MEP CLEARANCE REQUIREMENT - 2 WEEKS LOOKAHEAD

S.No

Activity

1
2
3
4
5
6
7

Gym Floor Clearance for Combo Roof


12th Floor Plaster Clearance
9th To Roof Shaft Closing
Ground Floor Plaster Clearance
Basement Grating Work
Epoxy Floor Clearance @ Basement
Epoxy Floor Clearance @ GF

1st Four Floors 100% False Ceiling Clearance

9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

5th Floor Flase Ceiling Clearance


6th Floor Flase Ceiling Clearance
7th Floor Flase Ceiling Clearance
8th Floor Flase Ceiling Clearance
Sanitary Fitings @ 1st Floor
Sanitary Fitings @ 2nd Floor
Sanitary Fitings @ 3rd Floor
Gym Floor MEP Clearance for Plaster
Lift Shaft Clearance
Basement Pump Room Works
Complete Delivery of Machine/Material
Satircase -01 100% MEP Clearance
Satircase -02 100% MEP Clearance
Water Tank Installation

01.06.15
Mon

02.06.15
Tue

03.06.15
Wed

04.06.15
Thu

05.06.15
Fri

06.06.15
Sat

Days
07.06.15 08.06.15
Sun
Mon

09.06.15
Tue

10.06.15
Wed

11.06.15
Thu

12.06.15
Fri

13.06.15
Sat

14.06.15
Sun