CC02 Change Engineering Change Request


Definition:Engineering Change Request will contain the object to be changed. E.g.
BOM or routing to be changed using this Engineering Change Request
Engineering change request will be normally created by the design
department.
Objective
This document will explain how to change Engineering Change
Request after performing the task in the object. I.e. after performing
create or change BOM.
Prerequisites:ECR number must be available.
Task must be completed on the object.
Required authorization
Menu path
Logistic Central FunctionsEngineering --> Engineering Change
Management Change Number CC02 - Change
Double click Change

Note:Press F4 to search the change number

In this example change number is being searched based on the valid


from date

Press

List of ECR numbers will appear satisfying the search condition &
select the appropriate one & press ENTER.

Press

Select the item


Press

- Detail view

Press the Status icon

to set the status to the object.

Note: - If there is more than one object for each object this procedure
has to be done.

Press

in Complete change

Note:- At this stage, using this ECR, changes must have been done to
the object, i.e in this case to the material BOM TEST-FGPI-01.
Otherwise warning message appear as below

Pleas go to CS01 or CS02 do create or change BOM with this change


number and come back again. If you do not then after releasing the
change you can no more use this ECR number.

Press
Press

Press

in Release change

Press

to set the status.

Press

in Close ECO

Press

in Release ECO

Press

Click
Now this ECR is completely released and no changes can be done.
Press
Message

Save icon to save.


appear at the bottom

Case no.1
No more changes can be processed with that ECR number. If you
attempt to use that number to change any other object, which is not in

that Engineering Change Request, it will give the error message.


Example Below is the screen shot shows the error message when
attempt to change the BOM of one material, which is not in that ECM.

Case no.2
Even if the material is mentioned as the object in the ECR, once it is
released it cant be processed twice with the same number after
release.

SAP PP/QM
User manual
Published by Team of
SAP Consultants
at
SAPTOPJOBS
Visit us at www.sap-topjobs.com

Copyright 2008-10@SAPTOPJOBS

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in
any form, or by any means electronic or mechanical including photocopying, recording or any information storage
and retrieval system without permission in writing from SAPTOPJOBS

Potrebbero piacerti anche