PROCUREMENT SCHEDULE

Sl.No

Description

HVAC

Jet Fans

Axial Fans

Fan Coil Units


i 1st Lot
ii 2nd Lot
iii 3rd Lot
iv 4th Lot

Inline Fans
1st Lot
2nd Lot

CSU
1st Lot
2nd Lot

Cable Trays

Cables

Outdoor Units
1st Lot
2nd Lot

AHU's
1st Lot
2nd Lot
3rd Lot
4th Lot

10

Cooling Towers

11

Condenser Pumps

12

SPU

13

Toilet Exhaust Fans

14

Lift Well Pressurization Units

15

Lift Lobby Pressurization Units

16

VAU

17

Make Up Tank

18

Primary Pumps

19

Secondary Pumps

20

Ducts
1st Lot
2nd Lot
3rd Lot
4th lot

21

HVAC Related Electrical Panels

Electrical

PVC conduits
i 1st Lot
ii 2nd Lot
iii 3rd Lot
iv 4th Lot

M S Conduits

PVC Wires
i 1st Lot
ii 2nd Lot
iii 3rd Lot
iv 4th Lot
v 5th Lot

Switches & Sockets


i 1st Lot
ii 2nd Lot
iii 3rd Lot
iv 4th Lot
v 5th Lot

Cable Trays
i 1st Lot
ii 2nd Lot

DURATION

START

FINISH

Earth Flats
i 1st Lot
ii 2nd Lot

Distribution Boards
i 1st Lot
ii 2nd Lot
iii 3rd Lot
iv 4th Lot
v 5th Lot

HT Cables

LT Cables

10

LT Panels

11

Raising Mains

12

Light Fixtures
i 1st Lot
ii 2nd Lot
iii 3rd Lot
iv 4th Lot
v 5th Lot

13

RMU

14

Transformer

15

HT Panels

PHE

Sanitary Items

CP Fittings

CPVC & UPVC Pipes & Fittigns


i 1st Lot
ii 2nd Lot
iii 3rd Lot
iv 4th Lot

Valves
i 1st lot
ii 2nd Lot

Hume Pipes

DI Fram & Covers

Monoblock Pumps

Submersible pumps

Booster pumps

10

Power Cables & Electrical accessoriers

11

WTP filters (PSF, ACF, Softner)

12

Filter feed pump

13

Chlorine doser

FIRE PROTECTION & DETECTION SYSTEM

Pipes & Accessorries


i Lot 1
ii Lot 2
iii Lot 3

Sprinklers
3 Valves
i 1st Lot
ii 2nd lot

Fire Extinguishers

Smoke & Heat Detectors

Isolator & Control Modules


i 1st Lot
ii 2nd lot

FAS cables
i 1st Lot
ii 2nd lot

PA cables

Speakers
Pump Room Equipments

10

Hydrant & Sprinkler Pumps

11

Engine & Jockey pump

12

Electrical Cables,Trays,Panel

13

Valves

BMS SYSTEMS

Field Devices

PVC Conduits

Cables

UPS 20KVA

UPS Panel

Distribution Boards

Switches & Sockets

DDC Panels

PC & Software

CCTV System:

DVR

Co Axial Cables

TFT Monitors

CCTV Cameras

Camera Poles

PVC Conduits

Access Control System:

Access Controller

EM Lock

Card Readers

Egress Switch

Cables

PVC Conduits

PA System:

Volume Alarm Controller

Amplifier

Call Station

DVD

5
6

PVC Wire
PVC Conduits

Speakers

CONSTRUCTION SCHEDULE
Sl.No

Description

BASEMENT
1

Electrical
i Setting out
ii Conduiting & Wiring
iii DB fixing & Terminations
iv Lighting Fixtures Installation

HVAC
i Setting out
ii Cable tray installation (for JetFans)
iii Jet Fan Installations
iv Exhaust ducting (Maintenance room)
v Axial Fan Installations
vi Ventilation system cabling & Isolations

Fire
i Setting out
ii Sprinkler Piping Installation
ii Pressure Testing

PHE
i Setting out
ii Scupper drain Piping
iii Sump Pump - Piping
iv Sump Pump Installations

IBMS & LV First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i MEP First Fix - Finishes clearence (ceiling + wall)
ii MEP Second Fix

Lift Lobbies
i MEP First Fix - Finishes clearence (ceiling + wall)
ii MEP Second Fix

GROUND FLOOR
1

Electrical
Painting
i Conduiting & Wiring
ii DB fixing & Terminations
iii Lighting Fixtures Installation

HVAC
i Kitchen Exhaust Ducting
ii Kitchen Fresh Air Ducting
iii VAU & EAU Installations
iv VAU & EAU Electrical Works
Painting
v AHU Installations
vi Valve Packages & Drain Installations
vii 24 TR CSU Installation
viii CSU CHWP Installations

IBMS & LV First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i MEP First Fix - Finishes clearence (ceiling + wall)
ii MEP Second Fix

Main Entrance Works


i MEP First Fix - Finishes clearence (ceiling + wall)
ii MEP Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

Sl.No

Description
ii Pressure Testing

EXTERNALS
1

Substation
i Substation Civil Works
iii External Equipment Installations
iv Internal Panel Installations & Cabling
v Cable Terminations
ii Bescom Liaison/Power connection works

DG Yard & Diesal Tank


i DG Yard Civil Works
ii Diesal Tank Civil works
iii DG Installations
iv DG Exhaust Stack
v Diesal Tank Installation
vi Diesal pumps and piping Works

Transformer Yard
i Transformer yard civil works
ii Transformer Installations
iii Panel Installations, Cabling & Terminations

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

Sl.No

Description

SEWAGE TREATEMENT PLANT


i Equipment installations & Piping works
ii Panel Installation & Electrical Works
UG SUMP & PLANT ROOM
i UG sump civil works
ii Fire pump installations
iii Fire Piping & accessories installations
iv Fire Panel Installation & Electrical Works
v WTP Equipment/Pump Installations
vi WTP Piping installations
vii WTP Electrical Installations
FIRST FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

2ND FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

3RD FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

Sl.No

Description
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

4TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

5TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

Sl.No

Description

6TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

7TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

8TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

Sl.No

Description
i Sprinkler Piping Installation
ii Pressure Testing

9TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

10TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Sprinkler Piping Installation
ii Pressure Testing

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

Sl.No

Description

11TH FLOOR
1

AHU Rooms
Painting
i AHU Installation
ii Valve Package Installations

Elec Rooms
Painting
i Conduiting & wiring
ii DB Fixing & Terminations
iii Lighting Fixtures Installation

IBMS First Fix - cabling & conduiting


ii IBMS & LV Devices Fixing

Toilets
Block Work
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Lift Lobbies
i First Fix - Finishes clearence (ceiling + wall)
ii Second Fix

Sprinkler & Fire Alarm for Office Areas


i Services Corridor
i Sprinkler Piping Installation
ii Pressure Testing

Cooling Tower Area - HVAC works


i Cooling tower & chiller civil Foundations
iii Chiller Installations
ii Cooling tower installation
iv Pumps installations
v Piping Works & Valve installations
vi Panel & cable tray installations (HVAC)
vii Cabling & Terminations (HVAC)
viii Cable tray works (Sequent)
ix Cabling & Terminations (Sequent)

Cooling tower Area Acoustic Works

TERRACE FLOOR
MEP Related Civil works(Pedestals,shaft
finises etc)
1

HVAC Works
i Liftwell Pressurization Fan & Ducting
ii Stair case Pressurization Fan & Ducting
iii Toilet Exhaust Fan & Ducting
iv AHU Fresh Air Fan & Ducting
v Chiller Installations
vi CHW Pump Installations
viii CHW Piping & Valve installations
vii Chiller Isolator & Cable tray works
ix Cabling & Terminations
x STP Exhaust Fan & Ducting
xi Kitchen Exhaust Fans & Ducting

PHE works
i Water supply piping & support works
ii Booster pump installations & valves
iii Level controller installations & cabling works
iv Electrical works & terminations

Electrical works
i Terrance Lighting & Power works
ii Lighting Arrestor works

IBMS Cabling and termination works

Fire
i Pumps installations
ii Pipe lines

LIFTS

MEP SHAFTS
i Electrical - 1,2

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

Sl.No

Description
ii Fire - 1,2,3
iii Toilet Exhaust - 1,2
iv PHE -1,2
v RWP - 1,2,3
vi LV-1,2
vii CHWP-1,2

viii Pressurization shafts 1, 2, 3


ix STP Exhaust
x Kitchen Exhaust
TESTING & COMMISSIONING
i Substation Testing
ii Substation commissioning
iii Upper Basment LT Panels
iv DG sets Testing
v DG sets Commissioning
vi Transformers
vii STP
viii UG Sump & Fire Sump
ix Rising Mains
x Basement Ventilation System
xi Floor wise - MEP systems (AHU/Toilets/Lobbies)
xii Terrace Equipments(Incl of SPU)
xiii Lifts
xiv IBMS

DURATION

TOWER C
START

FINISH

DURATION

TOWER D
START

PROCUREMENT SCHEDULE

CONSTRUCTION SCHEDULE
TOWER D
FINISH

TOWER D
FINISH

TOWER D
FINISH

TOWER D
FINISH

TOWER D
FINISH

TOWER D
FINISH

TOWER D
FINISH

TOWER D
FINISH

Sl.No

Description

Dec-13
DURATION

UPPER BASEMENT
8

Main Electrical Room


i Cable Tray works

45

ii Panel Installations

30

iii Cabling

60

iv Terminations

30

EXTERNALS
1

Substation
i Substation Civil Works

75

iv Internal Panel Installations

45

v Substation Testing
ii Bescom Liaison/Power connection works
2

DG Yard & Diesal Tank


i DG Yard Civil Works

90

iii External Equipment Installations

35
180
.
75

iii DG Installations

75

iv DG Exhaust Stack

60

ii Diesal Tank Civil works

90

v Diesal Tank Installation

60

vi Diesal pumps and piping Works

60

Transformer Yard
i Transformer yard civil works

75

ii Transformer Installations

55

iii Panel Installations, Cabling & Terminations

28

SEWAGE TREATEMENT PLANT


i Equipment installations & Piping works
ii Panel Installation & Electrical Works

100
43

UG SUMP & PLANT ROOM


i UG sump civil works
ii Fire pump installations

45

iii Fire Piping & accessories installations

75

iv Fire Panel Installation & Electrical Works

30

v WTP Equipment/Pump Installations

60

vi WTP Piping installations

60

vii WTP Electrical Installations

30

TERRACE FLOOR
1

HVAC Works

PHE works

100
60

Electrical works

19

IBMS Cabling and termination works

31

Fire Hydrant piping & Hose Reel Installations

LIFTS

44
120

TESTING & COMMISSIONING


1

Substation Testing

29

Substation commissioning

15

Transformers

15

DG sets testing

45

DG sets Commissioning

24

Upper Basment Main Electrical Room

45

STP

UG Sump & Fire Sump

25

Rising Mains ( Tower A & B)

25

10

Basement Ventilation System

20

11

Floor wise - MEP systems (AHU/Toilets/Lobbies)

45

12

Terrace Equipments(Incl of SPU)

27

13

Lifts ( Tower A & B)

25

14

IBMS

45

STATUTORY APPROVALS & INSPECTIONS


i Fire Completion certificate

60

ii CEIG Approval for Lift

60

START

FINISH

1st

2nd

3rd

Jan-14
4th

1st

2nd

3rd

Feb-14
4th

1st

2nd

3rd

Mar-14
4th

1st

2nd

3rd

Apr-14
4th

1st

2nd

3rd

May-14
4th

1st

2nd

3rd

Jun-14
4th

1st

2nd

3rd

4th

1st

2nd

3rd

4th

1st

2nd

3rd

4th

1st

2nd

3rd

4th

1st

2nd

3rd

4th

1st

2nd

3rd

4th

iii CEIG Approval for Electrical

60

iv CEIG Approval for DG

60

v Approval for HSD

60

vi CFO - Air and water

60

vii Occupance certificate application

1st

2nd

3rd

4th

1st

2nd

3rd

4th

1st

2nd

3rd

4th