48
68.04
71.64

3.60
3.60
3.60
3.60
3.60
3.60

143.25
63.07
129.60
106.13
244.94
555.82

Beams
Side
Bottom

1X2
1X1

88.92
88.92

0.30
0.24

16.12(area)

52.95
21.17
16.12
=1478.08

1.00

2.10

16.80

D1

0.90

2.00

10.80

D2

10

0.80

2.00

16.00

19

1.50

1.50

42.75

W1

12

1.00

1.50

18.00

10

0.50

0.50

2.50

Stair
Deduction

=106.85
=1371.23m2

Item

Description

No.

Length

Breadth

Height

Quantity

6.20

0.07

0.10

0.347

D1

6.00

0.07

0.10

0.168

D2

5.80

0.07

0.10

0.325

Remarks

No
5.

Wood work for the


frames of doors and
windows
Doors

Windows
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

71

Project Report 2012

6.

7.

8.

Mini Civil Station at Chittur

19

9.00

0.07

0.10

1.197

W1

13

7.50

0.07

0.10

0.682

2.00

0.07

0.10

0.112
=2.831m3

Wood work for the


shutters of fully
paneled doors
D

1.98

0.88

13.94

D1

1.88

0.78

5.87

D2

1.88

0.68

10.23
=30.04m2

Shutters of fully
glazed windows
W

19X3

0.427

1.38

33.59

W1

13X2

0.415

1.38

14.89

8X1

0.38

0.38

1.16
=49.64m2

Painting for doors


and windows two
coats over one coat
wooden primer used
over approved
quality in cement
paint
D

1.00

2.10

2.25

37.80

0.90

2.00

2.25

17.01

No.

Length

Breadth

Height

Quantity

D2

0.80

2.00

2.25

28.80

19

1.50

1.50

1.00

42.75

W1

13

1.00

1.50

1.00

19.50

0.50

0.50

1.00

2.00

D1

Item

Description

Remarks

No

=147.88m2
10.

White washing 2
coats only on out
side walls and
ceilings

Dept of Civil Engineering


College, Palakkad

same

as item

no.4

592.55
Govt Polytechnic

72

Project Report 2012


same

Out side area


Ceiling area
11.

Item

no.11

493.65
=1086.2m2

Ceiling plastering in
c.m 1:3 12 mm thick
under side of slab
Town employment
Soil conservation
Stair room
Food inspector
A.E
Verandah(Toilet)
Verandah
A.E.O

12.

as item

Mini Civil Station at Chittur

Colour washing two


coats only in inside
walls
Inside area

Description

1
1
1
1
1
1
1
1

5.00
10.40
4.82
5.24
8.50
3.00
36.44
7.18

area

same as

47.50

9.50
9.50
3.10
9.50
9.50
9.70
2.50
11.36

that of it

98.80
14.94
49.78
80.75
29.10
91.10
81.56
=493.65m2

1126.29

em no.4

=1126.29m2

No.

Length

Breadth

Height

Quantity

Supplying and fixing


10 mm iron hinges
For doors

20

4Nos/

1 door

80

For windows W

19

9Nos/1

window

171

W1

13

6Nos

78

2Nos

16

Remarks

No
13.

=345Nos
Supplying and fixing
75 mm iron tower bolt
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

73

Project Report 2012

Mini Civil Station at Chittur

Doors

20

3Nos/

1 door

60
=60Nos

Fixing 75 mm iron
hookes
For windows W

19

6Nos/1

window

114

W1

13

4Nos

52

1Nos

8
=174Nos

Providing 150 mm
aluminium door
handle
Doors

20

2Nos/

1 door

20
32
8

4Nos/
2Nos
2Nos

1 door

40
=40Nos

Providing flat iron


hold fast size
350x50x6 for
doors,windows etc.
Doors
Windows
Ventilators

80
64
16
=160Nos

11. RATE ANALYSIS


Item
No.

Quantity

1.

1No.

Description of work
Clearing site and leveling by
removing the bushes etc. including
trees up to 30cm grills etc.
Labour
Man
Add 10% CP
Total

Unit

Rate

Amount

100m2
each

276.00

276 .00
28.00
304/100m2

2.

Earth work excavation hard soil and


depositing on bank with initial lead

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

74

Project Report 2012

4No.
3No.

up to 50cm and liftupto 1.5m


including breaking clods, watering,
ramming and sectioning of spoil
bank etc.
Labour
Man
Woman
Total
Add 10% CP

Mini Civil Station at Chittur

10 m3
each
each

276.00
276.00

1932.00
193.20
2125.20

Grand Total
3.
0.95
0.48
171kg

Pcc 1:4:8 using 40mm nominal size


broken stone
Materials
40mm broken stone
sand
cement

0.10
1.0
1.40

Labour
Brick mason
Man
Woman

1104.00
828.00

m3
m3
m3
tonne

563.50
2012.50
5405.00

535.32
966.00
924.25

each
each
each

373.75
276.00
276.00

37.38
276.00
386.40

m3
m3
tonne

346.15
308.20
269.10

325.89
147.93
46.01
3645.10
364.51
4009.61/m3

Conveyance
0.95
0.48
171kg

40mm nominal broken stone


Sand
Cement
Total
Add 10% CP
Grand Total

Item
No.

Quantity

4.

Description of work

Unit

Rate

Amount

1.03
0.30
86kg

RR masonary work in cm 1:6 for


foundation and basement
Materials
Blasted rubble
Dry sand
Cement

m3
m3
tonne

310.50
2012.50
5405

319.81
603.75
464.83

0.70
0.35
0.70

Labour
Rubble mason
Man
Woman

each
each
each

373.75
276.00
276.00

261.62
96.60
193.20

m3

Conveyance
Dept of Civil Engineering
College, Palakkad

Govt Polytechnic

75

Project Report 2012


1.03
0.3
86kg

5.
3.60
1.80
100kg
20kg
5nos
5nos
1no
LS
3.60
1.80
100kg

Blastered rubble by lorry


Dry sand
Cement
Total
Add 10% CP
Grand Total
2.5 cm DPC with CC 1:1 :3
Materials
20mm nominal size broken stone
Dry sand
Cement
Cem seal (1kg/bag of cement)
Labour
Mason
Man
Woman
Sundries, tools etc.
Conveyance
20mm nominal size broken stone
Dry sand
Cement
Total
Add 10% CP
Grand Total

Mini Civil Station at Chittur


m3
m3
tonne

347.00
308.20
269.10

357.41
92.46
23.14
2412.82
241.28

100m2

2654.10/m3

m3
m3
tonne
kg

805.00
2012.50
5405.00
69.00

2898.00
3622.50
540.50
1380

each
each
each
LS

375.75
276.00
276.00

1878.75
1380.00
276.00
50.00

m3
m3
tonne

460.00
308.00
269.10

1656.00
554.76
26.91
14263.42
1426.34
15689.76/m2

Unit

Rate

Amount

Item
No.

Quantity

6.
500nos
0.24m3
69kg
0.70nos
0.35nos
0.70nos
LS

Description of work
Brick work in cm 1:5 with country
burnt bricks 19x9x9cm
Materials
Country burnt bricks
Dry sand
Cement
Labour
Brick mason
Man
Woman
10% of labour charge hire charge for
scaffolding materials

Dept of Civil Engineering


College, Palakkad

m3
1000nos
m3
tonne

3220.00
2012.50
5405.00

1610.00
483.00
372.84

each
each
each

373.75
276.00
276.00

261.62
96.60
193.20
27.00

Govt Polytechnic

Project Report 2012

500nos
0.24
69kg

7.

76

Conveyance
Brick by lorry
Sand
Cement
Total
Add 10% CP
Grand total

Form work for RCC in slabs


including wooden plank, joining
bamboo posts and labour for taking
down after complection of work
Materials
30mm thick mango or jungle wood
planks and jungle joists 100mm x
10mm at 60cm interval.

Mini Civil Station at Chittur

1000nos
m3
tonne

499.10
308.20
269.10

249.55
73.96
18.56
3359.43
335.94
3695.37/m3

10dm2

320dm3

Mango or jungle wood planks


(Taking that the materials can be
used 4 times)

10dm3

165.84

1326.72

190dm3

Jungle wood joists and cleats etc.


(Taking that the materials can be
used 4 times)

10dm3

165.84

787.74

Item
No.

Quantity
Description of work
9Nos
Bamboos (Taking that the materials
can be used 4 times)

Unit
each

Rate
120.75

Amount
271.68

1kg

Spike and wire nails

Kg.

48.30

48.30

LS

Coir

LS

50

50.00

320 dm
190 dm3
4Nos
2.50Nos

Conveyance
Manager
Jungle wood
Labour
Carpenters for fitting up forms and
taking down after completion.
Man
Total
Add 10% CP

Dept of Civil Engineering


College, Palakkad

M3
M3

351.90
351.90

112.60
66.86

each
each

373.75
276.00

1495.00
690.00
4848.90/10m2

Govt Polytechnic

77

Project Report 2012

Mini Civil Station at Chittur

Grand Total
Form work for sunshades, lintel and
beams with rate for 10m2 form work
for slab
Add 10%
Total
Add 10% CP
Net Total

8.

Form work for columns with rate for


10m2 form work for slab
Add 20% extra
Total
Add 10% CP
Net Total

9.

0.009m
0.0045
3.3kg

RCC work with CC 1:2:4 using


20mm nominal size broken stone
Materials
20mm broken stone
Dry sand
Cement

0.002
0.01
0.035
LS

Labour
Mason
Man
Woman(including for watering)
Form work for RCC in slab

10.
3

484.89
5333.79/10m2
10m2

4848.90

5333.79
533.39
5867.18/10m2

10m2

5333.79

5333.79
1066.75
6400.54
640.05
7040.59

m3
m3
tonne

805.00
2012.50
5405.00

7.25
9.05
17.83

each
each
each
LS

373.75
276.00
276.00
50.00

Unit

Rate

Amount

m3
m3
tonne

460.00
308.20
269.10

4.14
1.38
0.88
53.74/10dm3
5.37
59.11/10dm3

10dm2

0.7475
2.76
9.66
0.05

Item
No.

Quantity

Description of work
Conveyance

0.009
0.0045
3.30kg.

11.

20mm broken stone


Sand
Cement
Total
Add 10% CP
Grand Total
Reinforcement for RCC work bent,
tied and placed in position using
HYSD bars

Materials
Tor steel

Dept of Civil Engineering


College, Palakkad

5142.80

5142.80

Govt Polytechnic

78

Project Report 2012

Mini Civil Station at Chittur

0.45 q

Iron wire tying coil

kg.

80.50

36.22

1No
1.48No

Labour
Black smith
Man

each
each

373.75
276.00

373.75
408.48

q
kg.

269.10
23.90

269.10
26.91
5988.16
598.81

1q
0.45kg

Conveyance
Tor steel
iron wire tying coil
Total
Add 10% CP
Grand Total

6586.98
12.
14.4dm3

0.02Nos
0.33Nos

Teak wood scantiling


Material
Teak log, average rate of I,II,III
classes
Labour
Man to put log in position and to
assist sawyers
Sawing (at 4.3 sawyers per 10m3
sawing Rs.200/- each)
Total

10d m3
m3

each
10 m2

88550.00

276.00
1233.37

1275.12

5.52
407.01
1687.65

Item
No.

Quantity

13.
10.5dm3

Description of work
Teak wood paneled and framed
work for frame of door and
windows, ventilators etc.
Material
Teak wood scantling
Add 5% wastage

Unit

Rate

Amount

10dm3
10dm3

650.00
32.50

682.50
32.50

each
each

373.75
276.00

82.22
27.60

Teak wood scantling


Add 5% wastage
0.22Nos
0.10Nos

Labour
Carpenter
Man

10.5dm3

Conveyance
Teak wood scantling

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

79

Project Report 2012


Total
Add 10% CP
Grand total
14.

0.2m3

Supplying and fixing teakwood


fully paneled shutters to suit the
door frame already fixed inclusive
of cost of fitting etc. complete
Material
Teak wood scantling
Add 5% wastage

Labour
0.386Nos Carpenter
0.028Nos Man
0.2m3

15.

Conveyance
Teak wood scantling
Total
Add 10% CP
Grand total

Mini Civil Station at Chittur


10dm3

35.19

10dm2

650.00

13.00
0.65

each
each

373.75
276.00

137.54
7.728

10dm2

35.19

0.70
159.62

Unit

Rate

10dm2

650.00

10m2
kg.

365.84

each
each

373.75
276.00

36.94
862.96
86.29
948.26/10dm3

Supplying and fixing teak wood


fully glazed shutters to suit the
window frame already fixed
inclusive of labour charges for
fitting all fittings but exclusive of
cost of fitting etc. complete

Item
No.

Quantity
1.3dm2
0.35
LS

Description of work
Material
Teak wood scantling
Add 5% wastage
Glass pans (3mm)
For nails flitters or putty

Labour
0.386nos Carpenter
0.028nos Man
Total
Add 10% CP
Grand total
16.

Ceiling plastering with CM 1:3


9mm thick one coat

Dept of Civil Engineering


College, Palakkad

Amount
84.50
4.22
12.80
68.00

144.26
7.725
321.50
32.15
353.65

10m2

Govt Polytechnic

80

Project Report 2012

Mini Civil Station at Chittur

0.09m
43kg.

Material
Dry sand
Cement

m3
tonne

2012.50
5405.00

181.12
232.41

0.90Nos
0.50Nos
1.10Nos

Labour
Brick mason
Man
Woman

each
each
each

373.75
276.00
276.00

336.37
138.00
303.60

m3
tonne

308.20
269.10

27.73
11.57

0.09
43kg.

17.

0.15 m3
54kg.

Conveyance
Dry sand
Cement
Total
Add 10% CP
Grand total

1230.30
123.03
1353.38/m2

Plastering with CM 1:4 12mm thick


one coat

10m2

Material
Dry sand
Cement

m3
tonne

2012.50
5405.00

Unit

Rate

each
each
each

373.75
276.00
276.00

336.37
151.80
303.60

m3
tonne

308.20
269.10

46.23
14.53

301.87
291.87

Item
No.

Quantity
0.90Nos
0.55Nos
1.10Nos
0.15
54kg.

18.

Description of work
Labour
Brick mason
Man]
Woman
Conveyance
Sand
Cement
Total
Add 10% CP
Grand total

Pointing random rubble masonary


with C.M 1:3
Material
0.028m3 Dry sand
13.25kg. Cement

Dept of Civil Engineering


College, Palakkad

Amount

1446.27
144.62
1590.89
10m2
m3
tonne

2012.50
5405.00

56.35
71.61

Govt Polytechnic

81

Project Report 2012

Labour
0.54No.. Rubble mason
0.54No. Man
0.54No. Woman
Conveyance
0.028m Dry sand
13.25kg. Cement
Total
Add 10% CP
Grand total
3

19.

0.14m3
66kg.
0.90
0.55
1.10

Mini Civil Station at Chittur

each
each
each

373.75
276.00
276.00

201.82
149.04
149.04

m3
tonne

308.20
269.10

8.63
3.56
640.05
64.00
704.05/10m2

Plastering with CM 1:3, 12mm thick


one coat (out side)

10m2

Material
Dry sand
Cement

m3
tonne

2012.50
5405.00

281.75
356.73

Labour
Brick mason
Man
Woman

each
each
each

373.75
276.00
276.00

336.37
151.80
303.60

Unit

Rate

Amount

m3
Tonne

308.20
269.10

43.14
17.76
1491.15
149.11
1640.26/m2

805.00
2012.50
5405.00
448.00
320.00

1513.40
1891.75
2432.25
268.50
12.80

Item
No.

Quantity
0.14m3
66kg.

20.

1.88m3
0.94m3
0.47m3
0.60m3
0.04m3

Description of work
Conveyance
Sand
Cement
Total
Add 10% CP
Grand total
Flooring
Mosaic flooring 6mm thick mosaic
layer 1:11/2 over 20mm thick C.C
1:2:4
Materials
20mm stone ballast
Sand
Cement
Marble chips 3mm guage
Marble dust

Dept of Civil Engineering


College, Palakkad

100m2

m3
m3
tonne
q
50kg

Govt Polytechnic

82

Project Report 2012


0.40m3
1No
20No
20No
2No

21.

Cement
Labour
Mistri
Mason
Man
Polisher
Total
Add 10% CP
Grand total
For 1m2 = 90.519/Painting primary coat on new iron
work after rubbing with new emery
paper and cleaning the surface.

0.75L
LS

0.40

Materials
Iron primer
Sundries including brushes, emery
paper, soap etc.
Labour
Painter
Total
Add 10% CP
Grand total

Mini Civil Station at Chittur


tonne

5405.00

each
each
each
each

373.75
373.75
276.00
276.00

2162.00
373.75
7475.00
5520.00
552.00
22201.75
2220.17
24421.92/m2

10m2

140.00

LS

25.00

each

155.00

105.00
25.00

62.50
192.00
19.20
211.25

Item
No.

Quantity

22.

Description of work
Painting with synthetic enamel paint
using approved quality an specified
one coat (over a primary coat
already done and to be paid
separately) for new iron work after
cleaning the surface

0.70L
LS
0.675

Materials
Synthetic enamel paint
Sundries for brushes, soap etc.
Labour
Painter
Total
Add 10% CP
Grand total

Dept of Civil Engineering


College, Palakkad

Unit

Rate

Amount

10m2

1
LS

180.00
25.00

126.00
25.00

each

310.50

104.63
255.63
25.56
281.19

Govt Polytechnic

83

Project Report 2012


23.

White washing over plastered


surface 2 coats
0.03
LS
0.12No.

24.

Materials
White cement
Glue and other sundries
Labour
Painter
Total
Add 10% CP
Net total

Mini Civil Station at Chittur

10m2
kg
LS

17.25
0.60

42.28
0.60

each

310.50

37.24
80.64
8.06
88.70/m2

Provide M.S rods for windows and


ventilators
1q
2Nos.

Materials
M.S. rod (20mm dia.)
Labour
Carpenter
Total
Add 10% CP
Net total

1q

3737.50

3737.50

each

373.75

747.50
4485.00
448.50
4933.50

Item
No.

Quantity

25.

Description of work

Unit

Rate

Amount

each
each
each
each
each
each
each

30.00
23.50
95.00
30.00
7.40
5.15
22.00

30.00
23.50
95.00
30.00
7.40
5.15
22.00

Fitting and fixtures of doors and


window frame
150mm
100mm
300mm
120mm
1No.
40x60
100mm

Butt hinges(150mm)
Butt (100mm)
Aldrop set(Aluminium)
Tower bolt(Aluminium)
Hook hold fast
MS hold fast
Aluminium peg stay
Total

213.05

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

84

Project Report 2012

Mini Civil Station at Chittur

RATE ANALYSIS FOR FIRST FLOOR


Item
No.

Quantity

1.

Description of work
Brick masonary in C.M 1:5 with
country burnt brick for super
structure in II floor

Unit

2.

Scaffolding materials
Total
Add 10% CP
Net total
RCC work with C.C 1:2:4 using
20mm nominal size broken stone
Rate of ground floor
Add 10% labour charge

Dept of Civil Engineering


College, Palakkad

Amount

m3

Rate of ground floor


Add10% labour charge
LS

Rate

3695.37
557.40
LS

25.00

3695.37
55.14
50.00
3800.51
380.05
4180.54

10dm3
59.11
13.21

59.11
1.32

Govt Polytechnic

85

Project Report 2012

Mini Civil Station at Chittur

Total
Add 10% CP
Net total

60.43
6.04
66.47/10dm3

3.

Reinforcement work using HYSD


bars for RCC work bent, tied and
placed in position

.
q

Rate of ground floor


Add 10% labour charge
Total
Add 10%CP
Net total

6586.98
782.25

6586.98
78.22
6665.20
666.52
7331.72

4.

Ceiling plastering with cm 1:3, 9mm


thick one coat

10m2

Rate of ground floor


Add 10% labour charge
LS

1230.80
777.97
LS

Scaffolding materials
Total
Add 10% CP
Net total

1230.80
77.80
25.00

5.00
1333.60
123.36
1466.96/10m2

Item
No.

Quantity

5.

Description of work

Unit

Plastering with CM 1:4, 12mm thick


One coat (inside)

10m2

Rate of ground floor


Add 10% labour charge
LS

6.

Scaffolding materials
Total
Add 10% CP
Net total
Plastering with CM 1:3, 12mm thick
one coat (out side)

LS

Rate

Amount

1446.27
791.77

1466.27
79.17

5.00

25.00
1550.44
155.04
1705.49

1491.15
791.77

1491.15
79.17

5.00

25.00
1595.32

10m2

Rate of ground floor


Add 10% labour charge
LS
Scaffolding materials
Total
Dept of Civil Engineering
College, Palakkad

LS

Govt Polytechnic

86

Project Report 2012

Mini Civil Station at Chittur

Add 10% CP
Net total
7.

White washing over plastered


surface two coat

159.53
1754.85
10m2

Rate of ground floor


Add 10% labour charge
LS

Scaffolding materials
Total
Add 10% CP
Net total

LS

80.64
37.26

80.64
3.73

5.00

25.00
109.37
10.93
120.30

RATE ANALYSIS FOR SECOND FLOOR


Item
No.

Quantity

1.

Description of work
Brick masonary in C.M 1:5 with
country burnt brick for super
structure in II floor

Unit

2.

Scaffolding materials
Total
Add 10% CP
Net total
RCC work with C.C 1:2:4 using
20mm nominal size broken stone
Rate of first floor
Add 10% labour charge
Scaffolding materials
Total

Dept of Civil Engineering


College, Palakkad

Amount

m3

Rate of first loor


Add10% labour charge
LS

Rate

3800.51
557.40
LS

5.00

3800.51
55.14
25.00
3880.65
388.06
4268.71

10dm3

LS

60.47
13.21
5.00

60.47
1.32
25.00
67.79

Govt Polytechnic

87

Project Report 2012

Mini Civil Station at Chittur

Add 10% CP
Net total

6.80
74.50/10dm3
.

3.
Reinforcement work using HYSD
bars for RCC work bent, tied and
placed in position

q
6665.20
782.23

Rate of first floor


Add 10% labour charge
Total
Add 10%CP
Net total

6665.20
78.22
6743.42
674.34
7417.76

4.
Ceiling plastering with cm 1:3, 9mm
thick one coat
LS

10m2
1333.60
777.97

Rate of first floor


Add 10% labour charge
LS

1333.60
77.80
25.00

5.00

Scaffolding materials
Total
Add 10% CP
Net total

1436.40
143.64
1580.04

Item
No.

Quantity

5.

Description of work

Unit

Plastering with CM 1:4, 12mm thick


One coat (inside)

10m2

Rate of first floor


Add 10% labour charge
LS

6.

Scaffolding materials
Total
Add 10% CP
Net total
Plastering with CM 1:3, 12mm thick
one coat (out side)

LS

Rate

Amount

1550.44
791.77

1550.44
79.20

5.00

25.00
1654.64
165.46
1820.10

1595.32
791.77

1595.32
79.20

5.00

25.00
1699.52
109.25

10m2

Rate of first floor


Add 10% labour charge
LS
Scaffolding materials
Total
Add 10% CP
Dept of Civil Engineering
College, Palakkad

LS

Govt Polytechnic

88

Project Report 2012

Mini Civil Station at Chittur

Net total
7.

1869.47

White washing over plastered


surface two coat

10m2

Rate of first floor


Add 10% labour charge
LS

Scaffolding materials
Total
Add 10% CP
Net total

LS

109.37
37.26

107.37
3.75

5.00

25.00
138.10
13.81
151.91/10dm3

12. ABSTRACT ESTIMATE


Sl
No.

Quantity

Description of work

Unit

Rate

Amount

1.

1125 m2

100 m2

304.00

3420.00

2.

314.56m3 Earth work excavation

10 m3

2125.20

66850.29

3.

52.43m3

m3

4009.61

210223.85

4.

256.68m3 R.R masonary in cm 1:6 for


m3

2654.10

681254.85

100 m3

2363.00

41510.82

m2

156.90

22577.91

138.75m3 Ground floor

m3

3695.37

512732.58

169.93m3 First floor

m3

4180.53

710402.56

Cleaning and leveling the site


P.C.C 1:4:8 for foundation
foundation and basement

5.

175.67m3 Filling of basement

6.

143.90m2 D.P.C 2.5 c.m with c.c

7.

Brick work in cm 1:5 for super


structure

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

89

Project Report 2012


188.75m3 Second floor

Mini Civil Station at Chittur


m3

4268.71

805719.01

103.29m3 Ground floor

10dm3

59.11

610547.19

95.06m3

10dm3

66.47

631863.82

10dm3

74.59

760146.69

8.

C.C for R.C.C work 1:2:4


First floor

101.91m3 Second floor


9.

Wood work using teak wood


Planed and framed for doors,
windows etc.
2.257m3

Ground floor

10dm3

948.26

214022.28

2.972m3

First floor

10dm3

1043.08

310003.37

20831m3

Second floor

10dm3

1147.38

238993.25
5820274.00

Item
No.

Quantity

10.

Description of work

Unit

Rate

Amount

Wood work using teak wood palned


and framed shutter for doors,
windows etc.
26.80m2

Ground floor

10dm2

159.62

42778.16

35.51m2

First floor

10dm2

167.60

59514.76

30.04m2

Second floor

10dm2

175.98

52804.39

11.

Glass fitting for shutters of


windows and ventilators

12.

36.73m2

Ground floor

10dm2

353.65

129895.64

48.77m2

First floor

10dm2

371.33

181097.64

49.64m2

Second floor

10dm2

389.89

193541.39

Plastering in c.m 1:4, 12mm thick


one coat

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

90

Project Report 2012

Mini Civil Station at Chittur

1800.1m2 Ground floor

10m2

1590.89

286376.10

1854.1m2 First floor

10m2

1705.49

316214.90

1894.6m2 Second floor

10m2

1820.10

344.836.14

410.71m2 Ground floor

10m2

1353.38

55584.66

493.65m2 First floor

10m2

1466.96

72416.48

493.65m2 Second floor

10m2

1080.04

77998.64

61.11m2

10m2

1590.89

9721.95

13.

Ceiling plastering in c.m 1:3, 9mm


thick one coat

14.

Pointing with c.m 1:3 for basement

7643114.86

Item
No.
15.

Quantity

Description of work

Unit

Rate

Amount

10m2

4861.00

204555.74

420.81m2 Ground floor

10m2

2442.19

102769.79

538.74m2 First floor

10m2

2564.30

138149.09

538.74m2 Second floor

10m2

2692.57

145056.28

121.77m2 Ground floor

10m2

281.19

3424.00

161.15m2 First floor

10m2

295.29

4758.00

147.86m2 Second floor

10m2

310.65

4584.00

993.20m2 Ground floor

10m2

88.70

8809.68

1014.9m2 First floor

10m2

930.13

9451.76

1086.2m2 Second floor

10m2

97.79

10621.95

Flooring with c.c 1:3:6


420.81m2 Ground floor

16.

17.

Mosaic cast in site 18 mm thick

Painting with synthetic enamel


using approved quality

18.

White washing two coats only on


out side wall, ceiling etc.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

91

Project Report 2012


19.

Mini Civil Station at Chittur

Colour washing two coats only on


inside walls
1232.4m2 Ground floor

10m2

84.94

10460.00

1371.2m2 First floor

10m2

89.18

12228.36

1371.2m2 Second floor

10m2

93.65

12840.78

20.

975Nos

Iron hinges for doors, windows

10Nos

330.00

32175.00

21.

476Nos

Hook and eye for windows and

10Nos

235.00

11186.00

ventilator
8354193.29

Item
No.

Quantity

22.

Description of work

Unit

Rate

Amount

Reinforcement work
70.13 q

Ground floor

10 q

6586.98

461944.90

63.43 q

First floor

10 q

7331.72

465050.19

67.99 q

Second floor

10 q

7414.26

504129.53

23.

124Nos

Aluminium door handle

10Nos

550.00

6820.00

24.

186Nos

Tower bolt for doors

10Nos

565.00

10509.00

25.

474Nos

Hold fast for doors and windows

10Nos

430.00

20382.00

26.

124 q

3953.12

4902.00

Window grills

9827930.81
7659189.00

Total amount
Dept of Civil Engineering
College, Palakkad

9827930.81
Govt Polytechnic

92

Project Report 2012

Mini Civil Station at Chittur

Amount of septic tank and soak pit

154910.17

Total amount

9982840.98

2 % water charge

199565.82

5% for work charged establishment

499142.05

8% electrification charges

798627.28

10% for plumbing and sanitary charges

998384.00

Net total

1,24,78,551.25

13. CONCLUSION
The practical lessons learned from the execution of the project work
were of great help on completing of Civil engineering studies and lessons
were the integral part of our technical education with our complementary
knowledge derived from the project work. Our knowledge of theoretical
possibilities have been put in to practice in the execution of this project
scheme.

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Project Report 2012

93

Mini Civil Station at Chittur

14. REFERENCE
1. STRUCTURAL ENGINEERING ARUL MANIKKAM
2. INDIAN STANDARD CODE OF PRACTICE IS 456 : 2000
3. NATIONAL BUILDING CODE
4. ESTIMATING AND COSTING B.N. DUTTA
5. SURVEYING 1 KANITKAR AND KULKARNY

Dept of Civil Engineering


College, Palakkad

Govt Polytechnic

Potrebbero piacerti anche