Duration : 2 hours
____________________________________________________________________
Section A
1.
50 X 1= 50 marks
2.
3.
4.
5.
6.
7.
The __________________process helps draw a blue print to get executed with little
or no modifications.
a. Project development
b. Project planning
c. Project implementation
d. Feasibility analysis
8.
All these tools are used in project planning and scheduling except
a. PERT
b. Gantt chart
c. SWOT
d. CPM
9.
10.
___________of the product is a major driving force for any project to take off.
a. Price
b. Distribution
c. Communication
d. Sale
11.
If production, R&D, sales and finance are used as bases to organise a company,
then it is a ______________organisation.
a. Line
b. Line and staff
c. Functional
d. Product
12.
13.
14.
b. Management
c. Allocation
d. Levelling
15.
If the resources are limited or there are constraints, then the project manager might
face _______________situation.
a. Resource levelling
b. Resource smoothing
c. Resource levelling or resource smoothing
d. Resource levelling and resource smoothing
16.
17.
18.
19.
20.
21.
22.
23.
24.
Energizer's tagline that says, 'It keeps going, and going, and going', stresses on the
_______________of the brand.
a. Reliability
b. Durability
c. Safety
d. Serviceability
25.
26.
27.
28.
d. Competitors
29.
30.
31.
32.
33.
34.
35.
36.
37.
Once the project is finalised, the execution part begins. At the onset of this phase,
the project manager organises a meeting called ____________meeting to announce
the start of the project.
a. Onset
b. Start-up
c. Kick-off
d. Initiation
38.
40.
41.
42.
d. It means that the succeeding activity can start only if none of the preceding
activities to it have been completed.
43.
44.
45.
46.
47.
d. The present value of future cash inflows is more than the present cash inflow
48.
The time when the event can be completed at the earliest is known as
___________________.
a. EOT
b. LOT
c. Optimistic time
d. Pessimistic time
49.
50.
Section B
25 X 2= 50 marks
51. A project management process ___________ and ______________ the work of the
project.
a. Selects, organises
b. Interprets, organises
c. Describes, selects
d. Describes, organises
52. The _______________ feasibility aspect of a project relates to the earning capacity
of the project, which depend on the ________________.
a. Economic, volume of sales
b. Technical, volume of sales
c. Financial, volume of sales
d. Economic, project idea
56. Assertion (A): It is useful to break the project into some steps.
Reason (R): It is essential to detail all the activities of the project because activities are
the basic building blocks of a network diagram.
a. A is true, R is true
b. A is true, R is false
c. A is false, R is true
d. A is false, R is false
57. Planning of tasks from the date resources become available to determine the
shipping date or the due date is referred to as ______________scheduling, while
planning the tasks from the due date or required-by date to determine the start date
and/or any changes in capacity required is referred to as ________________
scheduling.
a. Forward, backward
b. Backward, forward
c. Vertical, Horizontal
d. Horizontal, vertical
58. Assertion (A): When the project includes a risky event, the cost of the project will
always decrease.
Reason (R): If the project includes a risky event, there is likelihood of delay in the
scheduled project.
a. A is true, R is true
b. A is true, R is false
c. A is false, R is true
d. A is false, R is false
59. Two factors that are essential to all human decision making are risk
_____________and risk _________________.
a. Communication, perception
b. Communication, management
c. Perception, alleviation
d. Perception, management
60. Assertion (A): Organisations can generate a lot of profit if they deal with uncertain
project events in a reactive manner.
Reason (R): There are a lot of benefits of proper risk management in projects.
a. A is true, R is true
b. A is true, R is false
c. A is false, R is true
d. A is false, R is false
61. Vodafone, 'Happy to help you' stresses on _____________of the brand while Punjab
National Bank, 'The name you can bank upon' stresses on ___________.
a. Reliability, durability
b. Serviceability, reliability
c. Serviceability, durability
d. Durability, reliability
62. Assertion (A): A good quality planning process starts with a clear definition of the
goals of the project.
Reason (R): Quality planning is the process of identifying the quality standards that are
related to the project and determining how to these standards can be achieved.
a. A is true, R is true
b. A is true, R is false
c. A is false, R is true
d. A is false, R is false
5 Political parties
a. 1 and 2
b. 1, 2 and 3
c. 2 and 3
d. 1, 2 and 5
65. Which of these is/are included in the product specification?
1 Commercial design
2 Function
3 Indent
4 Performance
a. 1 and 2
b. 2 and 3
c. 3 and 4
d. 1, 2 and 4
c. ACWP/BCTW
d. ACWP +BCWP/BCWS
68. Which of these statements are true?
1 Work-to list is a list prepared separately for each agency
2 It is prepared before the resource scheduling process
3 A work-to list is generally prepared to cover a few years ahead.
4 It is a recommendation to the concerned managers of the sequence and timing of
work to be done
a. Statements 1, 2 and 3 are true
b. Statements 2, 3 and 4 are true
c. Statements 1 and 3 are true
d. Statements 1 and 4 are true
71. Assertion (A): Team members have this tendency to leave a number of small work
outstanding.
Reason (R): As the project nears completion, the project manager works really hard
and conducts regular meetings to be in focus.
a. A is true, R is true
b. A is true, R is false
c. A is false, R is true
d. A is false, R is false
72. Which of these can errors cannot be detected by error detection routines?
1 An incorrect activity duration
2 An incorrect activity name
3 An Incorrect precedence logic
4 An Incorrect cost data
a. 1, 2 and 3
b. 1, 3 and 4
c. 2, 3 and 4
Cumulative BCWS
d. 1, 2, 3 and 4
73.
Time
a. Effectiveness, efficiency
b. Quality, effectiveness
c. Efficiency, quality
d. Productivity, quality
75. Data collected from balance sheet of the company is known as _____________ data
while data collected from interviewing employees is known as ______________ data.
a. Primary, secondary
b. Secondary, primary
c. Internal, external
d. External, internal
Section C
4*10=40 marks