for
Enhancement of
Private Sector Investment on
Small Hydro IPP Projects
in Indonesia
Final Report
June 2015
OS
JR
15-041
Survey
for
Enhancement of
Private Sector Investment on
Small Hydro IPP Projects
in Indonesia
Final Report
June 2015
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Survey
for
Enhancement of Private Sector Investment on
Small Hydro IPP Projects in Indonesia
Final Report
Table of Contents
Chapter 1 Background and Objectives of the Survey ........................................................................... 1
1.1
1.2
Chapter 2 Status of Small Hydropower Sector and Related Legal Framework .................................... 3
2.1
Investor....................................................................................................................................23
Financial Institutions ...............................................................................................................23
Construction Equipment Manufacturer ...................................................................................23
Equipment Suppliers/Manufacturer ........................................................................................24
General ....................................................................................................................................25
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
5.1
5.2
5.3
5.4
ii
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
List of Table
Table 2.1.1 Installed Capacity (2013)................................................................................................... 4
Table 2.1.2 Power Generation (2013)................................................................................................... 4
Table 2.1.3 Capacity Factor and Load Factor (2013) ........................................................................... 5
Table 2.1.4 Increase in Installed Capacity (PLN only, MW)................................................................ 6
Table 2.1.5 Power Development Plan (RUPTL 2013-2022) ................................................................ 6
Table 2.1.6 Outline of Crash Programs ................................................................................................ 7
Table 2.1.7 (1) 35 GW Power Development Plan (2015-2019) ........................................................... 7
Table 2.1.7 (2) 35 GW Power Development Plan (2015-2019) in Each Region .................................. 8
Table 2.1.7 (3) 35 GW Power Development Plan (2015-2019) in Each Source .................................. 8
Table 2.1.8 Potential of Renewable Energy ......................................................................................... 8
Table 2.1.9 Development Plan of Renewable Energy .......................................................................... 9
Table 2.1.10 Status of Small Hydropower Development (as of the end of February 2015)................. 9
Table 2.1.11 Historical Revision of Electricity Tariff......................................................................... 13
Table 2.1.12 Subsidy from the Government to PLN .......................................................................... 15
Table 2.1.13 Power Generation Cost by Sources ............................................................................... 15
Table 2.3.1 Power Purchase Price for Small Hydropower Project ..................................................... 19
Table 2.3.2 Power Purchase Price for Small Hydropower Project Utilizing Existing Structures ...... 20
Table 2.3.3 Permission/License for Small Hydropower Business...................................................... 22
List of Figure
Figure 2.2.1
Figure 2.3.1
Figure 4.2.1
Figure 5.3.1
Figure 5.3.2
Figure 5.4.1
Figure 6.1.1
iii
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Abbreviation
AMDAL
(Analisis Mengenai Dampak Lingkungan)
FIT
HGB
(Hal Guna Bangunan)
HO
(Hinder Ordonantie)
IMB
(Izin Mendirikan Bangunan)
IPP
IUPTL
(Izin Usaha Penyediaan Tenaga Listrik)
IUPTLS
(Izin Usaha Penyediaan Tenaga Listrik Sementara)
SIPPA
(Surat Izin Pengambilan dan Pemanfaatan Air)
SIPTPP
(Surat Izin Pemanfaatan Tanah Pemerintah Provinsi)
UKL/UPL
(Upaya Pengelolaan Lingkungan Hidup/
Upaya Pemantauan Lingkungan Hidup)
RUPTL
iv
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Chapter 1
1.1
In order to respond to the rapidly growing demand for electric power that has been increasing at an
annual rate of approximately 8%, the Government of Indonesia (GOI) has been promoting a new
power development by launching the First and Second Crash Program consecutively. According to
RUPTL 2013-2022, PT PLN plans to develop an additional 59,518MW of electric power facilities by
2022. In this plan, 836 MW will be filled through the development of small hydropower generation
facilities. Specifically, GOI attaches importance to the system of utilizing small hydro IPP projects
for 10 MW or less capacity. GOI is thus politically expediting small hydropower development, which
is small in size but can be developed in a short period of time with relatively small amount of
investment.
Under these circumstances, the number of private companies related to small hydro IPPs has been
increasing significantly, although actual physical construction has not been progressing smoothly.
The reasons for this are: (a) lack of technical experience in planning, designing, and engineering of
power generation facilities especially in local private companies, and (b) absence of Indonesian
rupiah-denominated long-term loans under project-based finance scheme. However, since no bidding
process is required under Indonesian laws, and also because business profitability is somewhat secured
by the feed-in tariff (FIT) system, small hydro generation is the area of interest among Japanese
companies with high technical capacities in terms of equity investment and equipment supply. At the
same time, the Japan International Cooperation Agency (JICA) provides a comprehensive framework
to support the enhancement of renewable energy in developing countries, from grant assistance for
feasibility study conducted by a private sector through the private sector investment finance
(hereinafter referred to as PSIF).
As described above, promoting small hydropower generation conforms to GOIs challenge and its
development policy. By utilizing the Japanese companies technology as well as JICAs PSIF, it is
possible to solve technical and financial problems, which have been the bottlenecks to promote small
hydro IPPs by the private sector. Therefore, this survey is designed to collect and verify related
information, and to coordinate needs and solutions of relevant parties.
1.2
1) Objectives
In order to promote private small hydropower projects, the survey aims to:
Examine the existing situation of small hydropower sector, the features and progress of the
projects, and the intention of Japanese companies and financial institutions on the sector; and
List up the projects which will be suitable for JICA-PSIF as well as participation of Japanese
companies.
2) Target Projects
Small hydropower projects listed by PLN.
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
3) Survey Area
Sumatra and Sulawesi islands in Indonesia
4) Targeted Project
Small hydropower project under FIT system (less than 10 MW)
5) Counterpart
Ministry of Energy and Mineral Resources (MEMR), PT PLN (Persero)
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Table 2.1.1
Region
Power Source
Hydro
Steam (Oil and Coal)
Gas Turbine
Combined Cycle
Geothermal
Diesel 1)
Solar
Wind
Subtotal
Sumatra
Sulawesi
863.82
223.56
1,182.00
635.60
857.88
110.00
1,047.57
0.43
0.00
4,696.70
112.00
134.72
0.00
80.00
454.55
3.08
0.08
1,007.88
Java - Bali
30.00
0.00
0.00
3.00
631.13
3.82
0.35
673.27
IPP
Total
7,437.18
1)
Includes diesel gas and rental.
(Source: Study Team, created from PLN Statistics 2013 and 2013 PLN Annual Report)
Table 2.1.2
IPP
Entire Indonesia
2,392.03
3,519.49
13,970.00
2,034.56
7,896.23
375.00
100.63
0.00
0.00
15,554.00
2,893.88
8,814.11
568.00
2,847.78
7.98
0.43
34,205.63
26,768.45
11,898.37
11,897.37
11,897.37
46,104.00
10.3%
45.5%
8.5%
25.8%
1.7%
8.3%
0.0%
0.0%
100.0%
(74.2%)
(25.8%)
(100.0%)
(GWh)
Region
Item
Hydro
Steam (Oil and Coal)
Gas Turbine
Combined Cycle
Geothermal
Diesel 1)
Diesel Gas
Solar
Sumatra
3,699.16
5,233.94
1,967.09
3,482.29
825.18
707.06
371.19
0.36
Sulawesi
1,453.10
470.43
54.35
0.00
521.09
472.67
3.76
2.05
Kalimantan
163.53
1,760.37
257.10
393.38
0.00
956.14
6.80
0.44
Java - Bali
7,663.15
73,314.28
3,637.97
32,547.75
2,970.89
69.27
-
Entire Indonesia
13,009.55
80,926.10
5,916.51
36,423.42
4,345.09
3,212.13
381.75
5.48
6.0%
37.4%
2.7%
16.8%
2.0%
1.5%
0.2%
0.0%
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Region
Sumatra
Sulawesi
Kalimantan
Item
Wind
0.00
0.00
0.00
Rental
9,536.02
2,014.83
3,959.75
IPP
7,337.42
3,657.65
869.52
Total
33,159.71
8,649.93
8,367.03
(Source: Study Team, created from PLN Statistics 2013 and 2013 PLN Annual Report)
Java - Bali
Entire Indonesia
1,544.87
40,209.21
161,957.39
9.1%
24.2%
100.0%
Table 2.1.3
Region
19,755.71
52,222.79
216,188.55
Sumatra
Item
Installed Capacity (MW)
4,697.30
Peak Load (MW)
5,329.11
Load Rate (%)
113.5%
Reserve Ratio (%)
-13.5%
Total Yearly Power
41,148.3
8,830.0
9,247.2
Generation (GWh) 2)
Yearly Power Generation
25,822.29
4,992.28
7,497.51
(GWh) 3)
4)
Capacity Factor (%)
62.8%
56.5%
81.1%
Yearly Peak Power
46,683.00
11,798.67
7,025.52
Generation (GWh) 5)
Total Yearly Power
33,159.71
86,49.93
8,367.03
Generation (GWh) 6)
7)
Total Load Factor (%)
71.0%
73.3%
119.1%
(Source: Study Team; created from PLN Statistics 2013 and 2013 PLN Annual Report)
Note: 1) IPP is not included.
2) Capacity x 8,760 hours
3) Power generation at power station side.
4) Capacity Factor = Yearly Power Generation / Capcity x 8,760 hrs
5) Peal Load x 8,760 hrs
6) Total power generation including imported one.
7) Total Load Factor = Total Yearly Peak Power Generation / Peak Load x 8,760 hrs
Java - Bali
Entire Indonesia
26,768.45
22,575.21
84.3%
15.7%
34,205.63
30,833.60
90.1%
9.9%
5,924.1
234,491.6
299,641.3
3,905.5
12,1748.18
163,965.75
65.9%
51.9%
54.7%
6,749.40
197,758.84
270,015.44
4,054.5
161,957.39
216,188.54
60.1%
81.9%
80.1%
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
In the nine years from 2005 to 2013, the installed capacity of 11,690 MW has increased. On the other
hand, RUPTL 2013, which involves the construction of power plants of 59,518 MW including IPP is
planned in the ten years up to 2022. It means 6,000 MW capacity power plants every year shall be
constructed. In the plan, 836 MW of small hydropower is to be developed.
Existing
Addition
Total
Capacity
Planning
PLN
IPP
Unallocated
Total
Power Source
Steam
Geo-thermal
Combined
Gas
Diesel
Mini-hydro
Hydro
Solar
Others
2022
Total
6,053
59,518
52,728
58,676
64,135
74,762
83,916
91,389
96,737
102,790
2,919
2,003
1,026
5,948
1,869
1,506
2,084
5,459
1,234
6,838
2,555
10,627
55
6,410
2,689
9,154
90
3,948
3,435
7,473
2,003
1,391
1,954
5,348
1,244
1,535
3,274
6,053
16,853
25,552
17,113
59,518
2,891
85
1,200
1,376
249
10
137
2,014
580
950
273
241
341
1,040
20
7,339
495
2,350
128
31
284
-
6,933
1,665
165
5
386
-
5,640
650
60
3
671
450
-
2,932
670
123
1,173
450
-
3,280
1,825
120
824
4
37,969
6,060
5,000
3,676
836
3,753
1,940
282
2,518
314
2,908
878
2,832
3,786
2,013
729
96
2,838
2,464
90
250
21
6
2,931
60
80
539
107
20
50
1,545
30
330
642
180
45
65
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
The Indonesian government will supply the rapid increase in power demand and to reduce its
dependence on oil. As part of the urgent power development plan, two crash programs were
formulated and implemented. The outline of the crash programs is as follows:
Item
Development Plan Period
(Initial)
Purpose
Developed Capacity
10,000 MW
(Java-Bali: 6,900 MW
Outside the territory : 3,100 MW)
Power Supply
Configuration
Coal: 100%
Progress in 2014
Completed: 7,368 MW
In progress: 2,439 MW
2010-2014
- Emergency power supply
development
- Power diversification
- Utilization of renewable energy
10,000 MW
(Java-Bali: 5,070 MW
Outside the territory : 4,452 MW)
Review in 2012 and 2013, with
18,000 MW as target.
Renewable energy 54%
(Geothermal 41%, Hydro 13%)
Fossil fuel 46% (Coal 36%, Gas
1%, Combined Cycle 9%)
Completed: 55 MW
In progress: 17,403 MW
Both crash programs are experiencing significant delays, main reasons for which are delays in land
acquisition and various licensing/permission procedures. Projects in the 1st crash program were
mainly contracted with Chinese companies. However, many problems such as lack of cash for
construction have been reported. Moreover, there were many out of orders and insufficient rated
output of the power generation equipment even it was completed.
Furthermore, the 2014 new president, Mr. Jokowi, announced his ambitious plan to develop a 35.5
GW power plant over the next five years.
Table 2.1.7 (1)
No
1
2
3
4
Total
Each region and power source of the 35 GW Power Development Plan are shown in Table 2.1.7 (2)
and Table 2.1.7 (3), respectively.
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Sumatra
Jawa-Bali
Kalimant
an
Sulawesi
Nusa
Tenggara
Maluku
PLN
1.1
5.0
0.9
2.0
0.3
IPP
7.6
15.9
1.0
0.7
0.0
Total
8.7
20.9
1.9
2.7
0.3
(Source: PLN)
*) 35.5 GW corresponds to Total (excl. Construction) in Table 2.1.7 (1)
Table 2.1.7 (3)
Steam
PLN
Extension
IPP
PPP
Total
Papua
0.7
0.0
0.7
0.2
0.1
0.3
Total
10.2
25.3
35.5*)
Steam
(Mine
Mouth)
5.6
5.2
12.3
23.1
1.6
1.2
2.8
Gas/
Combined
Hydro
Geothermal
Others
Total
7.2
1.4
0.1
0.1
6.2
0.2
1.1
0.7
13.4
1.6
1.2
0.8
14.4
5.2
22.1
1.2
42.9*)
(Source: PLN)
*) 42.9 GW corresponds to Total (incl. Construction) in Table 2.1.7 (1)
Ratio (%)
(4) = (3)/(2)
1.15
0.89
0.01
0.01
The development plan for renewable energy until 2022 is listed below by year.
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Table 2.1.9
No.
1
2
3
4
5
New/Renewable
Energy
Mini/Microhydro
Solar Power
Wind Power
Biomass
Ocean
Total
Unit
MW
MWp
MW
MW
MW
MW
2013
2014
33
6
48
87
42
104
10
156
2015
2016
96
75
50
15
1
237
149
54
20
20
243
2017
237
36
20
30
1
324
2018
192
60
20
40
3
315
2019
186
75
30
50
3
344
2020
156
75
40
50
5
326
2021
190
75
50
50
5
370
2022
200
75
50
50
10
385
Total
1,481
634
280
363
28
2,786
Small hydro-electric power takes the major share in renewable energy and its development is
expected.
According to the PLN, a total of 318 projects with less than 10 MW capacity as well as under FIT
scheme has been proposed to PLN in the entire Indonesia. Out of 318 projects, 49 projects are
currently in operation and 49 projects are under construction. About 220 projects are at present before
financial closure status.
Table 2.1.10 Status of Small Hydropower Development (as of the end of February 2015)
Status
Indonesia Timur
Operation
Construction
Financing Proces
PPA Process
Proposal
Jawa Bali
Operation
Construction
Financing Proces
PPA Process
Proposal
Sumatera
Operation
Construction
Financing Proces
PPA Process
Proposal
Grand Total
(Source: PLN)
In Table 2.1.5, the development capacity of mini hydropower until 2022 is 834 MW. On the other hand, the total
development capacity is 1,481 MW in Table 2.1.9, thus there is a discrepancy between the tables. Taking the present
application condition of FIT projects into consideration, Table 2.1.9 is deemed to be correct.
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
2.2
Oil:
Natural gas:
Coal:
Renewable energy:
In addition, the electrification rate is targeted at 85% by 2015 and nearly 100% by 2020. Domestic
primary energy shall be used for domestic purposes as much as possible. As a related policy, the
National Energy Management Blueprint (BP-PEN) 2006-2025 was established and national targets
related to energy were set.
Based on the policy in KEN, in the electric power sector, the MEMR established the National Electric
Power General Plan (RUKN) and developed PLN, who is the only power supply company in
Indonesia. It also prepared the Electric Power Implementation Plan (RUPTL) and implemented the
power development plan. The RUPTL is formulated for a period of ten years, however, it is revised
every year. As a relevant economic policy, national development plans such as the National Long-term
Development Plan (RPJPN) are formulated every 20 years. Governed by the RPJPN, the National
Medium-term Development Plan (RPJMN) is formulated every five years. The latest RPJMN was
prepared in 2014.
As for the laws on energy and power, these are the: 1) Energy Law (2007), 2) Electric Power Law
(2009), 3) Decree on Save Energy (2009), and 4) Geothermal Power Law (2003). The Energy Law of
2007 covers management and usage of all energy resources such as 1) management of energy
resources by the government, 2) stable energy supply, 3) resources development promotion, 4)
formulation of national energy policy and energy plan, and 5) use of renewable energy. The new
power law is a revision of the old energy law in 1985. In the power law, the government is responsible
for power supply. However, aimed at the improvement of power supply, it is now possible for
state-owned companies other than PLN, public enterprises, private enterprises, cooperatives, and civic
groups to participate in the power generation business. RUKN and the revision of power tariff require
parliament approval. The Decree on Save Energy stipulates to oblige energy saving in large consumers
of energy. The Geothermal Power Law acknowledged the participation of private investors in
integrated development of geothermal projects including steam development, supply and power
generation for geothermal development promotion. The processes of getting permits and licenses in
each phase of geothermal energy development have become clear.
10
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Development of peak load power plants by gas, pumped storage power plant; and
11
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Establishment of sustainable power supply system for various energy power sources; and
Support of gas supply for gas power generation and storage of coal for coal-fired power
generation as a reduction measure for oil-dependency of fuel.
The RUPTL is a ten-year plan, but due to actual delays of the plan and changes in conditions, it is
updated every year. It is a power development plan prepared based on the present situation. The power
development plan is established to satisfy the electricity demand which is forecasted to consider future
economic and population growths. Construction of the transmission and distribution networks are
planned in order to harmonize with the power development plan. Further, the required construction
costs for these electric power development and fuel costs required for operation are estimated.
12
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Contract Voltage
Basic Tariff
(Rp./kVA/month)
Condition
before 2013
Oct. 2013
Nov. 2014
14,800
Social
S-1/TR 220 VA
S-2/TR 450 VA
(per month)
10,000
S-2/TR
900 VA
15,000
14,800
14,800
Block I : 0 - 30 kWh
123
123
123
Block II : 30 - 60 kWh
265
265
265
360
360
360
Block I : 0 - 20 kWh
200
200
200
Block II : 20 - 60 kWh
295
295
295
360
360
360
S-2/TR 1,300 VA
605
708
708
S-2/TR 2,200 VA
650
760
760
755
900
900
K x P x 605
K x P x 735
K x P x 735
P x 605
P x 735
P x 735
925
925
Peak
Off peak
kVArh
Residential
R-1/TR
R-1/TR
900 VA
20,000
Block I : 0 - 30 kWh
169
169
169
Block II : 30 - 60 kWh
360
360
360
495
495
495
Block I : 0 - 20 kWh
275
275
275
Block II : 20 - 60 kWh
445
445
445
495
495
495
R-1/TR 1,300 VA
790
979
1,352
R-1/TR 2,200 VA
795
1,004
1,352
890
1,145
1,352
1,352
1,352
Block I
H1 x 890
Block II
H2 x 1,380
Business
B-1/TR
B-1/TR
450 VA
900 VA
23,500
26,500
Block I : 0 - 30 kWh
254
254
254
420
420
420
420
420
420
465
465
465
790
966
966
905
1,100
1,100
1,352
1,352
K x 800
K x P x 1,020
K x P x 1,020
800
P x 1,020
P x 1,020
1,117
1,117
B-1/TR 1,300 VA
B-1/TR 2,200 VA-5,500 VA
B-2/TR 6,600 VA-200 kVA
Block I
H1 x 900
Block II
B-3/TM more than 200 kVA
H2 x 1,380
Peak
Off peak
kVArh
13
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Customer/
Category
Contract Voltage
Basic Tariff
(Rp./kVA/month)
Condition
before 2013
Oct. 2013
Nov. 2014
Block I : 0 - 30 kWh
160
160
160
395
395
395
Block I : 0 - 72 kWh
315
315
315
Industry
I-1/TR
450 VA
26,000
I-1/TR
900 VA
405
405
405
I-1/TR
1,300 VA
790
930
930
I-1/TR
2,200 VA
905
960
960
915
1,112
1,112
K x 800
K x P x 972
K x P x 972
800
P x 972
P x 972
I-1/TR
I-2/TR
31,500
Peak
Off peak
kVArh
I-3/TM
1,057
1,057
K x 680
K x P x 803
K x P x 1,115
680
P x 803
P x 1,115
864
1,200
723
1,191
723
1,191
575
Peak
Off peak
kVArh
I-4/TT
605
-
20,000
575
575
P-1/TR 900 VA
24,600
600
600
600
880
1,049
1,049
885
1,076
1,076
1,352
1,352
K x P x 750
K x P x 947
K x P x 1,115
P x 750
P x 947
P x 1,115
1,026
1,200
997
1,352
K x 390
K x 483
K x 483
390
483
483
808
808
K x 445
Q x 707
Q x 707
445
Q x 707
Q x 707
1,450
1,650
1,650
P-1/TR 1,300 VA
P-1/TR 2,200 VA-5,500 VA
P-1/TR 6,600 VA-200 kVA
H1 x 885
H2 x 1,380
P-2/TM
Peak
Off peak
kVArh
P-3/TR
Railway
T/TM
Peak
23,000
Off peak
(30,950 after 2013)
kVArh
30,000
( 0 after 2013)
Emergency/Multipurpose
L/TR, TM, TT
Notes,
1) K : Factor for cost between Peak and Off-peak in each system (region) decided by PLN. (1.4 < K < 2.0)
2) P : Factor for social building, (Pure social building : 1.0, General social building : 1.3 )
3) kVArh : If monthly average power factor is less 85%, electric tariff for kVarh is added.
4) H1 : National average % saving on Lighting Time x Connected Power (kVA)
5) H2 : Energy consumption - H1
6) Q : Factor depend on commercial use and non-commercial use decided by PLN (08 < Q < 2.0)
14
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Year
Subsidy (Rp10^9)
2013
101.2
As reference, generation costs of each power source are shown in Table 2.1.13.
Table 2.1.13
15
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Income TaxDevelopers can obtain 5% reduction in the income tax rate of its investment each
year for a period of six years.
Accelerated DepreciationDepreciation of fixed assets can be completed within ten years and
hence, reduce the income tax.
Incentives for Foreign CompaniesIncome tax on dividends of foreign investors can be 10%.
Import DutyThe import duty is exempted for equipment and machinery that cannot be
procured in Indonesia.
16
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Figure 2.2.1
17
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
2.3
Submission of application
DG of EBTKE
Receipt of decision
Temp. IUPTL application
DG of EBTKEPLN(copy)
MEMRDG of EBTKE(copy)
Deposit submission
DG of EBTKE
MEMR
Financial closure
DG of EBTKE(copy)
DG of EBTKE(evidence)
PL
IUPTL appl.
Sign PPA
MEMR
DG of EBTKE(copy)
MEMR
IUPTL receipt
DG of EBTKE(copy)
Construction
30 days
30 days
30 days
15 months
3 months
90days
Feed-In Tariff(<10MW):
1 8
Rp.1,075.0/Kwh x F
Factor F
9 20
Rp.750.0/Kwh x F
Java,Bali and Madura: 1.00Sumatera: 1.10Kalimantan and Sulawesi: 1.20West Nusa Tenggara and East Nusa
Tenggara: 1.25Maluku and North Maluku: 1.30Papua and West Papua: 1.60
18
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
2) Negative List
The latest version of the Investment Negative List, which entered into effect on April 24, 2014,
clarifies the situation regarding foreign direct investment (FDI) in the mini-hydro sector. Under the
previous version of the list, such investment was stated as being 100% open to FDI subject to a
partnership arrangement with a local firm.
However, as it was unclear what precisely was meant by a partnership arrangement, thus this tended
to discourage foreign investors. By contrast, the regulation states that the small hydro sector is now
open to up to 49% FDI.
3) Issues on Process of Appraisal and Approval
The current issues on the process of appraisal and approval for small-hydro IPPs can be identified as
follows:
When a developer has an issue on debt financing, the developer recognizes that the duration
from the agreement of PPA to the financial closure is short.
When the viability of a project has an issue on revenue and power tariff, the schedule for the
feasibility study may be delayed.
A developer identified the need for PLN and MEMR to strengthen their coordination in
providing a clear direction for the application of the regulations such as PPA.
Medium Voltage
(up to 10 MW)
Year 1 - 8 : 1,075.0 x F
Low Voltage
(up to 250 kW)
Year 1 - 8 : 1,270.0 x F
Year 9 - 20 : 750.0 x F
Year 9 - 20 : 770.0 x F
1.0
1.1
1.2
East
1.25
1.3
1.6
(Source: JICA Survey Team based on the Regulation of the Minister of Energy and Mineral Resources of
Indonesia No. 12/2014)
The procedures necessary for implementing small hydropower projects such as required documents,
permits, approvals, and necessary period became clear.
19
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Due to this modification and clarification of the purchase prices and procedures, many have applied
for small hydro projects under FIT. In August 2014, the Government of Indonesia through MEMR
Regulation No. 22 of 2014 (Reg. 22/2014) revised the applicability of the FIT system to also cover
mini- hydro power projects utilizing multipurpose dams and/or irrigation channel water resources.
However, a lower FIT is applied for these projects.
Table 2.3.2 below summarizes the FIT currently applicable to small hydropower projects utilizing
existing structures. According to information source, there may be an ongoing review on the FIT price
by PLN as of the study period (February 2015). The review would examine the increase of tariff as
well as the currency for payment.
Table 2.3.2
Power Purchase Price for Small Hydropower Project Utilizing Existing Structures
Feed-In-Tariff (Rp./kWh)
Voltage/Capacity
F Factor, Depending on the Location
Small Hydro Projects utilizing
multipurpose dams and/or irrigation
Medium Voltage
(up to 10 MW)
Year 1 - 8 : 967.5 x F
Low Voltage
(up to 250 kW)
Year 1 - 8 : 1,143.0 x F
Year 9 - 20 : 675.0 x F
Year 9 - 20 : 693.0 x F
1.0
1.1
1.2
East
1.25
1.3
1.6
(Source: JICA Survey Team based on the Regulation of the Minister of Energy and Mineral Resources of
Indonesia No. 22/2014)
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
average price set out in the regulation, which is adjusted based on voltage and location. The new price
is fixed and must be directly set out in a PPA. It remains valid for the duration of PPA. The price
adjustment process must be completed within 90 working days of the designation of the project
sponsor as a hydropower producer. The adjusted price must also be approved by the Minister.
4) Hydro Power Plants of more than 10 MW
The power tariff from hydropower plants of more than 10 MW is stipulated in the MEMRs
Regulation (No.03/2015). The power tariff is charged at a maximum of US9.00/kWh for 10 MW to
50 MW, US8.50/kWh for 50 MW to 100 MW, and US8.00/kWh for more than 100 MW. The
purchase price is subject to the agreement between PLN and the developer.
Take-and-pay clauseThe impact on revenue has been identified in case the plants cannot sell
the scheduled energy due to the demand situation in the power grid.
The power tariff is low, hence, the developer cannot secure a financial return. (This tariff may
be being revised according to an information source.) PLN can consider a simple increase of
power tariff as well as a two-part tariff of the fixed payment based on the output capacity and
the energy production.
The feasibility study needs to deal with additional matters due to the request from the PLN
equipment related with the receiving purchased power since there is a need to confirm the
appropriateness of the current system.
PLN may be able to take a proactive action for a project whose PPA will expire.
PLN could consider the power tariff payment in other currency other than Indonesian rupiah.
21
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
In some cases SPCs have limited access to debt financing based on the credit record of SPC
and may be requested to submit a collateral by parent companies. Since the execution of PPA
may not be fulfilled by SPC alone, having a counterpart of the PPA may also be studied.
Some developers hope that PLN can strengthen its capacity for guiding the developers and
coordinating with the government offices.
In addition to the establishment of SPC (Special Purpose Company), the permissions and licenses
required for small hydropower business are as follows:
No.
1
2
3
4
5
6
7
8
9
Table 2.3.3
Name
Izin Princip
UKL&UPL
Izin Lokasi
HGB
IMB
HO
SIPTPP
SIPPA
HPO*)
(Hydropower Operation License)
10 IUPTLS
11 IUPTL
*) Tentative name because of no official name
(Source: JICA Survey Team)
Development permission
Environmental permission
Land acquisition license
Land register
Construction permission
Obstacle permission
River use permission
Water use permission
Local government
Local government
Local government
Local government
Local government
Local government
River administrator
River administrator
MEMR (EBTKE)
MEMR (Kelistrikan)
MEMR (Kelistrikan)
No.1 to No.8 can be processed in parallel and the period is estimated to be around 9 months.
After No.3 Izin Lokasi, land acquisition is carried out and then HGB is obtained.
For application of No.9 HPO, No.1, Pre-FS report and No.3-N.8 are required.
In case that the project area includes public forest, Izin Pinjam Pakai (Forest Use Permission) from
the Ministry of Forest is required.
22
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Investor
To cope with the rapid growth in power demand, public funding for electric power development is not
enough. Then, the Indonesian government has issued Presidential Decree No. 37/1992 in order to
expedite participation of private companies into the power business, namely as IPPs business.
Afterwards, due to the increase of IPPs in 2013, the power supply from the IPPs has reached 24%.
According to government policy, the maximum use of renewable energy including hydropower, FIT to
purchase fixed tariff for renewable energy was introduced in 2012. Further, in May 2014, MEMR
issued Decree No.12/2014 in revising the part about small hydropower and PLN is obliged to purchase
at the fixed prices from small hydro power plants of less than 10 MW. Introducing the FIT system
means enhancing participation of private investors by buying at advantageous prices. In addition, rural
electrification and replacement of diesel power plants will be accelerated.
On the other hand, Presidential Decree No. 39/2014 (so-called Negative List) has been issued in April
2014. The decree stipulated that the maximum capital participation of foreign companies to IPP
developer (SPC: Special Purpose Company) is at 49% in order to protect Indonesian investors and
enhance incentives. As exemption, SPCs established before April 2014 can keep the original capital
ratio.
Based on these backgrounds, Indonesian private investors have high motivation to participate in IPP
business in which FIT is applicable. According to PLN information, 318 IPP projects under FIT from
the entire Indonesia have been submitted for approval, and pre-feasibility study (Pre-FS) and
feasibility study (FS) reports have been filed. Out of the 318 projects, 49 projects are now in operation,
49 projects under construction, and 220 projects are under before financial closure status.
3.2
Financial Institutions
It was found that they have some experience of funding small hydropower project with difficulties on
examination of loan application. Therefore, the corporate finance is more common than the project
finance.
3.3
Considerable numbers of Indonesian contractors are participating in capital of SPCs for hydropower
IPPs, however, it is hard to judge from the name of the SPCs only. Detailed information about SPC
will be confirmed. State-owned construction company, PT. Wijaya Karya is active in the IPP business.
There are not so much IPP applicable FIT projects under operation or under construction, as the
contractors are joining as the Contractor as their main business.
Participation of foreign contractors to IPPs is only for large-scale hydropower IPP as the contractor.
Participation of Korean companies as the contractor is remarkable. On the other hand, foreign
contractor participation to IPP project under FIT is almost nil.
23
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Many developers planned to employ domestic civil construction contractors for the construction work.
A few of them have plans to use the Chinese contractor by mobilizing the debt from China. Some
developers undertake the design and engineering work on their own and outsource the construction
work only, while for developers who do not have a construction team, a leasing company for
construction equipment will construct the plant on its own using their own equipment and staff. Thus,
the mode of the construction varied depending on the resources and situation of the developers.
3.4
Equipment Suppliers/Manufacturer
Equipment manufacturers/suppliers are participating as the contractors to IPP as per normal activity.
Gates and penstock can be produced by domestic companies. Both domestic and foreign companies
can design, manufacture, and install gate facilities. On the other hand, turbines, generators, and related
equipment should be relied on foreign companies and design and manufacturing shall be by a foreign
company except for some minor portions.
24
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
General
The issues for selection and identification of potential projects are: i) technical aspect, ii) organization
and financial aspect, and iii) environmental aspect. In addition, the possibility of project bundling is
considered.
For the technical aspect, i) annual rainfall, ii) design discharge, iii) waterway length, iv) capacity and
power generation, v) unit cost of construction and electricity, and vi) transmission line have been
examined. In addition, detailed examination was carried out for potential projects. With regard to the
organization and financial aspect, i) organizational capacity, ii) financial capacity, iii) status of project
preparation, and iv) investment scale have been examined referring to the results of individual
interviews in addition to the general review. For the environmental aspect, all projects must have
already passed their initial environmental examination and it is assumed that there is no serious
environmental problem. Therefore, related information such as UKL/UPL and FS was reviewed and
environmental issues of the projects were examined.
25
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
PLNlist
Project Information(FSetc.)
Technical
aspect
Organization and
Finance
Environmental
aspect
Complehensive
evaluation
Data collection
Generalreview
Data collection
Generalreview
Project bandling
1stselection
Evaluation
Evaluation
2ndselection
Detailed
evaluation
PotentialProjects
Figure 4.2.1
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Chapter 5
5.1
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
on events such as force majeure. Finally, the situation where the project SPC runs into financial
difficulty should be examined, and the loan-providing banks should consider execution of collateral
for recovery of the loan. This issue is not for the developers and therefore, it is extremely important for
the banks to carefully examine their own resources.
z
According to Article 19 of the PPA template, which is under review by PLN, the termination of
the PPA occurs if the project SPC (referred to as SELLER in the PPA) runs into bankruptcy or
other similar situation. If the termination of the PPA occurs, the termination of purchasing
obligations of PLN under the FIT system occurs accordingly. It is an extremely serious situation
for the bank because the small hydropower IPP facilities become practically of zero value without
the FIT system.
ARTICLE 19 AGREEMENT TERMINATION
1. Each of the following events is the SELLERs failure which may result in this AGREEMENT
TERMINATION:
a. (omitted)
b. (omitted)
c. the occurrence of the following events: (i) the passing of judgment on bankruptcy, financial
inability, liquidation process, or liquidation or other similar events related to the SELLER; (ii)
appointment of trustee, liquidator, custodian, temporary officer to implement the process set
forth in point (i), where such appointment is not revoked or survives for more than 60 (sixty)
CALENDAR DAYS, or (iii) court order to execute liquidation process, or confirm bankruptcy
or financial inability, where such order is not revoked or survives for more than 60 (sixty)
CALENDAR DAYS.
On the other hand, special consideration, as stipulated under Article 18 of the PPA, is made for
the lender of the loan in financing the construction of small hydropower IPP facilities.
ARTICLE 18 ASSIGNMENT OF AGREEMENT
1. (omitted)
2. (omitted)
3. If in the performance hereof, the SELLER assigns and delegates part or all of its rights and
obligations to any OTHER PARTY without the BUYERs prior written approval, the BUYER
may unilaterally terminate this AGREEMENT, save such assignment and delegation are
obliged by the lender in connection with POWER PLANT construction financing.
(underlined by the JICA study team)
One of the simple interpretations of these articles in a manner, which are rather favorable for the banks
is that the project SPC under financial difficulty should sell its project assets to a third party by
following the order of the bank in accordance with Article 18 before it goes into real bankruptcy as
stipulated in Article 19. Then, it is possible that the assignment of the PPA will be made after the sales
of the project assets, and the purchasing obligation of the PLN continues under the FIT system in
accordance with the PPA. Another interpretation may be that Article 18 applies only when the project
SPC were to assign the PPA to a third party and does not apply when 100% of the shares of the project
SPC were to be sold to the third party without changing any legal status of the project SPC under the
PPA. On the contrary, such an interpretation may be opposed by PLN because the share sales of the
28
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
project SPC may practically have the same impact of the assignment of the PPA. Obviously, these are
the issues that should be consulted with Indonesian lawyers, but what is important is that the
loan-providing banks should secure the legal status where the value of the project assets would not be
seriously deteriorated.
4) Sponsor Risks of the Developers
It should be examined if the developers have the necessary engineering capacity and operational
organization to carry out a small hydropower IPP project. It is often the case where the developer
becomes the operator of the IPP facility. The developers experience on hydropower operation should
also be examined. Furthermore, the financial capacity of the developers should be confirmed in order
to pay down the equity contribution of the project SPC, but the risk will be mitigated if the
disbursement of the loan occurs only after the equity is fully paid.
Other procedures and items to be confirmed are described below.
5)
Legal Risks for Real Estate-related Contract, Water Utilization and Other Licenses
Including Those by the Local Government
A stable business environment is indispensable for the project to generate the revenues estimated in
the cash flow projection. For this purpose, it should be confirmed during the appraisal process that the
legal status have been clarified such as land and water utilization rights and other authorization or
licenses, including those from the local government. Sometimes in developing countries, these legal
issues are not as rigid as in developed countries. In such a case, it may be realistic to accept the normal
banking practice in the local market.
5.2
In consideration of the financing structure for small hydropower projects, the transaction costs such as
for FS, due diligence, and legal fees for loan documents, including the collateral agreements are the
most important issues from a practical banking point of view. In a typical type of project financed by
investment banks in the private sector with loan amount of US$100 million, for example, it is
anticipated that the FS and other transaction costs are approximately 2%-3% of the total loan amount,
which is approximately US$2-3 million. The transaction costs should cover all the necessary credit
risk analysis as discussed in the previous section of this report.
On the other hand, it should be strongly mentioned that the issues to be covered does not change in the
credit appraisal process of the project financing. For example, a project financing of US$10 million
29
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
requires almost the same degree of rigor in the credit appraisal process as that of US$100 million, and
therefore, the FS and other transaction costs should be almost the same amount. Approximately
US$2-3 million of the transaction costs represent 2%-3% in the project financing of US$100 million,
but they represent 20%-30% of the US$10 million, which seriously deteriorates the profitability of the
project. For small hydropower IPP projects regulated under 10 MW in Indonesia, the maximum initial
investment should be limited below Rp300 billion, which is calculated by applying the benchmark of
Rp30 billion/MW, as discussed in the previous section. Therefore, the project financing loan amount
would be approximately Rp150-210 billion, which correspond to 50%-70% of the initial investment of
Rp300 billion. In such small-scale project financing, it is important to secure the sufficient FS and
other transaction costs.
One of the solutions to the transaction cost issue is provided by JICA through the public offering
initiative in the public-private partnership (PPP) infrastructure preparatory study, which supports up to
JPY 150 million for FS to potential developers of various infrastructure projects. Some may claim that
the support of JPY 150 million does not fully cover the necessary costs, but it certainly help the
developers burden for FS and other transaction costs. Another approach may be considered by
combining a few small hydropower projects to arrange a medium-scale project financing loan. In the
next section, some financing structures will be studied for this purpose based on various efforts by the
financial institutions in the Indonesian financial market.
5.3
IFC
Development Agencies
in Europe
Private Sector
Investors
Fund investment
Investment Fund (Armstrong etc.)
Equity investment to projects
Project
Project
Project
There are some technical issues on this scheme such as limited timing for application because
renewable energy funds are often raised in closed form, in which investors can submit application only
within an application period.
2) Financing Structure for Bank Loan
The two-step loan scheme is recommended in order to encourage these Indonesian banks to work on
project financing. As a pre-condition, it should be mentioned that the target project for lending is small
30
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
hydropower IPP with equity contribution by Japanese investors at a certain percentage, which
differentiates the project target from the two-step loan that has been already implemented by the
French development assistance agency AFD.
JICA / PSIF
Loan
[Issues, which Intermediary
Intermediary Banks (SMI, IIF)
Banks take main role]
(1) Construction costs and
Project Financing Loans
completion risk
(2) Water flow risks
Project
Project
Project
(4-2) Indonesian
sponsor risks
As for the credit appraisal process, all the credit issues in the project financing approach should be
covered in an appropriate manner, but adequate segregation of roles should be discussed between
JICA and intermediary banks in order to avoid overlapping roles, which may cause increasing the FS
and other transaction costs. As mentioned in Section 6.1, the main risks are as follows:
Construction risks for small hydropower IPP facilities
Drought, flood, and discharge risks
Risks related to the PPA to be signed with PLN
Sponsor risks of the developers
[Issues, which JICA takes main role]
Among other credit risks, it is recommended for JICA to be mainly responsible for (3) Risks related
to the PPA to be signed with PLN because the template form of the PPA has been already publicly
announced by PLN and it covers all the future small hydropower IPP projects in a comprehensive
manner. If there is any serious credit issue, which may be identified in this phase, there is no need to
go further in the credit appraisal process, including the engineering appraisal mostly conducted by the
intermediary banks.
In general, the credit appraisal process should not be conducted only by analyzing the contract, but it
should be based on the specific project file in order to avoid idealistic arguments. However, a small
hydropower IPP project is an exceptional case because the sales risk of the project SPC is mostly
mitigated by the FIT system as defined in the PPA, and therefore the assumptions for the cash flow
projections are foreseeable. Moreover, there are some files, which are already reviewed by the PPP
infrastructure preparatory study and it is relatively easily anticipate the specific features of the project.
In this context, it is recommended to conduct credit analysis based only on the PPA in exceptional
cases.
31
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
The issue of (4-2) Japanese sponsor risks is also recommended for JICA to take a main role for
tackling the issue because most of such risks are often related to Japanese companies.
[Issues, which the intermediary banks take main role with JICAs support]
Among other risks, it is recommended that (1) Construction risks for small hydro IPP facilities and
(2) Drought, flood and discharge risks should be taken by the local intermediary banks because
these are mostly related to engineering issues, which are reflected by the topographical conditions of
each project site. It is practical to assume that the engineering works should be done by the consultants
who know the local conditions and the intermediary banks confirm the validity. The overall procedure
should be reconfirmed by JICA, which may also provide various advice if needed. As a conclusion, it
is expected that all the credit issues should be covered without duplication. The other issue of (4-1)
Indonesia sponsor risks is also recommended for JICA to take a main role for tackling such issue
because most of these risks are often related to Japanese companies.
With regard to the proposed credit guidelines for intermediary banks, it is recommended to include the
following items.
(1) The involvement by Japanese company to the project SPC with XX% or more equity contribution,
or other commitment to the management, which is explicitly confirmed such as secondment of
board member, who is based in Indonesia if possible.
(2) The intermediary bank receives JICAs capacity development program in the similar manner as
AFDs two-step loan.
(3) The necessary measures have been taken to mitigate the construction risks, such as completion
guarantee by a stakeholder who has strong financial bases, action plan is prepared for capital
increase in case of cost-over-run, favorable opinion from engineering review by a reputable
consulting firm and so on.
(4) Other issues raised at the appraisal process of the PPA related risks.
The proposed credit guideline is more focused on the engineering issues because it is assumed that
JICA goes through the appraisal process of the PPA related before entering into the detailed
negotiation with the intermediary bank. (1) is to confirm the Japanese involvement for PISF program
of JICA. On the other hand, the final decision should be made by its own discretion without too much
influenced by the credit guideline because the intermediary bank fully takes the credit risk under the
two-step loan scheme. But, the capacity building program should be provided if the intermediary bank
does not have sufficient experience in project financing.
5.4
A single developer that is considering to conduct several small hydropower IPP projects in the same
river basin may be referred to the same technical data for (2) Drought, flood and discharge risks,
which may contribute to the reduction of the FS cost. It may be applied for both direct loan structure
under JICA-PSIF as well as two-step loan via local intermediary banks.
32
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Project
Project
However, it is advised to be identical for the developer because a holding company should be
established for bundling the SPC of each project. The holding company will be the borrower of the
JICA loan and the repayment sources will be served from the total cash flow of each project, and
therefore it may be considered as if each SPC cross guarantees the holding companys loan. If the
equity contributors are different among the projects, it will be difficult to provide the cross guarantee
among the project SPCs.
33
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Chapter 6
Based on the survey results, the preliminary action plan considering the permissions/approvals
procedure for small hydropower development in Indonesia, timing for project participation by
Japanese companies, and procedures for JICA-PSIF was examined. Even though the actual
development schedule seems to be different due to past revisions of regulations and individual
situations of the various projects, a typical schedule for small hydropower development is shown in
Figure 7.1.1 below. The development is divided into five stages, from project identification to project
commissioning, as illustrated in the figure.
No.
Item
1 Project Identification
2 SPC establishment
3 Principle permit
4 Pre-FS, UKL&UPL
5 Location Permit
6 Land acquisition
7 Permissions (IMB, HO, SIPTPP, SIPPA)
By
Developer
Developer
1st Yr
2nd Yr
3rd Yr
4th Yr
5th Yr
2 4 6 8 10 12 2 4 6 8 10 12 2 4 6 8 10 12 2 4 6 8 10 12 2 4 6 8 10 12
Development
stage
Local gov.
Developer
Local gov.
Developer
Local gov., River authority
Proposal
stage
ProessPPA
stage
13 FS
Developer
14 FS submission to PLN (incl. other required docs) Developer
15 PPA
Developer, PLN
JICA
Developer
19 IUPTL
MEMR(Kelistrikan)
Developer
Developer
Developer
Processfinancing
stage
Implementation
stage
Development stage
In this stage, project identification, establishment of special purpose company (SPC), acquisition of
principle permission, pre-feasibility study (pre-FS), approval of UPL/UKL, land acquisition and
acquisition of necessary permissions (IMB, HO, SIPTPP, SIPPA) shall be carried out. In case that a
Japanese company prefers to participate in greenfield projects, it is expected that the Japanese
company joins to carry out the pre-FS and then continue to develop the project together. In addition, it
is realistic that the local developer takes care of land acquisition and acquisition of the
abovementioned permissions.
34
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
Proposal stage
The SPC submits the pre-FS, UPL/UKL, and other necessary documents to EBTKE (New/Renewable
Energy Department, Ministry of Energy and Mineral Resources), and HPO (Hydropower Operator
Approval) is issued to the SPC through technical verification by PLN, and then the SPC shall be
approved as the hydropower operator. For effective scheduling, depending on the reliability of the
pre-FS, the feasibility study (FS) shall be carried out in parallel with the activities in the development
stage. In case a Japanese company prefers to participate in brownfield projects, it is expected that the
Japanese company joins to carry out the FS and then continue to develop the project together.
PPA stage
After the HPO is issued, the SPC shall pay the deposit (equivalent to 5% of the total investment
amount) to EBTKE, and then the IUPTLS, which is a temporary power supply business license, is
issued to the SPC. In general, the FS is finished in this stage. In case that a Japanese company prefers
to participate in brownfield projects, the Japanese company as investor should decide up to this stage.
In the FS, the specifications and cost of equipment shall be almost fixed, therefore, project
participation as equipment supplier should also be promised up to this stage.
In the FS, the following issues should be carefully examined:
;
Financing stage
After the PPA is concluded, debt financing becomes possible. At this moment, corporate financing by
local banks seems to be common in Indonesia. In case of application of JICA-PSIF, it may take time to
examine the loan application. Therefore, earlier related actions including investment to the SPC by a
Japanese company are preferable in parallel with the activities in the PPA stage and immediately after
confirmation of almost all FS results. It is noted that the timing of acquisition of IUPLT is not critical
in the schedule.
Implementation stage
After the financing of the project is finished, the construction shall be started through bidding of
contractors. The financing may take time in general. Therefore, the detailed design and preparation of
bidding documents better to be carried out in terms of effective schedule. In case that the contractor is
a local Indonesian company, the selection of capable contractors and establishment of quality control
system is important. Moreover, it is necessary to examine schemes preventing troubles during
construction and delays such as the bidding conditions fixing the construction method and equipment.
35
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Final Report
In addition, the following actions are required from the Indonesian and Japanese sides:
Indonesian side
a) Confirm the situation of project preparation such as financing, engineering, procurement
management, and project management, and identify the needs for reinforcement. Request
appropriate assessment and consultation of experts.
b) For the above needs, examine the possibility of collaboration with the Japanese side in order to
solve problems. Request appropriate consultation from JICA and experts.
c) In parallel with the project stages, prepare the contract conclusion in collaboration with the
Japanese side. Include preparation of JICA-PSIF.
Japanese side
a) Review the FS report of the project.
b) Examine the needs of the Indonesian side, level, timing for projects and developers, and then
screen considering the company strategies and resources.
c) Contact and consult the developer on future collaboration.
d) In parallel with the project stages, prepare the contract conclusion of the collaboration with the
Indonesian side. Include preparation of JICA-PSIF.
36
Nippon Koei
KRI International
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
required information and data to be included in feasibility study report and how to preliminarily evaluate them are summarized below.
Item
1.0
Required Information/Data
Evaluation
INTRODUCTION
1.1
2.0
Background, Objectives,
Background, Objectives, Scope of Work are described Verify the description of the information/data.
Scope of Work
2.1
Geographic features
Administrative information etc. are described briefly and Verify the description of the information/data.
comprehensively.
2.2
Socio-economy
2.3
Power situation
3.0
SITE CONDITIONS
3.1
Site Conditions
General condition of the project site (topography, land Verify the description of the information/data.
use, existence of local people) is investigated and
described.
3.2
Site Access
The project location and access to the project including Verify the description of the information/data.
information of administrative area, close major city, land
route to the site with distance, road condition (width,
pavement condition) are described.
The
information
especially
for
transportation
of
Topography
Regional topography around the project area including Verify the description of the information/data.
any lineament to show fault and special topography of Regional topography may affect the overall project layout.
land slide is examined.
Topographic survey is carried out and make topographic Verify the description of the information/data.
map. Topographic map needs to be 1/1,000-1/2,000 scale The topographic survey with the required accuracy is
for general layout covering in and around the project indispensable for FS stage.
and 1/100 -1/500 scale for design of structures.
For the survey, bench marks need to be firmly established.
The survey records such as bench marks, triangle points,
base points, survey points including survey method and
used equipment need to be kept for clarification.
Information of geological investigation (location of core
boring, seismic exploration lines) is also included in the
topographic information.
3.4
Geology
Regional geology is investigated. Geological map of Verify the description of the required information/data.
1/250,000 scale is commonly available. General geology Regional topography may affect the overall project layout.
around the project is examined. Special geological
condition such as existence of large fault needs to be
carefully confirmed.
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
The related available data (geological map, record of In order to properly design the structures, geological
earthquake, activity of volcano) are collected.
Geological condition at each structure site is specified. Intake site requires sound rock foundation and water
Sound rock surface at each structure site is investigated tightness. Depth of river bed deposit is also investigated.
Depth of overburden (soil, weathered rock) along
and estimated.
Meteorology and
Hydrology
River catchment area, length of main stream and each Verify the description of the information/data.
tributaries, average slope, and average basin elevation
based on topographic map with 1/25,000 or 1/50,000
scale.
These data are used as parameters of low flow and flood
flow analysis.
Monthly meteorological data in and around the river Verify the description of the information/data.
The data are used for hydrological analysis. All collected
basin.
The meteorological data is 1) monthly mean temperature, data shall be attached to the FS report.
2) monthly maximum temperature, 3) monthly minimum
temperature, 4) monthly mean humidity, 5) monthly mean
wind speed/direction, 6) monthly mean sunshine hour, and
7) monthly mean evaporation.
The data are classified into 3 items by every year and
figured; 1) Complete data, 2) Incomplete data (including
missing data), and 3) Data not available.
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Daily rainfall data in and around the river basin for low The estimated annual rainfall will be more accurate when
several rainfall stations exist around the project site. But,
Hourly rainfall data for design flood hyetograph of flood the estimation shall be inaccurate when there is few or no
rainfall station around the project site.
Daily river water level data, daily discharge data, and H-Q The required discharge data in the project river basin and
(river water level - discharge) curve to convert river water vicinity of the river basin are compiled. If data is not
level into discharge in and around the project river basin.
Data of river flow measurement at water level gauging Verify the description of the information/data.
station site. Frequency of the measurement is 2 times in a The required data shall be used for hydrological analysis.
month at the minimum. The H-Q curve needs be properly
updated by result of the measurement.
For low flow analysis, F.J. Mock method and Nreca Evaluation of design discharge:
method are popular in Indonesia. These methods are half 1) The design discharge shall be evaluated considering
monthly or monthly basis, therefore these are applicable
stage.
design discharge.
catchment area ratios between the water level gauging 2) The design discharge less than 1.5 times of the
station sites and the project intake site.
range.
Probable flood discharge for design of spillway and Evaluation of flood discharge:
powerhouse shall be estimated. The probable rainfall is Adequacy of the estimated design flood discharge shall be
generally estimated using Gumbel or Log Pearson III evaluated by Creagers Curve. Range of Creagers
methods. Those methods are common in Indonesia.
For flood flow analysis, Nakayasu unit hydrograph Probability of flood discharge for intake weir and
method is common in Indonesia.
3.5.8 Sedimentation
Sampling survey for suspended load and riverbed material Based on the survey result, sand flush gate at intake and
survey is desirable for examining abrasion prevention sand trap basin shall be suitably designed.
countermeasure of turbine and generator. The sand trap
basin is designed considering the survey result.
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
4.0
4.1
Layout
Run-of-river type
is generally
applied
hydropower project.
optimized using discharge data from result of low flow This value is expected to be less than 10 for project
analysis. In order to optimize the layout, alternative study feasibility.
for several layouts is carried out. Penstock costs Intake location at start of rapid flow of river is preferable.
prominently and therefore shorter penstock for the head is It is also noted that the layout should be avoid high and
theoretically economical.
huge excavation.
Plant Discharge
Based on the result of low flow analysis, daily (monthly) In general, maximum plant discharge is set so that the
discharge is calculated and the FDC is established.
Based on the FDC, alternative study for several maximum approximately 70% even though the maximum plant
plant discharge is carried out in order to optimize project discharge shall be set based on the result of alternative
study.
scale.
4.3
Based on the layout and maximum plant discharge, In order to correctly estimate energy production,
Energy Production
installed capacity and annual energy production is maximum plant discharge, head losses, efficiencies of
calculated. Head loss in the waterway and efficiencies of turbine and generator shall be properly set and seasonal
turbine and generator shall be considered.
5.0
BASIC DESIGN
5.1
Civil Works
a. Layout
a. Layout
b. Foundation
c. Dam shape
b. Foundation
d. Dam material
rubble masonry
covered
by
concrete
is
acceptable.
2) Spillway
2) Spillway
The following issues shall be appropriately examined.
a. Design flood
a. Design flood
b. Type
c. Width
d. Stilling basin
b. Type
Non-gated ogee crest type is common for small
hydropower.
c. Width
Width shall be nearly same with river width.
d. Stilling basin
Stilling
basin
shall
be
designed
to
adjust
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
a. Bottom elevation
a. Bottom elevation
b. Dimension
4) River Diversion
River diversion during construction shall be planned
a. Method
construction period.
shall be confirmed.
a. Method
If
b. Return period
stage
river
diversion
cause
huge
volume
considered.
Layout of the river diversion does not disturb the
layout the permanent structure. Closing measure of
the river diversion so considered.
b. Return period
Return period of design flood shall be 5-10 years
depending on the construction schedule.
5.1.2 Power Intake and Sand
Trap
1) Power Intake
1) Power Intake
The following issues shall be appropriately examined.
a. Layout
a. Layout
b. Dimension
c. Elevation
b. Dimension
Power intake shall have appropriate dimension.
c. Elevation
Bottom of power intake shall be set 1m or more
higher than the sand flush way.
Approach velocity shall be at around 1.0m/s.
2) Sand Trap
2) Sand Trap
Necessity of sand trap shall be examined and number
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Type
Route
Section
As for typical section, if geological condition is good, In terms of the project layout, length of headrace
trapezoidal section leaning on the both excavation face channel/head is checked and the value less than 10 is
with wet rubble masonry is adoptable. If geology if not so preferable.
Section
Crossing
The headrace crossing the deep river/valley shall provide flume type. Independent wet rubble masonry wall is not
the waterway bridge or siphon. Appropriate cross drain appropriate.
structure shall be provided at the crossing of small
rive/valley.
Along the headrace channel, access road shall be bottom. Flow velocity is around 1.0-1.5m/s.
constructed for construction and maintenance purposes.
Possible landslide along the waterway route shall be and not disturb flowing of the flood water.
checked.
Location
Location
Head pond is located at the end of the headrace channel Location of head pond is selected to suit to topography
and the beginning of the penstock.
Function
Capacity
Head pond functions to supply water when power Volume of head pond shall have about 3 minutes of the
generation operation is started and waste surplus water Plant discharge in general.
when power generation is downed or stopped. In addition, Structure
Head Pond has sand trap function.
Spillway
Spillway
Spillway of Head Pond shall have capacity equal to Plant Spillway and chute way of Head pond have enough
Discharge and chute way to the river shall protected capacity and are correctly designed.
appropriate structure.
Route
Length
Diameter of penstock shall be selected economical penstock length is more than 500m shall be carefully
diameter. Thickness is also designed correctly.
Anchor block
examined
In terms of the project layout, length of penstock/head
The anchor block shall be prepared at bending portion and is checked and the value less than 3 is preferable.
at around 50-100 m interval. The anchor block shall be
constructed on the sound rock. If not, the pile foundation Flow velocity of economical diameter is usually at around
shall be considered.
2-3m/s.
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Layout
Layout of powerhouse is correctly arranged in relation elevation of erection bay and yard around powerhouse
with Penstock and Tailrace/River course. The Access shall be set higher than 100 years flood.
Road to transport the equipment is correctly designed.
Type
constructed
on
the
sound
rock.
Layout
of radius curvature.
Main transformer yard/Switchyard shall be set at around These yards shall be designed easy for construction and
the powerhouse and same or higher elevation of maintenance.
powerhouse yard.
5.2
Hydro-mechanical Works
Necessity and function of screen, gate and hoist at each Detail design will be made by the Contractor, design
condition of each gate and hoist shall be prepared clearly.
General layout study and design of civil works decide the Detail design will be made by the Contractor. The design
condition shall be prepared clearly.
penstock layout.
Diameter and thickness of penstock shall be designed
based on the plant discharge and internal water pressure
including of water hammer or minimum thickness for
transportation. For allowable stress of steel, the available
material in the country shall be considered.
5.3
Electro-mechanical Works
Based on the decided effective head and plant discharge, Selection of type of turbine is correctly done subject to
reference. Francis type turbine with horizontal axis is
Following the selected turbine, the type of generator shall Selection of type of generator shall be correctly done.
Flywheel effect (GD2), maximum speed rose and
be selected.
Transmission Line
Transmission and distribution line system around the Verify the description of the information/data.
Transmission and
Distribution Line
Based on the above study, the connection point to PLN Connection point to PLN grid, size and length of
grid is decided. Length of transmission and distribution conductor shall be cleared.
line shall be minimized. Required capacity of conductor is Evaluation of transmission line:
studied for new or the existing transmission and The case that length of transmission line more than 20km
distribution line.
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
6.0
6.1
IEE
b. Land acquisition/use
government.
Social Environment
Social environmental impact such as land acquisition and Verify the description of the information/data.
resettlement, if any, is studied carefully.
6.3
Natural Environment
Natural environmental impact such as special fauna and Verify the description of the information/data.
flora, if any, is studied carefully.
7.0
7.1
Construction Materials
Type
Materials of sand and gravel for concrete aggregate and Source of construction materials and volume shall be
mentioned clearly.
masonry is important
Quantity
Location
Construction Method
Method
Construction method of each structure shall be studied period of main structures shall be studied and mentioned
clearly.
and mentioned.
Equipment
Period
Construction Schedule
Construction schedule from mobilization to COD Construction period of small hydropower project is
expected to be around 24 months.
of
the
contract
lots
such
as
civil,
CONSTRUCTION COST
8.1
Cost Estimate
Construction cost of civil works is estimated generally The related cost shall be appropriately estimated.
referring to the market price and/or contract unit price of
similar and/or neighboring projects. The work quantities
for cost estimate refer to the basic design.
Construction cost of hydro-mechanical works is estimated The related cost shall be appropriately estimated.
Penstock)
Construction
cost
of
electro-mechanical
works
Works (Generating
Equipment)
JICA Survey for Enhancement of Private Sector Investment on Small Hydro IPP Projects in Indonesia
Cost of in-direct cost including engineering, land Verify the description of the information/data.
acquisition,
administration,
general
expenses
and
Total project cost includes the above direct costs, in-direct Evaluation of cost:
cost and tax.
9.0
FINANCIAL EVALUATION
Conditions for Financial
1)
Analysis
Inflation rate for CAPEX (Capital Expenditure) and Verify the description of the information/data.
OPEX (Operational Expenditure) and
2)
3)
4)
5)
OPEX
6)
7)
8)
Financial Analysis
Financial Evaluation
10.0
CONCLUSION
1)
2)
3)
Balance sheet
1)
2)
Project IRR
3)
4)
Financial sensitivity
Both of technical and financial feasibility of the project Verify the description of the information/data.
shall be concluded.
Attachment -1
Design Drawings
Attachment -2
Investigation Data
- Topography
- Geology
- Hydrology
Attachment -3
Remarks)
For details of the colored evaluation, see the survey report.