ITP for CS Fittings to IS 1239 for Normal Service

TYPICAL
INSPECT

Rev 0 Dtd 19/09/2013

RIL Spec : Technical Supply Condition 10080-1-SS-PP-004 Part - 2


Inspection by

Characteristics

Type/Method of check

Reference
Documents

Acceptance Criteria

Format of Record

Chemical

Review of test certificates


for Chemical

Test certificates

As per code

Physical and identification of


raw material

Corelation with TC,


dimensionsal check

Test certificates
and PO

As per code

2.1

Visual inspection, surface


condition, workmanship,
identification marking
(stockcode number, purchase
order no, PO item no), mill
applied varnishing as applicable

Visual

Visual per PO item per


offer

PO Spec

As per code & RIL spec

Inspection Report

2.2

Dimensional check
(measurement of dia, thickness,
length/end dimensions,
threading etc as applicable)

Measurement

Measurement per PO item


per offer

PO Spec

As per code & RIL spec

Inspection Report

2.3

Selection of sample for testing

Sampeling

Sampling per offer

PO Spec

As per code & RIL spec

Inspection Report

2.4

Mechanical testing

Testing

Testing of samples taken

PO Spec

As per code & RIL spec

2.5

Chemical testing

Testing

Testing of samples taken

PO Spec

As per code & RIL spec

Certificate

All offered lot

PO Spec

As per code & RIL spec

Sr. No.
1

1.1

Stage / Component operation

Remarks

Vendor

TPIA

Client

MTC

---

---

Identification report
& MTC

---

Pipe to be certified hydrotested in


MTC.

W (10%)

---

100% by vendor
10% witness of offered lot by TPI
For 1.5" & smaller size fittings,
identification marking shall be on
the packing carton

W (10%)

---

100% by vendor
10% witness of offered lot by TPI

---

Per offred lot per Heat

Inspection Report

---

---

Inspection Report

---

---

MTC

---

Material certification shall be as


per EN10204 type 3.2

---

---

All fittings which are


visual/dimensional checked shall
be double stamped. All other
fittings shall be single stamped

---

Raw Materials

Pipes

Final Inspection

2.6

Review of Internal test reports,


calibration reports and mill test
certificate of fittings

2.7

Stamping of fittings by TPIA

Visual

Stamping

PO Spec

As per code & RIL spec

Inspection Report

2.8

Issue of Inspection Release


Note

Compleeness

Completeness

PO Spec

As per code & RIL spec

IRN

NOTE 1:- All measuring instruments shall be properly calibrated. Calibration certificates shall be submitted for verification.
NOTE 2:- Chemical and Physical Testing shall be carried out inhouse or at NABL approved laboratory
Galvanising, if applicable, shall be done by hot dip method. All threads shall be free from Galvanizing. TPIA to check galvanizing thickness, coating and adhesion
NOTE 3:test on random samples as per IS 1239 Part II.
NOTE 4:- Fittings shall be capable of withstanding Hydrotest.
Applicable Legends : P : Perform/Prepare (100%) R : Review,

W : Witness, H Hold point. The work can not proceed unless the Hold Point is cleared .

TPIA: Third Part Inspection Agency

Digitally signed by Vijay


Shah
DN: CN = Vijay Shah, C
= US, O = RIL, OU =
SSO E3, Jamnagar
Date: 2013.12.19
16:29:37 +05'30'

ITP_for_CS_IS 1239_Fittings - CS LTCS Forged Seamles Fittings

Potrebbero piacerti anche