Shipyard engineering
Lecture 6-1: Outfitting
Applied Mechanics
Marine Technology
Introduction
Design process
and materials
management
Hull production
Contents:
Product hierarchy for outfitting
Construction method Productization - Work breakdown
structure - product hierarchy
Literature
Laivatekniikka. Risnen toim., 2000
Ship production, Storch et al., SNAME
Construction is fragmented
Outfitting production
- Area or space
- Cabin
- Separator module
Productization
Target of productization
Dividing of the ship into the sub parts, which can be
manufactured by the yard or someone else as cheaply as
possible
Productization
Technical aspects on the basis of ship project
System-area matrix
Passing through system
Design process
Agreement in the various design stages
Production control
Transport technology
Ship
Zones
Hull
System
Shkjrjestelmt
Kansi xx
IV jrjestelmt
LV jrjestelmt
Basic elements
Prefabricated
Assembly
Basic elements
Pre fabrication
Prefabricated
Assembly
Assembly
Prefabrication
Block outfitting
Basic elements
Prefabrications
Assemblies
Workshops
Traditional workshops
at the shipyard
Machine workshop
Pipe workshop
Module workshop
Heavy plate workshop
Sheet metal workshop
Wood workshop
Electrical workshop
Rigging workshop
Workshops today
in co-operation with suppliers
Subcontractor for contract products
Subcontractor has specialized
workshops for their products
Shipyard has had only basic
equipment and workers
Co-operation is based on annual
contracts
Coefficient
1.0
1.2
1.5
2.0
4.0
Other benefits
Lesser need for repair painting
Reduction of the scaffold and
other supporting work
Better balancing of outfitting
work
Small disturbances due to other
workers
During the manufacturing of grand block (Block is located right side up)