( JSA )
Job Description : Erection Formwork Peri & Steel Structure
Area/Unit
: Indocement Slag Storage
WO No
:
References
: SHE Standart Manual
PPE Required to do this job:
Safety glasses
Dust/weldingmask
Goggles/faceshield
Catridgefilter mask
Earplug/Earmuff
Safety boot
Coveralls
Safety helmet
Leather/chemical gloves
DATE ISSUED
:
LAST REVIEWED DATE :
Page 1 of 2
Safety hamess/lifenes
Life Vest
Leather/chemical boot
IF YOU DON'T MEET THE REQUIRETMENTS AS STATED IN THIS PROCEDURE DO NOT PERFORMING THE JOB
JOB STEP
1. Pre-job Safety meeting
(Tool Box Meeting)
Machine/Equipment/Tool
involved in each step
Standard regulation, Manual standard
of Procedure Operational, Another
references that supported (empirical
evidance ever existed and occurred)
Potential Hazard/Loss
Planning mistakes, less accurated and not
completed manual information,
misunderstanding of the subject matter,
Implementer and work backer less
understand of the topics discussed
Control Statement
1. Make sure that the reference in the form of regulations, standard
operating procedures manual is still valid and accountable
2. Determine whether the potential hazard can be eliminated, if it can't be
eliminated, it must be controlled based on procedure.
3. Ensure the scope of work clearly, decisive step in working with procedures
and good regulations
4. Explain all subject matter to all involved workers clearly and establish
backer from each step of the work, limitation of authority and
responsibilities
5. Decide firmly every step of work that can be accounted for by all related
parties.
2. Preparation
Work Permit
Webbing sling
6. Clean
Manual
Chain block
Note :
Created by,
Supervisor
1. Filling permit as work that has done and permit has approved by HTC
team.
Crushed by object is lifted due to binding of 1. Use APD (safety shoes, safety helmet, vest, glasses, masker and gloves)
the less scrupulous
2. Do inspection to work equipment and heavy equipment periodically.
Heavy equipment must has SIA
Wire rope sling broken off
Crane 50 T
4. Handling Material
5. Erection formwork peri &
steel structure
Hit by Material
Confined by Material
Scraped by material
Hit by Heavy equipment
Operation's button broken
Hand scraped
Respirable dust
1. Use APD (safety shoes, safety helmet, vest, glasses, masker and gloves)
2. Make sure work location is clean before leaving the location
Reviewed by,
Chef Enginerring
Approved by,
PT WIKA HSE manager
Acknowledged by,
HTC HSE