Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Electrical Engg. Deptt., Medi-Caps Institute of Science & Technology, Indore, M.P., India
Electrical & Electronics Engg. Deptt., UIT, Rajiv Gandhi Technological University, Bhopal, M.P., India
c
Electrical Engg. Deptt., Shri G.S. Institute of Technology & Science, Indore, M.P., India
b
a r t i c l e
i n f o
Article history:
Received 13 April 2010
Received in revised form 8 April 2012
Accepted 24 May 2012
Available online 7 July 2012
Keywords:
Distribution system
Reliability indices
Failure rate
Repair time
Differential evolution
PSO
a b s t r a c t
This paper describes an analytical methodology for reliability evaluation and enhancement of distribution system having distributed generation (DG). Standby mode of operation of DG has been considered
for this purpose. Reliability of the composite distribution system has been optimized with respect to failure rate and repair time of each section of the distribution system subject to constraints on (i) failure
rates/ repair times and (ii) customer and energy based reliability indices i.e. SAFI, SAIDI, CAIDI and AFNS.
The objective function includes (i) cost of modication for failure rates/repair times (ii) additional cost of
expected energy supplied by DG. Differential evolution (DE), Particle swarm optimization (PSO) and coordinated aggregation based PSO (CAPSO) have been used to develop computational algorithms. Developed algorithms have been implemented on a sample distribution system.
2012 Elsevier Ltd. All rights reserved.
1. Introduction
Distribution systems were not originally designed to accommodate generation in itself. Hence increasing penetration level of DG
is causing changes in the planning, operation and maintenance of
distribution systems. Presence of DG in a distribution network affects network planning, operation and maintenance, auxiliary services, quality of service and regulatory aspects [14]. Ackerman et
al. [5] have analyzed the term DG in detail. Usually in reference to
this present paper, DG will be considered as electricity generation
systems connected to distribution networks, characterized by their
small rating and located near connection points. Distribution system operators (DSOs) may have their own DG or may encourage
large consumer to install DG which is owned and controlled by
these customers. Availability of such customer owned and controlled DG may not be high, but may be of great help in improving
the reliability indices of the distribution network.
The reliability of a distribution system may be increased by
modifying failure rate and repair time of each section of the network. Such modications may require additional investments
which in the presence of DG may be mitigated. This will result in
annual savings. On the other hand cost per unit energy obtained
Corresponding author.
E-mail address: aryarajesh@yahoo.com (R. Arya).
0142-0615/$ - see front matter 2012 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.ijepes.2012.05.045
608
s, rs
sw, s
Load Point
dg, rdg
Fig. 1b. Reliability network of the schematic diagram of Fig. 1a.
eq, req
Fig. 1c. A single component equivalent of reliability network of Fig. 1b.
LP - iA
where keq is the equivalent failure rate; req the equivalent interruption duration; ks the represents total failure rate up to load point
from substation supply; rs the represents average interruption duration from substation supply; kdg the failure rate of DG; rdg the average outage duration of DG; and ksw the failure rate of manual
switch; and s is the service restoration time from DG.
s, rs
dg, rdg
Main Source
DG
Load Point (LP)
Fig. 1a. Schematic diagram of a load point fed from main source and as stand by
supply from DG.
Distribution System
LP - iB
DG
Fig. 2a. Reliability modeling for ith load point having limited DG capacity available.
NC
X
ak
2
k1 kk
NC
X
bK
K1
rK
ADCOSTEENSO EENSD
s, rs
Source
LP - iA
LP - iB
dg, rdg
Fig. 2c. Reliability network for evaluating indices at LP iB.
expected energy not supplied without DG; EENSD the expected energy not supplied with DG and ADCOST is the additional cost per
kWh to be paid to DG owners.
The objective function constitutes of three parts i.e. (i) rst part
reects cost of modications of failure rates of each section. It includes cost of preventive measures for reducing failure rate. The
quadratic form is based on the reliability growth model of Duane
[17], (ii) second part gives cost of modications in average repair
time of each section which is again based on a growth model of repair time. Larger is the repair time lesser is the cost of repair and
vice versa, and (iii) third part represents additional cost to be paid
to the owners of DG. This term in fact is the expected energy supplied (EENSOEENSD) by DG multiplied by additional charge per
kW h (ADCOST). Thus the objective function provides a balance between additional cost incurred by the provision of DG and cost due
to modications in failure rates and repair times. It is to be noted
that the operation of DG has been considered in standby mode
and DG has been assumed to be privately owned. Hence power obtained from DG is costlier than that obtained from distribution
substation. Other side one has to pay price for modications in failure rates and repair times to achieve desired values of reliability
indices as given by relations (7)(10). Hence a compromise has
to be achieved between failure rate and repair time modications
and additive cost of energy obtained from DG sources. This, in fact,
is achieved by minimizing the objective function given by relation
(3). This framed objective function includes the cost of modications and additional cost of energy purchased from DSO. Further
note that as explained in Section 2, power cannot be taped immediately from DG, but with a time delay of s (service restoration
time from DG) hours and this has been accommodated in modeling
aspects. Another aspect which has been included that the demand
may be fullled even partially in emergency conditions. This has
been included in modeling aspects.
Expected energy not supplied (EENS) is calculated for all load
points as follows [18]
X
EENS
Li U SYS;i
U SYS;i
4a
k2S
4b
kk;min 6 kk 6 kk;max
r k;min 6 r k 6 r k;max
SAIFI 6 SAIFId
X
SAIFI
kSYS;i Ni
X
Ni
SAIDI 6 SAIDId
SAIDI is dened as
X
SAIDI
U N
i SYS;i i
P
Ni
10
CAIDI 6 CAIDId
11
U SYS;i Ni
CAIDI Xi
k N
i SYS;i i
12
(v) Constraint on average energy not supplied (AENS) per customer also known as average system curtailment index
(ASCI)
AENS 6 AENSd
13
AENS
kk r k
609
P
LU
Pi SYS;i
Ni
14
In all above Ni is the number of customers at ith load point; Li average load at ith load point; kSYS;i is average failure rate at ith load
point; rSYS,i is average interruption duration at ith load point; USYS,i
is average annual outage duration given as product of kSYS;i and
rSYS,i.
SAIFId, CAIDId, SAIDId and AENSd are threshold values of the SAIFI,
CAIDI, SAIDI and AENS respectively. In Eqs. (5) and (6) the upper
limits on failure rate (k) and repair time (r) are considered as current (present) values as provided by any system data. Lower limits
on failure rate (kk,min) and repair time (rk,min) are the values which
can be achieved in practice. In any case these values cannot be
made zero. These lower limits are obtained in practice using failure
610
and repair data analysis along with the associated costs. The procedure is similar to that of reliability growth model [17]. The threshold values of reliability indices i.e. SAIFId, SAIDId, CAIDId, and AENSd
are based on managerial/administrative decisions.
The formulated reliability optimization problem has been
solved using robust population based optimization algorithms
known as differential evolution (DE), particle swarm optimization
(PSO) and one of its variant known as co-ordinated aggregation
based particle swarm optimization (CAPSO). The formulated problem has been solved using these three optimization techniques so
as to get condence in the optimization results and applicability of
these methods for solving such problem may be veried and comparison of the result may be made. The main idea of the paper is to
obtain the optimum values of failure rates and repair times of each
distribution segment subject to satisfaction of threshold values of
reliability indices (SAIFI, SAIDI, CAIDI, and AENS) and incorporating
the effects of distributed generation available in standby mode.
The optimized values may be allocated as target values to preventive maintenance and corrective repair crew. Computational algorithms have been explained in next two sections.
k
Step-7. Select two random vectors X k
p and X q from the population, where p q i best.
Step-8. Generate a mutated vector using following relation
Vi
K
X best rX K
p Xq
K
k
ij
X 0i k0i ; r0i ;
i 1; . . . ; M
if
if
v ijK 6 xj;min
v ijK P xj;max
8
< xbest;j randxj;min xbest;j ;
16
15
tij
8
< v k ;
ij
if
randj 6 C r ;
k
xij ;
or
otherwise
j jrand
17
611
Xi
i 1; . . . ; M
18
best;i X i
k1
k1
c2 rand2 Gbest X i
k1
P best;i
19
th
k1
Gbest
where
is the best previous position i particle;
is the
global best position among all the participation in the swarm from
objective function view point; rand1, rand2 are random digits in the
range [0, 1]; w is inertia weight and c1, c2 are acceleration constants
A large inertia weight (w) facilitates global exploration and a smaller inertia weight tends to facilitate local exploration to ne tune
the current search area. Therefore the inertia weight w is an
important parameter for convergence behavior of PSO. A suitable
value of inertia weight usually provides balance between global
and local exploration abilities and consequently results in a better
optimum solution. In view of this it has been suggested that inertia
weight w is varied as follows [23]
wmax wmin
w wmax
k
kmax
where kmax is the maximum number of iteration specied and k denotes current iteration. wmax and wmin denotes maximum and minimum values of inertia weight.
K1
Step-6. position of each particle, X i
, is updated using following relation
k
k1
Xi Xi
qi
20
Pbest;i
8
< X k ifJX k < JPk1
i
best;i
k1
Pbest;i otherwise
21
qik w qik1
k1
rj AF ij
k1
Xj
k1
Xi
22
k1
k1
AF ij
JX i
X h
K1
JX j
JX K1
i
l2T
K!
JX l
23
24
X k1
is randomly selected particle, X pk1 is the best particle in the
m
swarm and r is random digit between [0, 1]. The updating of best
particle of group behaves in a crazy way and helps the swarm to escape from local minima. Remaining steps are same as explained in
previous section. CAPSO has better convergence characteristics and
require only inertia weight parameter to start the updating
procedure.
7. Results and discussions
The algorithm developed in this paper has been implemented
on a sample radial distribution system as shown in Fig. 3 [11].
The system has seven load points in addition to a source sub-station and seven distributor segments. The system has been modied
due to presence of DG at load points LP-3, LP-6 and LP-8. In the absence of loss of supply at these nodes continuity is maintained with
the help of these distributed sources. Further it is assumed that
DG-6 present at LP-6 is sufcient to feed the need of only 50% consumers connected at the load point and distributed generator DG-3
612
DG-8
Table 2
Average load and number of customer at load points.
LP-8
#7
LP-7
1000
200
700
150
400
100
500
150
300
100
200
250
150
50
Table 3
Cost coefcients ak and bk for calculating objective function (J).
#6
Sr. No.
ak (Rs.)
246
100.00
40
72.90
81
72.00
250
200.00
32
180.00
4.5
38.40
5.0
93.60
bk (Rs.102)
LP-2
#1
#2
U SYS;4 k1 r 1 k2 r 2 k3 r 3
Source
#3
~
#4
rSYS4
U SYS;4
kSYS;4
DG-3
kSYS;5 k1 k4
LP-3
LP-5
U SYS;5 k1 r 1 k4 r 4
rSYS;5
#5
U SYS;5
kSYS;5
kSYS;7 k1 k2 k6
~
DG-6
LP-6
and DG-8 connected at load points LP-3 and LP-8 are having sufcient capacities to meet demand of all the consumers connected at
these load points. Table 1 gives current failure rates k0j , repair
time r 0j and bounds on these quantities for each section. Due to
presence of distributed energy resources modications on both
sides of decision variables have been considered. Records of
growth model of these variables allow to estimate bounds on these
variables. Table 2 provides average loads and number of customers
at each load point. Table 3 provides cost coefcient ak, bK as required to evaluate objective function (J). The ADCOST is selected
as Rs.1.5 per kW h.
Reliability modeling aspects are described in Section 2. kSYS ; rSYS
and USYS, for load points LP-2, LP-4, LP-5 and LP-7 (these do not
have DG) are evaluated using following relation.
U SYS;7 k1 r 1 k2 r 2 k6 r 6
rSYS;7
U SYS;7
kSYS;7
kS3 k1 k2
rS3
k1 r1 k2 r2
k1 k2
kSYS;3 and rSYS,3 with DG are obtained using relation (1) and (2) as
follows
kSYS;2 k1
rSYS;3
r SYS;2 r 1
In above kd3 ; rd3 are failure rate and average down time of DG-3 kSW3
failure rate of manual switch of DG-3 s3 average service restoration
time of DG-3Similarly reliability diagram for LP-8 is shown in Fig. 5;
basic reliability indices kSYS;8 ; rSYS;8 and USYS,8 are evaluated using following relations.
U SYS;2 k1 r1
kSYS;4 k1 k2 k3
Table 1
System data for sample radial distribution system.
Distribution section
k0j 1=yr
kj;min 1=yr
kj;max 1=yr
r 0j hrs
rjmin(hrs)
rjmax(hrs)
1
2
3
4
5
6
7
0.4
0.2
0.3
0.5
0.2
0.1
0.1
0.2
0.05
0.1
0.1
0.15
0.05
0.05
0.6
0.3
0.5
0.8
0.3
0.15
0.15
10
9
12
20
15
8
12
6
6
4
8
7
6
6
15.0
14.0
18.0
30.0
22
12
18
613
s3, rs,3
sw3, s3
LP - 3
d3, rd3
Fig. 4. Reliability network for LP-3.
s8, rs,8
sw8, s8
LP - 8
d8, rd8
Fig. 5. Reliability network for LP-8.
Decision variables
#1
#2
#3
#4
#5
k1
k2
k3
k4
k5
k6
k7
r1
r2
r3
r4
r5
r6
r7
Objective function,
J 104
0.3040
0.0719
0.1392
0.1522
0.1980
0.0941
0.0928
6.2027
7.4233
5.1253
22.0984
15.4493
9.5325
6.7674
2.7322
0.2253
0.0623
0.2257
0.2511
0.2519
0.1041
0.0943
7.4363
11.0731
7.5651
14.5564
8.9905
7.6173
8.3229
2.2322
0.2208
0.0674
0.2834
0.2043
0.2638
0.0944
0.0886
7.5631
8.5684
4.2047
14.1669
17.8474
8.6555
10.6841
2.2402
0.2248
0.1946
0.4197
0.1499
0.2388
0.1384
0.0654
6.0613
11.8895
6.1739
11.9885
8.7557
11.1945
6.3030
2.0557
0.2339
0.0539
0.2940
0.2087
0.2219
0.1231
0.0955
7.7577
10.0196
10.8947
8.4468
13.3241
6.2040
11.0793
2.6592
Table 4
Failure rate and average down time for distributed generation.
Sr.
No.
DG
Failure
Rate
kd 1=yr
Down
time rd
(h)
Failure rate of
manual switch ksw
(1/yr)
Service
restoration
time s (h)
DG3
DG6
DG8
1.50
15.78
0.5
1.5
1.75
18.68
0.5
1.5
2.00
20.61
0.5
1.5
2
3
Table 7
Control parameter for DE, PSO and CAPSO.
kS8 k1 k2 k6 k8
r S8
S. No.
Parameters
Values of parameters
1
2
3
4
5
6
7
8
9
10
10, 20
0.7
0.3
300
1.0
1.0
1
0.1
300
5, 10, 20
k1 r 1 k2 r 2 k6 r 6 k8 r 8
kS8
distribution network or DG and remaining are supplied by DG-6
in case of loss of supply from source node. The basic reliability indices are evaluated for LP-6A using following formula.
kSYS;6A k1 k4 k5
U SYS;6A k1 r 1 k4 r 4 k5 r 5
rSYS;6A
U SYS;6A
kSYS;6A
Basic reliability indices at LP-6B is evaluated using following relations as given by relations (1) and (2)
Table 5
Initial population generated for DE.
Decision variables
#1
#2
#3
#4
#5
#6
#7
#8
#9
#10
k1
k2
k3
k4
k5
k6
k7
r1
r2
r3
r4
r5
r6
r7
Objective function, J 104
F/NF*
0.2585
0.0636
0.2208
0.2217
0.2749
0.0767
0.1001
7.5019
11.5107
5.7112
8.8760
14.1625
11.8015
16.3618
2.2411
F
0.3914
0.1299
0.4862
0.5069
0.2705
0.0506
0.0890
10.4011
12.0494
11.9502
27.5932
19.2267
8.3456
8.8771
1.0170
NF
0.2320
0.2093
0.4127
0.7234
0.2323
0.0939
0.0711
8.6868
8.4746
14.4646
8.5542
7.2507
10.3021
8.4427
0.9647
NF
0.4874
0.1163
0.4514
0.5934
0.2777
0.1408
0.0996
6.7307
11.8140
5.4722
13.7090
17.1514
10.9863
14.5380
0.8031
NF
0.4799
0.1278
0.1356
0.3538
0.2767
0.1374
0.1354
6.4992
7.8369
11.7145
29.5521
12.6668
9.5162
12.5851
1.2098
NF
0.3470
0.1009
0.2651
0.6560
0.1829
0.1409
0.0945
12.8142
10.7832
6.5088
27.6815
20.6401
7.0240
6.1168
1.1411
NF
0.2565
0.0955
0.3874
0.3548
0.1969
0.1448
0.1019
13.3613
6.5648
7.8263
23.9893
13.8181
7.7196
11.6384
1.3185
NF
0.3955
0.2051
0.1332
0.4777
0.2419
0.0984
0.0840
12.2991
10.3990
8.4846
11.3934
16.8318
10.3243
12.6372
1.3519
NF
0.3186
0.0523
0.1849
0.4668
0.2273
0.0501
0.0543
11.7836
12.5356
17.3843
11.4329
13.2455
6.7416
10.2956
2.5975
NF
0.2985
0.0844
0.2336
0.4535
0.2082
0.0620
0.0992
12.6151
11.0427
14.8331
24.9299
21.6527
9.1818
14.4749
1.4889
NF
614
Source
#1
#4
#1
#5
#4
#5
Table 9
CPU Time for convergence required for DE, PSO, and CAPSO Techniques on Intel
core2duo processor, 2.9 GHz.
LP 6A
LP 6B
S. No
Techniques
Population size
DE
10
20
125
250
PSO
05
10
20
78
141
281
CAPSO
05
10
20
62
141
250
DG - 6
Table 8
Optimized values of failure rates and repair times as obtained by DE, PSO and CAPSO.
Variables
Magnitudes as
obtained by DE
Magnitudes as
obtained by PSO
Magnitudes as
obtained by CAPSO
k1 (yr)
k2 (yr)
k3 (yr)
k4 (yr)
k5 (yr)
k6 (yr)
k7 (yr)
r1 (h)
r2 (h)
r3 (h)
r4 (h)
r5 (h)
r6 (h)
r7 (h)
Objective
function
(J) 104
0.2331
0.1789
0.3104
0.3430
0.2845
0.0920
0.1483
6.0033
6.0767
6.1595
8.0100
7.0643
9.2649
8.3064
1.1701
0.2471
0.1357
0.2932
0.3685
0.2998
0.0952
0.1487
6.0023
6.0012
13.2311
8.0029
7.0685
11.3771
6.0047
1.1836
0.2245
0.1743
0.3449
0.3731
0.2719
0.0901
0.1239
6.4414
6.7191
8.6474
8.1497
7.2750
6.1672
6.7933
1.1841
r SYS;6B
In above kd6 ; r d6 are failure rate and average down time of DG-6. ksw;6
is failure rate of manual switch of DG-6. s6 denotes average service
restoration time of DG-6.
The basic indices evaluated as above are used to evaluate
SAIFI, SAIDI, CAIDI and AENS as given by relation 8,10,12, and 14
Table 8a
Population as obtained at the converged iteration along with values of objective function.
Decision Variables
#1
#2
#3
#4
#5
#6
#7
#8
#9
#10
k1
k2
k3
k4
k5
k6
k7
r1
r2
r3
r4
r5
r6
r7
Objective function, J 104
F/NF*
0.2215
0.1501
0.3951
0.3893
0.2642
0.0992
0.1460
6.1616
6.0016
5.5218
8.0227
7.1219
6.9751
7.4315
1.1796
F
0.2195
0.1600
0.3716
0.3933
0.2672
0.0978
0.1472
6.4672
6.0016
5.3490
8.0153
7.0767
7.3910
7.1725
1.1786
F
0.2324
0.1616
0.3264
0.3632
0.3000
0.0936
0.1497
6.0052
6.0174
5.0580
8.0009
7.0000
6.0009
17.9415
1.1769
F
0.2231
0.1646
0.3733
0.3843
0.2658
0.0872
0.1369
6.6341
6.0015
6.0633
8.0070
7.1101
6.6675
10.2842
1.1836
F
0.2331
0.1789
0.3104
0.3430
0.2845
0.0920
0.1483
6.0033
6.0767
6.1595
8.0100
7.0643
9.2649
8.3064
1.1701
F
0.2312
0.1619
0.3286
0.3683
0.3000
0.0920
0.1495
6.0006
6.0013
6.8840
8.0004
7.0001
6.0009
17.9447
1.1768
F
0.2200
0.1639
0.3381
0.3928
0.2492
0.1065
0.1490
6.4915
6.2205
5.1022
8.0366
7.1857
6.9686
6.8025
1.1818
F
0.2247
0.1683
0.3320
0.3749
0.2922
0.0890
0.1448
6.0185
6.2610
5.0691
8.0115
7.0374
6.5093
8.1343
1.1757
F
0.2328
0.1576
0.3283
0.3702
0.3000
0.0914
0.1500
6.0033
6.0095
7.7476
8.0009
7.0000
6.0000
17.9345
1.1774
F
0.2333
0.1575
0.3296
0.3628
0.3000
0.0956
0.1500
6.0096
6.0004
5.8432
8.0012
7.0010
6.0014
17.9507
1.1772
F
615
Index
Current values
1
2
3
4
SAIFI interruptions/customer
SAIDI h/customer
CAIDI h/customer interruption
AENS kW h/customer
0.6610
7.2671
10.9933
22.2334
Fig. 7. Variation of best value of objective function (J) with population size 5 in PSO,
CAPSO and population size 10 in DE.
Optimized values
Threshold values
DE
PSO
CAPSO
0.4997
3.0731
6.1495
9.0454
0.5000
3.3297
6.6595
9.9999
0.5000
3.2324
6.4648
9.8024
0.5000
4.0000
8.0000
10.0000
Fig. 9. Variation of best value of objective function (J) with population size 20 in
PSO, CAPSO and DE.
8. Conclusions
This paper has presented a methodology for reliability design of
a radial distribution system in the presence of distributed generation. An optimization problem has been formulated which obtains
optimum failure rates and repair times of each section subject to
satisfaction of inequality constraints based on energy and customer based reliability indices. Operating philosophy of DG has
been assumed in standby mode and cost of purchased energy is
more than that supplied from distribution substation. Formulated
problem has been solved using two most robust and popular population based algorithm, i.e. DE and PSO. The solution has also been
obtained using CAPSO, one of the variant of PSO. The results obtained have been compared. PSO requires less CPU time (population size 5) even with less population size than used in DE
(population size 10). It was also observed that CPU time required
for convergence increases with population size for all the three
techniques. It was also observed that for population size twenty
CPU time required by DE is less than that required by PSO.
References
Fig. 8. Variation of best value of objective function (J) with population size 10 in
PSO, CAPSO and DE.
616
[6] Sallam AA, Desouky M, Desouky H. Evaluation of optimal reliability indices for
electrical distribution systems. IEEE Trans Reliab 1990;39(1):25964.
[7] Chang WF, Wu YC. Optimal Reliability design in an electrical distribution
system via polynomial-time algorithm. Int J Electr Power Energy Syst
2003;25:65966.
[8] Chowdhury AA, Custer DE. A value based probabilistic approach to designing
urban distribution systems. Int J Electr Power Energy Syst 2005;27:64755.
[9] Bhowmik S, Goswami SK, Bhattacherjee PK. A new power distribution systems
planning through reliability evaluation technique. Electr Power Syst Res
2000;54:16979.
[10] Su CT, Lii GR. Reliability design of distribution systems using modied genetic
algorithms. Electr Power Syst Res 2002;60:2016.
[11] Arya R, Choube SC, Arya LD. A decomposed approach for optimum failure rate
and repair time allocation for radial distribution systems. J Inst Eng (India)
2009;Pt. El-Vol.89:38.
[12] Bae In-Su, Kim Jin-O. Reliability evaluation of distributed generation based on
operation mode. IEEE Trans Power Syst 2007;22(2):78590.
[13] Bae IS, Kim JO, Kim JC, Singh C. Optimal operating strategy for distributed
generation considering hourly reliability worth. IEEE Trans PS 2004;19(1):
192287.
[14] Louit D, Pascul R, Benjevic D. Optimal interval for major maintenance actions
in electric distribution networks. Int J Electr Power Energy Syst 2009;31(78):396407.
[15] Costa PM, Matos MA. Assessing the contribution of micro grids to the
reliability of distribution network. Electr Power Syst Res 2009;79:3829.