Sei sulla pagina 1di 64

Commission of the European Communities

energy

DESIGN OF WASTE HEAT BOILERS


FOR THE RECOVERY OF ENERGY
FROM ARC FURNACE WASTE GASES

Blow-up from microfiche original

Commission of the European Communities

energy

DESIGN OF WASTE HEAT BOILERS


FOR THE RECOVERY OF ENERGY
FROM ARC FURNACE WASTE GASES
J. DIXON, S. BRAMFOOT
British Steel Corporation
9, Albert Embankment, London SE1 7SN
Great Britain

Contract No. EE-B-2-160-UK(N)


FINAL REPORT

Research financed by the Commission of the European Communities


within the frame of the energy R & D programme
- ENERGY CONSERVATION -

Directorate-General for Science, Research and Development

1985

EUR 9850 EN

Published by the
COMMISSION OF THE EUROPEAN COMMUNITIES
Directorate-General
Information Market and Innovation
Btiment Jean Monnet
LUXEMBOURG

LEGAL NOTICE
Neither the Commission of the European Communities nor any person acting on behalf
of the Commission is responsible for the use which might be made of the following
information

ECSCEEG EAEC Brussels - Luxembourg, 1985

III -

British Steel Corporation


THE FEASIBILITY OF USING WASTE HEAT BOILERS TO RECOVER ENERGY
FROM THE EXHAUST GASES OF ELECTRIC ARC FURNACES
EEC Agreement No. EE-B-2-160-UK(N)

SUMMARY
Energy can be rejected in the waste gases of a UHP electric arc furnace at
rates of up to about 15 MW, accounting for 200 kW h/t of liquid steel. The
possibility of recovering a significant proportion of this energy as steam
using a waste heat boiler has been investigated. The options of using the
steam to satisfy the in-works demand or for generating electricity or a
combination of the two have been considered.
Extensive measurements of the conditions existing in the waste gas stream have
been made throughout the steelmaking cycle for furnace practices involving
oxygen blowing, continuous charging and supplementary firing with oxyfuel
burners.
Various practical implications of the use of a waste heat boiler have been
studied. These include the location of the boiler, the accretion of solid
matter on tubes, the effect of the presence of the boiler on gas cleaning and
the control of furnace extraction to achieve optimum performance.
The economics of using a waste heat boiler on a 180 t furnace to supply part of
the steam demand from a works producing special steels have been examined.
Payback periods of between 1.7 and 2.9 years according to the fraction of the
load supplied are indicated. The rate of return on investment is forecast to
be in the range 33-58%.
The use of waste heat steam to generate electricity is not attractive under
present circumstances unless generating capacity already exists. This
conclusion applies to a large user of energy in the UK; the economics could be
more favourable in other EEC countries where different tarrif structures and
energy price relativities pertain.
Further tests on the performance of tube arrays in the waste gas stream of an
electric arc furnace and the installation of a full-scale boiler could form the
basis of a suitable Demonstration Project.

IV

Page

CONTENTS

1.

INTRODUCTION

2.

THE WASTE GASES OF THE ELECTRIC ARC FURNACE

3.

WASTE HEAT UTILISATION

4.

PRACTICAL ASPECTS INVOLVED IN THE USE OF A


WASTE HEAT BOILER

5.

4.1

General Considerations

4.2

Location

4.3

Control of Inlet Gas Temperature

4.4

Fouling

4.5

Gas Cleaning

ECONOMIC EVALUATION

5.1

Steam Demand

5.2

Case Studies

5.3

Increased Steam Usage

5.4

Electricity Generation

6.

FURTHER DEVELOPMENT

7.

CONCLUSIONS

8.

REFERENCES

9.

ACKNOWLEDGEMENTS
TABLES
FIGURES
APPENDICES

8
9
9
9
10
11
19
30

LIST OF TABLES
1.

Approximate Concentrations of the Main Constituents of


Electric Arc Furnace Fume (Particle Size 0.03-1 urn)

2.

Steam Demand for Electric Arc Works

3.

Waste Gas Temperature and Flow for a Typical Cast

4.

Performance of Boiler - Base Load Case


*

5.

Cost Balance - Base Load

6.

Performance of Boiler - Intermediate Case

7.

Cost Balance - Intermediate Case

8.

Performance of Boiler - Maximum Demand

9.
10.

Cost Balance - Maximum Demand Satisfied


Steam Turbine Performance - Large Boiler Producing for
Electrical Generation Only

11.

Steam Turbine Performance - Large Boiler Satisfying


Base Load, Turbine Using Surplus Steam

12.

Steam Turbine Performance - Small Boiler Producing for


Electrical Generation Only

13.

Steam Turbine Performance - Small Boiler Satisfying


Base Load, Turbine Using Surplus Steam

14.

Cost Balance - Large Boiler Producing for


Electrical Generation Only

15.

Cost Balance - Large Boiler Satisfying Base Load,


Surplus Generating

16.

Cost Balance - Small Boiler Producing for Electrical


Generation Only

17.

Cost Balance - Small Boiler Satifying Base Load,


Surplus Generating

LIST OF APPENDICES
1.

Waste Gas Measurements

2.

New Offtake Elbow

3.

Model Similarity Theory

4.

Performance of the Extraction System with Enlarged Elbow

LIST OF APPENDICES TABLES


A2.1

Relationships Between Elbow Gas Flow (Q ) , Slice Air Flow (Q ) ,


a
Temperature (T) and Chamber Suction Level (S)

A2.2

Predicted Elbow Gas Flows (Q ) and Chamber Suction Levels (S)

VI

LIST OF FIGURES
1.

Waste gas conditions - 180 t furnace

2.

Typical waste heat rejection cycle - 180 t furnace

3.

Typical waste heat rejection cycle - 180 t furnace


with continuous feeding

4.

General layout of electric arc furnace and associated waste gas ducting.
Possible boiler sites

5.

Waste gas conditions for 180 t furnace with modified extraction system

6.

Section through the probe

7.

Deposit on test probe

8.

Heat transfer coefficients

9.

Effect of water vapour on precipitator efficiency

10.

Diagram showing the monthly variation in steam demand for Works A

11.

General arrangement of boiler

LIST OF APPENDICES FIGURES


A2.1

Measurement positions

A2.2

Entry port and elbow diameter combinations

A2.3

General view of the model

A2.4

Graph of relationship between Q:Qe and elbow gas temperature, T

A2.5

A4.2

Graph showing relationship between chamber suction level, S


and slice air flow, Q_
a
Graph showing relationship between elbow flow and heat flow
for a series of carbon removal rates
Graph of elbow flow for original extraction system

A4.3

Graph of elbow flow for modified extraction system

A4.1

VII
British Steel Corporation
LA FAISABILITE DE L'UTILISATION DE CHAUDIERES DE RECHAUFFAGE
POUR RECUPERER L'ENERGIE PROVENANT DES GAZ D'ECHAPPEMENT
DE FOURS A ARC ELECTRIQUES
Accord CECA n EE-B-2-160-UK(N)
RESUME
L ' n e r g i e peut t r e r e f o u l e dans les e f f l u e n t s gazeux d'un f o u r arc
l e c t r i q u e UHP au taux d ' e n v i r o n 15MW pour 200kW h / t d ' a c i e r l i q u i d e .
L'on a t u d i l a p o s s i b i l i t de rcuprer une p r o p o r t i o n i m p o r t a n t e
de c e t t e nergie sous forme de vapeur en u t i l i s a n t une chaudire de
r c h a u f f a g e . L'on a galement t u d i les d i v e r s choix p o s s i b l e s :
u t i l i s e r l a vapeur pour s a t i s f a i r e les besoins d'une a c i r i e ou bien
pour gnrer de l ' l e c t r i c i t , ou encore les deux.
L'on a e f f e c t u des s r i e s de mesures des c o n d i t i o n s auxquelles sont soumis
les e f f l u e n t s gazeux l o r s du processus de f a b r i c a t i o n de l ' a c i e r dans
des f o u r s , y compris le s o u f f l a g e d'oxygne, l e chargement c o n t i n u e t
l a mise feu supplmentaire l ' a i d e de b r l e u r s o x y f u e l .
L'on a t u d i les d i v e r s e s i m p l i c a t i o n s p r a t i q u e s de l ' u t i l i s a t i o n d'une
chaudire de r c h a u f f a g e , parmi l e s q u e l l e s l'emplacement de la
chaudire, les c o n c r t i o n s q u i se forment sur les t u b e s , l ' e f f e t de l a
prsence de la chaudire sur l ' p u r a t i o n des gaz e t le c o n t r l e du
processus d ' e x t r a c t i o n du f o u r ncessaire la performance o p t i m a l e
de ce d e r n i e r .
L'on a t u d i la r e n t a b i l i t d'une chaudire de rchauffage u t i l i s e sur
un f o u r de 180t pour f o u r n i r une p a r t i e de l a vapeur ncessaire
une a c i r i e p r o d u i s a n t des a c i e r s s p c i a u x . L'on s ' e s t rendu compte
qu'en f o n c t i o n de l a q u a n t i t de vapeur f o u r n i e , i l f a u d r a i t de
1,7 2,9 ans pour r e n t a b i l i s e r l ' i n s t a l l a t i o n .
L'on p r v o i t un
taux de rendement d ' e n v i r o n 33 58%.
Dans les c i r c o n s t a n c e s a c t u e l l e s , i l n ' e s t gure i n t r e s s a n t d ' u t i l i s e r
de la vapeur de rchauffage pour gnrer de l ' l e c t r i c i t , sauf s i
l ' o n dispose dj d'une g n r a t r i c e . Cette c o n c l u s i o n est v a l a b l e
pour un grand consommateur d ' n e r g i e au Royaume-Uni; l a r e n t a b i l i t
p o u r r a i t t r e s u p r i e u r e dans d ' a u t r e s pays de la CEE o l e s
s t r u c t u r e s t a r i f a i r e s e t l e cot de l ' n e r g i e sont d i f f r e n t s .
Une a u t r e s r i e d ' e s s a i s sur l a performance des tubes dans l e s q u e l s
c i r c u l e n t les e f f l u e n t s gazeux d'un f o u r arc l e c t r i q u e e t
l ' i n s t a l l a t i o n d'une chaudire la cote p o u r r a i e n t c o n s t i t u e r
la base d'un p r o j e t de dmonstration adquat.

VIII
SOMMAIRE

Page

1.

INTRODUCTION

2.

LES EFFLUENTS GAZEUX DU FOUR A ARC ELECTRIQUE

3.

UTILISATION DE LA CHALEUR PERDUE

4.

LES ASPECTS PRATIQUES DE L'UTILISATION D'UNE


CHAUDIERE DE RECHAUFFAGE

4.1
4.2
4.3
4.4
4.5

2
3
3
4
5

5.

Considrations d'ordre gnral


Emplacement
Contrle de la temprature du gaz d'arrive
Impurets
Epuration des gaz

EVALUATION ECONOMIQUE

5.1 Demande en vapeur


5.2 Etudes sur le terrain
5.3 Augmentation de l'usage de vapeur

6
6
8

5.4 Gnration d'lectricit

6.

TRAVAUX SUPPLEMENTAIRES

7.

CONCLUSIONS

8.

REFERENCES

9.

REMERCIEMENTS

10

TABLEAUX

11

FIGURES

19

APPENDICES

30

IX

LISTE DES TABLEAUX


1.

Concentration approximative des principaux constituants des fumes de


four arc lectrique (particule de 0,03 1 um)

2.

Demande de vapeur des installations arc lectriques

3.

Temprature et dbit des effluents gazeux pour une coule typique

4.

Performance de la chaudire - Charge de base

5.

Balance des cots - Charge de base

6.

Performance de la chaudire - Cas intermdiaire

7.

Balance des cots - Cas intermdiaire

8.

Performance de la chaudire - Demande maximum

9.

Balance des cots - Demande maximum satisfaite

10.

Performance de la turbine vapeur - Grosse chaudire utilise uniquement pour


la gnration d'lectricit

11.

Performance de la turbine vapeur - Grosse chaudire satisfaisant la charge


de base, turbine utilisant la vapeur excdentaire

12.

Performance de la turbine vapeur - Petite chaudire utilise uniquement


pour la gnration d'lectricit

13.

Performance de la turbine vapeur - Petite chaudire satisfaisant la charge


de base, turbine utilisant la vapeur excdentaire

14.

Balance des cots - Grosse chaudire utilise uniquement pour la gnration


d'lectricit

15.

Balance des cots - Grosse chaudire satisfaisant la charge de base,


gnration d'un surplus

16.

Balance des cots - Petite chaudire utilise uniquement pour la gnration


d'lectrici t

17.

Balance des cots - Petite chaudire satisfaisant la charge de base,


gnration d'un surplus

LISTE DES APPENDICES


1.

Mesures des effluents gazeux

2.

Nouveau coude d'vacuation

3.

Thorie de la similarit des

4.

Performance du systme d'extraction avec plus grand coude

modles

LISTE DES TABLEAUX DES APPENDICES


A2.1 Rapports entre l'coulement des gaz dans le coude (Q ), le dbit d'air de
lance (Q ) , la temprature (T) et le niveau d'aspiration de la chambre (S)
a
A2.2 Dbits gazeux prvus dans le coude (Q ) et niveaux d'aspiration de la chambre (S)
9
LISTE DES FIGURES
1.

Effluents gazeux - four de 180 t

2.

Cycle typique de refoulement de la chaleur perdue - four de 180 t

3.

Cycle typique de refoulement de la chaleur perdue - four de 180 t


alimentation continue

4.

Agencement gnral d'un four arc lectrique et de la tuyauterie pour les


effluents gazeux. Emplacements possibles des chaudires

5.

Effluents gazeux pour un four de 180 t avec systme d'extraction modifi

6.

Section de la sonde

7.

Dpt sur la sonde d'essai

8.

Coefficients de transfert de chaleur

9.

Effet de la vapeur d'eau sur l'efficacit du prcipitateur

10.

Diagramme montrant la variation mensuelle de la demande de vapeur pour


1'installation A

11.

Agencement gnral de la chaudire

LISTE DES FIGURES DES APPENDICES


A2. 1 Positions

des mesures

A2.2 Combinaisons d'orifice d'entre et de diamtre de coude


A2.3 Vue gnrale du modle
A2.4 Graphique du rapport entre Q :Q et la temprature des gaz du coude, T
9 e
9
A2.5 Graphique montrant le rapport entre le niveau d'aspiration de la chambre, S
et le dbit d'air de la lance, Q
a
A4.1 Graphique montrant le rapport entre le dbit du coude et le dbit de chaleur
pour une srie de vitesses d'enlvement du carbone
A4.2 Graphique du dbit du coude pour le systme d'extraction d'origine
14.3 Graphique du dbit du coude pour le systme d'extraction modifi

XI

British Steel Corporation


Die Eignung des Einsatzes von Abhitzkesseln fr Wiedergewinnung
der Energie aus den Abgasen der Lichtbogenfen
EWG Vertrag Nr. EE-B-2-160-(N)
Zusammenfassung
Energie kann in den Abgasen eines Lichtbogenofens, der mit
ultrahoher Kraft angetrieben wird, in Mengen bis zu ca. 15 MW
ausgestoen werden, und das macht 200 kW h/t des Flssigstahls
aus. Die Mglichkeit, einen bedeutenden Anteil dieser Energie
als Dampf unter Einsatz eines Abhitzkessels wiederzugewinnen, ist
untersucht worden. Die Wahl zwischen dem Einsatz des Dampfes, um
die Nachfrage im Stahlwerk zu befriedigen, oder um Elektrizitt
zu erzeugen, oder eine Kombination der beiden, ist auch bercksichtigt worden.
Eingehende Messungen der Bedingungen, die im Abgasflu existieren, sind berall im Stahlherstellungsproze fr Ofenverfahren gemacht worden, und das betrifft Sauerstoffblasen,
kontinuierliche Beschickung und zustzliche Befeuerung mit
Brennern, die mit Sauerstoff und Brennstoff beheizt werden.
Verschiedene praktische Auswirkungen des Einsatzes von Abhitzkesseln sind untersucht worden, und diese betrafen den Standort
des Kessels, die Zunahme an Trockensubstanz in den Rohren, die
Auswirkung auf die Gasreinigung, wenn ein Kessel gebaut wird, und
die Steuerung der Ofenextraktion, um optimale Leistungen zu
e rzielen.
Die Rentabilitt des Einsatzes eines Abhitzkessels in einem 180 t
Ofen, um Teil der Dampfnachfrage in den Stahlwerken zu befriedigen, wo Spezialsthle hergestellt werden, ist untersucht
worden. Rckzahlungszeitrume von zwischen 1,7 und 2,9 Jahren
werden angedeutet, dies hngt von dem Anteil der beschickten
Ladung ab. Man schtzt, da die Kapitalverzinsung der
Investierung zwischen 33-58% liegt.
Der Gebrauch von Abwrmedampf, um Elektrizitt zu erzeugen, ist
unter den heutigen Umstnden nicht attraktiv, es sei denn, da
Erzeugungskapazitt bereits existiert. Diese Schlufolgerung
trifft auf einen groen Energieverbraucher in Grobritannien zu;
die Ersparnisse knnten in anderen EWG Lndern gnstiger sein, wo
andere Tarifgefge und Energiepreisbedingungen vorherrschen.
Weitere Untersuchungen der Rohranordnungsleistung im Abgasflu
eines Lichtbogenofens und die Installation eines Kessel im
Mastab 1:1 knnten die Grundlage fr ein geeignetes Demonstrationsprojekt bilden.

XII
PE 1 0 6 - 6 841

EE-B-2-1

Inhaltsverzeichnis

Seite

1.

Einleitung

2.

Die Abgase des L i c h t b o g e n o f e n s

3.

Abwrmeverwertung

4.

P r a k t i s c h e A s p e k t e , d i e den E i n s a t z e i n e s
Abhitzkessels betreffen

4.1
4.2
4*3
4.4
4*5

2
3
3
4
5

5.

A l l g e m e i n e Erwgungen
Standorte
Steuerung der einstrmenden Gastemperatur
Verunreinigung
Gasreinigung

Wirtschaftliche
5.1
5.2
53
5.4

60-UK(N)

Bewertung

Dampfnachfrage
Einzelfallstudien
Zunehmender Dampfgebrauch
Elektrizittserzeugung

6
6
6
8
8

6.

Schlufolgerungen

7.

Literaturverzeichnis

8.

Danksagungen

10

Tabellen

1 1

Abbildungen

19

Anhnge

30

XIII

Aufstellung der Tabellen

1.

Ungefhre Konzentrationen der Hauptbestandteile des Licht


bgenofenrauches (Teilchengre 0,031 )

2.

Dampfnachfrage fr Lichtbogenfen in Stahlwerken

3.

Abgastemperatur und Flu fr einen typischen Gu

4.

Leistung des Kessels Grundbelastungsfall

5.

Kostenbilanz Grundbelastung

6.

Leistung des Kessels dazwischenliegender F all

7.

Kostenbilanz dazwischenliegender F all

8.

Leistung des Kessels maximale Nachfrage

9.

Kostenbilanz maximale Nachfrage befriedigt

10.

Dampfturbinenleistung groer Kessel erzeugt nur Elektrizitt

11.

Dampfturbinenleistung groer Kessel befriedigt die


Grundbelastung, Turbine benutzt berschigen Dampf

12.

Dampfturbinenleistung kleiner Kessel erzeugt nur Elektrizitt

13.

Dampfturbinenleistung kleiner Kessel befriedigt die


Grundbelastung, Turbine benutzt berschigen Dampf

14.

Kostenbilanz groer Kessel erzeugt nur Elektrizitt

15.

Kostenbilanz groer Kessel befriedigt die


Grundbelastung, berschu wird erzeugt

16.

Kostenbilanz kleiner Kessel erzeugt nur Elektrizitt

17.

Kostenbilanz kleiner Kessel befriedigt die


Grundbelastung, berschu wird erzeugt

Aufstellung der Anhnge


1.

Abgasmessungen

2.

Neues Abzugknierohr

3.

hnlichkeitstheorie des Modells

4.

Leistung des Extraktionssystems mit vergrertem Knierohr

Aufstellung der Anhnge zu den Tabellen


A2.1 Verhltnisse zwischen dem Knierohrgasflu (Q ) , dem Luftdurch
flu im Zwischenraum (Q ) , der Temperatur (T? und den Kammerabsaugniveaus (S)
a
A2.2 Vorhergesagte Durchflsse durch das Knierohr (Q ) und den
Kammerabsaugniveaus (S)

XIV

Aufstellung der Abbildungen


1.

Abgasbedingungen ISO t Ofen

2.

Typischer Verwerfungszyklus der Abwrme 180 t Ofen

3.

Typischer Verwerfungszyklus der Abwrme 180 t Ofen


mit kontinuierlicher Beschickung

4.

Allgemeine Anlage des Lichtbogenofens und dazugehrige


Abgasrohrleitungen mgliche Kesselstandorte

5.

Abgasbedingungen fr einen 180 t Ofen mit modifiziertem


Extraktionssystem

6.

Querschnitt durch die Sonde

7.

Ablagerung auf der Versuchssonde

8.

Koeffizienten der Wrmebertragung

9.

Auswirkung des Wasserdampfes auf die rationelle


Arbeitsweise des Niederschlagapparates

10.

Diagramm, gezeigt wird die monatliche Schwankung der


Dampfnachfrage im Stahlwerk A

11.

Allgemeine Anordnung des Kessels

Aufstellung der Anhnge zu den Abbildungen


A2.1

Messungspositionen

A2.2

Kombinationen der Eingangsffnung und dem Knierohrdurchmesser

A2.3

Allgemeine Ansicht des Modells

A2.4

Graphische Darstellung des Verhltnisses zwischen Q :Q


und der Knierohrgastemperatur, T

A2.5

Graphische Darstellung, gezeigt wird das Verhltnis zwischen


dem Kammerabsaugniveau, S und dem Luftdurchflu im
Zwischenraum, Q

A4.1

Graphische Darstellung, gezeigt wird das Verhltnis zwischen


dem Knierohrflu und dem Wrmeflu fr eine Reihe von
Kohlenstoffbeseitigungsmengen

A4.2

Graphische Darstellung des Knierohrflusses fr das ursprngliche


Extraktionssystem

A4.3

Graphische Darstellung des Knierohrflusses fr das modifizierte


Extraktions system

OL

British Steel Corporation


THE FEASIBILITY OF USING WASTE HEAT BOILERS TO RECOVER
ENERGY FROM THE EXHAUST GASES OF ELECTRIC ARC FURNACES
EEC Agreement No. EE-B-2-160-UK (N)
FINAL TECHNICAL REPORT

1.

INTRODUCTION

The proportion of steel manufactured by the electric arc process has steadily
increased over the past 30 years. In 1982, it accounted for about 34% of UK
liquid steel production, and there are over 250 electric arc furnaces in
operation within the ECSC.
Electrical energy is a major contributor to the overall manufacturing cost, and
its conservation is of prime importance. The largest single source of energy
loss from an electric arc furnace is via the waste gas stream, and urgent
consideration is being given to methods of reducing the quantity of energy lost
in this way, and to recovering heat from the exhaust gases. Scrap preheating
is potentially the most attractive method of energy recovery, but its
effectiveness is often restricted because of practical considerations. In
general, steelworks use considerable quantities of steam for various purposes.
The objective of this study was to investigate the feasibility of using a waste
heat boiler to generate steam using energy recovered from the exhaust gases of
an electric arc furnace. The steam produced in this manner would replace that
generated in conventional boiler plant, thereby reducing energy costs.
Case studies, based on a furnace producing special steels within the British
Steel Corporation, have been used to demonstrate the advantages and
disadvantages of this method of energy recovery in practical and economic
terms.
2.

THE WASTE GASES OF THE ELECTRIC ARC FURNACE

The volume, temperature, composition, and hence the energy content, of the
waste gases vary throughout the furnace cycle, and depend on such variables as
the charge material, melt down rates, oxygen practice, supplementary firing
practice and the type of steel being produced'. A survey of the literature was
carried out at the beginning of the project and revealed a diversity in the
reports of the quantity of energy contained in the waste gases. Of the total
energy input to the furnaces, fractions of between 5 and 29%, accounting for 30
to 130 kW h/t of liquid steel, were estimated to be lost in the exhaust
gases 2-1 *. In order to produce reliable information, detailed measurements were
made on a number of furnaces within BSC using techniques developed specially
for use in the aggressive conditions to be found in the waste gases of electric
arc furnaces 5 ' 6 . Figure 1 shows the data obtained from a typical cast on a
180 t UHP electric arc furnace; an average waste heat cycle is shown in
Fig. 2. When continuous charging techniques or supplementary firing with
oxyfuel burners are employed, the rate of energy rejection in the waste gases
may be increased. Figure 3 is an average waste heat cycle for 180 t furnace
with continuous feeding of granulated iron. In this case, the average rate of
energy rejection is 15.5 MW, which for a charge of 180 t is equivalent to a
loss of about 200 kW h/t of liquid steel. Details of the measurements made and
the techniques used are given in Appendix 1.
3.

WASTE HEAT UTILISATION

In considering the practical applications of recovered waste heat from the arc
furnaces, the following factors should be taken into account:1.

Changes in heat flow within the furnace cycle.

2.

Forms in which the waste heat is recovered (e.g. scrap preheating,


steam, electricity generation).

3.

Destination and transportation of recovered energy.

4.

Reliability of recovery equipment, maximisation of furnace


availability and ease of maintenance.

5.

Effect of the presence of the waste heat recovery unit on


the operation of other items of plant.

6.

Capital and operating costs.

The exhaust gas leaves the arc furnace at a high temperature and in principle
should have considerable potential for energy recovery. However, its dirty
condition and variable nature create significant difficulties in achieving this
end. Much of the effort devoted to energy recovery has justifiably been
concentrated on scrap preheating because the recovered heat is returned to the
process. Some examples of the scrap heating techniques are basket preheaters,
the BBC/Brusa rotary kiln process and the twin-shell method'-11*. The first of
these has been the most widely applied because of its relative simplicity and
its ability to be retrofitted in an established melting shop. A number of
installations are now operating successfully, but experience has shown that the
quantity of energy which can be recovered is restricted by practical
considerations such as the need to avoid overheating the charging basket, and
to prevent welding and bridging in the charge. The reported energy savings are
in the region of 20 to 50 kW h/t, representing 10 to 25% of the total energy in
the waste gas.
The more elaborate techniques suffer from the disadvantage of high capital
cost, high maintenance costs and unsuitability for incorporation into existing
melting shops.
Consideration could be given to other uses for the waste heat, such as the
production of
hot water for boiler feeding, space heating, district heating and
amenity use 15 . However, a more attractive alternative would be to provide
energy for steam raising. Most steelworks require considerable quantities of
steam for process and heating purposes, and its generation from waste heat
would reduce the consumption of fuels in steam raising plant. The use of a
waste heat boiler would be particularly advantageous either in a melting shop
where practical considerations render scrap preheating uneconomic or in tandem
with a preheater which removes only a small fraction of the energy in the waste
gas stream.
To realise its economic potential, a waste heat boiler system must fulfil a
number of requirements:1.

It should be capable of incorporation into the extraction system


of the furnace with minimum reorganisation of the melting shop
facilities and the existing waste gas handling equipment.

2.

The steam cycle must be capable of being matched to the works


demand and complemented by existing steam raising plant.

3.

The boiler must be reliable and easily maintained so that


production stoppages are avoided.

4.

The waste gas extraction system must operate without the boiler
in service, if necessary.

The various aspects of the use of a waste heat boiler have been considered in
this project.
4.

PRACTICAL ASPECTS INVOLVED IN THE USE OF A WASTE HEAT BOILER

4.1

General Considerations

A number of practical aspects involved in the use of a waste heat boiler have

been considered in detail involving experimentation on plant or in the


laboratory where appropriate. The main factors discussed in Section 4.2 are:(a)

The location of the boiler within the waste gas handling system.

(b)

Maximisation of energy recovery by control of the waste gas


conditions.

(c)

The effect of the accretion of solid material on boiler tubes,


and its effect on heat transfer.

(d)

The effect of the presence of the boiler on gas cleaning.

4.2

Location

Figure 1 indicates that the gases from the furnace contain up to 55% of carbon
monoxide. Furthermore, at certain parts of the furnace cycle, up to 10% of
hydrogen may be involved. The variable composition of the gases render their
collection extremely difficult. The practice adopted within BSC is to mix the
gases with air and burn them in a brick lined combustion chamber. The volume
of air added is designed to ensure that the temperature of the gases after
combustion is never greater than 1250C. The combusted gases are then cooled
further, either by water in a spray tower, or by mixture with large quantities
of air drawn from the roof extraction hoods of the melting shop. Finally, the
gases are cleaned using wet or dry electrostatic precipitators, or bag filters.
An alternative method of cleaning not commonly used on the electric arc furnace
plants of BSC, would be a high pressure-drop Venturi scrubber.
To ensure safe operation of a boiler, it is considered necessary to retain the
use of the brick lined combustion chamber. The gases would continue to be
mixed with sufficient air to ensure complete combustion, and to reduce their
temperature to an acceptable level. The waste heat boiler would be situated
immediately after the combustion chamber and fitted with a hot gas by-pass to
avoid interruption to furnace operation in the event of boiler problems.
Consideration was given to the replacement of the combustion chamber by a shell
boiler but this course of action was rejected because it would not be possible
to extract an acceptable amount of heat within the dimensions available. Also,
a failure of the boiler could result in an interruption to furnace operation.
Figure 4 indicates suggested locations for the boiler.
The most desirable site for the boiler is considered to be immediately
downstream of the combustion chamber for the following reasons:(a)

The gases leaving the furnace have mixed and burned in the
air indrawn at the slice gap, and hence are at their
maximum temperature at the end of the combustion chamber.

(b)

Large particulates will have dropped out of the gas stream


in the combustion chamber and will not reach the boiler.

(c)

The conditioning tower, if used, does not require lining to


withstand high temperatures and can function as before when
the boiler is by-passed at times of low steam demand, or in
an emergency situation.

(d)

This position requires the shortest possible length of lined


ductwork.

Should it be desirable to use a boiler in conjunction with a scrap preheater,


it is preferable to locate the boiler upstream of the preheater, thereby
presenting gases at the highest possible temperature to the boiler and
maximising its efficiency. In this case, the boiler should be designed to have
an exhaust gas temperature in the region of 700C maximum which would be
adequate for the scrap preheater in which a final steel temperature in the
region of 400C is desirable.
4.3

Control of Inlet Gas Temperature

Whilst the maximum temperature of the combusted waste gases is designed to be

1250C, this figure is seldom reached in practice. During the cast illustrated
in Fig. 1, the maximum temperature was in the region of 800C, and for much of
the time a lower value was achieved. To obtain the maximum benefit from a
waste heat recovery system, it is essential to avoid degradation of the waste
gas temperature. Furthermore, to obtain the most efficient overall performance
in energy terms, it is necessary to ensure that as far as possible combustion
takes place within the furnace, rather than externally in the combustion
chamber. The arrangement of the waste gas extraction system and its control
must, therefore, be designed to allow the most suitable conditions for heat
transfer in the furnace whilst achieving simultaneously the maximum efficiency
of the waste heat recovery unit. A study has been made of methods of changing
the geometry of the furnace offtake elbow, the air infiltration gap and the
combustion chamber to effect better control of the absolute and relative rates
of furnace extraction and air infiltration.
An isothermal model was used to determine the most appropriate geometry and the
results indicated that an increase in the diameter of the offtake from 1.0 to
1.4 m diameter would produce the best performance. The layout of the water
cooled roof panels precluded an elbow of the ideal size, and a compromise
diameter of 1.3 m was found to be acceptable. The model tests and their
results are described in detail in Appendices 2 and 3.
The new elbow was designed, constructed and installed on the furnace and
extensive waste gas measurements were made to assess the benefits of the new
arrangement. Appendix 4 describes the approach made to optimise the release of
heat in the furnace and the operation of the waste gas extraction system.
The experimental trials showed that it was possible to control the furnace
pressure to a level which would permit the inspiration of sufficient air into
the furnace to combust carbon monoxide fully. Consequently, the release of
chemical heat in the furnace would be at the highest level. The trials also
indicated that it should be possible to control the rate of extraction of waste
gases to avoid excessive infiltration of air during periods of low gas emission
from the furnace, thereby avoiding excessive heat losses and the degradation of
the waste gas temperature level. Some further adjustment of the geometry of
the air infiltration gap and the combustion chamber entry was shown to be
desirable in order to increase further the temperature of the gases reaching
the boiler. Figure 5 shows typical operating conditions experienced during the
trials.
4.4

Fouling

The waste gases from an electric arc furnace contain large amounts of
particulate matter; concentrations of up to 200 g/m3 have been measured. At
the outlet of the combustion chamber, the material will be in solid form with
the typical size range and composition shown in Table 1. The accretion of
solid matter on the tubes of a waste heat boiler would present a maintenance
problem as well as a reduction in its efficiency. To simulate a boiler tube,
probes were constructed to the design shown in Fig. 6. The probes were
constructed with concentric water passages so that they could be readily
inserted into the measurement positions and removed for inspection.
To simplify the experimental procedure, the flow of water through the probe was
selected to avoid boiling and the production of steam. The experimental
measurements made were as follows:(a)

Heat flux intensity.

(b)

Gas temperature.

(c)

Gas flow rate.

(d)

Effect of accretion on heat transfer rate.

(e)

Accretion of solid matter and its subsequent removal.

Two probes were installed at a point between the combustion chamber and the
conditioning tower in the extraction system of a 180 t arc furnace. This
position was chosen as it is the most probable location for a boiler and the

gas conditions would be similar to those encountered in a boiler. One probe


was installed horizontally and one vertically to allow the effect of the
orientation of a tube to be assessed. The position has good access to the
inside of the duct to allow in situ examination of the probes to be made.
The probes were left in position for three months during which the furnace was
in normal production. At the end of this period, there was only a thin, fairly
even deposit of material on the vertical probe. The horizontal tube showed an
accretion of material on the downstream segment of its surface. The deposit
was fine and powdery, crusting in places and easily friable. The maximum
thickness was less than 8 mm. The nature of the material suggested that it
would be readily removed with conventional soot-blowing equipment. Figure 7
shows photographs of the horizontal probe at the end of the test.
Figure 8 shows the variation of the heat transfer rate with gas temperature,
and indicates the importance of keeping the latter at the highest possible
level. No significant change in this relationship was detected over the trial
period.
The position of the probes had been selected to allow them to be subjected to
similar gas temperatures and dust loadings to those existing in a boiler.
However, the velocity of the gas at the experimental position was higher by a
factor of approximately five than would exist in a boiler. Clearly this
unrepresentative velocity may have an effect on the extent of fouling.
Therefore, one probe was resited in the combustion chamber close to the exit
where the gas velocities are more comparable with those in a boiler. It
remained in this position for two months, during which time the accretion of
material was similar in nature and extent to that experienced in the original
location.
As a more rigorous test of the accumulation of deposit in a boiler, it would be
advantageous to insert a bank of steam tubes into the combustion chamber. It
is planned that an experiment of this nature should take place, but it was not
possible to carry out this work within the time scale of this project.
The experimental work carried out has been encouraging in that the extent of
fouling has been less than was feared, and its influence on heat transfer rates
was not serious.
4.5

Gas Cleaning

The methods commonly used for gas cleaning are as follows:(a)

Dry electrostatic precipitator.

(b)

Wet electrostatic precipitator.

(c)

Bag filter.

(d)

Wet scrubber.

In every case, the temperature of the gases would be reduced by the addition of
air or by water sprays before entry to the gas cleaning system. The presence
of the boiler would reduce substantially the cooling requirement although it
would be necessary to retain the facility to cater for periods when the boiler
was inoperative.
The reduction in temperature of the waste gases leaving the boiler would create
a problem with the operation of dry precipitators. The efficiency of this type
of plant is critically dependent on the humidity of the gases as shown in
Fig. 9. Water is usually added in the spray quenching carried out in the
conditioning tower. It would be impossible to achieve the desired
concentration of 15% water vapour with gases which have left the boiler at
700C, or less. To restore the humidity by the addition of steam, would negate
the benefits of the waste heat boiler. It is concluded, therefore, that the
use of a dry precipitator would be incompatible with a waste heat boiler, or
other device giving a similar level of energy recovery.
With wet electrostatic precipitators, there is a danger that material deposited

on the electrodes may become caked and difficult to remove should the humidity
of the waste gases be low. The reduced requirement for water addition which
will exist if a boiler is used could produce problems of this nature, but past
experience indicates that these would not be insuperable.
The other methods of gas cleaning involve no particular problem when applied to
a system which incorporates a waste heat boiler.
5.

ECONOMIC EVALUATION

5.1

Steam Demand

To obtain the best return on investment, it is necessary to match the output of


a waste heat boiler to steam users in the steelworks, and elsewhere. The
demand for steam will vary from works to works and will be to some extent
variable within an individual plant. A survey was carried out in the Sheffield
area of BSC in order to obtain information about the extent of the steam
demand.
Table 2 gives a summary of the information collected. The quantity entitled
'base load' is the lowest demand encountered under normal production
conditions. The steam demand varies throughout the year, and Fig. 10 shows a
typical pattern. It is significant that the quantity of steam used by the
various works has been reduced substantially over the last two years by energy
conservation measures, plant rationalisation and conversions to other sources
of energy. It is vital that plans to reduce the steam demand be considered
when assessing the viability of a waste heat boiler.
The choice of the quantity of steam to be produced and hence the number and
sizes of boilers depends on the economic viability of a number of stages of
increasing steam production. These are as follows:(a)

Satisfy base load only.

(b)

Generate enough steam to satisfy loads up to the highest


existing demand, by-passing the boiler when necessary.

(c)

Increase the works demand for steam, or export to other users.

(d)

Electricity generation.

5.2

Case Studies

5.2.1

General Principles

Case studies involving these options for Works A have been made. A number of
manufacturers were invited to submit proposals for waste heat boilers to
operate under the typical conditions defined by the initial extraction system
surveys. Detailed discussions were conducted with one manufacturer who showed
particular interest. Outline designs were prepared for the boilers needed to
produce steam at the rates and pressures required to satisfy the demand for
various options, and budget costs estimated. The cost of the modifications
required to incorporate the boilers into the plant was estimated by BSC staff.
The information gained from the extraction system surveys was used to define
the waste gas conditions for an average cast (Table 3 ) . These results combined
with the design characteristics of the boiler, were used to forecast the steam
generation cycle. In order to estimate the annual savings, it was assumed that
the furnace produced 40 casts/week, operating over 120 h, with 48 weeks
production per year. Because the steam production from an arc furnace is
variable, and will fall to zero for short periods between casts or longer
periods in the event of a plant stoppage, it is necessary to provide some
accumulation capacity and also maintain conventional boiler plant on standby.
For flexible and reliable operation it is considered that one fuel fired boiler
should be kept in production at all times at its minimum firing rate so that it
can fulfill the works demand without interruption to production when required.
For the works under study, the boiler would be fired with heavy fuel oil at a
minimum rate of 5000 kg/h and produce steam at a marginal cost of 11.43/t.

With the boiler operating on minimum flow, its efficiency is assumed to fall by
4% and this change is recognised by an increased cost for the production of
steam in these circumstances.
A preliminary economic evaluation was included in earlier reports of this
project 16 and this has been refined in the light of the following information:(a)

Downward revision of the steam demand for Works A.

(b)

Furnace steam cycle considered in more detail.

(c)

Practice for operating conventional boilers amended.

Additionally, further cases have been examined.


For each example studied, the simple payback of capital and the rate of return
on investment have been calculated following the procedure recommended in the
Commissions's Document No. XII/962-2/81-EN, 'Guidelines for the presentation of
periodic and final reports. Energy savings evaluation and cost/benefit
calculation'. The economic life time of the installation has been taken to be
10 years.
5.2.2

Case 1 - Satisfy Base Load

This boiler would produce enough steam to satisfy the works demand (less the
minimum output of the conventional boiler plant) during the summer months. At
other times, the balance of the demand would be produced by the regular boiler
plant. The general arrangement of the boiler is illustrated in Fig. 11. The
heat exchanger would consist of two banks of plain tubes of 50.8 mm outside
diameter arranged in rows on 100 mm centres. Each bank would be 23 tubes wide
and 7 deep being 4 m in length. The two pass arrangement allows the gases to
be returned to the existing extraction system with least modification. Steam
would be produced at a pressure of 1.1 MN/m2 from deaerated feed-water at
105C. The boiler would be fed from existing water treatment plant. Table 4
shows the variation of steam production throughout a furnace cycle.
Table 5 shows the cost balance for this arrangement for which the payback
period is slightly less than 2.9 years, and the rate of return on investment is
32.9%.
5.2.3

Intermediate Case

The boiler for this case would have the general arrangement shown in Fig. 11
but would consist of two banks of 5.5 m tubes arranged 33 wide by 13 deep. The
steam condition would be the same as for the previous case. The output of this
boiler would exceed the base load for a substantial part of the year, and on
occasions it would be necessary for some of the waste gases to by-pass the
boiler. However, the steam demand is well above the base load for most of the
year and the full output of the boiler will be absorbed. Table 6 shows the
steam cycle for this unit, and Table 7 summarises the economic balance.
5.2.4

Maximum Demand-

The final case to be considered is that of a boiler sized to meet the maximum
normal demand of the works. The main boiler plant would operate for the
majority of time on its minimum firing rate, and would act solely as a standby
unit. No detailed proposal for a boiler of this duty was obtained from a
manufacturer, and the cost and performance estimates have been extrapolated
from the information supplied for other units. The accuracy of this prediction
will be inferior to the others, but indicates the effect of the scale of the
installation. The forecast steam cycle is shown in Table 8, and the economic
balance in Table 9. The simple payback of capital would be 1.72 years, and
the rate of return on investment is 57.6%.
5.2.5

Comments on In-Works Steam Use

The case studies above show that the maximum demand for Works A could be
satisfied by a boiler on a single furnace. Whilst supply and demand could be
more conveniently met by smaller boilers on two or three furnaces, the costs

involved in modifying the existing equipment in the melting shop would render
the use of more than one boiler uneconomic. The analyses show that it is
beneficial to size the boiler to generate more than the base load, even though
this will involve partially by-passing the boiler at certain times. The
indication is that there is an optimum size for the boiler which lies towards
meeting the maximum demand. All three cases yield a return on investment which
would be acceptable to many companies, though the smallest boiler may not meet
the economic criteria demanded in the present circumstances.
5.3

Increased Steam Usage

As indicated earlier a survey of electric arc furnace plants in BSC showed that
the maximum potential for steam generation from waste heat far exceeds the
current demand. In recent years the drive for economies in the use of energy
have led to reductions in steam consumption from all areas within the
steelworks. This reduction has been effected both by energy management schemes
and by the replacement of steam by other media such as compressed air in
atomisation applications and hot water for heating.
Opportunities for using additional steam within the steelworks are limited by
the quest for continual reduction in energy costs unless the economic benefits
of employing waste heat steam are attractive. A return to using steam for
items such as burner atomisation is not favourable even with waste heat
generated steam as the variable nature of this supply requires that fuel fired
boilers are needed to maintain the supply to match the continuous demand. The
melting shop does not necessarily operate during periods when the potential
steam users are active and vice versa, leading either to extensive use of fuel
fired boilers or over production by the waste heat boilers.
It is apparent from previous work that few new applications for large steady
steam consumption will arise and on this basis consideration must be given to
the export of steam to other works or to the generation of electricity via a
steam turbine.
The export of steam depends on the availability of suitable users in the
locality and the existence of a distribution network. The export of steam from
a waste heat boiler is again complicated by its variability of the level of
supply. Whenever the waste heat boiler is non-productive steam has to be
generated and exported from primary fuel fired boilers, and the pricing of any
exported steam must take these periods into account.
5. 4

Electricity Generation

Consideration has also been given to using excess steam to generate


electricity. The economic analysis will also indicate the value of electricity
generation to works where the steam demand is too low to justify the
installation of a waste heat boiler.
Discussions were held with boiler and turbine manufacturers, and it was
considered that the most straightforward approach would be to use saturated
steam from the boiler to drive a single stage turbine. Although the generation
efficiency would be lower than that achieved with a multistage machine, the
added complications of superheating the steam and the more stringent control of
steam temperature and pressure would be avoided.
Four cases relating to Works A were considered in detail:(a)

The boiler sized to meet the maximum steam demand delivering


excess steam to a turbine.

(b)

The same boiler producing steam for electricity generation


only.

(c)

The boiler sized to meet the summer base load delivering steam to
the turbine during limited periods when production exceeds demand.

(d)

The small boiler producing steam for generation only.

In each case, the steam production cycle was forecast as previously and the

quantity of electricity generated calculated from the operating characteristics


of suitably sized turbines.
The electricity generation patterns are shown in Tables 10 to 13 respectively,
and the economic balances in Tables 14 to 17.
It would seem that the installation of a waste heat boiler and turbine for
generation only is uneconomic under present circumstances. The use of a
turbine to use excess steam is a better proposition, but gives a poorer return
on investment than direct use of the steam. In the case of the smallest
boiler, the use of a turbine is clearly uneconomic.
Where surplus generating facilities already exist, of course, there will be a
direct saving with little capital outlay. The main cost involved in this
situation would be the provision of a steam main from the melting shop to the
generating plant plus any control equipment which is necessary.
The above cases were based on the relative costs of energy to a large user in
the UK. Electricity generation may warrant further consideration in other
EEC countries where different tarrif structures and price relativities exist.
6.

FURTHER DEVELOPMENT

The case studies have shown that the recovery of energy from the exhaust gases
of an electric arc furnace can yield an attractive return on investment. There
are apparently no insuperable technical or logistical problems. The insertion
of a water cooled probe into a typical waste gas stream indicated that fouling
would be tolerable and that the heat transfer performance of a boiler would not
deteriorate at an unacceptable rate. However, final confirmation of this view
could only be obtained by tests using an array of boiler tubes in a situation
which is closely representative of the conditions in a full sized boiler.
It is recommended that a prototype boiler section be installed on a suitable
furnace to be followed, if successful, by a full scale installation. These
tests could form the basis of an EEC-sponsored Demonstration Project.
Recent charges in the demand for stream and its availability from other sources
have rendered the installation of a boiler less attractive on the site
originally envisaged. However an alternative site within the British Steel
Corporation is now being examined.
7.

CONCLUSIONS

The energy rejected in the waste gases of a UHP electric arc furnace has been
shown to be in the region of 200 kW h/t of liquid steel.
Economic case studies of using steam derived from a waste heat boiler to
supply part of the demand for a works producing special steels indicate that a
payback of capital may be obtained over periods of 1.7 to 2.9 years. Based on
an economic lifetime of ten years, the rate of return on investment would range
from 33-58%. The installation of a boiler would therefore be a suitable topic
for a Demonstration Project.
The use of waste heat steam to generate electricity is not attractive under the
present circumstances relating to a large user of energy in the UK. unless
surplus generating capacity already exists. It is possible that the economics
may be more favourable in other EEC countries where different tarrif structures
and energy price relativities pertain.
Various practical factors including modifications to existing plant, the effect
of gas cleaning, the fouling of boiler tubes and the optimisation of the
overall energy balance of the furnace and boiler have been considered.
8.

REFERENCES

1.

Johnson, J.E., 'Electric Arc Furnaces : Technical Aspects of


Fume Control', Environmental Pollution Management,
January/February 1980, pp 20-25.

2.

Blank, J.R. and Garbutt, F.R., 'Energy Conscious Electric Are


Steelmaking', Leoben Conference 1980, Metals Society,
Book 270, 1981.

3.

Pantz, J. 'Recovery of Energy from Arc Furnaces', Elektrowrme


International, Vol. 37, No. B2, April 1979, pp 86-92.

4.

Fernandez Lopez, M. et al, 'Uses of Arc Furnace Fume Energy',


Cenim Revista de Metalurgia, 15, (1), 1979, January/February,
pp 43-56.

5.

Smithson, D.J., 'Remote Monitoring of the Properties of


Untreated Effluent Gas from Oxygen Steelmaking Processes',
British Steel Corporation, ECSC Sponsored Research Project
6254.07/8/254.

6.

Page, R.A., 'Remote Monitoring of the Properties of the Waste


Gases from Steelmaking Processes', British Steel Corporation,
ECSC Sponsored Research Project 7257.03/351/08.

7.

Isenberg O'Laughling, J., EF Update '82 'Bearing Down on


Melting Costs', Metal Producing, November 1982, pp 45-56.

8.

Schermer, K., 'Reduction of Power and Consumption in Arc


Furnace Melting by Utilising the Exhaust Gas to Preheat Scrap',
Elektrowrme International, 'June 1981 (3), pp B138-B-142.

9.

Forestier, G. and Vervacke, J., 'NKK Process for Preheating


Scrap in the Arc Furnace', Revue de Metallurgie CIT, April 1983,
80 (4), pp 293-301.

10.

Watanabe, H. et al, 'Scrap Preheating for Electric Arc Furnace'


Iron and Steel Engineer, April 1983, 60, (4), pp 45-50.

11.

Prach, R.H., Leu, H.W. and Neumann, F., 'The BBC/Brusa Process
A Contribution to Economical Production of Arc Furnace Steel',
Brown-Boveri, Rev. 1/2 - 75.

12.

Fedele Dell' Oste, E., Galluzzo, S. and Garzitto, V.,


'Heat Recovery from an Electric Arc Furnace for Scrap
Preheating', 1st European Electric Steel Congress,
12-14 September, 1984, Aachen.

13.

Dening, W., Klein, K.H., Paul, G. and Schindler, J.,


'Scrap Preheating at Badische Stahlwerke', ibid.

14.

Hill, B. and Marshall, P., 'The Application of Scrap


Preheating to Electric Arc Furnace Practice', ibid.

15.

Ameling, D., Strunck, F.J. and Wolf, J., 'Energieruckgewinnung


bei Lichtbogenofen mit Hilfe eines kombinierten Heikuhlsystems',
ibid.

16.

Bramfoot, S., Dixon, J., Martin, J.R. and Page, P.A., 'The
Feasibility of Using Waste Heat Boiler to Recover Energy from
the Exhaust Gases of Electric Arc Furnaces', Energy
Conservation in Industry Conference, Dusseldorf, 1984.

9.

ACKNOWLEDGEMENTS

The authors thank staff of BSC Special Steels, Senior Green Ltd. and NEI-APE
Ltd. for assistance and advice given during this project.

AP/BL

10

TABLE 1

APPROXIMATE CONCENTRATIONS OF THE


MAIN CONSTITUENTS OF ELECTRIC
ARC FURNACE FUME
(PARTICLE SIZE 0.03-1 inn)
Concentration, %

TABLE 2

Sample 3

Sample 1

Sample 2

Fe 2 0 3

37

46

Fe 3 0 4

10

A1 2 0 3

CaO

16

17

MgO

MnO

ZnO

14

PbO

50

STEAM DEMAND FOR ELECTRIC ARC WORKS


Works
A

Base load, t/h

15

32

2.7

37

Maximum load, t/h

38

55

45

Pressure, bar

11

10-12

Temperature, C
Existing capacity, t/h

205

210

48

110.7

11

16

7-14.5

205

165-200

14

53.5

TABLE 3

WASTE GAS TEMPERATURE AND FLOW FOR A TYPICAL CAST


Gas Temperature
OC

Time into Cast


min

Mass Gas Flow


kg/h

0-20

111 130

33.6

525

20-25

30.78
32.0

725

25-30

93 890
92 250

30-35

73 930

26.2

1050
1250

Gas Molecular Weight

750

35-40

69 400

27.5

40-45

84 820

31.77

900

45-50

102 060

30.4

500

50-55

Scrap charging period.


Gas temperature too low for heat recovery
129 275
375
38.5

55-60
60-65
65-90

115 670

35.26

500

85 275

28.66

725

90-140

127 000

32.65

325

TABLE 4

PERFORMANCE OF BOILER - BASE LOAD CASE

Time into Cast


min

Gas Flow
kg/h

Average Steam
Production
kg/h

Gas Inlet
Temperature

0-20

111 130

3 825

525

20-25
25-30

93 890
92 250

5 910

725
750

30-35
35-40

73 930
69 400

11 755

40-45

84 820

7 865

45-50

102 060

3 230

50-55
55-60

129 275

0
1 850

375

60-65

115 670

3 550

500

85 275

5 485

725

127 000

1 040

325

65-90
90-140

6 145
9 120

1050
1250
900
500
200*

Boiler on By-pass
TABLE 5

COST BALANCE

BASE LOAD
k

Costs
Supply and installation
of boiler

150

Modifications to
melting shop

334

Savings
Value of steam
Running Costs
Reduced efficiency of
main boilers
Maintenance and fixed
costs

484

k/annum
187

-3
-15
169

Simple payback period


= 2.86 years
Rate of return on investment = 32.9%
12

PERFORMANCE OF BOILER INTERMEDIATE CASE

TABLE 6

Time into Cast


min
020
2025
2530
3035
3540
4045
4550
5055
5560
6065
6590
90140

Average Steam
Production
kg/h

Gas Flow
kg/h
111
93
92
73
69
84
102

130
890
250
930
400
820
060

10
15
15
21
28
16
7

129
115
85
127

275
670
275
000

5
9
12
4

Gas Inlet
Temperature
C

000
000
455
364
077
591
955
0
455
545
273
545

525
725
750
1050
1250
900
500
200*
375
500
725
325

* Boiler on Bypass

TABLE 7

COST BALANCE
Costs

INTERMEDIATE CASE
Savings

Supply and installation


of boiler

300

Modifications to
melting shop

433

Value of steam
Running Costs
Reduced efficiency of
main boilers
Maintenance and fixed
costs

733

Ek/annum
418

7
15
396

Simple payback period


1.85 years
Rate of return on investment = 53.3%

13

TABLE 8

PERFORMANCE OF BOILER - MAXIMUM DEMAND

Time into Cast


min
0-20
20-25
25-30
30-35
35-40
40-45
45-50
50-55
55-60
60-65
65-90
90-140

Average Steam
Production
kg/h

Gas Flow
kg/h
111
93
92
73
69
84
102

130
890
250
930
400
820
060

23
28
29
37
43
30
17

129
115
85
127

275
670
275
000

16
22
24
14

Gas Inlet
Temperature
OC

636
636
091
273
182
682
727
0
364
273
091
545

525
725
750
1050
1250
900
500
200*
375
500
725
325

Boiler on By-pass

TABLE 9

COST BALANCE

MAXIMUM DEMAND SATISFIED


Savings

Costs
Supply and installation
of boiler

550

Modifications to
melting shop

516

k/annum

Value of steam

653

Running Costs
Reduced efficie ncy of
main boilers
Maintenance and fixed
costs

-17

1066

-15
621

Simple payback period


= 1.72 year!
Rate of return on investment = 57.6%

14

TABLE 10

STEAM TURBINE PERFORMANCE - LARGE BOILER PRODUCING FOP ELECTRICAL GENERATION ONLY

Time into Cast


min
0-20
20-25
25-30
30-35
35-40
40-45
45-50
50-55
55-60
60-65
65-90
90-140
TABLE 11

0-20
20-25
25-30
30-35
35-40
40-45
45-50
50-55
55-60
60-65
65-90
90-140

0-20
20-25
25-30
30-35
35-40
40-45
45-50
50-55
55-60
60-65
65-90
90-140

130
890
250
930
400
820
060

23
28
29
37
43
30
17

636
636
091
273
182
682
727

129
115
85
127

275
670
275
000

16
22
24
14

364
273
091
545

94
140
767
783

Gas Flow
kg/h

Average
Steam
Production
kg/h

Surplus
Available for
Generation
kg/h

111
93
92
73
69
84
102

130
890
250
930
400
820
060

23
28
29
37
43
30
17

636
636
091
273
182
682
727

14
19
19
27
33
21
8

129
115
85
127

275
670
275
000

16
22
24
14

364
273
091
545

6
12
14
5

at Turbine
kN/m2

140
1480
140
2000
590
2060
800
2920
700
3560
182
2200
300
860
Boiler on By-pass
864
720
770
1340
590
1530
050
520

Rate of
Electrical
Power
Production
kW
880
1380
1440
2180
2780
1560
330

Total
Electrical
Power
Production
kW h
293
115
120
182
232
130
27.5

220
730
930
100

18.3
60.8
388
83

Gas Flow
kg/h

Average Steam
Production
kg/h

111
93
92
73
69
84
102

130
890
250
930
400
820
060

7
10
11
15
20
13
6

170
735
120
910
175
955
100

129
115
85
127

275
670
275
000

3
6
9
2

790
695
870
405

Rate of
Electrical Power
Produced
kW
1500
380
2245
720
2330
750
3320
1160
4200
1540
2920
1000
1280
300
Boiler on By -pass
800
120
1400
350
2060
640
520
40

Total
Electrical Power
Produced
kW h

Steam Pressure
at Turbine
kN/m2

127
60
62
97
128
83
25
10
30
266
33

STEAM TURBINE PERFORMANCE - SMALL BOILER SATISFYING BASE LOAD,


TURBINE USING SURPLUS STEAM

Time into Cast


min
0-20
20-25
25-30
30-35
35-40
40-45
45-50
50-55
55-60
60-65
65-90
90-140

111
93
92
73
69
84
102

Total
Electrical Power
Produced
kw h
1500
190
192
258
267
205
105

Rate of
Electrical Power
Produced
kW
2480
1800
3000
2280
3040
2300
3910
3100
4100
3200
3210
2460
1860
1260
Boiler on By -pass
1730
1130
2340
1680
2520
1840
1540
940

Steam Pressure
at Turbine
kN/m2

STEAM TURBINE PERFORMANCE - SMALL BOILER PRODUCING FOR ELECTRICAL GENERATION ONLY

Time into Cast


min

TABLE 13

Average Steam
Production
kg/h

STEAM TURBINE PERFORMANCE - LARGE BOILER SATISFYING BASE LOAD,


TURBINE USING SURPLUS STEAM

Time into Cast


min

TABLE 12

Gas Flow
kg/h

Gas Flow
kg/h

Average
Steam
Production
kg/h

111
93
92
73
69
84
102

130
890
250
930
400
820
060

7
10
11
15
20
13
6

170
735
120
910
175
955
100

129
115
85
127

275
670
275
000

3
6
9
2

790
695
870
405

Surplus
Available for
Generation
kg/h

1
1
6
10
4

235
620
410
675
455

Steam Pressure
at Turbine
kN/m2

280
360
1360
2240
940

Boiler on By-pass

370

15

_
-

Rate of
Electrical
Power
Production
kW

Total
Electrical
Power
Production
kW h

0
20
340
720
180

0
1.7
28.3
60
15

_
_
_
-

_
_
-

TABLE 14

COST BALANCE

LARGE BOILER PRODUCING FOR ELECTRICAL GENFRATION ONLY

Costs

Boiler
Supply and installation
of boiler

550

Savings

ek

Value of steam
Maintenance and
fixed costs

Modifications to
melting shop

k/annum

Ek/annum

0
15

516
1066

Turbo Alternator
Supply and installation
of turbine

15

1066

235

Provision of ancillaries,
pumps, building,
electrical connection,
etc.

Value of
electricity

183.4

Maintenance and
fixed costs

15

15

117.5
352.5

352.5

168.4

1418.5

168.4
153.4

Simple payback period


9.25 years
Rate of return on investment = 1.4%

TABLE 15

COST BALANCE LARGE BOILER SATISFYING BASE LOAD, SURPLUS GENERATING


Costs

Boiler
Supply and installation
of boiler

Savings

k/annum

Value of steam

492.5

Reduced efficiency
of main boilers

17

Maintenance and
fixed costs

15

Ek/annum

550

Modifications to
melting shop

516

1066
Turbo Alternator
Supply and installation
of turbine

460.5

1066
Value of
electricity

235

Provision of ancillaries,
pumps, building,
electrical connection,
etc.

Maintenance and
fixed costs

460.5

84
15

117.5
352.5

352.5

69

69
529.5

1418.5
Overall simple payback period
Overall rate of return on investment
Marginal payback on generation
Rate of return of investment on generation

16

2.68 years
35.5%
5.11 years
14.5%

TABLE 16

COST BALANCE - SMALL BOILER PRODUCING FOR ELECTRICAL GENERATION ONLY


Costs

Savings

Boiler
Supply and installation
of boiler

250

Modifications to
melting shop

350

Value of steam
Maintenance and
fixed costs
600

Turbo Alternator
Supply and installation
of turbine

Value of
electricity
Maintenance and
fixed costs

Ek/nnu

0
-15
-15

600

102

Provision of ancillaries,
pumps, building,
electrical connection,
etc.

Ek/annum

-15

46.9
-10

71.5
173.5

36.9

173.5

36.9
21.9

773.5
Simple payback period 3 5.3 years
Rate of return on investment negligible

TABLE 17

COST BALANCE - SMALL BOILER SATISFYING BASE LOAD, SURPLUS GENERATING


Costs

Boiler
Supply and installation
of boiler

250

Modifications to
melting shop

Savings
Value of steam
Reduced efficiency
of main boilers

350

600
Turbo Alternator
Supply and installation
of turbine

Maintenance and
fixed costs

Value of
electricity
Maintenance and
fixed costs

Ek/annum

315.5
-6
-15
294.5

600

102

Provision of ancillaries,
pumps, building,
electrical connection,
etc.

Ek/annum

294.5

5.5
-10

71.5
173.5

173.5

-4.5

773.5

-4.5
290

Overall simple payback period


2.67 years
Overall rate of return on investment = 35.7%
No marginal payback or return on investment for generation

17

CO concentration
% /

100
80
60
40
20
0

% v/v

40 \

r50

Elbow, CO,
Elbow, CO

. 40
r 30

concentration

% v/v

20

<MX^

10
0

Elbow O 2

30
20
10

Flow, m 3 / s
stp dry

CO,

40 \
30

f\

\-

Roof duct
After combustion

XX

>

20
10 J
0
Temperature,
C

1000 .
750 .

Tap No.

40
20

250 1

HO

400

% V/V

30

500 -i
0
Temperature,
C

50 H 2 0 concentration

, roof duct
Temp, after combustion

Heat flow roof duct


Temp, roof duct

40 Heat flow, MW

300

30

200

20

100
0

10
Oxygen lancing r a t e ^

o x y g e n lancing
rate, m3/s
l
1.2

0.8

8 -I

2
0 L.
0

20

40

60
80
Time from power o n , min

100

WASTE GAS CONDITIONS 180 t FURNACE

li n

0.4

120

FIG. 1

lp
140

Sample

ir.

\[

Melt

I Tapi

Refine

Melt

--oLC

Oxygen lance r a t e , m 3 / s
40
Waste gas
heat, MW

0.94

0.16

j.

40

60

Mean 14.5 MW

Two basket charge

20

Variable

80
100
120
Furnace time, min

140

160

FIG. 2
(R1/6232)

TYPICAL WASTE HEAT REJECTION CYCLE 180 t FURNACE


O

Sample
J [_

Melt

CL

Refine

| T a p JFettle

| Delays 3.2 min

03

Oxygen lance r a t e , m 3 / s
Waste gas
heat, MW

0.47

40 r

Variable

0.97

Mean 15.5 MW

One basket charge + continuous feed

30

^-V^__

20

f*-""""

^ ^

~*-^^

10
0
0

20

40

60

80
100
120
Furnace time, min

140

180 t FURNACE
TYPICAL WASTE HEAT REJECTION CYCLE
WITH CONTINUOUS FEEDING

160

FIG. 3
(R1/6233)

To fume
cleaning
fume
Roof
extraction
hood
Spray
conditioning <
tower
Slice or air
infiltration
gaf
Fume elbow

Combustion
|chamber

\_.

Arc
'furnace

Possible
boiler sites

GENERAL LAYOUT OF ELECTRIC ARC FURNACE


AND ASSOCIATED WASTE GAS DUCTING
POSSIBLE BOILER SITES

21

FIG. A
(R2/873)

Combusted gas
temperature, C
1000

Combusted gas temperature


Heat flow

Heat flow, MW
,-50

500 -

-2 5

Normalised combusted
gas flow, m-'/s stp
100 -,

50 -

Elbow flow, m-Vs stp


20

10

Carbon removal
rate, kg/s
r-2

Elbow flow
Carbon removal rate

^ V W\r- . . - t y M / l
"
20

40

60

80
Time,

100
min

120

140

160

WASTE GAS CONDITIONS FOR 180 t FURNACE WITH MODIFIED EXTRACTION SYSTEM

180

FIG. 5
(R2/873B)
Continued.

Transformer
Tap No.
10 -

Elbow CO
concentration
% v/v
1- 20

Elbow CO2
concentration
% v/v
40

20-

- 10

Elbow O2
concentration
% v/v
40

80
100
Time, min

180

FIG. 5
(R2/873B)

-< Copper - copper-nickel


thermocouple

Platinum - 13% rhodium/platinum


Thermocouple

SECTION THROUGH THE PROBE

FIG. 6
(R1/7609)

tf&&$? f*?.- *.

~:^x---^W^^m^^'^

Upstream

(a)

Top

(b)

(c)

Downstream

DEPOSIT ON TEST PROBE

25

FIG. 7

Heat flux, kW/m2


180

16

o
Symbols refer

to different
measurement periods

140

120

100

A
9

80
A
*

60

"od*

%
40
*

<*kT
20

200

400
600
800
Gas temperature, "C

1000

HEAT TRANSFER COEFFICIENTS

26

12*

FIG. 8
(R1/9708)

Precipitator
efficiency, %

100

99.5

99

98.5

98

97.5

97
4

12

16

20

24

I
28

Water vapour concentration, %


EFFECT OF WATER VAPOUR ON
PRECIPITATOR EFFICIENCY

27

FIG. 9
(R1/7608)

.Mid-week
Process steam demand, kg/h
25 OOOr

Weekend

20 000-

15 000-

N)
00

10 000-

5 000One boiler - minimum fire

Jan

Feb

Mar

Apr

May

JL
June

_L
July

Aug

Sept

Oct

DIAGRAM SHOWING THE MONTHLY VARIATION IN STEAM DEMAND FOR WORKS A

Nov

Dec
FIG. 10
(R2/873A)

All dimensions in mm

3800
Water/steam
riser tubes
Steam
drum

6700

Membraned
wall tube
enclosure

o oo

2000

Dust
removal
hoppers

Tube nest comprises


50.8 mm OD plain tubes
at 100 mm by 100 mm
line centres

-o-o-o

Membraned division
wall to form two
gas passes
Tube bank

GENERAL ARRANGEMENT OF BOILER

20

FIG. 11
(R1/8615)

APPENDIX 1
Al.l

WASTE GAS MEASUREMENTS

MEASUREMENTS MADE

In order to assess fully the conditions in the waste gas extraction system of
an electric arc furnace the following measurements were required.
1.

Furnace Offtake

(a)

Oxygen, carbon dioxide and carbon monoxide concentrations.

(b)

Methane and hydrogen concentrations.

2.

After Combustion

(a)

Gas velocity and volume flow rate.

(b)

Gas temperature.

(c)

Carbon monoxide and carbon dioxide concentrations.

From the measured data the following waste gas parameters were calculated:(a)

Carbon removal rate from the furnace.

(b)

Waste gas flow and temperature in the furnace elbow.

(c)

The waste gas heat flows after combustion.

Figure Al.l is a schematic diagram showing the positions where measurements


were made.
Al.2

TECHNIQUES

Al.2.1

Gas Analysis

A gas sample was extracted by a peristaltic pump through a water cooled sample
probe inserted into the waste gas stream. The sample was cleaned and dried,
and analysed for carbon dioxide and carbon monoxide using LIRA 303 infra-red
analysers. A Taylor Servomex paramagnetic analyser was employed for the oxygen
analysis of the furnace offtake gas sample.
The water vapour concentration was measured with an on-line infra-red analyser
which obtains the analysis without sampling the waste gas. A narrow spectral
band of radiation, corresponding to a water vapour absorption band, is
transmitted across the ducting. The attenuation of the transmitted signal
resulting from the presence of water vapour is established, and then from a
knowledge of the waste gas temperature and the measurement path length
employed, the water vapour concentrations can be computed.
Al.2.2

Temperature

Waste gas temperatures were monitored using a 3 mm diameter chromel alumel


mineral insulated thermocouple supported by either the associated gas sampling
probe or a length of metal tubing.
Al.2.3

Flow

The technique employed to measure flow was infra-red cross correlation flow
analysis. The method resembles flow measurement with chemical, dye or
radioactive tracers between two measuring points a known distance apart.
However, instead of an artificial tracer being added the naturally occurring
fluctuations of the physical parameters of the gas stream are used as the
tracer. Hence, the basis of the technique is simple, consisting of measuring
the time taken for a characterisitic disturbance within a flow stream to travel
between two points of observation of known spacing. With a knowledge of this
transit time it is a simple calculation to determine the waste gas velocity and
hence flow.

30

APPENDIX 2

NEW OFFTAKE ELBOW

A2.1

DESIGN CONSIDERATIONS

A2.1.1

General

The redesign of the elbow had the following aims:(a)

Improved combustion within the furnace by more precise


control of furnace pressure.

(b)

The maximum rate of extraction must allow the capture of all


of the gases evolved during steelmaking.

(c)

Control of the extraction rate to avoid the inspiration of


excessive amounts of air, and hence reduction in waste gas
temperature, during periods of low emission.

A2.1.2

Fume Offtake Elbow and Slice Gap Geometry

The extraction systems discussed in the feasibility study have a common feature
in the fume offtake elbow and associated slice gap and combustion chamber entry
port. The entry port is a large oval orifice which is necessary to allow fume
capture from the elbow during periods when the furnace is tilted for slagging
whilst oxygen lancing is still in progress.
On several furnaces a large water cooled oval flange is fitted to the slice gap
end of the fume offtake elbow. The purpose of this oval flange is to limit the
amount of air infiltrated at the slice gap in order to allow adequate
draughting from within the furnace. The layout of a typical arc furnace
extraction system is shown in Fig. A2.1.
A2.1.3

Design Parameters of the Existing System

The design was intended to cope with maximum oxygen lancing rates of 1.1 m 3 /s
and the tilting of the furnace 5 either side of its normal position during
oxygen lancing. The slice gap geometry between offtake elbow and combustion
chamber was designed in conjunction with the total extraction volume to provide
adequate furnace pressure control and capture of fume from within the furnace.
The design was also arranged to infiltrate adequate air into the combustion
chamber via the slice gap to combust fully with sufficient excess to reduce the
gas temperature to an acceptable level after mixing.
Air is forced into the combustion chamber to ensure all furnace gas is burned
at peak oxygen lancing rates and so eliminates any danger of explosive mixtures
being formed in the event of an extraction failure.
In addition to the oxygen added to the furnace via the lance, air is
infiltrated via doors and other apertures because of the suction applied to the
furnace. At a lance rate of 1.1 m 3 /s elbow gas compositions of 65% carbon
monoxide and 35% nitrogen are found with elbow gas flows of 4.75 m 3 /s stp. At
this flow and composition the heat contained in the gases is 40 MW of which the
sensible heat is 10 MW when the gas temperature is 1500C.
The temperature of the gases leaving the combustion chamber must be restricted
to 1250C by the use of excess air. Consequently, the flow rate at the exit of
the chamber is 24 m 3 /s stp. The combustion air from the forced draught fan is
7.3 m 3 /s stp, which is the stoichiometric air requirement. The elbow flow is
4.75 m 3 /s stp giving a flow of 13.5 m 3 /s stp through the slice gap.
The fume offtake elbow was 1.0 m inside diameter at the roof end expanding to
1.4 m inside diameter at the flanged end. Previous work has shown that the
slice gap must be no smaller than 130 mm, to enable the roof to swing away from
the combustion chamber during scrap charging, without fouling. However even at
this distance the oval flange must be shaped to ensure the passage is a clear
one. The entry port in the combustion chamber was 1.4 m high by 2.8 m wide,
allowing fume capture during 'tilt and blow periods'. Recently elbows having a
consistent diameter of 1.0 m throughout their length have been fitted to
several furnaces. This has required the reduction of entry port size to

31

maintain furnace extraction.


Fig. A2.2.

The elbow diameters and entry ports are shown in

A2.2

NEW FUME OFFTAKE ELBOW

A2.2.1

General

To provide higher and more stable temperatures in the fully combusted waste gas
presented to a waste heat boiler, it would be advantageous to use an offtake
elbow of greater diameter. There would also be consequent changes to certain
other components of the extraction system. It is also necessary to devise a
means of control of the extraction rate to optimise the temperature of the
gases entering the boiler. The design, construction and testing of a modified
extraction system were undertaken and the following actions carried out:(a)

The elbow was designed within the restrictions placed by


physical features such as the construction of the water cooled
roof of the furnace and the general layout of the furnace
superstructure.

(b)

Isothermal model tests were required to establish the geometry


of the slice gap and entry port and to determine the potential
extraction rate.

(c)

The construction and installation of the modified elbow and


associated roof panel.

(d)

Monitoring of the waste gas temperatures and flow rates and


consideration of a suitable control parameter for the
extraction rate.

(e)

The effects on temperature and flow rate and cycling of


temperature were monitored in detail to demonstrate the
benefits of the changed extraction system to a waste heat
recovery medium.

A2.2.2

Initial Design

In the early stages of the redesign it was considered that a maximum elbow
diameter of 1.4 m would be possible on the furnace. This dimension was largely
governed by the positioning and type of the water cooled roof which was fitted
to the furnace. The roof which exists is of the replaceable panel type and the
existing offtake elbow is fitted to an individual panel which imposes rigid
limits on its size.
It was not considered that a larger elbow could be fitted because a major
redesign of the water cooled roof system would have been necessary, involving a
considerable time delay and excessive cost. It was therefore decided that
modification of the individual panel only was desirable and early indications
suggested that a 1.4 m diameter elbow was indeed possible.
The model tests were carried out on the basis that a 1.4 m elbow could be used;
however at a later stage, after model tests were completed, it became apparent
that a maximum diameter of only 1.3 m could be accommodated within the
structure of the existing roof.
Calculations indicated that this slightly smaller elbow would also give
satisfactory results and it was considered unnecessary to repeat the model
wor k.
A2.3

MODEL STUDIES

A2.3.1

Procedure

Scale models of the elbows and flanges were fabricated in perspex. A


photograph of the model is shown as Fig. A2.3. A combustion chamber size of
3.65 m was modelled with a geometrically scaled oval entry hole. The chamber
was made several times longer than on plant, and with no combustion air ports
or right angled offtake.

32

This approach was adopted in order to simplify the construction of the models
and in no way affects the results obtained, because the combustion chamber
length and combustion air ports have no effect on the slice gap geometry as
they are well downstream.
The offtake elbow was attached to a chamber representing the furnace and the
slice gap was set to 130 mm, the minimum distance allowable for operational
reasons.
The pressure-flow characteristic across the elbow was determined before the
furnace elbow was installed on the overall model. With the elbow flow and
slice gap held constant at 130 mm, the extraction volume required to reduce
furnace pressure to zero was measured. This was carried out for a range of
elbow and entry port combinations.
A2.3.2

Tests

The offtake elbows and entry port combinations are listed below, entry port
geometries are detailed on Fig. 2.2.
Test 1

Original entry port (Fig. A2.2(a)), original cranked elbow.

Test 2

Original entry port (Fig. A2.2(a)), existing 1.0 m elbow.

Test 3

Reduced size of entry port (Fig. A2.2(b)), existing 1.0 m elbow.

Test 4

Original entry port (Fig. A2.2(b)), 1.4 m elbow.

Test 5

Reduced size of entry port (Fig. A2.2(c)), 1.4 m elbow.

Test 6

Existing entry port (Fig. A2.2(d)), existing 1.0 m elbow.

Test 7

Original entry port (Fig. A2.2(a)), 1.3 m elbow.

A2.3.3

Results

Using the similarity theory shown in Appendix 3 the relationships between elbow
gas temperature and the ratio of slice gap air flow to total entry port flow
are plotted on Fig. A2.4. The relationships between slice gap air flow and
combustion chamber suction are shown in Fig. A2.5.
The results of the model tests were then used to forecast the conditions which
will exist with a 1.3 m elbow using the original entry port design, i.e. one
diameter high by 2 diameters wide.
For any specific geometry the elbow gas flow is dependent on the elbow gas
temperature and the slice air flow. For convenience the suction level in the
combustion chamber can also be related to the slice air flow. The predictions
contained in Table A2.1 for Tests 1 to 6 are based on model tests and the
predictions for Test 7 are based on interpolation of the results.
The nomenclature and assumptions used in the similarity theory and for the
calculations are included along with the similarity theory in Appendix 3.
A2.3.4

Implications

The predicted performance of the various geometries is shown graphically in


Figs. A2.4 and A2.5. The elbow flow is a minimum at maximum temperature and a
value of 1800C can be used for comparison purposes.
The original design achieved a total3 extraction flow of 24-m3/s stp with a
forced combustion
air flow of 7.5 m /s stp giving an available flow through the
slice of 16.5 m3/s stp.
Removal of the forced combustion air could raise the
slice air flow to 24 m3/s stp however.3 It has been suggested that the present
value of total extraction flow is 20 m /s stp giving slice air flows of 12.5
and 20 m3/s stp. The predictions for the above conditions, for elbow gas flows
and chamber suction levels are shown in Table A2.2.

33

RELATIONSHIPS BETWEEN
ELBOW GAS FLOW (Q ) ,
SLICE AIR FLOW (Qf),
TEMPERATURE (T)
AND CHAMBER SUCTION
LEVEL (S)

TABLE A2.1

s,

a's t p

Test

m3/s

N/ro2
1.00

Qa2

0 . 1 0 7 / T g Qg

0.84

Qa2

0.091 /T

1.35

Qa2

0.0509 / T

1.02

Qa2

Q
g g
0.0447 /T Q

1.47

Qa2

0.0784 /T

2.29

Q2

0.97

O2

0.083 /T

Q
g g
0.059 /T Q

TABLE A2.2

PREDICTED ELBOW GAS FLOWS (Q ) AND CHAMBER SUCTION


9
LEVELS (ST
T o t a l Flow E n t e r i n g Combustion Chamber
m3/s stp

Test

12.5

3/V
nr/s^stp
1
2
3
4
5
6
7

2.65
2.15
2.4
3.75
4.15
2.75
3.4

S,
N/m 2
100
90
140
80
100
220
80

16.5

3 '
nr/s^stp
3.45
2.8
3.2
5.0
5.45
3.6
4.45

S,
N/m 2
170
160
240
140
180
380
140

34

20
Q

g'
nr/s^stp
3/

4.2
3.4
3.85
6.0
6.6
4.4
5.4

S
',
N/m 2

250
230
350
200
260
560
210

24
m3/systp

N/m 2

5.05
4.1
4.65
7.2
7.9
5.25
6.5

360
330
510
290
380
800
300

Electric arc furnace

.Fume offtake elbow


Large oval flange
Large oval entry port

Position

Conditioning
tower

Ti

Gas analysis (CO,


C0 2 , 02)

Position T,
Gas analysis (CO, CO,, 0,)
Temperature

MEASUREMENT POSITIONS

35

FIG. A2.1
(R1/9709)

Scale 2.0 m

(a)

Original entry port for cranked elbow

(b)

Reduced entry port for 1.0 m ID elbow

'

1
I

-'*(c)

Reduced entry port for 1.4 m ID elbow

(d)

ENTRY PORT AND ELBOW DIAMETER COMBINATIONS

- - '

Entry port now in use

FIG. A2.2
(R1/8613)

CENERAI. VIEW OF TUK MODEL

FIG. A2.3

, c

GRAPH OF RELATIONSHIP BETWEEN Q g : Q P AND ELBOW GAS TEMPERATURE,

Q a , m 3 /s stp

22

FIG. A2.4

14

20
18
16
14
12
10
8
6
4
2
0

100

200

300
S, N/m 2

400

500

600

GRAPH SHOWING RELATIONSHIP BETWEEN CHAMBER SUCTION LEVEL, S


AND SLICE AIR FLOW, Q-,

38

FIG. A2.5
(R1/8614)

APPENDIX 3

M ODEL SIM ILARITY THEORY

Geometrie models of the elbow and combustion chamber were fabricated in perspex
and operated isothermally. In using isothermal modelling to study a
non-isothermal system certain similarity criteria must be satisfied. The
geometric similarity is satisfied and the ratio of flow through the elbow to
that passing into the slice gap is distorted to provide a momentum flux ratio
in the model similar to that in the plant. In satifying the geometric and
momentum flux similarity the pressure drop across any part of the plant is
satisfied automatically in terms of velocity heads.

MOMENTUM FLUX SIM ILARITY


Let

subscripts

V
Q
A
T

h
k

=
=
=
=
=
=
=
=
=
=

momentum flux, N
actual velocity, m/s
flow rate, m 3 /s stp
cross sectional area, m2
absolute temperature, K
pressure drop, N/m 2
gas density, kg/m3 stp
theoretical mean velocity head, N/m 2
pressure drop coefficient (equal on model and plant)
scale factor, model:plant

g
a
e
c
t
o
m

=
=
=
=
=
=

elbow gas
slice air
total flow at entry port
forced combustion air
extraction flow leaving chamber
stp condition
model
plant

US = ^2E
M

am

(1)

ap

M = ^O AV2
T

->? h
substituting
p

(2) into (1) gives


T

A T

gm gm
gm
am o
A T
P Q 2 T
K
gm o
am v am
am
assuming that p__ = __
gp
ap
2

ap
Q 2
v
gp

(2)

gp

gp
gp
A T
gp o

A T

ap o
p Q z T
H
ap w a p
ap

am
Q
w
gm

(3)

gp
T
ap

ELBOW PRESSURE DROP


The pressure drop across the elbow in the model is related to that in the plant
through the equations
h = 0.5 pV 2

... (4)

39

assuming the elbow gas density (stp) in the plant to be similar to air
h = 0.5 1.29 ^ S _
T
o A g2

... (5)

with geometric similarity


p

gp=pgm

<6>

aR
gm

S u b s t i t u t i n g (5) i n t o (6) , w i t h an elbow gas t e m p e r a t u r e on p l a n t and a


gp'
model a i r t e m p e r a t u r e of 15C g i v e s :

23L.
2

P g p = PgmZE
288

**

...

(7)

CHAMBER SUCTION
Assume uniform velocity head at the entry port, no gas mixing and let the area
of the entry port occupied by the infiltration air be A .
h

ep

' 5 p gp ^2
T

from (8)

(9)

^gp

ap

from

fA
m

' o

... (8)

= 5 e a m I S H
T
o A xm

<9>

xp'

xp
l

ft

' em

xm'

am

- A l

* ep

fl

gm

A
m

?S
em ~ Axm>

(A

ap

gp

< ep xp'

em = 5 p gm ^ 2 "
T
o

.5 p a p ^a ^a_

?2P
A

xm

from equation (3)


A

fl

xp
<Aep A xp> 2
A 2
_xm_2
A xp

A 2
xm
<Aem " A xm ) 2
fl

m ^

(10)

and geometrie similarity is retained at the entry port.

h
Q 2

_iU2 = _*E , ap_


_ap
am
ham vQam2
Tam
_

40

(11)

but , the pressure drop for the slice air, is relative to an ambient pressure
of zero and is therefore equivalent to the chamber suction level, S.
Since T__
ap = am :Q

K = S m -S... (12)

m
2
v
am
The similarity theory and equations derived in this Appendix use the following
assumptions:1.

Elbow gas density is similar to that of air.

2.

Ambient air temperature is 15C.

3.

Volumetric change (stp) due to loss of oxygen during combustion is


insignificant,
hence Q g + Qfl = Q e and Q e + Q c Qfc.

4.

The only source of air ingress into the chamber is the entry port and
forced air ports where relevant.

5.

Furnace pressure at roof level is zero.

6.

Compared with elbow pressure drop, buoyancy due to elbow height is


negligible.

41

APPENDIX 4
A4.1

PERFORMANCE OF THE EXTRACTION SYSTEM WITH ENLARGED ELBOW

ADVANTAGES OF IMPROVED FURNACE EXTRACTION

The original operation of the electric arc furnace extraction system under
trial with its smaller 1.0 m offtake elbow used a series of selected extraction
rates chosen by the furnace operative for any given stage of the cast. These
pre-set extraction rates have been chosen as a result of considerable
experience of the process and the existing limitations of the extraction
system, and are the optimum settings under these circumstances. It must be
remembered, however, that the arc furnace process is extremely variable and
generates gases and fume at widely different rates. Any attempt to guarantee
the capture of all this fume and gases at a particular stage in the cast, using
preset extraction rates, will tend to lead to over-extraction at periods of low
emission. Consequently, larger quantities of sensible heat are removed from
the furnace than is absolutely necessary.
During the oxygen lancing period, large quantities of carbon monoxide are
removed from the furnace and burnt in the combustion chamber. It has been
shown that if greater extraction rates could be achieved through the elbow
during the lancing period, air indrawn into the furnace at the greater rates
would burn the combustibles more completely thus reducing heat flow in the
waste gases. Previous work demonstrated that as elbow flows are increased the
temperature and consequently heat flow of the waste gases leaving the furnace
are reduced, Fig. A4.1. This graph is a family of curves relating the rate of
waste gas flow through the extraction elbow to heat content for a series of
rates of carbon removal from the bath.
It can be seen that the heat flux passes through a minimum value as the elbow
flow increases. This condition occurs when the combustion in the furnace is at
its most efficient. By enlarging the offtake elbow several benefits are
gained. These include better control of the extraction system to ensure total
fume capture and improved furnace efficiency by allowing greater volumes of
oxygen to be indrawn. This allows the release of more potential heat into the
furnace charge by burning the carbon monoxide and other combustibles present.
The resultant waste gas condition profiles should be more suitable for waste
heat recovery in that temperatures in the non-lancing periods are higher than
before as the ratio of elbow gas to slice air is higher. During the lancing
periods better extraction allows the temperature of the gases to be more
constant without the large peaks generated previously by burning high
concentrations of carbon monoxide in the combustion chamber.
It should be possible to optimise the extraction rates by monitoring the
effectiveness of fume capture and waste gas composition, particularly at the
elbow. The extraction rates would be reduced in non-lancing periods to just
contain fume escape. This measure improves elbow gas to slice air ratio even
further and thus elevates temperature levels at the entry to a heat recovery
system. In the lancing periods the concentrations of carbon monoxide and
oxygen levels in the elbow gases can indicate whether the extraction rate is
adequate. When a large sustained concentration of carbon monoxide accompanied
by zero oxygen concentration is present in the elbow gas, the extraction flow
should be increased in an attempt to reduce the carbon monoxide level to zero.
These measures were tried successfully within the limitations of the extraction
system.
A4.2

PLANT TRIAL RESULTS

Plant trials were carried out with the new larger offtake elbow fitted to a
180 t electric arc furnace in order to determine whether the benefits described
in Section 4.1 could be achieved in practice. Waste gas measurements were made
using the techniques described in Appendix 1 with the exception that methane,
hydrogen and water concentrations were not measured in this case. Measurements
were made over casts during which attempts were made to adjust the extraction
rates based on observations of the effectiveness of fume capture and the
composition of the waste gas.
The modified system with larger offtake has indeed produced a greater range of

42

elbow gas flow rates and the elbow flows have increased in line with the
flows predicted by the model tests. A comparison of the elbow flow rates of
the original and new offtake systems are shown in Figs. A4.2 and A4.3.
The increased range of flow rates through the elbow has resulted in more
complete fume capture and consequent capture of waste heat which previously
escaped and a general increase in waste gas temperature levels as predicted.
A direct comparison between old and new system heat flows in the early part of
the cast was not possible as changes in the steelmaking practice implemented
since the original trials have limited the oxygen infiltrated to the furnace.
Lancing is now carried out mainly at high levels and for much shorter periods
than previously. Hence, any comparison must be made in periods when the
current practice is similar to previous furnace operation. It is still
possible however, to conclude that the new offtake has produced a more
acceptable heat flow pattern in this period of the cast.
The levels of heat flow and temperature have been reduced in the lancing period
and more efficient furnace operation has resulted. The heat flow and
temperatures produced are now much smoother than previously as is indicated by
close inspection of Figs. 1 and 5.
The attempts to balance the extraction rate to contain fume capture whilst
burning combustibles as fully as possible during the lancing period were
inconclusive because the periods of carbon monoxide emission were brief and the
relatively small changes in temperature and heat flow are masked by the overall
variation. It was, however, noticed that whenever the extraction flow was
increased during periods of high carbon monoxide levels, a reduction in
concentration occurred indicating that the changes were affecting the
combustion of carbon monoxide in the furnace.
From the results it is possible to speculate that more precise control of the
furnace extraction system could be achieved by using certain of the parameters
for control. By monitoring carbon flow and fume escape via a technique such as
an obscuration meter, automatic control of the extraction system to give the
benefits discussed could be attempted.
The advantages to the waste heat boiler are apparent as maximised temperatures
and smoother heat flows are produced, in addition to which furnace operation is
more efficient. It is possible also that overall extraction rates may be
lowered thus providing a saving in electrical costs in running the fans.

43

Heat flow, MW
32

28 -

24

20

16

.8 kg/s)
(0.7 kg/s)

12

(Carbon flow 0.6 kg/s)


1.0

2.0

3.0
4.0
5.0
6.0
Elbow flow, m 3 /s stp

7.0

GRAPH SHOWING RELATIONSHIP BETWEEN


'ELBOW FLOW AND HEAT FLOW FOR A
SERIES OF CARBON REMOVAL RATES

44

8.0

FIG. A4.1
(R2/873C)

Elbow flow
m3/s stp
1086"
4-

^rl

-/ v-^

2i

lo"
Time, min

80

Too"

GRAPH OF ELBOW FLOW FOR ORIGINAL EXTRACTION SYSTEM

Elbow flow
m3/s stp
10
8-

120

FIG. A4.2

642"

20

r80

1
T
TT

100
60
Time, min
GRAPH OF ELBOW FLOW FOR MODIFIED EXTRACTION SYSTEM
40

To
FIG. A4.3
(R2/873D)

CDNA09850ENC

Potrebbero piacerti anche