Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
MATERIALS MANAGEMENT
BITS Pilani
Pilani Campus
Anil Jindal
Department of Mechanical Engineering
BITS Pilani
Pilani Campus
Capacity Management
Orders
PLANNING
Committed orders
Inventory
status
Bill of
Materials
1.Order
Entry
system
Production scheduling
Committed
Orders
Material
Planning
Capacity planning
Supplier
Management
2. Master
Production
Scheduling
Monthly
Build Plan
3 .Weekly
Production
Scheduling
Capacity
Plan
5. Capacity
Planning
Material
Request
7. Supplier
6. MRP
Management
Weekly
Build Plan
4. Daily
Production
Scheduling
Purchase
Orders
Suppliers
EXECUTION
Materials
Daily
Work
orders
Job dispatching
& Resource
Allocation
8. Shop
Floor
Control
Production
Process
Warehousing
Products
9. Packaging &
shipping
Introduction
So for we were concerned with planning priority, that is,
determining what is to be produced and when.
However without the resources to achieve the priority plan
will be unworkable.
So, capacity management is concerned with supplying the
necessary resources.
Introduction
Capacity: The capability of a worker, machine, work center,
plan, or organization to produce output per period of time.
It is rate of doing work, not the quantity of work done
Capacity Management: The function of establishing,
measuring, monitoring, and adjusting limits or levels of
capacity in order to execute all manufacturing schedules is
capacity management.
Capacity available, load and capacity required are important in
capacity management
Capacity Planning: The process of determining the resources
required to meet the priority plan and the methods needed to
make the capacity available
BITS Pilani, Pilani Campus
Capacity Management
Capacity is the amount of work that can be done in a
specified period of time.
Capacity Management is concerned with supplying
necessary resources.
Two kinds of capacity are important:
1. Capacity available 2. Capacity required
Capacity Planning
It involves calculating the capacity needed to achieve the
priority plan and finding ways of making that available
Process:
1.Determine the capacity available at each work center in
each planning period
2. Determine the load at each work center
3. Resolve difference b/w available capacity and required
capacity
Planning levels
Resource Planning
Rough-cut capacity
planning
Capacity requirement
planning
Directly linked to
material requirements
plan
Focus on component
parts in greater detail
Concerned with
individual orders at
individual work centers
Calculates work centre
loads and labor
requirements for each
time period
Concerned with MRP
Routing file:
It shows the path that work follows from work center to
work center as it is completed. A routing file should exist
for every component manufactured and contain the
following information:
Operations to be performed
Sequence of operations
Work centers to be used
Possible alternate work centers
Tooling needed at each operation
Standard times: setup times and runtimes per piece.
Available capacity
It is the capacity of a system or resource to produce a
quantity of output in a given time period. It is affected by
the following:
Product specifications: If the product specifications change, the
work content will change, thus affecting the number of units that
can be produced.
Product mix: Each product has its own work content measured in
the time it takes to make the product. If the mix of products being
produced changes, the total work content for the mix will change.
Plant and Equipment: If the method is changed the output will
change.
Work effort: This relates to the speed or pace at which the work is
done. If the workforce changes pace the capacity will be altered.
BITS Pilani, Pilani Campus
Capacity measurement
Capacity available is the capacity of a system or resource
to produce a quantity of output in a given time period
It is affected by product specification, product mix, plant
and equipment and work effort
For common items units of output
For variety of items units of time is preferred
Capacity needs to measured a three different levels i.e.
machine or individual worker, work center and plant
Capacity measurement
Rated or calculated capacity = available time*utilization*efficiency
Utilization= hours actually worked *100
available hours
Capacity Load
Load on work center= sum of required times for all
planned and actual orders to be run on the work center in
the required period
Steps for calculating load:1. Determine the standard hours of operation time for all
the planned and released order for each work center by
time period
2. Add all the standard hours together for each work center
in each period. The result is the total required capacity
(load) on that work center for each time period
BITS Pilani, Pilani Campus
Capacity Load
Work center load report shows future capacity requirements
based on released and planned orders for each time period
of the plan
Scheduling orders is calculation of starting and completion on each
Work center so the final due date can be met.
STEPS:1.For each work order, calculate the capacity required (time) at each
work center
2.Starting with the due date, schedule back to get the completion and
start dates for each operation
BITS Pilani, Pilani Campus
FEW EXAMPLES
Example: A work center has three machines and is operated for eight
hours a day five days a week. What is the available time?
Answer: Available time = 3 x 8 x 5 =120 hours per week.
Example: A work center is available 120 hours but actually produced
goods for 100 hours. What is the utilization of the work center?
Answer:
100
Utilization
100%
120
83.3%
BITS Pilani, Pilani Campus
Demonstrated capacity
One way to find out the capacity of a work center is
to examine the previous production records and to use
that information as the available capacity of the work
center.
Example:
Over the previous four weeks, a work center produced 120,
130, 150, and 140 standard hours of work. What is the
demonstrated capacity of the work center?
Answer:
Setup time
( hours)
Run time
( hours/ piece)
Released orders
222
333
100
150
0
1.5
0.2
0.2
Planned Orders
444
555
200
300
3
2.5
0.25
0.15
BITS Pilani, Pilani Campus
Example
Answer:
Released orders 222 total time = 0 + (100 * 0.2) = 20.0 standard hours
333 total time = 1.5+(150 * 0.2) = 31.5 standard hours
Planned Orders 444 total time = 3+(200 * 0.25) =53.0 standard hours
555 total time= 2.5+(300 * 0.15) =47.5 standard hours
Total time
Scheduling Orders
Scheduling: process of calculating when orders must be
started and completed on each work center so the final
date can be met
Back Scheduling: start with the due date and, using the
lead times, work back to find the start date for each
operation
Adjusting capacity
Schedule overtime or under time
Adjust the level of the workforce by hiring or laying off
workers
Shift workforce from under loaded work centers
Use alternate routings to shift some load to another work
centre
Subcontract work when more capacity is needed or bring
in previously subcontracted work to increase required
capacity
BITS Pilani, Pilani Campus
CAPACITY
OK ?
NO
Feedback
Yes
Feedback
MRP
NO
Yes
CRP
OK?
Purchsing
Yes
PAC
Performance measures
BITS Pilani, Pilani Campus
Problem
A study under taken by materials management department
found that over the past year the work center was available
for work 20000 hours, work was actually being done for
18500 hours, and standard hours for the same was 19600.
calculate the utilization, efficiency, and demonstrated
weekly capacity. Assume a 50-week year.
Solution
Utilization = 18500/20000
= 0.925
= 92.5%
Efficiency
= 19600/18500
=1.0594
=105.94% 106%
Problem
Parent W requires one of the component B and two of
component C. both B and C are run on work center 10.
Setup time for B is 2 hours and runtime is 0.1 hour per
piece. For component C, setup time is 2 hours, and run
time is 0.15 hour per piece. If the rated capacity of the
work center is 80 hours, how many Ws should be
produced in a week?
Solution
Total available capacity for B and C = 80 hours