Project Description : EIA/EMP report for the proposed expansion of steel plant
to 1.5 MTPY along with waste gas CPP (17 MW) at
Wardha, Maharashtra
Package reference/general
50%
100%
Reports/FR/DPR
Software development
Basic Engg.
Detailed Engg.
Management Consultancy
Project Management
1 of 4
( % )
Actual
( . % )
Note : Up to point no. 2 the CSM form be filled by MECON Project Co-ordinator and handed over to
Customer.
up to 5 % ahead schedule
V. Good (4)
on schedule
Good
within 5 % of schedule
(3)
Average (2)
Poor
(1)
Due to climatic
adversity
Non-availability of
technical data from
Client
Due to fund/
resource constraint
(MECON / CLIENT)
delay in drawing
approval from Client
On account of
Sub-Contractor
engaged by Client
Non-availability
Of front by Client
On account of MECON
2 of 4
Excellent
(5)
V. Good
Good
Average
Poor
V. Good
Good
Average
Poor
(4)
(3)
(2)
(1)
Reports/FR/DPR
Basic Engg.
Detailed Engg
Procurement
Inspection
Vendor Drg. Approval
Construction
Supervision
Erection
Commissioning
Post Commissioning
Project Management
Any other, Specify
Excellent
(5)
(4)
(3)
(2)
(1)
Competence
Commitment
Courteousness
Co-ordination
Responsiveness
3 of 4
DISCLAIMER
The above feedback is based on current ongoing project and is being furnished
with the sincere objective of realizing the goal of Q.M.S. This shall not be treated
as legally and contractually binding on either party.
Signature
Name: Sankar Ramakrishna
Designation: Director(Technical & Engineering)
Organisation: Uttam Galva Metallics Limited
To:
<Dr. Vikas Kumar,DGM, Env.Engg>
4 of 4