Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Ganda M. Simangunsong
GMS
Introduction
There are two reasons to go underground and
excavate:
1. to use the excavated space, e.g. for storage,
transport etc.
2. to use the excavated material, e.g. mining and
quarrying operations.
In both cases tunneling forms an integral part of the
entire operation.
The main difference between tunnel blasting and
bench blasting is that tunnel blasting is done towards
one free surface while bench blasting is done towards
two or more free surface.
GMS
Introduction (cont.)
Underground vs. Open Pit Blast Design:
One free face explosive consumption is higher than
open pit blast design
Environmental constraint toxic fumes
Small burden at area of Cut Desensitization 75200 mm; and sympathetic detonation <75mm
Explosive charge at LIFTER should be water resistant.
CONTOUR should be smooth blasting
GMS
Introduction (cont.)
GMS
Introduction (cont.)
GMS
Blasting Round
GMS
Look Out
Empirical guidance
L = 10 cm + 3 cm/m X Hole depth
GMS
CUT
Various types of Cut (Langefors & Kihlstrm, 1978)
Wedge cut or V-cut
Pyramid or diamond cut
Drag cut
Fan cut
Burn cut
GMS
GMS
Drag Cut
The drag cut is particularly suitable in small sectional
drifts where a pull of up to 1 m is very useful
GMS
Fan Cut
The fan cut is one-half
of a wedge cut and is
applicable mainly where
only one machine is
employed in a narrow
drive.
Generally the depth of
pull obtainable is limited
to 1.5 m
GMS
Burn Cut
A series of parallel holes are
drilled closely spaced at right
angles to the face. One hole or
more at the centre of the face
are uncharged. This is called the
burn cut.
Rock factor, c
The rock constant is an empirical measure of the
amount of explosive needed for loosening 1 m 3 of rock
B
Example
= 32 mm
Q = 0.3 kg/m3
C = 1.2Q = 0.36
B=K= 0.5-1.0 m
1.3B
0-1 m
GMS
Rock Factor, c
c?
t?
RMR ?
C = 0.50 + 2.60(t/c)0.5 + 13t/c, kg/m3
For first trial C=0.4 kg/m3
GMS
Example:
Persson, Holmberg, Lee
GMS
Process (cuts)
Define reamer/
uncharged hole
Define 1st cut
Define 2nd cut and
others
A2
B2
A1
B1
GMS
4.
5.
Define advance, I
Define hole depth, H (I = 95%H)
Define reamer
H = 0.15 + 34.1 39.42
Smaller diameter of reamer can be adopted with
number of reamers is estimated as follow,
d = /n0.5
Define charge concentration (explosive type and
diameter), l
l ANFO?
Difine first burden, B1
l = 55d [(B1/)1.5 (B1-/2)(c/0.4)]/WSRANFO
GMS
7.
GMS
2.
3.
4.
5.
6.
GMS
Process (Lifters)
1.
2.
3.
3.
4.
5.
Process (Stoping)
1.
2.
3.
3.
4.
5.
GMS
Process (Contours)
If normal, follow geometry of the downward stoping
If smooth blasting is required, :
1. Define spacing, S
S = (15-16) d
2. Defind burden, B
B = S/0.8
3. Defind charge concentration, l
l = 90 d2
4.
5.
GMS
Hole types
Number
of holes
Charge per
hole
Total
charge
1st cut
1.59
6.37
2nd cut
2.62
10.48
3rd-4th cut
3.76
29.36
Lifters
3.20
16.00
Roof
1.77
14.16
Wall
3.20
19.20
Stoping
3.20
16.00
Total charge
111.6 kg
Opening area
19.5 m2
Advance
3.0 m
Specific charge
1.9 kg/m3
40
Hole depth
3.2 m
Specific drilling
2.2 m/m3
GMS
Example:
Stig O. Olofsson
Swedish Technique
GMS
D = dn
D = diameter lubang samaran
d = diameter lubang kosong
n = jumlah lubang
GMS
GMS
Perhitungan
Agar peledakan berhasil dengan baik (cleaned blast),
jarak antara lubang ledak dengan lubang kosong,
tidak boleh lebih besar daripada 1,5 lubang kosong.
Apabila jaraknya lebih besar hanya akan menimbulkan
kerusakan (breakage) dan jika jaraknya terlalu dekat
ada kemungkinan lubang ledak bertemu dengan
lubang besar kosong
GMS
Waktu tunda:
Hole depth 4 m
Clean Blast 60 100 ms
Stoping 100 500 ms
Antar cut utk V > 50 ms
a = 1,5 D
D = diameter samaran
GMS
GMS
GMS
B=W
GMS
Stemming Cut
Panjang kolom lubang bor yang tidak diisi bahan peledak.
ho = 0,5 B
Perhitungan berikut utk lubang tembak 38 mm
GMS
Merencanakan Cut
Bujursangkar I
a
= 1,5
W1 = a 2
mm
76
a mm
W 1 mm
mm
76
W 1 mm
C C = 1,5 W1
C-C mm
W2 = 1,5 W1 2
W 2 mm
Bujursangkar II
B1
= W1
89
89
GMS
Merencanakan Cut
Bujursangkar III
B2 = W2
C C = 1,5 W2
W3 = 1,5 W2 2
Bujursangkar IV
B3
= W3
C C = 1,5 W3
W4 = 1,5 W3 2
mm
76
102
127
159
W 2 mm
560
670
CC
840
1.000
W 3 mm
89
mm
76
102
127
159
W 3 mm
560
670
CC
840
1.000
W 4 mm
89
GMS
Geometri Bujursangkar
GMS
GMS
GMS
Spacing
(m)
Height bottom
charge
(m)
Bottom
(kg/m)
(Column)
(kg/m)
Floor
1xB
1.1 x B
1/3 x H
lb
1.0 x lb
0.2 x B
Wall
0.9 x B
1.1 x B
1/6 x H
lb
0.4 x lb
0.5 x B
Roof
0.9 x B
1.1 x B
1/6 x H
lb
0.3 x lb
0.5 x B
Upwards
1xB
1.1 x B
1/3 x H
lb
0.5 x lb
0.5 x B
Horisontal
1xB
1.1 x B
1/3 x H
lb
0.5 x lb
0.5 x B
Downwards
1xB
1.2 x B
1/3 x H
lb
0.5 x lb
0.5 x B
Part of time
round
Stemming
(m)
Stoping :
GMS
Number of Holes
Check
Recheck!
GMS
Specific Charge
Check
Recheck!
GMS
Initiation Sequence
GMS
GMS
GMS
Shafts
Shafts are either driven downwards, sink
shafts/shaft sinking, or upward, raise shafts.
GMS
Shaft Sinking
Shaft sinking is one of the most difficult and risky blasting
jobs as the work area is normally wet, narrow, and noisy.
Furthermore, the drilling and blasting crews are exposed to
falling objects.
The advance is slow as the rock has to be removed
between each blast with special equipment which has
limited capacity. The blasted rock must be well fragmented
to suit the excavation equipment.
The design of the cross section of the shaft principally
depends on the quality of the rock. Nowadays most of the
shaft are made with circular cross section which gives
better distribution of the rock pressure, thus decreasing the
need for reinforcement, especially in deep shafts.
GMS
Shaft Sinking
An important requirement in shaft
sinking is to provide optimum
fragmentation of the rock so that
it can be cleared quickly from the
congested shaft-face area.
Blasting operation is carried out
against gravity, and the scatter of
the broken rock is confined in the
shaft. It is common to use
generous distribution of
explosives hroughout the rock
using a large number of small
diameter (35 42 mm) shotholes.
GMS
Shaft Sinking
Shaft Sinking
with pyramid cut
GMS
Shaft Sinking
with pyramid cut
Shaft Sinking
The explosives used in shaft sinking must always be
water resistant. Even if the ground is dry, the flushing
water from the drilling machines will always stay in
the blastholes.
The powder factor in shaft sinking is rather high,
ranging from 2.0 kg/m3 to 4.0 kg/m3 (Olofsson).
Nonel type detonators are increasingly preferred for
initiation.
GMS
Raise Shafts
Older methods:
Timbered shafts
Open shafts up to 25 m, not recommended
Modern methods:
Boliden elevator type Jora
Alimak Raise Climber
Longhole drilling
GMS
Timbered Shaft
The rise shaft is driven vertically
and divided into two sections by
a timber wall which is extended
before each blast.
When the round is fired, one
section is filled with rock. The
blasted rock will then act as a
working platform for the next
round.
The second section is used as
ladder-way and for
transportation of equipment, drill
steel, explosive and timber. The
ventilation is also placed which is
covered during blasting.
GMS
Timbered Shaft
Timbered rise shafts have
been driven up close to 100
m, but normally the
maximum height should not
exceed 60 m.
The cross section area is
usually 4 m2, and the
advance per round approx.
2.2 m.
GMS
GMS
GMS
Shaft raising
by long hole drilling
GMS
GMS
GMS
Livingstones theories:
L = 6 x D (mm)
Lopt = 0.5 x Lcrit (mm)
Lcrit = S x Q1/3; (mm);
S : Strain energy (1.5)
Q = (3 x d3 x phi x P)/2; kg;
P : Charging density (kg/liter)
Lopt = 0.5 x S x ((3 x phi x d)/2) 1/3 x d x 10 (mm)
GMS
Ring Blasting
GMS
Ring Blasting
GMS
Ring Blasting
GMS
Ring Blasting
Design Example
GMS
Ring Blasting
Design Example
GMS
Ring Blasting
Design Example
GMS
Ring Blasting
GMS
Blast Damage
GMS
GMS
Overbreak Extend
GMS
GMS
Measuring EDZ
There are currently three methods of actually measuring
excavation profiles:
surveying techniques,
laser based, and
GMS
Measuring EDZ
GMS
Measuring EDZ
using PPF and Q
PPF = (Pe.Ee)/Vrp
PPF : Perimeter Powder Factor (PPF)
GMS
Measuring EDZ
EDZo = (-a + b.PPF c.log Q)/100
Polynomial 2D
Model First
Order
i n
bo n b1
i 1
i i
i n
bo
i 1
i n
b2
y i z i bo
b1
i 1
i 1
i 1
i n
i n
i 1
i 1
i n
x z
i n
i 1
i n
xi2
b2
x y
i
i 1
i n
y i b1
i n
xi y i b2
i 1
y i2
i 1
x y bo z
2
x
xy b1 xz
2 b
x
y
y
2 yz
GMS
Measuring EDZ
using PPV
PPV = k (R/W1/3)-n
GMS
PPV (mm/s)
635 2540
Notes
305 610
635
1000 - 3000
Rock damage
600
Major damage
Bogdanhoff (1996)
2000 - 2500
2050
Tunnel damaged
GMS
(a) Major damage: fall of rock/coal blocks from roof and/or pillars.
(b) Minor damage: detachment of loosened chips from roof and/or pillars.
(c) No damage: no visual damage.
GMS
Supplement
GMS
GMS
GMS
GMS
GMS
Bieniawski (1989)
GMS
Discussion .
END
GMS