Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Report
Elana_Ubax_Inspection_report_July_2013_customer_version.do1
c
Content
Page
INTRODUCTION.......................................................................................................................................................3
ELECTRICAL POWER............................................................................................................................................4
COOLING WATER................................................................................................................................................. 4
COMPRESSED AIR................................................................................................................................................4
NITROGEN............................................................................................................................................................4
LINE 01 45 TON/DAY........................................................................................................................................... 7
4.1 PROCESS FLOW DIAGRAM...................................................................................................................................7
4.2 PRE-CRYSTALLIZATION LOOP...............................................................................................................................8
4.3 CRYSTALLIZER LOOP............................................................................................................................................9
4.4 PREHEATER....................................................................................................................................................... 10
4.5 HOT CONVEYING................................................................................................................................................10
4.6 REACTOR...........................................................................................................................................................11
4.7 COOLER.............................................................................................................................................................12
4.8 NPU...................................................................................................................................................................12
4.8.1 Gas coolers.............................................................................................................................................12
4.8.2 Catalyst system.......................................................................................................................................13
4.8.3 Gas dryer.................................................................................................................................................14
5 LINE 02 60 TON/DAY.........................................................................................................................................15
5.1 PROCESS FLOW DIAGRAM................................................................................................................................15
5.2 PRE-CRYSTALLIZATION LOOP.............................................................................................................................16
5.3 CRYSTALLIZER LOOP......................................................................................................................................... 17
5.4 PREHEATER....................................................................................................................................................... 18
5.5 HOT CONVEYING................................................................................................................................................18
5.6 REACTOR...........................................................................................................................................................19
5.7 COOLER.............................................................................................................................................................20
5.8 NPU...................................................................................................................................................................21
5.8.1 Gas coolers.............................................................................................................................................21
5.8.2 Catalyst system.......................................................................................................................................21
5.8.3 Gas dryer.................................................................................................................................................22
6 UTILITY CONSUMPTION.....................................................................................................................................23
7 FINAL MATERIAL HANDLING........................................................................................................................... 23
8 CONCLUSIONS AND RECOMMENDATIONS.................................................................................................24
Introduction
SSP-1
1995 Start-up. Design capacity = 45 tons/day
1997 Plant was dismantled and re-assembled in a different location (close to SSP-2).
Until 2012 Continuous capacity increasing. Maximal throughput achieved was 60 tons/day (BG).
Main bottlenecks for higher capacities were: raw material shortage and rotary valves.
20112012 Several campaigns with RPET material supplied by different customers.
Typical process conditions used for RPET processing:
SSP throughput: 2200 kg/h 2400 kg/h
IVinlet:
SSP-2
1997 Start-up. Design capacity = 60 tons/day
Until 2012 Continuous capacity increasing. Maximal throughput achieved was 76.8 tons/day
(BG).
Main bottlenecks for higher capacities were: raw material shortage and rotary valves.
20102011 Processing of Technical Yarn (TY) grade supplied by spanish customer.
Typical process conditions for TY:
SSP throughput: 1300 kg/h 1500 kg/h
IVinlet:
0.620 dl/g
220/380 V (10 %)
50 Hz (1 %)
Control Voltage
24 V
DC
24 V
DC
Analog signals
4 20 mA
3 phase
for controllers
Outlet max.
Temperature
35C
Pressure
5 bar g
closed system
ambient
Pressure (min)
4.5 bar g
Dew Point
-20 C
Condition
Oil free
2.4 Nitrogen
Temperature
ambient
Pressure (min)
4.5 bar g
Pressure fluctuation
0.5 bar
- 20 C
Purity
99.5 vol %
Condition
Oil free
Fig. 3-01: Overview of SSP building and raw material handing area.
A classifier located downstream raw material silo removes oversized particles (Elana used to process
material from batch system) and dust from feedstock before convey it to the top of the SSPs.
Fig. 3-02 and 3-03: Classifier downstream raw material silos (left: SSP-45tpd; right: SSP60tpd).
Design capacity:
Fig. 3-04 and 3-05: big-bag unloading system and pneumatic conveying line to raw material silos.
Line 01 45
ton/day
4.1 Process Flow Diagram
Pre-crystallizer:
Fan:
Heater:
Cyclone
OKRB-175
Fig. 4-02 and 4-03: Pre-crystallizer OTWK-180 and Pre- & Crystallizer fans
The Pre-crystallizer was fairly clean and fluidization sieve does not have signs of damage (the sieve
holes were not clogged with dust and/or pellets)
Crystallizer:
Fan:
Heater:
Cyclone
OKRB-150
The Pre-crystallizer is in a good condition: gas flaps, product lever and "pulsator" are working properly
and sight glasses are free of scratches / dirty.
The fluidization sieve has have signs of deformation in the front section (it is recommend to replace the
OTWG sieve). The sieve holes were not clogged with dust and/or pellets customer never
observed product entrainment is this loop.
4.4 Preheater
Preheater:
Fan:
Heaters:
Jet-filter
PGFZ-52/18
As usual all sight glasses were completely covered by oligomer. Normal condition after years in
operation.
Manhole on top of the OKTD was not opened during the plant visiting
Blower:
Heater:
Fig. 4-06: hot conveying system using D+H blower fluid-lift conveying.
4.6 Reactor
Reactor:
Heater:
OKTN-19-130
3
3
Fig. 4-07 and 4-08: reactor OKTN-19-130 conveying hopper and temperature probes / load cell.
Fig. 4-09 and 4-10: reactor OKTN-19-130 internal view and product distributor.
The Reactor was inspected internally (manhole located on its top). No signs of deformation or damage
were observed. Note: the current reactor does not have any kind of inserts.
The original temperature sensors (rope sensor) were replaced by PT-100 installed in the reactor wall.
There is a small hopper installed on the top of the reactor.
Elana_Ubax_Inspection_report_July_2013_customer_version.d1o
1c
4.7 Cooler
Cooler:
Fan:
Cyclone
MGXD-95
The product cooler was fairly clean and fluidization sieve does not have signs of damage (the sieve
holes were not clogged with dust and/or pellets)
Gas flaps, product lever and "pulsator" are working properly and sight glasses are free of scratches /
dirty.
4.8 NPU
4.8.1
Gas coolers
The original gas cooler upstream main blower (TAG: 327 BEM type) was replaced by new one
manufactured in Poland due to frequently clogging / corrosion on the water side. The new H.E. is made
of stainless steel.
Other heat exchangers like 343 (downstream main blower) and 318 (ECO) never had similar problem.
4.8.2
Catalyst system
Catalyst vessel:
o
Catalyst amount:
OGR-10
0.26 m3
OGAF-26
OKUR-TM-230
According to the customer the current catalyst charge was in operation for approx. 05 years. Tests with
recycled material performed in 2012 apparently affected the catalyst charge: gunk was collected in 327
gas cooler and condensate water from gas dryer.
4.8.3
Gas dryer
Delair GDCA-NES-0912
Line 02 60
ton/day
5.1 Process Flow Diagram
Pre-crystallizer:
Fan:
Heater:
Cyclone
OKRB-175
Fig. 5-02 and 5-03: Pre-crystallizer OTWK-180 and its fluidization sieve
Analog to SSP-1 the Pre-crystallizer was fairly clean and fluidization sieve does not have signs of
damage (the sieve holes were not clogged with dust and/or pellets).
Crystallizer:
Fan:
Heater:
Cyclone
OKRB-150
Similar to SSP-1, the Crystallizer from line 02 is in a good condition: gas flaps, product lever and
pulsator are working properly and sight glasses are free of scratches / dirty.
The fluidization sieve has have signs of deformation in the outlet section (it is recommend to replace the
OTWG sieve). The sieve holes were not clogged with dust and/or pellets customer never
observed product entrainment is this loop.
Visual inspection did not detect any irregularity with respect to the crystallizer fan.
5.4 Preheater
Preheater:
Fan:
Heaters:
Jet-filter
PGFZ-52/18
Manhole on top of the OKTD was not opened during the plant visiting
Customer never observed presence of pellets inside intermediate heater or material collected from
PGFZ filter.
Blower:
Heater:
Fig. 5-07: hot conveying system using D+H blower fluid-lift conveying.
5.6 Reactor
Reactor:
Heater:
Fig. 5-08 and 5-09: reactor OKTN-19-150 top section and temperature probes / load cell.
The Reactor was inspected internally (manhole located on its top). No signs of deformation or damage
were observed. Note: the current reactor does not have internals.
The original temperature sensors (rope sensor) were replaced by PT-100 installed in the reactor wall.
5.7 Cooler
Cooler:
Fan:
Cyclone
MGXD-95
The product cooler was fairly clean and fluidization sieve does not have signs of damage (the sieve
holes were not clogged with dust and/or pellets)
Gas flaps, product lever and pulsator are working properly and sight glasses are free of scratches /
dirty.
5.8 NPU
5.8.1
Gas coolers
The original gas cooler upstream main blower (TAG: 327 BEM type) was replaced by new one
manufactured in Poland due to frequently clogging / corrosion on the water side. The new H.E: is made
of stainless steel.
Other heat exchangers like 343 (downstream main blower) and 318 (ECO) never had similar problem.
5.8.2
Catalyst system
OGR-10
Catalyst vessel:
o
Catalyst amount:
0.26 m3
OGAF-26
OKUR-TM-230
According to the customer the current catalyst charge was in operation for approx. 05 years.
Fig. 5-14 and 5-15: Catalyst vessel and catalyst panel resp.
Elana_Ubax_Inspection_report_July_2013_customer_version.d2o
1c
5.8.3
Gas dryer
Delair GDCA-NES-1212
The gas dryer from SSP-02 has a spare charge supplied by Delair
Fig. 5-17 & 5-18: desiccant charge (spare) for SSP-2 gas dryer
Utility consumption
Data for both SSP lines in steady production condition (including conveying systems):
Power consumption:
SSP-1 (motors/heaters):
SSP-2 (motors/heaters):
Compressed air:
Nitrogen:
Cooling water:
117 m /ton
3
0.0175 m /ton
Design capacity:
SSP-1: 2x stainless steel silos of 100 m capacity each total storage capacity: 140 tons
SSP-2: 3x stainless steel silos of 125 m capacity each total storage capacity: 270 tons.
3
3
Elana_Ubax_Inspection_report_July_2013_customer_version.d2o
3c
14
Elana_Ubax_Inspection_report_July_2013_customer_version.doc
It is not necessary to carry out any modification or repairing for bottle and technical yarn grades
processing except in case of further capacity increasing (plant debottlenecking).
However, some modifications in the gas purification unit (NPU) are required if new owner plans to
process recycled material (RPET).