Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Ocean Engineering
journal homepage: www.elsevier.com/locate/oceaneng
art ic l e i nf o
a b s t r a c t
Article history:
Received 17 September 2015
Accepted 8 December 2015
Failure of submarine power cables have been shown to be attributed to cable eld joints in 18% of cases.
This high failure rate at the joining location indicates that the current acceptance testing of these joints is
inadequate. The failure mode of these joints is believed to be entirely due to water ingress at the eld
joint location. Submarine cable eld joints are required during installation due to cable repair, joining of
insufcient manufactured cable lengths or when the lay process has to be abandoned due to the
sea state.
Current design guidance for cable eld joints suggests sea trails to determine if the proposed eld
joining technique is acceptable. Sea trails, however, are often prohibitively expensive, such that a set of
standardised onshore testing regimes which improves both the reliability and affordability of these tests
would be advantageous.
This paper outlines a recent cable eld joint onshore testing regime to ensure the cable joint integrity
during the laying process as well as serviceability in operational life. The paper outlines a process for
simulation of the calculated cable laying tension and bend radius with a set of physical tests developed
for mechanical and water ingress protection.
& 2015 Elsevier Ltd. All rights reserved.
Keywords:
Offshore eld joint
Subsea power cable
In-line deployment
Radial water penetration test
High voltage alternating current (HVAC)
cable
Deployment simulation
1. Introduction
According to Worzyk (2009) a study on subsea power cable
failures was undertaken in 1986 by CIGR (Conference Internationale des Grandes Reseaux Electriques). This study indicated a
typical failure rate of 0.32 failures/year/100 km. Furthermore, 82%
and 18% of the failures occurred in the cables and the joints,
respectively. The study did not specify the exact failure causes,
however, the three major fault causes for submarine cable joints
were known to be: 1) Inadequate joint design, 2) Poor joint
assembly work onboard the vessel, 3) Adverse weather conditions
during jointing, 4) Inadequate installation procedures.
The other failures to subsea power cables are due to many
other factors such as shing, anchors, dredging and other activities. According to the International Cable Protection Committee
(2009) anchors represent the largest portion of submarine cable
damages. Contact between a cable and an anchor is often
n
Corresponding author at: Qatar Petroleum, Doha, Qatar. Tel.: 974 5576 5276;
fax: 974 4013 9058.
E-mail address: reda@qp.com.qa (A.M. Reda).
http://dx.doi.org/10.1016/j.oceaneng.2015.12.019
0029-8018/& 2015 Elsevier Ltd. All rights reserved.
Negligent anchoring.
A vessel being anchored inadequately and a resultant dragging
session.
154
Worzyk (2009) stated that The failure of some early installation joints during service shaded the reputation of submarine
power cable joints. Failures in the joints were usually caused by
poor engineering or inadequate installation procedures.
CIGR study (Update of Service Experience of HV Underground
and Submarine Cable Systems, 2009) revealed that there were
only four joint failures out of 49 failures in total in 7000 km of
installed submarine cable. The study stated that 19 of the 49
reported faults could be repaired within one month. The ratio of
joint failures changed from 0.22 to 0.095 failures/year/100 km,
from 1986 to 2009, respectively as per Worzyk (2009). This
demonstrates that the design of submarine cables has been
improved over the years and the cable joints are safer and more
reliable today than in 1986.
CIGR (2010) & Worzyk (2009) highlighted that manufacturing
of a reliable joint is often the most difcult undertaking during the
development. During the installation or the deployment of the
joints, they should withstand the mechanical stress and strains.
CIGR TB490 (CIGR TB490) emphasized the importance of
paying attention to repair joints as part of the AC submarine cable
system. DNV-RP-J301 (2014) indicated that all joints and terminations shall be subjected to a test program in accordance with the
applicable standards. Since subsea installation eld joints and
repair joints connect the cable parts along the cable route to form
one integrated cable, the joint has to withstand all the expected
different loads during the service life the same as the cable
(Karlsdttir, 2013). This paper focuses only on the stiff joints which
have a rigid outer casing. This rigid joint serves as a connection
point for the armouring wires of each cable end. The deployment
of a rigid joint on the sea bed is probably the trickiest and most
complicated operation of the cable installation. This is in part
because during the deployment operation the two jointed cables
must be handled with the rigid joint. Neither over-bending nor
over-tensioning must occur or the cable arrangement being stuck
in other structures on board Worzyk (2009). The deployment of
the rigid joints requires a complicated crane arrangement due to
the stiffness of the joints as well as the increased diameter of the
joint compared to the cable. The stresses experienced by the joints
during the deployment on the sea bed are the likely maximum
stresses experienced by the joint during the service life. Therefore,
it is important to verify the mechanical integrity and reliability of
the rigid joint during deployment.
Jointing operation is challenging and requires valuable vessel
time, good planning, highly qualied personnel, proper equipment
for deployment, jointing facility container load on the vessel as
well as good coordination between the jointing crew and the
vessel crew. Jointing operation typically requires from one day to
several days, depending on the cable joint and joint design, by
which a good weather window is required to complete the
155
contrary, the OFJ did not meet the criteria dened in CIGR TB490
(CIGR TB490) for the radial water penetration (RWP) test.
Therefore, it was decided to undertake a trial laying test with OFJ
in addition to the third RWP test as required for part of the type
test. It should be mentioned that after the investigations using the
results from type tests 1 and 2, it was concluded that the OFJ
during the two type tests were not dismantled carefully. Moreover,
stresses were introduced to the pre-molded joint during the
release from the compound lling before conducting the RWP
tests. The OFJ failed the two RWP tests due to one of the premolded joints containing incomplete llings at two locations of
the copper housings. During the third test, the OFJ was dismantled
cautiously and it was ensured that no additional stresses would be
introduced to the pre-molded joint during the release from the
compound lling before the execution of the RWP test. Also, it was
ensured that adequate measures were implemented to ensure that
the copper housing of the pre-molded joint was lled completely.
156
2.
3.
4.
5.
6.
7.
Fig. 5. Plumbing area after in-line test and water penetration test.
157
Fig. 7. Lift the joint outboard. Tensioner to pay out cable to ensure sufcient slack during operation.
crane wire does not become entangled with the joint. During this
step, it is important to ensure that the departure angle is according
to the dynamic simulations undertaken.
Fig. 9 illustrates the lowering of the joint until it rests on the
seabed. The remote operate vehicle (ROV) will conrm proper set
down. It is important to ensure that the departure angle is
according to the dynamic simulations undertaken. The installation
vessel then proceeds with the laying of the remaining cable as
illustrated in Fig. 10.
Fig. 11 presents the cable lay conventions which are used in the
paper. The results presented are parametric with respect to the
The cross section and the mechanical properties of the submarine cable are highlighted in Fig. 13 and Table 1.
158
Fig. 10. Installation vessel to resume the normal cable laying operations.
159
Table 1
The mechanical properties of 132 kV HVAC submarine cable.
The joint is comprised of the actual joint, armor pot and bend
restrictor. The joint schematic is shown in Fig. 4. Tables 24 present the properties of the actual joint, armor pot and bend
restrictor, noting that the joint is not a rigid body but a exible
member having prescribed bending limits.
The allowable tension in the cable inside the bend restrictor
varies with the angle of the bending. Table 5 illustrates the relationship between the bending angle and allowable tension for the
cable inside the bend restrictor.
4.3. Crane lifting capacity
Table 6 highlights the maximum crane capacity limit used
throughout the simulations.
Item
Value
Unit
Outer diameter
Weight in air
Weight in water
Axial stiffness
Bending stiffness
Allowable tension (Straight Pull)
Allowable tension (on Minimum Bend Radius (MBR) pull)
Allowable compression (Straight Pull)
Allowable compression (on MBR pull)
Minimum Bending Radius (For installation)
Allowable curvature (For installation)
191
70
41
650
26
160
115
17.3
10.2
2.9
0.345
mm
kg/m
kg/m
MN
kN m2
kN
kN
kN
kN
m
Rad/m
Table 2
Joint body details.
Item
Value
Unit
Length
Outside diameter
Axial stiffness
Bending stiffness
Bending moment
Weight in air
Submerged weight
5580
605
2680
88000
125
744
449.3
mm
mm
MN
kN m2
kN m
Kg/m
kg/m
T
Hs
T
Hs
p
p
for 3:6 o p o 5;
exp 5:75 1:15p
and
T
Hs
p
:
1 for 5 o p
The inuence of the steepness factor over the Hs can be summarized as shown in Fig. 14.
160
Table 3
Armor pot details.
Table 7
Lifting aids capacity.
Item
Value
Unit
Item
Value
Unit
358
291
3695
36400
180
210.7
142.5
mm
mm
MN
kN m2
kN m
Kg/m
kg/m
Shackle
Eye-Bolt
9.5
17.3
Tonnes
Tonnes
Table 4
Bend restrictor details.
Item
Value
Unit
2129
291
650
26
4600
100
281.4
213.2
3.0
mm
mm
MN
kN m2
kN m2
kN m
Kg/m
kg/m
m
Table 5
Bend restrictor allowable tension.
Angle Allowable tension (kN)
0
15
30
45
60
75
90
120
116
104
85
60
35
20
Table 6
Crane capacity.
Item
Value
Unit
13
4.9
30
Tonnes
Tonnes
Tonnes
Table 8
Wave data.
Hs [m] Lower bound (LB)
[s]
0.5
0.75
1.0
3.24
3.97
4.58
2.55
3.12
3.61
3.87
4.74
5.48
161
particularly important for the stress. The timestep size can be very
important to the accuracy of the results, but also has a signicant
impact upon the time it takes to run a simulation. For this reason it
is desirable to maximize the time steps, but without compromising accuracy or model stability.
162
Fig. 18. OrcaFlex Model showing the starting point of the simulation.
The allowable tension, minimum bend radius, axial compression of the cable, etc. are not exceeded.
The total movement of the joint is displayed in Fig. 21. Additionally, Fig. 21 highlights the cable shape at different time steps of
the dynamic simulation undertaken using the OrcaFlex software.
This gure starts at the moment the crane lifts the in-line joint
until the moment the in-line joint is laid on the seabed. It is worth
Fig. 20. Initial position of the crane hook with reference to the in-line joint.
Fig. 21. Cable shape at different time line of events and important events marked.
163
164
indicating that the slings were released from the pulley once the
in-line joint was laid on the seabed.
Wave height
Wave Period
Wave direction
Current velocity
The dynamic simulations are required to determine the maximum seastate condition within which the vessel can deploy the
joint and the cable giving regard to the following:
Fig. 24. Cable bending moment over length 38.4 m water depth.
Maximum
Maximum
Maximum
Maximum
165
cable will be presented only in this section. The other results will
not be presented due to the paper length.
Fig. 25 presents the tension in the cable obtained from the range
graph. In this gure, the maximum and minimum tensions are given
as a function of environment. It can be seen from the gure that the
signicant wave height of 1 m at the upper bound wave period shows
tensions are beyond the acceptable limit of the cable.
Fig. 25. Cable tension value versus signicant wave height, peak period and steady current for the worst wave heading and current.
Fig. 26. Cable tension value versus wave direction and current for wave height 1 m and time 5.47 s.
Fig. 27. Cable curvature value versus signicant wave height, peak period and steady current for the worst wave heading and current.
166
Fig. 28. Cable curvature value versus wave direction and current for wave height 1 m and time 5.47 s.
Table 9
Boundary condition and loading condition of analysis cases.
Analysis case Boundary condition
I
II
Loads applied
Maximum TensionDynamic
112
1:6
70
Maximum Tension for still water condition
167
Fig. 30. The boundary and loading condition of analysis case II.
Fig. 31. Stress contour of OFJ (Fixed at 2 Main Flanges, Bending Moment: 125 kNm).
168
Fig. 32. Stress contour of OFJ (Fixed at 2 Intermediate Flanges, Bending Moment: 125 kNm).
Table 10
Load applied during the on-land simulations.
Stage
1
2
3
Tension (Tonnes)
Left Side
Right Side
Left Side
Right Side
6.4
3.9
0.7
3.8
9
6.3
45
0
45
45
0
45
169
Table 11
Summary of in-line test items & associated acceptance criteria.
Specic In-Line Test Item
Acceptance Criteria
2. Torsion Test
Torsion of cable at end of bend restrictor
3. Radial Water Penetration Test
Radial water penetration test on one pre-molded joint including plumbing areas, 24
hours water pressure test
4. Visual Check of plumbing area
Visual check of plumbing area between cable sheath and copper housing ( three joints )
5. Measurement of internal displacement of cable
Check the measurements in axial and angular in the 3 dimensions
6. Visual Checks
Visual check of armor pot and bend restrictor
7. Dimensional/material check on pre-molded and OFJ used
No visible crack.
No Hole in plumbing area.
No visible gap between plumbing and lead sheath and copper housing.
Information for further analysis & usage. The accuracy if the measurements
was less than 5 mm.
No visible crack or deformation
This was done in accordance with the applicable manufacturing plans
170
Fig. 34. Tensile bending test (45 degrees) for in-line joint simulation.
optics joint and were found to pass the visual inspection and the
test plan which comprised of the serious of mechanical tests, ber
attenuation measurements and a water leakage test.
6. Conclusion
Currently, there are huge demands on the installation of subsea
cables around the globe. Often the installation takes place between
two distant locations where long cable lengths are required for
which subsea installation joints are unavoidable. The installation
of long cables requires repair joints. Based on that, it is essential
that the repair joint and installation joint will be designed to
withstand all the expected different loads during the design life
the same as for the cable. This is to increase the reliability and
availability of the subsea system and reduce the high cost involved
in the repair in the future.
171
Fig. 37. Tensile bending test ( 45 degrees) for in-line joint simulation.
Acknowledgment
The authors would like to thank Qatar Petroleum for their
permission to publish this paper.
Fig. 38. 45 degrees pulling test.
References
Failure of submarine power cables have been shown to be
attributed to cable eld joints on some cables. This could provide
indications that the current acceptance testing of these joints is
inadequate. Subsea cable failure could result in signicant nancial losses especially when power is transmitted via cables to
offshore production platforms.
Design guidance for cable eld joints suggests sea trails to
determine if the proposed eld jointing technique is acceptable.
Sea trails however are often prohibitively expensive, time-consuming, require large preparation and access to a vessel which is
CIGR (2010). NorNed, World's Longest Power Cable, CIGR, France, CIGR publication B1_106_2010.
CIGR TB490. Recommendations for testing of long AC submarine cables with
extruded insulation for system voltage above 30 (36 ) to 500 (550) kV.
DNV-RP-J301. Subsea power cables in shallow water renewable energy applications, February 2014.
DNV RP-C205. Environmental Conditions and Environmental Loads.
Electra 189. Recommendations for tests of power transmission DC cables for a rated
voltage up to 800 kV.
Electra 171. Recommendations for Mechanical Tests on Sub-marine cables.
International Cable Protection Committee (2009). Damage to submarine cables
caused by anchors. Loss Prevention Bulletin.
172
Worzyk, T., 2009. Accessories, Submarine power cables: design, installation, repair,
environmental aspects. Springer-Verlag Berlin Heidelberg, Berlin.
Woo, Jinho, Kim, Dongha, Na, Won-Bae, 2015. Safety analysis of rock berms that
protect submarine power cables in the event of an anchor collision. Ocean Eng.
107, 204211.
Yoon, Han-Sam, Na, Won-Bae, 2013. Safety assessment of submarine power cable
protectors by anchor dragging eld tests. Ocean Eng. 65, 19.