Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
BRIDGE
Price List
No
Item
Unit
Labor
Materials
Equipment
Misellaneous
Rate (Rs)
Insitu Concrete
F.01
Provision of concrete, designed concrete to relevant British Standards with Sulphate resisting cement to
size 14mm
Assumed Quantity for Rate build up
6
Cu.m
Work Item :
Item Nr
Labour Component
Units
Qty
Day
Day
1.00
2.00
Item Nr
Plant/Equipment Component
Units
Qty
Day
Day
1.00
0.25
Item Nr
Material Component
Units
Qty
Cement
Sand
Bag
m3
27.72
4.10
Aggregate
m3
4.26
Water
Wastage (5%) material cost
1.13
Item Nr
Units
Qty
Rate covers : Material cost, Transport cost upto the site and mixing cost (plant and labor related exp
Assumptions made
1. Allowed 5% of material cost as wastage
2. Allowed 1.1% of labor cost for additional tools used
3. Allowed mark up of 20% for the build up basic rate
4. Asumed that materials are trasport to the site by using tractor with trailer (3T) and mixed at the s
litres).
5. Assumed that machinary chargers are hire chargers with wet lease basis inlcuing operator
6. Water is available within 25m from the site
Insitu Concrete
F.02
Provision of concrete, designed concrete to relevant British Standards with Sulphate resisting cement to
size 20mm
Assumed Quantity for Rate build up
4
Cu.m
Work Item :
Item Nr
Labour Component
Units
Qty
Day
Day
1.00
2.00
Item Nr
Plant/Equipment Component
Units
Qty
Day
Day
1.00
0.25
Item Nr
Material Component
Units
Qty
Cement
Sand
Bag
m3
42
2.52
Aggregate, 19mm
m3
4.20
Water
Wastage (5%) material cost
0.68
Item Nr
Units
Qty
Rate covers : Material cost, Transport cost upto the site and mixing cost (plant and labor related exp
Assumptions made
1. Allowed 5% of material cost as wastage
2. Allowed 1.1% of labor cost for additional tools used
3. Allowed mark up of 20% for the build up basic rate
4. Asumed that materials are trasport to the site by using tractor with trailer (3T) and mixed at the s
litres).
5. Assumed that machinary chargers are hire chargers with wet lease basis inlcuing operator
6. Water is available within 25m from the site
Insitu Concrete
F.03
Provision of concrete designated concrete to relavant British Standards with Sulphate resisting cement
aggregate size of 20mm.
Assumed Quantity for Rate build up
9
Cu.m
Work Item :
Item Nr
Labour Component
Units
Qty
Day
Day
2.00
4.00
Item Nr
Plant/Equipment Component
Pump car
Units
Qty
m3
9.00
Item Nr
Material Component
Units
Qty
m3
Item Nr
Units
Qty
Rate covers : Material cost, Transport cost upto the site and related labor expences
Assumptions made
1. Allowed 5% of material cost as wastage
2. Allowed mark up of 20% for the build up basic rate
3. Asumed that ready mix concrete is to be transport to the site by using the pumpcar from the batch
himself which is located within 15kn from the site
4. Slump of the ready mix concrete is to be 120mm at the site
Item Nr
Labour Component
Units
Qty
Day
Day
Day
1.00
2.00
2.00
Item Nr
Plant/Equipment Component
Mobile crane(30T)
Units
Qty
Hr
0.75
Item Nr
Material Component
Water
Units
Qty
litre
1800
Item Nr
Units
Qty
SAY RATE
NOTE:
Rate covers : Hoisting cost upto the relevant place, placing, compacting and curing
Assumptions made
1. Allowed 2.0% of labor cost for additional tools used
2. Allowed mark up of 20% for the build up basic rate
3. Assumed that mobile crane (30T) is used to place the concrete whose chargers are to be hire charg
operator
4. The rate include the cost of trasport upto 25m from the ground level
Item Nr
Cu.m
Labour Component
Units
Qty
Day
Day
Day
Day
2.00
1.00
3.00
3.00
Item Nr
Plant/Equipment Component
Poker Vibrator
Mobile crane(30T)
Units
Qty
Day
Hr
1.50
1.00
Item Nr
Material Component
Water
Units
Qty
litre
2100
Item Nr
Units
Qty
Rate covers : Hoisting cost upto the relevant place, placing, compacting and curing
Assumptions made
1. Allowed 2.0% of labor cost for additional tools used
2. Allowed mark up of 20% for the build up basic rate
3. Assumed that poker vibrator is used whose chargers are to be hire chargers on wet lease basis exc
4. Assumed that mobile crane (30T) is used to place the concrete whose chargers are to be hire charg
operator
5. The rate include the cost of trasport upto 25m from the ground level
Mark - up
20%
Rate
Amount
1,173.88
957.17
1,173.88
1,914.34
-
3,088.22
Rate
Amount
7,300.72
6,308.40
7,300.72
1,577.10
8,877.82
Rate
Amount
834.00
3,571.30
14,642.33
1,495.29
6,369.94
26.90
30.50
23,118.48
2,208.06
46,369.31
Rate
Amount
33.97
33.97
58,369.32
11,673.86
70,043.19
11,673.86
11,674.00
h trailer (3T) and mixed at the site by using concrete mixture (400
basis inlcuing operator
Mark - up
20%
Rate
Amount
1,173.88
957.17
1,173.88
1,914.34
-
3,088.22
Rate
Amount
7,300.72
6,308.40
7,300.72
1,577.10
8,877.82
Rate
Amount
834.00
3,571.30
35,028.00
1,553.94
6,526.55
26.90
18.29
8,999.68
2,528.63
53,101.14
Rate
Amount
33.97
33.97
65,101.15
13,020.23
78,121.38
19,530.35
19,531.00
h trailer (3T) and mixed at the site by using concrete mixture (400
basis inlcuing operator
Mark - up
20%
Rate
Amount
1,173.88
957.17
2,347.76
3,828.68
-
6,176.44
Rate
Amount
850.00
7,650.00
7,650.00
Rate
Amount
14,217.80
127,960.20
6,398.01
134,358.21
Rate
Amount
148,184.65
29,636.93
177,821.58
19,757.95
19,758.00
abor expences
Mark - up
20%
Rate
Amount
1,173.88
957.17
957.17
1,173.88
1,914.34
1,914.34
-
5,002.56
Rate
Amount
9,936.22
7,452.17
7,452.17
Rate
Amount
1.15
2,070.00
103.50
2,173.50
Rate
Amount
100.05
100.05
14,728.28
2,945.66
17,673.93
2,945.66
ng and curing
2,946.00
Mark - up
20%
Rate
Amount
1,173.88
1,076.86
957.17
957.17
2,347.76
1,076.86
2,871.51
2,871.51
-
9,167.64
Rate
Amount
2,070.80
9,936.22
3,106.20
9,936.22
13,042.42
Rate
Amount
1.15
2,415.00
120.75
2,535.75
Rate
Amount
183.35
183.35
24,929.16
4,985.83
29,915.00
ng and curing
4,985.83
4,986.00
BILL NO 6:
Concrete Ancillaries
G.05/G.06/G.07/G.09
Item No:
Work Item :
Formwork rough finish for sides of abutment, cappimg beam and ballast wall including dismantling
Assumed Quantity for Rate build up
5.57
Sq.m
(Including 10%
Item Nr
Labour Component
Units
Qty
Carpenter (SK'A')
Unskilled Labour (U/SK)
Day
Day
1.00
1.00
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
m2
Cu.Deci m
Kg
Litre
m
0.49
39.62
0.23
0.90
25.00
Item Nr
Units
Qty
Total For ( E + F )
Rate per Unit ( E+F)/Q
SAY RATE
NOTE:
Rate covers : Cost of material, making mould, assembling, cleaning, repairing and dismantling
Assumptions made
1. Allowed 10% wastage and assumed to be used for 5 times
2. Allowed 5% of labor cost for additional tools used and scaffolding
3. Allowed mark up of 20% for the build up basic rate
4. All the material rates included with transport cost.
BILL NO 6:
Concrete Ancillaries
G.02/G.08
Item No:
Work Item :
Formwork rough finish for concrete components of constant cross sections, intrusions including disman
Assumed Quantity for Rate build up
7.32
m
Item Nr
Labour Component
Units
Qty
Carpenter (SK'A')
Unskilled Labour (U/SK)
Day
Day
1.25
2.50
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
m
Kg
Litre
13.25
3.46
2.45
Item Nr
Units
Qty
Rate covers : Cost of material, making mould, assembling, cleaning, repairing and dismantling
Assumptions made
1. Allowed 5% wastage
2. Allowed 2.5% of labor cost for additional tools
3. Allowed mark up of 20% for the build up basic rate
4. All the material rates included with transport cost.
Item Nr
Labour Component
Units
Qty
Carpenter (SK'A')
Unskilled Labour (U/SK)
Day
Day
1.00
1.50
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
m
Kg
Litre
14.26
3.46
2.45
Item Nr
Units
Qty
Rate covers : Cost of material, making mould, assembling, cleaning, repairing and dismantling
Assumptions made
1. Allowed 5% wastage
2. Allowed 2.5% of labor cost for additional tools
3. Allowed mark up of 20% for the build up basic rate
4. All the material rates included with transport cost.
Concrete Ancillaries
G.10/G.11/G.12/G.13
Work Item :
Formwork, Rough Finish, left in, 20mm thick permenant formwork
Assumed Quantity for Rate build up
5.57
Sq.m
Item Nr
(Includ
Labour Component
Units
Qty
Carpenter (SK'A')
Skilled Labour (SK'B')
Unskilled Labour (U/SK)
Day
Day
Day
1.75
1.75
2.50
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
m2
Cu.Deci m
Kg
Litre
m
2.45
118.86
1.15
4.50
125.00
Item Nr
Units
Qty
Item Nr
Labour Component
Units
Qty
Carpenter (SK'A')
Skilled Labour (SK'B')
Unskilled Labour (U/SK)
Day
Day
Day
0.25
0.50
0.75
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
m2
Cu.Deci m
m
0.44
11.00
12.00
Kg
Litre
0.12
0.24
(Including 10%
Item Nr
Units
Qty
Rate covers : Cost of material, making mould, assembling, cleaning, repairing and dismantling
Assumptions made
1. Allowed 10% wastage and assumed to be used for 5 times
2. Allowed 5% of labor cost for additional tools used and scaffolding
3. Allowed mark up of 20% for the build up basic rate
4. All the material rates included with transport cost.
BILL NO 6:
Concrete Ancillaries
G.16
Item No:
Work Item :
Formwork fair finish with Class II timber for Bridge deck soffit and sides including dismantling
Assumed Quantity for Rate build up
7.32
Sq.m
(Including 10%
Item Nr
Labour Component
Units
Qty
Carpenter (SK'A')
Skilled Labour (SK'B')
Unskilled Labour (U/SK)
Day
Day
Day
1.00
1.50
2.5
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
Cu.Deci m
Cu.Deci m
m
Kg
Litre
67.10
52.36
7.11
3.18
3.64
Item Nr
Units
Qty
Rate covers : Cost of material, making mould, assembling, cleaning, repairing and dismantling
Assumptions made
1. Allowed 10% wastage and assumed to be used for 3 times
2. Allowed 5% of labor cost for additional tools used and scaffolding
3. Allowed mark up of 20% for the build up basic rate
4. All the material rates included with transport cost.
BILL NO 6:
Concrete Ancillaries
G.18/G.21
Item No:
Work Item :
Formwork fair finish with Class II timber for Edges and sides of footwalk including dismantling
Assumed Quantity for Rate build up
5.57
Sq.m
(Including 10%
Item Nr
Labour Component
Units
Qty
Carpenter (SK'A')
Unskilled Labour (U/SK)
Day
Day
1.25
1
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
Cu.Deci m
m
Kg
Litre
49.53
12.20
0.27
0.90
Item Nr
Units
Qty
Rate covers : Cost of material, making mould, assembling, cleaning, repairing and dismantling
Assumptions made
1. Allowed 10% wastage and assumed to be used for 4 times
2. Allowed 2.5% of labor cost for additional tools used and scaffolding
3. Allowed mark up of 20% for the build up basic rate
4. All the material rates included with transport cost.
BILL NO 6:
Concrete Ancillaries
G.17/G.19
Item No:
Work Item :
Formwork fair finish for concrete components of constant cross sections, intrusions including dismantl
Assumed Quantity for Rate build up
7.32
m
Item Nr
Labour Component
Units
Qty
Carpenter (SK'A')
Semi Skilled Labour (SK'A')
Unskilled Labour (U/SK)
Day
Day
Day
1.25
1.25
2.50
Item Nr
Plant/Equipment Component
Units
Qty
Item Nr
Material Component
Units
Qty
m
Kg
Litre
13.25
3.46
2.45
Item Nr
Units
Qty
Rate covers : Cost of material, making mould, assembling, cleaning, repairing and dismantling
Assumptions made
1. Allowed 5% wastage
2. Allowed 2.5% of labor cost for additional tools
3. Allowed mark up of 20% for the build up basic rate
4. All the material rates included with transport cost.
Item Nr
Labour Component
Units
Qty
Barbender (SK'A')
Semi skilled Labor (S/SK)
Day
Day
1.00
1.00
Item Nr
Plant/Equipment Component
Bar cutter
Bar bending machine
Units
Qty
Day
Day
0.15
0.15
Item Nr
Material Component
Units
Qty
Item Nr
Material Component
Reinforcement
Binding wire
Units
Qty
Kg
Kg
52.50
0.45
Item Nr
Units
Qty
Rate covers : Cost of material (including mass of other supports except supports to the top reiforcem
Assumptions made
1. Allowed 5% of material cost as wastage
2. Allowed 2.5% of labor cost for additional tools
3. Allowed 10% of labor cost for spacer block
4. Allowed mark up of 20% for the build up basic rate
5. All the material rates included with transport cost.
6. Reinforcement cost in icluded with 5% of additional mass of other supports
Amount
1,173.88
957.17
1,173.88
957.17
-
2,131.05
Rate
Amount
Rate
Amount
993.25
57.25
148.70
486.69
2,268.25
34.20
22.50
1,291.25
25.00
51.65
3,616.20
Rate
Amount
106.55
106.55
5,853.80
1,170.76
7,024.56
1,261.14
1,262.00
20%
Rate
Amount
1,173.88
957.17
1,467.35
2,392.93
-
3,860.28
Rate
Amount
Rate
Amount
55.00
148.70
25.00
728.75
514.50
61.25
65.23
640.98
Rate
Amount
42.46
42.46
4,543.72
908.74
5,452.46
744.87
745.00
20%
Rate
Amount
1,173.88
957.17
1,173.88
1,435.76
-
2,609.64
Rate
Amount
Rate
Amount
55.00
148.70
784.30
514.50
61.25
25.00
68.00
643.75
Rate
Amount
28.71
28.71
3,282.10
656.42
3,938.51
538.05
539.00
20%
Amount
1,173.88
1,076.86
957.17
2,054.29
1,884.51
2,392.93
-
6,331.72
Rate
Amount
Rate
Amount
993.25
57.25
148.70
2,433.46
6,804.74
171.01
112.50
6,456.25
25.00
51.65
13,544.49
Rate
Amount
316.59
316.59
20,192.80
4,038.56
24,231.36
4,350.33
4,351.00
mantling
(Including 10% wastage and for 5 uses)
Mark - up
20%
Rate
Amount
1,173.88
1,076.86
957.17
293.47
538.43
717.88
-
1,549.78
Rate
Amount
Rate
Amount
993.25
57.25
51.65
437.03
629.75
148.70
17.84
6.00
25.00
619.80
1,710.42
Rate
Amount
77.49
77.49
3,337.69
667.54
4,005.23
2,002.61
2,003.00
Amount
1,173.88
1,076.86
957.17
1,173.88
1,615.29
2,392.93
-
5,182.10
Rate
Amount
Rate
Amount
57.25
57.25
51.65
148.70
3,841.48
2,997.61
367.23
472.87
91.00
25.00
7,770.18
Rate
Amount
259.10
259.10
13,211.38
2,642.28
15,853.66
2,165.80
2,166.00
Mark - up
20%
Rate
Amount
1,173.88
957.17
1,467.35
957.17
-
2,424.52
Rate
Amount
Rate
Amount
57.25
51.65
148.70
2,835.59
630.13
40.15
22.50
25.00
3,528.37
Rate
Amount
60.61
60.61
6,013.50
1,202.70
7,216.21
1,295.55
1,296.00
20%
Rate
Amount
1,173.88
1,076.86
957.17
1,467.35
1,346.08
2,392.93
-
5,206.35
Rate
Amount
Rate
Amount
55.00
148.70
728.75
514.50
61.25
25.00
65.23
640.98
Rate
Amount
57.27
57.27
5,904.60
1,180.92
7,085.52
967.97
968.00
Mark - up
20%
Rate
Amount
1,173.88
1,025.53
1,173.88
1,025.53
2,199.41
Rate
Amount
1,500.00
2,000.00
225.00
300.00
525.00
Rate
Amount
Rate
Amount
116.00
136.35
6,090.00
61.36
307.57
6,458.93
Rate
Amount
54.99
219.94
274.93
9,458.26
1,891.65
11,349.91
supports
227.00
227.00