Sei sulla pagina 1di 11

CEC - UG1B

CONTRACT: ICB No. :-JP/EW/1B/C1


METHOD STATEMENT FOR
EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

PROJECT: Design and Construction of Tunnel between


Chandpole and Badi Chouper and reversal line by
Shield TBM, Underground Metro Stations at Choti
Chouper & Badi Chouper by Cut & Cover Method on
East-West Corridor of Jaipur Metro (Phase 1B) at Jaipur,
Rajasthan, India.

LOCATION: JAIPUR

TITLE: Method Statement for Excavation


Work of Roof Slab at Choti Chaupar - R0
22th July 2015

Page 1

CONTRACT: ICB No. :-JP/EW/1B/C1

CEC - UG1B

METHOD STATEMENT FOR


EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

DGM-Planning
Department,

CEC

DPMConstruction
Department,

CEC

Senior
Manager
QA/QC
Department,

Chief Manager
HSE
Department,

CEC

Project Leader

CEC

CEC

SUMMARY
Scope of work

: Design and Construction of Tunnel between


Chandpole and Badi Chouper and reversal line by
Shield TBM, Underground Metro Stations at Choti
Chouper & Badi Chouper by Cut & Cover Method on
East-West Corridor of Jaipur Metro (Phase 1B) at
Jaipur, Rajasthan, India.

Employer

: Jaipur Metro Rail Corporation (JMRC)

Engineer

: Delhi Metro Rail Corporation (DMRC)

Contractor

: Continental Engineering Corporation

Contract Length

: 36 months

Bored Tunnel

: 1390.940M

Choti Choupar Station

: 232.60M

Badi Choupar Station

: 232.60M

Cut & Cover (Badi C.- : 268.631M


West)
Page 2

CONTRACT: ICB No. :-JP/EW/1B/C1

CEC - UG1B

METHOD STATEMENT FOR


EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

Cut & Cover (Badi C.- : 114.918M


East)
TBM Shaft 1 (CH: : 20.00M (app) Launching Shaft
8377.88)

Table of Contents
Sr. No.

Description

Page No.

1.0

Purpose

2.0

Scope of Work

3.0

Reference Documents

4.0

Definitions

5.0

Responsibilities

6.0

Construction Equipment

7.0

Methodology

8.0

Quality Assurance

9.0

Health, Safety and Environment

List of Enclosures

10.0

Page 3

CEC - UG1B

CONTRACT: ICB No. :-JP/EW/1B/C1


METHOD STATEMENT FOR
EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

1. PURPOSE
This method statement describes the procedure for excavation work for Roof Slab
Excavation at Choti Chaupar . This method will also be applied for other
construction sites. Any change in case of various site conditions, specified drawing
or method statement will be submitted as per actual site.
2. SCOPE OF WORK

The scope of work involves the excavation of soil from Roof Slab and the disposal of
soil to the designated dumping yard with necessary preparation and systems as per
contract documents.
MAIN CONTRACTORS OBLIGATIONS

Page 4

CONTRACT: ICB No. :-JP/EW/1B/C1

CEC - UG1B

METHOD STATEMENT FOR


EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

Prior to the commencement of excavation, CEC will undertake to carry the following:
a. Obtain the consent of the DMRC to commence work.
b. Install all necessary ground monitoring instrumentation and commence initial
readings.
c. Install soft panel at specified location as per design.
d. Complete truck wash bay facility (if required) and associated temporary drainage
system.
e. Provide general site provisions like barricading/illumination /ingresses & egresses
and other
basic requirement.
3. REFERENCE DOCUMENTS
a. Technical Specification of IS Codes- IS 5878 for excavation.
b. Ref Drawing No. 172/14.03.2015.
c. Method Statement of Instrumentation Scheme.

4. DEFINITIONS
o

JMRC

DMRC

Delhi Metro Rail Corporation. (Engineer)

CEC

Continental Engineering Corporation. (Contractor)

OK-ICPL

GOR

PHED

:
:

Jaipur Metro Rail Corporation.(Employer)

Omikron Kappa Indus Consultants Private Limited.


Government of Rajasthan.

Public Health Engineering Department. (GOR)

Page 5

CEC - UG1B

CONTRACT: ICB No. :-JP/EW/1B/C1


METHOD STATEMENT FOR
EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

QA/QC

GFC

Quality Assurance and Quality Control


:

Good For Construction

5. RESPONSIBILITES

The responsible persons and their responsibilities are listed below.

A) Project Leader:
He shall be overall responsible for following:
Safety Rules
Statutory Compliances
Quality Manuals
Overall responsible for the whole operation.
B) Station Manager:
He shall be overall responsible for the whole procurement of men, material and
machinery at site, including operation planning and adhered with works programme.
C) Site-In-charge:
Overall Responsible for the whole site operation.
D)

Site Engineer:
Responsible for site operation.
Material and equipment planning.
Ensure that works are carried out in accordance with the method statement.
Ensure that works follow approved drawings and specifications.
Ensure that works are carried out in a safe manner.
Field control and supervise all site activities.
Apply and issue relevant work permits.

E) Design Engineer:

Page 6

CEC - UG1B

CONTRACT: ICB No. :-JP/EW/1B/C1


METHOD STATEMENT FOR
EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

He shall be responsible to issue controlled copies of all drawings to the site personnel
and return back all obsolete copies. He shall provide detailed design specifications to
carry out the work.

F) Planning Engineer / Cost Control :


He shall be responsible for Budget Control, Contractor evaluations and raising of bill of
quantities.
G) Safety Personnel:
Ensure that works are carried out in a safe manner and in accordance with the safety
requirements stipulated in the SHE plan.
Conduct tool box talks on the safety requirements, construction risks and its control
measures etc.
H)

Surveyor
Carry out setting up works and locate as per submission drawings.
Carry out inspection for location and level of structure.
Keep monitoring the movement of ground and structure.

I) QC Engineer:
Ensure works are carried out in accordance with specification.
Prepration Of Method Statements and its Application.
6. CONSTRUCTION EQUIPMENT
(Responsibility: Plant Manager, Sub-contractor (if applicable) & Section Manager)
The following equipment will be provided at worksite where excavation and strutting
work coincides.
1.

Long Boom Excavator EX-200

01 no.

2.

Short Boom Excavator EX-200

01 no.

Page 7

CEC - UG1B

CONTRACT: ICB No. :-JP/EW/1B/C1


METHOD STATEMENT FOR
EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

3.

Dumper capacity

12 nos.

4.

Excavator EX-70

5.

Loader 2021

01 no.

6.

Doser BD 65

01 no.

7.

Ventilation Fan

02 no.

8.

40 Tonn Crane

01 no.

9.

Concrete Pump

02 no.

02 nos.

The above mentioned heavy machineries/equipments would be deployed when


excavation work will be in full swing and the quantities will be subject to change to
suit the site requirement and meet the excavation programme. Apart from the
above equipments and plant, submersible water pump, water jet pump, spot light
etc. shall be provided as per the site requirement.

7. METHODOLOGY
a) Preceding Activities
The following activities to be completed prior to commencement of excavation:
Barricading with barricading board all around the construction site.
Site temporary drainage.
Access and egress for men and machinery.
Temporary bench mark to be fixed and pre level to be jointly recorded.

Installation of all necessary ground monitoring instrumentation around


excavation area.
b) Installation of submersible pumps for the purpose of dewatering whenever
required.

Page 8

CEC - UG1B

CONTRACT: ICB No. :-JP/EW/1B/C1


METHOD STATEMENT FOR
EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

JAIPUR METRO RAIL


CORPORATIONLIMITED

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

c) All excavation works shall be done as per approved drawings enclosed.


d) The excavated material shall be transported through dumpers and dumped at the
designated dumping
area.
Stage 1:
Excavation upto the bottom of Top Slab and Prepration of Ramp as per Drawing
172 Sec. A-A using suitable equipments and transportation of soil to the designated
dumping yard, spreading and compaction.
Stage 2:
While Ramp Excavation the Soil adjoining to the D Wall of Approximate 2.5 meter
of slope shall be Well maintained all along the D Wall as per sec. B-B of Drawing no
172 parallel the trench of 4 m wide and 1 mtr deep shall be excavated as per
Drawing 172 Sec. C-C.
Stage 3:
Excavator EX-70 shall be placed in the trench with clearance height of 4.1 mtr and
cutting of excavated soil from both the left and right side equally removing PCC
from Top Slab area as well Maintaing the slope of 2-2.5 mtr wide all along the D
Wall as mentioned in Stage 2. And hauling of excavated soil shall be done with
Loader 2021 and excavated soil shall be Shifted to the Ramp Area.
Long Boom Excavator EX 200 shall be placed on the Ramp area for lifting of
excavated soil from Ramp to the Top Slab Area.
Short Boom Excavator EX 200 shall be used for loading of excavated soil from Top
Slab Area to Dumpers for transportation of soil to Dumping Yard.
Stage 4:
After Final Excavation and removal of excavated soil from Roof Slab area by EX 70
Excavator.The
Excavator shall Excavate the soil of slope area which was maintained
along the D Wall as mentioned in stage 2.
The Excavated soil shall be placed in the Trench Area And Well Compacted By Chain Of EX
70 from Chand Pole Area back To Badi Chaupar Ramp Area.
Stage 5:

Page 9

CONTRACT: ICB No. :-JP/EW/1B/C1

CEC - UG1B

JAIPUR METRO RAIL


CORPORATIONLIMITED

METHOD STATEMENT FOR


EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

After Clearing of all Excavated Earth A Plate Compactor shall be used for
Compaction of the Soil.
PCC (M15 Grade) shall be placed by Pump on The Compacted Soil. Fixing of 3
mm Thick Plywood shall be laid on PCC for Laying Of Reinforcement for Roof Slab
Concrete.

8. QUALITY ASSURANCE
CEC will verify that the excavation is executed to the dimension, lines, levels and
sequences above.
CEC will carry out the following:

Observation of the procedure laid out in the Project Quality Plan.

9. SAFETY, HEALTH & ENVIRONMENT


Relevant works on site shall be executed in accordance with the Risk Assessment
plan attached.
Environmental Consideration
Safety, Health and Environment (SHE) plan shall be followed throughout the
construction program.
Emergency Procedures
Emergency evacuation plan shall be prepared on site basis and it shall be duly
approved by the respective section in-charges. The emergency evacuation plan
shall be displayed at the site office. In addition to that, emergency contact list shall

Page 10

CONTRACT: ICB No. :-JP/EW/1B/C1

CEC - UG1B

JAIPUR METRO RAIL


CORPORATIONLIMITED

METHOD STATEMENT FOR


EXCAVATION OF ROOF SLAB AT CHOTI CHAUPAR

CONTRACT UG1B

DOC NO: PR/DMRC/MS/UG1B/PHOF/005-R0


Date: 22 July 2015

be displayed at the site office. Ambulance and other emergency services shall be
made available as per details submitted in the SHE plan.
Evacuation Procedure
In event of an evacuation being required, e.g. flood, fire, power failure, gas or failure
of ventilation, the following procedures will be followed.
1. In event, the site engineer and site supervisor to quickly and safely manage
the evacuation of all personnel within the excavation. This will include all
workers, CEC staff and any visitors.
2. The site supervisor immediately informs the site engineer that an incident
has occurred and gives details. The site engineer will then inform the
management.
3. All personnel will gather at the designated assembly point. A plan indicating
this location will be displayed at the top and bottom of the excavation access
and at the gate of assembly point designated at the station.
4. No one is to enter the excavation area until the emergency is over and
without the approval of the project manager.
10.

LIST OF ENCLOSURES

SL.
NO.
1
2
3

Description
of
Attachment
Drawing No. 172 (Plan)
and Drawing No. 172
(Section)
Risk Assessment
Instrument Monitoring

Page 11

Attachmen
t No.
2
3
4

Potrebbero piacerti anche