Penang Second Bridge

Marine Bridge Substructure


Construction

Spun Pile
Main Span Pilecap Construction
by

Ir. Cheng Kim Bong


Senior Resident Engineer
MMSB Consult Sdn. Bhd.

Content

Penang Second Bridge Alignment


Type Of Piles
Summary of Piles
Pile Testing Locations
Pile Testing of Spun Pile, Steel Pile & Bored Pile

Spun Pile
Spun Pile Detail
Spun Pile Length
Spun Pile PDA Test
Spun Pile Test For BHT11 (P163)
Mobilization Factor of Spun Pile
Pile Head Damage Analysis
Validation of Spun Pile

Main Span Pilecap Construction

Penang Second Bridge

Penang Second Bridge Alignment

Type Of Piles

P0-P11 : Spun Pile


P12-P23 : Steel Pile

Approach Span

P000
Batu Maung

P023

P24-P27 :
Bored Pile

Main Span

P024

P027

P28-P43 : Steel Pile P145-P282 : Spun Pile


P44-P144 : Spun Pile P283-P292 : Bored Pile

Approach Span

P028

P144

Approach Span

P145

P292
Batu Kawan

Summary of Piles
Description

Passed Pile
(Nos.)

Rejected Pile
(Nos.)

Total Pile
(Nos.)

Steel Pile (1.6m)

368

368

Spun Pile (1.0m)

5158+19*

10

5168+19*

Bored Pile (2.3m-2.0m)

66

66+1 (P26-20 rejected)

Bored Pile (1.5m)

80

80

* 19 nos. replacement spun piles P107-07 A & B, P102-12 A & B, P061-13 A & B,
P120-04 A & B, P122-07A & B, 8A, P137-7A & 7B, P193-21A & B, P9-17
A&B, P280-R15 A&B

Pile Testing Locations

BHT8

BHT9
BHT10
BHT7
BHT6

BHT4

BHT3&5
BHT2

BHT11
BHT1

BHT12

Pile Testing On Spun Pile, Steel Pile & Bored Pile


Pile Test

No.

Chainage

Location
(near to)

Pile Type

Working
Load (kN)

Total Test
Done

Total
Passed

Not
Conclusive

O-Cell Test

BHT 3

CH 9+700

P161

1.2m Steel Pile

5,800

O-Cell Test

BHT 7

CH 2+688

P33

1.6m Steel Pile

8,100

O-Cell Test

BHT 9

CH 1+981

P25

2.3~2.0m
Bored Pile

25,500

MLT & PDA

BHT 1

CH 15+900

P273

1.0m Spun Pile

3,800

MLT & PDA

BHT 2

CH 11+700

P197

1.0m Spun Pile

3,800

MLT & PDA

BHT 5

CH 9+700

P161

1.0m Spun Pile

3,840

MLT

BHT 4

CH 3+500

P48

1.0m Spun Pile

3,800

MLT & PDA

BHT 6

CH 3+530

P48

1.2m Spun Pile

4,600

MLT & PDA

BHT 3

CH 9+700

P161

1.2m Steel Pile

5,800

MLT & PDA

BHT 11

CH 9+818

P163

1.0m Spun Pile

3,720

Statnamic

CH 11+028

P185-L08

1.0m Spun Pile

3,100

Statnamic

BHT 11

CH 9+818

P163

1.0m Spun Pile

3,720

MLT & (Statnamic


on Anchor Pile)

BHT 12

CH 16+913

P292

1.5m Bored Pile

8,000

MLT & (Statnamic


on Anchor Pile)

BHT 8

CH 1+368

P15

1.6m Steel Pile

7,210

Statnamic

CH 3+548

P49-R15

1.0m Spun Pile

3,410

Statnamic

CH 1+980

P25-09

2.0m Bored Pile

27,200

SPUN PILE

Spun Pile Detail

ICP Spun Pile Sectional Details


Revised pile shoe
detail as per next
slide

SEE DETAIL X

Spun Pile Detail

Pile Shoe Details

DETAILS OF PILESHOE

Spun Pile Detail

Extension Joint

Spun Pile Detail

Extension Joint

Spun Pile Detail

4 Lifting Points of Spun Pile

L1

L2

L3

L4

L5

L= Pile Length L1 = 0.05L L2 = 0.28L L3 = 0.31L L4 = 0.23L L5 = 0.13L


* Average Pile Length is about 58.5m

Spun Pile Length

Design Pile Length vs Actual Pile Length


Difference Between Design Pile Length & Actual
Pile Length
Description

Spun Pile
(1.0m)

Total Pile
(Nos.)

0 to 2m

2 to 5m

> 5m

5187

4744 (92%)

329 (6%)

114 (2%)

Average Design Length


Average Nett Length
Average Cut-off Length

= 58.67m
= 57.28m
= 1.38m (2.4%)

Spun Pile Length

Bore Log Record For BHT 11 (near P163)

~ -55.00

SPT = 50

Spun Pile Length

Design Pile Length vs Actual Pile Length


Pier

Design Pile
Length (m)

Design Toe
Level (m)

Actual Toe
Level (m)

Differences

P161

59

-57.62 to -58.42 -56.14 to -57.02

<2m

P162

58

-56.63 to -57.42 -55.13 to -55.95

<2m

P163

56

-54.66 to -55.42 -53.20 to -54.49

<2m

P164

55

-53.67 to -54.42 -52.17 to -52.97

<2m

P165

53

-51.70 to -52.42 -49.71 to -51.09

<2m

Spun Pile PDA Test

PDA Test Summary


Description

Initial Strike
for Pile
Integrity

BTA
<80%

Re-strike

Total PDA
Done

Total (nos.)

331

396

735

PDA Test Frequency

At least two PDA to be carried out at a pair of pilecap :


i) PDA initial
: to verify pile integrity
ii) PDA re-strike : to verify pile capacity

Spun Pile Test For BHT11 (P163)

Objective Of Pile Load Test

To determine the pile ultimate bearing capacity


To determine the pile ultimate resistance at pile base

To determine pile shaft skin friction parameter at each soil layer


To determine correlation between Static Load Test, PDA & Statnamic
To provide the basis for the revision of pile final set criteria

To provide parameters for verification or modification basis for working pile


PDA analysis
To obtain Load vs Settlement relationship

Spun Pile Test For BHT11 (P163)

PDA Test...

Spun Pile Test For BHT11 (P163)

Statnamic Test...

Spun Pile Test For BHT11 (P163)

Static Load Test...


Load Cell

Spun Pile Test For BHT11 (P163)

BHT 11 (P 163) Setting Up

Anchor Pile,
M2-1

Anchor Pile,
M2-2

Pile

Spun Pile

Pile
Length

Design Toe
Level

Actual Toe
Level

M2-1

1000mm

59m

-57.0

-56.98

M2-2

1000mm

59m

-56.0

-56.00

Reference Pile, M2-3


J2-2
M2-4

1000mm

59m

-56.0

-55.97

1000mm

59m

-56.0

-55.95

J2-1

1000mm

50m

-46.5

-46.43

J2-2

1000mm

50m

-46.5

-46.41

S2

1000mm

61m

-57.0

-56.88

4m

Reference Pile,
J2-1

Test Pile, S2

4m

Anchor Pile,
M2-3

4m

4m

Anchor Pile,
M2-4
* Working load = 3720kN

Spun Pile Test For BHT11 (P163)

BHT 11 (P 163) Testing Process

Anchor Pile, M2-1


PDA (EOD)

Test Pile, S2

PDA (EOD)
Min. 7 days after pile installation

Statnamic

PDA (Restrike)

w/o instrumentation

Min. 28 days after pile installation

MLT
Min. 15 days after MLT

Statnamic

Spun Pile Test For BHT11 (P163)

Comparison of Static 2nd Cycle Static and Statnamic Load


Test Results

Spun Pile Test For BHT11 (P163)

Comparison of Static 2nd Cycle Nett Static and Statnamic


Load Test Results

Spun Pile Test For BHT11 (P163)

Comparison of Static and Statnamic Load Test Displacement


Table 1 : Comparison of Static & Statnamic Load Test Displacement

Table 2 : Comparison of 2nd Cycle Nett Static & Statnamic Load Test Displacement

From Table 1, settlement recorded from Statnamic test for M2-1 at 2.0 WL is 5.14mm less than
Static test for S2
From Table 2, settlement recorded from Statnamic test for M2-1 at 2.0 WL is 2.38mm less than
Static test for S2

Spun Pile Test For BHT11 (P163)

Summary Comparison Between Statnamic & Static Load Test

Spun Pile Test For BHT11 (P163)

Comparison Between PDA & Static Load Test


Test
Pile
S2

Pile
Penetrated
Length
Length
(m)
(m)
64

54.68

Set
(mm)

Ultimate
Capacity of
MLT(kN)

Initial
PDA
(kN)

Restrike
PDA
(kN)

Restrike /
Initial

MLT / PDA
Initial

5.9

> 11,160

5150

10,800

2.10

>2.17

- Summary Comparison Between PDA & Static Load Test

It can be observed the analytical results of PDA test are accurate verified by BHT11s MLT
test result and can be concluded that the PDA test procedures are in order.

Mobilization Factor of Spun Pile

M-Factor of Spun Pile Using PDA


Major objective of PDA restrike test is to verify the pile capacity to satisfy the required
design capacity (2.5 times of working load)

In order to verify the capacity of piles which no restrike test but only end of drive test
(EOD) was performed, recommended mobilization factor is proposed based on :
i) pile embedment
ii) pile toe founding layer
iii) total number of blow

Mobilization factor of bearing capacity of a given pile can be obtained by dividing restrike
test capacity (Q2) by EOD test capacity (Q1)

Mobilization Factor of Spun Pile


M-Factor vs Pile Embedment
Relationship Diagram Between Pile Embedment & Mobilization
Factor

3
2.5
Mobilization
Factor

1.5
1

0.5
0
40

45

50

LP (m)

55

60

Mobilization Factor of Spun Pile


M-Factor vs Blow Count
Relationship Diagram Between Blow Count & Mobilization Factor

3
2.5
Mobilization
Factor

2
1.5
1
0.5
0
0

1000

2000

3000

Blow Count

4000

5000

Mobilization Factor of Spun Pile


Mobilization vs Set
Relationship Diagram Between SET & Mobilization Factor

3
2.5
Mobilization
Factor

2
1.5
1
0.5
0
0

SET (mm)

10

12

14

Mobilization Factor of Spun Pile


Mobilization vs Period
Relationship Diagram Between Period & Mobilization Factor

3
2.5
Mobilization
Factor

2
1.5
1
0.5
0
0

10

Period (Day)

15

Mobilization Factor of Spun Pile

Recommended M-Factor of Spun Pile Using PDA


Conservative Considering
According to the statistical result of comparison between M-factor and pile embedment,
final set and period, it is found that the effect of EOD set to M-factor is most dominant and
relatively obvious among the three factors considered.

98% of the restriked piles have penetration of 0.0mm. It is understood that most piles did
not achieve its maximum capacity during restrike test due to limited energy.
From the data collected from tested working piles, the average M-factor is 1.77. On the
other hand, the M-factor for BHT 11 test pile is 2.17.
Therefore, M-factor of 1.77 to 2.00 is a conservative engineering selection.
Recommended M-Factor
Based on the abovementioned analysis and statistics, it is recommended to use M-factor
of 1.7 for spun pile.

Pile Head Damage Analysis


Pile Head Damage Cases vs Month

Cases

14
13
12
11
10
9
8
7
6
5
4
3
2
1
0 MayJuneJulyAugSepOct NovDec JanFebMarAprMayJuneJulyAugSepOct NovDecJanFebMarAprMayJuneJulyAugSep
09 09 09 09 09 09 09 09 10 10 10 10 10 10 10 10 10 10 10 10 11 11 11 11 11 11 11 11 11

Month

Pile Head
Damage Cases

Total cases = 55

Pile Head Damage Analysis


% Pile Head Damage vs Monthly Progress
8%
7%
6%
5%
4%
3%
2%
1%

150

125

177

279

244

160

156

148

175

68

256

252

195

209

208

270

247

327

226

185

09 09

169

09

145

09

73

94

09

112

225

90

0%
220

% Pile Head Damage

May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJune July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep
09

09

09

10 10 10

10 10 10

10

10

10

10 10 10

Monthly Progress (nos.)

11 11

11

11 11

11

11 11

11

Pile Head Damage Analysis


% Pile Head Damage vs Cumulative Piles Driven
1.59%

1.37%

1.14%

0.91%

0.68%

0.46%

0.23%

5187

5185

5035

4910

4733

4454

4210

4050

3894

3746

3571

3503

3247

2995

2800

2591

2383

2113

1866

1539

1313

1128

959

814

741

629

535

310

0.00%
220

% Pile Head Damage

May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJuneJuly Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep
09

09

09 09 09 09 09 09

10 10 10

10 10 10 10

10 10 10 10 10

Cumulative Piles Driven (nos.)

11 11 11 11 11

11

11 11 11

Pile Head Damage Analysis

List of Preventive Actions

No

Actions Taken

Remarks

QC on standard operating procedure


with introduction of additional
checklist (Spun pile production)

Mould

QC on standard operating procedure


(Piling Operation)

To

Factory visit, inspection and QAQC


procedure auditing at ICP factory

inspection
Concrete feeding process
Spinning process
Steam curing
Staking yard
More frequent checking on raw material
Concrete cubes & cores strength
Calibration certificates
replace hammer cushion once worn out
Provide sufficient cushion materials
Ensure hammer hits pile evenly and axially
Reduce pile driving stresses by controlling hammer drop
height during hard driving

Pile Head Damage Analysis

Other Stringent QAQC Measures

Production data for each produced pile is recorded in In-process checklist.

2 hours waiting time was set aside for pile which has undergone spinning
process. On top of that, 8 hours of steam curing time is above the usual practice
of 5 hours.
Audit to supplier raw material suppliers (sand, aggregate) was conducted on a
regular basis to ensure the conformity of material supplied.
The allowable gap between end plates is only 2mm, which is much more
stringent than 5mm tolerance stated in MS1314: Part4:2004.
Monthly inspection from CHEC & MMSB to ensure all piles produced to the
highest standard as stipulated in the Technical Requirements for Spun Pile.

Pile Head Damage Analysis

Other Stringent QAQC Measures


Welding facilities at ICP factory enable
us to overcome constraints of on-site
welding and reduce the possibility of
pile damage, which usually associate
with on-site welding. MIG wire was
used to ensure top quality welding work
was performed.

The welding quality of jointed pile was


further inspected with the use of
Magnetic Particle Test.

Pile Head Damage Analysis

Other Stringent QAQC Measures

Top Beam Of Jacking Frame


Jack

Test Pile

Dial Gauges

Support

Support

Pile Bending Test (MS1314 Part 2:2004)

Pile Head Damage Analysis

Other Stringent QAQC Measures

Pile Bending Test

Pile Head Damage Analysis

List of Investigation Actions

No.

Actions Taken

Remarks

Thorough investigation involving ICPs


R&D department

Additional tests been carried out

Petrographic

Additional PDA tests been carried out

P160 (10

examination
X-ray diffraction (XRD)
nos)
P121-P123 (18 nos)

Pile Head Damage Analysis

Comments On Additional Test Results

Raw material testing found comply to requirement

Petrographic examination & XRD found satisfactory except


some air and water voids
Additional PDA test results shown no pile integrity problem

Pile Head Damage Analysis

Repair Method For Pile Head Damage

Carry out pile head strengthening work (with carbon fiber & ICP method)

PDA Test
Coring Test
PDA & coring test result found satisfactory

Pile considered acceptable

Validation of Spun Pile

Validation Process
Piling work done in accordance with :
- Approved construction drawing
- Set criteria
- HPDI revised pile length confirmation
- Shop drawing (if any changes)

Pile Driving Record

Pile Certification Report


-PDA test report
- PDAR if required
- SOR / NCR closure if any

Pile Cutting

Validation of Spun Pile

Set Criteria

Validation of Spun Pile

Piling Record

H>2m

Validation of Spun Pile

PDA Result

> 80%

> 2.5 x WL

Validation of Spun Pile

Pile Driving Acceptance Record (PDAR)

PDAR is required when the different between design toe level and actual toe level
> 2m.
The pile is considered acceptable if :
- Pile capacity shown in PDA test > 2.5WL
- Pile integrity, BTA value in PDA test > 80%
BTA value classification:
i) 100 %

: Uniform. No apparent anomaly was detected

ii) 80-99%

: Minor anomaly. Relatively minor impedance reduction detected

iii) 60-79%

: Moderate anomaly. Relatively moderate impedance reduction detected

iv) <60%

: Major anomaly. Relatively major impedance reduction detected

Validation of Spun Pile

Pile Driving Acceptance Record (PDAR)

Validation of Spun Pile

Pile Certification Report

Cost Comparison For Different Types Of Pile Foundation

Pile Type

PHC
Driven
Spun Pile
Driven
Steel Pile
Bored Pile

(m)
1.0

Average
Length
(m)
53m

Number /
Pier
10

Economic
Rate
1.00

1.6

83m

2.87

1.5

105m

3.62

Diameter

Main Span
Pilecap Construction

Main Span Pilecap Construction

Main Span Structure Location

P24

P25
P26
P27

Main Navigation Span

Span Length

p26
p25
p27

p24

117.5 m
240 m

117.5 m

150 m
Navigation
Navigation
ChannelChannel

Main Navigation Span

Pylon Detail
30m

5m

Main Navigation Span

General Description
Main Span arrangement : 117.5m 240m 117.5m

Cable at 6m (typical) spacing


Deck constructed by cast-insitu balanced cantilever method
Deck post-tensioned longitudinally and transversely

The structure design service life is 120 years.

Main Span Pilecap Construction

P25 & P26 Pilecap Layout

17.5m

48.1m

6m

Main Span Pilecap Construction

P25 & P26 Steel Fender Layout

Main Span Pilecap Construction

P24 & P27 Steel Fender Layout

Main Span Pilecap Construction

Steel Fender Cross Section

STEEL FENDER

P025 & P026

steel fender

P024 & P027

Main Span Pilecap Construction

Construction Flow Chart

Clearing of formwork
platform

Installation of supporting
brackets and bearing beams

Demarcation of
platform

Platform clearing and 1st


stage rebar fixing

Installation of hydraulic
jacks

Hydraulic jacks in
operation

Discharge seawater, load


transfer

Installation of
operation platform

1st stage 3m thk. pilecap


concreting
Construction joint

Remove corbels below


platform

2nd stage rebar fixing

Installation of steel fender

Lower down formwork to


design level
Mass concrete casting

Fabrication of rebar
onshore

Platform leveling and


verticality check

2nd stage 3m thk. pilecap


concreting

Fabrication of rebar
onshore

Main Span Pilecap Construction

Mechanism Of Lowering Down Steel Fender

Main Span Pilecap Construction

Mechanism Of Lowering Down Steel Fender

Main Span Pilecap Construction

Hydraulic Jack Arrangement

Steel
St eelCasing
case

Steel
St eelCasing
case

Main Span Pilecap Construction

Steel Fender Installation

Main Span Pilecap Construction

Lowering Mechanism Installation

Main Span Pilecap Construction

Steel Fender At Design Level

Main Span Pilecap Construction

Lean Concrete Casting

Main Span Pilecap Construction

Transferring Of Support System


The transferring of supporting system will be carried out after water is
pumped out from mass concrete and before proceeding for installation
of 1st layer pilecap reinforcement.
+3.48m

-3.32m
-5.12m

Corbels as loading transferring points of hanging rods

Main Span Pilecap Construction

Concreting Of Pilecap
+3.48m
+2.68m

2nd
Layer
the second layer concrete
of the pilecap(2.0m)
(2.0m)

the
ndsecond layer concrete
of the pilecap(3.0m)

2 Layer
(3.0m)

+0.68m

steel fender

1sttheLayer
first layer concrete of
the pilecap(2.0m)
(2.0m)

steel fender

-1.32m
st Layer
1the
second layer concrete
of the pilecap(3.0m)
(3.0m)

mass Concrete
concrete(1.2m)
Mass
(1.2m)

Mass
Concrete
mass concrete(1.8m)
(1.8m)

P025 & P026

P024 & P027

-2.52m

Main Span Pilecap Construction

Temperature Control
JKR Specification

NO.

Items

Requirement

Placing Temperature

36

Maximum Internal Temperature

70

Maximum Temperature Gradient

27.7

Rise rate in Temperature

10/30min

Main Span Pilecap Construction

Temperature Control Measures

Low

heat cement (Portland Pulverised-Fuel Ash Cement) to be

used
Additive like GGBS and silica fume are added to the design mix
to minimize the cement content
Water cooling pipe with cycling of ice water and thermocoupler
to be embedded in the concrete

Main Span Pilecap Construction

Cooling Pipe System

Water boat

Thermocoupler
Cooling pipe

Main Span Pilecap Construction

Temperature Monitoring For P24 & P27

Main Span Pilecap Construction

Temperature Monitoring For P25 & P26

Main Span Pilecap Construction

Temperature Monitoring For P25 & P26


1

10

11

Ambient Tempt.

Peak Temperature

80

Temperature/

70
60
50
40
30
20
10
0
0

20

40

60

80

100

Time/h

120

140

160

180

Thank You