IPBs Installation
Rev. 00
29 July 2011
Contents
1.
Purpose.................................................................................................................................... 2
2.
Scope ....................................................................................................................................... 2
3.
Definitions............................................................................................................................... 2
4.
References ............................................................................................................................... 2
5.
Responsibilities ....................................................................................................................... 2
6.
5.1.
5.2.
5.3.
5.4.
IMPLEMENTATION ............................................................................................................. 3
6.1.
General ............................................................................................................................. 3
6.2.
6.3.
Transport .......................................................................................................................... 3
6.4.
Installation ........................................................................................................................ 4
HSE ......................................................................................................................................... 5
7.1.
7.2.
Machinery......................................................................................................................... 5
7.3.
7.4.
7.5.
Manual handling............................................................................................................... 6
7.6.
7.7.
Restriction ........................................................................................................................ 6
7.8.
Page 1 of 7
METHOD STATEMENT
IPBs Installation
Rev. 00
29 July 2011
1. Purpose
Purpose of this method statement is to define the sequence of bus ducts installation and safe execution of
the job.
2. Scope
The procedure applies for bus ducts transportation, handling, and installation at all workplaces where
these activities will be performed.
3. Definitions
4. References
Project HSE Manual
Drawings and design details
5. Responsibilities
5.1. Site Manager:
5.1.1.
5.1.2.
5.1.3.
5.1.4.
5.1.5.
5.1.6.
Page 2 of 7
METHOD STATEMENT
IPBs Installation
5.2.9.
5.2.10.
5.2.11.
5.2.12.
5.2.13.
5.2.14.
Rev. 00
29 July 2011
To ensure that the staff involved in the activities has read and understand the
method statement.
To brief the staff involved about the healthy and safe performance of all
activities (toolbox talks).
To receive and/or define all standards including this Method Statement,
To obtain all the necessary standards,
To ensure maintenance compliance with this method statement.
To coordinate with the PPR.
6. IMPLEMENTATION
6.1. General
Busducts are used for carrying energy.
Galvanized spray
6.3. Transport
Transportation of bus ducts is made proper places to work in site. Crane will be used and all
necessary precaution matures will be taken. Provide crane and truck to transportation of busducts
KKS No. 440-00-YF-SNO-KSR-003
Page 3 of 7
METHOD STATEMENT
IPBs Installation
Rev. 00
29 July 2011
and accessories from lay down area to the field. Use crane for lifting and carrying bus ducts.
When crane will be used according to 7.3. lifting operation. It will be stayed suitable places, so it
prevents to work and workers work safely.
6.5. Installation
Check last revision of approved project then start installation. Controlling the montage
equipments of bus duct with the supervisor and performed an examination on the project then
gives the tasks to the team. Scaffold will be set by trained people. It will be color-coded.
Installation will be carried out in accordance with the last approved revision of the installation
projects. Request form for materials will be prepared. Site will be controlled by busduct
supervisor then according to supervisor, it will be transported. Bus ducts will be transported from
lay down area to site with crane and pickup. While it will be carried, it will be fixed safely in the
truck board. The assembly drawings will be checked on the place of installation. At the working
area, the bus ducts will be placed in a way that will not prevent safe access and egress. Checking
will be done for the accessories of bus ducts and preparation of bus ducts accessories for
montage, after boxes will be opened. Erection of bus ducts will be started by crane. Signaler will
help operator when it will be lifted. All personnel, who work high places, will have PPE.
Installation of bus ducts will be executed according to the requirements. According to supervisor,
it will be erected. Erection will be tracked from transformers to circuit breaker then from circuit
breaker to turbine. Precondition Generator including the terminals to IPB has been installed.
Installation will follow the erection drawing. The silicone bushings at phase side must be
installed during alignment of shipping units. Preconditions the unit auxiliary transformer must be
installed before erection of the connecting shipping units. Installation will follow the erection
drawing. Bus ducts comply with the projects requirements. Where cutting of bus ducts is needed,
it will be sprayed with spray immediately. When all erection and testing will be done, scaffold
will be dismantled by competent personnel. PPE will be used all level of action. When all of
Page 4 of 7
METHOD STATEMENT
IPBs Installation
Rev. 00
29 July 2011
works will be done, it will be controlled all equipment. After the works is done daily, working
areas will be cleaned.
7. HSE
7.1. Personal protective equipment
PPE will be provided and used in accordance with requirements. Helmet, safety glasses, high
visibility vest, and safety shoes will be used at all the times.
When work in dusty environment personnel will use dust protective half masks.
Hearing protection will be used where exposure levels exceed 85 dB.
When work at height fall arrest system will be used if other protective measures are not feasible.
When work with welding, welders will use welders clothes, gloves, protective face masks.
7.2. Machinery
All machinery, equipment and tools will be maintained in good working order; will be inspected
regularly; and will be operated by competent persons. All necessary measures will be in place in
order to prevent environmental pollution. In case of oil spill an immediate actions will be taken
to localize and clean the area in accordance with the procedure. Guards will be in place to protect
workers from moving parts. Electrical tools will be double insulated and grounded connected to
ground fault circuit interrupters (GFCI).
All vehicles will have backing warning device. Banks man will guide vehicles in narrow work
places and when reversing. Vehicles will not pass, will not be positioned or parked close to
excavation edges.
Page 5 of 7
METHOD STATEMENT
Rev. 00
29 July 2011
IPBs Installation
7.7. Restriction
No food or beverages to be consumed at jobsite
No smoking
No work without permit
Page 6 of 7
METHOD STATEMENT
IPBs Installation
Rev. 00
29 July 2011
List of attachments:
1. List of the staff involved in the job
2. Toolbox attendance sheet
3. Risk Assessment
4. Lifting Plan
Page 7 of 7