Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
OF
23
1.
1.1
Documentation
This section includes a listing of the technical documentation,
which will be submitted to the Employer. The following lists are
indicative only and will have to be adjusted to the actual project.
1.1.1
General Documents
Document / Subject
Weeks after
Signing of
Contract
4-6
4-6
4-6
QA Schedule
4-8
8 weeks prior to
testing
4 weeks prior to
testing
TOC +
6-8
PAGE 2
1.1.2
OF
23
Weeks after
Signing of
Contract
Basic Design:
Civil engineering basic calculations
(foundations and structures)
12
12
12
12
Main gate
Material description
Detailed Design:
Site preparations (general leveling and subfoundation works)
12
12
16
12
PAGE 3
OF
Document / Subject
23
Weeks after
Signing of
Contract
plate
Engine/alternator foundation, upper block
12
12
16
20
20
Stairways
20
20
Roof structure
20
Internal walls
20
20
16
20
20
PAGE 4
OF
Document / Subject
1.1.3
23
Weeks after
Signing of
Contract
12
20
Color codes
16
20
Weeks after
Signing of
Contract
20
PAGE 5
OF
Document / Subject
23
Weeks after
Signing of
Contract
1.1.4
Noise study
Control descriptions
20
Lubrication scheme
20
Weeks after
Signing of
Contract
PAGE 6
OF
Document / Subject
23
Weeks after
Signing of
Contract
20
20
20
Calculations for cable dimensioning and voltage drop for main cables
20
Lighting and small power installation drawings, all built and outdoor installations
30
List of cables
25
PAGE 7
OF
Document / Subject
Weeks after
Signing of
Contract
30
1.1.5
23
20
Weeks after
Signing of
Contract
10
20
PAGE 8
OF
Document / Subject
1.1.6
23
Weeks after
Signing of
Contract
Control concepts
10
10
Weeks after
Signing of
Contract
20
20
PAGE 9
OF
Document / Subject
23
Weeks after
Signing of
Contract
20
20
20
20
1.2
Quality Management
1.2.1
General
CONSULTANT Quality Management System is partly based on
the requirements in DS/EN ISO 9001 and covers internal
general QA/QC-procedures and procedures for project
execution.
It is within the framework of the system possible to vary the requirements on review, inspection, testing, verification, and
documentation, depending on specific agreed Employers
requirements or project specific requirements.
PAGE 10
1.2.2
OF
23
PAGE 11
procedures will
procedures.
1.2.3
OF
be
supplemented
23
with
project
specific
Project QA/QC
This section describes in general the Project Quality
Assurance, as it will be carried out for the project to ensure a
quality level as specified.
The execution of the detailed QA/QC work will be carried out
by the engine supplier respectively CONSULTANT, where each
party will follow their own detailed procedures and use own
formulas etc. as described in their respective company QA
manual systems.
1.2.3.1
1.2.3.2
Project Manuals
A Project Manual System will be established in the initial startup period for the project.
The Project Manual System will comprise:
PAGE 12
OF
23
1.2.3.4
1.2.3.5
PAGE 13
OF
23
certificates,
inspection
PAGE 14
OF
1.2.3.7
1.2.3.8
23
Sub-contracting
The mechanical-electrical and civil/building subcontractors shall
follow the procedures in CONSULTANT Project QA Manual.
In principle, each sub-contractor will be responsible for executing
the QA/QC procedures for his scope of works. The practical
execution and split-up of the QA/QC works and
administration/filing
etc.
between
the
contractor
and
CONSULTANT will be clearly stated in the sub-contract.
The subcontractors will be obliged to co-ordinate the site QA/QC
works with CONSULTANT's site manager and supervisors.
1.2.3.10
PAGE 15
1.2.3.11
OF
23
1.2.3.12
for
each
building/area/equipment/
1.2.3.13
PAGE 16
OF
23
1.2.5
QA/QC Documentation
All QA/QC documents may finally be collected in a special
Quality Manual.
The complete QA/QC documentation will cover:
- All QA/QC documents from factory inspection/tests as
described in this section
- All QA/QC documents from site inspections/tests for civil and
building works
- All QA/QC documents from site inspections/tests
mechanical and electrical erection works
for
1.3.1
General
The Operation and Maintenance Manual will be supplied as
follows:
PAGE 17
OF
23
1.3.2.1
Part B:
Part C:
PAGE 18
OF
23
Part D:
Part E:
Part F:
Volumes
The contents of the parts will be placed in a number of volumes.
The volumes will be numbered from 1 to X.
If an extra volume is required, this is numbered as X-1
Ex.:
Part C
Part C
Electrical
Electrical
Volume 9
Volume 9-1
PAGE 19
1.3.2.3
OF
23
Sections
Each volume is divided into sections.
Examples: Volume 9, Section 3.4
(in which "3" indicates the section and "4" the sub-section)
1.3.3
Lubrication Schedules
30 days prior to commencement of pre-commissioning of the
plant a lubrication schedule will be provided. The schedule will
include specification of details regarding shipping, storage and
definition of coatings and lubricants applied to the equipment
included in the total plant.
1.4
1.4.1
General
BWCSs document control system will be used to ensure a
controlled handling of all essential technical documents.
1.4.2
PAGE 20
1.4.3
OF
23
1.4.4
Document Submittal
Documents may be forwarded as:
- Hard-copy paper documents submitted by telefax, courier,
airmail or carried by personnel traveller.
- Electronic
documents
submitted
per
submitted/carried as diskettes or CD-ROMs.
or
1.4.6
PAGE 21
1.4.7
OF
23
Approval Procedures
For each project detailed approval procedures will be worked out.
In the initial start-up stage for a project, it will be agreed:
- Which parts of the technical documentation, the Employer
(and other relevant parties) is requesting to be submitted for
information, comments and approval.
- The amount of documents to be transmitted between all
involved parties in the project organisation. If local
authorities require approval of specific equipment/systems,
such submittals shall form a part of the agreed procedures.
The approval time will be maximum 10 calendar days.
Approval of major technical documentation will be incorporated in
CONSULTANTs planning as separate activities in relation to the
planning for engineering and purchase activities.
1.4.8
CONSULTANT
Consultant)
Submittal
to
Employer
(and
Employers
the
CONSULTANT given
status for submitted
technical documents
FOR INFORMATION
(PRELIMINARY)
PAGE 22
FOR APPROVAL
OF
23
REVISED
1.4.9
Drawings
Drawings will be in sufficient details for providing adequate design
information for project activities. The scales will be established
during the actual design process by CONSULTANT.
Drawing sizes will be in accordance with ISO 5457 (DS/ISO 5457)
i.e. ISO A format
A0 841 x 1189 mm
A1 594x 841 mm
A2 420 x 594 mm
A3 297 x 420 mm
A4 210 x 297 mm
Drawings above A4 will be folded to A4 size: 8.27 x 11.69 (210 x
297 mm).
1.4.10
PAGE 23
OF
23