PROJECT TITLE:
PROPOSED SERI KEMBANGAN INTERCHANGE AND TOLL PLAZA
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
Section
Titles / Subtitles
Page
1.0
Objective
3 of 9
2.0
Scope of Work
3 of 9
3.0
References
3 of 9
4.0
Resources Planning
3 of 9
4.1
4.2
4.3
Material Planning
Manpower Planning
Machinery & Equipment Planning
5.0
5.1
5.2
Material Handling
Material Delivery Inspection: Checking Methodology
6.0
6.1
6.2
6.3
6.4
7.0
Work Methodology
7.1
7.2
7.3
7.4
7.5
7.6
7.4
8.0
8.1
8.2
8.3
9.0
9 of 9
10.0
Attachment
9 of 9
4 of 9
5 of 9
6 of 9
8 of 9
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
1.0
OBJECTIVE
2.0
SCOPE OF WORK
In general scope of work for this work method statement cover the
following:Scope of Works
Earthworks for road
and highway project
including earth cutting, earth
filling and compaction.
3.0
Descriptions / Details
Earthworks consist of the following items;
Survey Setting Out
Preparation To Start Work
Protection and Preventive Actions
Dewatering System and Silt Traps
Method of working in Cutting Section
Method of working in Filling Section
REFERENCES
4.0
RECOURCES PLANNING
4.1
Material Planning
Item
1
2
4.2
Manpower Planning
Item
1
2
3
4
4.3
Material Descriptions
Manpower Descriptions
Project Manager
Project Engineer / Supervisor / Surveyor
Machinery Operator (Excavator, Backhoe, Compactor, Truck)
General Workers
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
5.0
5.1
Material Handling
All good earth (suitable for backfilling) shall be placed at designated
location as stockpile where the material not mixed with the unsuitable
material where free from swamps, marshes, logs, peat, bogs, stump or
other toxic materials
5.2
Earth suitable
for backfilling
Method of
Inspection
Visual &
Test
Random
Sampling
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
6.0
6.1
6.2
6.3
6.4
The following are the common underground M&E services such as: Water Reticulation System
Sewerage Route
Telecommunication Cables
Electrical or Power Supply
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
7.0
WORK METHODOLOGY
7.1
7.2
7.3
Land Acquisition: Prior start work, the project manager shall checked
and ensure that the Employer or relevant authorities have acquired
the right of way lands
Temporary works: Silt Trap/ Access road, temporary drainage, wash
through and silt trap shall be constructed accordingly. Solid waste
dumps sites shall be predetermined within or outside the site for the
dumping of the site clearing materials.
Mackintosh Probe: Testing carried out according to the Consultant
Engineer Instruction. All test results submitted to Consulting
Engineer to confirm the depth of USM removal.
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
7.5
QUICK
plastering
work,excavation
check the works,
following:QUICKCHECK:
CHECK:Prior
Before
and during
check the following: All fixed joinery
items
installed
accordingly
Check possible obstruction or any temporary works
Brick surface notrequired
contaminated
fungus
organic
growth orof
beforeby
start
workor
such
as relocation
oils which may interfere
coating
adhesion
underground M&E services/ risky excavation works
Alignment withinnear
tolerances
/ Correct
setting out
to private
property
Finished products
(Aluminium/Timbe
Check site condition soggy or swamp or unsuitable
material shall be removed and replaced
7.6
7.6.1
Trial Compaction
For first filling and compaction activities, contractor shall arrange trial
compaction to see and evaluate the number of passes required to achieve the
required degree of compaction. Theoretically, different type of soil and type of
compactor machine will produce different degree of compaction achievement.
The machine capacity and effectiveness may the addition factor.
7
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
8.0
8.1
No
Stage of
Work
Setting Out,
Boundary or
ROW check
Submission
of Traffic
Diversion
for Authority
approval
Frequency
Every
Location
When
Required
Traffic
Diversion
(Submission
follow Authority
Requirements)
Preparation,
Protection &
Temporary
Work
When
Required
Site / Soil
Investigation
Every
Location
suspected
to be USM
(Site Condition)
Checking Required
Method
Survey Check
Within survey
tolerance
Planning and
preparation required
for the traffic diversion
Letter
Submission
Approved by
Relevant
Authority
Using temporary
shoring required C&S
consultant approval or
design calculations
Review
Design
Calculation
Design
Calculation
Approved by
Design
Consultant
Random
Sampling and
Test
Visual /
Review
Mackintosh
Probe Results
Removing
Unsuitable
Material /
Topsoil
All areas
Working
in Cutting
Section or
Slope
Every
Cutting
Section or
Slope
Excavation or Cutting
to required level as
per surveyor pegs
Survey pegs/
Construction
Drawing
Trial
Compaction
Once
To check number of
passes required
Compacted
by Roller
Working
in Filling
Section
Every
Filling
Section
Compaction
Test
One(1) test
for every
1000
sq.meter
Filling or Backfilling
according to required
level as per surveyor,
Filling layer by layer,
maximum thickness
300mm per layer
Conduct Field Density
Test (FDT) to check
Degree of Compaction
of minimum 90%
Acceptance
Material not
under USM
category such
as clay etc.
Consultant
approval prior
to backfilling
Excavation or
Cutting to the
required level or
depth as per
Drawing
Achieve the
required degree
of compaction
Survey pegs/
Construction
Drawing
Filling to the
required level
as per
Construction
Drawing
FDT Test
FDT Results
achieved the
specified
compaction
Doc. Date:
24 Mar.14
Doc. Reference:
MH/WMS/001(EA)rev1
9.0
10