Sei sulla pagina 1di 22

SLAB

LENGTH

WIDTH

QUANTITY

GROUND FLOOR
S-1 (ONE-WAY)
S-2 (TWO-WAY)
S-3 (ONE-WAY)

6
3
3

3
3
1.5

16
1
1

2ND FLOOR
S-1 (ONE-WAY)
S-2 (TWO-WAY)
S-3 (ONE-WAY)

6
3
3

3
3
1.5

16
1
1

3RD FLOOR
S-1 (ONE-WAY)
S-2 (TWO-WAY)
S-3 (ONE-WAY)

6
3
3

3
3
1.5

16
1
1

ROOF DECK
S-4

TEMP. STRAIGHT BARS

AREA

REINFORCED STEEL BARS


SPACING
(m)

(Sq.m)

18
9
4.5

FACTOR

DISCONTINUOUS (CUT BARS)


AREA
(Sq.m)

REINFORCED STEEL BARS


SPACING
(m)

FACTOR

SHORT SPAN
MIDSPAN (CUT BARS)
AREA
(Sq.m)

REINFORCED STEEL BARS


SPACING
(m)

FACTOR

SLAB REINFORCEMENT
CONTINUOS (CUT BARS)
AREA
(Sq.m)

FACTOR

ARS)

DISCONTINUOUS (CUT BARS)


REINFORCED STEEL BARS
SPACING
(m)

AREA
(Sq.m)

DISCONTINUOUS (CUT BARS)

FACTOR

REINFORCED STEEL BARS


SPACING
(m)

LONG SPAN
MIDSPAN (CUT BARS)
AREA
(Sq.m)

FACTOR

RS)

CONTINUOS (CUT BARS)


REINFORCED STEEL BARS
SPACING
(m)

AREA
(Sq.m)

CONTINUOS (CUT BARS)

FACTOR

REINFORCED STEEL BARS


SPACING
(m)

Slab Cos

Slab

Length

Width
(m)

Quantity

(m)

Thicknes
(m)

Area
(sq.m)per
slab

GROUND FLOOR
S-1 (ONE-WAY)
S-2 (TWO-WAY)
S-3 (ONE-WAY)

6
3
3

3
3
1.5

16
1
1

0.125
0.125
0.125

18
9
4.5
31.5

2ND FLOOR
S-1 (ONE-WAY)
S-2 (TWO-WAY)
S-3 (ONE-WAY)

6
3
3

3
3
1.5

16
1
1

0.125
0.125
0.125

18
9
4.5

3RD FLOOR
S-1 (ONE-WAY)
S-2 (TWO-WAY)
S-3 (ONE-WAY)

6
3
3

3
3
1.5

16
1
1

0.125
0.125
0.125

18
9
4.5

ROOF DECK
S-1
s-2

6
3

3
3

17
1

0.125
0.125

18
9

Slab Cost Estimate


Volume (cu.m)
with 5%
allowance

37.8
1.18125
0.590625
39.571875

Total Amount
for Concrete
Pouring Using
Ready Mix
(3000psi)

Number of
Total weight in
Reinforced
kilograms
with
Steel Bars
5%
allowances
Required
(12mm x 7.5m)

132,300.00

4,134.38

2,067.19
138,501.56

570.24
17.82
8.91
596.97

37.8 132,300.00
1.18125
4,134.38
0.590625
2,067.19
138,501.56

#16 G.I. Tie


Wire (kg)

570.24
17.82
8.91
596.97

3191.63
99.74
49.87
3341.24
6682.48
3191.63
99.74
49.87
3341.24

44.62
1.39
0.7
46.71
93.42
44.62
1.39
0.7
46.71

37.8 132,300.00
1.18125
4,134.38
0.590625
2,067.19
138,501.56

570.24
17.82
8.91
596.97

3191.63
99.74
49.87
3341.24

44.62
1.39
0.7
46.71

40.1625 140,568.75
1.18125
4,134.38
144,703.13
560,207.81

605.88
17.82
623.7
2414.61

3391.11
99.74
3490.85
13514.57

47.41
1.39
48.8
188.93

Total Amount
for
Reinforcements

Total Cost

155340
4854.24
2427.36
162621.6

287,640.00
8,988.62
4,494.55
301,123.16

155340
4854.24
2427.36
162621.6

287,640.00
8,988.62
4,494.55
301,123.16

155340
4854.24
2427.36
162621.6

287,640.00
8,988.62
4,494.55
301,123.16

165048.96
4854.24
169903.2
657768

305,617.71
8,988.62
314,606.33
1,217,975.81

Cost Estimates

Special Moment Resisting Frame

SLAB
FLOOR
Ground
2nd
3rd
Roofdeck

THICKNESS
t(m)
0.125
0.125
0.125
0.125

Area
m
301.5
301.5
301.5
315
Total =

Total Vol. of Concrete

BEAMS
2nd
3rd
Roofdeck
Total =
COLUMNS
Ground
2nd
3rd
Total =
MASONRY WALLS
Ground - 3rd Floor

w/ 5% allowance (m )
24.306
24.306
24.306
72.918
Total Vol. of Concrete
w/ 5% allowance (m )
13.44
11.76
11.76
36.96
Area
m
1190.4

Total Vol. of Concrete

Total Weight of Ste


w/ 5% allowance (k
6775.9
6776.9
6777.9
6778.9
27109.6

w/ 5% allowance (m )
39.571875
39.571875
39.571875
41.34375
160.059375
Total Weight of Steel
w/ 5% allowance (kg)
2820
2820
2820
8460
Total Weight of Steel
w/ 5% allowance (kg)
7706.72
6743.33
6743.38
21193.43
CHB Pieces (6")

w/ 5% allowance for breakage

1190.4(12.5)

15624

Steel Bar Reinforcement for C =


(3(1190.4))/
596
=
367.456385 kg
Source for factors used: Architectural & Const. Data
By Salvan, George S
Source for Prices used:
www.magkano.com/construction/construct.htm
Year updated:
March, 2014

pcs

TOTAL COST FOR SPECIAL MOMENT RESISTING


TOTAL AMOUNT:
Price (Peso)
Concrete
269.937375
4000
Re-bars
57130.48638
65
CHB(6")
15624
16
Plaster
331
230
Sand
33.1
1500
Total =

FRAME
Cost
1079750
3713482
249984
76130
49650

5,168,995.12

Cost Estimates

Special Moment Resisting Frame

SMRF DURATION IN HOURS:


For Slab, Beams and Columns
Activities
Duration
Formworks
2.9 man-hours/sq.m
installation
Bar Reinforcing

3 man-hours/sq. m

Concrete Pouring
CHB Layering

0.111 hours/sq.m
8 hours/ 100 pcs.

Duration computation in Man-hours =

Total
2601.63
706.283
269.937375
15624
10943.459 Man-hours 52.6128

Cost of SMRF having a drift of 4.05 cm on x-direction and 4.03 cm on y-direction

SMRF

Weight (kN)
13119.96

Volume (m3)
558.3

Price (Peso)
4000

Cost
2,233,200.00

Cost Estimates

Special Moment Resisting Frame

Total Weight of Steel


w/ 5% allowance (kg)
6775.9
6776.9
6777.9
6778.9
27109.6

PLASTER
bags (1:3 m

331
10-mm bar

Pesos

SAND
m
33.1

Cost Estimates

Months

on y-direction

Special Moment Resisting Frame

Cost Estimates

OMRF with Shearwall

SLAB
FLOOR
Ground
2nd
3rd
Roofdeck

THICKNESS
t(m)
0.125
0.125
0.125
0.125

Area
m
301.5
301.5
301.5
315
Total =

Total Vol. of Concrete

BEAMS
2nd
3rd
Roofdeck
Total =
COLUMNS
Ground
2nd
3rd
Total =

w/ 5% allowance (m )
23.306
23.306
23.306
69.918
Total Vol. of Concrete
w/ 5% allowance (m )
9.34
8.1725
8.1725
25.685

Total Vol. of Concrete

Total Weight of Stee


w/ 5% allowance (kg
6775.9
6776.9
6777.9
6778.9
27109.6

w/ 5% allowance (m )
39.571875
39.571875
39.571875
41.34375
160.059375

Total Weight of Steel


w/ 5% allowance (kg)
2720
2720
2720
8160
Total Weight of Steel
w/ 5% allowance (kg)
7606.72
6643.33
6643.38
20893.43

SHEARWALL
t(mm)
L(m)
Quantity
150
3
8
Volume of Concrete
=
39.6
cubic meters
MASONRY WALLS
Ground - 3rd Floor

Height (m)
11

Area
m
1190.4

Reinforcements
138
pcs. 16-mm diam. Bar (6m long)
74
pcs. 16-mm diam. Bar (6m long)
212
pcs. 16-mm diam. Bar (6m long)
334.607 kg
CHB Pieces (6")
w/ 5% allowance for breakage

1190.4(12.5)

15624

Steel Bar Reinforcement for CH =


(3(1190.4))/
596
=
367.45638 kg
Source for factors used: Architectural & Const. Data
By Salvan, George S
Source for Prices used:
www.magkano.com/construction/construct.htm
Year updated:
March, 2014

pcs

Cost Estimates

OMRF with Shearwall

TOTAL COST FOR SPECIAL MOMENT RESISTING FRAME


TOTAL AMOUNT:
Cost
Price (Peso)
Concrete 295.2624
kg
4000
1181049.5
Re-bars 56865.09
65
3696231.07
CHB(6")
15624
16
249984
Plaster
331
230
76130
Sand
33.1
1500
49650
Total =

5,253,044.57

Pesos

Cost of OMRF with Shear Wall having a drift of 0.78 cm on x-direction and 0.83 cm on y-dir

OMRF w/ Shear Wall

Weight (kN)
13718.82

Volume (m3)
583.78

Price (Peso)
4000

Cost
2,335,120.00

Cost Estimates

Total Weight of Steel


w/ 5% allowance (kg)
6775.9
6776.9
6777.9
6778.9
27109.6

diam. Bar (6m long) vertical


diam. Bar (6m long) horizontal
diam. Bar (6m long)
PLASTER
bags (1:3 mix

331
10-mm bar

SAND
m
33.1

OMRF with Shearwall

Cost Estimates

on and 0.83 cm on y-direction

OMRF with Shearwall

TRADE-OFFS
SMRF
OMRF WITH SHEAR WALL

TOTAL COSTS
5,168,995.12
5,253,044.57

Potrebbero piacerti anche