Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Large investments
Long gestation period
Increases cost of power transmission
Sediment erosion problem in Himalayan
Rivers
Hydropower plants
Availability of water
Water storage
Water head
Accessibility of the site
Distance from load centre
Type of the land of site
Hydropower plants
gate hoist
Intake gate
Intake trashrack
Tunnel Inlet
Surge tank
Tunnel Inlet
trashrack
Penstock inlet
Valve
Desilting basin
Headrace tunnel
Anchor block
Anchor block
Shaddle
Power house
Exp. joint
DT end gate
IV
G
Tailrace
SC
IV -inlet valve
R -turbine runner
R
SC -spiral case
G -generator
DT
Hydropower plants
Inlet gate
Air inlet
Surge shaft
Penstock
Tunnel
Sand trap
Trash rack
Self closing valve
Tail water
Main valve
Turbine
Draft tube
Catchment area
Reservoir
Dam
Spillways
Conduits
Intakes, Canals, Tunnels, Fore-bay,
Flumes etc. to control Gates and
Valves
Surge tanks
Protection device e.g. Trash racks,
Debris cleaning device and Heating
element
Prime movers
Draft tubes
Power house and equipment
Hydraulic turbines
Electric generators
Governors
Gate valves
Relief valves
Water circulating pumps
Flow measuring equipment
Air duct
Water circulating pumps
Switch board equipment and instruments
Oil circuit breakers
Reactors
Low tension and high tension bar
Storage batteries
Cranes etc
Classification of Hydro-electric
plants
According to availability of head
High head power plants
Medium head power plants
Low head power plants
Cost of hydro-plant
Reservoirs
70-80
Dams:
Average life
(years)
35-50
Earthen,
concrete or
masonry
150
Generators
25
Loose rock
60
Transformers
30
Turbines
(hydraulic)
50-100
Pumps
20-25
40-50
Concrete
25-50
Water ways:
Canals, tunnels
Penstocks:
Steel
Trash Racks
Gravfoss
Power Plant
Norway
Trash Rack size:
Width: 12 meter
Height: 13 meter
Stainless Steel
CompRack
Trash Rack delivered
by VA-Tech
CompRack
Trash Rack delivered
by VA-Tech
Flap Gate
Circular gate
Canals
25
Shape of Tunnels
Circular Tunnel
Spherical Valve
Butterfly Valve
Butterfly valve normally applied in front of the low and medium head
water turbine with head range up to 200m
Butterfly Valve
Dams
Rock-fill dams
1.
2.
3.
4.
Core
Filter zone
Transition zone
Supporting shell
Arc dam
Steel pipes
Glomfjord
Power Plant
GUP-Pipe
Raubergfossen Power Plant, Norway
Wood Pipes
Impulse turbines
(Partial turbines)
Turgo
Pelton
Jostedal, Norway
Kvrner
Reaction turbines
(Full turbines)
Francis
Kaplan
Bulb
Catchment area
The whole area behind the dam draining into
a stream or river across which the dam has
been built at a suitable place
Reservoir
A reservoir is employed to store water which
is further utilized to generate power by
running the hydraulic turbines
Two types: Natural and Artificial
An artificial reservoir is built by erecting a dam
across the river
Water held in upstream reservoir is called
storage whereas water behind the dam at the
plant is called poundage
Dam
Dam is a barrier to confine or raise water for
storage or diversion to create a hydraulic
head
An hydro-electric dam diverts the flow from
the river to the turbines and usually increases
the head
A reservoir dam stores water by raising its
level
Dams are built of concrete or stone masonry,
earth or rock fill, or timber
Dam contd..
Masonry dams may be the solid-gravity,
buttress or arch type
A barrage is a diversion dam, especially at
a tidal power project
A weir is a low overflow dam across a
stream for measuring flow or maintain
water level, as at a lake outlet
Types of dams
Fill dams
Earth dams
Rock-fill dams
Masonry dams
Solid gravity dams
Buttress dams
Arch dams
Timber dams
Nature of valley
Spillways
When the water enters the reservoir basin,
the level of water in basin rises. This rise is
arranged to be of temporary nature because
excess accumulation of water endangers the
stability of dam structure
To relieve reservoir of this excess water
contribution, a structure is provided in the
body of a dam or near the dam or on the
periphery of a basin
This safeguarding structure is called a
spillway
Spillways contd..
A spillway should fulfill the following
requirements
It should provide structural stability to the dam
under all conditions of floods
It should be able to pass the designed flood
without raising reservoir level above high
flood level (H.F.L)
It should have an efficient operation
It should have an economical selection
Types of spillways
Selection of spillway
Based on the type of dam
Quantity of flood water to be discharged
below
It also depends on the site conditions
Conduits
A headrace is a channel which leads water
to a turbine and a tailrace is a channel
which conducts water from the wheels
Two types:
Open conduits:- Canals and flumes
Close conduits:- Tunnels, pipelines and
penstocks
Surge tanks
Small reservoir or tank in which the water level is rises
or falls to reduce the pressure swings so that they are
not transmitted in full to a closed circuit
Server the following purposes:
To reduce the distance between the free water surface and
turbine thereby reducing the water-hammer effect ( the
water hammer is defined as the change in pressure rapidly
above or below normal pressure caused by sudden
changes in the rate of water flow through the pipe
according to the demand of prime mover) on penstock and
also protect upstream tunnel from high pressure rises
To serve as a supply tank to the turbine when the water in
the pipe is accelerating during increased load conditions
and as a storage tank when the water is decelerating
during reduced load conditions
Prime movers
Converts the energy of water into mechanical
energy and further in to electrical energy
Classified on the basis of the action of water on
moving blades
Impulse turbine:- here the pressure energy of water is
converted into kinetic energy when passed through
the nozzle and forms the high velocity of jet of water
Reaction turbine:- in this case water pressure
combined with the velocity works on the runner. The
power in this turbine is developed from the combined
action of pressure and velocity of water that
completely fills the runner and water passage
Draft tubes
Draft tubes serves the following two
purposes:
It allows the turbine to be set above tail-water
level, without loss of head, to facilitate
inspection and maintenance
It regains, by diffuser action, the major portion
of the kinetic energy delivered to it from the
runner