Sei sulla pagina 1di 527

Task Force on Fault Current Limiter Testing

Frank C. Lambert
Georgia Tech - NEETRAC

&
Michael Mischa Steurer
Center for Advanced Power Systems,
Florida State University, Tallahassee, FL

Presented at the 8th EPRI Superconductivity Conference


Oak Ridge, TN, Nov 12, 2008

New IEEE Task Force


Goal
Develop a guide for testing novel FCL technologies (SC and
non-SC)
Complements activities by CIGRE WG-A3.23

Scope
Identify FCL testing requirements from a utility point of view
Identify specific testing needs regarding the different FCL
technologies (e.g. superconducting vs. power electronics)
Identify applicability of existing power equipment testing
standards
Recommend additional tests and testing procedures as needed
Identify gaps in availability of testing capabilities and recommend
power requirements for upgrading

11/12/2008

FCL_Testing_TF_EPRI-SC_Lambert_Steurer_12nov2008

New IEEE Task Force


Approach
Study and review novel fault current limiter (FCL) technologies
for medium and high voltage systems.
Map testing requirements against the needs by different FCL
technologies
Map testing requirements against existing power equipment
testing standards
Map testing requirements against available laboratory
capabilities
Coordinate with other technical committees, groups, societies
and associations as required

Status
New IEEE task force was approved by the IEEE Switchgear
Committee in October 2008
We still need participants!
First meeting possible during the Joint Technical Committee
Meetings in Atlanta (http://www.pestechnical.com)
January 12 15, 2009
Next regular meeting of the IEEE Switchgear Committee will be
in Asheville, NC, May 3 7, 2009
11/12/2008

FCL_Testing_TF_EPRI-SC_Lambert_Steurer_12nov2008

NEETRAC Fault Current Limiter Needs


Assessment Survey
Goal
Help target and direct FCL development towards applications
with the maximum potential benefit for utilities

Approach
NETRAC customer sponsored 10-page survey
Planning, Substation Engineering/Design
Operations/Maintenance
Protection & Control

Individual utility responses will be collected and aggregated by


NEETRAC
Only composite results will be distributed to sponsoring
NEETRAC members, survey participants, and CIGRE WG A3.23

Status
Revisions of the survey questions are possible until mid of
January 2009
Interested parties please contact Frank Lambert
Email
Phone
Fax
11/12/2008

frank.lambert@neetrac.gatech.edu
404-675-1855
404-675-1820
FCL_Testing_TF_EPRI-SC_Lambert_Steurer_12nov2008

Eighth Annual Superconductivity Conference


Cigre WG A3.23 Update
Ashok Sundaram
Senior Project Manager
EPRI
asundara@epri.com
(650) 855-2304
November 12th-13th, 2008
Doubletree, OakRidge, TN
Hosted by DOE and ORNL

New Cigre WG A3.23 on Application and feasibility of


fault current limiters in power systems
Met in Erlangen, Germany (near Nuremberg) hosted by Mr. Heino
Schmitt of Siemens on Sept 3rd & 4th , 2008
Twenty members selected worldwide to serve on this WG picked on a
competitive basis from a large number of applicants
Scope of the WG A3.23 is as follows:
Build on WG A3.10 and A3.16 and draw to a close A3s
investigation into FCLs
Location of FCL installation
Different type of FCLs
Experience from former and new pilot projects
Feasibility of application of conventional and novel FCLs
Acceptance issues and how to overcome them
Customer system requirements (fault level, insulation
coordination, power quality and stability)
Interactions with protection and other control and power devices
Potential economical savings (examples from utility experiences)
2008 Electric Power Research Institute, Inc. All rights reserved.

New Cigre WG A3.23 on Application and feasibility of


fault current limiters in power systems
Time Schedule 3 years
Deliverables:
Technical brochure and report in Electra
Sessions symposium papers as appropriate
Tutorial material (enhancing that available from previous WGs)
Next Meeting
Early March 2009 sponsored by Zenergy (formerly SCPower) in
South San Francisco for a 2 days followed by a field visit to SCE
to observe testing of Zenergy Superconducting FCL at the
Avanti circuit of the future.
Non members of the WG are welcome to attend and provide input
but cannot participate in voting on motions passed.

2008 Electric Power Research Institute, Inc. All rights reserved.

Reports from Cigre on Fault Current Limiters


Cigre Technical Brochure No 239 (WG A3.10) December
2003.
Fault current limiters in electrical medium and high
voltage systems
Cigre Technical Brochure No 339 (WG A3.16) February
2008
Guideline on the impacts of fault current limiting
devices on protection systems

2008 Electric Power Research Institute, Inc. All rights reserved.

2008 Electric Power Research Institute, Inc. All rights reserved.

HTS Cables
Status of Standards Work
David Lindsay
Southwire Company
EPRI HTS Conference
Oak Ridge, TN
12 Nov 2008

IEEE (www.ieee.org)

IEEE

PES Power & Energy Society

ICC Insulated Conductor Committee


C22D

C22D Superconducting Cables

Inactive past ~5 years


Re-activated in Oct 2008
Discussion Group = no formal task for
standard development at this time.
Chair = David Lindsay

Cigre (www.cigre.org)

Cigre International Council on Large


Electric Systems

Study Committee B1 Insulated Cables

TF B1.31 Testing of Superconducting Cable


Systems

Created August 2008


1 year duration
Provide terms of reference of future WG
Convenor = David Lindsay

Cigre guides for HV/EHV cable are typically used as base for
new IEC standards.

Proposal for
US Sub-Committee on
HTS Standards
From Lance Cooley
IEEE-CSC Standards Chair
And Bill Hassenzahl
Past IEEE-CSC Standards Chair

IEEE-CSC Standards
IEEE Council on Superconductivity recognizes
and supports standards activities
Hosted discussions 2004-2007 that led to new IECTC90 working group on HTS current leads
Acts as liaison between individuals, organizations
(EPRI, IEEE, NEMA, Labs, Companies), and
countries (IEC, VAMAS, CIGRE)
Request to IEEE-CSC from Japanese National
Committee for US participation in further work

Proposal: IEEE-CSC will continue support as a


liaison until a more formal organization is formed
and funding can be secured

JNC-IEC Proposal

At the Berlin IEC TC-90 meeting the JNC proposed the creation of
an ad hoc group to discuss the validity of the general requirements
of HTS (document available). The result of voting was 3
agreements(Japan, Korea and Poland) and 2 abstention (Germany
and China). So the ad hoc group became possible to start.
Professor Osamura was nominated as the Rapporteur. His
comments to LD Cooley of the IEEE-CSC were:

1) The group should be organized by the experts from USA, Germany, Poland,
China, Korea Japan and possibly others.
2) I feel this is very tough job for getting any reasonable conclusion whether its
creation is valid or not.
3) So I would like to collect comprehensively opinions from the experts and also from
people relating to SC science and technology. Please give me your opinion on this
matter. And I would like to ask you to recommend the experts from USA.

Cooley replied that we need to have general discussions in the USA


and that we would provide a formal response in December 2008.

New IEC Ad-Hoc Group


October 9, 2008
Secretary IEC/TC90
Ad-hoc Group 3: Standardization of Superconducting Wires
Task: To study standardization issues on Superconducting wires and to report a result
at the next TC90 meeting
Member
Kozo Osamura (Japan) Rapporteur
Koichi Nakao (Japan)
Jeonwook CHO (Korea)
Jacek Sosnowski (Poland)
TBD (USA) Cooley (as of 11/7/08)
TBD (China)

e-mail address
kozo_osamura@rias.or.jp
nakao@istec.or.jp
jwcho@keri.re.kr
sosnow@iel.waw.pl

Motivation
Groundwork by EPRI, IEEE-CSC, AEA
DOE and others is working towards
defining an effective organization
Activity in, and request from, Japan
requires a response at some level
HTS conductors are becoming defined;
end uses are developing; products are not
yet there --- ripe for groundwork.

Potential US Committee Members


approached by Cooley

DOE: Haught
IEEE-CSC: Cooley, Levy
EPRI: Eckroad
NIST: Goodrich
NEMA: Liebowitz
AFRL: Barnes
NRL: Gubser

NHMFL: Larbalestier
ORNL: Lee
LANL: Marken
GE: Bray
AmSC: Maguire, Fleshler
SuPwr: Xie, Martchevskii
AEA: Hassenzahl

Action items for coming year

Hold a workshop
Define an organizational structure
Prepare a Formal US response to JNC-IEC
Seek support
Assess landscape and needs

Current leads already in progress


WG1 begin work on terminology
WG2 some characterizations need standards
Activities by CIGRE, EPRI, NEMA

USA Formal Response to JNC


Details TBD
Suggest forming an ad hoc committee (following the IEC
plan) within the US with some or all of the individuals
listed above.
Suggest that the chair be from the IEEE-CSC and that
this organization act as a coordinator for activities.
During a workshop early in 2009 determine areas where
standards are needed, both now and in the future.
Address national and international issues in the
standards area and how to establish a level playing field.

An Assessment of Fault Current


Limiter Testing Requirements
Brian Marchionini &
Ndeye K. Fall
Energetics Incorporated

Dr. Michael Mischa Steurer


Florida State University

EPRI Superconductivity Conference, November 12-13, 2008

What is a FCL and How Does it Work?

Very Low Impedance

Fault

Project Purpose and Scope

Identify testing requirements for advanced electricitydelivery devices such as fault current limiters

Make an assessment of the existing capabilities of


testing facilities in the U.S. and internationally

Perform a gap analysis to determine where existing


testing capabilities and facilities fall short

The scope of the project includes solid-state and


superconducting-based fault current limiters

Focuses on projects sponsored by the U.S. Department


of Energy

Methodology
Subject
SubjectMatter
MatterExpert
ExpertInterviews
Interviews

Testing
TestingNeeds
Needs

Testing
TestingFacility
Facility
Capabilities
Capabilities

Gap
GapAnalysis
Analysis

Organizations Contacted

Electrivation

Types of Testing
Immediately
needed

Category

Description

Research and
Development
Tests

Electrical and mechanical tests performed in a laboratory and


conducted during development.

Type Tests

Performed to demonstrate the adequacy of designs and materials of a


system. Generally required when there is a significant change in
materials or the manufacturing process.

Commissioning
Tests

Tests performed to detect shipping or installation damage. Also


reveals defects in workmanship.

Factory
Production Tests

Verify that the device meets specifications before leaving the factory.

Long-Term
Prequalification
Tests

IEC definition A test made before supplying of a general


commercial basis of a system in order to satisfactory long term
performance of the complete system.

Maintenance
Tests

Field tests during the lifetime of a system to detect deterioration.

Special-Purpose
Tests

Specialized tests designed to obtain specific information.

Based on Table 3-2, on test categories for underground cable in EPRI Specifying and Testing HTS Power
Equipment (Report number TBD)

Specifications for DOEs FCL Projects


Specification

AMSC

Silicon Power

SuperPower

Zenergy Power

Design

Resistive FCL
3-phase,
transmission voltage
Low-inductance
bifilar coil switching
module technology
using 2G wire

Uses high power


semiconductors
Super-gate turn-off
thyristor (SGTO)

Resistive FCL
Matrix design
has parallel, 2G
HTS elements
and conventional
coils

DC-based iron core


One DC first-generation HTS
coil for a three-phase AC FCL
Saturable reactor-type FCL
Suitable for 2G materials,
when available

Ratings (final
design)

138 kV, 2000 A


Class (115 kV, 1200
Amps at SCE site);
3-phase

69 kV; 3,000 Amps;


3-phase

138 kV; 1200


Amps; 3-phase

138 kV; 2,000 to 4,000 Amps


steady-state; 3-phase

Fault Current
Reduction

2050% Reduction
37 % at SCE (63
kA to 40 kA)

50% reduction of an
80 kA fault

20%50%
reduction

20% to 40% reduction of a 60


kA to 80 kA fault

Cable, Transformer

Transformer,
Reactor, and Circuit
Breaker

Transformer,
Reactor, and
Circuit Breaker

Transformer

Testing
Protocol
Basis

Current Status and Future


Requirements of FCLs
Zenergy

Line-Line Voltage / kV rms

100

SuperPower
AMSC

Full
Scale

Silicon Power

Transmission
Distribution

10

Zenergy
AMSC
Silicon Power

1
SuperPower
0.1
0.1

Current
Status

Resistive HTS
Saturated Iron Core
Solid State

1
Rated Current / kA rms

10

Examples of Test Facility Capabilities


Name

Location

Insulation Test (MV) at zero


current
AC
50/60 Hz

Lightning
Impulse
1/2/50s

Current Test (kA) at


zero voltage

DC

Fault

No-load
voltage
(kV)

High-Power Test
Maximum
(Surge)
Power
Rating
(MVA)

Kind of Source(s) for the Lab

Continuous
Power
(MVA) @
nominal
voltage (kV)

KEMA

Chalfont, PA 0.55

0.80

0.10

50 for 1 s
13.8
63 for 0.5 s.

3250

N/A

KEMA

Arnhem, The 1.00


Netherlands
Vancouver, 0.80
Canada
Oak Ridge, 0.2
TN

2.60

1.00

N/A

3.00

1.00

15 @50Hz 8400
390 for
0.42 s.
17@60Hz
110 for 3 s. 13.6
1500

N/A

Short-circuit generators rated for


1,000 and 2,250 MVA
parallel operation possible
4 short-circuit generators, 2,100
MVA each
Power system grid (12,000 MVA)

0.8

0.3

50

N/A

N/A

DC and AC power supplies

0.025

4 (100 for
~1 sec. with
upgrade)

1400

5 @ 13.4
400 for 1 s

13.4-kV power grid; 1400 MVA


generator

1000 MVA at
18 kV

Short-circuit generator rated 4800


MVA at 18 kV

N/A

Power Tech
ORNL
LANL

Los Alamos, 0.138 (with N/A


NM
upgrade)

KERI

Changwon,
Korea

400 kV

NEETRAC

Atlanta, GA

1.00

Florida State
UniversityCAPS

Tallahassee, 0.1
FL

0.3 (0.6
with
upgrade)

4200 kV, 50 400 kV, 154 kA @ 24, 48, 72, 4800 MVA
s
10 mA 50/60 Hz at 96 kV
18 kV
2.20
1.00
25 for 2 s
.12
N/A
0.14

0.14

84
13
7
1.7
13
4.8 (DC)

0.385
0.48
4.16
4.16
0.48
1.15 (DC)

130

7.5 @ 4.16
1.5 @ 0.48

2.2 MV, 220 kJ Impulse generator


1MV Cascade Transformer
60 Hz power system grid fed from
12.47 kV

N/A

6.2 @ 4.16
1.5 @ 0.48

Variable frequency and voltage


converter

Testing Facility Gaps

Voltage across FCL (kV)

Source Capacity KEMA Holland


Source Capacity PowerTech
Source Capacity KEMA PA
Source Capacity KEMA Holland with Ideal 4x Transformer

80

Silicon Power 80 kA Prospective Fault with 25% reduction


Silicon Power 80 kA Prospective Fault with 50% reduction
Zenergy 80 kA Prospective Fault with 25% reduction

60

Zenergy 80 kA Prospective Fault with 50% reduction


SuperPower 90kA Prospective Fault with 25% reduction
SuperPower 90kA Prospective Fault with 50% reduction

40
20
0
0

10

20

30

40

50

60

Limited Current (kA)

70

80

90

100

Major Findings Part 1

T&D equipment testing facilities can provide voltage and


current to adequately test FCLs at the distribution level
There is no place that has the capabilities to test FCLs at
transmission-level current and voltage levels
simultaneously
While there is a need to conduct high voltage-current
tests, synthetic tests, similar to the ones used for circuit
breakers, may be sufficient for certain tests
There are a number of experts who
believe advanced modeling and
simulation may possibly substitute
for certain tests

Zenergys FCL Device

Major Findings Part 2

Commercial testing facilities are not always conducive for


advanced design and prototype testing for R&D projects

Commercial T&D equipment testing facilities tend to be


costly, busy, and difficult to schedule

There are approximately 100 testing facilities around the


world and these are equipped and managed
to conduct routine tests of existing or
market-ready devices to meet known
standards and protocols

AMSCs FCL module testing

Major Findings Part 3

Today there are no common guidelines for testing


prototype high-temperature superconducting (HTS) and
solid-state FCLs and for integrating these devices with
the electric system
Testing procedures have been and will continue to be
developed by FCL device manufacturers and their utility
R&D partners and will vary depending on the design of
the equipment and the application
This lack of standards complicates the testing process
as each trip to the testing facility has unique
requirements, protocols, and procedures
The existence of standards could help expedite and
accelerate the testing process

Conclusions

There is a need for testing facilities that have the flexibility


to respond to the special requirements of R&D projects
Given the unique capabilities of fault current limiters there
is an expectation that utilities will allow prototype FCLs to
be installed and tested on their own systems, before they
have been simultaneously tested for high current and
high voltage
There is a need to continue the discussion
on FCL testing recommendations

SuperPowers FCL module testing

Questions?

Brian Marchionini
bmarchionini@energetics.com
202-406-4109
Michael Mischa Steurer
steurer@caps.fsu.edu
850-644-1629

Calculating required voltage

System impedance w/o FCL (1)= Single


phase voltage/Fault current
Required FCL impedance (2)= Single
phase voltage/Limited fault current
Required voltage drop = (1-2) X
Reduced fault current

Development of Test Protocol


for 15kV Class Solid-State
Fault Current Limiter

Ashok Sundaram
EPRI
asundara@epri.com
(650) 855-2304

Mahesh Gandhi
Silicon Power Corp.
mahesh_gandhi@siliconpower.com
(484) 913-1520

9:30AM 10:00AM
SSCL Program Overview

Ashok Sundaram

SSCL Test Protocol

Mahesh Gandhi

SSCL design
SSCL field test circuits
SSCL test protocol
Performance Verification testing at KEMA
Pre-connection test (dielectric, partial discharge, etc.)
Field operations testing (Steady-state test & Transient performance)

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

EPRIs Smart Grid


Power-electronic based Technologies
SOLID-STATE
BREAKER

SENSITIVE
LOAD

COMPENSATED
VOLTAGE, POWER FACTOR
HARMONICS,

DSTATCOM

SSCL
REDUCED
SAGS, TRANSIENTS,
HARMONICS

ENERGY
STORAGE

DYNAMIC
NON-LINEAR
LOAD

DVR
SENSITIVE
LOAD

ENERGY
STORAGE

UNINTERRUPTED
SUPPLY

SSTS
CRITICAL
LOAD
IUT
Silicon Power Corporation Proprietary

RESIDENTIAL
LOAD
2007 Electric Power Research Institute, Inc. All rights reserved.

Fault Current Management


Growth in the generation of electrical energy and an increased
interconnection of the networks and distributed generation leads to
higher fault currents
Higher fault causes more stress on the system reducing the life of
critical components such as transformers and has adverse impacts
on grounding.
The growth in capacity requires replacing existing circuit breakers
with higher fault current ratings. Major cost impact and down time.

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

Pat Duggan - ConEdison


Fault Current Limiting functionality is a critical enabler for open
access for new transmission and generation, and more cost effective
infrastructure upgrades and replacements. In addition fault current
limiters can mitigate recovery time of superconducting cables and
give selected DGs an advanced option to serve peak loads after
external faults.

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

FCL Technology Taxonomy


New terminology as defined in previous EPRI FCL study now adopted by CIGRE WGa3.16
Permanent impedance increase
during nominal and fault conditions

Condition based impedance increase


Small impedance at nominal load
fast increase of impedance at fault

Old term:
passive
Splitting into
sub grids
Introducing a
higher voltage
range
Splitting of
bus bars

Topological
measures

High
impedance
transformers
Current
limiting
reactors

Apparatus
measures

Old term:
active
Fuse based devices
(< 36 kV)
Stand alone HV fuse
(< 1 kA)
Sequential Commutating Current
Limiters (< 5 kA)
tripping

Topological
measures

Silicon Power Corporation Proprietary

Superconductors
Semiconductors
Hybrid systems

Apparatus
measures

2007 Electric Power Research Institute, Inc. All rights reserved.

novel concepts

69 kV SSCL EPRI / DOE


Outline of 69kV, 1000A, 1Ph Unit
SSFCL looks like a Transformer
Tank Size - 12h x 12w x
12d
OFAF Cooling System
Size - 10h x 5w x 7d
Total weight 80,000 lbs
Local / Remote Control

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

15 kV 1200A SSCL
CEC/SCE/EPRI Project

Silicon Power Corporation Proprietary

Voltage Class

15 kV

Number of phases

Frequency

60 HZ

Current rating

1200 A

Fault current

23 kA

Let-thru current

9 kA

Let-thru current duration

30 cycles

BIL rating

110 kV

Size

12 H 11 W 12D

Weight

40 000 lbs

2007 Electric Power Research Institute, Inc. All rights reserved.

SSCL Program Team


DOE / Washington HQ

- Gil Bindewald

DOE / Chicago

- Stephen Waslo

EPRI Project manager

- Ashok Sundaram

Villanova University

- Dr. Amy Fleischer

SSCL Developer

- Silicon Power Corp.

SSCL Commercializer

- Howard Industries

Technical Consultant

- Dr. Laszlo Guygyi

Utility Advisors

- Pat Duggan (ConEd)


- Pat Dilillo (ConEd)
- Sanjay Bose (ConEd)

EPRI P37D Task Force on Advanced Solid-State Substations Techniques


Chair: Jim Houston Alabama Power Company

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

Current Limiting Effect

2007 R&D100 Award Winner


SGTO Device
- Performance Driver

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

10

Limiting Inductor

SSCL Concept
Design Features:
No cryogenics
Immediate recovery
Fail safe
No current distortions
SuperGTO
Lower losses
Reduced Overall size and
weight
Modular design expandable to
desired Voltage & Current Ratings

Main
SGTO
switch

iLINE
Line
reactance

Circuit
Breaker

Auxiliary SGTO
switch

Commutation
Capacitor

Commutation
Inductor

Varistor

Operation:
Normally the continuous current flows thru the fast speed switch (Main SGTO).
Once the fault is sensed by high-speed sensor and declared by FPGA board, the current
is commutated to Limiting Inductor (CLR).
Introduction of CLR will limit the current to the level below the rating of the downstream
breaker. The downstream breaker will trip and open the ckt within 30 cycles.
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

11

SSCL Architecture

VLC Voltage Level Controller

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

12

SSCL Design

SGTO Module 800A 5kV

Standard Building Block


44L x 13w x 15h, 100 lbs

Power Stack
90h x 66w x 46d
1800 lbs

Silicon Power Corporation Proprietary

15kV 1200A Final Assembly


11h x 12w x 12d, 40,000 lbs
including Oil

2007 Electric Power Research Institute, Inc. All rights reserved.

13

SSCL Accessories

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

14

SSCL Ratings

Parameters
Rated Maximum Voltage, kV rms
Rated Continuous Current, Ampere rms
Rated Power Frequency
Available fault current, kA rms
Rated Let-thru Current, kA rms
Rated Let-thru Current Duration, cycles
Rated Dielectric
Power Frequency 1 min dry kV, rms
Impulse, Full-wave Withstand, kV peak
Impulse, Chopped-wave Withstand, kV peak
Ambient Temp, Degree C
Rated Control Power, V DC or AC, 60Hz, 1ph
SSCL Power Efficiency
Line Voltage drop
Line Harmonic Distortion
Partial discharge
Audible sound test

Silicon Power Corporation Proprietary

69kV
72.5
1000
60
80
40
30
160
350
452
40 / 50
125 DC
99.75%
0.3%
None
TBD
TBD

15kV
15.5
1200
60
23
9
30

4000
11
5.5

50
110
142
120 AC

125 DC

100 pC/19.5kV
55dBA/20
58dBA/6

2007 Electric Power Research Institute, Inc. All rights reserved.

15

SSCL Field Test Circuits

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

16

Inherently Fault Current Limiting Cable +


Stand Alone Fault Current Limiter Demonstration
Substation
Hi

Fault Current
Limiter

et
e
r
St

gh
wa
y

Refrigeration

Generating
Station

Silicon Power Corporation Proprietary

Substation (new)

2007 Electric Power Research Institute, Inc. All rights reserved.

17

SSCL Application In ConEd


SSFCL in two
locations

East 75th Street Substation


CBT1SE

To
74440

T1
CBT1E

CBT2SE

To
74441

T2
CBT2E

CBT3SE

To
74442

T3
CBT3E
SSFCL

To
74443

CBT4SE

T4
CBT4E
SSFCL

CBT1W

CBT2W

CBT3W

CBT4W

CBT1SW

CBT2SW

CBT3SW

CBT4SW

York Substation
CBT1SE

CBT2SE

CBT3SE
HTS
Cable

To
74416

T1
CBT1E

To
74417

T2
CBT2E

To
74485

T3
CBT3E

CBT1W

CBT2W

CBT3W

CBT1SW

CBT2SW

CBT3SW
F8

ConEd 138 kV
system
equivalent from
PSS/E data base

One fault location


Most severe case
Silicon Power Corporation Proprietary

HTS cable PI circuit


equivalent from
Southwire data sheet

2007 Electric Power Research Institute, Inc. All rights reserved.

18

SCEs Avanti circuit a.k.a circuit of the future


Shandin
Substation
Fiber Optic
Duct temp
Monitoring
System

SCADA System
Gateway

Northpark
12KV

Solid State
Fault Current
Limiter

Circuit
Tie
Switch

Comm.

Tie
RCS

Fiber

Typ. Load
Transformer

SEL 2100
Logic Processor

Distributed
Generation

Tie
RCS

USAT

RCI
1

Multi-Stage Capacitor
Banks

VFI/Remote
Controlled
Switch

Silicon Power Corporation Proprietary

RAR

Sweetwater
12KV

Circuit
Tie
Switch

Secondary
Network
RCI
2
2007 Electric Power Research Institute, Inc. All rights reserved.

19

Tie
RCS

RCI
3

15kV 1200A SSCL


Test Protocol

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

20

Controlled Testing at KEMA Power Lab


Dielectric Test
Power frequency Voltage Withstand Test
Full-wave lightning impulse withstand voltage tests
Chopped wave lightning impulse withstand voltage tests
Insulation test by power factor measurement (Dobble test)
Insulation test by resistance measurement (Megger test)
Partial Discharge Test
CLR resistance & impedance measurement
Current Limiting Test
Efficiency (power loss) Test (Steady state Operation test)
Continuous Current Carrying Test/ Temperature Test (Steady state
Operations test)
Audible sound test
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

21

Tests at Southern California Edison


Tests at SSID facility:
Insulation test by power factor measurement (Dobble test)
Insulation test by resistance measurement (Megger test)
Partial Discharge test
Tests at Shandin Sub-station:
Pre-connection testing
Visual Inspection
Tank Pressure test
Insulation/Dielectric tests
Insulation test by power factor measurement (Dobble test)
Insulation test by resistance measurement (Megger test)
Field evaluation testing
Steady-State and Transient (at fault) performances
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

22

Power frequency Voltage withstand Test

Tests SSCL dielectric integrity against the continuous operating


voltages.

60Hz sine-wave voltage of rated amplitude is applied for 60seconds


from SSCL line terminals to ground. Leakage current is monitored

Wet test procedure - The wet tests are made only on outdoor SSCL
or on external components such as bushings, in accordance with the
procedure described in IEEE Std C57.19.00-1991.
Note: For those bushings, where their voltage distribution is negligibly
influenced by their surroundings, and which have been tested separately as
individual bushings in accordance with IEEE Std C57.19.00-1991, the tests
need not be repeated on the assembled SSCL.

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

23

Power Frequency Voltage Withstand Test schematic

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

24

Full-wave Impulse withstand Voltage Test

Tests to verify their ability to withstand their rated full-wave lightning


impulse withstand voltages.

Both positive and negative, lightning impulse voltages having a peak


value equal or greater than the rated full-wave lightning impulse
withstand voltage shall be applied between the terminals of the SSCL
and the ground / case.

Waveform for lightning impulse tests per IEEE Std 4

Positive Impulse

Silicon Power Corporation Proprietary

Negative Impulse

2007 Electric Power Research Institute, Inc. All rights reserved.

25

Full Wave Impulse Test Schematic

AC
Source

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

26

Chopped-wave impulse
withstand voltage Test
To verify their ability to withstand their
assigned rated chopped wave lightning
impulse withstand voltage.
The voltage shall be applied to the
terminals of the SSCL, without causing
damage or producing a flashover, following
the same procedure as for full-wave
impulse test.
The waveform and application of the
chopped wave test voltage, and the type of
rod gap and its location, shall be as
described in IEEE Std 4-1978
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

27

Schematic for Chopped Wave Impulse Test

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

28

Fault Current Limiting tests


Objective: The current-limiting test of the SSCL is to demonstrate the

current-limiting performance and the related capabilities.


Test set up:
Adjust the source impedance and voltage such that it provides
Available fault current at power factor of not to exceed 5.9%
lagging, equivalent to X/R = 17 at 60 Hz (11kA @ 600V for AMSC
15kV SSCL)
Operating condition:
Run SSCL at continuous current operation and limit current at
fault
Close SSCL on fault and limit the let-thru current
Test Sequence
Pilot shot at 25% of rated let-thru fault current
Intermediate shot at 40-50% 25% of rated let-thru fault current
Final shots at 100% of rated let-thru fault current
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

29

Efficiency tests
Objective: The of the test is to evaluate the SSCL performance for power

losses at various current levels.


Test conditions
Input At the lower end of operating voltage range and higher end of
input frequency.
Output / load At 25%/50%/75% and rated load current, and 0.85
lagging power factor.

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

30

Continuous Current / Temp Rise tests


Test conditions
Ambient Room temp.
Output 3ph bolted short.
Input Voltage Variable low voltage enough to provide 25%
and gradual rise to 50%-75% and finally to rated load current.
Temp. Monitoring
Built in Heatsink temp. sensors
Cooling liquid temp (Top, Mid, and lower level)
Tank (top, bottom, middle on both sides)

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

31

Pre-installation test
Visual Inspection
SSCL once received at site an external inspection of the SSCL tank and
fittings will be done which will include the following points:
1. Is there any indication of external damage?
2. Is the paint finish damaged?
3. Are the attached fittings loose or damaged?
4. Is there evidence of fluid leakage on or around the tank coolers?
5. Are any of the bushings broken or damaged?
6. Is there any visible damage to the parts or packaging which shipped
separately from the SSCL?
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

32

Pre-installation test
Tank Pressure
The tank pressure may be positive or negative when received, depending
on liquid temperature. In some cases, the vacuum pressure gauge may read
zero, which could indicate a tank leak. In such cases, it is recommended to
contact manufacturer before installation.

Dielectric tests
Dielectric tests are the group of tests during which the SSCL will be
subjected to higher voltage levels and therefore higher voltage stresses than
would normally be experienced in service. The purpose is to confirm that the
design, manufacture and processing of the SSCL and insulation structure and
materials are adequate to provide many years of satisfactory life.
Recommended test is power frequency voltage withstand at reduced level
to 75% of rating.
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

33

Field Performance Evaluation


Steady-state and Transient Performance
Objective: The objective of this test is evaluate the SSCL

performance in the field under Steady-State and transient condition


of the system in which the SSCL is connected.
Test Monitoring:
Steady state voltage and current sensors.
High speed voltage and current sensors.
Power Monitor and data recorder
Temp. and Pressure Sensors

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

34

Field Performance Evaluation


BYPASS SWITCH

SCE

SCE
15kV
LINE

Line

SSCL

Breaker

15kV
No-load DISC.

LINE

SWITCH

Sequence of Operation:
Turn-ON: Close Bypass Switch. Close Load Disc Switch. Close Line
Breaker. Open Bypass switch. Turn-on SSCL.
Turn-OFF: Turn-off SSCL. Close Bypass switch. Open Line Breaker.
Open Load Disc Switch.
Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

35

Field Performance Evaluation

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

36

Real time monitoring and analysis


Temp. Alarm

Pressure alarm
Power monitoring - V, I, kVA, KVAR
Gas relay alarm
Fault data records
SITE REQUIREMENT:
AC Aux Power
Internet Access
Working Space

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

37

Thank you

Silicon Power Corporation Proprietary

2007 Electric Power Research Institute, Inc. All rights reserved.

38

Status of High Temperature Superconductor Cable


and Fault Current Limiter Projects at
American Superconductor
J. F. Maguire and J. Yuan

EPRI Superconductivity Conference


Oak Ridge, TN
November 12-13, 2008

Agenda

HTS Projects at AMSC


HTS Project Objectives and Milestones
Development Results of HTS Projects
Conclusions

HTS Projects at AMSC

Cable Projects
- Transmission Voltage
LIPA 1 (BSCCO Wires)
LIPA 2 (YBCO Wires)

- Distribution Voltage
Project Hydra Consolidated Edison

Fault Current Limiter Project


- Transmission Voltage
Southern California Edison

Projects Objectives
LIPA 1

Demonstrate a transmission voltage level HTS cable and


outdoor terminations in an operational power transmission
grid

LIPA 2

Demonstrate a 2G HTS transmission cable and a cable


joint in an operational power transmission grid.
Demonstrate an FCL cable technology and repairable
cryostat. Demonstrate modular refrigeration system.

Hydra
Project

Demonstrate HTS fault current limiting link between


substations. Demonstrate feasibility of an underground
installation of a fault current limiting HTS system in
population condensed urban area

FCL

Demonstrate standalone HTS fault current limiter based


on 2G wires in an operational power transmission grid.
Introduce HV into FCL

Projects Specifications
LIPA 1

600m long using BSCCO wires


138kV/2400A, ~ 576 MVA

LIPA 2

Fault Current 51kA @ 12 line cycle (200ms)


600m long using YBCO wires
138kV/2400A, ~ 576 MVA
Fault Current 51kA @ 12 line cycle (200ms)

Hydra
Project

320m long using YBCO wires


13.8kV/4000A, ~ 96 MVA
Fault Current 40kA @ 4 line cycle (67ms)

FCL

138kV/ 1200A
Fault Current 63kA @ 4 line cycle (67ms)
Fault Current reduction rate 36% (limit to 40kA)

Projects Timelines
Year

2003

2004

2005

2006

LIPA 1

LIPA 2

HYDRA

FCL

2007

2008

2009

2010

2011

2012

Project Partners

OAK RIDGE NATIONAL LABORATORY


U. S. DEPARTMENT OF ENERGY

Development Results of HTS Projects


LIPA 1
Transmission Voltage Cable Project
Long Island Power Authority
New York

LIPA 1 Project Team

Installation Site
Port
Jefferson

Shoreham

Wading
River

Miller
Place
Terryville

Centereach

Superconductor

Holbrook Substation

10

Major Challenges of LIPA 1 Project


System Design
-

138 kV, 2,400 amp operation


Survive 51 kA @ 200 ms fault
Manage Through-Faults
Manage larger cold contraction

HTS Conductor Design


- Handle real-world cabling stress using standard manufacturing
equipment

Termination Design
- Qualify to 138 kV operation, 650 kV BIL
- Safely manage voltage breakdown
- Manage results from loss of cryostat vacuum
Worlds First Installation of a Transmission Voltage HTS Cable

11

LIPA 1 HTS Cable System

Return

Supply

12

Redundant
Cooling & Control

Bulk LN2
Storage

Cold Termination

Heat

Power

SCADA

HV Termination

LIPA 1 HTS Cable Design


Outer Cable Sheath
LN2 Coolant

HTS Tape

Former

High Voltage Dielectric


HTS-Shield
Outer Cryostat
Wall

13

Copper Shield
Stabilization
Inner Cryostat Wall

Prototype Testing
A test program has been
defined together with the
DOE review team based
on existing standards

Tests included
- High voltage dielectric
tests
- High current tests
- Hydraulic tests
- Load cycles
- Loss measurements

Type test performed prior starting manufacturing

14

Pre-Construction

15

Installation - Terminations
Terminations were
installed with the cable
phase in place

No issues identified
during termination work

16

Installation - Terminations
Terminations were
installed with the cable
phase in place

No issues identified
during termination work

17

Installation - Cable Pulling


Cable pulling operation was tested using a 70
meter long test setup to verify method and
estimate force

Cable puling on site was achieved without


issues

Vacuum level of cryostat was checked before


and after pull

Pulling force was recorded and compared to


estimated values
Cable Pulling Force

10000

20000
Phase 1

18000

theoritical curve total (coef f


0,24)
therotical (rolls)

8000

Phase 2

16000

theoritical (cable in PE pipe)

7000

Phase 3

Force (N)

14000
Force [N]

9000

12000
10000
8000

6000
5000
4000
3000

6000

2000

4000

1000

2000

0
0

100

200

300

400

500

600

700

Distance [m]

10 15 20 25 30 35 40 45 50 55 60 65 70 75 80
HTS cable distance in the PE pipe (m)

18

Refrigeration substation

19

Cable cool down


LIPA Cooldown Termination Temperature
PT 101

PT 601

model

model

300

Predicted

275
250

Temperature (K)

225
200
175
150
125

Actual

100
75
50
0

48

96

144
Time (hours)

20

192

240

Cable Energization
AC-High Voltage test
completed successfully
- 1.5 Uo applied at each phase
for one hour
- PD measurement completed
No partial discharge detected

24 hour dielectric soak test


completed successfully
- Cable connected to LIPA grid
at one end

Cable connection at both ends


completed on April 22nd
- Operation with parallel overhead line for 24 hours
- Operation without parallel path Cable Commissioning Successfully Completed
afterwards

21

Cable Operation - Measurements


The cable system is monitored
regarding a variety of parameters to
- Ensure safe operation
- Gain measurement data to
compare with design results
Measurement data analyzed so far:
- Cable cool down behavior
- Cable cryostat thermal loss
- Nitrogen pressure drop
- Temperature increase due to
dielectric loss
- Temperature increase due to ACloss
- Thermal behavior of termination
(bushing)
- Cable system time constants
Cable System Measurements in very good Agreement with Design Results

22

Steady State Operation (I)


90

400

80

350

70

300
Phase Current (A)

Total MVA

60
50
40
30

Phase R
Phase S
Phase T

250
200
150
100

20
50

10
0
7/2/08 12:00 AM

7/2/08 12:00 PM

0
7/2/08
12:00 AM
7/3/08 12:00 AM

23

7/2/08 12:00 PM

7/3/08 12:00 AM

Steady State Operation (II)

73

15.0

700
Inlet Pressure

72

14.5

600

LN2 Pressure (bara)

Temperature (K)

71

70

69

14.0

500
Flow Rate

13.5

400

13.0

300

68
Inlet Temperature

66
7/2/08 12:00 AM

Return Pressure

12.5

67

7/2/08 12:00 PM

7/3/08 12:00 AM

24

12.0
7/2/08 12:00 AM

7/2/08 12:00 PM

LN2 Mass Flow Rate (g/s)

Return Temperature

200

100
7/3/08 12:00 AM

Sound Issues
Several questions regarding
noise at the site (during
operation)

Conducted sound study


- 35 db at ambient
- Source: refrigerator building
- 50 db with refrigerator running

Acoustical Louvers
- Lowered sound signature
during operation to 38 db
(modeled)

25

Sound & Site Mitigation

26

Development Results of HTS Projects


LIPA 2
Transmission Voltage Cable Project
Long Island Power Authority
New York

27

LIPA 2 Project Team

28

Major Challenges of LIPA II Project


System Design
- Integrate single phase fault current limiting phase into the existing
system

2G HTS Conductor Design


- Address real-world cabling stress using standard manufacturing
equipment

Cable Design
- Demonstrate field joint
- Demonstrate field reparable cryostat

Develop a 20 KW modular high efficiency refrigerator

29

LIPA II HTS Cable System

Existing HV Termination
Existing Cold Termination

Return

Supply

30

Redundant
Cooling & Control

Bulk LN2
Storage

Field Joint

Heat

Power

SCADA

Replacement 2G Phase

LIPA 2 HTS Cable Concept


Inner Cryostat Wall

LN2 Coolant

Cable conductor has to be


redesigned for thermal contraction
(and current limiting)

HTS-Shield

Outer Cryostat Wall

31

Copper Shield
High Voltage Dielectric
Stabilization to be
removed

LIPA 2 Wire
YBCO Coated Tapes
- Lower Tc, higher resistance substrate: Can be made to
be current-limiting
- Different dimensions and physical properties:

YBCO coated onto one side of buffered Ni-W


substrate
Brass laminated onto both sides
~ 0.3 mm thick, splices even thicker

Splices are being developed

32

Cable design and manufacturing process


Dummy cable approach to develop the
cable design
- Develop cable design based on modified
modeling tools
- Manufacturing of short samples

Measurement of electrical
characteristics (AC-loss)
- Manufacturing trials using industrial
machine adapted to HTS tape stranding
- Testing of samples in terms of mechanical
and high voltage aspects

Status
- Two different design options considered
- First manufacturing trials (dummy cables)
focus on one of the two designs

33

Dummy cable 01 - Current Status


Hollow flexible former
- Dummy cable is being produced now
- Superior concept

Only small force due to thermal contraction


Small cross-section, stainless steel:
High resistance, good for current limitation
- Requires some effort due to flexibility of former in the
machine
- Preferred design

34

High Voltage Termination


LIPA 1 terminations design is kept for this
project but adapted for the new YBCO HTS
cable:
- Removal of the cable termination shrinkage
management (blocking of the cable)
- Adaptation of the cable connection for 2G wires

Status:
- Updating of the cable connection is in progress with different new brazing alloys
studied
- Continuation of the development required now some LIPA 2 cable samples in order
to achieved some connection and mechanical tests and improved the components

35

High Voltage Termination


LIPA 1 terminations design is kept for this
project but adapted for the new YBCO HTS
cable:
- Removal of the cable termination shrinkage
management (blocking of the cable)
- Adaptation of the cable connection for 2G wires

Status:
- Updating of the cable connection is in progress with different new brazing alloys
studied
- Continuation of the development required now some LIPA 2 cable samples in order
to achieved some connection and mechanical tests and improved the components

36

Superconducting Cable Joint


HTS cable joint
- Develop and test a straight joint to connect
superconducting cables

Design of conductor connection


Design of joint dielectric insulation
Design of screen connection
Design of joint cryostat

Cryostat for subscale test


Cryostat for on site installation
- Full prototype test of cable joint in the laboratory
- Installation of a single cable joint on site

37

Status: High Voltage Joint


A first joint design has been set up considering two main physical constraints
- Thermal: no overheating in the central cable connection with nominal current (not in
direct contact with liquid nitrogen)

- Electrical: E field management in an optimum dimension of the joint

Prototypes for testing assembly procedures successfully prepared and tested


with nominal current in LN2 (temperature measurement)

38

Status: High Voltage Joint


The first design of the joint has been assembled in NEXANS Hanover testing
laboratory in June/July 2008
First results on this component achieved in September 2008
AC withstand test 190 kV / 30 min
Lightning impulse test 650 kV (+/-)
Partial discharge measurement

39

Joint in the Test Field


Inlet Termination
(Connection to the
Transformer)
Outlet Termination
with the Joint inside

25 m Coated Conductor Cable

40

Field Repairable Cryostat


Field repairable cryostat
- Perform optimization study to determine
cryostat vacuum barrier distance based on
- Develop and demonstrate vacuum barrier
manufacturing techniques
- Develop improved thermal insulation system to
perform under repair vacuum conditions
- Demonstrate field repair in laboratory

Status of work
- Vacuum barrier manufacturing techniques

Various designs developed


- Improved thermal insulation system

Investigation of vacuuming behavior of


alternative thermal insulation materials

41

Modular Refrigeration System Objective


Develop a new Refrigeration technology dedicated to long-length HTS
cable with the main characteristics below

- Low operation cost


High efficiency
Low maintenance

- Low refrigerator cost


Simple design
Modular design

- High reliability
- Long lifetime

42

Refrigeration System Objective


Develop a new Refrigeration technology dedicated to long-length HTS cable
with the main characteristics below
Liquid nitrogen delivered

72 K

LN2 pressure drop

3 bars

Cold power

120 kW total - 20 kW Modules

Efficiency

> 20% Carnot

Cooling

Air cooling (-20 / 50C)

Manufacturing cost target

<$100/cold W series production

43

Refrigerator Development Status (Phase 1)


Progress made thus far
- Thermodynamic analyses of reverse Turbo-Brayton cycle

Completed

- Cooler configuration scenarios

Identified

- Numeric modeling of cooler configuration and


Refrigeration sub components

Completed

- Model validation

Completed

- Creation of a numerical model for each cooler configuration

Completed

- Optimization of each cooler configuration

Underway

44

Development Results of HTS Projects


Project Hydra
Distribution Voltage Cable Project
Consolidated Edison
New York City

45

Team Roles and Responsibilities


DHS
S&T Division

AMSC
Prime Contractor
AMSC

ORNL

Southwire

Con Edison

System Design

Utility Requirements

Wire Development

Project Oversight

Wire Manufacturing

HTS FCL Cable


System Site

Cable and
Accessory Design
Cable Manufacturing
Cable and
Accessory
Installation

Project Management
Technical Oversight

Altran Solutions

System Hardware
Development

Air Liquide

46

50m Prototype
Cable Test Site
Technical Support

Installation Site

Worlds First FCL Distribution Cable to be Installed in Operating Grid

47

Program Structure
DHS/ HYDRA

Currently Executing
Planning

Phase 1
System
Development

Phase 1A
Fault Current Limiting
Cable technology

Phase 2
System Installation

Phase 1B
Stand-Alone Fault Current
Limiting Technology

48

ORNL
50 Meter Test and
Technical Support

HYDRA HTS Cable System


Heat

Supply

Return

HTS Cable

Return Line

49

Refrigerator

Power

Secure Super Grids Technology


Substation #1

Substation #2

138kV Transmission Bus

138kV Transmission Bus

Fast Switch
(Circuit Breaker)

Reactor

HTS Fault-Current Limiting Cable

Conventional Copper Cable

13.8kV Distribution Bus

13.8kV Distribution Bus

Note:
Red breakers are Closed
Green breaker is Open
To Loads

To Loads

50

Cable Design- TriaxTM by Southwire


HTS Layers

Cryostat

Hollow Former

Dielectric

51

Shield

3 m Cable FCL Tests


The prospective fault current of 60 kA was reduced to 44 kA on the
first cycle to < 30 kA at the end of the 140 ms duration fault

A perspective 140 ms fault current of 44 kA was reduced to 29 kA


The voltage developed due to the heating was 8-11 V/m over the 140
ms duration fault

This was comparable to the design fault of 300-m cable which results
in ~ 10 V/m

Measured temperature increase to 85-95 K


Re-cooling time to 77 K is 9 min
No change in temperature measured after a 9.1kA, 270ms through
fault test

No change in temperature or voltage after a 2000 ms, 7.2kA overload


test (1.8X)
52

3m Cable FCL Tests

53

3 m Cable FCL Tests

54

Refrigerator Requirements
Refrigeration Cycle chosen is the Reverse-Brayton
- Best suited technology for high power applications (> 6 kW)
- Best return on specific efficiency (We/Wc) vs. capital cost

Flexibility Requirement:
- 80% of time at 50% heat load on HTS cable

Reliability
- Redundancy accomplished at component level: compressors,
pumps, expanders, electronics, instrumentation
- No 1st order single point of failure allowed

Capacity Margin
- Current design has 50% safety margin to the expected losses

55

Reverse Brayton-Cycle Hardware


- Estimated foot print size & weight
13 m x 7 m ( 42 x 25 ) + roof for cooling water exchanger
~ 24 000 kg ( 53 000 lbs ) empty
Fits within available space

56

Development Results of HTS Projects


FCL Project
Transmission Voltage FCL Project
Southern California Edison
California

57

Team Roles and Responsibilities


DOE
SPE - SCE
AMSC
Prime Contractor

AMSC
System Design
Wire Development
Wire Manufacturing
Project Management

Siemens

Nexans

Utility Requirements

FCL Module and


Accessory Design

HV Termination

Project Oversight

FCL Manufacturing

HTS FCL
System Site

FCL Module and


Accessory
Installation

SCE

Technical Oversight
System Hardware
Development

Air Liquide

58

HV Consulting

SuperLimiterTM Demonstration Site


Selection criteria

Riverside

- Voltage
- Transmission planning
- Civil engineering

Valley Substation selected

Valley
Substation

Located near Riverside, CA in a


desert climate

Analysis used to select bus tie


application

Significant load growth planned


over the next 10 years
- Tapped external reactor
enables device to easily adapt
The Valley Substation is selected

59

SCE Profile
50,000 Mile2 Service Territory
120 years of service
$17 Billion T&D Assets

Distribution
85,000 Circuit Miles
690,000 Transformers

Customers
4.7 Million Meters
13 Million
Customers
22,889 MW Load

Transmission
12,600 Circuit Miles
4,200 Transformers

SCE is one of the largest utilities in the United States

60

SuperLimiterTM Southern California Edison


SCE is investing in the future
- > $3 billion invested in T&D over the last five years
- $11 billion planned infrastructure investments over the
next decade.

SCE has considerable experience with


superconducting Fault Current Limiters
- Since 1993 in DOE-SPI, tested a 15kV FCL in 1999
- SCE role in this program is
Specifying requirements
Providing the prototype operation site

138 kV Transmission Voltage level FCL addresses


- Elimination of CB and other equip. replacement
- Enhanced reliability, shorter customer outages
- More stable, higher-quality electricity supply
- A self-healing grid

July 1999: FCL at a Southern California


Edison substation

SCE has unique experience with HTS FCL technology and this program extends
this to transmission voltage levels

61

SuperLimiterTM Major Elements


Cryostat sized for
modular expansion

Valley
Substation
138kV termination in
operation at LIPA site
Insulation
Stainless Strip
HTS Film
NiW Strip
Solder

Cooling System Similar


to Navy Motor Program
N+1 Redundancy

Bifilar 2.2 MVA medium voltage


module tested Jan. 2007

1.2 cm insulated HTS tape


based on standard insert

Design based on validated components is designed for modular expansion

62

FCL Operating Principle


During fault
conditions,
superconductor
becomes resistive
and with reactor,
limits current

Supply Bus

Normal State
Resistance

Virtual Switch
Superconductor

Under normal
conditions, power
flows through
superconductor with
virtually no impedance
and system is
Physical Switch
electrically invisible
Shortly after fault
clears, power resumes
flow through
superconductor

Reactor
Physical
switch opens
to protect
FCL system;
reactor
maintains
current

FCL system operation is based on simple operating principles

63

Load Bus

Basic Specifications
Requirement

Prototype
System

Production
Units

Nominal Voltage

115kV rms

115-138kV

Insulation Class

138kV

138kV

Reactor
Sized to Limiting Requirements

Load
Opening Switch

Nominal Current

1,200A

>2,000A

Maximum Site
Unlimited Fault
Current

63kA

>80kA

Site Limited
Current

40kA

Source

Switch
Control

FCL Vessel
Assembly

As required
by customer
Refrigeration
System

Protection and
DAQ System

Trip Current

1.6pu

As required
by customer

Power

Team has approved a working specification for system

64

Heat

SuperLimiterTM Operating Conditions


Constraints
-No bubbles around the bottom of bushing sub-cooled LN2
-Termination dielectric requirement P > 3bar
-Fast recovery time saturated LN2
FCL Vessel
Assembly

Solution
-Operate FCL in sub-cooled LN2 with nominal operating
temperature lower than design point.

Refrigeration System

FCL design at temperature 74K@5bar(a), but operate at


temperature 72K@5bara
Power
Temperature margin determines the number of faults the system
can absorb before system is off-line to re-cool
2K margin allows LN2 to absorb 57MJ energy (~6 faults)
5 bar pressure will allow LN2 in coil vicinity absorb fault energy
without bubbling
FCL operates at high pressure sub-cooled LN2 temperature

65

Heat

SuperLimiterTM Refrigeration System

Level

Pressure

Level

Heat Load

Value (W)

Cryostat

850

Other Refrig. System

200

Terminations

900

Lines, Valves, Bayonets

350

AC Losses

1950

Total Max. Predicted

4250

Planned Capacity

6000

AMSC has operated HTS systems in utility/harsh industrial conditions


- LIPA and TVA/SuperVAR Project

DOE-FCL system based on lessons learned in those systems


- Phase 1b open cycle option shown above
- Phase 2 - replace with closed cycle modification

Simplified, COTS based system


Significant margin planned for prototype system
Refrigeration based on experience at LIPA and other AMSC utility HTS systems

66

SuperLimiterTM Test Site


Present Installation:

Inland Empire

4-3Phase, 336/448/560 MVA


525-120 kV, OA/FOA/FOA
Transformers.
Sectionalized 115 kV bus each section fed by 2
transformers

Devers
500 kV

Serrano
500 kV
A

B
500 kV

Max. single-phase-to-ground
fault = 30 kA
All 115 kV CBs rated 40 kA
Planned Future Installation:
Load growth in the area and
interconnection of new
generators will require
additional transformers
Fault current duty will rise
above 40 kA

C
115 kV

115 KV
Outgoing
1000 MW
Feeder
Future Gen
(Studied)

Bus Tie
(Selected)

A bus tie application at the Valley Substation is selected

67

AB
115 kV

115 kV

Switching Module for the HV SFCL Project


Main design characteristics

The switching module comprises


3 parallel x 17 series = 51 bifilar
pancake coils per phase

Two in hand winding with 12 mm


wide wire to increase the current

Alternating current
directions between
adjacent turns of
bifilar coils cancel
most magnetic
fields
Regions stressed by
BIL tests, numbering
see next slide

Improved electrical strength due to:


- Insulated wire
- New contact design
- Corona rings around the coils

(1)

(2)
(3)

Horizontal stack with radial supports


between module and cryostat wall

68

(1)

Performance Modeling and Testing


Switching

First tests on a 3 m sample of 12 mm wide HTS-wire:


Critical current 167 A @ 77 K, 258 A @ 72 K

77 K, sat., t: 100 ms

More than 60 switching test in saturated (77 K)


2000

400

1000

200

-1000

-200
T: ~72 K

-2000

10

20
30
Time (ms)

40

69

-400
50

Voltage (V)

Current (A)

and sub-cooled (72 K, 1.2 bar) LN2

72 K, 1.2 bar, t: 500 ms

Performance Modeling and Testing

Resistance ratio (%)

Recovery time
About 12 - 15 sec measured on full size dummy coil in sub-cooled LN2
12 mm wide dummy wire insulated with wrapped Teflon tape
Amount of LN2 available for cooling restricted by appropriate enclosure
to simulate adjacent coils
110
T: 77 K, p: 1 bar
T: 72 K, p: 1.2 bar

100
90
80
70
60

-0.05

10

0
Time (s)
70

20

FCL Termination Design Validation


AC withstand test successfully completed according IEC 60840
- 190kV / 30 minutes

Partial Discharge measurement sucessfully completed (IEC 60840)


- Voltage increase up to 140 kV for few minutes
- Decreasing to 114 kV and measurement
- No PD measured (noise level < 3pC)

Lightning impulse test successfully completed (IEC 60840)


- 650 kVp (10 shots in both polarity)

Switching impulse successfully completed based on IEEE C57.12.00:


- Success of the test (540 kVp 250/2500s both polarity)

FCL termination high voltage design successfully validated

71

Summary
AMSC is currently advancing the state of the art in
HTS power products
- Worlds First Transmission Voltage HTS Cable in
Operation
- Worlds First Fault Current Limiting Cable for use in a
distribution grid under development
- Transmission Voltage Fault Current Limiter under
development

72

superior performance.
powerful technology.

Transmission Level HTS Fault Current


Limiter
Chuck Weber
8th Annual EPRI Superconductivity Conference
Oak Ridge, TN
November 12, 2008
SuperPower, Inc. is a subsidiary of Royal Philips Electronics N.V.

SFCL program overview


138 kV, 650 kV BIL
Bushings

Partners

Pressure Vessel
Vacuum Vessel

"
2
6
.3
7

"
8
4
.2
5
1

"
2
6
.3
7

"
8
4
.2
5
1

Inner
Height

Specifications

YBCO based, resistive type FCL


138 kV class device
Fault Current 13.8 kA
Load Current 1,200 Arms
Design fault current 37 kA
Design device response Recover
to superconducting state after a fault
carrying full load current

HTS
Assembly
Height

Matrix Assembly

8th Annual EPRI Superconductivity Conference November 12, 2008

Assembly diameter
Inner diameter

Generalized SFCL Specification Development


Baseline Design for Program was the AEP SPORN substation site
This is a niche application site, operating at 400Arms, 138 kV
Prospective fault current 26 kArms (~90 kA peak) and 13.8 kArms
(~ 37 kA peak)
Working with AEP, we have identified a site with broader general
application
TIDD substation
1,200 Arms, 138 kV
Prospective fault current is 13.8 kArms (~37 kApeak)

8th Annual EPRI Superconductivity Conference November 12, 2008

TIDD Substation (Partial) One-Line Diagram

Proposed SFCL
Installation
Location

8th Annual EPRI Superconductivity Conference November 12, 2008

Prior accomplishments
Proof-of-Concept demonstrated
MCP 2212 (2004)
2G YBCO (2006)
Beta device testing specifications
established
Completed design and testing of HV
bushings (SEI)
Investigated several engineered 2G
architectures for improved RUL

Thermal simulation of RUL process


Weibull plots of standard 2G failures
Conceptual CRS & vessel design
Investigated LN2 dielectric properties

Probability of failure [%]

Design and laboratory testing of shunt


coils to withstand high fault transient loads

2G FCL - Probability of failure for 2G tapes as function of energy


input
100
10
1
0.1
0.01
20

25

30

35

40

45

Energy [J/cm/tape]
Probability of Failure - Test data
Probability of Failure Calculated using Weibull Distributuon

8th Annual EPRI Superconductivity Conference November 12, 2008

50

Improvements to shunt coil and contact design


Shunt coil improvements:
Manufacturing improvements
(easier assembly, more robust
coil)
Mechanical strength
Multi-Layer winding (size
reduction)
Connector improvements:
Shape optimization to avoid
contact hotspots
Improvement in RUL Time
Improvement in RUL Current
Improvement in consistency of
contact resistance
8th Annual EPRI Superconductivity Conference November 12, 2008

Tape heating near contact during fault impacts


RUL

8th Annual EPRI Superconductivity Conference November 12, 2008

Correlation between different contact geometries


Total Current (80A peak)

Superconductors Current

Total Current (80A peak)


Straight Thick Contacts
(M3-460 Tape):
I load = 80 A
RUL = 82 sec.

Superconductors
Current

Recovery Voltage
Recovery Voltage

Straight -Tapered Contacts


(M3-460 Tape):
I load = 80 A
RUL = 3.5 sec.

Total Current (80A peak)


Superconductors
Current

Straight -Tapered Contacts


(M3-460 Tape):
I load = 80 A
RUL = 2.8 sec.

Recovery Voltage

8th Annual EPRI Superconductivity Conference November 12, 2008

Recent KEMA tests


Recent rounds of KEMA testing focused on critical AEP reclosure sequence on
an HTS element
5 Cycles
Fault
13kA/7kA

5 Cycles
Fault
13kA/7kA

18 Cycles
Load Current

5 Cycles
Fault
13kA/7kA

15 sec
Load Current

5 Cycles
Fault
13kA/7kA

5 Cycles
Fault
13kA/7kA

135 sec
Load Current

160 sec
Load Current

Straight elements were


used
Improved connector
designs were used
Standard, pre-qualified
tapes were used
Test Dates: May 2008,
July 2008
8th Annual EPRI Superconductivity Conference November 12, 2008

Breaker opens
and locks-out

Recovery under
NO Load Current

2G RUL capabilities tested at KEMA


Standard SF12100 2G wire used
Total R ecovered Pow er, 2x5 cycles Faults at 37kA w ith 10
mOhm

Test conditions
- 37 kA fault

250000
200000

- follows AEP sequence

150000
Loa d P ow e r (VA)

- Shunt impedance
- Number of parallel tapes
- System voltage (v/cm/tape)
- Load Current

8th Annual EPRI Superconductivity Conference November 12, 2008

50000

300V
250V

Vo
lta
ge

Test variables

100000

200V

16 Tapes

Para8 Tapes
lle
Tape l
s

100V
4 Tapes

Achieving RUL is a difficult task


Without load current recovery is very fast

w/o Load

w/ Load

3 x load
Base-Line
Voltage
Adding
current
makes
recovery much more difficult
8th Annual EPRI Superconductivity Conference November 12, 2008

Electrical stress on the tapes can limit RUL


RUL time can affected by
increasing the V/cm on the
tape

RUL

Base-Line Voltage

Limits of the design


optimization are understood

RUL

RUL

1.5 x Base-Line Voltage

3 x Base-Line Voltage

8th Annual EPRI Superconductivity Conference November 12, 2008

Factors impacting RUL defined by test results


Total Recovered Power, 2x5 cycles Faults at 37kA with 4 Tapes

80000
70000
60000
50000
40000 Load Power (VA))
30000
20000

1.67 Sm-Ohm
hu
nt
Im
5pem-Ohm
da
nc
e

10000

100 V

tageV
ol250
200 VV

0
300 V

Sample surface plot of RUL conditions


8th Annual EPRI Superconductivity Conference November 12, 2008

Ability to predict RUL over wide design space


Maximum Load Current as a function of shunt impedance, operating voltage & number of
tapes

1000
900
800
700
600

Maxim un Recovered
Load Current

500
400
300

pes
a
T
,#

16Tapes, 100V

8Tapes, 100V

4Tapes, 250V

4Tapes, 100V

eda
nce

5 m-Ohm

Imp

1.67 m-Ohm

8Tapes, 250V

100

e
ltag
o
V

16Tapes, 250V

200

Recovered Current with 2 Asymmetrical 37kA Faults, 5 cycles each

8th Annual EPRI Superconductivity Conference November 12, 2008

Worst case conditions at Tidd can achieve RUL

RUL with 90% of the Power recovered within


the 2nd and the 3rd 37 kA Faults

Full recovery expected with optimal bath conditions

8th Annual EPRI Superconductivity Conference November 12, 2008

Bath Conditions Impact on Ability to Recover


During the fault transient, tape heats up to film boiling region.
Bath conditions (pressure, subcooling) shift boiling heat transfer curve
Bath conditions have an impact on the dielectric strength of LN2
No Recovery Due to Film Boiling

Boiling Heat Transfer for LN2

600

Heat Out
Heat In

100.0

500

Lower Zshunt,
Higher Ztape

10.0

Power (W)

q/A (W/cm )

400

300

200

1.0

100

0.1

1.0

10.0

100.0

T wall - T sat (K)

100

150

200

1000.0

250

300

350

400

450

500

Temperature (K)

Lowering the shunt coil value or


increasing the resistance of the
stabilizer layer will help with film boiling.

8th Annual EPRI Superconductivity Conference November 12, 2008

550

Bath Conditions Impact on Ability to Recover


Once film boiling threshold is crossed, nucleate boiling ensues
Bath conditions (pressure, subcooling) shift boiling heat transfer curve
Bath pressure shifts saturated boiling temperature, limiting nucleate boiling
recovery
No Recovery Due to Nucleate Boiling
600

Boiling Heat Transfer for LN2

Heat Out
Heat In

100.0

500

Lower pressure

Power (W)

q/A (W/cm )

400

10.0

300

200

1.0

100

0.1

1.0

10.0

100.0

1000.0

75

80

85

90

Temperature (K)

T wall - T sat (K)

Lowering the operating pressure will


help with nucleate boiling, but
decreases dielectric properties
8th Annual EPRI Superconductivity Conference November 12, 2008

95

100

Modeling indicates where operating conditions


for successful RUL exist
Recovery Under Load vs Number of Tapes
1300

Baseline
1200
1100

Pressure = 0.5 atm


Tbulk = 71.922 K

Recovery Load Current (arms)

1000
900

Pressure = 0.5 atm


Tbulk = 71.922 K
Stabilizer = 1% AgAu

800
700

Pressure = 0.75 atm


Stabilizer = 1% AgAu

600

Pressure = 0.75 atm


Stabilizer = 2.2% AgAu

500

Baseline Substrate = 4 mil


Stabilizer = Ag
Shunt Coil = 10 m/m
No dielectric coating
Ic @ 77 K = 250 amps
n-value = 20
Pressure = 1 atm
Tbulk = 72 K

400
300
200
100

Baseline
Shunt = 5 m/m

Baseline
Shunt = 7.5 m/m

0
0

10

12

14

Number of Tapes per Element


8th Annual EPRI Superconductivity Conference November 12, 2008

16

Introducing bubbles in LN lowers


breakdown strength: FCL recovery
Bubbles form thermally or electrically and can affect the breakdown strength

Two experiments
Open bath LN
Pressurized cryostat
Nitrogen gas provided
by fused silica capillary
tube
Varied flow rates
Parallel plane profiled
SS electrodes
2 mm gap
0.5 mm capillary tube

BD strength of LN is
~5x the gas at 1 bar
Important for FCL Recovery under Load

19 Managed by UT-Battelle
for the Department of Energy

DOE Peer Review 2008

Effect of externally provided bubbles


on LN Breakdown: AC breakdown
Effect of Bubbles

16

all data w and w/o bubbles


Cumulative Failure Probability (%)

Average Electric Field (kVrms/mm)

18

14
12
10
8
6
4
2

99.9
99.0
95.0
90.0
80.0
70.0
60.0
50.0
40.0
30.0
20.0
10.0
5.0

1.0

0
without bubbles

with bubbles

7 8 9 10

20

Breakdown Field (kVrms/mm)

Presence of bubbles

Liquid nitrogen at 1 bar

Bubbles in LN lowers breakdown strength


Change in slope at lower probability indicates change in BD
mechanism
20 Managed by UT-Battelle
for the Department of Energy

DOE Peer Review 2008

30

Summary
Significant progress in understanding and impacts of:
RUL
Variables impacting RUL studied and understood
Worst case conditions at TIDD can be met
Impact of device design and cost under evaluation

LN2 Dielectrics
Impact of bubbles on breakdown mechanism and dielectric
strength

Loss of cryogenic partner a setback, but not fatal


Next step: Alpha detailed design

8th Annual EPRI Superconductivity Conference November 12, 2008

Thank You for your attention!


For more information:

www.superpower-inc.com
or
cweber@superpower-inc.com

8th Annual EPRI Superconductivity Conference November 12, 2008

superior performance.
powerful technology.

Status Update for the Albany HTS


Cable Project
C.S. Weber (SuperPower)

8th Annual EPRI Superconductivity Conference


Oak Ridge, TN
November 12, 2008
SuperPower, Inc. is a subsidiary of Royal Philips Electronics N.V.

Program Overview
350m long - 34.5kV - 800Arms - 48MVA
Cold dielectric, 3 phases-in-1 cryostat, stranded copper core design
Two Phases Phase I - 320m + 30m BSCCO
Phase II - 30m BSCCO replaced by 30m YBCO cable
Project Manager; Site infrastructure,
Manufacture of 2G HTS wire
Host utility, conventional cable & system
protection, system impact studies
Design, build, install, and test the HTS cable,
terminations, & joint
Design, construct and operate the Cryogenic
Refrigeration System, and provide overall
cable remote monitoring and utility interface
Supported by Federal (DOE) and NY State
(NYSERDA) Funds

9th Annual EPRI Superconductivity Conference November 12, 2008

Site Location

Phase I: BSCCO

Phase II: 30m YBCO

9th Annual EPRI Superconductivity Conference November 12, 2008

System Protection Philosophy

Worst case fault conditions 23 kA rms (33 kA peak)

Multiple levels of relay & breaker protection


Primary - RFL-9300 charge comparison relays (87L) 8 cycle clearing time
Secondary - SEL-311B relay packages 8 38 cycle clearing time
Breaker failure protection
Will initiate fault clearing by tripping breakers on associated Menands or Riverside 34.5kV bus
cleared in 20 to 50 cycles (0.33 to 0.83 sec)
System monitoring @
BOC Remote Operating Center
NM Eastern Regional Control Center

9th Annual EPRI Superconductivity Conference November 12, 2008

Albany HTS Cable Design


Electrical Insulation
PPLP +Liquid Nitrigen

Advantages of the 3-in-One Cable

Stainless Steel
Double Corrugated
Cryostat

Cu Stranded Former

Design
Compact size (O.D. = 135mm) (5.3)

35 mm

135 mm

Nearly perfect magnetic shielding


> 95% cancellation of field
Significant reduction of contraction

Cu Shield
HTS Conductor
2-layer

HTS Shield
1-layer

forces due to slack winding


Excellent fault current protection
Cable remains superconducting at
worst case fault condition,
survives extended duration (2nd
contingency) fault without damage

9th Annual EPRI Superconductivity Conference November 12, 2008

Tension Member

Cryogenic Refrigeration System: Approach


Hybrid arrangement permits
transparent use of bulk liquid
nitrogen for back-up

Cryocooler

Thermosyphon

Liquid Nitrogen
Storage/buffer

Thermosyphon provides common


heat exchange interface between
cable and open or closed
refrigeration sources
Advantages:
- excellent reliability/cost ratio
- compact footprint
- flexible plug & play design
- good efficiency
Subcooled liquid nitrogen loop

HTS cable

9th Annual EPRI Superconductivity Conference November 12, 2008

Minimum CRS Requirements & Cold Box Arrangement


Item

Specification

Coolant supply temperature


Temperature stability

67 to 77 K
+-0.1 K - normal operation
+-1.0 K - backup operation
5 kW at 77 K
3.7 kW at 70 K
1 to 5 barg +-0.2
50 liter/min +-1

Refrigeration capacity
(excluding CRS)

Minimum coolant pressure


Maximum coolant flow rate

BOC

1.4 m

1.6 m
9 Annual EPRI Superconductivity Conference November 12, 2008
th

Post-Cable Testing: Cryogenic System Step


Response
80
30
Coolant return
North Termination

76

Coolant Supply

74

Temperature (K)

25

South Termination

20

Refrigeration power
72

+ - 0.05K

70

15

68

Hybrid operation

66
64

10

+ - 0.10K

8 Kw peak

62

3 Kw nominal

60

0
0

10

11

12

Time (hours)

Pre-energization: 3 Kw nominal. Post-energization: 3.1-3.3 kW nominal overall heat load


9th Annual EPRI Superconductivity Conference November 12, 2008

13

Cooling Power (Kw)

78

Summary of Phase I Operation


Supply
Issue was checked for damageChiller
The
HTSVoltage
cable system
after the
faultShutdown
event
System
Energized
No Issues
Re-connected to Power Grid
Completed
on July 20,2006

7kA
Cable Outlet Temperature

70
Temperature [K]

on May 1, 2007

16

Cable Inlet Temperature

69

20

12

8 cycle

68

More Than 6,700 Hrs of Reliable Power Transmission


67

4
Transmitted Electricity

66

0
7/20

8/17

9/14

10/12

Fault Current Event

11/9

12/7

1/4

2/1

Date (2006-2007)

9th Annual EPRI Superconductivity Conference November 12, 2008

3/1

3/29

4/26

Transmitted Electricity [MVA]

71

Commencement of Phase II
Before warming-up,

No Change

Megger Test
Ic Measurements
Warm-up Process,

(1) LN2 pumped into the CRS bulk storage tank


(2) Remaining LN2 in system allowed to evaporate naturally
South
Term

50

North
Term

30m HTS Cable


320m HTS Cable

350m Return Pipe

21D

Temperature []

14D

Vacuum level
No leakage
Cable Tension
Returned to the
original value
(approx. 200kg
compressive force)

11D

-50

9D
7D
1D

-100
5D
12H

3D

-150

-200
0

100

200

300

400

500

600

700

800

Position [m]
9 Annual EPRI Superconductivity Conference November 12, 2008
th

1 Meter Cable Characterization (after removal)


Contact was made to 12 strands with single
strand Ic(B=sf, 75K) ~ 92 amperes
Contact resistance measurements were
performed in the superconducting state
T=75.5K

The critical current of the inner layer with


12 strands of superconductor was
measured at 75.5K in self field.
Distance between voltage taps = ~75cm
Ic = 965Amperes @ 1V/m
1100A @ 1V/cm
200

40000
30000

150

Contact #2
R=32 uohms

V(uV)
20000

100
V(uVolts)

50

Contact #1
R = 6 uOhms

10000

0
0

500
I(Amperes)

1000

-50

200

400

600

800 1000 1200

I(Amperes)
*Data courtesy of Yates Coulter, LANL

9th Annual EPRI Superconductivity Conference November 12, 2008

In 2007, 30 m cable was manufactured by Sumitomo Electric


with ~10,000 m of SuperPower 2G HTS wire
2G wire cable
winding

3 core stranding

Stainless Steel Double


Corrugated Cryostat

Electric Insulation
(PPLP + Liquid Nitrogen)
Cu Stranded
Wire Former

135 mm

2G HTS wire
(3 conductor Layers)

2G HTS wire
(2 shield Layers)

Cu Shield

9th Annual EPRI Superconductivity Conference November 12, 2008

Summary of 30 meter YBCO Cable Shipping Tests

Manufacture of 30m YBCO cable completed in March 2007

The following shipping tests were conducted successfully on samples from long
cable:
Critical Current
Conductor : 2660 2820A (DC) at 77K
Shield
: 2400 2500A (DC) at 77K
AC Loss
0.34W/m/phase at 0.8kArms, 60Hz
Bending Test (18D: Bending Dia. = 2.4 m)
No Ic degradation
No defect was found at dismantling
Inspection
Voltage tests (Based on AEIC)
AC 69kV for 10 minute,
Imp 200kV, 10 shots/each
DC 100kV for 5 minutes
9th Annual EPRI Superconductivity Conference November 12, 2008

YBCO Cable - Critical Current Measurement


Sample: 3 meter 3-Core

Ic (Conductor) = Approx. 2660 2820A (DC, 77K, 1uV/cm)


Ic (Shield) = Approx. 2400 2500A (DC, 77K, 1uV/cm)

Conductor
Core-1
Core-2
Core-3

1.5

Shield

Electrical Field(uV/cm)

Electrical Field(uV/cm)

Ic Criterion (1uV/cm)

0.5

-0.5

Core-1
Core-2
Core-3

1.5

Ic Criterion (1uV/cm)

0.5

-0.5

500

1000

1500

2000

2500

3000

500

Current (A, DC)

1000

1500

2000

Current (A, DC)

Very good match between test results and design values


9th Annual EPRI Superconductivity Conference November 12, 2008

2500

3000

AC Loss Measurement

AC loss (W/m/phase)

Sample
: 2.5 meter single core
Current loading : go & return through conductor and shield
Measuring
: Lock-in amplifier with electrical 4 terminals
1

0.1

0.01

Measured value

0.34 W/m/ph @ 800 Arms


Slightly better result than the
1 meter test sample core

0.001
100

1000
10000
Loading Current (Arms, 60Hz)
9th Annual EPRI Superconductivity Conference November 12, 2008

Fault Current Test with 1 m 2G


Sample
Cable
Test Site : Nissin Electric (Kyoto)

Fault Current Testing

Sample: BSCCO Core YBCO Core


(Compare YBCO core with BSCCO one)
Current: 23kA
Duration: 8 38cycles
Cooling: Open Bath (77K)

L1

L2

Generator
(5000V)

L0

Transformer
(6600V/550V)

SW

Test Samples

Lg

Maximum Temperature Rise [K]

100
BSCCO Conductor
BSCCO Shield
YBCO Conductor
YBCO Shield

90
80
70
60

Shield

50
40
30
Conductor

20
10
0
0

10

20
30
Duration [cycles, 60Hz]

40

Temperature Rise During Fault


nearly identical to BSCCO core
9th Annual EPRI Superconductivity Conference November 12, 2008

50

Replacement of 30 meter section with new YBCO cable


[ 30m cable Installation ]

[ Termination Re-assemble ]

[ Joint Re-assemble
BSCCO-YBCO]

World firsts HTS cable replacement is completed!

9th Annual EPRI Superconductivity Conference November 12, 2008

Summary of Various Commissioning Tests at Phase-II


HTS cable system successfully passed following commissioning tests:
Test Items

50

Test Results

System withstand pressure Test

z 0.61 MPaG (based on ASME code): good

Initial cooling test

z Maximum core tension: approx. 1000kg


Tension minimized by loosely stranded 3-core structure
z Vacuum level at each part: good (no leakage)
z Core behavior inside the joint: within the scope of Design

Ic measurement (dc, defined at 1uV/cm)

z 2.3kA (at 73K), 2.8kA (at 69K): Same Ic as Phase-I

Heat loss measurement


(under no-load condition)

z 350 m cable section (including joint): 1.0kW


z Entire cable system (not including CRS: 3.4kW

DC withstand voltage test

z 100 kV, 5 minutes, each phase (based on AEIC) : good

South
Termination

North
Termination

2.5

0H

Electric Field [uV/cm]

6H
10H

Temperature []

Cable Mean Temp : 73K

Core-1

-50

18H
1D

1.5D
3D

-100

9D

69K

Core-2
Core-3

1.5

Ic c ritrion (1 V/ cm)

1
0.5
0

-150
10.8D

10.7D

10.9D

11.5D

-0.5

10.5D

-200
0

50
0

100
50

150
100

200
250
150
200
Length [m]

250300

300350

500

1000

350 400

9th Annual EPRI Superconductivity Conference November 12, 2008

1500
Current [A, DC]

2000

2500

3000

Demonstration of the worlds first device with 2G


HTS wire in a live power grid
1.2

20

16

0.8

Jan 8
2008
0.6

12

8
0.4
4

0.2
Transmitted Electricity

0
1/7

1/21

2/4

2/18

3/3

3/17

3/31

Date (2008)

Cable made with 2G HTS wire was energized in the grid in


January 2008 & performed without any issues
9th Annual EPRI Superconductivity Conference November 12, 2008

Transmitted Electricity [MVA]

Temperature Deference [K]

Temperature Deference between Outlet and Inlet of Cable

Ic-T characteristics
Ic-T
characteristics
of
DI-BSCCO
of DI-BSCCO

2.5

Short Sample Ic
Short Sample
Ic
(1800A
at 77.3K)
(1800A at 77.3K)

Commissiong Test
(320m+30m Cable)

Electrical Field [uV/cm]

3500
3500
3000
3000
2500
2500
2000
2000
1500
1500
1000
1000
500
500
0
0 65
65

Core-1
Core-2
Core-3

2
1.5
1

69K
73K

Ic criterion1V/cm

0.5
0

-0.5

70
75
70
Temperature [K]75
Temperature [K]

2500

Critical Current [Adc, at 73K]

Critical
Current
1uV/cm]
Critical
Current
[A,[A,
atat
1uV/cm]

Variation of Critical Current from Phase-I through Phase-II

80
80

2000

1500

500

1000

1500
2000
Current [A]

2500

The Ic of long cable are very good


match with expected value from
short sample testing at 77K.

Core-1
Core-2
Core-3

1000

The Ic values had no change


through Phase-I and Phase-II
including heat- cycles.

500

0
Sample Test

3000

Phase-I
Phase-I
Phase-II
Phase-II
(after cooldown) (after long-term (after cooldown) (after long-term
operation)
opearion)

9th Annual EPRI Superconductivity Conference November 12, 2008

Variation of Temperature Difference on the Cable during


Phases I & II
[ Phase-I ]

[ Phase-II ]

1.2

1.2

20

20

0.8
12
0.6
8
0.4
4

0.2

Temperature Deference [K]

16

Transmitted Electricity [MVA]

Temperature Deference [K]

16

0.8
12
0.6
8
0.4
4

0.2

Transmitted Electricity

Transmitted Electricity

0
7/20

0
8/17

9/14

10/12

11/9

12/7

1/4

2/1

3/1

3/29

Transmitted Electricity [MVA]

Temperature Deference between Outlet and Inlet of Cable

Temperature Deference between Cable Outlet and Inlet

4/26

0
1/7

1/21

2/4

2/18

3/3

3/17

3/31

Date (2008)

Date (2006-2007)

Temperature difference between outlet and inlet of the HTS cable was 0.9 +/- 0.1K
Temperature deference was very stable during the long-term In-grid operation in
Phase I and Phase II
Maintained good CRS operation and No change of cable heat loss during longterm in-grid operation
9th Annual EPRI Superconductivity Conference November 12, 2008

Presentation Summary
World class team has successfully executed on all phases of the program
Met or exceeded all goals and objectives
Cable ran flawlessly for >12 months with ZERO instances of downtime due
to the HTS system
Efficient, reliable and robust design capable of handling real-world utility
operating environment
ALL equipment/systems responded as designed without any adverse effects

Biggest reliability concern (CRS) addressed & proven to meet commercial


requirements
Achieved Worlds first in-grid demonstration of a YBCO device
Technology transfer & education achieved by numerous tours/events (>20) and
articles/presentations(>50) given throughout the program

9th Annual EPRI Superconductivity Conference November 12, 2008

The Bottom Line


Of importance to National Grid is that this project has
demonstrated the reliability of the technology. We
encountered no difficulties in integrating the project into our
grid and the entire installation was totally transparent to our
customers. The system has stood up to very exacting utility
standards and we look forward to further developments in
HTS technology.
- William Flaherty,
Energy Solutions Regional
Director of National Grid
9th Annual EPRI Superconductivity Conference November 12, 2008

Thank you!
For more information:

www.superpower-inc.com
or
cweber@superpower-inc.com
9th Annual EPRI Superconductivity Conference November 12, 2008

2008 12 13

Power
PowerSystem
SystemNetwork
Network
(345kV
(345kVand
andabove)
above)
Legend
765kV System
345kV Overhead System
345kV Underground System
DC180kV Cable Link
765kV Substation
345kV Substation
Generating Plant

Peak Demand [MW]


Classification 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Peak Demand 37,293 41,007 43,125 45,773 47,385 51,263 54,631 58,994 62,285 62,794
Increase Rate 13.0 10.0
5.2
6.1
3.5
8.2
6.6
8.0
5.6
0.8

Transition of Fault Current [kA]


Voltage

2008

2010

2014

2020

765kV

21.7

24.4

23.6

25.3

345kV

50.0

57.2

56.6

57.9

154kV

49.4

49.2

50.0

54.0

The rate of underground transmission line


Seoul
51.3%

Total
12.68%

Kyunggi
18.3%

Incheon
29.5%
Chungnam
5.0%

Chungbuk
6.2%

Kangwon
5.3%

Kyungbuk
4.1%
Daegu
21.9%

Daejun
45.2%
Junbuk
6.1%

Ulsan
18.7%

Jeju
11.9%
Gwhangju
26.5%

Kyungnam
7.4%

Busan
31.5%

(As of 2007)

High cost for civil work and construction


Difficulty of excavating roads for construction of conduit or
culvert
NIMBY for the construction of new substations in urban area
Needs for environmental friendly power apparatus
Need to decide how to renewal the aged power cables
Electric power demand is increasing every year
Continuous increase of fault current

High Capacitance & Low loss + Eco-friendly


HTS Cable & SFCL

The name of Project : DAPAS (Development of Advanced

power system by applied Superconductivity technology)


Project period : 2004~2011
Total budget : $146million

(Government : $100million / Industry : $46million)


Participants

22.9kV HTS Cable has been developed and


154kV HTS power cable is under development till 2010
Year

2001

2002

2003

2004

2005

1 st Phase

2006

2007

2008

2009

2010

3 rd Phase

2 nd Phase

Fundamental
Design
Single
Core 30m

DAPAS

Fab. Evaluation.
50MVA/30m
22.9kV
3-Core

50MVA/100m
3-Core

Evaluation

Type test

154kV
Basic study Design

Real-grid application

Long term Demonstration


Operation on Real grid

1,000MVA
Fab. Evaluation Type test

Fundamental Studies

Seamless Aluminum Cryostat for HTS Cable was developed

Fabrication
350

0.1

Outer
layer

Thot= 300K

Tcold= 77K

Vaccum
1. MLI
Spacer

Cryostat

Displacement
Simulation

250
0.01
200

1E-3

150

1E-4

100

1E-5

50

1E-6
0

500

1000

1500

2000

2500

3000

Time (hr)

Experimental result

3500

Vacuum rate (Torr)

Inner layer

Temperature
Vacuum rate
300

Temperature (K)

M
LI

HTS Cable

Design & Fabrication of HTS Cable

Optimal Design for Conductor/Shield Stranding & Fabrication

EM field calculation
HTS Shield

HTS Conductor

Pitch determination
for each layer

Impedance matching

Fabrication

HTS Cable

HTS Cable System


22.9kV (Nominal), 13.2kV (Phase)
1,260A (50MVA)
9 Fault Current : 25kA, 15cycle (Cu Stabilizer)
9 Closed loop cryo-coolers incorporated in CRS

HTS Cable
Cold Dielectric
Diameter : 145mm
Seamless Aluminum Cryostat
PVC Sheath
~ 35kV Insulation level
3 - phases in one cryostat
FC Stabilizer incorporated

Design of Accessories

Termination

Insulator

(800mm , 3.5m L 2.1m h)


~ 35kV Insulation level
3 - phases in one cryostat
Pressure withstand : Min. 15bar
Pre-fabricated components
Polymer composite Bushing

Approx. 2100

Compact Design

Cryostat

Bellows

Approx. 3500

Joint Box
Compact Design
,

L)

(500mm 3.5m
~ 35kV Insulation level
Pre-fabricated components
Pressure withstand : Min. 15bar

Cable

Cable core

Cryostat

Approx. 3500

Bellows

Installtion
Installation & handling of HTS cable are same as ordinary cable

Tunnel

Pipe duct (175mm)


Snake and cleats
(for TM behavior)

Jointing Works
Minimum jointing work at site
(14 days for termination, 21 days for joint box)
Pre-fabricated

Pre-fabricated

Jointing at site

Termination

Joint Box

CRS
Configuration of CRS
- Closed loop ( no evaporation of LN2 )
- Total heat loss covered by packaged cryo-cooler
LN2
Tank
(5 ton)

Stirling
Cryocooler
(640W @65K)
Evaporator

Vacuum
Pump
Ambient

Separator
Coldbox1

Pulse Tube
320W@65K

Coldbox2

GM
840W@65K,
2EA
Sub-cooler

Circulation
Pump

Bypass line

HTS Cable & Acc.

Heat
Exchanger

Evaluation
Configuration of system installation
( Fully simulating real grid conditions )
Pipe Duct [15 m]

Termination (Load)

Tunnel (55 m)

Termination (Power source)


Joint
box

U-bend
On the ground
[30 m]
100 m
Joint box
Ground level
Termination (Load)

Termination (Power source)

Evaluation

Test program
- Reference tests for confirmation of sound installation
- Main dielectric tests were executed after 2nd cool down
1st Cool down

Reference Tests
Dielectric Loss
Partial Discharge
Dielectric security
DC Ic

Warm-up
& 2nd Cool down
Shrinkage (Ref.)

Load Cycle Test


Applied Voltage

- 1.5Uo for 30days


Load current
- 1,260 A (8hrs On, 16hrs off)
Cooling Circuit Pressure Control

Residual Performance
Tests
DC Ic
PD (@Uo,1.5Uo, 2.5Uo)
Dielectric Loss (@Uo, 1.5Uo, 2.5Uo)
Dielectric Security (@2.5Uo for 24h)
Thermal/Electrical loss (Ref.)
Impulse (BIL)

Test Results
Temperature profile during the whole type test procedure

Reference
test

Residual
test

Voltage & Current

Test Results
Load Cycle Test at 1.5Uo for 30 days was successfully finished
8h
(1260A)

1 cycle

Voltage
(20kV ; 1.5U0)

16h (No load)

Time (h)

Current

Test Results
PD, dielectric loss were tested successfully

* High Frequency Antenna


Applied Voltage (kV)

PD (pC)

Tan

< 10

0.00002

10

< 10

0.000027

13.2 (Uo)

< 10

0.000039

20.1 (1.5Uo)

< 10

0.00004

33 (2.5Uo)

< 10

0.000041

* Background noise : 5~10 pC

Test Results
AC Dielectric Security Test @2.5Uo for 24hours was passed

Test Results
DC Ic showed no degradation after all electrical & thermal cycle tests
2
0
1
x
6
.
1
2
0
1
x
4
.
1

Operating range

2
0
1
x
2
.
1
3
0
1
x
0
.
8

Phase R @ 75K
Phase S @ 75K
Phase T @ 75K
Phase R @ 72K
Phase S @ 72K
Phase T @ 72K

3
0
1
x
0
.
6

Voltage (V)

2
0
1
x
0
.
1

Ic criterion (1uV/cm)

Result

3
0
1
x
0
.
4

Phase
(Cable)

Design
@ 75 K

75 K

72 K

3 kA

3.01 kA

3.34 kA

3 kA

3.06 kA

3.43 kA

3 kA

3.03 kA

3.34 kA

3
0
1
x
0
.
2
0
.
0

* Operating temperature : 72 ~ 75 K
* Operating current range : ~ 1.8 kA

0
1
x
0
.
2
-

0
0
5
,
3

0
0
0
,
3

0
0
5
,
2

0
0
0
,
2

0
0
5
,
1

0
0
0
,
1

0
0
5

Current (A)

The 22.9kV 50MVA HTS cable system was developed

and successfully passed 3 rd party inspected type test


The proposed type test specification fully considers

the real-grid operational conditions


Long term verification in end users real-grid has been

planned for commercialization of HTS cable system

HTS Cable Updated


In 2008, the main topic of R&D on the HTS cable system is
operation and maintenance skills regarding to the real grid operation

History
2001 ~ 2003 : Fundamental studies
2004 ~ 2005 : Application technologies
2006 ~ 2007.6 : Type test for 22.9kV products
HTS Cable, Joint, Terminations, CRS

Updated
2007.6 ~ 2008 : O&M Skills & 6 Times Thermal Cycles
Unmanned operation Technology, Live line maintenance

Planning
22.9kV 50MVA : Real grid application in KEPCOs substation
Longer than the length which needs joint box with network study

3phase 22.9kV/630A hybrid SFCL(2006)


Developed jointly by KEPRI and LS Industrial Systems.
Combined Superconductor and normal-conductor devices.
A 3 22.9 kV/630 A SFCL was built and tested for 3-phase faults
Limited fault current 29 kA to 17 kA (and to 8 kA after 5 cycles)

A hybrid SFCL
under test

Last version of 3phase 22.9kV/630A hybrid SFCL(2008)


Control & Monitoring Parts

Cryostat

Fast Switch

Current Limiting Resistor

Reliability Test Plan


Field test of 22.9 kV Hybrid SFCL is planned in Gochang Testing Yard.
Now, processing the network engineering

Automatic
Fault generator
Superconducting power machine
testing building

Korea Government
KETEP
(Korea Institute of
Energy and
Resources
Technology
Evaluation and
Planning)

KEPCO(KEPRI)
KERI
University
Detailed Feasibility
Study
Operating &
Maintenance

Project period : Nov. 2008 ~ Oct. 2013


Total budget : $17million

(Government : $8.5million/
Industry : $8.5million)

KEPCO
Head Quarter
Prime Contractor

KEPCO(KEPRI)
LS Cable
KERI, KBSi
University
Manufacture and
Installation in HTS
Cable Systems

KEPCO(KEPRI)
LS IS
University
Manufacture and
Installation in
SFCL Systems

154/22.9kV
MTR

3kA SFCL
150MVA HTS Cables

HTS Cable
500m

[ 22.9kV HTS Cable, Termination, and Splice]

[ 22.9 kV SFCL System-Trial Product ]

Supplying the huge buildings with electric power by HTS cables


Replacing 22.9kV conventional cables(2~3lines) with the superconducting
cables using the existing conduit or culverts without additional civil works
22.9 kV Superconducting Cables
to replace 154 kV conventional cables

Downtown Area
22.9 kV
SW/S

154 kV S/S in the suburbs

Circuit Breaker
(Normal open)

SFCL

SFCL

22.9 kV Superconducting Cables


to replace 22.9kV conventional cables

22.9 kV
SW/S

SFCL

Superconducting
Transformers

22.9 kV
SW/S

Superconducting Power System (SPS) applying distributed switching stations


for metropolitan areas
z Apply superconducting power devices (cables, transformers, FCLs) to real power system
z 154kV transmission power system 22.9kV superconducting power system
Replace 154kV substations in downtown with 22.9kV underground switching stations
Replace 154kV conventional cables with 22.9kV superconducting cables
Bulk power transfer by superconducting cables and transformers & Fault current reduction by SFCL
154kV conventional
cables

Suburb
Downtow
n

154kV
S/S

154kV
S/S

154kV
S/S

154kV
S/S

Suburb

154kV conventional
cables
Skip substations
Reduce
construction costs
Environmentfriendly
Avoid civil petitions

22.9kV
SW/S
154kV
S/S

22.9kV
SW/S
22.9kV
SW/S

22.9 kV
Superconducting cables

Downtow
n

22.9kV
SW/S
22.9kV
SW/S
22.9kV
SW/S

154kV
S/S

One of solutions for the site problem


z No substations & Compact size Easy to find a site for power facilities in downtown
z Underground switching stations Make a park on the switching stations

Economic benefits
z Reduction of cost for buying land
The site for 22.9kV switching stations is less than 30%, compared to 154kV substations.

z No additional construction cost


We can use established underground facilities such as existing electric power conduit pipes.

Environmental and social benefits


z Environment-friendly Avoid the trend of NIMBY
No oil for cooling the system
Free of the explosion danger (Superconducting transformer)

z No additional construction Reduce the construction cost and ease traffic congestion
z High efficiency and loss of superconductor Save energy and reduce CO2 emission

In Korean power system, increase of electric power demand have been accompanied
with increase of power plants, substations, transmission lines and distribution lines.
So that development of high capacitance power facility to accept increase demand
was required and during a past decade, superconducting cable and SFCL have been
developed.
Currently, developments and tests of 22.9kV superconducting cable and SFCL are
finished, and development of 154kV superconducting system is under development
till 2010.
From Nov.2008, to affirm stability and reliability of developed superconducting cable
and SFCL by gathering and analysis of operating and maintenance data, 22.9kV HTS
system real grid project is started for 5 years.
If stability of HTS system including superconducting cable and SFCL is affirmed, it
will be expended from urban.

2008 12 13

39

Southwire Entergy HTS Cable Project


Eigth Annual EPRI Superconductivity Conference
Oak Ridge, TN
November 12-13, 2008

Erik Guillot
Project Manager
Transmission EMCC

David Knoll
Project Manager
HTS Cable Systems

Project Partners

Project Specs
Cable Design
Length
Voltage
Load
Cooling
Splices
In-Service Date

HTS TriaxTM - Superconducting


1760 meters (1.1 miles)
13.8 kV
48 MVA
Single Point, Closed Cycle
2 (Cable Sections = 3)
1Q2011

13.8 kV, 2.0 kA (48 MVA) Triax HTS Cable


Cooling Plant

Project Location

Cable Route

Project Overview:
Replace Copper HV Transmission with HTS MV Distribution
Problem:
Saturated 13 kV distribution anticipate high load growth
230/13 subs to north & south of area - Need new sub at mid-point
Challenges:
OH RoW for 230 or 13 kV very difficult or impossible
Small footprint available for new substation
230 kV solution: placing transformer in dense residential area.
13 kV conventional: Voltage drop, power quality
Solution:
13 kV HTS cable to transmit 48 MVA into small footprint station.
1.1 mile HTS cable that meets load growth needs.
Leverage existing transformer capacity No new transformers needed
Single point cooling station.
13 kV HTS replaces 230 kV underground.
Cost effective with DOE support.

Southwire - HTS TriaxTM 2000A Cable


Phase 3 HTS
Phase 2 HTS
Former

Phase 1 HTS

LN
Cryostat

LN

Dielectric

1.
2.
3.

Copper Neutral

HTS TriaxTM Advantage vs Competition:


HTS tape usage = substantially cheaper
Single Cable = simplified mfg & installation
Smaller cold surface area = lower cooling & operating cost

Southwire Triax Cable Termination


3 Phase Connections

Neutral Connection

- Provides transition from


superconducting materials to
copper materials.
- Thermal transition from 200 C to
ambient temperature
- Controls electrical stresses.
- Provides input and/or output
location for LN coolant.
- Provisions made for temperature
and pressure measurements and
monitoring.
- Electrical connections to utility
made by means of industry
standard NEMA pad.

Cable Installation

On Going Effort - HTS Tape Options


1G BSCCO vs 2G YBCO

Mechanical testing
Compatibility with cabling process
Electrical Properties Ic, n-Value, AC Loss
Magnetic Properties
Piece Lengths
Wire availability
Per meter costs

On Going Effort Cable Configuration


Segment 1

Segment 2

Segment 3

Spare

Composite 1

1G

1G

2G

1G

Composite 2

1G

2G

2G

1G

All 1G

1G

1G

1G

1G

All 2G

2G

2G

2G

2G

On Going Thermal / Hydraulic Analysis


CABLE
ASSEMBLY
THERMAL
MODEL
Cryostat Wall
74

LN2 LN2

T [K]

73
72

Annulus

71

Tmax

Former
Ph1

70

Ph2

69

Ph3
Neutral

68

Insulation RT
HTS
Heater
AC- Loss,
QknownRT
Insulation RT
HTS
Heater
AC- Loss,
QknownRT

67
66
0

500

1000
L [m]

1500

2000

Insulation RT
HTS
Heater
AC- Loss,
QknownRT

Former, RT
LN2 LN2

Temp
Sensors

On Going Effort Cryogenic System Design

~ 10kW cooling required

Closed loop cooling system

Cryocooler Options
Pulse Tube
Sterling Cycle
Brayton Cycle

RFPs out after AC Loss study

System supplier will perform


detailed system design

LN2
Tank
Back-up
Open Cycle
Heat Exchanger
Closed Cycle
Sub-Cooled LN2

Cryocooler Bank

HTS Cable
Counter Flow Cooling
Out = thru former
In = thru annulus

Previous Experience AEP, Columbus, OH

AEP-Bixby
200 meters
8/2006 to present
13.2 kV, 3.0 kA,
Triax Cable

5 DAY Bixby Peak Load August 2007


3000

Peak Load = 2,715 A


2500

Current (Amps)

2000

1500

Phase 1
1000

Phase 2
Phase 3
Neutral

500

0
0:00:00

0:00:00

0:00:00

0:00:00

0:00:00

AEP Data Fault Currents

Transient event: I 3.0 kA (2,121 A-rms)

74 total events
39 events with >4,242 A-pk (3,000 A-rms)
19 events with >5,657 A-pk (4,000 A-rms)
13 events with >7,071 A-pk (5,000 A-rms)
7 events with >14,142 A-pk (10,000 A-rms)
Highest current = 17,765 Apk (222
milliseconds)
Longest duration = 1.785 seconds (5209
Apk, 3683 Arms)

07/11/2008
01:24:20.500

07/11/2008
01:24:27.425

HTS cable never taken out of service.

No measurable thermal response in


HTS cable or terminations.

Development
status up to 154kV
EPRI Superconductivity
HTS Cable
Systems in Korea
Conference
Evaluation of 100m long
12 Nov.HTS
2008Cable System
22.9kV 50MVA

KEPRI (KEPCO)
-Mo Yang
S. K.Byeong
LEE
Principal Research Engineer
Electric Power R&D Center
LS Cable Ltd
1 /31

Contents

About DAPAS program

R&D Results of HTS cable in 1st & 2nd Phase


Plan of 3

rd

Phase

Conclusion

2 /31

DAPAS program
DAPAS program

Development of Advanced Power system by Applied Superconductivity tech.


Name of the superconductivity frontier program in Korea
Selected on May. 2001 by MOST
Funded about 100 million US dollars for ten years from government.

The primary target


R & D and commercialization of the developed HTS products
Budget
z

10 years(2001~2010)

2007. 04 - 2008. 03

148 million $ ( Gov. : 100 & Ind. : 48 )


14 million $ ( Gov. : 10 & Ind. : 4 )

3 /31

Development targets for each phase


Phase
FY
Target

1st Phase
2001

2002

2003

Core technology
(to develop the HTS
wire and system
technology)

Power
cables

3rd Phase

2nd Phase

50MVA, 22.9kV
cable

2004

2005

2006

Pre-commercial pilot
(to improve the 1st
phase technology and
develop the prototype
devices)

2007

2008

2009

2010

Commercialization

(Field test and development of


the industrial technology for
commercialization)

50MVA, 22.9kV,
100m system

1GVA, 154kV,
3 phase

Transformers

1MVA, 22.9kV
Single phase

core
technologies

33MVA, 154kV
Single phase

Fault-current
limiters

6.6kV, 200Arms
SFCL

22.9kV,
630Arms SFCL

22.9kV, 3kA &


154kV, 4kArms

100~ hp
motor

1MVA~
motor

5MVA
motor

Motors

4 /31

Highest voltage class


120m 250m

50m

225kV

3 phase, 1 cryo, CD
3 phase, 3 core, CD
3 phase, 3 core, WD
1 phase, CD

Succeeded
Failed

DAPAS

Warm Dielectric
Cold Dielectric

1 core 3 ph

AMSC&Nexans
LIPA (~07)
(~11)
LIPA
SPE

154kV
DAPAS (~11)

LIPA 2

SEI&TEPCO
(~11)
77kV
66kV

36kV
24kV
12.5kV

AEP

SPE project

SEI & TEPCO (~01) Swire & NKT


(~07)
NKT (~02)
AMSC (~07)
DAPAS
(~04)

Swire &
NKT(~11)

IGC & SEI (~07)

Pirelli, AMSC,
Swire & IGC (~00) DTE (~01)
100m

138kV

Furukawa
(~04)

SEI (~99)

30m

1G wire
2G wire

Albany

200m

350m

500m 620m

34.5kV
22.9kV
13.8kV

1,780m
5 /31

History of HTS power cable in DAPAS


2001

2003

2005
Aug., 2005
Long Term Test

5m Cable core +
10m Cooling System

30m Single Phase


HTS Cable System
22.9kV, 50MVA

30m Three Phase


HTS Cable System
22.9kV, 50MVA
6 /31

HTS Cable in KEPCO Testing Center in 2006


Fully simulating real grid conditions
Pipe Duct [15 m]

Termination (Load)

Tunnel (55 m)

Termination (Power source)


Joint
box

U-bend
On the ground
[30 m]

Joint box
Ground level
Termination (Load)

Termination (Power source)

7 /31

Specification
Voltage : 22.9kV (Nominal), 13.2kV(Phase)
Current : 1,260A (50MVA)
Fault Current : 25kA, 15cycle
Cryogenic system : Closed loop cryo-coolers
Cable length : 100m

Approx. 2100

Insulator

Cryostat

Approx. 3500

Cable

Termination

Bellows

Cable

Cable core

Cryostat

Bellows

Approx. 3500

Joint Box
8 /31

Installation
Installation & handling of HTS cable are same as ordinary cable

Tunnel

Pipe duct (175mm)

Snake and cleats

9 /31

Evaluation
Specification of type-test
- Optimal test items & conditions
- Suitable to real grid application
Proposed to IEC SB1 by LS Cable ( under discussing )
Certification by 3rd party test institute
- Kinetrics, Canada
Confirmation by end user
- KEPCO/KEPRI
- Gochang power testing center
10 /31

Test Results (I)

Voltage & Current

Load Cycle Test at 1.5Uo for 30 days was successfully finished


8h
(1260A)

1 cycle

Voltage
(20kV ; 1.5U0)

Current

16h (No load)

Time (h)

PD and dielectric loss were tested successfully


* High Frequency Antenna

Applied Voltage (kV)

PD (pC)

Tan

< 10

0.00002

10

< 10

0.000027

13.2 (Uo)

< 10

0.000039

20.1 (1.5Uo)

< 10

0.00004

33 (2.5Uo)

< 10

0.000041

* Background noise : 5~10 pC

11 /31

Test Results (II)


AC Dielectric Security Test @2.5Uo for 24hours was passed

No degradation after all electrical & thermal cycle tests


2
0
1
x
6
.
1
2
0
1
x
4
.
1

Operating range

2
0
1
x
2
.
1
3
0
1
x
0
.
8

P hase
P hase
P hase
P hase
P hase
P hase

3
0
1
x
0
.
6

Voltage (V)

2
0
1
x
0
.
1

I c c rite rio n (1 u V /c m )

3
0
1
x
0
.
4
3
0
1
x
0
.
2

R
S
T
R
S
T

@
@
@
@
@
@

75K
75K
75K
72K
72K
72K

Result

Phase
(Cable)

Design
@ 75 K

75 K

72 K

3 kA

3.01 kA

3.34 kA

3 kA

3.06 kA

3.43 kA

3 kA

3.03 kA

3.34 kA

0
.
0
3
-

0
1
x
0
.
2
-

0
0
5
,
3

0
0
0
,
3

0
0
5
,
2

0
0
0
,
2

0
0
5
,
1

0
0
0
,
1

0
0
5

C u rre n t (A )

* Operating temperature : 72 ~ 75 K
* Operating current range : ~ 1.8 kA

12 /31

AC Loss
AC Loss was measured by calorimetric method on site
Loss (W)
Design
Heat Loss AC loss

Measured
Total

Heat Loss AC loss

W/m.phase @ 1260Arms
Total

70m

165.0

210.0

375.0

164.8

255.2

420.0

AC loss : 1.21 W/mphase

30m
(U-band)

105.0

90.0

195.0

102.9

113.2

216.1

AC loss : 1.25 W/mphase

165.0

135.0

300.0

180.0

157.6

337.6

Cable

Termination

0.8W/mphase @ 1260Arms in the Lab

13 /31

Plan (the 3rd phase)

14 /31

Target of 3rd phase (2007 ~ 2011)


R&D of 154kV, 1 GVA HTS Cable
- Specification : 154kV, 1GVA, 3phase, 100m
- Install the Power Grid in KEPCO Testing Center
154kV Over Head Line
(Youngkwang Nuclear Plant))

300m

154kV 2000SQ
XLPE 2 LIne

154kV

Tunn
el
10

0m
HTS C
able w
ill be
instal
led

in 201
0

Substation at Gochang
15 /31

Peak and average load for a year


70000

After 1997
financial
crisis in
Korea

Peak load
58994

Average load

60000

Last year
2007, over
60GW

54631
51246
47385

50000

45773
43125

Capacita (MW)

41007

40000

37293
35851
32996

30000

20000
25621

24577

1997

1998

27320

30327

32559

34985

36809

2002

2003

39057

41625

43513

10000

0
1999

2000

2001

Year

2004

2005

2006

16 /31

Necessity of Transmission HTS Cable in KEPCO


Status and Analysis of KEPCO Grid
1) Regional Load : Highest Seoul Region (42%)
2) Underground Cable among T/L : Highest Seoul Region (73.9%)
South-East
Region
30%

3) Increasing Underground T/L : about 12.68% (the rate of


Underground T/L in Korea)

Seoul
51.3%

Total

Kyunggi
18.3%

12.68%

Chungnam
5.0%

South-West
Region
8%
Middle
Region
13%

Kangwon
5.3%

Incheon
29.5%
Chungbuk
6.2%

Daegu
21.9%

Junbuk
6.1%

Gwhangju
26.5%

East Region
7%

Kyungbuk
4.1%

Daejun
45.2%

Jeju
11.9
%

Seoul
Region
42%

Ulsan
18.7%

Kyungnam
7.4%

Busan
31.5%

:C-Km

Voltage

T/L Length

Rate(%)

345kV

93

154kV

1,143

92

66kV

13

(As of 2007)
17

17 /31

Necessity of Transmission HTS Cable in KEPCO


Cu Conductor

150mm

HTS
Superconductor
LN2

800 mm
OF Cable (345kV, 840A, 2cct)

150 mm
HTS SC Cable
(154kV, 3.75kA, 1cct)

18

18 /31

Applying Concept of Transmission HTS Cable in


KEPCO
Applying Scenario of Transmission HTS Cable
345kV Substation
154kV Overhead Line
:Suburbs Large City
154kV Conventional Cable
154kV HTS Cable
: Center of Large City, high load density

Considerable Places for Applying HTS Cable to KEPCO Grid

Replacement

from Old Conventional Cable

Construction of New T/L in Large City

Enlargement of T/L due to increasing load in Large City

19

19 /31

Modeling of Transmission HTS Cable in KEPCO


Fault Analysis of 154kV HTS Cable by Using EMTDC
C

Ia

ISb

ISc

A
3kA

6kA

9kA

12kA

15kA

Ib

Ic

ISa

20 /31

Design of 154kV/1GVA HTS Cable


Electrical Characteristics
- Rated Voltage : 154 kV
(U0, Um = 89, 170 kV)
- Rated Current : 3.75 kA

Former/Stabilizer
HTS Phase Conductor
Insulation
HTS Shield

- BIL : 750 kV
- Design Fault Current

LN2

: 50 kA, 1.7s
Physical Characteristics
- Cold Dielectric Design
(Single Phase in One Cryostat)

Inner Cryostat
Thermal Insulation
(MLI + Vacuum)
Outer Cryostat

154 kV, 1GVA HTS Cable Cross Section


21 /31

Core Design for 154kV/1GVA HTS Cable


154kV/1GVA Stabilizer Design
-Fault Condition : 50 KA/ 1.7s

15.5 cycle
10.5 cycle
5.5 cycle

Temp. Limit : 94 K (5 bar)


Initial Temp. : 77 K

Stabilizer Size Min. 610 mm2

22 /31

HTS Wire Evaluation for Cable Application


The Mechanical & Thermal Properties of multi-kinds of HTS wires evaluated

Tential Stress

Multi-Bending

Thermal Cycling & Twisting

23 /31

Insulation Design of 154kV HTS Cable


99

90
80
70
60
50
40
30

Br e a kdown we ibu ll pr oba bility [ % ]

Variable
100
125
170

20
10
5
3
2
1
Shape
25.18
26.39
20.19

Scale N
AD
P
68.39 15 0.633 0.088
61.65 15 0.310 >0.250
55.76 15 0.431 >0.250

0.1

35

40

45
50
55
60
65
Br e a kdown s tr e n gth [ kV/ mm]

70

Variable

90
80
70
60
50
40
30

100
125
170

20
10
5
3
2
1
Shape
16.10
17.47
17.64

Scale N
AD
P
120.6 15 0.540 0.164
110.8 15 0.543 0.160
100.9 15 1.092 <0.010

0.1

75

65

AC Weibull Test

70

80
90
100
110
Br e a kdown s tr e n gth [ kV/ mm]

120

130

Impulse Weibull Test

50

11

45
40

y = 51.097x

B r eak d o wn vo l tag e [ k V ]

Br e a kdown w e ibu ll pr oba bility [ % ]

99

-0.0336

PPLP for EHV application

35
30
25

y = 40.175x

-0.0235

y = 40.043x

-0.0514

Insulation Thickness

20
15

< 15mmt

10
5
0
1.E+00

100
1.E+01

1.E+02

1.E+03
T i me [s e c ]

125
1.E+04

170
1.E+05

1.E+06

Overall Diameter < 145mm

AC V-t Test
24 /31

Cryogenic Characteristic Test of 154kV/1GVA HTS Cable


[ Cryogenic Vessel for Variable Temp.]
66K~77K, 5bar

[ DC power supply ]
DC 15,000 Amp / 5V

25 /31

Termination of 154kV/1GVA HTS Cable

26 /31

Cryogenic System of 154kV/1GVA HTS Cable


LN2
Storage

CryoCryo-Cooler

Phase A

LN2 Flow

Phase B

Phase C

5600W @ 65K

27 /31

Testing Facility for HTS Cable by KEPCO


Place : Gochang Testing Center
Design : 2007.11
Start : 2008.3
Finish : 2009.9

154kV Superconducting Cable Test will be start 2009.6


28 /31

Testing Facility Design

PQ

OF

HTS Cable Test Field


(Tunnel)

GIL

29 /31

Status of Standard for HTS cable


2008. 6. 9 Berlin Germany
11th IEC TC90 Meeting,
Proposed the Test Procedure the HTS Cable, like as Ic Measurement Procedure.
Suggest the round robin test the HTS cable for standard
2008. 8. 27, Paris France
CIGRE SCD1 Working Group Meeting WG.15
(Superconducting and Insulating Materials for HTS Power Applications)
Proposal the Specification of HTS Application
Proposals for test procedures of HTS power equipment and electrical insulation.
CIGRE SC B1 (Insulated Cable)
Decide to make TF for studying the specification of HTS cable
Korea
The KS (Korean Standard) is in progress for
Ic Measurement Procedure of HTS Cable

30 /31

Conclusion
The 22.9kV 50MVA HTS cable system was developed
and evaluated
154 kV , 1GVA HTS cable system is being developed in the 3rd
Phase of DAPAS program
HTS Cable R&D is moving from Grid Test to Grid Use in the world
Suggestion on the Collaboration for studying
Standard of HTS Cable Testing Procedures

< 21/21 >

31 /31

< 21/21 >

32 /31

superior performance.
powerful technology.

Status of 2G HTS Wire Technology Development


and Manufacturing at SuperPower
Chuck Weber
Y.-Y. Xie, Y. Chen, X. Xiong, K. Lenseth, M. Marchevsky, A. Rar,
Y. Qiao, B. Gogia, A. Knoll, R. Schmidt, D. Hazelton,
and V. Selvamanickam
Funded by Title III Program, DOE and AFRL
Supported by CRADAs with Los Alamos, Oak Ridge, & Argonne National Laboratories
EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN
SuperPower, Inc. is a subsidiary of Royal Philips Electronics N.V.

SuperPowers 2G wire is based on high throughput


processes & superior substrate
High throughput is critical for low cost 2G wire and to minimize capital investment
SuperPowers 2G wire is based on high throughput IBAD MgO and MOCVD
processes
Use of IBAD as buffer template provides the choice of any substrate
Advantages of IBAD are high strength, low ac loss (non-magnetic, high resistive
substrates) and high engineering current density (ultra-thin substrates)

< 0.1 mm

20m Cu

2 m Ag
1 m YBCO - HTS (epitaxial)
~ 30 nm LMO (epitaxial)
~ 30 nm Homo-epi MgO (epitaxial)
~ 10 nm IBAD MgO
100 nm

50m Hastelloy substrate


20m Cu

YBCO
LaMnO3
MgO (IBAD + Epi layer)
Y2O3
Al2O3

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

Hastelloy C-276

SuperPowers 2G pilot manufacturing facility has


been operational since 2006

Majority of investment already made for 1000 km/year capability

Pilot Substrate
Electropolishing

Pilot IBAD

Pilot MOCVD

Pilot buffer Sputtering

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

Our main objective in 2008 was to meet market


requirements for 2G wire
Replace 1G wire in large HTS device demonstration projects in the
U.S. and around the world
Key requirements: Long length, availability, Ic, price
Supply large volumes of 2G wire to customers who have been waiting
to take advantage of the superior performance of 2G
Key requirements: Long length, Ic, additional performance metrics
such as in-field Ic, ac losses, joints, insulation, FCL metrics
Advance towards medium-term goal of replacing copper wire in
commercial HTS projects and challenge LTS wire in high-field
applications
Key requirements: Long length, availability, Ic, price, in-field
performance and other additional performance metrics
EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

900
800
700
600
500
400
300
200
100
0

2008 (GdY)BCO

6
2

Jc (MA/cm )

Critical current (A/cm-width)

High current metric: Capability of ~ 1000 A in 12 mm widths


achieved!

2007
GdYBCO
2006
Sm YBCO
2005
Sm YBCO

2008 (GdY)BCO

5
4
2007
GdYBCO

3
2
1

2006
Sm YBCO

2005
Sm YBCO

1
2
3
Thickness ( m)

Over 1+ m length,
Ic = 976 A = 813 A/cm

Thickness (m)
Ic measurement using continuous dc current
(no pulsed current) across entire tape width
of 12 mm. No patterning

3.3 m film made in 10 passes: Ic = 976 A = 833 A/cm (Jc = 2.44 MA/cm2)
2.1 m film made in 6 passes: Ic = 929 A = 774 A/cm (Jc = 3.68 MA/cm2)
All achievements using production buffer tapes
EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

High current technology is being transferred to


pilot MOCVD
500

5.0E-07

Minimum Ic > 400 A/cm-w over 55 m length

4.0E-07
Voltage (V/cm)

Ic (A/cm-w)

400

300

200

3.0E-07
2.0E-07
Ic = 450 A/cm-w at 0.1 V/cm voltage criterion

1.0E-07
0.0E+00

100

-1.0E-07
0
0

10

15

20

25

30

35

40

45

50

55

100

200

300

400

500

Current (A/cm-w)

Position (m)

Over 55 m length,

Over 10 m length,

Minimum Ic = 481 A = 401 A/cm

Ic = 481 A = 401 A/cm

At 0.2 V/cm voltage criterion

At 0.1 V/cm voltage criterion

All achievements using production buffer tapes.


EPRI 8 Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN
MOCVD
process speed 90 m/h (4mm equivalent)
th

In-field performance metric: dramatic improvements


achieved by Zr doping
180

0.7 micron SmYBCO

450

3.5 micron SmYBCO

160

0.7 micron GdYBCO

400

2.8 micron GdYBCO

140

0.7 micron Zr:GdYBCO

350

3.3 micron Zr:GdYBCO

120

Ic (A/cm)

Ic (A/cm)

BZO additions have been very effective in improving in-field performance


of PLD films, but was yet to be demonstrated with MOCVD.

100
80
60
40

300

229 A/cm

250
200

186 A/cm

150
100

20

50

77K, 1T

77K, 1 T

-20

20

40

60

80

100

120

-20

20

40

60

80

100

120

Angle between field and tape (degrees)

Angle between field and tape (deg)


Data from Y. Zhang,
M. Paranthaman, A.
Goyal, ORNL

Gd substitution results in strong pinning parallel to the tape.


Zr doping strongly enhances pinning perpendicular to tape & in intermediate fields
2 to 2.5x improvement
IcSuperconductivity
by Zr doping.
Thin
films
and
EPRI 8in
Annual
Workshop, November
12-13, 2008,
Oak Ridge,
TN thick films
th

Excellent in-field performance at 65 K, 3 T


550

Title III Phase 3 program


goal is Je without stabilizer
of 15,000 A/cm2 at 65 K, 3 T

500
450
400

2008: 3.33 m Minimum Ic = 267 A/cm


corresponds to Je of
Zr:(Y,Gd)BCO

350
300

2008: 3.15 m
Zr:(Y,Gd)BCO

250
200

2007: 2.8 m
(Y,Gd)BCO

150
-20

20

40

60

41,000 A/cm2 at 65 K, 3 T
Ic perpendicular to tape =
340 A/cm corresponds to Je
of 52,300 A/cm2
Data from Y. Zhang,
M. Paranthaman, A.
Goyal, ORNL

80 100 120

Angle (deg)

Ic (77 K, 1 T)
B // c
Minimum Ic

2008 Zr-doped (Gd,Y)BCO

2007 (Gd,Y)BCO

Improvement

340 A/cm

181 A/cm

88%

267 A/cm

160 A/cm

67%

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

Zr-doped chemistry has been successfully transferred


from Research system to Pilot MOCVD

Crtical current (A)

160
150

(Y,Sm)BCO
(Y,Gd)BCO
(Y,Sm)BCO with Zr
(Y,Gd)BCO with Zr

140
130
120
110
100
90
80
70
60
50
40
30
20

Data from Y. Zhang,


M. Paranthaman, A.
Goyal, ORNL

10
0
-20

20

40

60

80

100

120

140

160

180

Angle between magnetic field & tape (degrees)

Long-length wires are now being produced with Zr-doped chemistry


EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

In 2007, we demonstrated world record high-field


magnet
Central Field (T)

19T background

Coil ID

9.5 mm (clear)

Winding ID

19.1 mm

Winding OD

~ 87 mm

# of Pancakes

12 (6 x double)

2G wire used

~ 462 m

Average Ic of wires
in coil

78 A in 4 mm width
(77 K, self field)

self field

30
25

26.8 T @ 175 A

20
15
10
5

9.81 T @ 221 A

0
0

50

100

150

200

250

Current (A)
SuperPower coil tested in NHMFLs unique,
19-tesla, 20-centimeter wide-bore, 20megawatt Bitter magnet

0.73 T generated by coil at 77 K

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

10

Coil tested by H. Weijers, D. Markewicz, & D. Larbalestier, NHMFL, FSU

New coil in 2008 with Zr-doped (Gd,Y)BCO wire


with better in-field performance
2007
coil

2008
coil

Coil ID (mm) clear

9.5

21

Winding ID (mm)

19.1

28.6

Winding OD (mm)

~ 87

~ 87

~ 51.6

~ 56.7

~ 462

~ 480

# of turns

~ 2772

~ 2664

Coil Je (A/mm2) per


amp of operating
current

~1.569

~1.635

Coil constant (mT/A)

~ 44.4

~ 41.9

Coil Height (mm)


# of double pancakes
2G tape used (m)

Wire Ic (A) 4 mm

EPRI 8 Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN


th

2007 coil

2008 coil

72 82

72 to 97

11

30% higher field in 2008 coil made with wire with


improved in-field performance
(Y,Sm)BCO wire 2007 coil
(Y,Sm)BCO wire 2007 coil
Zr:(Gd,Y)BCO wire for 2008 coil
Zr:(Gd,Y)BCO wire for 2008 coil

Ic (A) for 4 mm wide wire

35
30
25

Temperature

77 K, 1 T (ORNL)

20

77.4
70.25
65.8
64.5
63.8

15
10
75 K, 0.92 T (LANL)

5
0
-20

20

40

60

80

100

(K)

120

140

Coil
Max Central
current
Field
(A)
(T)
0.95
22.7
44
1.84
54
2.26
2.39
57
58
2.43

160

Angle between field and wire (degrees)

Temperature

2008 coil with Zr-doped


(Gd,Y)BCO

2007 coil with


(Y,Sm)BCO

Improvement

77 K

0.95 T

0.73 T

30%

65 K

2.39 T

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

12

This improvement remains effective at low T


[Ic/Ic@ 77K 0T- 2008]/[Ic/Ic@77K 0T-2007]

1.50
60 K
50 K
40 K
30 K
20 K

20-35% improvement in magnetic field range up to 4T


T=
1.25

1.00

0.75
0

0.5

1.5

2.5

3.5

B[Tesla] at 30o w.r.t. the tape surface

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

4.5

Measurement done by
M. Ogata and K. Nagashima
at Railway Technical
Research Institute

13

Continued routine manufacturing of kilometer


lengths of fully buffered tape in CY 2008
In-plane texture (degrees)

8
7
6
5
4
0

200

400

600

800
1000
Tape position (m)

1200

1400

1600

12 tapes with complete 5-layer buffer stack, by ISS2007, and now over
40 tapes have been produced in lengths of 1,300 m to 1,500 with in-plane
texture of 5 7 degrees and excellent uniformity of ~2%
Manufacture of kilometer-lengths of high quality, fully-buffered tape was
routine throughout 1 year
EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

14

250

250

200

200

Ic (A/cm)

Ic (A/cm)

Challenges in fabrication of complete, kilometer


long 2G wire
150
100
50

150
100
50

0
0

200

400

600

800

1000

200

Position (m)

Ic (A/cm)

400
300
200
100
0

200

400

600

800

1000

800

1000

Kilometer lengths limited by a few


bad regions in an otherwise uniform
wire;
Major sources of the problems
identified:
MOCVD instability;
Mechanical damage;
Substrate defects

EPRI 8 (m)
Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN
Position
th

400
600
Position (m)

15

Aug. 2008: Yet another world record!


450
400
350
Ic (A/cm)

300
250

200 m
Ic > 350 A/cm
4 mm: 140 A

200
150
100

320 m
Ic > 350 A/cm
4 mm: 140 A

77 K, Ic measured every 5 m using continuous dc


currents over entire tape width of 12 mm (not slit)

50

Voltage criterion = 0.2 microvolt/cm

0
0

200

400

310 m
Ic > 350 A/cm
4 mm: 140 A
Except for three spots, Ic of rest of
1,030 m > 300 A/cm 4mm: 120 A
600

800

1000

Position (m)

Length (m)

Minimum Ic (A/cm) @ 0.2 V/cm

Ic Length (A-m)

1030

227

233,810

630

302

190,260

337

181,980

540

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

16

Aug. 2008: Ic > 300 A/cm achieved over 600 m


450
400
350
Ic (A/cm)

300
250
200
150

77 K, Ic measured every 5 m using continuous dc


currents over entire tape width of 12 mm (not slit)

100

Except for four spots, Ic of


rest of 630 m > 350 A/cm

Voltage criterion = 0.2 microvolt/cm

50
0
0

100

200

300

400

500

600

Position (m)

Length (m)

Minimum Ic (A/cm)
(0.2 V/cm)

Ic Length (A-m)

630

302

190,260

540

337

181,980

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

17

Remarkable progress in 2G HTS wire scale-up


over the last 6 years

1,311 m
935 m

160,000

790 m

120,000

1 m to 1,300 m
in 6 years

80,000

Sep-08

Jan-08

Apr-07

Aug-06

Dec-05

Apr-05

Aug-04

Nov-03

206 m
62 m 158 m
1 m18 m
97 m
Mar-03

427 m
322 m

Jul-02

40,000

595 m

100,000
10,000
1,000
100

World Records

10
May-02
Oct-02
Mar-03
Aug-03
Jan-04
Jun-04
Nov-04
Apr-05
Sep-05
Feb-06
Jul-06
Nov-06
Apr-07
Sep-07
Feb-08
Jul-08

200,000

Critical Current * Length (A-m)

1,000,000

Growth in
last year

Nov-01

Critical Current * Length (A-m)

240,000

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

18

Great strides made in 2008 in all key metrics


Metric

Improvement

ISS 2006

ISS 2007

ISS 2008

470

595

813

37%

Ic (A/cm) at 77 K, 1 T

116

229

97%

Ic (A/cm) at 65 K, 3 T

181

340

88%

Ic (A/cm) over 1 m

in past year

Ic over 200 m (A/cm)

246

227*

378*

67%

Length with Ic > 200 A/cm (m)

322

322

1030

220%

170

337

98%

Ic over 500 m (A/cm)


Length with Ic > 300 A/cm (m)

103

202

630

212%

Completed 2G wire Piece Length


(m)

322

595

1,311

120%

70,520

102,935

233,810

127%

0.73

0.95

30%

65

40

39%

Ic L (A-m)
Coil: Field at 77 K (T)
2G Wire Price ($/m)

100

*atRidge,
100 TN
to
EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak

200% higher speed than in 200619

Development of Practical Conductors - Joints


Location of joints
180
160
140

Ic (A)

120
100
80
60
40
20
0
0

100

200

300

400

500 600 700


Position (m)

800

900 1000 1100 1200

Per customers requirement, 1200 m long wire was produced with 11 splices in a production
operation.
Arrangement of the 12 segments along the length was decided based on communication with
customer so that the Ic profile would fit the coil winding requirements
EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

20

Excellent resistance measured in all joints and


mechanical robustness also demonstrated
1st test

6.00E-05

4.00E-05
Joint#1: 70-75m
5.00E-05

Joint#3: 250-255 m
Joint#4: 350-355m
Joint#5: 440-445m

3.50E-05

Joint#6: 560-565m

3.00E-05

After running thru 2" rollers 6 times


Voltage (Volt)

4.00E-05

Voltage (Volt)

After running thru 4" roller 3 times

Joint#2: 175-180m

Joint#7: 670-675m

3.00E-05

Joint#8: 760-765m
Joint#9: 890-895m
Joint#10: 980-985m

2.00E-05

Joint#11: 1120-1125m
1.00E-05

2.50E-05
2.00E-05
1.50E-05

0.00E+00

1.00E-05

-1.00E-05
0

20

40

60

80

100

120

140

Current (A)

All but one of the joints showed resistance


around 33 n, One joint showed a
resistance of 100 n, still within limit

20

40
Current (A)

60

80

Wires with joints have to run through the


reel-to-reel Ic test rig with 4 and 2
roller. No trace of degradation was
shown in I-V curves

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

21

Continuous multifilamentary 2G wire is now scaled to


15m lengths with new industrial process

4 mm
2

unstriated

ac loss (W/m)

100 Hz

5.1 x

multifilamentary
0
0.00

0.01

0.02

0.03

0.04

Bac rms (T)

0.05

Good Ic and reasonable ac loss


reduction achieved;
Coils were made with long length
multifilamentary wires, showed lowered
ac loss in magnetic field and with
transport ac current as reported at DOE
Peer Review (July 2008)

0.06

EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

22

Customer-driven development of insulated wire


Several customers, primarily for coil applications, required insulated 2G wire
After evaluating a number of vendors, we procured a system for in-house
fabrication of insulated wire
System in place and being used for both 12 and 4 mm wide wire

Preliminary test showed no breakdown at 1000 V with 0.0025 mm polyimide film


Deliveries of insulated wire already being made.
EPRI 8th Annual Superconductivity Workshop, November 12-13, 2008, Oak Ridge, TN

23

1. AC Loss Characterization of HTS Coils


2. Proposed Integrated Cryo-cooled Test Bed for High
Power Density Power System Components
Sastry Pamidi
Florida State University
Center for Advanced Power Systems
Tallahassee

AC Losses With Liquid Nitrogen Boil-off


Measurements

Useful for Total AC loss measurements on coils


up to 140 mm in diameter and 250 mm tall.
Wide measurement range: fraction of a watt to
100 W
Coils can be arranged in any orientation with
respect to magnetic field
Magnetic field amplitude: up to 200 mT
Transport current amplitude: up to 650 A

AC Losses in YBCO Coils with


Nitrogen Boil-off Technique
Diameter - 145 mm
Length - 250 mm

Calibration
Heater

Calibration Highly Reproducible

Sample Coil
System has been tested and calibrated up to 60 W, 150 mT, 200 Hz

AC Losses in YBCO Coils with


Nitrogen Boil-off Technique
Losses are < 0.1 W in parallel and perpendicular field 150 mT, 55 Hz & 60 mT, 200 Hz

YBCO Coils, 29 turns, of wire ~4.5


m conductor
45 mm diameter, Ic = 32-34 A

Super Power Coil Losses


< 0.1 W
@ 150 mT, 55 Hz &
60 mT, 200 Hz

Two coils were tested


Coil made of normal YBCO tape and Coil
made of Striated YBCO ( five filaments).
Both have < 0.1 W losses. 0.1 W is
minimum detectable limit of the
measurement system

Objectives of the Proposed Integrated Cryogenic System


for Multiple High Density Power System Components

Address system issues arising from the complex


interrelationships between the electrical, thermal and
material performance characteristic to achieve high
power density systems through cryo-cooling.
Design and manufacture a 400 kVA, 13,8 kV HTS
transformer for application in Test loop
Design and manufacture a +/- 5 kV MVDC HTS cable

A Schematic of the Proposed Integrated Cryogenic System for


Multiple High Density Power System Components

Main Cryo
station

Capacitor
Bank

HTS
Transformer

AC/DC
Converter

HTS fault
Current
limiter

Flow sensors
Cryo booster
Temp sensors
Valves
Blowers
Electrical bushing

HTS
AC/DC
Cable

Load
Bank

Proposed Applications of Cryo-cooled


Test Bed
Understanding of cryogenic system integration
issues
For external users to test high density power
devices
Comprehensive test environment with PHIL
testing and heat loads and thermal gradients under
test conditions
Demonstrate integrated high power density
electrical network

Proposal of
9th Annual EPRI Superconductivity Conference
In Korea

Outline
Date

Host

From 9th Nov.(Monday) to 11th Nov.(Wednesday)


EPRI, KEPCO(KEPRI), and KIASC
* KIASC : Korea Institute of Applied Superconductivity and Cryogenics
z International Program Committee ;

Program
Committee

EPRI, KEPRI, KIASC


z Local Program Committee ;
KERPI, KIASC, KERI, LSC, KIMM, etc.
z KEPRI in Daejeon Korea (2 days)

Conference
Site

Accommodation : Yusung Hotel, Rivera Hotel etc


z Technical Tour : Gochang Test Field (1 day)
z LS Cable Factory Tour (1day) : option

Schedule (Tentative)

Nov. 2008

First Announcement
(9th Annul EPRI Superconductivity Conference)

Feb. 2009

Website Opens

Aug. 2009

On-Line Submission of Abstracts

Sept. 2009

Abstract Acceptance & On-line Registration

Oct. 2009

Last Announcement with Final Program

Nov. 2009

Conference

Conference Schedule (Tentative)


z First day ( KEPRI in Daejeon)
Registration
Presentation
Welcome Party and Dinner
z Second day
Presentation
KEPRI Superconducting Lab Tour in KEPRI
z Third day (Technical Tour : Gochang Test Field)
Move : Daejeon -> Gochang (by Bus)
Test Field Tour including 22.9kV and 154kV superconducting cable
Excursion : Sunwonsa Temple
z 4th Day (Option) : LS Cable Factory Tour

What benefit will you get ?


You can contact with many experts from oversea
You can get the current information on Superconductivity
System more broadly including Asia
You can see the overall of the Superconductivity System. For
Example, HTS Cable, SFCL, Flywheel developed by Korea
You can look around Gochang Test Center, specially new
underground test lab that is the biggest one in the world
through technical tour
Lastly, you can enjoy beautiful sightseeing that may be great
mountain covered with colorful tree at Autumn
5

Technical Tour

Seoul

Daejeon
Gochang
Busan

Seoul

Daejeon

Busan

Testing Facility for HTS Cable by KEPCO


Place : Gochang Testing Center
Start : 2008.3
Finish : 2009.9

154kV Superconducting Cable Test will start 2009.6

KEPRI in Autumn Conference site

Naejangsan national Park

10

SunWonSa Temple

11

High Opportunity Commercial


Applications for HTS Cables
Eighth Annual EPRI Superconductivity Conference
Oak Ridge, TN ~ November 12 13, 2008

Introduction
The scope and successful operation of recent HTS cable
projects has led to:
Increased interest in HTS cables
Increased interest in their characteristics
Increased interest in possible applications

Superconductor Cables are an Exciting New Tool for


Utility Planning Departments, but requires:
Education on their benefits and applications
Education on what is involved to install and operate

Agenda
Review of HTS cable applications which appear to be of
greatest interest during educational presentations
Issues moving forward

Key HTS Cable ELECTRICAL Characteristics


Very high power transfer capability compared to
conventional cables solves many siting problems
Very low impedance reduces loading on parallel lines
and equipment
Minimal magnetic field and elimination of heat
simplifies placement concerns and is easy on the
environment
Optional HTS cables with fault current management
capabilities eliminate need to upgrade existing equipment
HTS Cables offer unique capabilities

Power Transfer Equivalency of HTS Cables

345kV

XLPE Cable

230kV

XLPE Cable
HTS

138kV

XLPE Cable

Same Voltage, More


Power
Greatly increased
power transfer
capacity at any
voltage level

HTS

69kV

XLPE Cable
HTS
XLPE Cable

34.5KV

HTS 100
XLPE Cable

13.8 kV
0

MVA at 13.8 kV

200

400

600

800

1000

Power Transfer Capability - 3 MVA

HTS Cables provide much greater power transfer than conventional cable
* No XLPE cable de-rating factors applied.
HTS rating based on conventional 4000A breaker rating

Power Transfer Equivalency of HTS Cables

345kV

XLPE Cable

230kV

XLPE Cable
HTS

138kV

XLPE Cable
HTS

69kV

XLPE Cable
HTS
XLPE Cable

34.5KV

HTS
XLPE Cable

13.8 kV
0

200

400

600

800

Power Transfer Capability - 3 MVA

Same Voltage, More


Power
Greatly increased
power transfer
capacity at any
voltage level
Same Power, Lower
Voltage
New MV versus HV
Siting Opportunity
1000

MV Transmission
Ideal for NIMBY &
ROW sparse
environments

HTS Cables provides transmission-level power transfer at medium voltage


* No XLPE cable de-rating factors applied.
HTS rating based on conventional 4000A breaker rating

Project HYDRA Overview

Current ConEd System Configuration

Copper power cables

ConEds System of the Future:


Interconnected Distribution Substations
Integral Fault Current Limiting

HTS power cables

DHS Project supports development of a more resilient grid with increased


reliability and reduced power outages

Paralleling Urban Buses


Building on Project HYDRA

Typical 2-transformer
urban substations

VIRTUAL BUS
Connection

Virtual Bus must Handle high power flow between the substations
Conventional interconnection techniques not practical
Normal impedance during steady state operation would limit power transfer
Multiple cable circuits would be required

Paralleling low-side buses with conventional technology


is not practical

Paralleling Urban Buses: HTS Solution

Typical 2-transformer
urban substations

4000A
Load Current

HTS Cable Advantages


Low impedance allows for efficient power transfer
Ampacity of HTS cable capacity requires only one circuit
e.g. 100MVA at 15kV
Reduced external EMF and heat generation simplifies placement

HTS Cable Enables Low Side Interconnection

Paralleling Urban Buses:


Addressing Fault Currents

Typical 2-transformer
urban substations

With Fault Current Limiting HTS Cable

Fault Current
Contribution

60,000A

Reduced
Fault Current
Contribution

30,000A

Fault Current Limiting HTS Cable provides many benefits:


Reduces the fault current that flows through the HTS cable
Reduces fault current contribution to faults on either substation bus
Eliminates need to replace or upgrade station equipment
Fault Current Limiting HTS Cable makes low side networking practical

Paralleling Urban Buses:


The Appeal

Typical 2-transformer
urban substations

Typical
Loading
Practice

Total Load 60% total transformer MVA

Total Load 60% total transformer MVA

Advantages of Paralleled Substations Simple Case


Connect additional load without additional transformers or new substations
Increases transformer asset utilization
Reduces cost of N-1 contingency planning; Only 1 transformer required
versus 2
Increased interconnectivity protects vulnerable, critical loads in the event of
a catastrophic failure
Paralleling Dense Urban Load Centers Leads to Operational Efficiencies

Paralleling Urban Buses


Increased Asset Utilization

Transformer Asset Utilization TS Inteconnected


Substations; n-2 Criteria

100%

100%

90%

90%

80%
70%

2 XFRMR
3 XFRMR
4 XFRMR
5 XFRMR

60%
50%
40%
30%

Transformer Asset
Utilization

Transformer Asset
Utilization

Transformer Asset Utilization TS Inteconnected


Substations; n-1 Criteria

80%
70%

3 XFRMR
4 XFRMR
5 XFRMR

60%
50%
40%
30%

None

Number of Interconnected Substations

None

Interconnecting Substations increases transformer asset utilization*


Improves financial performance measures
Reduces the number of transformers required to serve load
* Theoretical limits

Number of Interconnected Substations

Paralleling Urban Buses


Serving Additional Load

HTS Interconnected Substation Loading Increase


Capability; n-2 Criteria
180%

100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%

160%
2 XFRMR
3 XFRMR
4 XFRMR
5 XFRMR

% Increased Load
Capability

% Increased Load
Capability

HTS Interconnected Substation Loading Increase


Capability; n-1 Criteria

140%
120%
3 XFRMR
4 XFRMR
5 XFRMR

100%
80%
60%
40%
20%
0%

Number of Interconnected Substations

Number of Interconnected Substations

Interconnecting Substations significantly increases load serving capability*


Significantly reduces need to expand or build new substations
* Theoretical limits

Segregated (Remote) Substation

Larger, HV station components


located where space is available

HTS CABLE

MV HTS cable acts as low


impedance, high capacity, virtual
bus between transformer and
switching stations

Reuse existing ROW


Simplified placement due to lower
voltage level
FCL HTS cable may reduce MV
breaker requirements

Smaller, remotely
located, lower voltage
switching station in space
or real-estate constrained
location

Permits new substation construction in spite of severe real estate constraints

Segregated (Remote) Substation

Multiple HV stations located


where space is available to
provide for contingency
planning

MV HTS cables provide links and fault current control


HTS CABLE

HTS CABLE

HTS Cables can be consistent with tradition reliability design practices

Overcoming Transmission Line


Siting Dilemmas

Power system reliability and load growth requires new


interconnections to strengthen the grid and supply new load

GG
GG
Substation A

Substation B

Underground construction
Preferred by the public
Better storm performance
HTS offers simplified
burial requirements
Space efficient
Lower voltage option simplifies
siting
Environmental benefits
No EMF emissions
Environmentally friendly
insulation system
Positive public relations

HTS Cables Very Attractive to Address Transmission Siting Issues

Simplifying Transmission Siting


One
OneMV
MVHTS
HTSCable
Cablecan
canreplace:
replace:
Many
Manyconventional
conventionalunderground
underground
circuits
circuits
Overhead
Overheadtransmission
transmissionline
line

Photo courtesy Consolidated Edison

HTS Cables Offer New Options to Siting Power Lines

Connecting Generating Stations to Grid


or Any Short, High Power Link
GG
GG
Generation
Station

HTS Section for sensitive


or ROW restricted areas

Conventional construction
for balance of link

Grid PCC

Advantageous for short, high power transfer situations


Permits use of more compact, easier to site, lower voltages
Environmentally and politically preferable underground
construction
Lower losses
Ideal for routes including sensitive or ROW restricted areas
HTS Cables Can Ease or Eliminate or Simplify Short Link Issues

Grid Congestion
Load Current
Load Current

Generation

G
Load

G
Undesired
Loop
Flow

Grid Congestion has many causes


Insufficient line ampacity
Overloaded critical assets and
circuits
Undesired loop flows
Stability issues

Line loading, equipment & operational limitations can lead to grid congestion

HTS Cable Can Alleviate Grid Congestion


During normal operating conditions, the HTS cable is a low impedance path
and allows for the transfer of large amounts of power.
Reduced
line
losses

Load Current
Load Current

Generation

G
G

Increased
line
loading
Reduced
loading
on assets

HTS Cable
High Normal Current
Low Fault Current

Load Current

Numerous benefits accrue:


Increased corridor transfer capability of the corridor
Reduced loading on parallel circuits
Improved efficiency from lower I2R losses on all lines

Load

During Faults HTS Cable Limits Fault Currents


When an HTS cable with resistive FCL capability becomes resistive during a
fault, the fault current must use relatively lower impedance paths
Fault Current

Generation

G
G

HTS Cable
High Normal Current
Low Fault Current

Fault
Current

Fault

Increased Fault
impedance increases
total circuit fault
impedance

The HTS cable results in higher system impedance during faulted conditions
lowering overall fault current magnitudes

Conventional Vs. Project Hydra Style HTS Cable

Fault Current Level


Change (kA)
MVA Transfer
Capacity Increase

Sub#1

Sub #2

230 MVA Base

42 kA

56 kA

2nd Conventional Cable

+230

+5

+2

Replacement HTS Cable

+248

-12

-3

Scenario
Base Case

Installing HTS Cable in the grid simultaneously can increase power


transfer capability and manages fault current levels

Summary

HTS Cable Systems offer solutions


unavailable or impractical until now
As utilities are exposed to HTS cable
concepts, applications become apparent
Most utility personnel have had little
exposure to HTS cables and
their characteristics
This exposure is for the most
part limited to a utilitys advanced
technology or R&D functions
i.e., those that are exposed to normal planning issues are not
considering HTS solutions
The industry must undertake an Educational Awareness program to
ensure HTS cables become part of the engineers toolset

HTS cable applications are nascent


Education is required to spur demand

Technology & Engineering Division

Development of HTS Cables for DC Power


Transmission and Distribution
Joseph V. Minervini
Leslie Bromberg
Makoto Takayasu
Christopher Miles and Nicholas R. LaBounty

MIT Plasma Science and Fusion Center


Eighth Annual EPRI Superconductivity Conference
Doubletree, Oak Ridge, TN ~ November 12 13, 2008

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Outline

HTS DC Advantages
Cable Design Concepts
Chubu-MIT HTS DC Cable Collaboration
Long Length Cooling
Current Lead Cooling
Potential Near Term Application
Conclusions

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

DC Superconducting Transmission Line


Technology & Engineering Division

Advantages:
No DC resistive losses
No AC inductive storage
Low or no AC losses
Long range transmission of high currents, including undersea
Very high power ratings including transmission of several GVA
Fault currents limited by fast acting inverters at AC/DC and DC/AC ends
of the line
Low voltage transmission, if desired, limiting the need for high voltage
transformers
Simplified cable design, more amenable to using HTS tape geometry
Cable coolant also used to cool solid state inverters increasing capacity
and reducing high temperature aging degradation
Disadvantages: Invertors can add substantially to cost
Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

HTS DC Applications

HTS DC increases efficiency for long distance transmission


Opens other advanced technology opportunities:

Direct connection of alternative low-carbon or carbon-free power


sources:

Wind
Solar PV
Fuel Cell
Microturbine
other

Connection of advanced energy storage devices

Flywheel
Battery
Supercapacitor
Superconducting Magnetic Energy Storage (SMES)
other

Grid independence

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

System
Stability and
Power
Quality

Technology & Engineering Division

Off-Shore Wind Farm Power


Transmission
Using HTS DC Cable
DC-to-AC Power Conversion
HTS DC Transmission
Cables

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Solar Photovolatic or Concentrated Solar Thermal


Power Transmission Using HTS DC Cable
Solar PV

Solar and Wind

CSP

Transmit DC before conversion?

DC Power

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

DC Superconducting Power
Transmission Line Experiment in
Chubu University
&
Collaboration with MIT
Prof. Satarou Yamaguchi
Dept. of Electrical Engineering
yamax@isc.chubu.ac.jp

Center of Applied Superconductivity


and Sustainable Energy Research
(CASER)

Experimental Device in Chubu University


Parameters
current > 2.5 kA
voltage > 20 kV
length ~ 20 m
Sumitomo Bi-2223 cable
coolant; LN2
equipped with pump and
cryogenic cooler
72 K - 77 K

SC Cable
Photo of cross-section

former
copper wires

insulation layer

HTS Tape x 39

HTS Tape

insulation
30kVDC

center hole
for coolant path
inner spring

earth layer

former
copper wires
40

Side View
made by
Sumitomo

1st layer; 19
Tape conductor
2nd layer; 20

Bi-2223/ 100A
grade

Insulation Volt.

DC20kV

Insulator, PPPL

Outer radius

40

Center hole 14

Technology & Engineering Division

MIT High Current HTS


DC Cable Designs

Multiple Layers

Carpet Stack

Triplet

Twisted Triplets

Wedge Stack
Twisted
Triplets

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Use Basic Carpet Stack


tapes can be insulated or soldered

Square or rectangular stack


Base element former can be
conducting
non-conducting
Structural

Tape shape requires relatively long twist


pitches
AC losses not an issue for DC applications

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

25 kA at T = 65 K - 77 K
Carpet Stack triplets have highest Je
Allows for smaller cryostat and lower heat leak
Carpet Stack and wedge base conductors allow many
variations on cable patterns and total tape number

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Potential Opportunity
Data Server Centers

In 2006, electricity consumed by servers in U.S. data


Google datacenter near The Dalles Dam
centers (including cooling and auxiliary infrastructure)
represented about 1.5 percent of national electricity
use*.

Internet data center consumes ~ 12 kW/m2.


10 MW-50 MW+ total capacity in new centers

DC may be preferred
Minimizes conversion losses
~7-10% energy savings migrating to DC

No reactive power
Power multiplier: for 1 W dissipation saved, 1.5 - 2 W
cooling eliminated
*Report to Congress on Server and Data Center
Energy Efficiency, U.S. Environmental Protection
Agency, Aug. 2, 2007

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Expected Data Server Center


Power Growth

G. Lawton, Powering Down the Computing Infrastructure, Computer, IEEE, 40, issue 2, p 16-19, Feb. 2007.

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

DC Distribution Demonstration Developed by


LBNL and Industry Partners

Measured Best in Class AC System Loss Compared to DC


~9-12% efficiency improvement measured by elimination of transformer
and second AC/DC conversion
William Tschudi, LBNL

Benefits of 400Vdc

PV

AC Distribution
DC
300- DC/AC
400V

Lighting
loads
DC/AC
AC/DC

Ballast
FC
60 Hz AC
480V

AC/DC

Electronic
loads

DC/AC
AC/DC

DC/DC
VR

PSU
Motor
loads
AC/DC

DC/AC
AC/DC

DC/AC

ASD

Slides courtesy of Annabelle Pratt-Intel

Benefits of 400Vdc

PV

Facility Level

DC
300- DC/AC
400V

FC
60 Hz AC
480V

AC/DC

XX
DC/AC

Lighting
loads
DC/AC

AC/DC

Ballast

X
AC/DC

Electronic
loads
DC/DC
VR

PSU

AC/DC

X
DC/AC

Motor
loads

X
AC/DC

DC/AC

ASD

Slides courtesy of Annabelle Pratt-Intel

Benefits of 400Vdc

400V DC facility with DG


DC
300- DC/DC
400V

Lighting
loads

DC/AC

Ballast
60 Hz AC
480V

Electronic
loads

AC/DC

DC/DC
VR

DC/DC

PSU
Motor
loads
AC/DC
DC/AC

ASD

Slides courtesy of Annabelle Pratt-Intel

Benefits of 400Vdc

400V DC facility with SC Bus


DC
300- DC/DC
400V

Lighting
loads

DC/AC

Ballast
60 Hz AC
480V

Electronic
loads

AC/DC

DC/DC
VR

DC/DC

PSU
Motor
loads
AC/DC
DC/AC

ASD

Slides courtesy of Annabelle Pratt-Intel

Technology & Engineering Division

Copper - Air cooled

1.75 Diameter cable


325 A per cable
14 Cables
35 lbs/ft

4400 Ampere Cable Sizes

Copper - Water cooled

0.605 Diameter cable


133 A per cable
33 Cables
8 lbs/ft

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

HTS- LN2 Cooled

1.75 Diameter
up to 30 Conductors
up to 200 Amps per Conductor
1 Cable
2.0 lbs/ft

Very High Power Density is


Achievable with Superconductors

x 10 = 4000 A @ 0 Voltage

Technology & Engineering Division

Schematic 10MW, 400V, 25 kA


Data Center Layout

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Technology Needed to Implement


SC Distribution
As opposed to transmission, there are a large
number of secondary spurs, with relatively
high density (depending on application)
Refrigeration losses dominated by leads, not
by distributed cryostat or AC losses
Need to address the problem of
Electrical connections through low-loss leads
Cooling manifolding

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Summary of Preliminary System Analysis


MIT Energy Initiative Seed Fund - 2008

Power Dissipation with Standard Leads (kW)

HTS Leads

Power Loss
HTS + Cu

Power Loss
HTS + Cu

(2007)

(2008-2011)

Power Loss
HTS + Cu
(2012-2016)

Power Loss
All Cu

10

10

10

0.45

0.225

0.225

HTS Cold
Power Total

10.450

10.225

10.225

Refrigerator
Wall Power

300

177

118

16

16

16

250

316

193

134

250

HTS Cryostat

Copper Bus
Total Electrical
System Power

Current lead loss is 0.05 W/A-lead


Navigant Consulting costing predictions of SC components in 2008-2012:
http://www.energetics.com/meetings/supercon06/pdfs/Plenary/07_Navigant_HTS_Market_Readiness_Study.pdf
Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

MITEI Seed Fund Study (contd)

Power Dissipation with Optimized Leads (kW)

HTS Leads

Power Loss
HTS + Cu

Power Loss
HTS + Cu

Power Loss
HTS + Cu

(2007)

(2008-2011)

(2012-2016)

Power Loss
All Cu System

0.450

0.225

0.225

HTS Cold
Power Total

5.450

5.225

5.225

Refrigerator
Wall Power

157

90

60

16

16

16

250

173

106

76

250

HTS Cryostat

Copper Bus
Total Electrical
System Power

Current lead loss is 0.025 W/A-lead achieved by intermediate cooling stage


Navigant Consulting costing predictions of SC components in 2008-2012:
http://www.energetics.com/meetings/supercon06/pdfs/Plenary/07_Navigant_HTS_Market_Readiness_Study.pdf
Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

MITEI Seed Fund Study (contd)

Capital Costs (k$)


Capital Costs
HTS + Cu
2007
HTS Tape
HTS Cryostat
HTS
Refrigerator
HTS Total
Copper Bus
Total Capital
Cost

Capital Costs
HTS + Cu
2008-2011

Capital Costs
HTS + Cu
2012-2016

Capital Costs
All Cu

2,800

560

112

200

130

44

1,050

640

260

4,050

1,330

416

11

11

11

160

4,061

1,341

427

160

Navigant Consulting costing predictions of SC components in 2008-2012:


http://www.energetics.com/meetings/supercon06/pdfs/Plenary/07_Navigant_HTS_Market_Readiness_Study.pdf

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

MITEI Seed Fund Study (contd)

Operating Costs of Power ($/Hr)


Operating
Costs

Operating
Costs

Operating
Costs

2007

2008-2011

2012-2016

HTS (standard leads)

31.69

19.27

13.38

HTS (optimized leads)

17.26

10.62

7.61

All Copper

25.07

25.07

25.07

HTS Payback Period


(standard leads)

Never

23 Years

2.6 Years

HTS Payback Period


(optimized leads)

57 Years

9.2 Years

1.75 Years

Electricity cost = $0.10/kW-Hr

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

Technology & Engineering Division

Summary

Use of HTS could open innovative opportunities in


datacenters for decreased power consumption, flexibility and
easy of construction

Application to data server centers is a near term application


with potential large efficiency gains

Short time scale implementation allows further development


for other MicroGrid applications with similar technology

Establishes technology for:

Bringing large-scale power to land from offshore wind farms

Combining large-scale solar PV or solar thermal systems to the grid

Long distance power transmission and/or grid interconnects

Optimized DC cable, cryostat and current leads require


development program

Portions reprinted, with permission, from Massachusetts Institute of Technology and Joseph Minervini.

A High-Power
Superconducting DC Cable
W. V. Hassenzahl
Eighth Annual EPRI
Superconductivity Conference
11/13/2008

Outline

11/13/08

The team
Visions Past and Present
Why a superconducting DC cable
Program goals
Design concept
Design process

An SC-DC Cable

The team

11/13/08

Steve Eckroad
Bill Hassenzahl
Paul Grant
Brian Gregory
Stig Nilsson

An SC-DC Cable

Why a SC DC Cable

11/13/08

High Power Capacity pluses and minuses


Negligible losses resistive and AC
Physical Dimensions Small vs. Power Lines
Security
High Current and Relatively Low Voltage
Reliability
Versatility
Efficiency Lower Life Cycle Cost

An SC-DC Cable

Why operate near 77 K?


To answer this question we need to explore conductor costs and the
life cycle energy demands of an installed cable

11/13/08

An SC-DC Cable

Why operate near 77 K?


To answer this question we need to explore conductor costs and the
life cycle energy demands of an installed cable

Caution
Comparisons are
model specific.

11/13/08

An SC-DC Cable

Why A DC Cable near 77K?


77 K a real sweet spot

11/13/08

An SC-DC Cable

Program Goals
Design a Superconducting DC Cable System that
meets future utility needs and requirements.
Recognize high power limitations of local AC system
Assess power levels and cable lengths
Note power independent costs of proposed design

Use existing engineering capability for materials


and fabrication processes.

11/13/08

Structural Materials
Cryogenics and vacuum
Power Converters
Superconductors
Not the driver!

An SC-DC Cable

2 SC DC Cable Systems
Assessed power levels and cable lengths

Selected two cable systems for Reference Designs


Regional 2 GW <300 km
Inter regional 10 GW >500 km

Established a simple set of design requirements


multiple power feeds and loads
redundant cables in each circuit
redundant converters

Iterative Process

Power Levels, Ranges, and Limits I and V


Conductors, other materials, standard practices
Metal Sheath OD and Vacuum shell piece length
Metal Sheath OD and Spool Sizes
Cable section lengths, i.e., Unit length between joints
Heat loads Cryogenic Requirements
Fluid Flow Area Cryogenic Diameter and stop joint
Vacuum requirement Outer Shell ID

11/13/08

An SC-DC Cable

Power Ranges - I and V


Regional 2 GW
1 GW per SCDC Cable
Each cable has full capacity for redundancy
~33.3 kA and ~60 kV*
Inter Regional up to 10 GW
E.g., power farm to major loads
5 GW per HVDC Cable
Each cable has full capacity for redundancy
~100 kA and ~100 kV
* May choose 100 kV

11/13/08

An SC-DC Cable

10

Design Concept
Details of cross section
depend on operational
conditions
Figure includes recent
changes to accommodate
ground issues raised by
AC/DC Integration team
Approximate diameter 12 cm

11/13/08

An SC-DC Cable

11

Cable Section Length


V, I, and material properties determine
Metal Sheath OD
Cable weight per meter of length
Note mechanical properties of insulation require a
larger minimum thickness than does voltage standoff

Metal Sheath OD, spool dimensions, and required


pulling force determine
cable section length from spreadsheet

Manhole or other access capability required at


end of each section for joint preparation
Experience with conventional cables is applicable
11/13/08

An SC-DC Cable

12

Heat Loads
Heat sources

Conduction
Convection
Radiation
AC losses = hysteresis from current changes and ripple
Cable ends / joints
Cryogen flow losses

Use nominal heat load of 1 W/m for initial


calculations.

11/13/08

An SC-DC Cable

13

AC Losses
Two types of heat input in the superconductor
Current ramping and faults
Harmonic currents

Several methods for calculating heat input.


Abrupt current decrease can only deliver energy
associated with inductance per unit length L/l
Energy goes into enthalpy of nitrogen T<0.01K
Harmonic currents set limits on converter design and
operation

P ( W / m ) 4 10

I
n n
all _ n

11/13/08

An SC-DC Cable

14

Vacuum
Conduction and convection heat load must be < 0.5 W/m
depends on use of mli and quality of vacuum
Required vacuum about 2x10-4 Torr
First approach permanently sealed system with getters
Not feasible to guarantee >500 km without leaks.

Second approach vacuum pumps at fixed spacing


Issue is pressure increase from pump to furthest point requires
large open cross section
Calculation of spacing is based on gas flow from largest leak,
conductance of the cable vacuum space, and vacuum pump capacity.
Determine that a 0.7 m pipe, 50 liter/s, 10-4 Torr vacuum pumps
with every km will meet vacuum needs even if some pumps fail.
Pumps need not work full time after operation begins
Also, pumps must be able to pump down the cable prior to use

Pump spacing is intimately connected with maximum cable piece length


11/13/08

An SC-DC Cable

15

Cryogenics
Superconductivity requires a low temperature
65 to 70 K for liquid nitrogen
Over distances of a 1000 km
Small temperature variations
Normal operation ~ 1 K
Upset/fault conditions > +5 K

Requires pressurized flow of liquid nitrogen


Pressure of several atm required to limit bubble formation
and to maintain consistent dielectric strength
This low pressure allows the use of thin walled pipes
Which, in turn, limits the allowable pressure rise caused by
flow resistance

11/13/08

An SC-DC Cable

16

Cryogenics
Refrigerator loads and separation
Choice of capacity of each refrigerator depends on

Total heat inflow between refrigerators


Need for on line maintenance
Operation during and after upset/fault conditions
The grid should not know
Cool down
about refrigerators
Cost vs. capacity factors (Optimization for the future)
Iterative process among heat load, refrigerator spacing, reliability, etc.

A pressure rise of 2.5 atm. is allowable for an operating


pressure of 5 to 10 atm.
A flow rate of 5 liters/s can remove 10 kW
The associated pressure rise in 10 km is ~3 atm, 45 psi.
Choose 5 to 10 km refrigeration spacing.
Pumping/friction power is about 0.2 W/m
11/13/08

An SC-DC Cable

17

Cryogenics Summary
Heat load, allowable temperature rise determine
Minimum cryogen mass flow

Cryogen mass flow and allowable pressure drop


determine
total refrigerator capacity and refrigerator spacing.

Refrigerator spacing is an optimization issue.


5 to 10 km is adequate with a 3 to 5 atmosphere
pressure drop for liquid nitrogen.

Part of iterative design, but not a driver

11/13/08

An SC-DC Cable

18

Design Concept

11/13/08

An SC-DC Cable

19

Factory Assembly
Outer pipe

Standard high pressure gas pipe


Special welding and cleaning
Reflecting surface on inner diameter
Environmental protective outer coating
Piece length determined by shipping constraints (?~20 m)

Cryogenic pipe and cryogen return pipe


Corrugated stainless steel
Special weld requirements
Supported at each end from outer pipe

Superinsulation
Most important 30 to 50 layers between outer pipe and
cryogenic components
A few layers between the two cold pipes.
11/13/08

An SC-DC Cable

20

Pipe Section and Transport

11/13/08

An SC-DC Cable

21

On Site Assembly

This procedure is
followed for some
50 sections

11/13/08

An SC-DC Cable

22

Vault and Cable Pulling

11/13/08

An SC-DC Cable

23

Joints

11/13/08

An SC-DC Cable

24

Joints
Cable joint Issues
Large number of superconductor tapes/wires
Field procedures especially repairs
End connections and terminations

Pipe joint characteristics determined by

11/13/08

Manufacturability
Cleanliness
Superinsulation protection
Accommodation of cable pulling loads
Thermal contraction associated with cooldown

An SC-DC Cable

25

Cable Installed

11/13/08

An SC-DC Cable

26

Cryogenic Vault

11/13/08

An SC-DC Cable

27

Outer Pipe Summary


Outer pipe diameter >70 cm determined by
Cryogen pipe diameter
Vacuum pressure drop
Vacuum pumping requirements with redundancy

Outer pipe piece length determined by


transportability ~ 20 m maybe 30 m max
Fabricate in plant with mli and cryogen tube
Includes supports for axial and radial motion of cold
components
Seal in factory for cleanliness

Assemble (weld) pipes and cryogen tubes on site and


pull cable from ends.
11/13/08

An SC-DC Cable

28

Gas Pipeline

11/13/08

An SC-DC Cable

29

SC-DC Cable Program Status


Critical issues for future evaluation
Cable piece length
Power converter and grid interface
Other existing and new superconductors
100 kA joints
Temperature optimization
Allowable heat loads
Vacuum requirements
Details of refrigerator mechanical interface to cable
Overall cost evaluation

11/13/08

An SC-DC Cable

30

Power Flow and Transient


Stability Impacts of
Superconducting DC Cables
Tom Overbye
University of Illinois and
PowerWorld Corporation
Eighth EPRI Superconductivity Conference
November 12-13, 2008
This presentation is based on work is being performed
under contract with EPRI

Overview
Goal of this work is to consider the power flow and
transient stability impacts of integrating a multi-tap,
superconducting DC (SCDC) cable system within the
Eastern Interconnect and within the WECC system.
Power levels are up to 10 GW

A dual SCDC cable system is assumed, with the ability


to failover with full power in the event of a fault on one
of the cables.
Analysis compared different failover scenarios with
remaining cable ramping to full power over a few seconds
After failover full power is assumed on the remaining cable

Eastern Interconnect
Study System
The system studied was the NERC/MMWG 2008
summer peak case from the 2006 series.
Case has 48,370 buses, 7397 generators, a total load
of 660 GW and total generation of 676 GW.
2006 series dynamic models.
Power flow and transient stability runs were done
using PowerWorld Simulator version 14.
As is common with the MMWG cases, there were
many initial line violations (330 lines at >= 100% of
A limit MVA, 95 lines >= 120% of A limit MVA)

Eastern Interconnect Route for 10


GW Cable System with Six Stations
2000 MW

2500 MW

2000 MW
1500 MW

10,000 MW of A sy nchronous Generation

2000 MW

System Modifications
System was modified to include the SCDC cable system
by adding five new buses (100001 to 100005) with their
generation set to match SCDC cable injections. Buses
were then connected to existing buses by short lines:

Bus 100001 to 36260 (2.5 GW) Chicago South


Bus 100002 to 36421 (2.0 GW) Chicago North
Bus 100003 to 31230 (2.0 GW) St. Louis
Bus 100004 to 57968 (1.5 GW) Kansas City
Bus 100005 to 54901 (2.0 GW) Oklahoma City

The remote source generator(s) was assumed to be


operating asynchronous with the rest of the grid.

System Modifications, cont.


Existing generation in areas with SCDC cable injections
was reduced to satisfy area ACE requirements.
Once the SCDC cable injections were modeled, two
new 345 kV lines needed to be added to reduce line
loadings.
Between buses 57977 57968 (South of Kansas City)
Between buses 57968 59200 (South of Kansas City)

System with SCDC cable was not augmented to make it


n-1 secure, but there were no significant base case
violations.

Example: Original Kansas City


Area Flows and Voltages

Kansas City Area Flows and


Voltages with SCDC Cable

Power Flow Conclusions


Integration of the SCDC cable within the existing system
will require modifications to the transmission grid similar
to those needed to accommodate a new power plant of
similar size or a new high voltage transmission line with
similar capacity.
Any new voltage problems can be corrected by new
reactive control devices, such as capacitors or SVCs.
Flow changes caused by cable failure would be rapidly
corrected by power transfer to the unfaulted cable.
Conclusion: From a power flow perspective the
integration of the SCDC system is straightforward.

Transient Stability Analysis


Transient stability analysis, the study of whether all
the system generators will retain synchronism
following a system disturbance, is a critical question.
The assumed fault scenario was to apply a balanced,
three phase, solid fault at each of the five SCDC
cable terminals. The fault was then cleared after
three cycles (0.05 seconds). Different scenarios were
then considered for the pick in the SCDC injections:
None (both cables failed)
Half (no transfer of power from the faulted cable)
Half, then ramp to full over either 1 second or 5 seconds

Frequencies for All Generators;


Complete Loss of Both Cables

Values are generator frequencies in Hz


Minimum Frequency is about 59.58 Hz

Frequencies for Selected Generators;


Complete Loss of Both Cables

Example of Governor Response


for Loss of 10 GW
Gen 1GASTON5 #5 Mech Input
860
859
858
857

Gen 1GASTON5 #5 Mech Input

856
855
854
853
852
851
850
849
848
847
846
845
844
0

7
8
9
Time in Seconds

10

Gen 1GASTON5 #5 Mech Input

11

12

13

14

15

Given a loss of
10 GW for a
676 GW system,
a proportional
generation increase
for this generator
would be
0.844/676*10 GW
= 12.4 MW.
Actual is slightly
different because
of differing governor characteristics

Frequencies for All Generators; Loss


of One Cable; No MW Transfer

Minimum Frequency is about 59.70 Hz

Frequencies for Selected Generators;


Loss of One Cable; No MW Transfer

Frequencies for All Generators; Loss


of One Cable; 5 Sec MW Ramp

Minimum Frequency is about 59.70 Hz

Frequencies for Selected Generators;


Loss of One Cable; 5 Sec MW Ramp

Example of Governor Response


for 5 Second Ramp Recovery
In previous plot for
this governor (for the
complete loss of
both cables case)
the output went up to
860 MW. Now in
recovers quite
quickly to its precontingency value

Gen 1GASTON5 #5 Mech Input


849

Gen 1GASTON5 #5 Mech Input

848

847

846

845

844
0

7
8
9
Time in Seconds

10

Gen 1GASTON5 #5 Mech Input

11

12

13

14

15

Frequencies for All Generators; Loss


of One Cable; 1 Sec MW Ramp

Minimum Frequency is about 59.72 Hz

Frequencies for Selected Generators;


Loss of One Cable; 1 Sec MW Ramp

Frequency Response Discussion


With no (or slow) power recovery the maximum
frequency drop was about 0.3 Hz (done to 59.7)
when only one cable failed (5 GW loss)
Well above highest load shed frequency of 59.3 Hz.

Likely drop could be more because


Study considered peak summer load condition, which has
more generators spinning
Transient stability cases tend to under-estimate frequency
decline since not all governors are available

But the modeled frequency decline tends to match


actual results (see next slide)

April 23, 2002 Frequency Response


Following Loss of 2600 MW
Decline for 2600
MW was about
0.1 Hz, so 0.3 Hz
for 5000 MW is
actually slightly
high. But chart at
left 1) only shows
the frequency at
one location, not
the lowest frequency
and 2) measurement
delay may have
missed the lowest
value.

Historical Eastern Interconnect


Frequency Response
Our values
were about
1700 MW/0.1
Hz for the
5 GW loss case
(one cable)
and 2500
for the 10 GW
Loss case
(both cables)
Source: Interconnected Power System Response to Generation Governing: Present Practice and
Outstanding Concerns, IEEE Task Force on Large Interconnected Power System Response,
IEEE Publication 07TP180, May 2007 (Figure 2-22)

23

Frequency Propagation
Animation
The accompanying slide set shows an animation of
the frequency for the first four seconds for the 5
second ramp recovery case.

Eastern Interconnect
Transient Stability Conclusions
From a transient stability point of view, a 10 GW SCDC
cable could be integrated into the existing Eastern
Interconnect.
Frequency response is fairly insensitive to how quickly
the power is transferred from faulted cable to the
unfaulted cable (one versus five seconds)
Transfer time does affect how much power needs to be picked
up by the generator governors, and for how long.

WECC System
The system studied was the WECC 2010 LA1-SA
Approved Base Case.
Case has 15,795 buses, 3100 generators, a total load
of 106 GW and total generation of 111 GW.
2006 series dynamic models.
Power flow and transient stability runs were done
using PowerWorld Simulator version 14.
Case had several minor initial flow violations.
Power flow and contingency limits were not
considered
26

WECC SCDC Cable Route: Six


Stations, 8.5 GW
Denver: 1500.0 MW

8500 MW Asynchronous Generation

Alburquerque: 1000.0 MW
Los Angles: 2500.0 MW

Phoenix2000.0 MW

SanDiego: 1500.0 MW

27

Freq. Deviation for All Generators;


Loss of One Cable: Worst Case

28

Freq. Deviation for All Generators;


Loss of One Cable; 8 Sec MW Ramp

29

Freq. Deviation for All Generators;


Loss of One Cable; 4 Sec MW Ramp

30

Freq. Deviation for All Generators;


Loss of One Cable; 2 Sec MW Ramp

31

Freq. Deviation for All Generators;


Loss of One Cable; 1 Sec MW Ramp

32

Comparison with Actual


WECC Frequency Results
WECC Frequency
Responses Tends
to be Around
800 or 900 MW/
0.1 Hz. So a 4.25 GW
sustained loss would
result in an anticipated
frequency decline
of close about 0.5 Hz,
slightly above the
59.3 load shed
threshold.
Source: L. Pereira, et. al., New Thermal Governor Model Selection and Validation in the WECC, IEEE
Transactions on Power Systems, February 2004, pp. 517-523 (Figure 1).

33

WECC Transient Stability


Conclusions
From a transient stability point of view, an 8.5 GW
SCDC cable could be integrated into the existing
WECC Interconnect provided following a fault the
power can be quickly transferred to the unfaulted
cable.
Quick power transfer (several seconds maximum)
can reduce the point of maximum frequency dip,
which occurs at about five seconds in both the
simulations and with actual system results.

34

Slides Show Locational Variation


in Bus Frequency for the 5
Second Ramp Eastern Case
Tom Overbye
University of Illinois and
PowerWorld Corporation
Eighth EPRI Superconductivity Conference
November 12-13, 2008
This presentation is based on work is being performed
under contract with EPRI
1

Transient Stability Frequency


Animation: Time = 0.0 Seconds

Time: 0.1 Seconds

Time: 0.2 Seconds

Time: 0.3 Seconds

Time: 0.4 Seconds

Time: 0.5 Seconds

Time: 0.6 Seconds

Time: 0.7 Seconds

Time: 0.8 Seconds

Time: 0.9 Seconds

Time: 1.0 Seconds

Time: 1.1 Seconds

Time: 1.2 Seconds

Time: 1.3 Seconds

Time: 1.4 Seconds

Time: 1.5 Seconds

Time: 1.6 Seconds

Time: 1.7 Seconds

Time: 1.8 Seconds

Time: 1.9 Seconds

Time: 2.0 Seconds

Time: 2.1 Seconds

Time: 2.2 Seconds

Time: 2.3 Seconds

Time: 2.4 Seconds

Time: 2.5 Seconds

Time: 2.6 Seconds

Time: 2.7 Seconds

Time: 2.8 Seconds

Time: 2.9 Seconds

Time: 3.0 Seconds

Time: 3.1 Seconds

Time: 3.2 Seconds

Time: 3.3 Seconds

Time: 3.4 Seconds

Time: 3.5 Seconds

Time: 3.6 Seconds

Time: 3.7 Seconds

Time: 3.8 Seconds

Time: 3.9 Seconds

Time: 4.0 Seconds

IssuesAssociatedwitha
SuperconductingDCLine
FedbyaMultiTerminalVSCSystem
TomBaldwin,FloridaStateUniv.
PauloRibeiro,CalvinCollege,and
BrianJohnson,Univ.ofIdaho
November12&13,2008

EighthEPRISuperconductivityConference

Outline
EnablingTechnologies:
HighPowerVoltageSourceConverters
DCSuperconductingCables

Topologies
MultiTapVSCs Issues

DCPowerControl
Rectifiers/Inverters
DealingwithTransientCurrent/PowerVariations
PracticalPowerandCurrentLimitations

Discussions

November12&13,2008

EighthEPRISuperconductivityConference

SCDCControlAnalysisandSimulations

SystemParameter
SCDCcablelength,l
cablepropagationdelay,tDelay
ControlVariables
maximumvoltageramprate

Cablemodelfrom

Value
2000miles
18.6ms
Value
40kV/s

SCDCcableelectricalcharacteristics
Parameter
Value
outerradiusofinnerconductor 17.5mm
innerradiusofouterconductor 29.5mm
CalculatedQuantities
Value
inductance,L
104.4nH/m
capacitance,C
319.6pF/m
characteristicimpedance,Z0
18.08
propagationspeed,
173x106 m/s

W.Hassenzahl,Ahighpowersuperconductingdccable,anEPRIprogram
SCDCProjectReviewMeeting,Charlotte,NC,10December2007

Systemmodelfrom
S.NilssonandA.Daneshpooy,SimulationofHTSCHVDCsystem,
SCDCProjectReviewMeeting,PaloAlto,CA,25July2008
November12&13,2008

EighthEPRISuperconductivityConference

TransientOscillationsofDCCables
LongDCcablesystem(>1000km)
thebehavioroftheconvertersareaffectedbythe
propagationdelaysintroducedbythecables
thepropagationtimeconstantissimilartoothercable
systems
withasmallfrequencydependentacresistance
providedbySCDCcables,slowertransientsignals
(<1kHz)havelittleattenuatedalongthecablelength
normalmismatchesbetweentheconverterimpedance
andthecablecharacteristicimpedancecausemostof
thetransientsignalenergytoreflectbackintothe
cable
November12&13,2008

EighthEPRISuperconductivityConference

Rectifier Terminal-Voltage Control

voltagerampingtoprecharge
thevoltageintheSCDCcable

Inverter Terminal-Current Control

Rectifier Terminal-Voltage Level

voltagecontrolattherectifier
maintainsthedcterminal
voltageatnearlyconstantvalue
forloadcurrentchanges

voltagelevelattheinverter
terminalexhibitsavoltagesag
duringtherampingupofthe
loadcurrent

Rectifier Terminal-Current Injection

Inverter Terminal-Current Injection

ringingofthecurrent
feedingthecable
currentrampingto
fullloadattherate
of5kApersecond

November12&13,2008

Inverter Terminal-Voltage Level

EighthEPRISuperconductivityConference

complementary
ringingofthecurrent
attheinverter
terminalofthecable

RampRateLimitsforLongCables
Apropervoltageprofileis
Thepropagationdelayand
maintainedattheconverter
mismatchofthecables
withvoltagecontrol
characteristicimpedancewith
theconvertersimpedance
Thevoltageataconverter
resultsinadecayingoscillation
withcurrentcontrolsagsand
swellsduetotheinductance Theramprateofthecurrent
oftheSCDCcable
affectthemagnitudesofthe
voltagesags,swells,andringing
Sags for the 2000-mile SCDC cable
Case Peak Idc
Greatest Vdc
Average Vdc
Ramp Rate
Sag
Sag
Run #1 1 kA/s
-0.38% (79.7 kV) -0.19% (79.85 kV)
Run #2 2 kA/s
-0.88% (79.3 kV) -0.44% (79.65 kV)
Run #3 5 kA/s
-2.75% (77.8 kV) -1.38% (78.90 kV)
Run #4 10 kA/s -5.50% (75.6 kV) -2.75% (77.80 kV)
Run #5 20 kA/s -11.0% (71.2 kV) -5.50% (75.60 kV)
November12&13,2008

EighthEPRISuperconductivityConference

ImpactofCableLength
1000milecable

Simulationparameters
80kV,10kA,two
terminalSCDCcable
currentcontrolterminal:
2kA/secramprate

Graphsofvoltageripple

0.302%V_offset
0.554%V_ripple

2000milecable

4000milecable

0.583%V_offset
1.108%V_ripple

1.13%V_offset
2.22%V_ripple

November12&13,2008

EighthEPRISuperconductivityConference

VSCModel

SingleDCpoleoperation
andaSCDCcablewith
groundreturn sheath

November12&13,2008

EighthEPRISuperconductivityConference

TransientOscillations

1000kmTypicalDCCable

November12&13,2008

EighthEPRISuperconductivityConference

TransientOscillations

1000kmSmallResistanceDCCable

November12&13,2008

EighthEPRISuperconductivityConference

10

TransientOscillations

1000kmNearSuperconductingDCCable

November12&13,2008

EighthEPRISuperconductivityConference

11

TransientOscillations

Current[kA]

1000kmNearSuperconductingDCCable

November12&13,2008

EighthEPRISuperconductivityConference

12

Comments
PSCADsimulationsshow
thattheoperationoftheVSCconvertersseemto
workadequatelyasfarasthecontrolofvoltageis
concerned
howeverthecurrenttransientsontheDClinefor
nearsuperconductingconditionsafteranACfault
areextremelysevereandneedstobedealtwith
creativesolutionsandmaynotbeeasilyachieved

November12&13,2008

EighthEPRISuperconductivityConference

13

ControlSchemes
Multiterminalsystems
extensionsofthepointtopointsystemcontrol
concepts(basedonthenotionofcontrolmodes)
voltageregulationmodeatoneconverterstation
generallyappliedtoarectifyingconverter

currentregulationmodeatallotherconverterstations

November12&13,2008

EighthEPRISuperconductivityConference

14

DCVoltageDroopControl
Adistributedvoltageregulationschemefor
controllingcurrentinjections
similartofrequencypowerregulationinacgrids
achangeinvoltageusedtosignalthecontrolsystemto
meetchangesinpowerdemand(currentinjections)
naturalregulationrequiringnocommunications

performsbestonaSCDCmeshorparallelnetwork
eachofthenodesreachthesamesteadystatevoltage
level

November12&13,2008

EighthEPRISuperconductivityConference

15

DynamicsofDroopControl
Thedroopdynamiccomponents
VSCrectifiersequivalentsourceimpedance
DCcapacitorsattheterminalsofeachconverter
SCDCcableinductance
SCDCpropagationdelayforlonglines(>1000km)

Droopdynamicrange
thebuiltindroopofarectifyingconverterisquite
small(e.g.,10sMW/0.001pu ofV)
simplifiesthepowerregulationatinvertingconverters
largechangesinthedcvoltagecanindicatesystem
problemsandtriggerloadsheddingasnecessary
November12&13,2008

EighthEPRISuperconductivityConference

16

DynamicswithLongSCDCCables
Twoofthelongcabledynamiccharacteristics
causeavoltagedifferentialacrosstheSCDC
cable
inductance
propagationdelay

Controlschememustaccountforthe
propagationdelayofthecable
delayvalues:1msto25ms

November12&13,2008

EighthEPRISuperconductivityConference

17

TwoCableSystem
Proposedfromareliabilityperspective
twinconvertersandtwincablesrunninginparallel
crossoverswitchesforaddressingfaultedsections

Fromacontrolperspective:
usingbothcablessimultaneouslypermitsa
doublingofthecurrentrampratesforaspecified
sag,swell,andripplerequirement
inthecaseofafailure,halfofthefullrated
currentwouldneedbetransferredtothe
remaininggoodcableorconverter
November12&13,2008

EighthEPRISuperconductivityConference

18

Pulse Tube Cryocooler


Refrigeration System
for HTS Cables
Praxair, Inc.
Greg Henzler
November 13, 2008

8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Outline
Praxair
Pulse

introduction

tube cryocooler technology

Columbus,
HTS

OH cryocooler experience

refrigeration system layout

2
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Praxair at a Glance

A Fortune 300 company

Sales of $9.4 billion in 2007

Largest industrial gas


company in North America

Operations in more than 30


countries

One million customers


worldwide

28,000 employees

3
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Strategic Global Position


Industrial Gases Sales by Region
2007 Sales $9.4 billion

Europe
14%

North
America
55%

Asia
8%

South
America
17%
Excludes worldwide sales of Praxair Surface Technologies (6% of total sales)
4
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

On-Site Supply Business Model

Plants are located on customer sites


z

Air separation, H2 and other types


of plants

Owned, operated, maintained and


updated by Praxair

Remote operation and monitoring

Reliably supply product 24/7

Critical customers include


z

Hospitals

Chemical plants

Semiconductor fabs

Steel mills

Praxair is viewed as a gas utility by many of our customers


5
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Praxairs Pulse Tube Cryocoolers

Coldhead
Inertance
Network

Pressure wave
generator (PWG)
converts electrical
energy into acoustical
energy
Coldhead and
inertance network
convert acoustical
energy into
refrigeration
capability

Coldhead
Vacuum
Container

Process
Lines
Inertance Tank

PWG

Linear Motors with Pistons


6
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Pulse Tube Benefits

Long life
High reliability
Low maintenance
High Carnot efficiency
Small modular footprint
Low noise and vibration
Environmentally friendly

No moving parts in cold end


No connecting rods
No wearing parts
No bearings
No oil

Key enabler of HTS cable technology!


7
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Pulse Tube Basics


Linear Motor

Warm Heat
Exchanger

Aftercooler
Regenerator

Pulse Tube

Cold Heat
Exchanger

Reservoir

Impedance
Network

Major components of electrically driven Pulse-tube cryocoolers


Linear

motor: electrically powered oscillating piston(s)

Aftercooler:

water cooled heat exchanger

Regenerator:
Cold

array of narrow passages - high Cp material

heat exchanger: refrigeration is extracted here

Pulse

tube

Warm

heat exchanger, impedance network, reservoir, oscillating gas


8

8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

PWG & Cold Head Improvements


2nd

generation PWG

Improved efficiency

Increased clearance

External thermal management


system

New drift control system

Shorter piston stroke length

2nd
z

generation cold head

1K Unit and Gen-2


3000

Design completed

Higher cooling capacity

Improved heat transfer

Enhanced regenerator

W
r,
e
w
o
P
g
nli
o
o
C

2500

1kW
G2

2000
1500
1000
500
0
40

60

80

100

120

Tc, K
9
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Columbus, OH HTS Cable Project

Termination

Cryostat

Refrigeration System

HTS cable energized 8/8/06


z

PT Cryocoolers

~ 20,000 hours of operation

2nd gen. PWG energized


8/20/08
z

Chiller

~ 2,000 hours of operation at


site

Praxair operates, maintains and


monitors refrigeration system

System working well

1 kW
Cryocooler

10
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Termination Refrigeration System


A loss
At full
ofrefrigeration
1 cryocoolerdemand
at full refrigeration
of
demand
5 kW, the
results
cryocoolers
in the remaining
operate cryocoolers
operating
at 85% of
at their
98% full
of their
capacity.
full capacity.

Cryocooler Shutdown

Percent of design
98%
97%
95%
93%
91%
89%
87%
capacity per cryocooler = 85%

11
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Refrigeration System for Long Lengths


Cryocoolers at the substations only

cooling
channels

RETURN

steel pipe

GO
RETURN

cryostat

GO

cable
f
f

f
e

f
f

12
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Cooling System Key Components


Pressure
z

Wave Generator (PWG)

Two opposing pistons on linear motors

Coldhead
z
z

Heat exchangers and regenerator


No moving parts

Water
z

Packaged unit

Cold
z

chiller

box

Cryo valves, piping, pumps etc.

Controls
z
z

VFD
Temperature, pressure, vibration etc.

Majority of components are existing technology and readily available.


13
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Benefits of Independent Cryocoolers


Each
If

cryocooler is operated by a single PWG

a motor fails, then only one cryocooler fails

Each

cryocooler acts independently

Leads

to overall higher reliability

Manage
More

redundancy on a smaller scale

turndown flexibility

14
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Conclusions
Praxair

reliably supplies product for critical


applications in diverse industries

Pulse

tube cryocoolers are a key enabler


for HTS cable applications

Praxair

continues to have significant


success with pulse tube cryocooler
technology

15
8th Annual EPRI Superconductivity Conference

Copyright 2008, Praxair Technology, Inc. All rights reserved.

Cost and Performance Comparisons Between


HTS And Conventional Utility Power
Transformers
Bill Schwenterly
Oak Ridge National Laboratory
Ed Pleva
Waukesha Electric Systems
Alan Wolsky
Argonne National Laboratory
November 13, 2008
8th EPRI Superconductivity
Conference

Managed by UT-Battelle
for the Department of Energy

OUTLINE
z Design assumptions
z Overview of design spreadsheet
z Capital and Operating Cost Comparison
z Efficiency Comparison
z Weight and Dimension Comparison
z Other Design Issues
z Summary of Requirements

Managed by UT-Battelle
for the Department of Energy

HTS Unit Design Summary


z 25-MVA rating; 115 kV / 13.09 kV; 72 A / 1103 A
z YBCO winding in pressurized, subcooled nitrogen bath
z HV Disc, 10 turns/disc
z LV Transposed screw, 8 wide or 16 narrow tapes in parallel
z Wrapped insulation on conductors
z Co-wound 1-mm copper

z Pressurized bath is coupled to cryocooler by cooling


shell.

z Air-cooled compressors

z Composite dewar
z Metal dewar would form a shorted turn around core.

z Core in air
3

Managed by UT-Battelle
for the Department of Energy

Conventional vs. HTS Unit


Ratings Comparison
z Conventional Unit
z 15/20/25-MVA ratings with no fans/1-stage fans/2-stages fans.
z 30 minute operation at 50 MVA with increasing winding
temperature.

z HTS Unit
z Cryocoolers are sized for 25-MVA heat load.
z HTS is sized for 50-MVA load with Ipeak < Ic.
z 15/20/25-MVA ratings with cryocoolers cycled to match heat
loads at lower ratings.
z 30 minute operation at 50 MVA with liquid nitrogen boiloff.
z Current leads are sized for 125% of 25-MVA current.
z Maximum current lead temperature rises to 120C at 50 MVA
with increased heat load.

Managed by UT-Battelle
for the Department of Energy

Transformer Schematic
Bushings
Cryocooler

Core

Winding

Foam

Removable
Top Plate

Cooling
Shell
Shield

Composite Coil
Dewar

Managed by UT-Battelle
for the Department of Energy

Unit is surrounded by weather enclosure in


place of oil tank.

Pressurized
Subcooled
Nitrogen

Single-Phase Transformer Concept


138-kV Bushing
Core
AL-300 Cryocooler
Composite Dewar

Winding Pack

Managed by UT-Battelle
for the Department of Energy

Cooling Shell

Common Dewar for 3-Phase Unit


Stainless outer
jacket

Composite core
limb jackets and
winding vessels

Composite top &


bottom plates

Managed by UT-Battelle
for the Department of Energy

Overview of HTS Unit Design


Spreadsheet
z Inputs:
z Ratings and voltages; overload factor
z 5 different volt/turn values can be specified
z Conductor dimensions
z Winding geometry disc or layer; number of layers or disc turns
z Materials properties Ic, cost, density
z Wall thickness for coil structure and dewars
z Insulation thickness and voltage standoff distances
z Refrigerator dimensions, weight, input power, cost

z Outputs:
z Capital and operating costs
z Winding, dewar, core, and enclosure dimensions
z Weights-conductor, core, dewar
z Length of conductor
z Lead and ac loss heat loads (Rhyners equations for ac losses)
z Room temperature input loss power
z % Fault impedance
8

Managed by UT-Battelle
for the Department of Energy

Managed by UT-Battelle
for the Department of Energy

15-MVA 30-Year Capital and


Operating Costs
z Assumptions: $50/kA-m HTS, 350 A/cm, 0.6 cm width, 70-K Toper
z $8.80/kg copper, $4.20/kg steel
120 V/turn
z Load losses $1250/kW
No-load losses $2500/kW
Item

HTS

Selling Price

$680 K

$458K

No-Load Loss

$84 K, 34 kW

$35 K, 14 kW

Load Loss

$4K, 3.3 kW

$58K, 46 kW

$768 K

$551 K

Oil Containment

----

$30 K

Fire Suppression

----

$100 K

Refr. Maintenance (2 AL-600)

$106 K

----

GRAND TOTAL

$874 K

$681 K

TOTAL

10

Conventional

Managed by UT-Battelle
for the Department of Energy

10

High cost of conductor forces minimum in


lifetime cost to high volt/turn values.
z V/n gives required number of
turns in a phase.

z V/n = Rcore2
z = 4.44 f Bcore

z Lcond = 2Rcoren = 2V/Rcore


z Thus, larger core diameter

reduces conductor length.

11

Managed by UT-Battelle
for the Department of Energy

11

15- and 25-MVA Efficiency


z Assumptions: Refrigerator COP 27 W/W.
z 2 Cryomech AL-600 refrigerators, ea. 560 W at 70 K, 15 kW input power.
z HTS and Lead losses are refrigerator input power.
Item
Load
Core Loss

HTS
15 MVA

15 MVA 25 MVA

23 kW

14 kW

AC Loss

2.9 kW

13.1 kW

----

Lead Loss

7.4 kW

8.8 kW

----

Copper Loss

12

25 MVA

Conventional

----

46 kW

131 kW

TOTAL LOSS

33.3 kW

44.9 kW

60 kW

145 kW

EFFICIENCY

99.8 %

99.8 %

99.6 %

99.4 %

Managed by UT-Battelle
for the Department of Energy

12

15-MVA Dimensions and Weights


z Assumptions: 0.3 m side and 0.1 m top/bottom enclosure clearances

Item

13

HTS

Conventional

Length

3.75 m including compressors

3.02 m

Width

1.65 m

3.33 m including radiators

Height

4.22 m including bushings

4.92 m including bushings

Core weight 16.4 t

9.1 t

Total weight 24.0 t

39.9 t

Managed by UT-Battelle
for the Department of Energy

13

What if conductor cost is lowered?


z Minimum in total cost moves

down and to left as conductor


cost falls.

z Capital cost approaches

conventional at $10/kA-m.
z Copper ~$25/kA/m in
conventional unit at 3A/mm2.
z Capital costs shown are at
minimum total lifetime cost.

z Refrigerator cost reduction


($109K in present design)
would also help cost
comparison.

14

Managed by UT-Battelle
for the Department of Energy

14

z
z
z
z

15-MVA 30-Year Capital and Operating


Costs

Assumptions: $20/kA-m HTS, 350 A/cm, 0.6 cm width, 70-K Toper


$8.80/kg copper, $4.20/kg steel
70 V/turn
Load losses $1250/kW
No-load losses $2500/kW
Refrigerator cost reduced by half
Item

HTS

Selling Price

$478 K

$458K

No-Load Loss

$60 K, 24 kW

$35 K, 14 kW

Load Loss

$5K, 4 kW

$58K, 46 kW

TOTAL

15

Conventional

$543 K

$551 K

Oil Containment

----

$30 K

Fire Suppression

----

$100 K

Refr. Maintenance (2 AL-600)

$106 K

----

GRAND TOTAL

$649 K

$681 K

Managed by UT-Battelle
for the Department of Energy

15

Other Design Issues Fault Handling


z IEEE/ANSI Standards specify a 2-sec total fault duration without
overheating.
z Extra copper is needed for fault handling.

z 2-sec requirement leads to large fraction of a conventional units Cu!


z 1 mm of copper is adequate for 1/2-sec 10X fault.

z Copper cannot be co-insulated with HTS tape


in advance because the inner conductor
buckles during winding.

HTS

Insulation

Copper

z HTS tape is too fragile to wind with high-voltage


insulation by itself.
z Winding on insulation as coil is wound is not practical,
especially for multiple conductors in LV winding.

z Need copper laminated or plated on both sides of the HTS tape,

so that the HTS is on the neutral axis.


z This would provide a robust conductor that could be insulated on
a high-speed machine.
16

Managed by UT-Battelle
for the Department of Energy

16

Other Design Issues Layer Build, Core,


AC Losses
z Designs with ~20-turn discs are desirable.
z Core limbs >2 m high are flexible and hard to handle in shop.
z Smaller core with shorter limbs and lower losses is possible with more
turns in discs.
z At constant window area,
h/w ratio of = 4/3 minimizes core loss.
Window area Aw = hw = w2 = h2/
Core volume Vcore = Acore[3h + 2(2w+3Dcore)]
Vcore = Acore[3 Aw + 4 Aw/ + 6Dcore]
Derivative = 0 with = 4/3.

h
w

z BUT-- more turns on a disc raises field on HTS


conductor on inner turns and increases ac loss.

z HTS loss reduction needed striations, nano-particles, etc.

17

Managed by UT-Battelle
for the Department of Energy

17

SUMMARY For a competitive HTS


Transformer:

z We need HTS tape cost near $20/kA-m. *(Not including extra Cu)
z We need HTS tape with 1/2 mm or more of copper laminated or
plated on each side.

z We need HTS tape with ac loss reduction features such as


striations or nanoparticles.

z We need reduced cryogenic refrigeration costs.


z With higher no-load losses and lower load losses than a

conventional unit, an HTS transformer is most appropriate in a base


load application where it is loaded most of the time.

18

Managed by UT-Battelle
for the Department of Energy

18

Potrebbero piacerti anche