Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Project Name)
METHOD STATEMENT
Method statement for concrete crack repairing works using
Concresive 2200 and Concresive 1320
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
1 of 8
PROJECT
CLIENT
MASTER DEVELOPER
PMC
LEAD CONSULTANT
SUB-CONSULTANT
MAIN CONTRACTOR
SUB-CONTRACTOR
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
2 of 8
TABLE OF CONTENTS
1.
REVISION RECORD............................................................................................................................................
2.
PURPOSE............................................................................................................................................................
3.
SCOPE.................................................................................................................................................................
4.
5.
REFERENCES.....................................................................................................................................................
5.1.
Contract documents......................................................................................................................................
5.2.
Contractors Submittal....................................................................................................................................
6.
DEFINITIONS / ABBREVIATIONS......................................................................................................................
6.1.
Definition.........................................................................................................................................................
6.2.
Abbreviations.................................................................................................................................................
7.
RESPONSIBILITIES............................................................................................................................................
8.
PROCEDURE.......................................................................................................................................................
8.1.
General............................................................................................................................................................
8.2.
Material............................................................................................................................................................
8.3.
Substrate Preparation....................................................................................................................................
8.4.
Application......................................................................................................................................................
9.
RESOURCE REQUIREMENTS...........................................................................................................................
9.1.
Manpower........................................................................................................................................................
9.2.
Material............................................................................................................................................................
9.3.
10.
11.
ATTACHMENTS..............................................................................................................................................
11.1.
Inspection Checklists................................................................................................................................
11.2.
11.3.
Risk Assessment.......................................................................................................................................
11.4.
11.5.
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
3 of 8
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and
title. All previous revisions are hereby superseded and are to be destroyed.
Rev
Date
By
Chkd.
Approve
d
Description of Revisions
First issue
Signature field
Revision
Number
Reviewed
By
Approved
By
Revision
Date
Constructio Technical
n Manager Manager
Project
Manager
Prepared
by
QA/QC
Engineer
Checked by
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
4 of 8
2. PURPOSE
3. SCOPE
This Method Statement details general procedures to be followed for concrete crack
repairing works using Concresive 2200 and Concresive 1320 at Project. It includes
preparatory works, repairs and curing.
5. REFERENCES
5.1.
Contract documents
1. Project Specification
2. Contract Drawings
5.2.
Contractors Submittal
::-
5. Material approvals
Sr.
No.
1
2
3
Description
Material Sub.
No.
Rev No.
Date
Remarks
Shop
Drawings
Rev No.
Date
Remarks
MET no.
Rev No.
Date
Remarks
6. Shop Drawings
Sr.
No.
1
2
3
Description
Description
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
5 of 8
6. DEFINITIONS / ABBREVIATIONS
6.1.
1.
2.
3.
4.
5.
6.
7.
8.
Definition
Project
-(Replace with project name)
Client
-(Replace with clients name)
Developer
-(Replace with developers name)
Consultant
-(Replace with consultants name)
PMC
-(Replace with PMC name)
Contractor
-(Replace with contractors name)
Sub-contractor
-(Replace with sub-contractors name)
Supplier
-(Replace with suppliers name)
6.2.
Abbreviations
1. Engineer
2. ICL
3. IR
4. ITL
5. ITP
6. ITR
7. MAT
8. MEP
9. MET
10.
11.
12.
13.
14.
spaces)
15.
16.
17.
18.
7. RESPONSIBILITIES
1.
2.
3.
4.
5.
Project Manager has the overall responsibility for the implementation of this
method statement and shall well ensure that Sub Contractors as well other team
members are aware of the requirements of the Method Statement.
Construction Manager will ensure that the Resources are available to carry out the
works as scheduled.
The Project Engineer/Site Engineer is responsible for inspection records and carries
out the works as per approved Shop Drawings, Method Statements.
The Site Engineer/Supervisor is responsible to ensure :
a. That the work has been carried out as per specifications & drawings and
inspections are done as per contract.
b. To check material being used is approved one.
c. Surface preparation is as per the method statement
d. Mixing and application are as per the method statement.
The Surveyor/Site Engineer/Supervisor is responsible for Setting out the area and
measuring, monitoring and controlling the lines and levels.
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
6 of 8
8. PROCEDURE
8.1.
General
1. The works shall be performed as mentioned in this procedure and the quality
assurance requirements shall be consistent with the relevant sections of Quality
System Procedure Manual of Contracting company as well with the Project Quality
Plan.
2. Shop/Design drawing to be strictly complied with at the site.
3. Work shall not proceed without formal approval by the Engineer.
4. Before commencement of the work, ascertain the nature and location of all
existing services on site by visual survey.
5. If any protection, rerouting, termination or removals of services are required for
the smooth progressing of work, it will be discussed and written approval will be
obtained from Employer as appropriate.
8.2.
Material
8.3.
Substrate Preparation
1. Remove surface laitance and contamination from area, centred on the crack
50mm wide and along the length of crack, using power wire
brushing, high
pressure water jetting or light blasting.
2. If packers are being used, drill holes along the centre of the crack to accept the
packers. The centre shall be 1-1.5 times the depth of the crack, but
not more than
300mm apart.
3. Use oil free compressed air to blow out the length of the cracks to remove dust
and debris.
4. If flanged injection ports are used, use Concresive 2200 as the bonding agent.
Apply mixed Concresive 2200 to the bottom of the flange at the perimeter. Ensure
that the
paste does not block the port. Use a nail or piece of wire inserted
through the port to
locate the port over the centre of the crack.
5. When all the ports or packers have been placed, apply Concresive 2200 in a strip
20mm wide and 2-3mm thick between the ports and centred on the crack.
6. The paste shall be forced into the substrate to ensure intimate contact. Make sure
the paste seals around the packer or port. Allow to cure.
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
7 of 8
7. If the crack is in a wall or suspended slab and both side can be reached, prepare
both sides in the same manner but centre the injection ports between the ports
on the opposite side.
8.4.
Application
1. Start the injection process from one end of the crack. In case of vertical cracks,
start from the bottom of the crack and work upward.
2. Thoroughly blend and mix 2 components (A & B) of Concresive 1320 for at least
1 minute, using slow speed drill with paddle attached, ensuring a uniform colour is
achieved. Pot life as per the manufacturer recommendation is 20 min / 35C
3. Pour the mixed resin into the injection gun and connect the injection gun to the
port in the lowest point of the crack.
4. Inject resin until it starts to flow from the next port, then close off the port being
injected and move to the port from which the resin is exuding.
5. Repeat the process of injection at a steady rate until the whole length of the crack
has been injected.
6. Allow to cure overnight then remove the injection ports and grind off the paste
over the cracks if required. Final curing to be done for 7 days.
9. RESOURCE REQUIREMENTS
9.1.
Manpower
1. - Site Engineer
3. - Supervisor
5. - Foreman
9.2.
2. - Technician
4. - Helpers
Material
1. - Concresive 1320
2. - Concresive 2200
3. - Packers / Injection ports.
9.3.
2. 4. 6. 8. 10.
12.
14.
Hammer
Chisel
Air compressor
water pump
- Gloves
- Goggles
- Water Tanker
Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages
TEC-036400-MET-DoR-003
NA
8 of 8
11. ATTACHMENTS
11.1. Inspection Checklists
11.2. Inspection Test Plan
11.3. Risk Assessment
11.4. Technical Data sheet (TDS)
1. Concresive 1320