Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Task Name
Duration
383 days
10 days
2 days
2 days
3 days
3 days
2 days
41 days
3 days
2 days
1 wk
2 wks
2 wks
2 wks
1 wk
35 days
2 wks
2 days
4 days
4 days
4 days
4 days
5 days
1 day
7 days
7 days
1 day
3 days
3 days
1 day
54 days
2 wks
2 wks
2 wks
2 wks
2 wks
Start
Mon 4/1/13
Mon 4/1/13
Mon 4/1/13
Mon 4/1/13
Wed 4/3/13
Sat 4/6/13
Wed 4/10/13
Fri 4/12/13
Fri 4/12/13
Tue 4/16/13
Thu 4/18/13
Thu 4/25/13
Thu 4/25/13
Thu 5/9/13
Thu 5/23/13
Thu 5/23/13
Thu 5/23/13
Thu 5/23/13
Thu 6/6/13
Sat 5/25/13
Thu 5/30/13
Tue 6/11/13
Sat 6/15/13
Tue 6/4/13
Wed 6/5/13
Fri 6/21/13
Thu 6/13/13
Sat 6/29/13
Fri 6/14/13
Tue 6/18/13
Wed 7/3/13
Wed 7/3/13
Wed 7/17/13
Wed 7/17/13
Wed 7/31/13
Wed 8/14/13
Finish
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 1
W T F S
Fri 6/20/14
Thu 4/11/13
Install temporary power
Tue 4/2/13
Tue 4/2/13 Install temporary water service
Set up site office
Fri 4/5/13
Set line and grade benchmarks
Tue 4/9/13
Prepare site - lay down yard and tempo
Thu 4/11/13
Wed 5/29/13
Mon 4/15/13
Stone site
Wed 4/17/13
Wed 4/24/13
Wed 5/8/13
Wed 5/8/13
Wed 5/22/13
Wed 5/29/13
Tue 7/2/13
Wed 6/5/13
Fri 5/24/13
Mon 6/10/13
Wed 5/29/13
Mon 6/3/13
Fri 6/14/13
Thu 6/20/13
Tue 6/4/13
Wed 6/12/13
Fri 6/28/13
Thu 6/13/13
Tue 7/2/13
Mon 6/17/13
Tue 6/18/13
Tue 9/3/13
Tue 7/16/13
Tue 7/30/13
Tue 7/30/13
Tue 8/13/13
Tue 8/27/13
Task
ID
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
Task Name
Duration
Start
Finish
Wed 8/28/13
Tue 9/3/13
Wed 7/31/13 Thu 10/31/13
Wed 9/4/13
Mon 9/9/13
Wed 7/31/13
Mon 8/5/13
Tue 9/10/13
Fri 9/13/13
Sat 9/14/13
Sat 9/21/13
Mon 9/23/13
Tue 9/24/13
Mon 9/23/13
Fri 9/27/13
Mon 9/23/13
Fri 9/27/13
Sat 9/28/13
Wed 10/2/13
Thu 10/3/13 Thu 10/10/13
Fri 10/11/13
Sat 10/12/13
Fri 10/11/13 Wed 10/16/13
Fri 10/11/13 Wed 10/16/13
Thu 10/17/13 Mon 10/21/13
Tue 10/22/13 Tue 10/29/13
Wed 10/30/13 Thu 10/31/13
Wed 9/25/13
Sat 9/28/13
Wed 9/25/13
Tue 10/1/13
Wed 9/25/13
Tue 10/1/13
Wed 9/25/13
Sat 9/28/13
Thu 10/17/13 Mon 10/21/13
Tue 10/22/13 Tue 10/29/13
Wed 10/30/13 Thu 10/31/13
Fri 11/1/13 Thu 11/21/13
Fri 11/1/13 Thu 11/21/13
Wed 8/14/13
Thu 1/2/14
Fri 11/1/13 Thu 11/28/13
Wed 8/14/13
Tue 9/10/13
Fri 11/22/13 Thu 12/26/13
Fri 12/27/13
Sat 12/28/13
Fri 11/29/13 Thu 12/12/13
Fri 12/27/13
Thu 1/2/14
Fri 12/13/13 Thu 12/19/13
Fri 12/27/13
Mon 2/3/14
Fri 12/27/13 Tue 12/31/13
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 2
ID
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
Task Name
Duration
2 days
5 days
5 days
2 wks
72 days
5 wks
5 wks
2 wks
3 wks
96 days
3 wks
4 wks
3 wks
3 wks
2 wks
2 wks
2 wks
4 wks
3 wks
2 wks
2 wks
48 days
4 wks
2 wks
2 wks
108 days
4 wks
2 wks
3 wks
2 wks
150 days
4 wks
4 wks
3 wks
3 wks
2 days
Start
Wed 1/1/14
Thu 1/9/14
Wed 1/15/14
Tue 1/21/14
Fri 12/27/13
Fri 12/27/13
Fri 1/31/14
Fri 3/7/14
Fri 12/27/13
Fri 1/31/14
Fri 3/7/14
Fri 3/28/14
Fri 1/31/14
Fri 3/7/14
Fri 3/28/14
Fri 4/11/14
Fri 4/11/14
Fri 4/25/14
Fri 4/25/14
Fri 4/25/14
Fri 5/9/14
Wed 9/11/13
Wed 9/11/13
Wed 10/9/13
Wed 10/23/13
Fri 1/3/14
Fri 1/31/14
Fri 1/3/14
Fri 2/28/14
Fri 4/25/14
Fri 11/1/13
Fri 11/1/13
Fri 1/31/14
Fri 2/21/14
Fri 3/14/14
Fri 3/14/14
Finish
Thu 1/2/14
Tue 1/14/14
Mon 1/20/14
Mon 2/3/14
Thu 3/20/14
Thu 1/30/14
Thu 3/6/14
Thu 3/20/14
Thu 1/16/14
Thu 5/22/14
Thu 3/27/14
Thu 4/24/14
Thu 2/20/14
Thu 3/27/14
Thu 4/10/14
Thu 4/24/14
Thu 4/24/14
Thu 5/22/14
Thu 5/15/14
Thu 5/8/14
Thu 5/22/14
Tue 11/5/13
Tue 10/8/13
Tue 10/22/13
Tue 11/5/13
Thu 5/8/14
Thu 2/27/14
Thu 1/16/14
Thu 3/20/14
Thu 5/8/14
Thu 4/24/14
Thu 11/28/13
Thu 2/27/14
Thu 3/13/14
Thu 4/3/14
Sat 3/15/14
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 3
ID
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
Task Name
Duration
2 wks
206 days
2 wks
4 wks
2 wks
3 wks
4 wks
71 days
1 wk
4 days
4 days
1 day
21 days
3 days
1 day
1 day
1 day
2 wks
2 days
1 day
1 day
Start
Fri 4/11/14
Wed 9/11/13
Wed 9/11/13
Fri 11/1/13
Fri 1/31/14
Fri 1/31/14
Fri 4/11/14
Fri 3/7/14
Fri 3/7/14
Fri 3/14/14
Fri 5/23/14
Wed 5/28/14
Wed 5/28/14
Wed 5/28/14
Sat 5/31/14
Mon 6/2/14
Tue 6/3/14
Wed 6/4/14
Wed 6/18/14
Wed 6/18/14
Fri 6/20/14
Finish
Thu 4/24/14
Thu 5/8/14
Tue 9/24/13
Thu 11/28/13
Thu 2/13/14
Thu 2/20/14
Thu 5/8/14
Wed 5/28/14
Thu 3/13/14
Tue 3/18/14
Tue 5/27/14
Wed 5/28/14
Fri 6/20/14
Fri 5/30/14
Sat 5/31/14
Mon 6/2/14
Tue 6/3/14
Tue 6/17/14
Thu 6/19/14
Wed 6/18/14
Fri 6/20/14
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 4
Apr 7, '13
S M T
May 5, '13
S M T
orary fencing
Clear and grub site
e access and temporary parking area
Rough grade site (cut and fill)
Install storm drainage
Install exterior fire line and building fire riser
Perform final site grading
Erect building batter boards and layout build
Excavate foundatio
Excavate elevator
Rough-in electric and plumbing
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 5
Apr 7, '13
S M T
May 5, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 6
Apr 7, '13
S M T
May 5, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 7
Apr 7, '13
S M T
May 5, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 8
Jun 2, '13
S M T
Jun 9, '13
S M T
lding
ions
r pit
Form column piers and spread foundations
g in elevator
Form elevator pit walls
Set reinforcing and anchor bolts
Pour column piers and foundations
Pour concrete elevator walls
Cure elevator wall concrete
Cure piers and foundations
Strip wall forms
Strip column piers and foundation forms
Install pneumatic tube in elevator pit
Prepare and pour concrete floor in elevator pit
Erect steel columns, beams and joist - 1st and 2nd floors
Erect steel c
Install miscell
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 9
Jun 2, '13
S M T
Jun 9, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 10
Jun 2, '13
S M T
Jun 9, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 11
Jun 2, '13
S M T
Jun 9, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 12
Jul 7, '13
S M T
Aug 4, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 13
Jul 7, '13
S M T
Aug 4, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 14
Jul 7, '13
S M T
Aug 4, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 15
Jul 7, '13
S M T
Aug 4, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 16
'13
T
Sep 1, '13
S M T
Sep 8, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 17
'13
T
Sep 1, '13
S M T
Sep 8, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 18
'13
T
Sep 1, '13
S M T
Sep 8, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 19
'13
T
Sep 1, '13
S M T
Sep 8, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 20
Oct 6, '13
S M T
Nov 3, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 21
Nov
S
Oct 6, '13
S M T
Nov 3, '13
S M T
Nov
S
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 22
Oct 6, '13
S M T
Nov 3, '13
S M T
t in mechanical room
Test and align doors and equipment
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 23
Nov
S
Oct 6, '13
S M T
Nov 3, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 24
Nov
S
17, '13
M T
Dec 1, '13
S M T
Dec 8, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 25
17, '13
M T
Dec 1, '13
S M T
Dec 8, '13
S M T
or masonry work
Install roof drains
Install tile in toilet rooms
Clean masonry
Clean toilet room tile
Install flashing at parapet walls
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 26
17, '13
M T
Dec 1, '13
S M T
Dec 8, '13
S M T
W
Instal
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 27
17, '13
M T
Dec 1, '13
S M T
Dec 8, '13
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 28
Jan 5, '14
S M T
Feb 2, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 29
Feb 9, '14
S M T
Jan 5, '14
S M T
Feb 2, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 30
Feb 9, '14
S M T
Jan 5, '14
S M T
Feb 2, '14
S M T
Feb 9, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 31
Jan 5, '14
S M T
Feb 2, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 32
Feb 9, '14
S M T
Mar 2, '14
S M T
Mar 9, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 33
Mar 2, '14
S M T
Mar 9, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 34
Mar 2, '14
S M T
Mar 9, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 35
Mar 2, '14
S M T
Mar 9, '14
S M T
Set HVA
Install hard tile flooring in common areas
Clean hard tile floors
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 36
Apr 6, '14
S M T
May 4, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 37
Apr 6, '14
S M T
May 4, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 38
Apr 6, '14
S M T
May 4, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 39
Apr 6, '14
W T F S S M T W T
Install light fixtures - test and clean
May 4, '14
S M T
Co
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 40
Jun 1, '14
S M T
Jun 8, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 41
Jun 1, '14
S M T
Jun 8, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 42
Jun 1, '14
S M T
Jun 8, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 43
Jun 1, '14
S M T
Jun 8, '14
S M T
Task
Rolled Up Task
External Tasks
Critical Task
Project Summary
Progress
Rolled Up Milestone
Group By Summary
Milestone
Rolled Up Progress
Deadline
Summary
Split
Page 44