1. PURPOSE
To ensure that installation of GI Boxes & DB Enclosure fixing are executed safely and in accordance with the contract
requirements and that all quality assurance / control activities required for the same are conducted in a systematic
manner, works are inspected and conformance is verified and documented.
2. SCOPE OF WORKS/METHOD
2.1 This procedure is applicable to the following works associated with the project titled 72 GALLERY
TOWNHOUSES PHASE 2
3. REFERENCES
3.1 Approved material submittals:
3.2 Latest Approved Shop Drawings
3.3 Specification 16130, 16440
3.4 Inspection and Test plan.
4. DEFINITIONS
4
4.1 EMPLOYER:
4.2 ENGINEER:
DIAR CONSULTANT
4.3 CONTRACTOR:
4.6 HSE:
4.7 ITR:
4.8 ITP:
4.9 QA/QC:
5. SAFETY
Tool box talk has to be conducted all the hazards have to be identified before starting the work.
Personnel Protective Equipments (PPE) to be worn by the Task force during execution at site.
Clear the obstructions from the surrounding area to avoid Near misses and accidents.
Manufacturers recommendation has to be followed on health and safety if applicable.
Any Process adopted and may have a particular safety risk will be assessed and addressed as required.
6. RESPONSIBILITIES
6.1
Project Engineer
To be the focal point for interfaces and other communications with the ENGINEER and Contractors as
required during execution of work.
He shall ensure that adequate quality measures are being undertaken.
He shall ensure that the proper tools and tackles are available for the timely completion of the job in a quality
manner.
6.2
shall be responsible for the total quality control for installation work. He shall liaise with ENGINEER for
inspection of installations works.
Inspect for any damage during, handling and storage.
Monitor the quality of work & ensure that fulfillment of specified requirement and that all quality records
related to work are completed.
Ensure the work is completed as per quality requirements. Contractor shall inspect the same work prior to
initiate ITR for ENGINEER approval.
Maintain Comprehensive inspection and test records for any further documentation.
Reviews the Method Statement before starting the work, explains the same to the subordinates and
prepares program for the daily job. Aware of all code of practices, Standards & Specifications and HSE plan
and to appreciate the workforce to perform a time bound and quality job.
He shall originate ITR for completed installation works and companies.
6.3
7. PROCEDURE
7.1
Equipments:
7.2
Standard Hand tools Hack saw, File, Cutter, Drilling machine, Marker, Grinding machine, chisel, water
level, spirit level. etc.
Handling
During transportation, material must not be handled roughly, it should be protected properly with the covers.
Use of improper machinery / handling equipment for lifting must be avoided.
7.3
Transportation:
The transporting vehicle must ideally have a flat bed, free for any rough surfaces or corrugation.
7.4
Storage
Material should be stored in covered store with locking facility.
It should be protected from expose of the sunlight and entry of water.
7.5
Site Work:
4
7.5.1
GI Boxes fixing
7.5.2
DB Enclosure fixing
8. QA/QC PROCEDURE
All inspection / Testing as defined in related Inspection and Test Plan (ITP) shall be conducted. Related check
sheets shall be completed.
9. ATTACHMENTS
9.1 CHECK LIST FOR INSTALLATION OF G. I. BOXES & D.B. ENCLOSURE FIXING.
GI Boxes fixing
Drawing No:
Report No:
Location:
Date:
SL.
NO
1.
2.
3.
4.
5.
6.
STATUS
Accepte
d
Date
SubContract
or
Rejecte
d
Contract
or
Consulta
nt
BHATIA
DIAR
Remark
s
7.
8.
9.
REMARKS:
For CONTRACTOR
For CONSULTANT
QA/QC
DIAR
SITE ENGINEER
(ELECTRICAL)
SIGNATURE
NAME
DATE
DB Enclosure fixing
Drawing No:
Report No:
Location:
Date:
SL.
NO
1.
2.
3.
4.
5.
6.
STATUS
Accepte
d
Date
SubContract
or
Rejecte
d
Contract
or
Consulta
nt
BHATIA
DIAR
Remark
s
7.
8.
9.
REMARKS:
For CONTRACTOR
For CONSULTANT
QA/QC
DIAR
SITE ENGINEER
(ELECTRICAL)
SIGNATURE
NAME
DATE