Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Spun Pile
Main Span Pilecap Construction
by
Content
Spun Pile
Spun Pile Detail
Spun Pile Length
Spun Pile PDA Test
Spun Pile Test For BHT11 (P163)
Mobilization Factor of Spun Pile
Pile Head Damage Analysis
Validation of Spun Pile
Type Of Piles
Approach Span
P000
Batu Maung
P023
P24-P27 :
Bored Pile
Main Span
P024
P027
Approach Span
P028
P144
Approach Span
P145
P292
Batu Kawan
Summary of Piles
Description
Passed Pile
(Nos.)
Rejected Pile
(Nos.)
Total Pile
(Nos.)
368
368
5158+19*
10
5168+19*
66
80
80
* 19 nos. replacement spun piles P107-07 A & B, P102-12 A & B, P061-13 A & B,
P120-04 A & B, P122-07A & B, 8A, P137-7A & 7B, P193-21A & B, P9-17
A&B, P280-R15 A&B
BHT8
BHT9
BHT10
BHT7
BHT6
BHT4
BHT3&5
BHT2
BHT11
BHT1
BHT12
No.
Chainage
Location
(near to)
Pile Type
Working
Load (kN)
Total Test
Done
Total
Passed
Not
Conclusive
O-Cell Test
BHT 3
CH 9+700
P161
5,800
O-Cell Test
BHT 7
CH 2+688
P33
8,100
O-Cell Test
BHT 9
CH 1+981
P25
2.3~2.0m
Bored Pile
25,500
BHT 1
CH 15+900
P273
3,800
BHT 2
CH 11+700
P197
3,800
BHT 5
CH 9+700
P161
3,840
MLT
BHT 4
CH 3+500
P48
3,800
BHT 6
CH 3+530
P48
4,600
BHT 3
CH 9+700
P161
5,800
BHT 11
CH 9+818
P163
3,720
Statnamic
CH 11+028
P185-L08
3,100
Statnamic
BHT 11
CH 9+818
P163
3,720
BHT 12
CH 16+913
P292
8,000
BHT 8
CH 1+368
P15
7,210
Statnamic
CH 3+548
P49-R15
3,410
Statnamic
CH 1+980
P25-09
27,200
SPUN PILE
SEE DETAIL X
DETAILS OF PILESHOE
Extension Joint
Extension Joint
L1
L2
L3
L4
L5
Spun Pile
(1.0m)
Total Pile
(Nos.)
0 to 2m
2 to 5m
> 5m
5187
4744 (92%)
329 (6%)
114 (2%)
= 58.67m
= 57.28m
= 1.38m (2.4%)
~ -55.00
SPT = 50
Design Pile
Length (m)
Design Toe
Level (m)
Actual Toe
Level (m)
Differences
P161
59
<2m
P162
58
<2m
P163
56
<2m
P164
55
<2m
P165
53
<2m
Initial Strike
for Pile
Integrity
BTA
<80%
Re-strike
Total PDA
Done
Total (nos.)
331
396
735
PDA Test...
Statnamic Test...
Anchor Pile,
M2-1
Anchor Pile,
M2-2
Pile
Spun Pile
Pile
Length
Design Toe
Level
Actual Toe
Level
M2-1
1000mm
59m
-57.0
-56.98
M2-2
1000mm
59m
-56.0
-56.00
1000mm
59m
-56.0
-55.97
1000mm
59m
-56.0
-55.95
J2-1
1000mm
50m
-46.5
-46.43
J2-2
1000mm
50m
-46.5
-46.41
S2
1000mm
61m
-57.0
-56.88
4m
Reference Pile,
J2-1
Test Pile, S2
4m
Anchor Pile,
M2-3
4m
4m
Anchor Pile,
M2-4
* Working load = 3720kN
Test Pile, S2
PDA (EOD)
Min. 7 days after pile installation
Statnamic
PDA (Restrike)
w/o instrumentation
MLT
Min. 15 days after MLT
Statnamic
Table 2 : Comparison of 2nd Cycle Nett Static & Statnamic Load Test Displacement
From Table 1, settlement recorded from Statnamic test for M2-1 at 2.0 WL is 5.14mm less than
Static test for S2
From Table 2, settlement recorded from Statnamic test for M2-1 at 2.0 WL is 2.38mm less than
Static test for S2
Pile
Penetrated
Length
Length
(m)
(m)
64
54.68
Set
(mm)
Ultimate
Capacity of
MLT(kN)
Initial
PDA
(kN)
Restrike
PDA
(kN)
Restrike /
Initial
MLT / PDA
Initial
5.9
> 11,160
5150
10,800
2.10
>2.17
It can be observed the analytical results of PDA test are accurate verified by BHT11s MLT
test result and can be concluded that the PDA test procedures are in order.
In order to verify the capacity of piles which no restrike test but only end of drive test
(EOD) was performed, recommended mobilization factor is proposed based on :
i) pile embedment
ii) pile toe founding layer
iii) total number of blow
Mobilization factor of bearing capacity of a given pile can be obtained by dividing restrike
test capacity (Q2) by EOD test capacity (Q1)
3
2.5
Mobilization
Factor
1.5
1
0.5
0
40
45
50
LP (m)
55
60
3
2.5
Mobilization
Factor
2
1.5
1
0.5
0
0
1000
2000
3000
Blow Count
4000
5000
3
2.5
Mobilization
Factor
2
1.5
1
0.5
0
0
SET (mm)
10
12
14
3
2.5
Mobilization
Factor
2
1.5
1
0.5
0
0
10
Period (Day)
15
98% of the restriked piles have penetration of 0.0mm. It is understood that most piles did
not achieve its maximum capacity during restrike test due to limited energy.
From the data collected from tested working piles, the average M-factor is 1.77. On the
other hand, the M-factor for BHT 11 test pile is 2.17.
Therefore, M-factor of 1.77 to 2.00 is a conservative engineering selection.
Recommended M-Factor
Based on the abovementioned analysis and statistics, it is recommended to use M-factor
of 1.7 for spun pile.
Cases
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0 MayJuneJulyAugSepOct NovDec JanFebMarAprMayJuneJulyAugSepOct NovDecJanFebMarAprMayJuneJulyAugSep
09 09 09 09 09 09 09 09 10 10 10 10 10 10 10 10 10 10 10 10 11 11 11 11 11 11 11 11 11
Month
Pile Head
Damage Cases
Total cases = 55
150
125
177
279
244
160
156
148
175
68
256
252
195
209
208
270
247
327
226
185
09 09
169
09
145
09
73
94
09
112
225
90
0%
220
May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJune July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep
09
09
09
10 10 10
10 10 10
10
10
10
10 10 10
11 11
11
11 11
11
11 11
11
1.37%
1.14%
0.91%
0.68%
0.46%
0.23%
5187
5185
5035
4910
4733
4454
4210
4050
3894
3746
3571
3503
3247
2995
2800
2591
2383
2113
1866
1539
1313
1128
959
814
741
629
535
310
0.00%
220
May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJuneJuly Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep
09
09
09 09 09 09 09 09
10 10 10
10 10 10 10
10 10 10 10 10
11 11 11 11 11
11
11 11 11
No
Actions Taken
Remarks
Mould
To
inspection
Concrete feeding process
Spinning process
Steam curing
Staking yard
More frequent checking on raw material
Concrete cubes & cores strength
Calibration certificates
replace hammer cushion once worn out
Provide sufficient cushion materials
Ensure hammer hits pile evenly and axially
Reduce pile driving stresses by controlling hammer drop
height during hard driving
2 hours waiting time was set aside for pile which has undergone spinning
process. On top of that, 8 hours of steam curing time is above the usual practice
of 5 hours.
Audit to supplier raw material suppliers (sand, aggregate) was conducted on a
regular basis to ensure the conformity of material supplied.
The allowable gap between end plates is only 2mm, which is much more
stringent than 5mm tolerance stated in MS1314: Part4:2004.
Monthly inspection from CHEC & MMSB to ensure all piles produced to the
highest standard as stipulated in the Technical Requirements for Spun Pile.
Test Pile
Dial Gauges
Support
Support
No.
Actions Taken
Remarks
Petrographic
P160 (10
examination
X-ray diffraction (XRD)
nos)
P121-P123 (18 nos)
Carry out pile head strengthening work (with carbon fiber & ICP method)
PDA Test
Coring Test
PDA & coring test result found satisfactory
Validation Process
Piling work done in accordance with :
- Approved construction drawing
- Set criteria
- HPDI revised pile length confirmation
- Shop drawing (if any changes)
Pile Cutting
Set Criteria
Piling Record
H>2m
PDA Result
> 80%
> 2.5 x WL
PDAR is required when the different between design toe level and actual toe level
> 2m.
The pile is considered acceptable if :
- Pile capacity shown in PDA test > 2.5WL
- Pile integrity, BTA value in PDA test > 80%
BTA value classification:
i) 100 %
ii) 80-99%
iii) 60-79%
iv) <60%
Pile Type
PHC
Driven
Spun Pile
Driven
Steel Pile
Bored Pile
(m)
1.0
Average
Length
(m)
53m
Number /
Pier
10
Economic
Rate
1.00
1.6
83m
2.87
1.5
105m
3.62
Diameter
Main Span
Pilecap Construction
P24
P25
P26
P27
Span Length
p26
p25
p27
p24
117.5 m
240 m
117.5 m
150 m
Navigation
Navigation
ChannelChannel
Pylon Detail
30m
5m
General Description
Main Span arrangement : 117.5m 240m 117.5m
17.5m
48.1m
6m
STEEL FENDER
steel fender
Clearing of formwork
platform
Installation of supporting
brackets and bearing beams
Demarcation of
platform
Installation of hydraulic
jacks
Hydraulic jacks in
operation
Installation of
operation platform
Fabrication of rebar
onshore
Fabrication of rebar
onshore
Steel
St eelCasing
case
Steel
St eelCasing
case
-3.32m
-5.12m
Concreting Of Pilecap
+3.48m
+2.68m
2nd
Layer
the second layer concrete
of the pilecap(2.0m)
(2.0m)
the
ndsecond layer concrete
of the pilecap(3.0m)
2 Layer
(3.0m)
+0.68m
steel fender
1sttheLayer
first layer concrete of
the pilecap(2.0m)
(2.0m)
steel fender
-1.32m
st Layer
1the
second layer concrete
of the pilecap(3.0m)
(3.0m)
mass Concrete
concrete(1.2m)
Mass
(1.2m)
Mass
Concrete
mass concrete(1.8m)
(1.8m)
-2.52m
Temperature Control
JKR Specification
NO.
Items
Requirement
Placing Temperature
36
70
27.7
10/30min
Low
used
Additive like GGBS and silica fume are added to the design mix
to minimize the cement content
Water cooling pipe with cycling of ice water and thermocoupler
to be embedded in the concrete
Water boat
Thermocoupler
Cooling pipe
10
11
Ambient Tempt.
Peak Temperature
80
Temperature/
70
60
50
40
30
20
10
0
0
20
40
60
80
100
Time/h
120
140
160
180
Thank You