Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
On
Website: www.prdcinfotech.com
1
Electrical
machine &
System
Dynamics
System
Governing
& load
Controls
Few sec
Seconds
Several
to minutes minutes
Over
Voltages
Prime
mover
energy
supply
system
dynamics
Energy
resource
dynamics
Fault
Transients
s/ms
Days to
weeks
2
Transient Phenomena
Scale
ms
cycles
Ferro - resonance
Surge period
Dynamic period
Steady State period
Relay co-ordination
Case Study :
1. Power evacuation study
2. Design of transmission system
3. Design of interconnection to grid
4. Stability
5. Relay co-ordination
6. Voltage instability study
7. Harmonic analysis
8. EMTP simulation
5
Network is balanced
Network is unbalanced
a
b
c
c
a
b
b
c
a
a
b
c
300Km
100Km
100Km
100Km
Positive sequence
impedance
Simple model
Complex model
Normal conventional
study
Network
Parameter
Generation
Schedule
Load
Schedule
Voltage magnitude
and angle
Load flow
Program
Network parameters
Fault MVA
Generator Xd, Xd
Vector groups
Motor data
Short Circuit
Study
Fault current
10
1. Angular Instability
2. Voltage Instability
Normally occurs in long radial EHV lines, meeting the radial load,
controlled by OLTC.
11
12
Operating point
Nose point or knee point
Voltage
Power
Available margin
13
Further tags
1. Unbalance in the system.
2. Harmonics in the system.
Non linear loads, electronic gadgets, thyristor drives, SVC are those
loads, which introduce harmonics.
R
L
50 MVAR
100 MVAR
50 MVAR
50 MVAR
16
a
b
c
Normally used in varying loads like dc drives and electric arc furnaces.
17
Harmonic Analysis
Measurement technique.
By simulation.
18
1 Cycle
19
Used to determine the load growth based on the past 5-10 year
load records.
Multi regression analysis is used, Load forecasting is normally
used by utility (electricity boards) and not by industries.
Demand
recorded
projected
No. of years
20
Relay Coordination
Over current relay Co-ordination
Computes the plug setting and time Computes the Z1, Z2 & Z3 setting
multiplier setting
A relay should operate for close in fault and should not operate for any
back-up faults immediately and should operate for back-up faults, if the
primary relay fails to operate, with a discrimination time of about 0.4sec.
0.4sec is arrived based on relay operating time, time to close the relay
contacts and circuit breaker operating time.
Time
R1
22
23
Electrical Transients
Electromechanical transients
1.
2.
3.
Electromagnetic transients
Electro magnetic transient
analysis program (EMTP).
24
25
Transient Stability
26
P
Pe= (E*V*Sin)/Xs
Pm
Shaft power
u
s
in degrees
Xs
27
1.
2.
3.
H d 2 = H d = P P
m
e
f dt 2 f dt
4.
As Pe is more, compared to Pm, rotor decelerates, speed comes
down and angle decreases. Hence s is the stable operating point.
5.
Due to disturbance, if u has changed to (u+), then, Pe is less
compared to Pm. Hence rotor further advances, taking the machine
out of step. Hence u is the unstable operating point.
6.
From 4 & 5, it is concluded that steady state stability limit is 900
angular separation between any two machines.
28
29
g
c
b
a
30
Discussions
31
Thank You
Power Research & Development Consultants Pvt. Ltd.
# 5, 11th Cross, II Stage, WOC Road,
Bangalore -560 086
Ph : +91-80-23192209, 42455555; Fax: 23192210, 42455556
E-mail : prdc@vsnl.com
Website: www.prdcinfotech.com
32