Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
STANDARD SPECIFICATIONS
for
HIGHWAY BRIDGES
University of Michigan-Flint
9015
Library
OOI2JI2SF
FLINT COLtEGE
STANDARD SPECIFICATIONS
for
HIGHWAY BRIDGES
Adopted by
The American Association
of State Highway
FIFTH EDITION
Second Printing
June,
Published
1950
by the Association
General Offices
917 National Press Building
Washington, D. C.
19 4
Officials
Copyright, 1949, by
'i
.
'
42287
CONTENTS
ft (,
I General Provisions
Division
Division II Construction
Design
Division
Division IV Materials
Appendix A Tables of Moments and Shears, Standard Loadings
Appendix 15 Steel Column Formulas (special)
Appendix C Truck Train and Equivalent Loadings
(1935 Specifications for reference use.)
Appendix D Permissible Unit Concrete Stresses for Rectangular
Columns
Index
Page
6
25
III
DIVISION
1-1
-11
1138
242
248
Concrete
249
250
General Provisions
Article
1.1.1
SECTION
Definition of Terms
SECTION
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
1.2.0
1.2.7
1.2.8
1.2.9
1.2.10
1.2.11
1.3.2
1.3.3
1.3.4
1.3.5
1.3.0
1.3.7
1.4.1
1.4.2
1.4.3
1.4.4
1.4.5
1.4.0
1.4.7
1.4.8
1.5.1
1.5.2
1.5.3
1.5.4
1.5.5
1.5.0
1.5.7
1 .5.8
1.5.9
1.5.10
1.5.11
1 .5.12
2 Proposal Requirements
and
Conditions
SECTION 3 Award
1.3.1
Pace
1 Definition of Terms
8
8
8
9
9
9
9
9
9
9
9
Consideration of Bids
Award of Contracts
Return of Proposal Guaranty
Requirements of Contract Bond
Execution of the Contract
Approval of Contract
Failure to Execute Contract
10
10
10
10
10
10
10
10
11
11
11
11
11
11
12
12
12
12
18
13
13
13
14
14
14
14
15
CONTENTS
SECTION
Article
1.6.1
1.6.2
1.6.3
1.6.4
1.6.5
1.7.1
1.7.2
1.7.3
1.7.4
1.7.5
1.7.6
1.7.7
1.7.8
1.7.9
1.7.10
1.7.11
1.7.12
l.S.J
1.8.2
1.8.3
1.8.4
1.8.5
1.8.6
1.8.7
1.8.8
1.8.9
1.8.10
1.9.1
1.9.2
1.9.3
1.9.4
1.9.5
1.9.6
1.9.7
of Supply and
Tests of Materials
Storage of Materials
Source
Control
of Materials
Page
15
15
16
16
16
Quality
Defective Materials
Silence of Specifications
to Public
16
17
17
17
17
17
17
18
18
18
18
18
19
19
20
20
20
21
21
DIVISION
19
lit
21
21
21
22
22
23
23
24
II
Construction
2.1.6
2.1.7
2.1.8
2.1.9
2.1.10
2.1.11
2.1.12
2.2.1
General
2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
Fill
25
25
25
25
26
26
26
26
26
26
27
27
27
*
2i
28
CONTENTS
V
Page
Article
2.2.2
2.2.3
2.2.4
2.2.5
2.3.1
2.3.2
2.3.3
Materials
Design and Conditions of Use
Preparation for Driving
(a) Excavation
(b) Caps
(c) Collars
(d) Pointing
(e) Splicing Piles
(f) Painting Steel Piles
Methods of Driving
(a) General
fb) Hammers for Timber and Steel Piles
(c) Hammers for Concrete Piles
(d) Additional Equipment
(e) Leads
(f) Followers
(g) Water Jets
(h) Accuracy of Driving
Defective Piles
Determination of Bearing Values
Loading Tests
Timber Pile Formulas
Concrete and Steel Piles
Test Piles
Order Lists for Piling
Storage and Handling of Timber Piles
Cutting Off Timber Piles
Cutting Off Steel or Steel Shell Piles
Capping Timber Piles
Manufacture of Precast Concrete Piles
General
Class of Concrete
Form Work
(d) Reinforcement
(e) Casting
(f) Finish
(g) Curing
Storage and Handling of Precast Concrete Piles
Manufacture of Cast-in-Place Concrete Piles
(a) General
(b) Inspection of Metal Shells
(c) Class of Concrete
(d) Reinforcement
(e) Placing Concrete
Extensions or "Build-ups"
Painting Steel Piles and Steel Pile Shells
Measurement and Payment
(a) General
(b) Method A
(c) Method B
(d) Falsework and Defective Piles
(e) Additional Requirements
Payment for Test Piles
Payment for Loading Tests
29
29
29
29
29
29
29
30
30
30
30
30
30
30
30
30
31
31
31
31
31
31
32
32
32
33
33
33
33
33
33
33
33
33
33
34
34
34
34
34
34
34
34
34
35
35
35
35
35
36
36
36
37
37
37
37
37
38
38
39
28
28
29
29
2.3.4
c)b)
ia)
2.3.5
2.3.6
2.3.7
2.3.8
2.3.9
2.3.10
2.3.11
2.3.12
2.3.13
2.3.14
2.3.15
2.3.16
2.3.17
2.3.18
2.3.19
2.3.20
2.4.1
2.4.2
2.4.3
2.4.4
2.4.5
VI
Consistency
Measurement
of Materials
Mixing Concrete
(a J General
(b)
(c)
(d)
le)
()
Constant Cement
2.4.10
2.4.11
2.4.12
2.4.13
2.4.14
2.4.15
2.4.10
2.4.17
2.4.18
2.4.19
2.4.20
2.4.21
2.4.22
2.4.30
2.4.31
42
42
44
44
Plant Mix
(h) Delivery
(i) Reteinpering
Handling and Placing Concrete
(a^ General
ib) Culverts
(c) Girders, Slabs and Columns
(d) Arches
Pneumatic Placing
Pumping
Depositing Concrete Under Water
Construction Joints
(a) General
(b) Bonding
Rubble or Cyclopean Concrete
Concrete Exposed to Sea Water
Concrete Exposed to Alkali Soils or Alknli Water
Falsework and Centering
Forms
Removal of Falsework, Forms, and Housing
Concreting in Cold Weather
Curing Concrete
Expansion and Fixed Joints and Bearings
(a) Open Joints
(h) Filled Joints
(c) Steel Joints
(d) Water Stops
(e) Bearing Devices
Concrete
General
Class
Class
Class
Class
Class
Class
(a)
(b)
0, 5, 4, 3, 2, 1,
(i) Joints
:i) Bond
2.4.32
41
42
Mixing at Site
Truck Mixing
Partial Mixing at the Central Plant
Finishing
2.4.23
2.4.24
2.4.25
2.4.20
2.4.27
2.4.28
2.4.29
Pas*
actor 40
42
2.4.0
<<k) Curing
(1) Reinforcement
Measurement
and
Payment
43
43
44
44
44
44
44
40
40
47
47
48
48
49
4'J
49
49
49
50
50
50
51
52
52
52
52
53
53
.,.}
2.4.G
2.4.7
2.4.8
Surfaces
Finish
53
54
54
54
55
55
55
55
55
5o
5.)
50
50
50
50
50
50
50
57
j'<
Article
CONTENTS
57
57
57
57
57
57
5<
58
CONTENTS
Material
Order Lists
Protection of Material
Fabrication
Mesh Reinforcement
Bar Mat Reinforcement
Placing and Fastening
Splicing
happing
Substitutions
58
^j*
^
8
59
59
*!
J
60
2r
Measurement
Payment
Ashlar Masonry
Description
Materials
Size of Stone
Surface Finishes of Stone
Dressing Stone
Stretchers
J gj gj;>}
61
"f,
Headers
Cores and Backing
62
62
General
Face Stone
(<) Stone Backing and Cores
(d) Concrete Cores and Backing
Leveling Courses
Resetting
Dowels and Cramps
Copings
Arches
Pointing
Measurement
and Payment
7
SECTION Mortar
.>
Dry
SECTION
HH
"
O<
Rubble Masonry
67
67
*>8
OS
Brick Masonry
SECTION
g*>
gjjgj>gg
Description
Materials
Size of Stone
Headers
Shaping Stone
Laying Stone
Coping, Bridge Seats and Backwalls
Measurement and Payment
gi
2.8.1
2.8.2
2.8.3
2.8.4
2.8.5
2.8.6
2.8.7
2.8.8
2.9.2
2.9.3
9.4
2.9.5
64
*;
>>
Size
2.7.10
2.9.1
Rubble Masonry
Description
Materials
Headers
Shaping Stone
Laying Stone
Copings, Bridge Seats and Backwalls
Arches
Pointing
Measurement
and Payment
2.7.!)
63
gl
2.7.1
2.7.2
2.7.3
2.7.4
2.7.5
2.7.6
2.7.7
2.7.8
"2
g2
Stone
ggjj
Mortar
g<g<
Mixing
Laying
(a)
(b)
gj
2.6.11
2.6.12
2.0.13
2.0.14
2.6.15
2.0.10
2.0.17
SECTION
2.0.1
2.0.2
2.0.3
2.6.4
2.6.5
2.0.0
2.0.7
2.0.8
2.6.9
2.6.10
p"8e
Description
Materials
Construction
Copings. Bridge Seats and Backwalls
and Payment
Measurement
''8
gggo
2.5.1
2.5.2
2.5.3
2.5.4
2.5.5
2.5.6
2.5.7
2.5.8
2.5.9
2.5.10
2.5.11
2.5.12
SECTION 5 Reinforcement
g*
Article
VII
69
69
VIII
CONTENTS
SECTION
Article
2.10.1
2.10.2
2.10.3
2.10.4
2.10.5
2.10.6
2.10.7
2.10.8
2.10.9
2.10.10
2.10.11
2.10.12
2.10.13
2.10.14
2.10.15
2.10.16
2.10.17
2.10.18
2.10.19
2.10.20
2.10.21
2.10.22
2.10.23
2.10.24
2.10.25
2.30.26
2.10.27
2.10.28
2.10.29
2.10.30
2.10.31
2.10.32
2.10.33
2.10.34
2.10.35
2.10.36
2.10.37
2.10.38
2.10.39
2.10.40
2.10.41
2.10.42
2.10.43
2.10.44
2.10.45
2.10.46
2.10.47
2.10.48
2.10.49
2.10.50
2.10.51
2.10.52
2.10.53
2.10.54
2.10.55
2.10.56
2.10.57
2.10.58
2.10.59
2.10.60
Type Fabrication
Quality of Workmanship
Storage of Materials
Straightening Material
10 Steel Structures
Fabrication
Page
09
69
09
70
Finish
liivet Holes
Punched Holes
Reamed or Drilled Holes
Subpunching, Keaming and Shop Assembly
Accuracy of Punched and Subdrilled Holes
Accuracy of Keamed and Drilled Holes
Shop Assembling
Camber Diagram
Drifting of Holes
Match-Marking
Rivets
Field Rivets
Bolts and Bolted Connections
(a) General
(b) Unfinished Bolts
(c) Turned Bolts
(d) Special Ribbed Bolts
Riveting
Edge Planing
Welds
Flame Cutting
Facing of Bearing Surfaces
Abutting Joints
End Connection Angles
Lacing Bars
Finished Members
Web Plates
Bent Plates
Fit of Stiffeners
Eyebars
Annealing
Pins and Rollers
Boring Pin Holes
Pin
Clearances
Screw Threads
Pilot and Driving Nuts
Notice of Beginning of Work
Facilities for Inspection
Inspector's Authority
Mill
Orders
Weighing of Members
Marking and Shipping
Erection
Erection of Structure
Plans
Plant
Delivery of Materials
Handling and Storing Materials
Falsework
Methods and Equipment
Bearings and Anchorage
Straightening Bent Material
Assembling Steel
Riveting
Pin Connections
Misfits
,
Removal of Old Structure and Falsework
Payment
Basis of Payment
Payment for Test Eyebars
Pay Weight
<0
70
JO
70
70
71
71
71
71
71
71
72
<2
72
73
<3
. .
73
73
73
74
t*
74
74
74
74
74
75
75
75
70
<"
7
70
'
7b
7b
jio
77
77
77
77
77
7<
78
78
78
J8
78
78
79
79
79
80
0
80
80
81
CONTENTS
Paf?
gj
Variance in Weight
Weight
Computed
11
81
Bronze
2.11.1
2.11.2
2.11.3
2.11.4
2.11.5
2.11.6
General
Materials
Bronze Plates
Copper-Alloy Plates
Placing
Measurement
and Payment
2.12.1
2.12.2
2.12.3
2.12.4
2.12.5
2.12.6
2.12.7
2.12.8
2.12.9
2.12.10
2.12.11
2.13.1
2.13.2
2.13.3
General
Materials
Line and Grade
2.13.4
2.13.5
Construction
Painting
2.13.6
2.13.7
2.13.8
2.13.9
2.13.10
2.13.11
General
Materials
Railings Cast in Place
Precast Rails
Surface Finish
Expansion Joints
gj{
82
82
82
SECTION
SECTION
83
83
83
83
84
84
84
Article
2.10.61
2.10.62
IX
So
13Railings
5
85
85
Metal Railing
85
85
Concrete
85
86
86
8b
86
Stone and
2.13.12
Railing
Brick Railing
General
86
Wood Railing
General
2.14.1
2.14.2
2.14.3
2.14.4
2.14.5
2.14.6
General
Measurement
and
SECTION
2.14.7
2.14.8
2.14.9
2.14.10
Paint
87
87
Payment
14Painting
Metal Structures
87
87
87
87
87
88
88
88
fg
2.13.13
2.13.14
gg
88
88
88
89
89
89
89
89
90
2.ir,.l
2.15.2
2.15.3
2.15.4
2.15.5
2.15.6
2.15.7
Pa&e
90
90
Shop Painting
Field Painting
SECTION 15 Riprap
Materials
Dry Riprap, Class 1 for Slopes
Dry Riprap Class 2 for Slopes
Mortared Riprap for Slopes
Grouted Riprap for Slopes
Stone Riprap for Foundation Protection
Concrete Riprap in Bags
General
Measurement
Payment
and Payment
j||,
*<'
18
Dampprooflng
J'
97
9*
of Surface
and
i
J'
Payment
SECTION
SECTION
2.20.8
2.20.9
2.20.10
2.20.11
2.20.12
;
._'
?i
General Requirements
95
90
?7
2.19.1
Measurement
J*
9;j
Storage of Fabric
Preparation of Surface
Application General
Application Details
Damage Patching
Protection Course
and Payment
Measurement
SECTION
2.20.6
2.20.7
17 Waterproofing
General
Materials
General
Materials
Preparation
Application
19 Name
Plates
20 Timber Structures
Materials
(a) Lumber and Timber
(b) Structural Shapes
(c) Castings
(d) Hardware
Timber Connectors
Storage of Material
Workmanship
Treated Timber
(a) Handling
(b) Framing and Boring
(c) Cuts and Abrasions
(d) Bolt Holes
(e) Temporary Attachment
Untreated Timber
Treatment of Pile Heads
(a) General
(b) Method A. Zinc Covering
(c) Method B Fabric Covering
Holes for Bolts, Dowels, Rods and Lag Screws
Bolts and Washers
Countersinking
Framing
Pile Bents
.
2.20.2
2.20.3
2.20.4
2.20.5
Cribbing
94
2.18.1
2.18.2
2.18.3
2.18.4
2.18.5
2.20.1
J<i
16 Concrete
SECTION
2.17.1
2.17.2
2.17.3
2.17.4
2.17.5
2.17.6
2.17.7
2.17.8
2.17.9
;>.$
and
General
Construction
93
Jg
Placing
SECTION
2.16.1
2.16.2
2.16.3
92
93
Concrete
Measurement
.)-
Slab Riprap
Concrete
2.15.8
2.15.9
2.15.10
2.15.11
M
J
91
97
98
Article
2.14.11
2.14.12
CONTENTS
89
99
99
99
100
100
100
100
100
100
100
100
100
10
101
101
101
101
101
102
102
XI
CONTENTS
Page
102
102
102
102
102
102
103
Article
Framed Bents
(a) Mud Sills
2.20.13
(b)
Concrete
(c) Sills
(dj Posts
pedestals
Caps
Bracing
Stringers
Plank Floors
Laminated or Strip Floors
Wheel Guards and Railings
Trusses
Truss Housings
Erection of Housing and Bailings
Painting
Measurement
and Payment
2.20.14
2.20.15
2.20.10
2.20.17
2.20.18
2.20.19
2.20.20
2.20.21
2.20.22
2.20.23
2.20.24
2.21.4
2.21.5
SECTION
2.22.1
2.22.2
2.22.3
2.22.5
2.22.0
2.23.1
2.23.2
2.23.3
2.23.4
2.23.5
2.23.6
2.23.7
2.23.8
2.23.9
2.23.10
2.23.11
104
104
104
104
104
104
2.21.1
2.21.2
2.21.3
2.22 A
303
103
103
'
22 Timber Cribbing
Material
(a) Timber
(b) Logs
Preparation
Dimensions
(a) Timber
(b) Logs
Construction
(a) Foundation
(b) Mud Sills
(c) Face Logs or Timbers
(d) Ties
(e) Fastening
Filling
Measurement
>
and Payment
of Measurement
101;
100
107
10*
10 <
107
10 1
107
JPJ
10,
10]
108
108
10S
108
108
109
10.J
109
109
110
Ill
JIT
J"
113
118
Basis of Payment
24 Wearing Surfaces
Concrete Wearing Surface
SECTION
Separate
2.24.1
2.24.2
2.24.3
2.24.4
Description
Measurement and Payment
Brick Wearing Surface
General Requirements
Materials
113
113
JJg
1"
XII
Article
CONTENTS
Page
Preparation of Subfloor
Bed
Sand-Cement
Placing Bedding Course
Laying the Brick
Rolling the Brick
Testing the Surface
Applying Asphalt Filler
Surface Dressing
Opening to Traffic
and Payment
Measurement
113
114
114
114
115
115
115
115
115
115
2.24.15
2.24.16
2.24.17
2.24.18
2.24.19
2.24.20
2.24.21
116
116
116
116
116
117
117
Bituminous Carpets
General
Materials
Preparation of Subfloor
(a) Wood Subfloor
(b) Concrete Subfloor
Construction of Tar Mat Surface
(a) Prime Coat
(b) Second Coat
(c) Seal Coat
of Asphalt Mat Surface (Mixed Method)
Construction
'
Prime Coat
Second Coat
, Seal Coat
Construction of Asphalt Mat Surface (Penetration Method)
(a) Prime Coat
(b) Second Coat
Opening to Traffic
and Payment
Measurement
117
117
117
117
118
118
118
118
118
119
119
119
119
120
120
120
120
120
2.24.22
2.24.23
2.24.24
2.24.25
2.24.26
2.24.27
2.24.28
2.24.29
DIVISION
III
2.24.5
2.24.6
2.24.7
2.24.8
2.24.9
2.24.10
2.24.11
2.24.12
2.24.13
2.24.14
Design
SECTION General
Features of Design
Determination of Waterway Area
Restricted Waterways
Channel Openings
Pier Spacing and Location
Size of Culvert Openings
Length of Culverts
Width of Roadway and Sidewalk
1
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
3.1.7
3.1.8
3.1.9
3.1.10
3.1.11
3.1.12
3.1.13
3.1.14
3.1.15
3.1.16
3.1.17
121
121
Clearances
Curbs and Safety Curbs
Railings
Drainage
Superelevation
Floor Surfaces
Blast Protection
Utilities
Roadway Width, Curbs and Clearances
(a) Roadway Width
(b) Clearance Between Walls
(c) Curbs
(d) Vertical Clearance
Roadway Width. Curbs and Clearances
(a) Roadway Width
for Tunnels
for Depressed
Roadways
121
121
122
122
122
122
122
124
124
124
124
124
125
125
125
125
126
126
126
126
XIII
CONTENTS
Article
3.1.18
"
Underpasses
Page
126
126
126
127
127
127
SECTION 2 Loads
3.2.1
3.2.2
3.2.3
3.2.4
3.2.5
3.2.6
3.2.7
3.2.8
3.2.9
3.2.10
3.2.11
3.2.12
3.2.13
3.2.14
3.2.15
3.2.16
3.2.17
3.2.18
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5
Loads
Load
Loads on Culverts
Si Rigid Culverts
Live Load
Overload
Provision
Highway Loadings
(a) General
(b) H Loadings
(c) H-S Loadings
(d) Classes of Loadings
(e) Designation of Loadings
(f) Minimum Loading
Traffic Lanes
Standard Trucks and Lane Loads
Application of Loadings
(a) Traffic Lane Units
Traffic Lane Units
(b) Number and Position,
(c) Lane Loadings Continuous Spans
(d) Loading for Maximum Stress
Reduction in Load Intensity
Electric Railway Loading
Sidewalk, Curb, Safety Curb, and Railing Loading
(a) Sidewalk Loading
(b) Curb Loading
(c) Safety Curb Loading
(d) Railing Loading
Impact
(a) Group A
(!>) Group B
(c) Impact formula
Longitudinal Forces
Wind Loads
Thermal Forces
Force of the Stream Current, Floating Ice and Drift
Buoyancy
Earth Pressure
127
127
128
128
128
129
129
129
129
129
129
129
130
130
130
132
132
132
132
133
134
134
134
134
134
134
135
135
135
135
135
136
186
137
137
137
137
138
138
138
139
139
139
141
141
141
141
141
142
142
142
143
143
143
143
143
143
Dead
XIV
CONTENTS
Article
Page
143
144
144
(a) General . .
(b) Floors Filled With Concrete
(c) Open Floors
SECTION 4 Unit
3.4.1
General
Grouping of Loads
(a) Group A
(b) Group B
:
144
144
3.4.2
3.4.3
3.4.4
3.4.5
3.4.6
3.4.7
3.4.8
3.4.0
3.4.10
3.4.11
Concrete
Concrete
3.4.13
3.4.14
1-50
130
130
Timber Structures
Standard Stress Grades and Working Stresses
Formulas for the Computation of Stresses in Timber
(a) Horizontal Shear in Rectangular Beams
(b) Axial Compression in Rectangular Columns
(c) Axial Compression on Connector Joined Spaced Columns
(d) Safe -Load on Round Columns
Notched
(g)
Timber Connectors
(f)
Beams
Bearing on Inclined Surfaces
3.4.18
3.5.1
Piles
SECTION 5 Substructures
(a)
(b)
(c)
(d)
(e)
General
Limitation of Use
Design
Loads
Spacing.
Clearances
Batter Piles
and Retaining
and Embedment
151
152
152
152
153
153
154
154
154
Miscellaneous
Bearing Power of Foundation Soils
Angles of Repose
Bearing Power of Piling
(a) General
(b) Case A Capacity of Pile as a Structural Member
(c) Case B Capacity of Pile to Transfer Load to the Ground
(d) Case C Capacity of the Ground to Support the Load De
livered by the Pile
(e) Maximum Design Loads for Piles
(f) Uplift
(g) Group Pile Loading
Moments. Shears and Floor Beam Reactions
3.4.15
3.4.16
3.4.17
146
146
146
147
148
148
148
148
140
140
140
140
150
150
(e)
14(i
14<i
Structures
Stresses
(a)
(b)
(c)
(d)
3.4.12
143
154
155
155
155
155
15(1
157
157
158
158
158
Walls
158
158
158
150
150
150
CONTENTS
Page
Article
(f) Buoyancy
160
100
(a J Depth
10'
3.5.5
102
10.3
103
103
103
104
104
104
104
164
104
165
16._
16._
10^
10..
}g._
]''._
16.
J0;_
J6T
16
J''"
16<,
160
3.5.6
10-
3.5.4
101
101
'
Anchorage
Distribution of Pressure
d) Spread Footings
(e) Internal Stresses in Spread Footings
(f) Reinforcement
(g) Transfer of Stress from Vertical Reinforcement
Abutments
(a) General
(b) Reinforcement for Temperature
(c) Wing Walls
(d) Drainage
Retaining Walls
(a) General
(b) Base or Footing Slabs
(c) Vertical Walls
(d) Counterforts and Buttresses
(e) Reinforcement for Temperature
if) Expansion and Contraction Joints
(g) Drainage
Piers
(a) General
(b) Pier Nose
Tubular Steel Piers
(a) Use
(b) Depth
(c) Piling
(d) Dimensions of Shell
(e) Splices and Joints
(f) Bracing
SECTION Structural Steel Design
Number of Trusses or Girders
Spacing of Trusses and Girders
Effective Span
Effective Depth
Alternating Stresses
161
101
Footings
Sb)c)
3.5.3
15D
15!
3.5.2
XV
3.6.19
3.6.20
3.6.21
3.6.22
3.6.23
3.0.24
3.6.25
3.6.26
3.6.27
3.6.28
3.6.29
Compression
Members
'
0.
1<
1<
17
J<
10
Stresses
Combined
Secondary Stresses
Rolled Beams
100
100
100
Jgn
100
169
16p
JWJ
1<0
1(0
8.0.1
3.0.2
3.0.3
3.6.4
3.6.5
3.6.6
3.0.7
3.0.8
3.0.9
3.0.10
3.0.11
3.0.12
3.0.13
3.6.14
3.6.15
3.6.16
3.0.17
3.6.18
'
1J0
Iifl
>')}
1"'
1'1
I'1
171
l'l
I"1
172
172
XVI
CONTENTS
Article
3.6.30
3.6.31
3.6.32
3.6.33
3.6.34
3.6.35
3.6.36
3.6.37
3.6.38
3.6.39
3.6.40
3.6.41
3.6.42
3.6.43
3.6.44
3.6.45
3.6.46
3.6.47
3.6.48
3.6.49
3.6.50
3.6.51
3.6.52
3.6.53
3.6.54
Strength of Connections
Splices
Indirect Splices
Fillers
(a) Welding
(b) Riveting
Gusset Plates
Stay Plates
Perforated Cover Plates
Net Section at Pin Holes
Net Section of Riveted Tension Members
Location of Pins
Pin Plates
Forked Ends
Pins and Pin Nuts
Bolts
Upset Ends
Sleeve Nuts
Expansion and Contraction
Expansion Bearings
Bronze or Copper Alloy Sliding Expansion Bearings
Fixed Bearings
Pedestals
and Shoes
Rollers
Inclined Bearings
Anchor Bolts
Name Plates
PaBe
172
172
172
172
172
172
173
173
174
175
175
175
176
176
176
176
176
J76
17
176
177
177
177
1'Z
17<
17<
17
Welding
3.6.55
Welding General
178
Floor
System
3.6.56
3.6.57
3.6.58
3.6.59
3.6.60
3.6.61
3.6.62
3.6.63
3.6.64
3.6.65
3.6.66
3.6.67
3.6.68
3.6.69
3.6.70
3.6.71
3.6.72
General
Minimum Size of Angles
Lateral Bracing
Portal and Sway Bracing
Deck Plate Girder Spans
Half -Through Truss Spans
Through Plate Girder Spans
Bracing of Long Columns
3.6.73
3.6.74
3.6.75
3.6.76
3.6.77
3.6.78
3.6.79
3.6.80
3.6.81
3.6.82
3.6.83
3.6.84
3.6.85
General
Flange Sections
Thickness of Web Plates
Flange Rivets
Flange Splices
Web Splices
Transverse End Stiffeners
Transverse Intermediate Stiffeners
Longitudinal Stiffeners
Ends of Through Girders
Sole Plates
Masonry Bearings
Camber
178
178
178
178
179
179
179
179
179
Bracing
179
180
180
180
180
180
181
181
Plate Girders
181
181
181
182
182
182
182
182
183
183
183
183
183
CONTENTS
Article
Trusses
3.6.86
3.6.87
3.6.88
3.6.89
3.6.90
3.6.91
3.6.92
3.6.93
3.6.94
3.6.95
3.6.96
3.6.97
General
Top Chords and End Posts
Bottom Chords
Working Lines and Gravity Axes
Camber
Riveted Tension Member in Pin-Connected Trusses
Counters
Eyebars
Packing of Eyebars
Diaphragms
Sole Plates
Masonry Bearings
3.6.98
3.6.99
3.6.100
3.6.101
3.6.102
3.6.103
3.6.104
3.6.105
3.6.106
Viaducts
Type
Bents and Towers
Batter
Single Bents
Bracing
Bottom Struts
Depth of Girders
Girder Connections and Bracing
Sole and Masonry Plates
3.7.1
3.7.2
3.7.3.
3.7.4
3.7.5
3.7.6
3.7.7
3.7.8
3.7.9
3.7.10
3.7.11
XVII
Pa8e
183
14
184
184
184
184
184
184
184
185
15
15
185
185
185
185
J
186
180
181)
186
187
18 i
187
187
188
188
188
189
190
192
192
192
}
192
192
192
ig
JJJjj
193
1
fg
193
193
193
194
194
194
194
J9|
19o
JfS
195
195
196
196
196
197
197
198
198
198
198
XVIII
Article
CONTENTS
3.7.12
3.8.1
3.8.2
3.8.3
3.8.4
3.8.5
Bolts
Washers
Hardware for Seacoast Structures
Columns and Posts
Pile and Framed Bents
(a) Pile Bents
(b) Framed Bents
(c) Sills and Mud bills
(d) Caps
(e) Bracing
(f) Pile Bent Abutments
Trusses
(a) Joints and Splices
(b) Floor Beams
(c) Hangers
id) Kyebars and Counters
(e) Bracing
(f) Camber
Floors and Bailings
(a) Stringers
(b) Bridging
(c) Nailing Strips
(d) Flooring
(e) Retaining Pieces
(f) Wheel Guards
(g) Drainage
(h) Bailings
Fire Stops
SECTION
3.8.0
3.8.7
3.8.8
Page
Design
198
198
of Timber Structures
108
199
IBS)
199
199
199
199
199
200
200
200
200
200
201
201
201
201
201
201
201
201
201
202
202
202
202
202
202
SECTION 9 Composite
3.9.1
3.9.2
3.9.3
3.9.4
3.9.5
3.9.0
General Assumptions
Effective Flange Width
3.10.1
3.10.2
3.10.3
3.10.4
3.10.5
3.10.0
3.10.7
3.10.8
3.10.9
General
3.11.3
3.11.4
3.11.5
3.11.0
3.11.7
3.11.8
203
203
203
203
Stresses
Shear
Deflection
Shear Devices
SECTION
3.11.1
3.11.2
204
204
10 Sectional
Plate Pipe
201
204
Bolts
Cover Exceeding Heights Specified
Sizes of Pipe Not in Table
Multiple Pipes
Strutting
in Table 1
General
Inventory
Ratings
of Existing
20; >
205
205
20;)
205
205
20;>
SECTION 12 Rating
3.12.1
3.12.2
Beams
206
200
20b
200
200
20!!
20 1
207
Bridges
207
207
XIX
CONTENTS
Article
3.12.15
3.12.7
3.12.8
3.12.5)
3.12.10
3.12.11
3.12.12
3.12.13
P**,!
Operating Ratings
Dead Load
Live Load
Minimum Wind Load
Unit
0J
TJSi
*}{
Stresses
Traffic Lanes
Allowable Stresses (Columns)
Batten Iilate Columns
Compression
on Flanges of Learns and Girders
Details of Design
ta) Strength of Connections
(b) Splices
(c) Pins
Field Inspection
.f"?
-"J
Ri
r,,,;
3.12.3
3.12.4
3.12.5
210
DIVISION IV
Materials
SECTION
SECTION
4.2.1
4.2.2
Quality
Tests
4.3.1
4.3.2
Fine Aggregate
Sand for Mortar
4.4.1
4.4.2
Coarse
211
211
Cement
211
211
Fine
SECTION
Aggregate
212
212
Coarse
Aggregates
2J2
212
Aggregate
SECTION
Bar Reinforcement
Reinforcement
Aggregates
Hubble or Cyclopean
SECTION
4.5.1
4.5.2
4.5.3
4.5.4
1 Cement
General
Sampling and Testing
2
4.1.1
4.1.2
212
213
213
213
4.7.1
4.7.2
4.7.3
4.8.1
Carbon Steel
4.0.1
4.0.2
4.0.3
4.6.4
4.0.5
4.0.0
4.0.7
4.6.8
4.0.J)
4.0.10
4.0.11
4.6.12
4.6.13
4.6.14
Steel
SECTION
Forgings
213
213
213
213
214
214
21.1
214
214
214
214
214
214
215
215
21o
215
Forgings
215
XX
CONTENTS
Page
Article
SECTION
9 Steel Castings
4.9.1
4.9.2
4.10.1
4.10.2
4.10.3
215
216
216
4.11.1
4.11.2
4.11.3
216
216
216
SECTION
SECTION
215
21o
Castings
10Gray-Iron
Castings
Bronze
4.12.1
4.12.2
4.13.1
Steel
4.14.1
4.14.2
4.14.3
4.14.4
4.14.5
12
SECTION
13 Steel Piles
Piles
216
SECTION
4.15.1
4.15.2
4.15.3
216
216
Steel
Protective Treatment
Concrete
15
Steel
217
217
217
217
217
Grid Floors
(Shop Coat)
217
217
218
SECTION 16 Paint
Paint for Timber Structures
4.16.1
4.16.2
4.16.3
4.16.4
4.17.1
SECTION
4.18.1
4.18.2
4.18.3
4.19.1
4.19.2
4.19.3
4.19.4
4.19.5
4.19.6
4.19.7
4.19.8
4.19.9
Sheet
Sheet
Sheet
18
Copper
Lead
Zinc
Sheet
218
218
218
219
219
219
219
220
221
223
224
224
224
224
224
225
225
225
225
225
226
226
CONTENTS
Article
4.20.1
4.20.2
4.20.3
Corrugations
Gage Determination and Tolerance
Field Inspection and Acceptance of Plates
SECTION 20 Stone for Masonry
Ashlar Stone
Rubble Stone
Riprap
4.21.1
4.21.2
Paving Brick
Brick for Masonry
4.22.1
4.22.2
Oil Asphalt
4.22.3
4.22.4
Tar
Asphalt
4.22.5
4.22.6
4.22.7
4.22.8
4.22.9
4.22.10
4.22.11
Waterproofing
Asphalt
Pitch
Fabric
Tar for Absorptive Treatment
Tar Seal Coat
Joint Fillers
Inspection and Delivery
4.19.10
4.19.11
4.19.12
SECTION
SECTION
Premolded
22
XXI
Page
226
226
220
226
227
227
21 Brick
227
227
Bituminous
Fillers
Joint Fillers
Expansion
227
228
Bituminous Carpets
228
228
Materials
4.25.6
4.25.7
4.25.8
4.25.9
General
Quality
Dimensions
4.26.1
Preservatives
4.23.1
4.23.2
4.23.3
4.23.4
4.23.5
4.23.6
4.24.1
4.25.1
4.25.2
4.25.3
4.25.4
4.25.5
229
2211
22V)
22V)
229
230
230
230
230
231
23.1
231
231
231
232
232
232
232
233
233
233
234
234
234
234
Timber Piles
234
235
SECTION
26Timber Preservatives
235
SECTION
4.27.1
4.27.2
4.27.3
4.27.4
4.27.5
4.27.6
General
27 Timber Connectors
230
236
236
236
237
237
INTRODUCTION
The compilation of these specifications
began with the organization,
in 1921, of the Committee on Bridges and Structures of the American
Association of State Highway Officials. During the period from 1921, until
the specifications were printed in 1931, the specifications were gradually
developed, and as the several divisions were approved, from time to time,
they were made available in mimeographed form for use of the State High
way Departments and other organizations. A complete specification was
Though they were not in
available in 1926 and it was revised in 1928.
printed form, the specifications were valuable to the bridge engineering
profession during the period of development.
HIGHWAY BRIDGES
The Committee on Bridges and Structures has jurisdiction over the
The present membership of the Com
bridge activities of the Association.
of 48 States, the District of Columbia,
mittee includes representatives
The following have served
Hawaii and the Public Roads Administration.
as chairmen of the Committee since its inception in 1921 : Messrs. E. F.
Kelley, who pioneered the work of the Committee, Albin L. Gemeny and
R. B. McMinn. Mr. Raymond Archibald, the present chairman, has served
in that capacity since the 1941 edition was published.
Suggestions for the improvement of the specifications will be welcomed.
They should be sent to the Chairman, Committee on Bridges and Structures,
A.A.S.H.O., Public Roads Administration, Washington 25, D. C.
State
ment, Montgomery.
25,
D. C.
Highway Depart
Phoenix.
State Highway
Little Rock.
CALIFORNIA F. W. Panhorst, Bridge Engineer, Division of Highways,
Commission,
COLORADO Paul
ment, Denver.
CONNECTICUT
J.
ment, Hartford.
Depart
Highway
Depart
KANSAS E.
Topeka.
Ames.
S.
KENTUCKY E.
State
Highway
Commission,
Frankfort.
LOUISIANA N. E. Lant, Chief Engineer,
NEBRASKA H.
Irrigation,
Helena.
G. Schlitt, Bridge Engineer, Department of Roads
Lincoln.
and
HIGHWAY
BRIDGES
NEW HAMPSHIRE H. E.
Department,
NEW
LANGLEY,
Department
of Highways,
Highway
Concord.
JERSEY Morris
Salem.
RHODE ISLAND D.
Works, Providence.
O.
SOUTH CAROLINA W.
Department,
Columbia.
Department
J.
Gooding,
Bridge Engineer,
State
Highway
ways, Richmond.
Cheyenne.
COMMITTEE
OF THE ASSOCIATION
1949
PRESIDENT
W. W. POLK
Illinois
W. BROWN
Missouri
Second Region
MILLER, JR.
W. V. BAISE
Third Region
M. ZIEGLER
C.
Michigan
N. Carolina
New Jersey
Fourth Region
A. P. WINKLER
Montana
EXECUTIVE COMMITTEE
M.
J.
HOFFMANN
R. H. BALDOCK
Minnesota
J.
A. ANDERSON
Virginia
Oregon
T. H. CUTLER
B. D.
TALL A MY
New York
Kentucky
H. E. SARGENT
T. H. MACDONALD
Vermont
Washington, D. C.
F. R. WHITE
Iowa
EXECUTIVE SECRETARY
H. H. HALE
Washington, D. C.
TREASURER
G.
H. HENDERSON
Rhode Island
D.
C. GREER
Texas
C.
H. PURCELL
California
DIVISION
General Provisions
SECTION I Definition of
1. 1. 1. Definition
In
"State
of
Terms
Terms.
these specifications
the following
oe Commonwealth"
of
"Commission
to be done.
the county
used to designate
or township in charge
of
the engineer
assigned
to
inspection
or materials therefor.
"Bidder" The individual, firm, or corporation formally submitting a pro
posal for the work contemplated, or any portion thereof, acting
directly or through an authorized representative.
the exe
of the
and requirements
contained herein, to
gether with all written or printed agreements and instructions,
except notes on plans, made or to be made pertaining to the
method and manner of performing the work, or to the quantities
and qualities of the materials to be furnished under the contract.
supplemental
directions, provi
not on the plans and adopted as a
and requirements
part of the contract with the express purpose that they shall
sions
GENERAL
PROVISIONS
contained
"Instructions
the bidder,
approaches
thereto.
substructure.
HIGHWAY
BRIDGES
be designated
materials, equipment,
"Working Day"Working
SECTION
1.2.
Preservers Association.
Society.
2 Proposal
Requirements
and Conditions
1. Contents
of Proposal Form.
furnished by the commission with proposal forms which
will state the location and description of the work contemplated and which
will show the approximate quantities of the work to be performed or
materials to be furnished, the amount of the proposal guaranty, and the
date, time and place of filing and of opening proposals.
The form will
also refer to any special provisions or requirements which vary from, or are
supplemental to, the standard specifications.
Bidders will
be
1. 2. 2. Interpretation
of
Estimates.
The engineer's
GENERAL PROVISIONS
1. 2. 4. Preparation
of Proposal.
Each proposal submitted shall be upon the form furnished. No other
The blank spaces must be filled in correctly
proposal will be considered.
and the amounts written legibly.
The bidder shall sign the proposal on the blank space provided therefor.
If the proposal is made by a partnership or corporation, the name and
address of the partnership or corporation, as well as that of the agent
acting therefor, shall be shown.
1. 2. 5. Rejection
of Proposals.
Proposals may be rejected if they show any alteration of form, addi
tions not called for, conditional or alternate bids, irregularities of any kind,
or if they contain a clause in which the bidder reserves the right to accept
Proposals in which the prices are
or reject a contract awarded to him.
obviously
unbalanced
may be rejected.
1. 2. 6. Proposal Guaranty.
marked as indicated
in an additional envelope. All proposals shall be filed prior to the time and
at the place specified in the advertisement or instructions to bidders.
1. 2. 8. Withdrawal
of Proposal.
A bidder will
it has
been
1. 2. 9. Public
Opening of Proposals.
Proposals will be opened publicly and read
specified in the advertisement.
at the time
and
place
1. 2. 10. Disqualification
of Bidders.
More than one proposal from an individual firm, partnership, corpora
tion, or association under the same or different names will not be consid
ered. Collusion between bidders will be sufficient cause for rejection of all
bids so affected.
1. 2. 11. Competency
of Bidders.
Bidders must be capable of performing the various items of work bid
They may be required to furnish a statement covering experience
upon.
on similar work, list of machinery, plant and other equipment available
for the proposed work, and such statements of their financial resources as
may be deemed necessary.
HIGHWAY
10
SECTION
1. 3. 1. Consideration
Award
BRIDGES
and Execution
of Contract
of Bids.
The right is reserved to waive defects and to reject any or all proposals.
1. 3. 2. Award
of Contracts.
Contracts shall be awarded at the time and place indicated
advertisement, or as soon thereafter as practicable.
in the
1. 3. 3. Return
of Proposal Guaranty.
The proposal guaranties of all except the three lowest bidders will be
returned promptly after the tabulation of bids has been made, and in no
days without
case will a proposal guaranty be held longer than
the bidder's written consent.
Should no award be made within
days, all proposals will be rejected and proposal guaranties returned.
1.3. 4. Requirements
of Contract Bond.
days from the date of accept
The successful bidder, within
ance of his proposal, shall furnish and file with the proper officer as
designated in the advertisement
or instructions to bidders, an acceptable
bond in an amount not less than
per cent of the contract amount.
Such bond shall be on the form specified, and shall meet all requirements
as specified in the laws of
.
Negotiable securities approved by the commission, in an amount equal
to that specified above, may, at the option of the contractor, be deposited
with the commission in lieu of a bond.
1. 3. 5. Execution
of the Contract.
The individual, firm, or corporation to whom the contract has been
awarded shall execute and file with the commission
copies of the
days after the date of the award.
contract within
1. 3. 6. Approval
of Contract.
Contracts requiring execution by the commission shall be so executed
Any material delivered or work
before any construction work is started.
started before such approval is noted on the contract is entirely at the
contractor's risk.
1. 3. 7. Failure
to Execute
Contract.
Failure
SECTION 4 Scope of
1. 4. 1. Intent
the Work
GENERAL PROVISIONS
Any deviation from these requirements
and terms of the contract.
be stipulated in the contract.
11
must
1. 4. 2. Special Work.
fully
herein.
2. 4. 3. Increased
or Decreased Quantities.
Work.
Temporary
The contractor may use in the construction of the work any suitable
sand, gravel, or stone found in the excavation but, if necessary, shall replace
any material so removed with material satisfactory to the engineer.
HIGHWAY
12
BRIDGES
SECTION 5 Control of
the Work
1. S. 1. Authority
of Engineer.
The engineer shall decide any and all questions which may arise as to
the quality and acceptability of materials furnished and work performed
and as to the manner of performance
and rate of progress of the work,
and shall decide all questions which may arise as to the interpretation of
the plans and specifications, and all questions as to the acceptable fulfillment
of the terms of the contract.
2. 5. 2. Plans and
Working Drawings.
contractor's risk.
Working drawings for steel structure shall consist of shop detail,
erection and other working plans showing dimensions, sizes of material,
details and other information necessary for the complete fabrication and
erection of the metal work.
Working drawings for concrete structures shall consist of such detailed
plans as may reasonably be required for the successful prosecution of the
work and which are not included in the plans furnished by the engineer.
These may include plans for falsework, bracing, centering and form work,
masonry lay-out diagrams, and diagrams for bent reinforcement.
It is expressly understood that the approval by the engineer of the
contractor's working drawings relates to the requirements for strength and
detail, and such approval will not relieve the contractor from responsibility
for errors in dimensions.
The contractor shall furnish the engineer with such blueprint copies
of the working drawings as may be required for approval and construc
tion purposes, and upon completion of the work, cloth tracings, if required
shall be supplied to the engineer.
The contract price shall Include the cost of furnishing all working
drawings, and the contractor will be allowed no extra compensation for
such drawings.
1. S. 3. Deviations
be
GENERAL PROVISIONS
1. 5. 4. Coordination of Specifications
13
and Plans.
In
by Contractor.
be determined
If
Inspectors shall be authorized to inspect all work done and all materials
furnished. Such inspection may extend to all or any part of the work and
to the preparation, fabrication or manufacture of the materials to be used.
Resident engineers and inspectors may be stationed on the work to
report to the engineer as to the progress thereof, and manner in which it
is being performed, also to report whenever it appears that materials fur
nished or work performed by the contractor fail to fulfill the requirements
of the specifications and contract, and to direct the attention of the con
tractor to such failure.
Such inspection shall not relieve the contractor
HIGHWAY
14
BRIDGES
and Defective
Work.
Inspection.
In
Claims.
GENERAL
PROVISIONS
15
tractor for keeping strict account of actual cost, then the contractor hereby
agrees to waive the claim for such extra compensation.
Such notice by the
contractor, and the fact that the engineer has kept account of the cost as
aforesaid, shall not in any way be construed as proving the validity of the
In case the
claim.
The claim must be passed upon by the commission.
claim is found to be just, it shall be allowed and paid as an extra as
provided herein for extra work.
1. 5. 12. Arbitration.
of Supply
and Quality.
All
of
Materials.
approved
HIGHWAY BRIDGES
16
of
Materials.
Materials.
All materials
SECTION
2. 7.
2. Laws
7 Legal Relations
to be Observed.
GENERAL PROVISIONS
of the work, and shall save the State and its representatives
against any claim arising from violation thereof.
17
harmless
The contractor shall procure all permits and licenses, pay all charges
and fees, and give all notices necessary and incident to the due and lawful
prosecution of the work.
I.
Plans not supplied by the State which embody the use of any patented
process or design shall be accompanied by a written statement of the exact
terms under which said plans are to be used, and shall provide a definite
and fixed price for which any responsible contractor may use said plans,
processes or designs without further liability of any character.
1. 7. 4. Federal
Participation.
The attention of the contractor is called to the fact that, when the
United States Government pays all or any portion of the cost of the work,
the Federal laws authorizing such participation and the rules and regula
tions made pursuant to such laws must be observed by the contractor.
The
work shall be subject to the inspection and approval of the representatives
of such Federal agencies as are created for the administration of these laws.
1. 7. 5. Sanitary
Provisions.
The contractor shall observe all rules and regulations of the State or
local health officials, and must take such precautions as are necessary to
avoid creating unsanitary conditions.
1. 7. 6. Public Safety and Convenience.
The contractor shall at all times so conduct his work as to insure the
The convenience of the general public
least possible obstruction to traffic.
and the residents along the highway and the protection of persons and
property are of prime importance and shall be provided for by the contractor
in an adequate and satisfactory manner.
1.7.
7. Barricades
The contractor shall at his expense and without further or other order
provide, erect and maintain at all times during the progress or temporary
suspension of the work, suitable barricades, fences, signs, or other adequate
protection, and shall provide, keep and maintain such danger lights, signals,
and watchmen as may be necessary or as may be ordered by the engineer
to insure the safety of the public as well as those engaged in connection with
the work. All barricades and obstructions shall be protected at night by
red signal lights which shall be suitably distributed across the roadway and
HIGHWAY BRIDGES
18
J.
of Property.
The contractor shall not enter upon private property for any purpose
without obtaining permission and shall be responsible for the preservation
of all public and private property, trees, monuments, etc., along and adja
cent to the highway, and shall use every precaution necessary to prevent
damage or injury thereto. He shall use suitable precautions to prevent, and
shall be responsible for damage to pipes, conduits and water mains, and
other underground structures, and shall carefully protect from disturbance
or damage all land monuments until these are properly referenced by the
engineer.
1. 7. 9. Responsibility
for Damages.
The contractor shall assume all responsibility for damages sustained
by persons or property due to the carrying on of his work and until final
acceptance thereof or until released by the engineer in writing.
He shall
be responsible for all accidents to persons or property, and shall save the
State harmless from all damages resulting from any accidents which may
occur on existing structures to be replaced by new construction under the
Any extension
contract after the date of completion as specified therein.
of time granted the contractor in which to complete the contract shall not
relieve him or his surety from this responsibility.
1. 7. 10. Contractor's
Until final
I.
7. 11. Personal
GENERAL PROVISIONS
19
and character of the work performed and materials furnished by the con
tractor, or from showing that any such measurement, estimate, or certificate
is untrue or incorrectly made, or that the work or materials do not conform
The State shall not be precluded or estopped, not
in fact to the contract.
withstanding any such measurement, estimate or certificate, and payment
in accordance therewith, from recovering from the contractor and sureties
such damages as it may sustain by reason of his failure to comply with the
Neither the acceptance by the commission, or by any
terms of the contract.
of the commission, nor any payment for nor acceptance of
representative
the whole or any part of the work, nor any extension of time, nor any
possession taken by the commission, shall operate as a waiver of any portion
of the contract or of any power herein reserved, or any right to damage
herein provided.
A waiver of any breach of the contract shall not be held
to be a waiver of any other or subsequent breach.
SECTION
2. 8. 1. Subletting
8 Prosecution
or Assignment
of
and Progress
Contract.
The contractor shall not sublet, sell or assign all or any portion of the
contract, or the work provided therein without the written consent of the
commission.
1. 8. 2. Prosecution
of the Work.
The execution of works under this contract shall not be commenced
until the contractor has received a written order to that effect, signed by
the engineer, and the work shall thereupon be at once begun and continu
ously carried on to completion, subject to such suspensions as are provided
for herein.
The progress of the work shall be at a rate sufficient to complete the
contract in an acceptable manner within the period of time specified. The
engineer shall at frequent intervals make progress reports to the commis
sion, and if it appears that the rate of progress is such that the contract
will not be completed within the time limit, or if the contract is not being
executed in a satisfactory and workmanlike manner, the commission may
order the contractor to take such steps as it considers necessary to complete
the contract within the period of time provided, or to prosecute the work
in a satisfactory manner.
2. 8. 3. Limitations
of
Operations.
The contractor shall begin work at such points as the engineer may
direct or approve and shall thereafter prosecute the work at such points
and in such order as may be prescribed or approved from time to time by
the engineer.
In the case of a dispute arising between two or more contractors en
gaged on the same work as to the respective rights of each under these
specifications, the engineer shall determine the matters at issue and shall
define the respective rights of the various interests involved, in order to
secure the completion of all parts of the work in general harmony and with
satisfactory results, and his decision shall be final and binding on all parties
concerned.
HIGHWAY
20
BRIDGES
of the Work.
The engineer shall have authority to suspend the work wholly or in
part for such period or periods as he may deem necessary, due to unsuitable
weather or such other conditions as are considered unfavorable for the
prosecution of the work, or for such time as is necessarily due to the failure
on the part of the contractor to carry out orders given or to perform any
or all provisions of the contract.
When under suspension, the work shall be put in proper and satisfac
tory condition, carefully covered and properly protected, as directed by the
In all cases of suspension of construction operations, the work
engineer.
shall not again be resumed until permitted by order of the engineer.
1. 8. 6. Determination and
All
requests
shall be submitted
1. 8. 7. Failure to Complete
on Time.
GENERAL PROVISIONS
21
If
of Contract.
1.8.10. Compensation
for
Unreasonable
Delays.
9 Measurement and
Payment
of Quantities.
All work
of
by the engi
Payment.
full
HIGHWAY
22
BRIDGES
arising from the nature of the work, or from the action of the elements,
or from any unforeseen difficulties which may be encountered during the
prosecution of the work, until its final acceptance by the commission.
I.
9. 3. Payments
for
Increased
or Decreased Quantities.
It is mutually
for Extra
Work.
All work done on a "force account" basis will be paid for in full in the
following manner:
(1) For all labor, teams, and foremen in direct charge of the specific
operation, including workmen's compensation and liability insurance on the
same, the contractor shall receive the current rate of wage for each and
every hour said labor, teams and foremen are actually engaged in such
work, to which shall be added an amount equal to 15 per cent of the sum
thereof.
(2) For all materials entering permanently into the work the con
tractor shall receive the actual cost of such materials, including freight
charges, as shown by original receipted bills, to which cost shall be added
an amount equal to 10 per cent of the sum thereof.
(3) For any machinery or special equipment, other than small tools
and including fuel and lubricants, which it may be deemed necessary or
desirable to use, the contractor shall be allowed a reasonable rental charge,
to be agreed upon in writing before the work is begun, for each and every
day such machinery is in use upon such work, and to which sum no per
centage shall be added.
The compensation herein provided shall be received by the contractor
as payment in full for extra work done on the "force account" basis and
GENERAL PROVISIONS
23
shall include superintendence, overhead and profit. For all work done on
the "force account" basis the contractor shall furnish certified copies of
the payroll on itemized forms provided for that purpose, invoices of all
material and such other detailed information as may be required by the
engineer.
J. 9. 5. Payment
Payments.
If
to complete
the unaccepted
or
24
I.
HIGHWAY
BRIDGES
DIVISION
II
Construction
SECTION I Excavation
and Fill
2. 1. 1. General,
whatever
2. 1. 2. Preservation
of Channel.
If
2.
I.
3. Depth of Footings.
2. 1. 4. Preparation of Foundations
for
Footings.
All rock or other hard foundation material shall be freed from all loose
material, cleaned and cut to a firm surface, either level, stepped, or rough
HIGHWAY
26
BRIDGES
special care shall be taken not to disturb the bottom of the excavation and
the final removal of the foundation material to grade shall not be made until
just before the masonry is to be placed.
2.
J.
5. Cofferdams
and Cribs.
(a)
General.
Cofferdams and cribs for foundation construction
shall be carried to
adequate depths and heights, be safely designed and constructed, and be
made as water-tight as is necessary for the proper performance of the work
which must be done inside them.
In general, the interior dimensions of
cofferdams and cribs shall be such as to give sufficient clearance for the
construction of forms and the inspection of their exteriors, and to permit
pumping outside of the forms. Cofferdams or cribs which are tilted or moved
laterally during the process of sinking shall be righted, reset or enlarged
so as to provide the necessary clearance and this shall be at the sole expense
of the contractor.
When conditions are encountered which, in the opinion of the engineer,
render it impracticable to unwater the foundation before placing masonry,
he may require the construction of a concrete foundation seal of such
dimensions as may be necessary.
The foundation shall then be pumped
out and the balance of the masonry placed in the dry. When weighted
cribs are employed and the weight is utilized to partially overcome the
hydro-static pressure acting against the bottom of the foundation seal,
special anchorage such as dowels or keys shall be provided to transfer the
entire weight of the crib into the foundation seal. During the placing of a
foundation seal, the elevation of the water inside the cofferdam shall be
controlled to prevent any flow through the seal and if the cofferdam is to
remain in place, it shall be vented or ported at low water level.
(b) Protection of
Concrete.
Cofferdams or cribs shall be constructed so as to protect green concrete
against damage from a sudden rising of the stream and to prevent dam
age to the foundation by erosion.
No timber or bracing shall be left in
cofferdams or cribs in such a way as to extend into the substructure ma
sonry, without written permission from the engineer.
( c)
Drawings
Required.
( d)
Removal.
CONSTRUCTION
27
I. 7. Inspection.
After each excavation is completed, the contractor shall notify the engi
neer, and no masonry shall be placed until the engineer has approved the
depth of the excavation and the character of the foundation material.
2. 1. 8. Back-fill.
All material
engineer
traneous
All
material.
or other
the sur
back-fill
shall be
The fill behind abutments and wing walls of all bridge structures shall
in horizontal layers not to exceed 12 inches in thickness and
well compacted. The back-fill in front of such units shall be placed first
to prevent the possibility of forward movement.
Special precautions shall
be taken to prevent any wedging action against the masonry, and the slope
bounding the excavation for abutments and wing walls shall be destroyed
Jetting of the fill be
by stepping or roughening to prevent wedge action.
hind abutments and wing walls shall not be permitted.
Fill placed around culverts and piers shall be deposited on both sides
to approximately the same elevation at the same time.
Adequate provision shall be made for the thorough drainage of all back
filling. French drains shall be placed at weep holes.
No back-fill shall be placed against any masonry abutment, wing wall
or culvert until permission shall have been given by the engineer and prefer
ably not until the masonry has been in place 14 days, or until test cylinder?
show the strength to be twice the working stress used in the design.
Back-filling of sectional plate pipes and arches shall be done in accord
ance with articles 2. 23. 5. and 2. 23. 6.
be deposited
For filled spandrel arches, the filling shall be carefully placed in such
manner as to load the ring uniformly and symmetrically. The filling ma
terial shall be acceptable to the engineer and shall be placed in horizontal
layers, not to exceed 12 inches in thickness, carefully tamped and brought
Wedge shaped sections of filling
up simultaneously
from both haunches.
material against spandrels, wings or abutments will not be permitted.
2. 1. 10. Approach Embankment.
When the contract for any bridge structure requires the placement of
approach embankments, they shall be constructed and paid for in accordance
with the highway specifications governing this class of construction.
2. 1. 11. Classification
set
of Excavation.
Classification, if any, of excavation
forth in the proposal.
will be indicated
HIGHWAY
28
2.1.
12. Measurement
BRIDGES
and Payment.
Payment for foundation excavation shall include the cost of all labor,
material, equipment, and other items that may be necessary or convenient
to the successful completion of the excavation to the elevation of the bot
tom of the footings. It shall also include the cost of removing cofferdams
and any surplus material which may have been thrown up during the proc
ess of excavation, and shall include the cost of back-filling in a compacted
Any
condition an amount of material equal to the amount of excavation.
back-fill required in excess of the amount excavated shall be paid for as
extra work unless a price for extra back-fill is included in the contract.
The yardage to be paid for shall be the actual number of cubic yards in
original position, of material acceptably excavated in conformity with the
plans or as directed by the engineer, but no yardage shall be included in
the measurement for payment which is outside of a volume bounded by
vertical planes 18 inches outside of and parallel to the neat lines of the
footing. The cross-sectional area measured shall not include water or other
liquids, but shall include mud, muck and other similar semi-solids.
The top
and bottom limits of computed volume shall be the original ground surface
and the bottom of the completed footing.
When it is necessary, in the opinion of the engineer, to carry the
foundations below the elevations shown on the plans, the excavation for
the first three feet of additional depth will be included in the quantity for
which payment will be made under the item Foundation Excavation.
Ex
cavation below this additional depth will be paid for as extra work, unless
the contractor is willing to accept payment at contract prices.
SECTION 2 Sheet
2. 2.
Piles
General.
CONSTRUCTION
2. 2. 4
29
Steel sheet piles shall be of the type and weight indicated on the plans
or designated in the special provisions and of the material required in
division IV. The piles, when in place in the completed structure, shall be
practically water-tight at the joints. Painting of steel sheet piles shall
conform to article 2. 3. 17.
2. 2. 5. Measurement
and Payment.
Payment for sheet piles shall include the cost of furnishing, driving and
cutting off. Payment will be made on the basis of the piles driven as ap
proved by the engineer, except that a deduction from the payment will be
made in an amount equal to the salvage value of the material cut off after
driving.
Timber, concrete, and steel sheet piles will be paid for at the contract
price per square foot.
2. 3. 1. Materials.
SECTION 3 Bearing
Piles
of division IV.
( a)
Excavation.
In general, piles shall not be driven until after the excavation is com
plete. Any material forced up between the piles shall be removed to correct
elevation without cost to the Commission before masonry for the foundation
is placed.
(b)
Caps.
The heads of all concrete piles, and the heads of timber piles, when
the nature of the driving is such as to unduly injure them, shall be pro
tected by caps of approved design, preferably having a rope or other suit
able cushion next to the pile head and fitting into a casting which in turn
When the area of the head of any timber
supports a timber shock block.
pile is greater than that of the face of the hammer, a suitable cap shall
be provided to distribute the blow of the hammer throughout the cross
section of the pile and thus avoid, as far as possible, the tendency to split
or shatter the pile.
For special types of piling, driving heads, mandrels, or other devices in
shall be provided so
accordance with the manufacturers' recommendation
that the pile may be driven without injury.
For steel piling the heads shall be cut squarely and a driving cap shall
be provided to hold the axis of the pile in line with the axis of the hammer.
(c) Collars.
(d) Pointing.
Timber piles shall be pointed where soil conditions require it. When
necessary, the piles shall be shod with metal shoes of a design satisfactory
HIGHWAY BRIDGES
30
to the engineer, the points of the piles being carefully shaped to secure an
even and uniform bearing on the shoes.
(f)
2. 3. 4. Methods
(a)
2. 3. 17.
of Driving.
General.
fe)
( d) Additional Equipment.
Leads.
Pile driver
(f)
Followers.
The driving of piling with followers shall be avoided if practicable and
shall be done only under written permission of the engineer.
When fol
lowers are used, one pile from every group of 10 shall be a long pile driven
without a follower, and shall be used as a test pile to determine the average
bearing power of the group.
CONSTRUCTION
81
( g)
Water Jets.
When water jets are used, the number of jets and the volume and
pressure of water at the jet nozzles shall be sufficient to freely erode the
material adjacent to the pile. The plant shall have sufficient capacity to
deliver at all times at least 100 pounds per square inch pressure at two
%-inch jet nozzles. Before the desired penetration is reached, the jets shall
be withdrawn and the piles shall be driven with the hammer to secure the
final penetration.
(h)
Accuracy of Driving.
Piles shall be driven with a variation of not more than % inch per
foot from the vertical or from the batter shown on the plans, except that
piles for trestle bents shall be so driven that the cap may be placed in its
proper location without inducing excessive stresses in the piles, and founda
tion piles shall not be out of the position shown on the plan more than 6
inches after driving.
2. 3. 5. Defective
Piles.
The procedure incident to the driving of piles shall not subject them
to excessive and undue abuse producing crushing and spalling of the con
crete, injurious splitting, splintering and brooming of the wood or deforma
tion of the steel. Manipulation of piles to force them into proper position
Any pile
considered by the engineer to be excessive will not be permitted.
damaged by reason of internal defects, or by improper driving or driven out
of its proper location or driven below the elevation fixed by the plans or
by the engineer, shall be corrected at the contractor's expense by one of
the following methods approved by the engineer for the pile in question :
(1) The pile shall be withdrawn and replaced by a new and if neces
sary, a longer pile.
(2) A second pile shall be driven adjacent to the defective or low pile.
(3) The pile shall be spliced or built up as otherwise provided herein
or a sufficient portion of the footing extended to properly embed the pile.
Timber piles shall not be spliced without specific permission of the engineer.
All piles pushed up by the driving of adjacent piles or by any other cause
shall be driven down again.
2. 3. 6. Determination of Bearing Values.
( a) Loading
Test*.
shall
be determined
HIGHWAY
32
2WH
S+1.0
2WH
S+0.1
BRIDGES
2H (W+Ap)
Twice the height of the bounce shall be deducted from "H" to determine
its value in the formula.
Unless otherwise ordered by the engineer timber piling shall be driven
to the bearing value given on the plans or in the supplemental specifications.
If bearing values are not given, timber piling shall be driven to a minimum
value of twenty tons.
In case water jets are used in connection with the driving, the bear
ing power shall be determined by the above formulas from the results of
driving after the jets have been withdrawn, or a load test may be applied.
Concrete and Steel Piles.
When not driven to practical refusal the bearing value for concrete
and steel piles preferably shall be determined by means of loading tests
above specified.
In the absence of loading tests, their safe bearing values
may be roughly approximated
by the formulas specified for timber piles.
However, the character of the soil penetrated, conditions of driving, dis
tributions, sizes, lengths and weights of the piles, shells or cores driven, and
the computed load per pile shall be given due consideration
in determining
the probable safe bearing value of concrete and steel piles.
( c)
2. 3. 7. Test Piles.
When required, the contractor shall drive test piles of a length and at
the location designated by the engineer.
These piles shall be of greater
length than the length assumed in the design in order to provide for any
variation in soil conditions.
2. 3. 8. Order Lists
for Piling.
The contractor shall furnish piles in accordance with an itemized list,
which shall be furnished by the engineer, showing the number and length
of all piles.
In determining lengths of piles for ordering and for footage to be in
cluded in the contract, the lengths given in the order list shall be based on
the lengths which are assumed to remain in the completed structure. The
contractor shall, at his own expense, increase the lengths given to provide
for fresh heading and for such additional length as may be necessary to
suit the contractor's method of operation.
CONSTRUCTION
2. 3. 9. Storage and Handling of Timber Piles.
The method of storing and handling shall be such as to avoid injury
to the piles.
Special care shall be taken to avoid breaking the surface of
treated piles and cant-hooks, dogs or pike-poles shall not be used. Cuts or
breaks in the surface of treated piling shall be given three brush coats of
hot creosote oil of approved quality and hot creosote oil shall be poured
into all bolt holes.
2. 3. 10. Cutting off Timber Piles.
The tops of all piling shall be sawed to a true plane, as shown on the
plans, and at the elevation fixed by the engineer.
Piles which support tim
ber caps or grillage shall be sawed to conform to the plane of the bottom
of the superimposed structure. In general, the length of pile above the
elevation of cut-off shall be sufficient to permit the complete removal of
all material injured by driving, but piles driven to very nearly the cut-off
elevation shall be carefully adzed or otherwise freed from all "broomed"
splintered or otherwise injured material.
2. 3. 11. Cutting off Steel or Steel Shell Piles.
the connection
shall
be
protected
as specified
(b)
Class
Class
of
Concrete.
concrete shall be used for precast
concrete piles.
(d) Reinforcement.
Reinforcement shall
be placed
II
plans.
(e)
Casting.
HIGHWAY
34
BRIDGES
(f)
to a uniform,
FinUh.
(a)
of
Cast-in-Place
Concrete Piles.
General.
Piles shall
be constructed
( c)
Class of Concrete.
Class A concrete shall be used for cast-in-place
(d) Reinforcement.
Reinforcement shall
be placed
piles.
mental specifications.
(e) Placing
Concrete.
No concrete shall
CONSTRUCTION
position.
concrete
35
be removed
before the
is placed.
2. 3. 16. Extensions
or "Build-Vps."
Extensions, splices or "build-ups" on concrete piles, when necessary,
shall be made as follows:
After the driving is completed, the concrete at the end of the pile shall
be cut away, leaving the reinforcing steel exposed for a length of 40 diam
The final cut of the concrete shall be perpendicular to the axis of
eters.
the pile. Reinforcement similar to that used in the pile shall be securely
fastened to the projecting steel and the necessary form work shall be placed,
The concrete shall be
care being taken to prevent leakage along the pile.
of the same quality as that used in the pile. Just prior to placing con
crete the top of the pile shall be thoroughly wetted and covered with a
thin coating of neat cement, retempered mortar or other suitable bonding
material. The forms shall remain in place not less than seven days and
shall then be carefully removed and the entire exposed surface of the pile
finished
as above specified.
17. Painting
2. 3.
2. 3. 18. Measurement
(a)
and Payment.
General.
Piling, whether
to Methods
A or B
be
(b) Method A.
For furnishing and driving piles at the contract price per linear foot.
(1) Cutoff. The total cutoff of piling shall be paid for at the prices set
forth by the Commission, in the special provisions for those of the following
items incorporated in the work:
Cutoff,
Cutoff,
Cutoff,
Cutoff,
Cutoff,
$
$
$
.
$
$
(2) Furnishing and Driving. The number of linear feet to be paid for
shall be the actual length of piles remaining in the completed structure
and the number of linear feet of cutoff to be paid for shall be the actual
number of linear feet cut off, except that no allowance will be made for
lengths in excess of those ordered by the engineer, and except that if the
contractor casts concrete piles full length of the reinforcing bars to facili
tate driving, no payment will be made for that portion where concrete must
on the plans.
be removed in order that bars may project as shown
If paid for as "cutoff," cutoff material (if the cutoff is in excess of 3 feet
Cutoff material
in length) shall become the property of the Commission.
3 feet or less in length, and other cutoff material which, in the opinion of
the engineer, is not worth salvaging shall be disposed of to the satisfaction
of the engineer.
HIGHWAY
36
BRIDGES
(3) Payment for Furnishing and Driving Piles. Payment for furnish
ing and driving piles shall include the material and work specified under
"Payment for Furnishing Piles" and "Payment for Driving Piles" Method
B.
(c)
Method B.
For driving
(d) Falsework
(e) Additional
If
Requirements.
the length of wood piles, steel piles or steel pile shells
designated
CONSTRUCTION
37
work.
If
3. 19
Payment
for
Test Piles.
for Loading
Tests.
Payment for loading tests shall include the cost of all material, equip
ment and labor incidental to making the loading test or tests as directed
by the engineer, or as specified in the special provisions. Payment shall be
made on the basis of the contract price for pile loading tests, or, in the
absence of such a price, shall be made on the basis of extra work
2. 4. 1.
SECTION
General.
Concrete
Masonry
2. 4. 2.
locations.
of
Cement.
HIGHWAY
88
BRIDGES
the cement is to be used. Stored cement shall meet the test requirements
at any time after storage when a retest is ordered by the engineer.
On small jobs, storage in the open may be permitted by written authori
zation from the engineer, in which case a raised platform and ample
waterproof covering shall be provided.
When required by the terms of the contract, the contractor shall keep
accurate records of the deliveries of cement and of its use in the work.
Copies of these records shall be supplied to the engineer in such form as
may be required.
4.Classes of Concrete.
The classes of concrete are A, B, C, X and Y. Each class of concrete
shall be used in that part of the structure in which it is called for on the
plans, or where directed by the engineer.
Unless otherwise specified,
The following requirements
shall govern
Class A concrete shall be used.
unless otherwise shown on the plans:
Class A concrete shall be used for all superstructures, except as noted
below, and for reinforced substructures except where the sections are
massive and lightly reinforced. The more important items of work included
are slabs, beams, girders, columns, arch ribs, box culverts, reinforced abut
ments and retaining walls and reinforced footings. Class A concrete shall
be used for precast piles and cribbing. Class A concrete shall also be used
for work exposed to salt water.
Concrete deposited in water shall be Class A with 10 per cent additional
cement.
Class B concrete shall be used for mass footings, pedestals,
massive pier shafts and gravity walls, with none or only a small amount
of reinforcing.
Class C concrete shall be used for very massive unreinforced sections.
Class X coB.tfrete shall be used for massive sections, lightly reinforced
where a higher grade than Class B is desired.
Class Y concrete shall be used in thin reinforced sections, for handrails
except as specified for precast railing under "Railings," and for filler in
steel grid floors.
2. 4.
2. 4. 5.L-Classification
and Proportioning
of Concrete Mixtures.
Class
Designated
Minimum compres
sive strength
at 28 days
size of coarse
Use
aggregate
square openings
in. to No. 4
2,200
in. to No. 4
1,500
3,000
2%
2
in. to No. 4
in. to No. 4
3,000
V2 in. to No. 4
General
use and
concrete
ex
posed to sea water.
Massive sections or lightly rein
forced sections.
Massive unreinforced sections.
Massive sections or lightly rein
forced sections.
Thin reinforced sections or hand
rails.
The concrete of the various classes given in the above table shall be
designed so as to secure concrete having not less than the strengths specified
CONSTRUCTION
39
(a) Method A.
The proportions of cement, aggregates and water necessary to conform
to these specifications shall be determined by means of preliminary labora
tory tests on concrete made with the cement and aggregates which are to
be used in the work.
For each class of concrete, the proportions by weight of cement, fine
and coarse aggregate and the quantity of water will be designated by the
engineer so as to meet the requirements given in the following table :
Designated
Class
1!
C
size of coarse
aggregate
of concrete
square
openings
in.
in.
2'/j in.
2
in.
% in.
to No. 4
to No. 4
to No. 4
to No. 4
to No. 4
1
2
Minimum
strength at
Maximum net
water content
per bag of
gallona
6.0
7.0
8.5
6.0
6.0
compressive
28 days
cement
Consistency,
range in slump
regular
vi
placing brated
inches
3-5
2-3
2-3
2-3
3-5
2-4
1-2
1-2
1-2
2-4
If
If
HIGHWAY BRIDGES
40
If
Proportions Based on
(b) Method B.
The weights of fine and coarse aggregate per bag (94 pounds) of
cement, the maximum size of coarse aggregate and the consistency for each
class of concrete shall be as follows:
Class
of
concrete
Amount of saturated
surface dry aggregate
per bag (94 pounds)
of cement
Minimum
Designated
size of coarse
aggregate
cement
factor
Bags per
square
openings
cu. 3rd.
Fine
Coarse
Founds
Pounds
Gravel Coarse
A
B
C
in
in.
2% in.
2
in.
% in.
1
2
to
to
to
to
to
No.
No.
No.
No.
No.
4
4
4
4
4
6.S
5.0
4.0
6.0
7.0
175
250
325
199
177
Stone Coarse
A
B
C
in
in.
in.
2%
2
in.
% in.
1
2
to No. 4
to No. 4
to No. 4
to No. 4
to No. 4
6.5
5.0
4.0
6.0
7.0
199
283
868
225
199
Slag Coarse
A
B
C
in
in.
in.
2%
2
in.
% in.
1
2
to No. 4
to No. 4
to No. 4
to No. 4
to No. 4
6.5
5.0
4.0
6.0
7.0
207
294
382
235
205
Maximum
net water
content
per bag
of cement
Gallons
Consistency range in
slump
Regular
Placing
Vibrated
IncheB
Inches
Aggregate
300
408
524
384
250
6.0
7.0
8.5
6.0
6.0
8-5
2-3
2-3
2-8
3-5
2-4
1-2
1-2
1-2
2-4
6.0
7.0
8.5
6.0
6.0
8-5
2-8
2-8
2-8
8-5
2-4
1-2
1-2
1-2
2-4
6.0
7.0
8.5
6.0
6.0
8-5
2-8
2-8
2-8
8-5
2-4
1-2
1-2
1-2
2-4
Aggregate
276
375
481
308
228
Aggregate
227
809
396
253
188
Note. Using the maximum allowable water content, the weights given above when mul
tiplied by the corresponding cement factors will furnish a cubic yard of concrete (absolute
volume ) .
The consistency range and the ratios of fine aggregate to total aggregate computed from
the weights shown above are based on the methods of placing which do not involve high fre
quency vibration. Where vibration is employed the ratios of fine aggregate to total aggregate
may be reduced about 5 per cent.
The minimum cement factor specified is for usual climatic conditions and quality of
concrete materials.
Where climatic conditions are favorable, and where concrete materials
available produce exceptionally high strength concrete, the engineer may lower the specified
cement factor, but not to exceed 10 per cent, with suitable adjustment in water content.
When a reduction is made, it shall be stipulated in the special provisions.
CONSTRUCTION
41
The proportions by weight given in the table above are based on the
maintenance of an approximately constant quantity of cement per cubic
The proportions are based on the use of aggregates
yard of concrete.
having bulk specific gravities in a saturated surface-dry condition of 2.65
plus or minus 0.05 for sand, gravel and crushed stone, and 2.25 plus or
minus 0.05 for crushed slag. For other specific gravities, the weights shall
be corrected by multiplying the weights shown in the table by the ratio of
the specific gravities of the aggregates used and those used in computing
the table. The bulk specific gravity tests shall be made in accordance with
Methods of Sampling and Testing A. A. S. H. O. Method T-84-45, section 6,
and Method T-85-45, section 6 (A. S. T. M. Designation C-128-42 and
C-127-42, respectively).
Since the weights given in the table are computed for aggregates in
a saturated surface-dry condition, the batch weights shall be corrected to
accord with the moisture condition of the aggregates
delivered to the
measuring bin. Absorption tests shall be made in accordance with Methods
of Sampling and Testing A. A. S. H. O. Method T-84-45, section 8, and
Method T-85-45, section 8 (A. S. T. M. Designation C-128-42 and C-127-42,
respectively).
The weights of sand and coarse aggregate given in the table have been
calculated on the basis of using a well-eraded natural sand in combination
These weights are subject to change,
with a well-graded coarse aggregate.
depending upon the gradation of the materials furnished by the contractor.
The weights of fine and coarse aggregate will be adjusted by the
engineer to insure concrete of satisfactory plasticity and workability, using
During
not more than the maximum permissible net water content shown.
the progress of the work, the total weight of aggregate per bag of cement
shall not be changed except under the following conditions:
(1) If concrete of satisfactory plasticity and workability cannot be
made without exceeding the maximum net water content, the engineer shall
reduce the total weight of aggregate by an amount sufficient to insure that
the maximum net water content will not be exceeded, and the contractor
shall not receive additional compensation for any extra cement which may
be necessary by reason of such adjustment.
(2) If during the progress of the work the specific gravity of one or
changes, the batch weights shall be changed
both of the aggregates
accordingly.
(3) The compression tests used in determining the strength of concrete
shall conform to Method T-23-45, "Method of Making and Storing Com
pression Specimens of Concrete in the Field," and Method T-22-45, "Method
of Making Compression Tests of Concrete," "Methods of Sampling and
Testing," of the A. A. S. H. 0. (A. S. T. M. Designations C-31-44 and
C-39-44, respectively) .
2. 4. 6. Consistency.
Concrete shall have a consistency such that it will be workable in the
It shall be of such a consistency that it will flow around
required position.
reinforcing steel but individual particles of the coarse aggregate when
isolated shall show a coating of mortar containing its proportionate amount
of sand. The consistency of concrete shall be gauged by the ability of the
equipment to properly place it and not by the difficulty in mixing or trans
porting. The quantity of mixing water shall be determined by the engineer
in accordance with article 2. 4. 5. and shall not be varied without his consent.
In general the slump, for concrete placed by the usual methods, when
HIGHWAY
42
BRIDGES
made in accordance with the Standard Method of Slump Test for Consistency
of Portland Cement Concrete, A. A. S. H. O., Method T-119-42 (A. S. T. M.
Designation C-143-39), shall be as follows:
inches.
sections,
of Materials.
Materials shall
be measured
or where
2. 4. 8. Mixing Concrete.
(a) General.
Unless otherwise authorized
mixed at the site.
(b) Mixing
at Site.
Concrete shall be thoroughly mixed in a batch mixer of an approved
size and type which will insure a uniform distribution of the materials
throughout the mass.
The mixer shall be equipped with adequate water storage and a device
for accurately measuring and automatically controlling the amount of
CONSTRUCTION
HIGHWAY BRIDGES
44
mixer or agitator. The mixing time in the truck mixer or agitator equipped
with adequate mixing blades shall be as specified for truck mixing.
for mixing
at the site.
( f) Time of Hauling
(h)
Delivery.
(i)
Retempering.
The concrete shall be mixed only in such quantities as are required for
immediate use and any which has developed initial set shall not be used.
Concrete which has partially hardened shall not be retempered or remixed.
(a)
General.
In preparation for the placing of concrete all sawdust, chips, and other
construction debris and extraneous matter shall be removed from the in
terior of forms. Struts, stays and braces, serving temporarily to hold the
forms in correct shape and alignment, pending the placing of concrete at
their locations, shall be removed when the concrete placing has reached an
elevation rendering their service unnecessary.
These temporary members
shall be entirely removed from the forms and not buried in the concrete.
No concrete shall be used which does not reach its final position in
the forms within the time stipulated under "Time of Hauling and Placing
Mixed Concrete," article 2. 4. 8.
Concrete shall be placed so as to avoid segregation of the materials and
the displacement of the reinforcement.
The use of long troughs, chutes and
pipes for conveying concrete from the mixer to the forms shall be permitted
only on written authorization of the engineer.
In case an inferior quality
of concrete is produced by the use of such conveyors, the engineer may
CONSTRUCTION
45
shall
be placed
12 inches
HIGHWAY BRIDGES
46
If
(b)
Culverts.
general, the base slab or footings of box culverts shall be placed and
In this
allowed to set before the remainder of the culvert is constructed.
case suitable provision shall be made for bonding the sidewalls to the culvert
base, preferably by means of raised longitudinal keys so constructed as to
prevent, as far as possible, the percolation of water through the construc
In
tion joint.
Before concrete is placed in the sidewalls, the culvert footings shall be
thoroughly cleaned of all shavings, sticks, sawdust, or other extraneous
material and the surface carefully chipped and roughened in accordance
with the method of bonding construction joints as specified herein.
In the construction of box culverts 4 feet or less in height, the sidewalls
When this method of con
and top slab may be constructed as a monolith.
struction is used, any necessary construction joints shall be vertical and
at right angles to the axis of the culvert.
In the construction of box culverts more than 4 feet in height, the
concrete in the walls shall be placed and allowed to set before the top slab
is placed.
In this case, appropriate keys shall be left in the sidewalls for
anchoring the cover slab.
Each wing wall shall be constructed, if possible, as a monolith.
Con
struction joints, where unavoidable, shall be horizontal and so located that
no joint will be visible in the exposed face of the wing wall above the
ground line.
Girders, Slabs and Columns.
Concrete, preferably, shall be deposited by beginning at the center of
the span and working from the center toward the ends. Concrete in girders
(c)
CONSTRUCTION
47
shall be deposited uniformly for the full length of the girder and brought
up evenly in horizontal layers.
Concrete in girder haunches less than 3 feet in height shall be placed
at the same time as that in the girder stem, and the column or abutment
Whenever any
tops shall be cut back to form seats for the haunches.
haunch or fillet has a vertical height of 3 feet or more, the abutment or
columns, the haunch and the girder shall be placed in three successive
stages; first, up to the lower side of the haunch; second, to the lower side
of the girder; and third, to completion.
Concrete in slab spans shall be placed in one continuous operation for
each span unless otherwise provided.
The floors and girders of through girder superstructures shall be placed
in one continuous operation unless otherwise specified, in which case special
shear anchorage shall be provided to insure monolithic action between
girder and floor.
Concrete in T-beam or deck girder spans may be placed in one con
tinuous operation or may be placed in two separate operations, each of
which shall be continuous; first, to the top of the girder stems, and second,
to completion.
In the latter case, the bond between stem and slab shall be
positive and mechanical, and shall be secured by means of suitable shear
The size and location of these keys
keys in the top of the girder stem.
shall be computed. In general, suitable keys may be formed by the use of
timber blocks approximately 2 by 4 inches in cross-section and having a
length 4 inches less than the width of the girder stem. These key blocks
shall be spaced along the girder stems as required, but the spacing shall
be not greater than 1 foot center to center.
The blocks shall be beveled and
oiled in such manner as to insure their ready removal, and they shall be
removed as soon as the concrete has set sufficiently to retain its shape.
Concrete in columns shall be placed in one continuous operation, unless
The concrete shall be allowed to set at least 12 hours
otherwise directed.
before the caps are placed.
Unless otherwise permitted by the engineer, no concrete shall be placed
in the superstructure until the column forms have been stripped sufficiently
The load of the
to determine the character of the concrete in the columns.
superstructure shall not be allowed to come upon the bents until they have
been in place at least 14 days, unless otherwise permitted by the engineer.
(d)
Arches.
operation.
48
HIGHWAY
BRIDGES
cleaned.
2. 4. 11. Pumping.
CONSTRUCTION
above the concrete.
49
be
maintained between
4 and 8 inches.
Unwatering may proceed when the concrete seal is sufficiently hard and
strong. All laitance or other unsatisfactory material shall be removed from
the exposed surface by scraping, chipping or other means which will not
injure the surface of the concrete.
2. 4. 13. Construction
(a)
Joints.
General.
If
(b) Bonding.
Concrete.
to Sea Water.
50
HIGHWAY
BRIDGES
ment steel shall be not less than 4 inches. The concrete shall be mixed for
a period of not less than 2 minutes and the water content of the mixture
shall be carefully controlled and regulated so as to produce concrete of
maximum impermeability. The concrete shall be thoroughly compacted and
stone pockets shall be avoided.
No construction joints shall be formed
between levels of extreme low water and extreme high water as determined
Between these levels sea water shall not come in direct
by the engineer.
contact with the concrete for a period of not less than 30 days. The original
surface, as the concrete comes from the forms, shall be left undisturbed.
2. 4. 16. Concrete Exposed
to
All forms shall be of wood or metal and shall be built mortartight and
of sufficient rigidity to prevent distortion due to the pressure of the concrete
operations.
and other loads incident to the construction
Forms shall be
constructed and maintained so as to prevent warping and the opening of
joints due to shrinkage of the lumber.
The forms shall be substantial and unyielding and shall be so designed
that the finished concrete will conform to the proper dimensions and con
tours.
The design of the forms shall take into account the effect of
vibration of concrete as it is placed.
Forms for exposed surfaces shall be made of dressed lumber of uniform
thickness with or without a form liner of an approved type, and mortar
CONSTRUCTION
51
tight. Forms shall be filleted at all sharp corners and shall be given a
bevel or draft in the case of all projections, such as girders and copings,
to insure easy removal.
Metal ties or anchorages within the forms shall be so constructed as
to permit their removal to a depth of at least 2 inches from the face without
injury to the concrete. In case ordinary wire ties are permitted, all wires,
upon removal of the forms, shall be cut back at least V* inch from the
face of the concrete with chisels or nippers; for green concrete, nippers
All fittings for metal ties shall be of such design that, upon
are necessary.
their removal, the cavities which are left will be of the smallest possible
size. The cavities shall be filled with cement mortar and the surface left
sound, smooth, even and uniform in color.
All forms shall be set and maintained true to the line designated until
Forms shall remain in place for
the concrete is sufficiently hardened.
When forms
periods which shall be determined as hereinafter specified.
appear to be unsatisfactory in any way, either before or during' the placing
of concrete, the engineer shall order the work stopped until the defects
have been corrected.
The shape, strength, rigidity, watertightness and surface smoothness
of re-used forms shall be maintained at all times. Any warped or bulged
Forms which are unsatis
lumber must be re-sized before being re-used.
factory in any respect shall not be re-used.
For narrow walls and columns, where the bottom of the form is inac
cessible, the lower form boards shall be left loose so that they may be
removed for cleaning out extraneous material immediately
before placing
the concrete.
All forms shall be treated with oil or saturated with water immediately
For rail members or other members with
before placing the concrete.
exposed faces, the forms shall be treated with an approved oil to prevent
the adherence of concrete.
Any material which will adhere to or discolor
the concrete shall not be used.
2. 4. 19. Removal
If
Arch
centers
14 days
14 days
7-14 days
12-24 hrs.
1-7 days
12-24 hrs.
If
HIGHWAY BRIDGES
52
favorable than the most unfavorable conditions for the portions of the
concrete which the beams represent.
Methods of form removal likely to cause overstressing of the concrete
shall not be used. In general, the forms shall be removed from the bottom
upwards.
Forms and their supports shall not be removed without the
approval of the engineer.
Supports shall be removed in such a manner as
to permit the concrete to uniformly and gradually take the stresses due
to its own weight.
In general, arch centering shall be struck and the arch made selfsupporting before the railing or coping is placed.
This precaution is
essential in order to avoid jamming of the expansion joints and variations
in alignment.
For filled spandrel arches, such portions of the spandrel
walls shall be left for construction subsequent to the striking of centers,
as may be necessary to avoid jamming of the expansion joints.
Centers shall be gradually and uniformly lowered in such a manner
as to avoid injurious stresses in any part of the structure.
In arch struc
tures of two or more spans, the sequence of striking centers shall be
specified or approved by the engineer.
2. 4. 20. Concreting
in Cold Weather.
F. without written
as directed
by the engineer.
If
(a)
Open Joints.
Open joints shall be placed in the locations shown on the plans and
shall be constructed by the insertion and subsequent removal of a wood
CONSTRUCTION
53
strip, metal plate or other approved material. The insertion and removal
of the template shall be accomplished without chipping or breaking the
Reinforcement shall not extend across an open
corners of the concrete.
joint unless so specified on the plans.
manner.
(d)
Water Stops.
(e) Bearing
Devices.
If
54
HIGHWAY
BRIDGES
and parapets; but not on the tops and bottoms of floor slabs and sidewalks,
bottoms of beams and girders, sides of interior beams and girders, backwalls above bridge seat or the underside of copings. The surface finish on
piers and abutments shall include all exposed surfaces below bridge seat
to 1 foot below low water elevation or 2 feet below finished ground line
when such ground line is above the water surface.
Wing walls shall be
finished from the top to 2 feet below the finish slope lines on the outside
face and shall be finished on top and for a depth of 1 foot below the top
on the back sides.
Unless otherwise specified, roadway floors shall be given Class 6,
Finish of this character for panels and other like work may be secured
Air
by the use of a bushhammer, pick, crandall, or other approved tool.
No tooling shall be done until the
tools, preferably, shall be employed.
CONSTRUCTION
55
concrete has set for at least 14 days and as much longer as may be
necessary to prevent the aggregate particles from being "picked" out of the
surface.
The finished surface shall show a grouping of broken aggregate
particles in a matrix of mortar, each aggregate particle being in slight
relief.
2. 4. 27
(b) Floating.
After striking
may be substituted
for
Transverse Floating.
The transverse float shall be operated across the pavement by starting
at the edge and slowly moving to the center and back again to the edge.
The float shall then be moved forward one-half of its length and the above
Care shall be taken to preserve the crown and cross
operations repeated.
section of the pavement.
(d)
HIGHWAY BRIDGES
56
(e)
Straightedging.
the longitudinal floating has been completed and the excess water
removed, but while the concrete is still plastic, the slab surface shall be
tested for trueness with a straightedge.
For this purpose the contractor
shall furnish and use an accurate 10-foot straightedge swung from handles
3 feet longer than one-half the width of the slab.
The straightedge shall be held in successive positions parallel to the
road centerline and contact with the surface and the whole area gone over
from one side of the slab to the other as necessary.
Advance along the
deck shall be in successive stages of not more than one-half the length of
the straightedge.
Any depressions found shall be immediately filled with
freshly mixed concrete, struck off, consolidated and refinished.
High areas
shall be cut down and refinished.
The straightedge testing and refloating
shall continue until the entire surface is found to be free from observable
departures from the straightedge and the slab has the required grade and
contour, until there are no deviations of more than % inch under the 10-foot
straightedge.
After
( f) Final Finishing.
When the concrete has hardened sufficiently,
a broom finish.
The broom shall be of an approved type. The strokes shall
be square across the slab, from edge to edge, with adjacent strokes slightly
overlapped, and shall be made by drawing the broom without tearing the
concrete, but so as to produce regular corrugations not over % of an inch in
depth. The surface as thus finished shall be free from porous spots, irregu
larities, depressions and small pockets or rough spots such as may be
caused by accidental disturbing, during the final brooming, of particles of
coarse aggregate embedded near the surface.
2. 4. 30. Sidewalk
Finish.
(a)
Applied Mortar.
General.
(b) Proportions.
The proportion of cement to sand shall be based on dry and loose
volumes and shall not be less than one to four for encasement of steel
members, one to three for concrete repair, nor one to four and a half for
special linings.
( c)
Water Content.
not in excess of
gallons
be maintained
at a practicable
per sack of cement as placed.
minimum and
CONSTRUCTION
57
(d) Mixing.
The cement and sand shall be thoroughly mixed before being charged
into the machine.
The sand shall contain not less than 3 nor more than 6
per cent moisture by weight.
(e)
Nozzle Velocity.
f)
rebound.
Nozzle Position.
The nozzle shall be held in such a position and at such distance that
the stream of flowing material will impinge at approximately right angles
to the surface being covered without excessive impact.
(g) Rebound
Sand.
to be covered
(h) Forms.
The forms shall be structurally sufficient and of such design that
rebound or accumulated loose sand can freely escape or be readily removed.
Shooting strips should be used at corners, edges, and on surfaces where
necessary to obtain true lines and proper thickness.
(i) Joints.
The pneumatically applied mortar at the end of any day's work or
similar stopping periods shall be sloped off to a thin edge. Before placing
an adjacent section this sloped portion shall be thoroughly cleaned and
wetted.
(j)
Bond.
(k) Curing.
Pneumatically applied mortar shall be so applied, protected, and cured
as to prevent its temperature falling below 50 F., or a loss of moisture
from the surface for the periods indicated below:
(1)
(2)
days.
(I)
Reinforcement.
HIGHWAY
58
2. 4. 32. Measurement
BRIDGES
and Payment.
The payment for concrete of the various classes shall include compen
sation for all equipment, tools, material, falsework, forms, bracing, labor,
surface finish and all other items of expense required to complete the con
crete work shown on the plans, with the exception of reinforcing steel. The
payment for concrete shall include the cost of joint fillers, metal drains,
expansion joints and miscellaneous metal devices unless they are covered
The quantity of concrete involved in fillets,
by other items in the contract.
scorings and chamfers 1 square inch or less in cross-sectional area shall
Payment will be made on the basis of the actual yardage
be neglected.
within the neat lines of the structure as shown on the plans or revised by
authority of the engineer, except that deduction shall be rnade as follows:
(1) The volume of structural steel, including steel piling, encased in
concrete.
assuming
the
SECTION
Reinforcement
2. 5. 1. Material.
Before ordering material, all order lists and bending diagrams shall be
furnished by the contractor for the approval of the engineer, and no ma
terials shall be ordered until such lists and bending diagrams have been
The approval of order lists and bending diagrams by the engi
approved.
neer shall in no way relieve the contractor of responsibility for the correct
Any expense incident to the revision of
ness of such lists and diagrams.
material furnished in accordance with such lists and diagrams to make it
comply with the design drawings shall be borne by the contractor.
2. 5. 3. Protection
of Material.
When
Steel reinforcement shall be protected at all times from injury.
placed in the work, it shall be free from dirt, detrimental scale, paint, oil
However, when steel has, on its surface, detri
or other foreign substance.
CONSTRUCTION
69
it
may
be
2. 5. 4. Fabrication.
Bent bar reinforcement shall be cold bent to the shapes shown on the
plans, and unless otherwise provided on the plans or by authorization,
bends shall be made in accordance with the following requirements :
Stirrups and tie bars shall be bent around a pin having a diameter not
less than two times the minimum thickness of the bar.
Bends for other
bars shall be made around a pin having a diameter not less than six times
the minimum thickness except for bars larger than 1 inch, in which case
the bends shall be made around a pin of eight bar diameters.
Bar reinforcement shall be shipped in standard bundles, tagged and
marked in accordance with the Code of Standard Practice of the Concrete
Reinforcement Steel Institute.
2. 5. 5. Mesh Reinforcement.
of division IV,
2. 5. 6. Bar
Mat Reinforcement.
Bar mat reinforcement shall conform to the requirements
of division IV.
be straightened
into
2. 5. 8. Splicing.
HIGHWAY
60
BRIDGES
less than the minimum clear distance to other bars and the minimum
distance to the surface of the concrete specified in article 3. 7. 7. Welding
of reinforcing steel shall be done only if detailed on the plans or if authorized
Welding shall conform to the current speci
by the engineer in writing.
fications for Welded Highway and Railway Bridges of the American Weld
ing Society.
2. S. 9. Lapping.
Sheets of mesh or bar mat reinforcement shall overlap each other
sufficiently to maintain a uniform strength and shall be securely fastened
at the ends and edges. The edge lap shall not be less than one mesh in
width.
2. 5. 10. Substitutions.
in
pounds
per
foot
Round
. .
Square
. .
M"
Vs"
Vs"
3A"
Vs"
1"
0.167
0.376
0.668
1.043
1.502
2/44
2.670
0.850
3.400
V4'
4.303
5.313
7.650
The weight of reinforcement used in railings, when they are paid for on
a linear foot basis, shall not be included.
The weight of reinforcement in
precast piles and other items where the reinforcement is included in the
contract price for the item shall not be included.
No allowance will be made for clips, wire, separators, wire chairs, and
other material used in fastening the reinforcing in place.
bars are sub
stituted upon the contractor's request and as a result more steel is used
than specified, only the amount specified shall be included.
If
When laps are made for splices, other than those shown on the plans,
for the convenience of the contractor, the extra steel shall not be included.
2. S. 12. Payment.
CONSTRUCTION
61
to the requirements
mented as follows:
Stone.
The stone shall be kept free from dirt, oil or any other injurious ma
terial which may prevent the proper adhesion of the mortar or detract
from the appearance of the exposed surfaces.
Mortar.
Mortar for laying the stone and pointing shall be composed of one part
of portland cement and three parts of sand unless otherwise provided.
The
of division IV for "Sand for
sand shall conform to the requirements
Mortar."
2. 6. 3. Size of Stone.
They shall
The individual stones shall be large and well proportioned.
not be less than 12 nor more than 30 inches in thickness.
The thicknesses
of courses, if varied, shall diminish regularly from bottom to top of wall.
The size of ring stones in arches shall be as shown on the plans.
2. 6. 4. Surface Finishes of Stone.
of this specification
of stone are
for
a depth
HIGHWAY BRIDGES
62
Vertical joints of face stone shall be fine-finished and full to the square
for a depth of not less than 9 inches.
Exposed surfaces of the face stone shall be given the surface finish
indicated on the plans, with edges pitched to true lines and exact batter.
Face
Chisel drafts 1% inches wide shall be cut at all exterior corners.
stone forming the starling or nosing of piers shall be rough-finished
unless
otherwise
specified.
be permitted
2. 6. 6. Stretchers.
Stretchers shall have a width of bed of not less than 1% times their
thickness.
They shall have a length of not less than twice their thickness,
nor less than 3 feet, and not more than 3% times their thickness.
2. 6. 7. Headers.
Headers shall be placed in each course and shall have a width of not
less than 1% times their thickness.
In walls having a thickness of 4 feet
or less, the headers shall extend entirely through the wall. In walls of
greater thickness, the length of headers shall be not less than 2% times
their thickness when the course is 18 inches or less in height, and not less
Headers shall bond with the
than 4 feet in courses of greater height.
core or backing not less than 12 inches. Headers shall hold in the heart of
the wall the same size shown in the face and shall be spaced not further
apart than 8 feet center to center. There shall be at least one header to
every two stretchers.
2. 6. 8. Cores and Backing.
Cores and backing shall consist either of roughly bedded and jointed
headers and stretchers, as specified above, or of Class "B" or "C" concrete,
as may be specified.
When stone is used for cores or backing, at least % of the stone shall
be of the same size and character as the face stone and with parallel ends.
No course shall be less than 8 inches thick.
Concrete used for cores and backing shall conform to the requirements
specified for Concrete Masonry, division II.
The headers and stretchers in walls having a thickness of 3 feet or
less shall have a width or length equal to the full thickness of the wall.
No backing will be allowed.
2. 6. 9. Mixing
Mortar.
(a)
General.
Stone masonry shall not be constructed in freezing weather or when
the stone contains frost, except by written permission of the engineer and
subject to such conditions as he may require.
CONSTRUCTION
63
(b)
Face Stone.
Stone shall not be dropped upon or slid over the wall, nor will hammer
ing, rolling or turning of stones on the wall be allowed, but shall be care
fully set without jarring the stone already laid and they shall be handled
with a lewis or other appliance which will not cause disfigurement.
Each stone shall be cleaned and thoroughly saturated with water before
being set and the bed which is to receive it shall be cleaned and well
All stones shall be well bedded in freshly made mortar and
moistened.
settled in place with a suitable wooden maul before the setting of the mortar.
Whenever possible, the face joints shall be properly pointed before the
mortar sets. Joints which cannot be so pointed shall be prepared for point
ing by raking them out to a depth of 2 inches before the mortar has set.
The face surfaces of stones shall not be smeared with the mortar forced out
of the joints or that used in pointing. No pinning up of stones with spalls
will be permitted and no spalls will be permitted in beds.
Joints and beds shall be not less than % inch nor more than % inch
in thickness and the thickness of the joint or bed shall be uniform
throughout.
The stones in any one course shall be placed so as to form bonds of not
Headers shall be
less than 12 inches with the stones of adjoining courses.
placed over stretchers and, in general, the headers of each course shall
equally divide the spaces between the headers of adjoining courses, but no
header shall be placed over a joint and no joint shall be made over a header.
(c)
Stone backing shall be laid in the same manner as specified above for
face stone, with headers interlocking with face headers when the thickness
of the wall will permit. Backing shall be laid to break joints with the face
stone. Stone cores shall be laid in full mortar beds so as to bond not less
Bed
than 12 inches with face and backing stone and with each other.
joints in cores and backing shall not exceed 1 inch and vertical joints shall
not exceed 4 inches in thickness.
(d)
Concrete
In case any stone is moved or the joint broken, the stone shall be
taken up, the mortar thoroughly cleaned from bed and joints, and the stone
reset in fresh mortar.
HIGHWAY
64
BRIDGES
2. 6.
I5. Arches.
be as specified
2. 6. 16. Pointing.
Pointing shall not be done in freezing weather nor when the stone
contains frost.
Joints not pointed at the time the stone is laid shall be thoroughly wet
with clean water and filled with mortar. The mortar shall be well driven
into the joints and finished with an approved pointing tool. The wall shall
be kept wet while pointing is being done and in hot or dry weather the
pointed masonry shall be protected from the sun and kept wet for a period
of at least three days after completion.
CONSTRUCTION
65
After the pointing is completed and the mortar set, the wall shall
thoroughly cleaned and left in a neat and workmanlike condition.
2. 6. 17. Measurement
be
and Payment.
The quantity of stone masonry to be paid for under this item shall
be the number of cubic yards measured in the completed work and the
limiting dimensions shall not exceed those shown upon the plans or fixed
by the engineer.
The contract price shall include all labor, tools, materials
and other expense incidental to the satisfactory completion of the work.
2. 7. 1. Description.
Mortar rubble masonry, as here specified, shall include the classes com
monly known as coursed, random and random range work and shall consist
of roughly squared and dressed stone laid in cement mortar.
2. 7. 2. Materials.
mented
of division
IV
supple
Stone.
The stone shall be kept free from dirt, oil, or any other injurious
material which may prevent the proper adhesion of the mortar.
Mortar.
The mortar used shall conform as regards materials, proportions and
mixing to the mortar specified for "Ashlar Masonry."
2. 7. 3. Size.
Individual stones shall have a thickness of not less than 8 inches and
width of not less than 1 % times the thickness.
No stones, except headers,
shall have a length less than 1% times their width. Stone shall decrease
in thickness from bottom to top of wall.
The size of ring stones for arches shall be as shown on the plans.
a
2. 7. 4. Headers.
Headers shall hold in the heart of the wall the same size shown in the
They
face and shall extend not less than 12 inches into the core or backing.
shall occupy not less than % of the face area of the wall and shall be evenly
distributed.
Headers in walls 2 feet or less in thickness shall extend
entirely through the wall.
2. 7. 5. Shaping Stone.
The stones shall be roughly squared on joints, beds and faces. Selected
stone, roughly squared and pitched to line, shall be used at all angles and
ends of walls. If specified, all corners or angles in exterior surfaces shall
be finished with a chisel draft.
All shaping or dressing of stone shall be done before the stone is laid
in the wall, and no dressing or hammering which will loosen the stone will
be permitted after it is placed.
2. 7. 6. Laying Stone.
Stone masonry shall not be constructed in freezing weather or when the
of the engineer and
stone contains frost, except by written permission
subject to such conditions as he may require.
HIGHWAY
66
BRIDGES
The masonry shall be laid to line and in courses roughly leveled up.
The bottom or foundation courses shall be composed of large, selected stones
and all courses shall be laid with bearing beds parallel to the natural bed
of the material.
Each stone shall be cleaned and thoroughly saturated with water before
being set and the bed which is to receive it shall be cleaned and well
moistened.
All stones shall be well bedded in freshly made mortar. The
mortar joints shall be full and the stones carefully settled in place before
the mortar has set. No spalls will be permitted in the beds. Joints and
beds shall have an average thickness of not more than 1 inch.
Whenever possible the face joints shall be properly pointed before the
mortar becomes set. Joints which cannot be so pointed shall be prepared
for pointing by raking them out to a depth of 2 inches before the mortar
has set. The face surfaces of stones shall not be smeared with the mortar
forced out of the joints or that used in pointing.
The vertical joints in each course shall break joints with those in
adjoining courses at least 6 inches. In no case shall a vertical joint be so
located as to occur directly above or below a header.
In case any stone is moved or the joint broken, the stone shall be taken
up, the mortar thoroughly cleaned from bed and joints, and the stone reset
in fresh mortar.
2. 7. 7. Copings, Bridge Seats and Backwalls.
Copings, bridge seats and backwalls shall be of the materials shown on
the plans and when not otherwise specified shall be of Class "A" concrete
which shall conform to the requirements for "Concrete Masonry."
Concrete copings shall be made in sections extending the full width of
the wall, not less than 12 inches in thickness, and from 5 to 10 feet long.
The sections may be cast in place or precast and set in place in full
mortar beds.
2. 7. 8
Arches.
CONSTRUCTION
67
2. 7. 9. Pointing.
be
done in freezing
weather
or when
the
stone
Joints not pointed at the time the stone is laid shall be thoroughly
wet with clean water and filled with mortar.
The mortar shall be well
driven into the joints and finished with an approved pointed tool. The
wall shall be kept wet while pointing is being done and in hot or dry
weather the pointed masonry shall be protected from the sun and kept wet
for a period of at least three days after completion.
After the pointing is completed and the mortar set, the wall shall be
thoroughly cleaned and left in a neat and workmanlike condition.
2. 7. 10. Measurement
and Payment.
The quantity of stone masonry to be paid for under this item shall be
the number of cubic yards measured in the completed work and the limiting
dimensions shall not exceed those shown upon the plans or fixed by the
engineer.
The contract price shall include all labor, tools, materials and
other items incidental to the satisfactory completion of the work.
Concrete used in connection with rubble masonry
in the case of other concrete construction.
shall
be paid
for
as
Dry rubble masonry as here specified shall include the classes com
monly known as coursed, random and random range work and shall consist
of roughly squared and dressed stone laid without mortar.
2. 8. 2. Materials.
Stone
for this
division IV.
class of masonry
shall conform
to the requirements
of
2. 8. 3. Size of Stone.
"Mortar
specified
for
2. 8. 4. Headers.
to
the
requirements
specified
for "Mortar
2. 8. 5. Shaping Stone.
The stones shall be roughly squared on joints, beds and faces. Selected
stone, roughly squared and pitched to line, shall be used at all angles and
ends of walls.
2. 8. 6. Laying Stone.
The masonry shall be laid to line and in courses roughly leveled up.
The bottom or foundation courses shall be composed of large, selected stones
and all courses shall be laid with bearing beds parallel to the natural bed
of the material. Face joints shall not exceed 1 inch in width.
In laying dry rubble masonry, care shall be taken that each stone takes
HIGHWAY BRIDGES
68
a firm bearing at not less than three separate points upon the underlying
course.
Open joints, both front and rear, shall be "chinked" with spalls
fitted to take firm bearing upon their top and bottom surfaces, for the
purpose of securing firm bearing throughout the length of the stone.
When required by the terms of the contract, the open joints on the
rear surfaces of abutments or retaining walls shall be "slushed" thoroughly
with mortar to prevent seepage of water through the joints.
2. 8. 7. Copings,
Copings, bridge seats and backwalls, when used in connection with dry
rubble masonry, shall conform to the requirements
specified for "Mortar
Rubble Masonry."
2. 8. 8. Measurement
and Payment.
The quantity of stone masonry to be paid for under this item shall
number of cubic yards measured in the completed work and the
limiting dimensions shall not exceed those shown upon the plans or fixed by
the engineer.
The contract price shall include all labor, tools, materials
and other expense incidental to the satisfactory completion of the work.
Concrete used in connection with rubble masonry shall be paid for as
in the case of other concrete construction.
oe the
Brick masonry shall consist of brick laid in cement mortar and shall
include such construction with building brick or ornamental brick as may
be specified.
Brick pavements are not included under this designation.
2. 9. 2. Materials.
(a) Brick.
Brick used for this class of work shall conform
specified in Brick for Masonry, division IV.
to the requirements
(b) Mortar.
The mortar used shall conform, as regards materials, proportions and
mixing, to the mortar specified for Ashlar Masonry.
,
2. 9. 3. Construction.
The brick shall be laid in such manner as will thoroughly bond them
into the mortar by means of the "shove-joint" method; "buttered" or
All brick must be thoroughly
plastered joints will not be permitted.
saturated with water before being laid. The arrangement of headers and
stretchers shall be such as will thoroughly bond the mass and, unless other
wise specified, brick work shall be of alternate headers and stretchers with
consecutive courses breaking joints. Other types of bonding, as for orna
mental work, shall be as specified on the plans.
All joints shall be completely filled with mortar. They shall not be
less than % inch and not more than % inch in thickness and the thickness
shall be uniform throughout. All joints shall be finished properly as the
work progresses and on exposed faces they shall be neatly struck, using the
"weather" joint.
No spalls or bats shall
be
irregular
CONSTRUCTION
69
2. 9. 4. Copings,
The tops of retaining walls, abutment wing walls and similarly exposed
brick work shall be provided, in general, with either a stone or concrete
coping which shall project at least 1 inch beyond the face of the brick work
and shall have a batter or drip bead, permitting water to drip clear of the
wall. The coping upon an abutment backwall will commonly have no pro
jection beyond its bridge seat face. When concrete is used it shall be of
Class "A" quality. For thin copings, mortar of the same proportions as
used for laying the brick may be used to produce precast sections not less
than 3 feet nor more than 5 feet in length.
No coping shall be less than
4 inches thick.
Copings of piers and abutment bridge seats shall be of ashlar stone
work or of Class "A" concrete and shall conform to the requirements for
Ashlar Masonry or Concrete Masonry as the plan may indicate.
When not
shown upon the plans, concrete shall be used.
2. 9. 5. Measurement
and Payment.
The quantity of brick work to be paid for under this item shall be the
number of cubic yards of brick masonry actually placed in the structure
in accordance with the plans or as modified by written instructions from
the engineer.
This price shall include all labor, materials and other expense
incidental to the satisfactory completion of the work. Filling material for
the interior of the wall, when not of brick, and concrete or mortar copings,
shall be paid for on the basis of the number of cubic yards actually placed.
SECTION 10 Steel
Structures
Fabrication
2. 10.
1. Type of Fabrication.
Riveted
2. 10.
construction
is intended,
unless
otherwise
indicated.
2. Quality of Workmanship.
practice
in
bridge
It
be
of steel is covered
erection by
HIGHWAY
70
2. 10. 4. Straighening
BRIDGES
Material.
If
Rolled material, before being laid off or worked, must be straight.
straightening is necessary, it shall be done by methods that will not injure
Sharp kinks and bends shall be cause for rejection of the
the metal.
material.
2. 10. 5
Finish.
All holes for rivets shall be either punched or drilled. Material form
ing parts of a member composed of not more than five thicknesses of metal
may be punched Me inch larger than the nominal diameter of the rivets
whenever the thickness of the metal is not greater than % inch for struc
tural steel or % inch for alloy steel.
When there are more than five thicknesses or when any of the main
material is thicker than % inch in carbon steel, or % inch in alloy steel,
or when required under article 2. 10. 9, all the holes shall be subpunched
or subdrilled $ie inch smaller and, after assembling, reamed Me inch larger,
or drilled from the solid to Me inch larger, than the nominal diameter of
the rivets.
2. 10. 7. Punched Holes.
The diameter of the die shall not exceed the diameter of the punch by
more than Mo inch. If any holes must be enlarged to admit the rivets, they
shall be reamed. Holes must be clean cut, without torn or ragged edges.
Poor matching of holes will be cause for rejection.
2. 10. 8
If
Unless otherwise specified, holes in all field connections and field splices
of main truss or arch members, continuous beams, plate girders and rigid
frames shall be subpunched (or subdrilled if subdrilling is required accord
ing to article 2. 10. 6) , and reamed while assembled in the shop. The
assembly, including camber, alignment, accuracy of holes and milled joints,
shall be approved by the engineer before reaming is commenced.
Unless otherwise authorized by the engineer, each individual (full
length) truss, arch, continuous beam or girder shall be assembled in the
shop before reaming is commenced.
All holes for floor beam and stringer field end connections shall be
subpunched and reamed to a steel template or reamed while assembled.
CONSTRUCTION
All
71
be specified
If
When holes are reamed or drilled, 85 per cent of the holes in any
contiguous group shall, after reaming or drilling, show no offset greater
than %2 inch between adjacent thicknesses of metal.
2. 10. 12. Shop Assembling.
assembly of trusses, arches, continuous beam spans and plate
be according to article 2. 10. 9.
Complete shop assembly of an entire structure, including floor system,
which may be necessary in the case of complicated designs shall be done
when shown on the plans or when stipulated in the special provisions.
Surfaces of metal in contact shall be cleaned before assembling.
The
parts of a member shall be assembled, well pinned, and firmly drawn to
gether with bolts before reaming or riveting is commenced.
Assembled
pieces shall be taken apart, if necessary, for the removal of burrs and
shavings produced by the reaming operation.
The member shall be free
from twists, bends, and other deformation.
Preparatory to the shop riveting of full-sized punched material, the
rivet holes, if necessary, shall be spear-reamed for the admission of the
rivets. The reamed holes shall not be more than Me inch larger than the
nominal diameter of the rivets.
End connection angles, stiffener angles, and similar parts shall be care
fully adjusted to correct positions and bolted, clamped, or otherwise firmly
held in place until riveted.
Parts not completely riveted in the shop shall be secured by bolts, in
sofar as practicable, to prevent damage in shipment and handling.
Shop
girders shall
of
Holes.
HIGHWAY
72
BRIDGES
The size of rivets called for on the plans shall be the size before heating.
Rivet heads shall be of standard shape, unless otherwise specified, and
of uniform size for the same diameter of rivet. They shall be full, neatly
made, concentric with the rivet holes, and in full contact with the surface
of the member.
2. 10. 17
Field Rivets.
(a)
General.
(b) Unfinished
Bolts.
CONSTRUCTION
78
( d)
Ribbed bolts, with drive fit, shall be used only where called for on the
Ribbed bolts may be substituted for field rivets in locations where,
plans.
in the opinion of the engineer, it is impractical to drive rivets.
2. 10. 19
Riveting.
Rivets shall be heated uniformly to a "light cherry red color" and shall
driven while hot. Any rivet whose point is heated more than the re
mainder shall not be driven.
When a rivet is ready for driving, it shall
Any rivet which, in
be free from slag, scale and other adhering matter.
the opinion of the engineer, is scaled excessively, will be rejected.
All rivets that are loose, burned, badly formed, or otherwise defective
shall be removed and replaced with satisfactory rivets. Any rivet whose
head is defective in size or whose head is driven off center will be con
sidered defective and shall be removed.
Stitch rivets that are loosened
by driving of adjacent rivets shall be removed and replaced with satis
factory rivets. Caulking, recupping or double gunning of rivet heads will
be
not be permitted.
Shop rivets shall be driven by direct-acting rivet machines when
practicable. Approved beveled rivet sets shall be used for forming rivet
When the use of a direct-acting rivet machine
heads on sloping surfaces.
pneumatic hammers of approved size shall be used.
is not practicable,
Pneumatic bucking tools will be required when, in the opinion of the engineer,
the size and length of the rivets warrant their use.
Rivets may
2. 10. 20
be
Edge Planing.
Weld.
HIGHWAY
74
BRIDGES
the name and title of the person who conducted the examination, the kind
of specimens, the positions of welds, the results of the tests and the date
of the examination.
Such a certification of prequalification may also be
accepted as proof that an operator on field welding is qualified, if the
contractor who submits it is properly staffed and equipped to conduct such
an examination or if the examining and testing is done by a recognized
agency which is staffed and equipped for such purpose.
2. 10. 22. Flame Cutting.
Steel or wrought-iron may be flame cut, provided a smooth surface
is secured by the use of a mechanical guide.
Flame cutting by hand shall
be done only where approved by the engineer and the surface shall be made
smooth by planing, chipping or grinding.
The cutting flame shall be so
adjusted and manipulated as to avoid cutting beyond the prescribed lines.
Re-entrant cuts shall be filleted to a radius of not less than % inch.
In the case of silicon steel, flame cut edges shall be removed to a depth
of at least % inch, by milling, chipping, or grinding.
2. 10. 23. Facing of Bearing Surfaces.
The top and bottom surfaces of steel slabs and base plates and cap
plates of columns and pedestals shall be planed, or else the plates or slabs
hot straightened.
Parts of members in contact with them shall be faced.
Sole plates of beams and girders shall have full contact with the
flanges. Sole plates and masonry plates shall be planed or hot straightened.
Cast pedestals shall be planed on surfaces to be in contact with steel
and shall have the surface to be in contact with masonry, rough-finished.
Surfaces of bronze bearing plates intended for sliding contact shall
be finished.
In planing the surfaces of expansion bearings the cut of the tool shall
be in the direction of expansion.
2. 10. 24. Abutting Joints.
Angles.
Floor beams, stringers and girders having end connection angles shall
built to exact length back to back of connection angles.
If end con
nections are faced, the finished thickness of the angles shall not be less
than that shown on the detail drawings.
be
unless
another
form
open joints.
2. 10. 28
be
Web Plates.
In girders having
CONSTRUCTION
75
angles and shall not be more than % inch below at any point.
Any portion
of the plate projecting beyond the angles shall be chipped flush with the
backs of the angles.
Web plates of girders having cover plates may be
Vz inch less in width than the distance back to back of flange angles.
shall
be sealed on the
At web splices, the clearance between the ends of the web plates shall
not exceed % inch.
The clearance at the top and bottom ends of the web
splice plates shall not exceed V* inch.
2. 10. 29. Bent Plates.
radius
1.0
1.5
2.0
T
T
T
If
Fit of Stiffeners.
End stiffener angles of girders and stiffener angles intended as sup
ports for concentrated loads shall be milled or ground to secure an even
bearing against the flange angles.
Intermediate stiffener angles shall fit
sufficiently tight to exclude water after being painted.
Fillers under
stiffeners shall fit within Vt inch at each end.
Welding will be permitted in lieu of milling or grinding if noted on the
plans or specified in the special provisions as provided in division III.
Welding transversely across the tension flanges of beams or girders, which
have a flange stress of more than 75 per cent of their designed capacity,
2. 10. 30
will
not be permitted.
Eyebars shall be straight, true to size, and free from twists, folds
in the neck and head, and other defects.
The heads shall be made by
upsetting and rolling or forging, and not by welding. The form of the
heads will be determined by the dies in use at the works where the eyebars
are made, if they are satisfactory to the engineer.
The thickness of the
head and neck shall not overrun more than Mg inch.
Eyebars that are to be placed side by side in the structure shall be
bored so accurately that upon being placed together, pins tys inch less
in diameter than the pin holes will pass through the holes at both ends
at the same time without driving.
HIGHWAY BRIDGES
76
2. 10. 32. Annealing.
In pins larger than 9 inches in diameter, a hole not less than 2 inches
in diameter shall be bored full length along the axis after the forging has
below the critical range under suit
been allowed to cool to a temperature
able conditions to prevent injury by too rapid cooling, and before being
annealed.
2. 10. 34. Boring
Pin
Holes.
Pin holes shall be bored true to the specified diameter, smooth and
straight, at right angles with the axis of the member and parallel with
The final surface shall be produced
each other unless otherwise required.
by a finishing cut.
The distance outside to outside of holes in tension members and inside
to inside of holes in compression members shall not vary from that specified
Boring of holes in built-up members shall be done
more than %2 inch.
after the riveting is completed.
2. 10. 35. Pin Clearances.
The diameter of the pin hole shall not exceed that of the pin by more
inch for larger pins.
than %o inch for pins 5 inches or less in diameter, or
Threads for all bolts and pins for structural steel construction shall
conform to the American National Coarse Thread Series, Class 2, free fit,
except that the pin ends having a diameter of 1% inches or more shall be
threaded six threads to the inch.
2. 10. 37
Two pilot nuts and two driving nuts for each size of pin shall
furnished, unless otherwise specified.
be
The contractor shall give the engineer ample notice of the beginning
of work at the mill or in the shop, so that inspection may be provided.
The term "mill" means any rolling mill or foundry where material for
the work is to be manufactured. No material shall be manufactured or
work done in the shop before the engineer has been so notified.
2. 10. 39. Facilities for Inspection.
CONSTRUCTION
2. 10. 40. Inspector's
77
Authority.
Mill
Orders.
as many
copies of mill
may direct.
Weighing of Members.
In case it is specified that any part of the material is to be paid for by
actual weight, finished work shall be weighed in the presence of the inspector,
if practicable. In such case, the contractor shall supply satisfactory
scales and shall perform all work involved in handling and weighing the
various parts.
2. 10. 42
ERECTION
2. 10. 44. Erection of Structure.
If
HIGHWAY BRIDGES
78
diagrams, list of field rivets and bolts, and copy of shipping statements
showing a list of parts and their weights.
2. 10. 46. Plant
The contractor shall provide the falsework and all tools, machinery
and appliances, including drift pins and fitting-up bolts, necessary for the
expeditious handling of the work.
2. 10. 47. Delivery
of
Materials.
If the contract is for erection only, the contractor shall receive the
materials entering into the finished structure, free of charges at the place
designated and loaded or unloaded as specified. The contractor shall unload
promptly upon delivery any material delivered on railroad cars or barges
which he is required to unload, otherwise he shall be responsible for
demurrage
eharges.
It
Material to be stored shall be placed on skids above the ground.
shall be kept clean and properly drained. Girders and beams shall be placed
upright and shored. Long members, such as columns and chords, shall be
supported on skids placed near enough together to prevent injury from
deflection.
If the contract is for erection only the contractor shall check
the material turned over to him against the shipping lists and report
He shall be re
promptly in writing any shortage or injury discovered.
sponsible for the loss of any material while in his care, or for any damage
caused to it after being received by him.
2. 10. 49. Falsework.
Before starting the work of erection, the contractor shall inform the
engineer fully as to the method of erection he proposes to follow, and the
amount and character of equipment he proposes to use, which shall be
The approval of the engineer shall
subject to the approval of the engineer.
not be considered as relieving the contractor of the responsibility for the
safety of his method or equipment or from carrying out the work in full
accordance with the plans and specifications.
No work shall be done until
such approval by the engineer has been obtained.
2. 10. 51. Bearings and Anchorage.
Masonry bearing plates shall not be placed upon bridge seat bearing
areas which are improperly finished, deformed or irregular.
Bearing plates
shall be set level in exact position and shall have a full and even bearing
upon the masonry.
Unless otherwise directed by the engineer, they shall
be placed on a layer of canvas and red lead applied as follows:
Thoroughly swab the bridge seat bearing area with red lead paint
it three layers of 12 to 14 ounce duck, each layer being
CONSTRUCTION
79
on the plans.
The contractor shall drill the holes and set the anchor bolts, except
where the bolts are built into the masonry.
The bolts shall be set accurately
and fixed with Portland cement grout completely filling the holes.
The
location of the anchor bolts in relation to the slotted holes in the expansion
shoes shall correspond with the temperature at the time of erection.
The
nuts on anchor bolts at the expansion ends of spans shall be adjusted to
permit the free movement of the span.
2. 10. 52. Straightening
Bent Material.
Steel.
as the rivets,
Pneumatic hammers shall be used for field riveting, except when the
of hand tools is permitted by the engineer. Rivets larger than % Inch
Cup-faced dollies, fitting the
in diameter shall not be driven by hand.
head closely to insure good bearing, shall be used. Connections shall be
Drifting
accurately and securely fitted up before the rivets are driven.
shall be only such as to draw the parts into position and not sufficient to
Unfair holes shall be reamed or
enlarge the holes or distort the metal.
drilled. Rivets shall be heated uniformly to a light "cherry red" color and
shall be driven while hot. They shall not be overheated or burned. Rivet
heads shall be full and symmetrical, concentric with the shank, and shall
They shall not be smaller than the heads of
have full bearing all around.
use
HIGHWAY
80
BRIDGES
the shop rivets. Rivets shall be tight and shall grip the connected parts
securely together.
Caulking or recupping will not be permitted.
In remov
ing rivets, the surrounding metal shall not be injured; if necessary, they
shall be drilled out.
2. 10. 55. Pin Connections.
Pilot and driving nuts shall be used in driving pins. They shall be
furnished by the contractor without charge.
Pins shall be so driven that
the members will take full bearing on them.
Pin nuts shall be screwed
up tight and the threads burred at the face of the nut with a pointed tool.
2. 10. 56. Misfits.
correction
of minor misfits involving non-harmful amounts of
cutting and chipping will be considered a legitimate part of the
However, any error in the shop fabrication or deformation result
ing from handling and transportation which prevents the proper assembling
and fitting up of parts by the moderate use of drift pins or by a moderate
amount of reaming and slight chipping or cutting, shall be reported immedi
ately to the inspector and his approval of the method of correction obtained.
The correction shall be made in his presence.
the contract provides for
complete fabrication and erection the contractor shall be responsible for
all misfits, errors and injuries and shall make the necessary corrections
If the contract is for erection only the inspector, with
and replacements.
the cooperation of the contractor, shall keep a correct record of labor and
materials used and the contractor shall render within 30 days an itemized
bill for the approval of the engineer.
The
reaming,
erection.
If
If
structure which,
If
Upon completion of the erection and before final acceptance, the con
tractor shall remove all falsework, excavated or useless materials, rubbish
and temporary buildings, replace or renew any fences damaged and restore
in an acceptable manner all property, both public and private, which may
have been damaged during the prosecution of this work, and shall leave
the bridge site and adjacent highway in a neat and presentable condition
All excavated material or falsework placed
satisfactory to the engineer.
in the stream channel during construction shall be removed by the contractor
before final acceptance.
2. 10. 58. Basis of Payment.
The contract price for fabrication and erection of structural steel shall
include all labor, materials, transportation, and shop and field painting
necessary for the proper completion of the work in accordance with the
contract.
The contract price for fabrication without erection shall include all
labor and materials necessary for fabrication, shop painting, shipping and
delivery at the place designated.
Payment will be made on a pound-price or a lump-sum basis, as required
CONSTRUCTION
81
Under contracts containing an item for structural steel, all minor metal
parts other than metal reinforcement,
such as expansion joints, drains,
bolts, etc., which are embedded in concrete shall be paid for as structural
steel.
2. 10. 59. Payment
If
in Weight.
If
the scale weight of any member is less than 97% per cent of the
This applies to both poundcomputed weight, the member may be rejected.
price and lump-sum contracts.
2. 10. 62. Computed
Weight.
Copper-alloy
Copper sheet
Iron, cast
Iron, malleable
Iron, wrought
Lead, sheet
Steel, cast, copper bearing,
Zinc
silicon, nickel
173.0
536.0
536.0
558.0
445.0
470.0
487.0
707.0
and stainless . . 490.0
450.0
Designation
7-46.
HIGHWAY BRIDGES
82
(3) The weight of all rivet heads, both field and shop, shall be included
on the basis of the following weights:
Diameter of rivet,
inches
Weight
per
100
heads, pounds
4
7
12
18
26
36
48
1.
General.
SECTION
2. 11.
or Copper-Alloy
Bearing
and Expansion
Plates
of division IV.
Sliding
Plates shall be cast according to details shown on the plans.
surfaces shall be planed parallel to the movment of the spans and polished
unless detailed otherwise.
2. 11. 4. Copper-Alloy Plates.
Placing.
and Payment.
The weight to be paid for shall be the inspector's certified shop scale
weight of the plates as placed in the structure, unless otherwise provided.
specified in the contract or permitted by the engineer, computed weights,
obtained as herein described, may be made the basis of payment.
If
CONSTRUCTION
Payment shall
be made
SECTION
2. 12.
83
12 Steel
Grid Flooring
1. General.
Steel grid flooring shall be of the open type, or the concrete filled type
as specified in the special provisions or as shown on the plans.
The floor shall meet the requirements for the design of steel grid floors,
division III. Before fabrication or construction is undertaken the con
tractor shall submit complete shop and assembly details to the engineer for
approval and his approval secured.
2. 12. 2. Materials.
Materials
division IV.
shall conform
to
the
requirements
for
steel
grid
floors,
2. 12. 3. Arrangement
of Sections.
Where the main elements are normal to center line of roadway, the
units generally shall be of such length as to extend over the full width of
the roadway for roadways up to 40 feet, but in every case the units shall
extend over at least three panels.
Where joints are required, the ends of
the main floor members shall be welded at the joints over their full crosssectional area or otherwise connected to provide full continuity.
Where the main elements are parallel to center line of roadway, the
sections shall extend over not less than three panels, and the ends of
abutting units shall be welded over their full cross-sectional area or other
wise connected to provide full continuity in accordance with the design.
2. 12. 4. Provision
for
Camber.
to Supports.
Before
The floor shall be connected to its steel supports by welding.
any welding is done the floor shall either be loaded to make a tight joint
HIGHWAY BRIDGES
84
with full bearing or it shall be clamped down. The location, length and
size of the welds shall be subject to the approval of the engineer, but in no
case shall they be less than the manufacturer's standards.
The ends of all the main steel members of the slab shall be securely
fastened together at the sides of the roadway for the full length of the
span by means of steel plates or angles welded to the ends of the main
members, or by thoroughly encasing the ends with concrete.
2. 12. 7. Welding.
All shop and field welding shall be done in accordance with the current
of "The American Welding Society for Welded Highway
specifications
and Railway Bridges."
Surfaces to be welded shall be free from paint, grease, loose scale, rust
and other material that will prevent a proper weld.
A thin coating of
Any clinkers or slag
linseed oil, without pigment, need not be removed.
caused by flame cutting or other causes shall be removed before welding.
2. 12. 8. Repairing Damaged
Galvanized
Coatings.
Floor types with bottom flanges not in contact shall be provided with
bottom forms of metal or wood to retain the concrete filler without excessive
leakage.
If metal form strips are used they shall fit tightly on the bottom flanges
of the floor members and be placed in short lengths so as to extend only
about 1 inch onto the edge of each support, but in all cases the forms shall
be such as will result in adequate bearing of slab on the support.
The concrete shall be mixed, placed and cured in accordance with the
The concrete shall be
specification for Concrete Masonry, division II.
The vibrating
thoroughly compacted by vibrating the steel grid floor.
device and the manner of operating it shall be subject to the approval of
the engineer.
Painting.
2. 12. 10
II.
CONSTRUCTION
85
specified.
SECTION
13 Railings
2. 13. 1. General.
Railings for bridges, wing walls, retaining walls, etc., shall include all
work constructed above the top of the roadway curb or of the sidewalk
surface.
Entrance posts, pylons, and other items integral with the railing
shall, for the purpose of measurement and payment, be included as railing
unless otherwise specified.
This item shall include the furnishing of all
material, equipment, tools, supplies, and labor necessary for the proper
construction
of the handrails and parapets, as shown on the plans or
provided for in the special provisions.
2. 13. 2
Materials.
The line and grade of the railing shall be true to that shown on the
plans, and not follow any unevenness in the superstructure. Unless other
wise specified or shown on the plans, the handrail and curbs on bridges,
whether superelevated or not, shall be vertical.
2. 13. 4. Construction.
Metal Railing
Unless otherwise specified, metal railing shall be given one shop coat
Painting shall conform
of paint, and three coats of paint after erection.
for Painting Metal Structures, division II.
to the requirements
2. 13. 6. General.
Concrete Railing
86
HIGHWAY BRIDGES
2. 13. 7. Materials.
2. 13. 10
of the
Stone
and
Brick
Railing
CONSTRUCTION
87
Wood Railing
according
to the requirements
for
and Payment.
Payment for railing shall include all materials, tools, equipment, sup
plies, labor, and other costs necessary for the satisfactory completion of
the work.
The reinforcing steel included in payment for rail shall be determined
as follows: The portion of slab or beam bars which project into the handrail
shall be paid for as metal reinforcement, but the portion of the handrail
steel which extends into the slab or beams shall be considered as part of
the handrail.
Payment will be made on the basis of the number of linear feet of
railing measured along the center line of the railing. When steel railings
are shown on steel structures and no separate bid is taken for railing, the
railing will be paid for at the price bid per pound for structural steel.
Structures
2. 14. 1. General.
of division
IV
and
All steel shall be painted one shop or prime coat, and with not less than
two field coats, as specified in division IV. The color shall be as specified
or determined by the engineer.
The coats shall be sufficiently different in
color to permit detection of incomplete application.
2. 14. 4. Mixing of Paint.
2. 14. 5. Weather
Conditions.
Paint shall not be applied when the air temperature is below 40" P.
or when the air is misty, or when, in the opinion of the engineer, conditions
are otherwise unsatisfactory for the work.
It shall not be applied upon
damp or frosted surfaces.
Material painted under cover in damp or cold weather shall remain
under cover until dry or until weather conditions permit its exposure in the
HIGHWAY BRIDGES
88
Painting shall not be done when the metal is hot enough to cause the
paint to blister and produce a porous paint film.
open.
2. 14. 6. Application.
(a) General.
(b) Brushing.
When brushes are used, the paint shall be so manipulated under the
brush as to produce a smooth, uniform, even coating in close contact with
the metal or with previously applied paint, and shall be worked into all
corners or crevices
(c)
Spraying.
Power spraying equipment shall apply the paint in a fine, even spray
without the addition of any thinner. In cool weather, the paint may be
warmed to reduce the viscosity for use.
Such warming shall be accom
plished by heating the paint containers in water or by placing them on
steam radiators.
Paint when applied with spray equipment shall be immediately fol
lowed by brushing when necessary to secure uniform coverage and to
eliminate wrinkling, blistering and airholes.
(d)
Inaccessible Surfaces.
On all surfaces which are inaccessible for paint brushes, the paint shall
be applied
by spraying or with sheepskin daubers to insure thorough
covering.
2. 14. 7. Removal
of Paint.
painting
is unsatisfactory to the engineer, the paint shall
If the
removed and the metal thoroughly cleaned and repainted.
be
permitted
by the engineer.
Surfaces.
CONSTRUCTION
89
galvanized surface, when it will assume a dark, almost black, color, which
on drying becomes a grayish film.
2. 14. 10. Cleaning
(a)
of Surfaces.
General.
(b) Method
( c)
Method B. Sandblasting.
C. Flame Cleaning.
90
HIGHWAY BRIDGES
will
be
no
recondensation
of moisture
on the
CONSTRUCTION
91
As soon as the inspector has examined and approved all field rivets
driven, the heads of such rivets and field bolts, all welds and any surfaces
from which the shop or first coat of paint has become worn off or has
otherwise become defective, shall be cleaned and thoroughly covered with
one coat of shop-coat paint.
Surfaces to be riveted in contact and surfaces which will be in contact
with concrete shall not be painted.
Surfaces which will be inaccessible
after erection shall be painted with such field coats as are called for on
plans or authorized.
When the paint applied for retouching the shop coat
has thoroughly dried and the field cleaning has been satisfactorily com
pleted, such field coats as are called for on the plans or are authorized shall
In no case shall a succeeding coat be applied until the previous
be applied.
coat has dried throughout the full thickness of the paint film.
All small
cracks and cavities which were not sealed in a watertight manner by the
first field coat shall be filled with a pasty mixture of red lead and linseed oil
before the second coat is applied.
The following provision shall apply to the application of both field
coats. To secure a maximum coating on edges of plates or shapes, rivet
heads and other parts subjected to special wear and attack, the edges shall
first be striped with a longitudinal motion and the rivet heads with a rotary
motion of the brush, followed immediately by the general painting of the
whole surface, including the edges and rivet heads.
If, in the opinion of the engineer, traffic produces an objectionable
amount of dust, the contractor shall, at his own expense, allay the dust for
the necessary distance on each side of the bridge and take any other pre
cautions necessary to prevent dust and dirt from coming in contact with
freshly painted surfaces or with surfaces before the paint is applied.
The application of the second field coat shall be deferred until adjoining
concreting operations have
concrete work has been placed and finished.
damaged the paint, the surface shall be recleaned and repainted.
The contractor shall protect pedestrian, vehicular and other traffic
upon or underneath the bridge, and also all portions of the bridge super
structure and substructure, against damage or disfigurement by spatters,
splashes and smirches of paint or paint materials.
If
SECTION
15 Riprap
2. 15. 1. Materials.
to the
requirements
for
Slopes.
Unless otherwise
for
Slopes.
HIGHWAY
92
BRIDGES
shall
for
Slopes.
Grout for grouted riprap shall consist of one part of portland cement
and three parts of sand, thoroughly mixed with water to produce grout
having a thick, creamy consistency.
The stones shall be of the same sizes and placed in the same manner
as specified above for Dry Riprap, Class 1, care being taken during placing
to keep earth or sand from filling the spaces between the stones.
After
the stones are in place, the spaces. between them shall be completely filled
with grout from bottom to top, and the surface swept with a stiff broom.
No riprap shall be grouted in freezing weather, and in hot, dry weather
the work shall be protected from the sun and kept moist for at least three
days after grouting.
2. 15. 6. Stone Riprap
Stone riprap for pier and abutment protection shall range, in size,
up to derrick stone and shall be graded from coarse to fine in such manner
as to produce a minimum of voids. It shall be deposited where directed;
CONSTRUCTION
stone deposited contrary to directions
not be paid for.
2. 15. 7. Concrete
will
93
be considered
wasted
and
will
Riprap in Bags.
The concrete slabs for riprap shall consist of concrete, cast in place,
inches thick, unless otherwise specified or noted on the plans. The slabs
shall be of two types, plain concrete or reinforced.
reinforcement is
required, it shall be furnished as shown on the plans. Except as modified
herein, construction shall conform to specifications for Concrete Masonry,
4
division
2. 15. 9
If
II.
Concrete.
The concrete shall be Class B unless the riprap is exposed to salt water,
in which case it shall be Class A. It shall be of such consistency that it
can be placed without the use of top forms.
2. 15. 10. Placing.
and Payment.
Payment for riprap shall include the cost of furnishing all materials
and tools, the preparation of the subgrade, the laying and grouting of the
stone and all other work incidental to finished construction in accordance
The basis of payment shall be as follows:
with these specifications.
Stone riprap for slope walls shall be paid for on the basis of the
actual number of square yards of material placed.
Stone riprap for foundation protection shall be paid for on the basis
of volume or weight as may be specified.
Concrete riprap in bags shall be paid for on the basis of the actual
number of cubic yards of riprap placed.
Concrete slab riprap shall be paid for on the basis of the actual number
HIGHWAY
94
BRIDGES
16Concrete
be
Cribbing
2. 16. 1. General.
The foundation or bed for the cribbing shall be firm and shall be
approved by the engineer before any of the crib work is placed. In general,
transverse concrete sill members shall be used to support the lower cribbing
course.
Crib members shall be carefully handled and erected in such
Each member shall
manner as to avoid any injury due to shock or impact.
be secured by approved interlocking details or by means of dowels passing
through galvanized casings. Any members which become cracked or other
wise injured during erection shall be completely renewed and replaced.
The filling for the interior of the crib shall progress simultaneously
with the erection of the cribbing, and shall be of approved material placed
in layers not to exceed 12 inches in thickness and tamped or consolidated
to the satisfaction of the engineer.
2. 16. 3. Measurement
and Payment.
Concrete cribbing will be paid for at the contract price per cubic foot
for concrete cribbing complete in place. This price shall include all mate
rials, equipment, tools, and labor incidental to the satisfactory erection of
The volume to be paid for
the cribbing, including necessary excavation.
will be the actual net volume of the concrete in the crib members as shown
on the plans.
The filling for the interior of the crib will be paid for at the
contract price per cubic yard for crib filling in place.
SECTION 17 Waterproofing
2. 17.
be
1. General.
CONSTRUCTION
95
2. 17. 2. Materials.
The bituminous material, fabric, and joint filler used for waterproofing
shall conform to the requirements
specified in division IV.
Sand for the
mortar protection course shall conform to the requirements of division IV.
2. 17. 3. Storage of Fabric
The fabric shall be stored in a dry, protected
not be stored on end.
place.
HIGHWAY
96
BRIDGES
last strip but one. The entire surface shall then be given a final mopping
of hot asphalt or tar.
The completed waterproofing shall be a firmly bonded membrane com
posed of two layers of fabric and three moppings of asphalt or tar,
together with a coating of primer. Under no circumstances shall one layer
of fabric touch another layer at any point or touch the surface, as there
must be at least three complete moppings of asphalt or tar.
In all cases the mopping on concrete shall cover the surface so that
no gray spots appear, and on cloth it shall be sufficiently
heavy to com
pletely conceal the weave. On horizontal surfaces not less than 12 gallons
of asphalt or tar shall be used for each 100 square feet of finished work,
and on vertical surfaces not less than 15 gallons shall be used. The work
shall be so regulated that, at the close of a day's work, all cloth that is
laid shall have received the final mopping of asphalt or tar. Special care
shall be taken at all laps to see that they are thoroughly sealed down.
2. 17. 6. Application Details.
so closely
than
24
hours.
CONSTRUCTION
2. 17. 9. Measurement
97
and Payment.
2. 18.
1. General.
SECTION 18 Dampproofing
special
provisions,
surfaces
Materials.
of
Surface.
and Payment.
SECTION 19Name
of square yards of
Plates
When specified, the contractor for the superstructure shall furnish and
install name plates of such form, dimensions, material and design as may
Unless otherwise provided, the contract price for
be shown on the plans.
the superstructure shall include the cost of such name plates.
HIGHWAY BRIDGES
98
SECTION 20 Timber
2. 20. 1. Materials.
(a) Lumber
Structures
and Timber.
tension
5" x 8"
and
larger
Stringers
Other floor members
(2)
(3)
Standard grade
Size of member
Il800#f, or
|
Caps
Posts, bridge and guard rail
Sills
Mud sills
Nailing strips
Truss members, compression
Timbers (culverts)
1600#f, or 1400#f
Joist
Decking, wearing
Other floor members
Rails
Rail posts
Nailing strips
1600ff, or 1400#f
structural joist and plank.
4"_ and
thinner
1800#f,
x 6" and
larger
/
\
1100#c structural
posts and
1200#f or 1100#f
joist
timbers
Sub-decking, laminated
Bracing, sway, sasl , and
longitudinal
4" and
thinner
Girts
Bulkhead plank
Scupper blocks
Cleats
Grillage
(6)
Cross-bridging
Sidewalk
Firestops
1
V
Inside sheathing
(8-
plank
<
No.
dimension
I D select
boards
and
finish,
or No.
CONSTRUCTION
99
(b) Structural
Shapes.
Rods, plates and shapes shall be of structural steel or wrought-iron,
of division IV. Eyebars shall
as specified, conforming to the requirements
conform to the requirements of division IV for structural steel eyebars.
( c)
the
(d)
Castings.
as
specified,
conforming to
Hardware.
as specified.
Timber Connectors.
Storage of Material.
Lumber and timber on the site of the work shall be stored in piles.
Untreated material shall be open-stacked at least 12 inches above the
ground surface and piled to shed water and prevent warping.
When re
quired by the engineer, it shall be protected from the weather by suitable
2. 20. 3
covering.
Creosoted timber and piling shall be close-stacked and piled to prevent
warping.
The ground underneath and in the vicinity of all material piles shall
be cleared of weeds and rubbish.
HIGHWAY
100
BRIDGES
2. 20. 4. Workmanship.
None but competent
Workmanship shall be first class throughout.
bridge carpenters shall be employed and all framing shall be true and
exact.
Unless otherwise specified, nails and spikes shall be driven with
just sufficient force to set the heads flush with the surface of the wood.
Deep hammer marks in wood surfaces shall be considered evidence of poor
workmanship and sufficient cause for removal of the workman causing them.
The workmanship on all metal parts shall conform to the requirements
specified for steel structures, division II.
2. 20. 5. Treated
Timber.
(a) Handling.
Treated timber shall be carefully handled without sudden dropping,
breaking of outer fibers, bruising or penetrating the surface with tools.
It shall be handled with rope slings. Cant hooks, peaveys, pikes or hooks
shall not be used.
(b) Framing and Boring.
All cutting, framing, and boring of treated timbers shall be
treatment in so far as is practicable.
When treated timbers are
done before
to be placed
in waters infested by marine borers, untreated cuts, borings or other joint
framings below high water elevation shall be avoided.
(c)
All
(d) Bolt
Holes.
holes bored, after treatment, shall be treated with creosote oil
by means of an approved pressure bolt hole treater. Any unfilled holes,
after being treated with creosote oil, shall be plugged with creosoted plugs.
All bolt
(e) Temporary
Attachment.
Whenever with the approval of the engineer, forms or temporary braces
are attached to treated timber with nails or spikes, the holes shall be filled
by driving galvanized nails or spikes flush with the surface or plugging
holes as required for bolt holes.
2. 20. 6. Untreated
Timber.
In structures of
untreated
timber the following surfaces shall be
thoroughly coated with two coats of hot creosote oil before assembling:
Ends, tops and all contact surfaces of sills, caps, floor beams and stringers ;
and all ends, joints, and contact surfaces of bracing and truss members.
The back faces of bulkheads and all other timber which is to be in contact
with earth, metal or other timber shall be similarly treated.
Bolts passing through non-resinous wood shall preferably be galvanized.
2. 20. 7. Treatment of Pile Heads,
(a) General.
Pile heads, after cutting to receive the caps, and prior to placing the
caps, shall be treated to prevent decay.
The heads of treated timber piles shall be protected by one of the fol
lowing methods, as specified on the plans. If not otherwise specified, method
B shall be used.
CONSTRUCTION
( b) Method A Zinc
101
Covering.
60
Covering.
The heads of all piles shall be covered with alternate layers of hot pitch
and loosely woven fabric similar to membrane waterproofing, using four
applications of pitch and three layers of fabric. The cover shall measure at
least 6 inches more in dimension than the diameter of the pile and shall be
neatly folded down over the pile and secured by large headed galvanized
nails or by binding or serving with not less than seven complete turns of gal
vanized wire securely held in place by large-headed galvanized nails and
staples.
The edges of the fabric projecting below the wire wrapping shall
be trimmed to present a workmanlike appearance.
The heads of untreated piles shall be given one of the following treat
ments, as may be specified or directed by the engineer :
(1) The sawed surface shall be thoroughly brush coated with two ap
plications of hot creosote oil.
(2) The sawed surface shall be heavily coated with red lead paint, after
which it shall be covered with cotton duck, of at least 8-ounce weight, which
shall be folded down over the sides of the pile and firmly secured thereto
with large-headed roofing nails. The edges of the duck shall be trimmed
to give a workmanlike appearance.
The duck shall then be waterproofed
by being thoroughly saturated and coated with one or more applications of
red lead paint.
2. 20. 8. Holes
for Bolts,
Holes for round drift-bolts and dowels shall be bored with a bit Me
inch less in diameter than the bolt or dowel to be used. The diameter of
holes for square drift-bolts or dowels shall be equal to the least dimension
of the bolt or dowel.
Holes for machine bolts shall be bored with a bit the same diameter
as the bolt.
Holes for rods shall be bored with a bit Me inch greater in diameter
than the rod.
Holes for lag screws shall be bored with a bit not larger than the body
of the screw at the base of the thread.
2. 20. 9. Bolts and Washers.
A washer, of the size and type specified, shall be used under all bolt
heads and nuts which would otherwise come in contact with wood.
The nuts of all bolts shall be effectually locked after they have been
finally tightened.
2. 20. 10. Countersinking.
HIGHWAY
102
BRIDGES
Framing.
2. 20. 11
All
lumber and timber shall be accurately cut and framed to a close fit
in such manner that the joints will have even bearing over the entire con
tact surfaces.
Mortises shall be true to size for their full depth and tenons
shall fit snugly.
No shimming will be permitted in making joints, nor will
open joints be accepted.
Pile Bents.
The piles shall be driven as indicated on the plans, with a variation
of the portion above the ground of not more than % inch per foot from the
vertical or batter indicated, or so that the cap may be placed in its proper
location without inducing excessive stresses in the piles. Excessive manipu
lation of the piles will not be permitted and the contractor will be required
to redrive or use other satisfactory methods to avoid such manipulations.
No shimming on tops of piles will be permitted.
The piles for any one bent shall be carefully selected as to size, to
avoid undue bending or distortion of the sway bracing.
However, care shall
be exercised in the distribution of piles of varying sizes to secure uniform
strength and rigidity in the bents of any given structure.
Cut-offs shall be accurately made to insure perfect bearing between the
2. 20. 12
(a) Mud
Bent:
SUU.
Untreated timber used for mud sills shall be of heart cedar, heart
cypress, redwood, or other durable timber.
Mud sills shall be firmly and
evenly bedded to solid bearing and tamped in place.
(b)
Concrete Pedestals.
(c) SUh.
Sills shall have true and even bearing on mud sills, piles or pedestals.
They shall be drift-bolted to mud sills or piles with bolts of not less than
%-inch diameter and extending into the mud sills or piles at least 6 inches.
When possible, all earth shall be removed from contact with sills so that
there will be free air circulation around them.
(d)
Posts.
Posts shall
CONSTRUCTION
at least 9 inches into the posts or piles.
approximately in the center of the post or pile.
extending
103
be
or Strip Floors.
The strips shall be of the grade specified in division II. The strips
shall be placed on edge, at right angles to the center line of roadway.
Each
strip shall be spiked to the preceding strip at each end and at approximately
18-inch intervals with the spikes driven alternately near the top and bottom
edges.
The spikes shall be of sufficient length to pass through two strips
and at least half-way through the third strip.
If timber supports are used every other strip shall be toe-nailed to
The size of the spikes shall be as shown on the plans.
every other support.
When specified on the plans, the strips shall be securely attached to steel
supports by the use of approved galvanized metal clips. Care shall be taken
to have each strip vertical and tight against the preceding one, and bearing
evenly on all the supports.
104
HIGHWAY
<
BRIDGES
Trusses.
Rails and rail posts, untreated timber, or timber treated with preserva
tive salts shall be painted with three coats of paint.
Parts of the structure, other than rails and rail posts, which are to be
painted, shall be designated on the plans or in the special provisions.
Metal parts, except hardware, shall be given one coat of shop paint and,
after erection, two coats of field paint.
2. 20. 24. Measurement
and Payment.
SECTION
21
Preservative
Treatments
for Timber
2. 21. 1. General.
shall be as specified in
The type of treatment
CONSTRUCTION
Creosote oil.
Creosote-coal-tar
solution.
Creosote-petroleum
solution.
Zinc chloride.
dinitrophenol solution
Sodium fluoride-arsenate
Chromated zinc chloride.
Zinc meta-arsenite (Z.M.A.).
105
(Wolman Salts).
IV
of division
used shall
(a)
Sorting.
(b) Framing.
So far as
(c) Incising.
All Douglas fir
HIGHWAY
106
BRIDGES
Minimum depth
Size
of incision
2x12
3 x 12
4x12
8x10
y2"
10x12
12x12
%"
%"
2. 21. 4. Amount
of Preservative.
The net retention in any charge shall be not less than 90 per cent of the
quantity of preservative that may be specified; but the average retention
by the material treated under any contract or order and the average reten
tion of any five consecutive charges shall be at least 100 per cent of the
quantity specified. Unless otherwise specified in the proposal or plans, the
minimum amount of preservative retained shall be as follows:
(a)
Creosote, Creosote
Treatment
Material
ness
(b)
full
eel!
14 lbs.
full
cell
Salts Treatments
Zinc chloride
Sodium
fluoride-arsenate-dinitrophenol
Salts)
Chromated zinc chloride
Zinc meta-arsenite (Z.M.A.)
2. 21. 5. Pressure
Treatment
1.00
(Wolman
.35
.75
.35
Processes.
All lumber
If
(a) Timber.
sion
CONSTRUCTION
If
sills, etc.
treated timber is used all hardware shall be galvanized
mium plated.
(b)
107
or cad
Logs.
2. 22. 2. Preparation.
(a)
Timber.
(b)
Logs.
(a) Foundation.
When mud sills are used, they shall be set at right angles to the face of
the cribbing and firmly and evenly beaded in the foundation material.
Mud sills shall be not less than 12 by 12 inches in squared cross-sectional
dimensions and not less than 3 feet in length.
They shall be spaced not
more than 4 feet apart.
Log or timber mud sills shall be leveled to fit the first tier resting upon
them. In no case shall there be less than 100 square inches of flat contact
surface between the face log and each mud sill.
Foundation material shall be thoroughly tamped around all mud sills.
Face Logs or Timbers.
The logs or timbers in the base tier and in alternate tiers above the
and, preferably, shall extend the full
base shall be as long as practicable
In intermediate tiers they may have a length of not
length of the face.
Crib faces shall be laid solid
less than 8 feet, arranged to break joints.
or with spacers as indicated on the plans.
All framed surfaces shall receive a heavy coat of approved preservative
at the time of assembling.
Care shall be exercised in the erection of all cribs to produce a true
face as shown on the plans and all timbers or logs in faces shall be hori
(c)
zontal.
HIGHWAY
108
(d)
Ties.
(e)
Fastening.
BRIDGES
Logs shall be paid for at the contract price per linear foot, for each size
specified, for material remaining in the finished structure.
Filling material shall be paid for at the contract price per cubic yard
for the actual volume placed.
SECTION
23 Sectional Plate
2. 23. 1. Description.
CONSTRUCTION
designated on the plans or by the engineer,
lines and grades established by the engineer.
109
2. 23. 2. Materials.
The materials shall be as specified in division
IV.
2. 23. 3. Description
of Plates.
Plates shall consist of structural units of galvanized corrugated metal.
Standard plates shall have a covering width of not less than 47 inches,
measured along the neutral axis of the plate, and shall be available in
nominal lengths of 10 feet, 7% feet, 5 feet, and 2% feet.
(Plates have ap
proximately a 2-inch lip beyond each end crest, which results in the actual
length of a given structure being approximately 4 inches longer than the
In constructing footings
nominal length, except when skewed or beveled.
for arches, this additional length must be provided for.)
The gage of plates and the radius of curvature shall be as specified in
or as shown on the plans.
division
The plates at longitudinal and circumferential seams shall be connected
by bolts.
Circumferential seams shall be staggered, so that no circum
ferential seam shall be continuous for a greater distance than the width of
the plates.
III
Each plate shall be curved to the proper radius, and the bolt holes
be so punched that all except end plates shall be interchangeable
in
the erection process.
As an alternate to this punching, the plates used in
the two bottom segments of the arch shall be punched with one row of bolt
holes adjacent to the longitudinal edge of the plate which is to rest upon
the pier or abutment.
Unless otherwise specified, bolt holes along those edges of the plates that
will form longitudinal seams in the finished structure shall be staggered in
rows 2 inches apart, with one row in the valley and one in the crest of the
corrugations.
Bolt holes along those edges of the plates that will form circumferen
tial seams in the finished structure shall provide for a bolt spacing of ap
proximately 12 inches.
The center of no hole shall be closer to the edge of the plate than 1%
times the diameter of the bolt.
Bolt holes in plates 7 to 1 gage, inclusive, shall be punched before plates
shall
are galvanized.
When the completed structure is to be a full circle pipe, the plates shall
be so curved that when bolted together, true circles shall be formed of the
The diameter of the pipe, in inches, divided by 15, shall
required diameter.
determine the number of plates required to make a full circle, unless other
wise shown on the plans.
Plates for forming skewed or sloped ends shall be cut so as to give the
Burnt edges shall be free from oxide and
angle of skew or slope specified.
burrs, shall present a workmanlike finish, and legible identification numerals
shall be placed on each part plate to designate its proper position in the
finished structure.
2. 23. 5. Field Erection Pipe Structures.
be made as provided in section 1 under Excavation
and as modified hereafter.
When a pipe structure is to be erected in a trench, the width of the
Excavation shall
and
Fill
HIGHWAY
110
BRIDGES
will not
After the pipe has been assembled, fill material shall be deposited evenly
on both sides of the pipe, in not to exceed 6-inch layers, until at least the
Special care shall be taken to thoroughly tamp
34 point has been reached.
the backfilling material between the pipe and the sides of the trench or, for
a distance each side of the pipe equal to the diameter of the pipe. Above
the 94 point, the fill shall be placed uniformly on each side of the pipe in
layers not to exceed 12 inches until a height is reached equal to the diameter
of the pipe, after which the remainder of the fill may be made from one
direction, but only under the supervision of the engineer.
When strutting is specified, the pipe shall be strutted as provided in
article 2. 23. 7. The bottom row of plates shall be lapped so that the
exposed edges
will
face downstream.
When backfilling arches before headwalls are placed, the first material
shall be placed midway between the ends of the arch forming as narrow a
The ramp shall be
ramp as possible until the top of the arch is reached.
built evenly from both sides, and the backfilling material shall be thoroughly
After the two ramps have been built to the top
compacted as it is placed.
of the arch, the remainder of the backfill shall be deposited from the top of
the arch both ways from the center to the ends, and as evenly as possible
on both sides of the arch.
If the headwalls are built before the arch is backfilled, the filling
material shall first be placed adjacent to one headwall, until the top of the
arch is reached, after which the fill shall be dumped from the top of the arch
toward the other headwall, with care being taken to deposit the material
evenly on both sides of the arch.
In multiple installations the procedure above specified shall be followed,
CONSTRUCTION
111
but extreme care shall be used to bring the backfill up evenly on each side
of each arch so that unequal pressure will be avoided.
In all cases the filling material shall be thoroughly but not excessively
tamped. Puddling the backfill will not be permitted.
Strutting.
Unless otherwise specified, sectional plate pipes shall be timber strutted
vertically 3 per cent out of round before placement of the fill. The timber
struts shall be in accordance with table 1 which follows unless an elongation
other than 3 per cent is specified.
The pipe shall be deformed the required amount by means of suitable
jacks. The method of jacking shall meet with the approval of the engi
neer. A. tolerance of % per cent above and below the specified amount will
2. 23. 7
be permitted.
Strutting shall be carried uniformly from end to end of pipe for pipes
without headwalls.
When headwalls are used there shall be no elongation of
the ends of the pipe.
The struts shall be left in place until the fill is
complete and compacted, unless otherwise instructed by the engineer.
2. 23. 8. Arch Substructures and Headwalls.
Substructures and headwalls shall be designed in accordance with the
requirements of division III.
Each side of the arch shall be anchored to the foundation by means
of a galvanized formed channel or galvanized structural steel angle. The
arch plates shall bear directly on the channel or angle.
Channels shall be made of 7-gage material not less than
inches
in depth with the shorter flange not less than 2 inches and the longer flange
not less than 4% inches. The 4% -inch flange shall be bolted to the bottom
row of plates on not to exceed 18-inch centers.
Anchors shall be attached
to the web of channel on approximately 18-inch centers.
If angles are used, they shall be not lighter than 3 inches by 3 inches
by
inch, and the vertical leg shall be bolted to the bottom row of plates
Angles shall be anchored to the founda
on not to exceed 18-inch centers.
tion by %-inch bolts, not less than 8 inches in length, on not to exceed
24-inch centers.
2. 23. 9. Workmanship.
2.
Uneven
laps.
Elliptical shaping
3. Variation from a
4. Ragged edges.
5. Loose, unevenly
6. Illegible brand.
7.
(unless
specified).
8. Dents
HIGHWAY BRIDGES
112
, o "3iO IOO O
co i0C0 c0^ coco id
00
v*
CO CO
t-4 H
.S.S b
io o iao o o to
S *! o
CS"" CO t>
co n id coco
IO
co
CQ
V
.Had
to ."
'3'
CM
o io oo
io co co.* coid
IO CO
Vi
E
a.S'
CO
oi
0 B
.9
to
i
M
CU
- coco '
IO o o o
Tfid oo coid Tf
.2.6 B .
to
i
BiS
Cft
==mo
w coio
CO
oo o o
id co coio
to io o
io co***
aj
.2 b a
to
co
ij
0J
ft
-flJ
w
B
cd
co,J
.2 B
' t
.5 *
# ;
id
CO '
OS i
2 B a
m-.S
,a o
id
^1
ra e w
o..E'
CO CO
en
h
+
fir
.SB d
CO
f
w
.2 .2
8 1
8
X3
ai
-5 C
S
3
B
a
rt
-g.o
co
co""*^*
_j
Tftd co"s co
id
til
it
3gi
fl IH A CO
T3.2
<U
*i
O SOCU
bo
ft
tj
o
I
.2 B a
CO- "|
SJ olo
a* st
OS CO
io co
O O 0 IO Lfi oW iO IO
goto
io coo
io co
td
s s
iflO .0
^!
t ^.
5 c
o|o
COCO
to
id
51
v *.
<
o,.2<
(I'M h
CONSTRUCTION
113
of Measurement.
The footage to be paid for shall be the actual number of linear feet
of the pipe or arch, installed in place, completed and accepted.
The
measurement shall be as follows:
Pipes and arches with square and vertical ends, end to end of metal,
on center line of structure.
Pipes with skewed and vertical ends, end to end, on center line.
Pipes with square ends, beveled, average end to end at top and bottom
of pipe.
Pipes with skewed ends, beveled, average end to end at top and bottom
of pipe, parallel to center line.
Arches, with ends other than square and vertical, as noted on the plans.
SECTION 24 Wearing
Surfaces
2. 24. 1. Description.
Separate concrete wearing surface shall consist of a concrete pavement
placed over other deck construction.
It shall conform to details shown on
the plans.
The concrete may be with or without reinforcement.
The construction
shall conform to that specified for Concrete Masonry,
II.
2. Measurement
division
2. 24.
and Payment.
Payment for separate concrete wearing surface shall include the cost
of furnishing all materials, equipment, tools and labor necessary for the
completion of the work. Unless otherwise specified, separately placed con
crete wearing surfaces will be paid for on the basis of the number of square
yards of wearing surface complete in place.
Brick Wearing Surface
2. 24. 3. General
Requirements.
Brick wearing surfaces for concrete floors shall be placed only after
the concrete floor has been thoroughly cured.
2. 24. 4. Materials
HIGHWAY
114
2. 24. 6
Sand-Cement
BRIDGES
Bed.
Upon the prepared floor slab, the bedding course shall be placed and
shaped so that its finished depth shall be not less than % inch and not
more than 1 inch.
The bedding shall be shaped to a true surface parallel with the surface
of the finished roadway by means of a template extending the entire width
of the roadway, drawn forward upon the curbs or other guide rails. When
the width of the roadway precludes the use of a template spanning the
entire distance, the bedding shall be shaped in sections, using scantlings
adjusted to correct elevations as guides.
The bedding course shall be
struck off at least twice with the template.
Any irregularities discovered
shall be corrected and the bed struck off with the template to its correct
This operation shall be continued until perfect
elevation and contour.
alignment is secured.
directed by the engineer, in addition to shaping with a template
the bedding course shall also be compacted with a hand roller. The bedding
course shall be alternately struck off and rolled until perfect alignment
is secured. The roller shall be not less than 36 inches in diameter and 24
inches in width, and shall weigh not less than 10 pounds per inch of width.
When the use of the template and guiderails is impracticable in finish
ing the bedding course, it shall be shaped to the surface required by
means of hand lutes.
After final shaping, the bedding shall not be disturbed prior to laying
the brick.
If
Upon the bedding course as prepared, the brick shall be laid in suc
cessive courses with the better face or wire-cut side upward. They shall
be laid with the ends and sides in contact and lugs, if any, shall be turned
in one direction.
Alternate courses of brick shall begin with one-half a
brick. Each course shall be completed by batting in at the end, if neces
sary, with fragments of brick at least 3 inches long, a portion of the next
adjoining brick being broken off if necessary to give the minimum 3-inch
bat at the end of the course.
The fractured end of cut or trimmed brick
Every course of brick
shall be turned toward the center of the roadway.
shall be laid true and even and, except in special cases, perpendicular to
No course shall deviate from a straight line more than
the curb line.
2 inches in 30 feet.
All brick laying shall take place over brick already
laid and shall follow the completion of the bedding within 50 feet.
Immediately after laying the brick, the surface of the roadway shall
Any inferior brick shall be lifted out and turned
be swept and inspected.
over, or removed and replaced by acceptable brick.
CONSTRUCTION
116
Dressing.
Immediately after the joints have been filled, and while the filler is
still soft and pliable, the pavement shall be covered with a thin layer of
dry sand, stone or slag screenings, or granulated slag. This top dressing
shall be of such sizes that all will pass a 14 -inch sieve. As soon as the
dressing is spread, the surface of the pavement shall be rolled thoroughly
to bed the dressing in the asphalt coating.
2. 24. 13. Opening to Traffic.
Traffic shall not be permitted
cooled to air temperature.
2. 24. 14. Measurement
on
the pavement
and Payment.
Payment for brick wearing surfaces shall include the cost of furnishing
HIGHWAY BRIDGES
116
all materials, equipment, tools and labor necessary for the satisfactory
completion of the work. Payment will be made on the basis of the number
of square yards of wearing surface complete in place.
Asphalt Block Wearing Surface
2. 24. 15. General Requirement.
be placed only
Upon the mortar cushion prepared as described above, the blocks shall
laid with close joints and uniform top surface.
The blocks shall be laid by the pavers standing upon the blocks already
laid and not upon the bed of mortar, and shall be laid at right angles to
be immediately
CONSTRUCTION
117
the axis of the pavement with such crown as is shown on the plans, and
in such a manner that all longitudinal joints shall be broken by a lap of
approximately 4 inches. The blocks shall be laid so as to make the lateral
joints as tight as possible, consistent with keeping a good alignment across
the pavement, and where possible the longitudinal joints shall be immedi
ately closed by pressing each course in the direction of its length with a
lever.
After the blocks are laid, any irregularities in the surface of the pave
ment shall be corrected and the pavement immediately covered with clean,
dry sand, all of which shall pass a 10-mesh sieve. The sand shall be spread
over the surface and swept into the joints and shall be allowed to remain
on the pavement not less than 30 days, or until such time as the action
of the traffic on the pavement shall have thoroughly ground the sand into
all the joints.
The requirements for irregularities shall be the same as for brick as
given in article 2. 24. 10.
2. 24. 20. Opening to Traffic.
After the pavement is laid and sanded it shall be protected from all
vehicle traffic for a period of at least 7 days and for a longer period if
directed by the engineer.
2. 24. 21. Measurement
and Payment.
Payment for asphalt block wearing surfaces shall include the cost
of furnishing all materials, equipment, tools and labor necessary for the
satisfactory completion of the work. Payment will be made on the basis
of the number of square yards of wearing surface complete in place.
Bituminous
2. 24.
22. General.
Carpets
of the engineer,
climatic
conditions
of Subfloor.
If
HIGHWAY
118
BRIDGES
the subfloor shall be allowed to become thoroughly dry and then swept with
stiff brooms before applying the first coat.
(b)
Concrete Subfloor.
The requirements as to cleanliness, as specified above for wood subfloors, shall also apply to concrete subfloors.
Irregularities in the surface
such as might project into or injure the bituminous carpet shall be removed.
Immediately before applying the first coat the surface shall be swept clean
and no traffic permitted thereon until the carpet coat is placed.
2. 24. 25. Construction
(a) Prime
After
Coat.
the subfloor has been prepared as hereinbefore specified and is
thoroughly dry, the entire surface shall be covered with a first coat of the
tar specified in division IV for Tar for First or Prime Coat. The tar shall
be applied cold at the rate of M gallon per square yard.
No traffic shall
be permitted to use the surface thus treated.
The prime coat shall remain
in place 12 hours before applying the second coat.
(b)
Second Coat.
The tar used for the second coat shall be that specified in division IV
for this purpose.
The tar shall be heated in an open tank or kettle to a temperature
between 200" and 225 F. and applied evenly to the surface at the rate of
% gallon per square yard. The methods and appliances used shall be such
as to insure a uniform distribution of the tar over the surface of the road
A suitable pressure spraying device, preferably, shall be employed.
way.
Immediately after the tar is sprayed or otherwise deposited upon the road
way surface, it shall be smoothed out to a uniform thickness by means of
squeegees, mops or other suitable spreading device.
Care shall be taken
not to overheat the material, the proper temperature being obtained when
it will flow with reasonable freedom and remain fluid for a sufficient period
to permit the aggregate to become thoroughly incorporated
in the mass.
Immediately after the application of this coat of tar the surface shall
be covered with the aggregate at the rate of approximately 0.4 cubic foot
per square yard. Accurate measuring or weighing devices shall be provided
by the contractor to insure the proper quantity of aggregate being used.
The aggregate shall be spread evenly over the surface by means of squareAs soon thereafter as practicable the surface shall be
pointed shovels.
hand tamped or rolled with a heavy hand roller.
After rolling or tamping is completed, if successive applications of
tar
shall
(c)
be applied
Seal Coat.
If a seal coat is required by the special provisions, or by the notes on
the plans, it shall be constructed as follows:
Immediately after the second coat has been completed, it shall be given
a seal coat using tar of the same grade as that specified for the second coat.
CONSTRUCTION
119
The tar shall be heated to a temperature not in excess of 225 F., depending
upon the grade used, and shall be applied at the rate of M gallon per square
yard.
The seal coat shall be immediately covered with a light dressing
of clean dry sand, stone screenings or granulated slag.
2. 24. 26. Construction
of
as hereinbefore
specified and is
thoroughly dry, the entire surface to be covered with the mat shall be given
a first or prime coat of asphalt of the type and grade set forth in article
4. 22. 4.
For application, these asphalts may be heated to a temperature
of not more than 120 F. and shall be applied to the floor surface at the
rate of from 0.15 to 0.25 gallon per square yard, depending upon the
condition of the surface.
Caution shall be used in heating the asphalts to
the temperature of application. The treated surface shall be allowed to
cure until it becomes tacky before applying the second coat. No traffic shall
be allowed
(b)
Second Coat.
(c)
Seal Coat.
HIGHWAY
120
BRIDGES
Asphalt Mat.
(b)
Second Coat.
III
DIVISION
Design
Design
Analysis.
In
as a design convenience,
SECTION General
Features
of Design
Waterways.
3.Channel Openings.
The channel openings shall, in general, conform in width, height and
location to all Federal, State and local requirements.
Particular atten
tion is directed to the Federal laws governing the bridging of navigable
waters and to the fact that the U. S. War Department exercises control
over all the navigable waters of the United States.
In general the clear width of all openings and the clear vertical dis
tance between the superstructure and the highest flood water of which there
are records or other authentic evidences shall be sufficient for the passage,
without damage to the structure, of ice floes and the largest drift or debris
which may be expected.
3. 1.
requirements
121
122
HIGHWAY BRIDGES
The horizontal clearance shall be the clear width, and the vertical
clearance the clear height, available for the passage of vehicular traffic,
as shown on the clearance diagrams.
Unless otherwise provided, the several parts of the structure shall be
constructed to secure the following limiting dimensions or clearances for
traffic :
The clearances and width of roadway for 2-lane traffic shall be not
The roadway width shall be increased
less than those shown in figure 1.
at least 10 feet and preferably 12 feet for each additional lane of traffic.
3. 1. 9. Curbs and Safety Curbs.
The face of the roadway curb is defined as the sloping or vertical surface
Horizontal measurements of roadway
on the roadway side of the curb.
and curb widths are given from the bottom of the face, or, in the case of
stepped back curbs, from the bottom of the lower face for roadway widths.
The face of the roadway curb shall be not less than 12 inches from that
portion of the structure above the elevation of the top of the curb and
nearest the roadway except in those cases where the clear roadway width
is equal to or greater than the shoulder width but not less than the approach
DESIGN
123
pavement width plus 12 feet, in which case the 12-inch clearance may be
The curb height
omitted, thus making the provision of a curb optional.
shall be not less than 9 inches above the adjacent finished surface of the
roadway, when not otherwise determined or provided by law. That portion
of a curb more than 10 inches above the roadway surface shall be stepped
back or sloped back so that no part of a vehicle except the tires may come
in contact with it.
designated
u
o
z
<
<
UJ
_1
CURB
CURB -12"MINIMUM
_l
<
ROADWAY
SEE FOOTNOTE
2Hr
o
u
HORIZONTAL CLEARANCE
CLEARANCE DIAGRAM
TWO-WAY HIGHWAY TRAFFIC
FIGURE
Footnote For important roads, carrying or likely to carry fast and heavy traffic or large
of trucks, roadway widths greater than the above minimums should be given con
sideration.
A reduction of two feet in the above minimum requirements shall be permitted if safety
curbs or contiguous sidewalks are used, or if traffic lane widths are in excess of 12 feet.
If both conditions exist, a reduction of four feet shall be permitted.
In special cases where traffic is light and meeting of vehicles on the bridge likely to
be infrequent, or where the bridge exceeds 1,000 feet in length, a width of 24'-0" may be
permitted.
For all bridges under 50 feet in length it is preferable that the overall width shall con
form as nearly as practicable to the full cross section of the highway (shoulder to shoulder).
percentages
HIGHWAY BRIDGES
124
3. 1. 10. Railings.
Substantial railings along each side of the bridge shall be provided for
Consideration shall be given to the architectural
to protection of traffic.
features of the railing to obtain proper proportioning of its various mem
Consideration shall also
bers and harmony with the structure as a whole.
as far as consistent with safety and appearance,
be given to avoiding,
obstruction of the view from passing vehicles.
In
(1)
(2)
Roadway railings.
Sidewalk railings.
feet
inches above
to the curb.
and contraction
of railings
Drainage.
If
3. 1. 12. Superelevation.
The superelevation
of the floor surface of a bridge on a horizontal
curve shall be provided in accordance with the standard practice of the
except that the superelevation
commission for the highway construction,
shall not exceed 0.10 foot per foot width of roadway.
3. 1. 13. Floor Surfaces.
All
characteristics.
DESIGN
125
The thickness of plates and other parts in direct contact with locomotive
blast shall be not less than % inch for cast-iron, % inch for wrought-iron
or alloy, % inch for plain asbestos-board and %e inch for corrugated as
Pockets
bestos-board.
Bolts shall be not less than % inch in diameter.
which may hold locomotive gases shall be avoided as far as practicable.
All
fastenings shall be galvanized or of corrosive resistant material.
3. 1. 15. Utilities.
Where required, provision shall be made for trolley wire supports and
poles, pillars for lights, electric conduits, telephone conduits, water pipes
and gas pipes.
3. 1. 16. Roadway Width, Curbs and Clearances for Tunnels.
(a)
Roadway Width.
The clear width between curbs shall
for bridges.
(b)
be
be 30 feet.
MINIMUM
CURB
CLEARANCE
DIAGRAM
FOR TUNNELS
FIGURE
CLEARANCE
T^T
S
FOR BRIDGES
* 1
31
r"
VERTICAL
IB"
NOT
-CURB
LESS
THAN
14 FT.
HIGHWAY BRIDGES
126
(c)
Curbs.
(d) Vertical
18 inches.
Clearance.
(a)
Roadway Width,
for
Depressed Roadways.
Width.
Roadway
bridges.
Clearance Between Walls.
The minimum width between walls for depressed roadways
two lanes of traffic shall be 30 feet.
(b)
(c)
carrying
Curbs.
18 inches.
3. 1. 18. Roadway
Underpasses
APPROACH
PAVEMENT
MINIMUM
CURB
18
30
FT.
MINIMUM
TRAFFIC
FIGURE
The height of
(Undivided
DESIGN
(a)
127
Widths.
The clear width between walls or columns shall be not less than 6 feet
wider than the approach pavement, but in no case shall the width be less
than 30 feet.
curbs,
if
curbs, or
traffic.
(c)
if
Curbs.
18 inches
in width.
SECTION 2 Loads
3. 2. 1. Loads.
Structures shall
be
they exist:
(1)
(2)
(3)
(4)
(5)
Dead load.
Live load.
Impact or dynamic effect of the live load.
Wind loads.
Other forces, when they exist, as follows:
Longitudinal force, centrifugal force, thermal forces, earth
erection
pressure, buoyancy, shrinkage stresses, rib shortening,
stresses, ice and current pressure, and earthquake stresses.
separately.
3. 2. 2. Dead Load.
The dead load shall consist of the weight of the structure complete,
including the roadway, sidewalks, and car tracks, pipes, conduits, cables and
other public utility services.
The snow and ice load is considered to be offset by an accompanying
decrease in live load and impact and shall not be included except under
special conditions.
HIGHWAY BRIDGES
128
490
450
175
50
150
120
100
140
60
150
Cinder filling
(a)
(per
200
170
Loads on Culverts.
or culvert untrenched
P=WH
H 0.87 B)
as rock or
for H>1.7 B
.385H
(such
= 2.59
BW^e
<
(1.92
1
.7
P=W
on unyielding foundation
l^for
is
where P=the unit pressure in pounds per square foot due to earth backfill
B= width in feet of trench, or in case there no trench, the overall width
of the culvert
H = depth in feet of fill over culvert
W= effective weight per cubic foot of fill material, which may be taken as
70 percent of actual weight in accordance with above stated provisions.
(
2
)
Note Formula
has been derived from Iowa Engineering Experiment Station Bul
letin 96, "The Theory of External Loads on Closed Conduits in the Light of The Latest Ex
periments," by Anson Marston, Director, February 19, 1930.
3. 2. 3. Live Load.
moving
load
DESIGN
129
3. 2. 4. Overload Provision.
The following provision for overload shall apply to all loadings except
the H 20 and H 20-S 16 loadings.
Provision for infrequent heavy loads shall be made by applying in any
single lane an H or H-S truck as specified, increased 100 per cent, and
without concurrent loading of any other lanes. Combined dead, live and
impact stresses resulting from such loading shall not be greater than
The overload shall
150 per cent of the allowable stresses allowed herein.
apply to all parts of the structure affected, including stringers, but except
ing flooring.
3. 2. 5. Highway Loadings.
(a)
General.
(b) H
Loadings.
(c) HS Loadings.
The H-S loadings are illustrated in figures 5 and 6. They consist
of a tractor truck with semi-trailer or of the corresponding lane loading.
The H-S loadings are designated by the letter H followed by a number
indicating the gross weight in tons of the tractor truck and the letter S
followed by the gross weight in tons of the single axle of the semi-trailer.
The variable axle spacing has been introduced in order that the spacing
of axles may approximate more closely the tractor trailers now in use.
The variable spacing also provides a more satisfactory loading for con
tinuous spans, in that heavy axle loads may be placed on adjoining spans
to produce maximum
negative moment.
(d)
Classes of Loadings.
Highway loadings shall be of five classes: H 20, H 15, H 10, H 20-S 16
and H 15-S 12. Loadings H 15 and H 10 are 75 per cent and 50 per cent,
respectively, of loading H 20. Loading H 15-S 12 is 75 per cent of loading
H 20-S 16. If loadings of weights other than those designated are desired,
they shall be obtained by proportionately changing the weights shown for
both the standard truck and the corresponding lane loads.
( e)
Designation of Loadings.
The policy of affixing the year to loadings, to identify them, was
instituted with the publication of the 1944 edition in the following manner:
H10-44
H10 Loading, 1944 Edition shall be designated
H15-44
H15 Loading, 1944 Edition shall be designated
H20 Loading, 1944 Edition shall be designated
H20-44
H15-S12 loading, 1944 Edition shall be designated
H15-S12-44
H20-S16 Loading, 1944 Edition shall be designated
H20-S16-44
'
The affix remains unchanged until such time as the loading specifica
tion is revised.
The same policy for identification shall be applied, for
HIGHWAY BRIDGES
130
) Minimum Loading.
For trunk highways, or for
Noth: In explanation of
mates
the
3. 2. 6. Traffic Lanes.
Where the spacing of main supporting members exceeds 6.5 feet for tim
ber floors or 10.5 feet for concrete or steel grid floors, the lane loading or
standard trucks shall be assumed to occupy a width of 10 feet. These loads
shall
be placed
Wc
in design traffic lanes having a width of W=
N.
and
W= Width of
Wc (in feet)
20 to 30 inc
over
over
over
over
over
over
over
over
30 to 42 inc
42 to 54 inc
54 to 66 inc
66 to 78 inc
78 to 90 inc
90 to 102 inc
102 to 114 inc
114 to 126 inc
N
2
3
4
5
6
7
8
9
10
DESIGN
131
IH
H
H
8.000- LBS
6,000 -LBS4,000- LBS.
20-44
15-44
10-44
IW
32,000-LBS.
24,000-LBS-
16,000-LBS.
-14-00.1
W-
-E
0.1 W
lO-o'cLEARANCE&LOAD
LAME WIDTH
CURB->
2-0"
6'-0M
STANDARD
TRUCKS
FIGURE
* In the design of floors (concrete slabs, steel grid floors, and timber floors) for H-20 or
H-20-S-16 loading, one axle load of 24,000 pounds or two axle loads of 16,000 pounds each,
spaced 4 feet apart shall be used, whichever produces the greater stress, instead of the 32,000pound
axle
shown.
HIGHWAY BRIDGES
132
3. 2. 8. Application of Loadings.
(b) Number
in article
3. 2. 9.
Spans.
18,000
FOR
MOMENT
H20-44
20
-S
15-44
I5-SI2-44
JiyUNIFORM
LOAD
LANE
AND
9,000 FOR
13,000
{9,000
320.LBS.
HIO-44
PER
MOMENT
OR SHEAR
LINEAR
FOOT
OF LOAD
LANE
HS LANE LOADINGS
Note
For the loading of continuous spans involving lane
load.
(c) which provides for an additional concentrated
:
LANE
LOADING
FIGURE
3.2.8
OF LOAD
LOADING
-CONCENTRATED LOAD
FOOT
LOADING
MOMENT
SHEAR
3,500 FOR
500 FOR
LOAD
L-CONCENTRATED
LOADING
16-44 LOADING
-G5
DESIGN
133
Stress.
-t
32,000 LBS:
24,000 LBS.
32,000 LBS.
24,000 LBS.
0'|wh
- WIDTH OF TIRES SHALL BE THE
SAME AS THE STANDARD H TRUCKS-
|-
0.4* -
oVw^j-
. 0.4VV-
V-VARIABLE
lO-o'cLEARANCE
8c LOAD
LANE WIDTH
CURB-,
2-0
t'-o"
2-0_
In
of floors (concrete slabs, steel grid floors, and timber floors) for H-20 or
H20-S16 loading, one axle load of 24,000 pounds or two axle loads of 16,000 pounds each,
spaced 4 feet apart shall be used, whichever produces the greater stress, instead of the 32,000pound axle shown.
the design
HIGHWAY
134
BRIDGES
A show which loading controls for simple spans. The axle spacing
for H-S trucks shall be varied between the specified limits to produce
appendix
maximum
stresses.
continuous spans, the lane loading shall be continuous or discon
tinuous, as may be necessary to produce maximum
stresses, and the
concentrated load or loads as specified in paragraph (c) shall be placed in
such position as to produce maximum stresses.
For
100
90
75
P = live
ft.).
Curbs shall be designed to resist a lateral force of not less than 500
pounds per linear foot of curb, applied at the top of the curb, but at a
point not over 10 inches above the floor.
(c)
',
DESIGN
135
(2)
Railings.
Sidewalk railings shall be designed to resist the same forces as
those specified for roadway railings, subject to the same restrictions
concerning curb heights.
Where through trusses, girders, or arches
separate the sidewalk and roadway or where sidewalks are protected
by curb railings, the sidewalk railings shall be designed only for the
forces specified for the top rail.
Sidewalk
3. 2. 12. Impact.
(a) Group
A.
(b) Group B.
retaining walls, piers and piling except Group
(1)
Abutments,
(2)
(3)
(4)
(5)
(2).
(A)
feet or more.
( c) Impact Formula.
The amount of this allowance or increment is expressed
of live load stress, and shall be determined by the formula:
I=ETl25
the
as a
fraction
in which
to produce
HIGHWAY BRIDGES
136
"
"
"
"
Longitudinal
Provision shall
to 1'
l'l"to2'
Forces.
be made
bearings
shall also
be provided
DESIGN
137
produces greater stress than the combined wind and lateral forces of
paragraphs (1) and (2). This requirement shall not apply if the provision
of paragraph (6) is effective.
(6) A reinforced concrete floor slab effectively keyed to its support, or
a steel grid floor adequately attached to its supports, may be assumed to
resist within the superstructure the wind loads specified under item (2).
3. 2. 15. Thermal Forces.
Temperature
rise
Concrete Structures
Moderate climate
Cold climate
30
35
F.
F.
Temperature
fall
40 F.
45
F.
All piers and other portions of structures which are subject to the
force of flowing water, floating ice, or drift shall be designed to resist the
maximum stresses induced thereby.
Pressure of ice on piers shall be calculated at 400 pounds per square
inch. The thickness of ice and height at which it applies shall be determined
by investigation at the site of the structure.
Effect of flowing water on pier
P=KV2, where
P= pressure in pounds per square foot,
V= velocity of water in feet per second,
K=a
3.2.
7. Buoyancy.
considered.
HIGHWAY BRIDGES
138
All designs shall provide for the thorough drainage of the back-filling
material by means of weep holes and crushed rock, pipe drains or gravel
drains, or by perforated drains.
SECTION 3 Distribution of
Loads
beams or stringers, no
longitudinal distribution of the wheel loads shall be assumed. The lateral
distribution shall be determined as follows : v
(1) Interior Stringers.
Interior stringers shall be designed for loads determined in accordance
with the following table :
Kind of floor
plank
in thickness,
4 inches
wood block on 4-inch plank
subfloor
or multi-thickness
plank more than 5 inches
Strip
Strip
inches
or
more
in
4.0
8.75
4.5
4.0
If
5.0
S exceeds 5.0 ft.
see footnote*
If
6.0
S exceeds 6.0 ft.
see footnote*
If
4.25
S exceeds 6.5 ft.
see footnote*
If
5.0
S exceeds 10.5 ft.
see footnote*
grid
thick)
Steel
Steel
grid
(less
than
(4 inches
4 inches
or more)
If
4.5
4.0
6.0
S exceeds 6.0 ft.
see footnote*
If
5.0
S exceeds 10.5 ft.
see footnote*
DESIGN
139
(c) Bending
Moment
in Floor Beams
(Transverse).
In calculating bending moments in floor beams no transverse distribu
tion of the wheel loads shall be assumed.
If longitudinal stringers are omitted and the floor is supported directly
on floor beams, the beams shall be designed for loads determined in accord
ance with the following table :
Fraction of wheel load to each
Kind of floor
floor beam
S
4
Strip
wood block
on 4-inch
in thickness,
4 inches
subfloor or multi-thickness plank more than 5 inches
plank
thick.
S
4.5
S*
5
S*
6
Steel grid
thick )
S *
4.5
S *
6
thickness.
*
S exceeds denominator, the load on the beam shall be the reaction of the wheel
assuming the flooring between beams to act as a simple beam.
If
3, 3, 2. Distribution
(a)
loads
Bending Moment,
according
E= width of
* The slab distribution set forth herein is based, substantially, upon the "Westergaard"
theory.
The following references are furnished concerning the subject of slab design :
Public Roads, March, 1930, "Computation of Stresses in Bridge Slabs Due to Wheel
Looads," by H. M. Westergaard.
University of Illinois Bulletin No. 303, "Solutions for Certain Rectangular Slabs Con
tinuous Over Flexible Supports," by Vernon P. Jensen ; Bulletin 304, "A Distribution
Procedure for the Analysis of Slabs Continuous Over Flexible Beams," by Nathan M.
Newmark ; and Bulletin 315, "Moments in Simple Span Bridge Slabs with Stiffened Edges,"
by Vernon P. Jensen.
HIGHWAY BRIDGES
140
curbs on bridges
across culverts
Q= uniform lane load per linear foot of lane
P1 and P2=load on one wheel
P1 = load on one wheel of single axle
P2=load on one wheel of tandem axle
P'= concentrated lane load per lane.
Case
Freely supported
+.25^S
+ .25 S
'1 andem
p.,
+.25^?S
+.2^rS
+ .23^S
.2 S.
Continuous
Spans
Spans
+.2^8
'.2
E,
Axles
Spans 2' to 7', E = .36S+2.58
po
Note: In the design for H-20 or H20-S16 loads, the single 24,000 pound axle governs
for spans under 10.5 feet and the two 16,000 pound axles govern for spans of 10.5 feet or over.
Case
Main Reinforcement
Parallel to
Traffic*
Spans 2 to
Feet
12
Distribution, E=.
175 S+3.2
+.25
Note:
Continuous
spans
+.2
E=
10N+W
4N
Spans over
12 Feet
Lane loads:
* In the design for H20 and H20 S16 loads, the single 24,000-pound axle shall be used for
spans under 18 feet in accordance
with the formulas of cases B & C. For spans 18 feet and
over the two 16,000-pound axles govern and the moments obtained from the formulas of Cases
B & C using a single axle load of 24,000 pounds shall be increased by the percentage expressed
by the formula 1.6 (S-18).
DESIGN
Uniform load=
Concentrated
0.5W+5N
NP'
load=
0.5
141
W+5 N
The moment for slabs over 12 feet shall be calculated as follows : The
loads per foot of slab shall be determined according to the method given
for distribution of loads. The loads thus determined shall be placed on the
span or spans in position to cause maximum positive or negative moments.
The moment shall be calculated in accordance with standard practice for
design of simple and continuous spans.
(b)
Edge beams shall be provided for all slabs having main reinforcement
parallel to traffic. The beam may consist of the curb section reinforced, of
a beam support or of additional slab width. It shall be designed to resist
a live load moment of 0.10 P S where P=the wheel load and
S=span length.
20
exact analysis.
100
g
Maximum 50%
(d)
(e)
Unsupported
Edges, Transverse.
The design assumptions of this article do not provide for the effect of
loads near unsupported edges. Therefore, at the ends of the bridge and at
intermediate points where the continuity of the slab is broken, the edges shall
be supported
by diaphrams or other suitable means.
The diaphrams
shall be designed to resist the full moment and shear produced by the wheel
loads which can come on them.
(f)
Cantilever
Slabs.
according
be
distributed
HIGHWAY BRIDGES
142
Moment
E=.8X+3.75
P
= X foot-pounds
E
in which X= distance in
The distribution for each wheel load on the element parallel to traffic
shall be as follows :
W
E=.35 X+3.2 but shall not exceed
2N
( g)
Slabs Supported
foot-pounds.
on Four Sides.
the case of slabs supported along four edges and reinforced in both
directions, the proportion of the load carried by the short span of the slab
shall be assumed as given by the following equations:
In
For
For
load uniformly
b*
distributed, p =
&*
load concentrated
b*
b3
at center, p =
a3
+ W
The distribution width E for the load taken by either span shall be
Moments obtained shall be used
determined as provided for other slabs.
in designing the center half of the short and long slabs. The reinforcing
steel in the outer quarters of both short and long spans may be reduced 50
per cent.
In the design of the supporting beams, consideration shall be
given to the fact that the loads delivered to the supporting beams are not
uniformly distributed along the beams.
(h)
In
designing
(i)
Span Lengths.
of stringer.
Vz
thickness
For simple spans the span length shall be the distance center to center
of supports but not to exceed clear span plus thickness of slab.
DESIGN
143
(H 10 loading 10 inches;
H 20 loading 20 inches.)
Normal to direction of span plank floor, distribution = width of plank.
Normal to direction of span laminated floor, distribution = 15 inches.
Spline, or doweled floor not less than 5% inches thick, distribution = 4
15 loading
15 inches;
times thickness.
Span length
of
one
loading.
If
the flooring is continuous over more than two spans the maximum
bending moment shall be assumed as being 80 per cent of that obtained for
a simple span.
3. 3. 5. Steel Grid Floors,
(a) General.
HIGHWAY BRIDGES
144
with Concrete.
The strength of the composite steel and concrete slab shall be determined
The allowable stresses shall
by means of the "transformed area" method.
be as set forth in section 4.
'c ) Open
Floors.
wheel load shall be distributed, normal to the main bars, over a width
of W plus twice the distance center to center of main bars, where W equals
Bending moment shall be
1 inch per ton of total weight of loaded truck.
calculated as specified in section 3 for concrete slabs.
The strength of the
section shall be determined by the moment of inertia method.
The allow
able stresses shall be as set forth in section 4.
SECTION
Unit
and Bearing
Power
of Soils
3. 4. 1. General.
For the purpose of application of stresses and pile loads, the loads and
forces shall be divided into two groups:
(a) Group A.
Buoyancy
Dead load
Earth
Live load
Impact
pressure
(b) Group B.
Longitudinal forces
Wind loads
Shrinkage stresses
Rib shortening
Centrifugal force
Back-fill (to original ground line)
Erection stresses
Ice
Current
Earthquake
Thermal stresses
Steel Structures
DESIGN
14S
18,000
18,000
13,500
18,000
Axial
compression,
gross section:
Pin
L2
15,000 hi-^r
ends
15,000^-;
ends
in inches.
For compression members with values of L/r greater than 140, and for
compression members of known eccentricity, see appendix "B."
Compression in extreme fibers of rolled shapes, girders
and built sections subject to bending (for values of
L/b
18,000 5
^_
L =
18,000
27,000
11,000
18,000
13,500
11,000
24,000
up to 25 inches
600d
20,000
Diameters
from
p 13,000
25 to 125 inches
3,000
20,000
d
p
Vd
HIGHWAY
146
BRIDGES
In proportioning rivets
Rivets.
98-41
S. T.
(A.
20,000
40,000
3. 4. 4. Wrought Iron.
hapes and bars, A. A. S. H. O. M 100-39
(A. S. T. M. A 42-47).
Pipe (A. S T. M. A 72-45).
Tension
Bending on extreme
(A. S. T. M. A 207-39).
14,000
14,000
fiber
For
shall
steel.
cast iron of the grades specified in division
able unit stresses shall be used:
Bending on extreme fiber
For
Shear
Direct compression
3. 4.
IV
(short columns)
. .
2,000
Steel.
242-46.
steel,
net section
Tension in extreme fibers of rolled
shapes, girders and built sec
tions subject to bending
Axial compression, gross section:
Stiffeners of plate girders
% in. and
under
50,000
over J in. to
1 XA in. inch
45,000
27,000
24,000
22.000
27,000
24,000
22,000
27,000
24,000
22,000
over
2
1 14 in . to
in. incl.
40,000
DESIGN
147
Riveted ends
22,000-0.56^
20,000-0.46^
18,000-0.39^
Pin
22,000-0.73^
20,000-0.61
18,000-0.48^
ends
For compression members with values of L/r greater than 125 low-alloy
steel, and for compression members of known eccentricity see Appendix B.
Compression in extreme fibers of
rolled shapes, girders and built
sections, subject to bending,
gross section.
(Values of L/b not to exceed 25
for low-* loy steel)
Compression, splice material gross
section
Stress in extreme fibers of pin
Shear in plate girder webs, gross
sections
Diagonal tension in webs of girders
and rolled beams at sections
where maximum
shear and
bending occurs simultaneously.
Shear in pins
Bearing on pins (not subject to
rotation)
Bearing on milled stifleners and
other parts in contact
Bearing on pins subject to rota
tion (not due to deflection)
Bearing on rollers and rockers:
Same formulas as in article 3.4.2.
NOTE
elled flanges
the greatest
tj
j.2
24,000-6.67^
22,000-6.11^
27,000
40,000
24,000
36,000
22,000
32,000
15,000
14,000
12,000
27,000
20,000
24,000
18,000
22,000
16,000
36,000
32,000
28,000
40,000
36,000
32,000
18,000
16,000
14,000
27,000-7.50g.2
For determining
Axial
Silicon steel
Nickel steel
24,000
30,000
24,000
30,000
24,000
30,000
20,0000.46^
24,000 0.66^
Pin
20,000 0.61
24,0000.86^
ends
j2
HIGHWAY BRIDGES
148
For compression on members with values of L/r greater than 130 for
silicon steel and 120 for nickel steel, and for compression members of known
eccentricity see appendix "B."
Silicon steel
extreme fibers of rolled
shapes, girders and built sections, subject
to bending, gross section (for values of
L/b not greater than 25 for silicon steel,
L2
24,000 6.67por 20 for nickel steel
Compression in
Nickel steel
30,000 8.33
24,000
36,000
14,000
30,000
44,000
17,500
24,000
18,000
32,000
27,000
22,000
40,000
36,000
44,000
16,000
18,000
L2
for Welding.
The allowable unit stresses in pounds per square inch of effective area of
weld shall be as given in the current specifications of the American Welding
Society for Welded Highway and Railway Bridges.
3. 4. 10. Bearing on Masonry.
800
400
1,000
700
(The above bridge seat unit stresses will apply only where the edge of
bridge seat projects at least 3 inches (average) beyond edge of shoe or plate.
Otherwise, the unit stresses permitted will be 75 per cent of the above
amounts.)
Concrete Structures
3. 4. 11. Concrete Stresses.
(a)
Standard Notations
and Assumptions.
DESIGN
149
fc =
f'c
(b)
General.
It shall
Allowable
Stresses
(c) Flexure.
Values if
f'c =30 00
fc =
}i f 'c
fc = .03 f'c
1000
90
None
(d)
Shear.
Beams without web reinforcement:
bars not anchored
Longitudinal
footings
Longitudinal bars anchored
Beams with web reinforcement:
Longitudinal bars not anchored
Longitudinal bars anchored
Punching shear
(e) Bond
or plain
concrete
02
03
f'c
f'c
60
90
046 f'c
06 f'c
053 f'c
140
180
160
on Piles
(in Seals).
Timber, steel or concrete piles, 10 lbs. per square inch.
pile has the resistance to pull thereby induced.)
(Providing the
HIGHWAY
150
(f)
(g)
BRIDGES
Columns
3. 4. 10.
L/D from 3 to
clusive, reinforced with longitudinal bars:
With lateral ties
Value if f'c=3000
equal
12
(4)
Eccentrically
L/D
-i
fc = .25f'cl
l + (n-l)p|
+12p')f
=
\f
(3)
750
in
fc = (.25
Spirally reinforced
fc = .25f \>
l)p]
( 2)
to or less than 3.
L/D
+
(n
'c[l
CI)
(l.33 -3^5)^
With
L/D
greater than
12
r2
fc
L/D
fe
With
fe
loaded columns
1+SS
+r
= f",
1+K
ec
is
is
fe,
fe,
Steel reinforcement:
18,000
16,000
.05
fo
(maximum 150)
Intermediate
Grade
3. 4. 12. Reinforcement.
20,000
16,000
.05 f'c
(maximum 150)
.075 f'c
.075 f'c
(maximum 225)
(maximum 225)
above allowable bond stresses fhall be reduced for footings as provided under
"Reinforcement," Article 3.5.2 (f).
According to article 4. 5.
it is required that the grade of reinforcing ateel shall
be either "Structural"
or "Intermediate," unless otherwise stipulated. In the event allowable
by
stresses for "Intermediate Grade" steel are used, it is necessary to modify article 4. 5.
special provision, to require that "Intermediate Grade" steel be furnished.
The grade re
quired should also be noted on the plans.
1
1,
NOTE: The
the item
DESIGN
151
Timber Structures
3. 4. 13. Standard
The following are the allowable unit stresses for treated timber
Fiber
Shortleaf
#f Tidewater
#f
1400#f Close-grained
1200#f
Douglas
(Inland)
Larch
Fir
#f Dense Shortleaf
Southern Pine
Red1200#f Close-grained
1000
....
#f Western
Red
Cedar
1200#f Port Orford Cedar.
1200#f Douglas Fir
...
(Coast)
1100#f Port Orford Cedar.
1100#f Tidewater Red
1100#f
120
120
380
380
1,600,000
1,300,000
1800
120
380
1,600,000
1600
100
345
1,600,000
1600
80
335
1,500,000
1600
100
345
1,300,000
1600
120
380
1,600,000
1600
80
267
1,200,000
1400
1400
120
120
300
500
1,200,000
1,500,000
1400
100
380
1,600,000
1400
80
267
1,200,000
1200
1200
80
100
315
325
1,500,000
1,300,000
1200
100
380
1,600,000
1200
70
267
1,200,000
1000
1200
100
100
200
250
1,000,000
1,500,000
1200
1100
100
80
325
250
1,600,000
1,500,000
1100
1100
100
100
300
500
1,200,000
1,500,000
Red-
1200#f
1200
1800
1800
Red
Oak
1400#f Dense Longleaf
1400
Modulus
of
elasticity
South-
1600#f Close-grained
Douglas Fir (Coast)
1600#f Close-grained
Douglas Fir (Inland)...
1600#f Close-grained
1400
Compression
perpendicular
to grain
Fir
Maximum
horizontal
shear
stress
in bending
or tension
Dense Douglas
1800#f
Oak
Compression
1 200 #c
-
1200#
1200#c
1200#c
1200#c
1200#c
1100#c
1100#c
1100#c
Larch
1100#cOak
1200
1^00
1^00
"J
n00
HIGHWAY BRIDGES
152
Compression
Columns
Close-grained
redwood
1100
1100
1000
1000
1000
1000
800
Oak
Dense longleaf southern
Close-grained redwood
Western red cedar
pine
.'
For untreated timber, except for temporary use, the stresses given
the above table shall be reduced to the following percentages:
Kind of stress
Extreme fiber in bending
Compression perpendicular to grain
Compression parallel to grain
Horizontal shear
Modulus of elasticity
3. 4. 14. Formulas
(a) Horizontal
for
in
Per cent
87%
70
92
100
100
of Stresses in Timber,
the Computation
s~2
bd
Where
(h) Axial
in Rectangular Columns.
P = total load in pounds
A = area of cross section in square inches
Compression
not over
Intermediate columns,
11
between
11
and
K.
DESIGN
Long columns.
163
K,
50
.274
(Hinged ends
Compression on Connector-Joined Spaced Columns.
assumed).
Timber connectors shall include devices used in the contact surfaces of
timber joints to increase the strength or shear resistance over that of
bolted joints.
(c) Axial
^Xl.25
^
50
of individual
Spacer blocks.
A single spacer block shall be within 5 per cent of L
from center of column. If more than one spacer block is used, the distance
between any two blocks shall not exceed one-half the distance between
Connectors of the same size as
centers of connectors in the end blocks.
used in the end block shall be used for spacer blocks under these conditions.
Spacer blocks shall be in contact with the full width of sides of the main
timbers.
Laminated columns and spaced columns with less than full width
spacer pieces shall not be permitted.
Intermediate columns.
Condition A.
K2 = 1.5811
Condition B.
^ to ^
P
A
Long columns.
.274
EX2.5
for condition A
X'(fe)'
P
(d)
.274
EX3
for condition B
The safe load on a round column shall not exceed that permitted for a
square column of the same cross-section area.
The diameter of a tapered
HIGHWAY BRIDGES
154
column shall be measured at a point one-third the length from the small
end and in no case shall it be assumed as more than 1% times the least
diameter at its small end. The compressive stress at the small end of a
tapered column shall not exceed the allowable stress for a short column.
(e)
Notched Beams.
Beams notched upward in the bearing face on supports
to maximum end load R as determined by the formula.
D
R
2bd2
shall
be limited
3h~
R
H
(f)
(g) Timber
Connectors.
Material
Alluvial soils
Clays
V2
Max.
1
Sand, confined
Gravel
10
Min.
soils,
DESIGN
155
30
25
30
15
25
35
Dry Sand. .
Miost Sand
Wet Sand.
Clay
Compact earth
to
to
to
to
to
to
45
35
45
30
45
40
Gravel .
Cinders
Coke
Coal.
30
25
30
25
to 40
to 40
to 45
to 35
In the absence of exact data which has been determined by field inves
tigation and soil analysis, the angle of repose of the material shall be
assumed to be the minimum given in the table.
3. 4. 17. Bearing Value of Piling.
(a)
General.
The design loads for pile3 shall not be greater than the minimum value
which shall be determined for Case A, Case B and Case C; where Case A is
the capacity of the pile as a structural member, Case B is the capacity of the
pile to transfer its load to the ground and Case C is the capacity of the
The values
ground to support the load delivered to it by the pile or piles.
assignable to each of the three cases shall be determined by making subsur
face investigations or tests of sufficient extent to justify the assumed design
values used for the particular condition of support under consideration.
In determining the bearing value of piles for use in designing, considera
tion shall be given to all information available relative to the subsurface
conditions.
Consideration shall also be given to :
The difference between the supporting capacity of a single pile and
a group of piles.
(2) The capacity of the underlying strata to support the load of the
pile group.
(3) The effect of driving additional piles and the effect of their loads on
(1)
(4)
(b)
adjacent structures.
Possibility of scour and its effect.
Case A.
(2)
Required
Subsurface
Investigations:
HIGHWAY
156
BRIDGES
that portion which is or may be, as a result of scour, in air, water, muck, peat,
thin mud or other very plastic or fluid material.
of Pile to Transfer Load to the Ground.
(1) Point-bearing Piles. A pile shall be considered to be a point-bearing
pile when placed or driven on or into a material which is capable of develop
ing the pile load by direct bearing at the point with reasonable factor of
(c)
Case B.
Capacity
safety.
The allowable load at the tip of the pile shall not exceed the following:
point
does
(a) Driving and loading test piles. The safe allowable load shall be as
defined by article 2.3.6 (a).
(b) Pile-driving experience in the vicinity. When piles are designed on
the basis of experience in the vicinity, due consideration will be
given to the variation in pile types and lengths, and in the varia
tion of the soil strata. Where possible, the complete driving records
of all piles in the vicinity shall be examined and compared to the
driving records of the project piles.
(c) Adequate tests of the soil strata through which the pile is to be
driven.
These tests should be projected and compared, if possible,
to tests of similar material through which piles of known capacity
have been driven.
Investigations:
Sufficient borings shall be made to determine
the presence, position, and thickness of the material which is capa
ble of developing point bearing, and the log of borings shall show
the nature of the overlying strata in order that the extent of lateral
support may be determined.
If the point-bearing stratum is of
doubtful thickness and quality, the borings shall be made to suffi
cient depth below this stratum such that the capacity of a friction
(3) Required
Subsurface
(b)
(c) Combination
sified as either
except
where
DESIGN
where
adequate
friction may
157
strength
be designed under
by the
(d)
Case C.
shall
(1) The capacity of the ground to support the load delivered by the pile
investi
be determined from the results of the required subsurface
Capacity
Pile.
gations.
(b) Friction piles. Borings shall be made well below the tips of the
piles in order to determine the characteristics of the underlying
material. In most cases a study of those borings will suffice to
determine whether or not the underlying soil will support the loads
delivered to it, but in doubtful or special cases, especially large
foundation areas and important footings the material should be
investigated more thoroughly by soil mechanics methods.
A single row of piles shall not be considered as a group provided
that they are not spaced closer center to center than 2% times the
nominal diameter or dimension.
In those cases where piles are
driven in groups into plastic material, the design load shall be
determined by the loading of a group of piles or definite allowance
shall be made for the difference between the supporting capacity of
a single pile and a group of piles.
(Refer to (g).)
subsurface
investigations or test loads the maximum assumed design load for piles shall
be as given in the table below.
These values may be increased 25 per cent
for certain combinations of loads as specified in article 3. 4. 1.
The assumed pile loads shall be substantiated
by determining the allowable load by formula, when the piles are driven, as
provided in article 2. 3. 6. (b).
Types of Piles
Size or Diameter
at Butt*, Inches
8
10
12
14
16
20
24
* Timber
Timber
Tons
Concrete
Tons
18
20
24
28
20
24
28
32
40
50
..
piles,
diameter to be measured
Steel
(Friction)
'
'
E?
3 feet
16
20
24
28
from butt.
Tons
Steel
Point Bearing
6000 pounds per
sq. in. of point
area.
HIGHWAY
158
(f)
BRIDGES
Uplift.
Friction piles may
tained
uplift
,(n-l)m+(m-l)n
Where
E =the efficiency or the decimal fraction of the single pile value to
is
<j, <*,
3. 4. 18. Moments,
Substructures
SECTION
3. 5. 1. Piles.
(a)
General.
general, piling shall be used when footings cannot, at
reasonable
expense, be founded on rock or other solid foundation material. At loca
tions where unusual erosion may occur and the soil conditions permit the
driving of piles, they, preferably, shall be used as
protection against
scour, even though the safe bearing resistance of the natural soil is sufficient
to support the structure without piling.
In general, the penetration for any pile shall be not less than 10 feet
the length of the pile nor less than
in hard material and not less than
%
In
20
(b) Limitation of
Use.
DESIGN
159
(c)
Design Loads.
(d)
Spacing,
it
When the lateral resistance of the soil surrounding the piles is inade
quate to counteract the horizontal forces transmitted to the foundation or
when increased rigidity of the entire structure is required, batter piles shall
be used in the foundation.
(f)
Buoyancy.
(g)
pressure
shall be considered
in the design
as
If a square
be of approved size and shape.
section is employed, the corners shall be chamfered at least one inch. Piles,
preferably, shall be cast with a driving point and for hard driving, prefer
ably, shall be shod with a metal shoe of approved pattern. Piling may be
In general, tapered piling shall not
either of uniform section or tapered.
be used for trestle construction except for that portion of the pile which
lies below the ground line; nor shall tapered piles be used in any location
In general, concrete piles shall
where the piles are to act as columns.
have a cross sectional area, measured above the taper, of not less than 140
square inches and when they are to be used in salt water they shall have
a cross sectional area of not less than 220 square inches.
The diameter of tapered piles measured 2 feet from the point shall
In all cases the diameter shall be considered as
be not less than 8 inches.
The point in all cases, where
the least dimension through the center.
less
than 6 inches in diameter and
be
not
used,
shall
are
not
steel points
the pile shall be beveled, tapered or sloped uniformly from the point to
2
HIGHWAY BRIDGES
160
(h)
(i)
Steel Piles.
DESIGN
161
(j)
(a)
Depth.
may require.
(b)
Anchorage.
Footings on inclined smooth solid rock surfaces which are not restrained
by an overburden of resistant material, shall be effectively anchored by
means of anchor bolts, dowels, keys or other suitable means.
(c) Distribution of
Pressure.
soil pressures
be designed to keep the maximum
within safe bearing values. In order to prevent unequal settlement, footings
shall be designed to keep the pressure as nearly uniform as practicable.
In footings having unequal pressures and requiring piling, the spacing of
the piles shall be such as to secure as nearly equal loads on each pile as
may be practicable.
162
HIGHWAY BRIDGES
f d)
Spread Footings.
Spread footings which act as cantilevers may be decreased in thickness
from the junction of the footing slab with column or wall toward the edge
of the footing, provided sufficient section is maintained at all points to
provide the necessary resistance to diagonal tension and bending stresses.
This decrease in section may be accomplished by sloping the upper surface
of the footing or by means of vertical steps. Stepped footings shall be
cast monolithically.
Except in small structures, no footing shall have a thickness at the
edge of less than 2 feet.
When piles are used, the footing shall have an
edge thickness of not less than 18 inches above the tops of the piles.
(e) Internal
DESIGN
168
not anchored.
(f)
Reinforcement.
Footing slabs shall
and, where
anchored to
(g) Transfer of
2o per cent
10
per cent
(a)
General.
HIGHWAY
164
BRIDGES
of piles at the point of maximum
pressure.
Temperature.
(d) Drainage.
The filling material behind abutments shall be effectively
weep holes with French drains, placed at suitable intervals.
drained
by
3. 5. 4. Retaining Walls.
(a)
General.
(b)
pressure, in
in accordance
gravity type.
counterforted,
DESIGN
165
(c) Vertical
Walls.
be designed as cantilevers
at the base.
The vertical or face walls of counterforted and buttressed walls shall
be designed as fixed or continuous beams.
The face walls shall be securely
anchored to the supporting counterforts or buttresses by means of adequate
reinforcement.
supported
(d)
Counterforts
and Buttresses.
Temperature.
(f)
( g)
Drainage.
(a)
General.
be designed to withstand the dead and live loads superImposed thereon; wind pressures acting on the pier and superstructure;
the forces due to stream current, floating ice and drift; and longitudinal
forces at the fixed ends of spans.
Where necessary, piers shall be protected against abrasion by facing
them with granite, vitrified brick, timber or other suitable material within
the limits of damage by floating ice or debris.
Piers shall
(b) Pier
Nose.
(a)
be
Use.
Preferably, tubular steel piers shall not be used and they shall never
used in locations where they will be subjected to lateral earth pressure.
HIGHWAY BRIDGES
166
(b)
Depth.
(c) Piling.
Piles used in connection with tubular piers shall extend into the
In
concrete filling a sufficient distance to thoroughly brace the tubes.
general, these piles shall extend not less than 6 to 8 feet above the bottom
of the concrete.
of Shell.
The minimum thickness of the metal in the shells of tubular piers shall
be %e inch.
This thickness shall be increased where necessary to secure
strength and rigidity for placing the shell. In all cases the pier shall be
designed for safe pile or soil bearing values as specified herein, but when
the diameter required by these values is greater than that required for the
superstructure bearing, the diameter may be reduced at any splice point.
The minimum diameter of steel cylinders used for piers shall be 42 inches.
(d)
(e)
Dimensions
be butt joints.
Vertical joints may be
the corners of the plates are properly scarfed.
When field
splicing is necessary the lower section of the tube shall extend at least 2 feet
above the water line when in position.
if
lapped
(f)
Bracing.
SECTION 6 Structural
Steel Design
Preferably, through spans shall have only two trusses, arches or girders.
3. 6. 2. Spacing of Trusses and Girders.
Main trusses, arches and girders shall be spaced a sufficient distance
apart center to center, to be secure against overturning by the assumed
lateral forces.
3. 6. 3. Effective Span.
For
follows
the
calculation
of stresses,
span
lengths
shall
be
assumed
as
DESIGN
16?
3. 6. 4. Effective Depth.
For
follows:
effective
depths
shall
be
assumed
as
If
If
the live load and dead load stresses are of opposite sign, only 70 per
cent of the dead load stress shall be considered as effective in counteracting
the live load stress.
3. 6. 6. Combined
Stresses.
The design and details shall be such that secondary stresses will be
as small as practicable.
Secondary stresses due to truss distortion or floorbeam deflection usually need not be considered in any member the width
of which, measured parallel to the plane of distortion, is less than one-tenth
If the secondary stress exceeds 4,000 pounds per square
of its length.
inch for tension members and 3,000 for compression members, the excess
shall be treated as a primary stress.
3. 6. 8. Rolled Beams.
HIGHWAY BRIDGES
168
For tension members, except rods, eyebars, cables, and plates, the
greatest ratio of unsupported length to radius of gyration shall not exceed
200 for main members, and shall not exceed 240 for bracing members.
3. 6. 10. Deflection.
For
For
For
trusses
plate girders and rolled beams used as girders
continuous spans, the span length shall be considered
as the distance between dead load points of contraflexure.
1/10
1/25
be not
DESIGN
169
shall
if
be so increased
these ratios had not
Sections.
be as
of Metal.
Gusset plates for main members shall not be less than % inch in
Other structural steel, except for webs of rolled shapes, fillers,
thickness.
and in railings, shall be not less than
inch in thickness.
The web thick
ness of rolled shapes shall not be less than 0.23 inch.
Silicon steel plates
shall be not more than 1% inches thick, low-alloy steel plates not more
than 1% inches thick and nickel steel plates not more than 1 inch in thick
ness.
shall
be
increased
in
thickness
3. 6. 15. Compression
Members.
In
HIGHWAY
170
3. 6. 16
Rib
BRIDGES
Arches.
The thickness of web plates in solid rib arches shall not be less than the
following fractions of the depth as defined in article 3. 6. 15, except that
when the web is reinforced along its axis with a longitudinal rib of ample
cross-sectional area and rigidity, the thickness shall not be less than one-half
of these amounts:
Vtto
%o
Vi8
Vis
for
for
for
for
carbon steel.
silicon steel.
low-alloy steel.
nickel steel.
3. 6. 17. Outstanding
Size
of Pins.
If
Details
3. 6.
19. Size of
of Design
Rivets.
Rivets shall be of the size shown on the drawings, but generally shall
be % inch or % inch in diameter.
Rivets % inch in diameter shall not be
used in members carrying calculated stress except in 2% -inch legs of angles
and in flanges of sections requiring % rivets.
The diameter of rivets in angles carrying calculated stress shall not
exceed one-fourth of the width of the leg in which they are driven.
In angles whose size is not determined by calculated stress, %-inch
rivets may be used in 2-inch legs, %-inch rivets in 2 %-inch legs, %-inch
rivets in 3-inch legs, and 1-inch rivets in 3 %-inch legs.
Structural shapes which do not admit the use of %-inch diameter rivets
shall not be used except in handrails.
3. 6. 20. Pitch
of
Rivets.
In
Members.
DESIGN
to \V times the maximum
is reached.
171
pitch
The maximum
If
The minimum
shall be:
edge,
except in flanges
If
if
so used
Counter
HIGHWAY
172
BRIDGES
shall
of
Connections.
FUler:
(a) Welding.
When welding is called for on the plans it shall be designed according
to specifications of the American Welding Society, "Welded Highway and
Railway Bridges."
(b) Riveting.
If rivets
be extended
DESIGN
173
enough additional rivets to average the total stress in the member over the
combined area of the member plus the fillers. As an alternate, the additional
rivets may be passed through the connected members without extending the
filler.
If the filler is less than %-inch thick it shall not be extended beyond
the splicing material and additional rivets are not required.
Fillers %-inch
or more in thickness shall consist of not more than two plates, unless special
permission is given by the engineer.
3. 6. 34. Gusset Plates.
Gusset or connecting plates shall be used for connecting main members,
except when they are pin-connected.
The rivets connecting each member
shall be symmetrical with the axis of the member, so far as practicable,
and the full development of the elements of the member shall be given
consideration.
The gusset plates shall be of ample thickness to resist shear,
direct stress, and flexure, acting on the weakest or critical section of
maximum stress.
Re-entrant cuts, except curves made for appearance, shall be avoided
as far as practicable.
If the unsupported edge of a gusset plate exceeds the following number
of times its thickness, the edge shall be stiffened:
60
50
48
45
HIGHWAY BR1DGES
174
connections will be not more than 40 nor more than two-thirds of the
slenderness ratio of the member.
In compression members, the shearing stress normal to the member in
the plane of the lacing or perforations shall be that obtained by the follow
ing formulas
For structural
carbon steel,
For structural
V
P
L
r
=
=
=
=
To the shear so determined shall be added any shear due to the weight
of the member or to other forces, and the lacing proportioned for the
combined shear.
If the distance across the member between the rivet lines in the flanges
is more than 15 inches and a bar with a single rivet in the connection is
used, the lacing shall be double and riveted at the intersections.
The angle between the lacing bars and the aiis of the member shall be
approximately 45 degrees for double lacing and ^0 degrees for single lacing.
Lacing bars may be shapes or flat bars.
For main members the
minimum thickness of flat bars shall be ViO of the distance along the bar
between its connections for single lacing and %o for double lacing.
For
bracing members the limits shall be %o for single lacing and Vis for double
lacing.
The diameter of rivets in lacing bars shall not exceed one-third of the
width of the bar. There shall be at least two rivets in each end of lacing
bars riveted to flanges more than 5 inches in width.
Perforated Cover Plates.
When perforated cover plates are used instead of lacing bars and stay
plates, the following provisions shall govern their design:
DESIGN
175
(1) The thickness of cover plate shall not be less than vaa of the unsup
ported distance between the nearest lines of connecting rivets for carbon
steel, Va for silicon steel, %2 for low-alloy steel and Vio for nickel steel.
(2) The transverse distance from the perforation to the nearest line of
connecting rivets or point of support shall not exceed twelve (12) times
the thickness of plate when measured at the centerline of perforation.
In
pin-connected
Pin
Holes.
J!
4g
where S = pitch of any two successive
g = gage of the same holes.
For angles, the gross width shall be the sum of the widths of the legs
The gage for holes in opposite legs shall be the sum
less the thickness.
of gages from back of angle less the thickness.
For splice members, the thickness shall be only that part of the thick
ness of the member which has been developed by rivets beyond the section
considered.
The diameter
nominal
diameter
be taken
as % inch greater
than the
Pins shall be so located with respect to the gravity axes of the members
as to reduce to a minimum stresses due to bending.
HIGHWAY BRIDGES
176
Pin
Nuts.
authorized.
Bolted connections shall not be used unless specifically
Bolts shall be unfinished; turned as specified and meeting the requirements
of division IV ; or an approved form of ribbed bolt.
Bolts in tension shall have single self-locking nuts or double nuts.
3. 6. 44. Upset Ends.
Bars and rods with screw ends shall be upset to provide a section at
the root of the thread, which will exceed the net section of the body of the
member by at least 15 per cent.
3. 6. 45. Sleeve Nuts.
Sleeve nuts shall not be used.
3. 6. 46. Expansion and Contraction.
DESIGN
177
3. 6. 48. Bronze
be
firmly anchored.
and Shoes.
They
Expansion rollers shall be not less than 6 inches in diameter.
shall be connected by substantial side bars and shall be guided by gearing
or other effectual means to prevent lateral movement, skewing and creep
ing. The rollers and bearing plates shall be protected from dirt and water
and the design shall be such that water will not be
as far as practicable,
retained and that the roller nests may be inspected and cleaned easily.
3. 6. 52. Inclined
Bearings.
For
Bolts.
Trusses, girders and I-beam spans shall be securely anchored to the
substructure.
Anchor bolts shall be swedged or threaded to secure a satis
factory grip upon the material used to embed them in the holes.
The following are the minimum
requirements
For I-beam
with
\\i
HIGHWAY BRIDGES
178
Welding
6.
Filler
plates.
caps sup
for
Floor System
3. 6. 56.r.Stiffness of Floor Members.
Floor members shall be designed with special reference to stiffness by
making them as deep as economy or the limiting under clearances will
permit.
3. 6. 57. Stringers.
beams or be
continuous
be placed
feet long.
3. 6. 59. Floorbeams.
Floorbeams, preferably shall be at right angles to the trusses or main
girders and shall be rigidly connected thereto.
Usually floorbeam con
nections shall be located above the bottom chord and, in riveted work, the
bottom lateral system shall engage both the bottom chord and the floorIn pin-connected trusses, if the floorbeams are located below the
beam.
DESIGN
179
bottom chord pins, the vertical posts shall be extended below the pins to
make a rigid connection to the floorbeam.
3. 6. 60. End
Floorbeams.
61. End
to the abutment
backwall.
In
skew bridges without end floorbeams, the end panel stringers shall
be secured in correct position by end struts connected to the stringers and
to the main trusses or girders.
The end panel lateral bracing shall be
attached to the main trusses or girders and also to the end struts. Ade
quate provision shall be made for the expansion movement of stringers.
3. 6. 62. End Connection
Brackets.
stresses
3. 6. 64. Expansion
Joints.
To provide for expansion and contraction movement, floor expansion
joints shall be provided at the expansion ends of all spans and at other
points where they may be necessary.
Apron plates, when used, shall be designed to bridge the joint and to
of roadway debris upon
prevent, so far as practicable, the accumulation
Preferably, they shall be connected rigidly to the end
the bridge seats.
floorbeam.
Bracing
3. 6. 65. General.
Bracing shall
If
intersections.
if
HIGHWAY BRIDGES
180
3. 6. 66. Minimum Size
of Angles.
The smallest angle used in bracing shall be 3 by 2% inches. There
shall be not less than three rivets in each end connection of the angles.
3. 6. 67. Lateral Bracing.
Through truss spans, deck truss spans and spandrel braced arches
shall have top and bottom lateral bracing.
Lateral bracing is not required for deck plate girder or beam spans
of less than 125 feet which have a steel or concrete floor keyed or attached
to the supporting members and which are supported laterally by substantial
cross frames or diaphragms.
Deck plate girder or beam spans more than 40 feet in length which
have a timber floor shall have at least one system of lateral bracing in
combination with substantial cross frames or diaphragms.
The spacing of cross frames or diaphragms shall not exceed 25 feet.
Adequate temporary bracing shall be placed, if necessary during construc
tion.
be as deep
For
a discussion
of Elastic Stability,"
DESIGN
181
If
Plate Girders
The flange angle shall form as large a part of the area of the flange
as practicable.
Side plates shall not be used except where flange angles
The area of
exceeding % inch in thickness otherwise would be required.
cover plates shall not exceed 50 per cent of the total flange area (including
one-eighth of web) except when the heaviest flange angles are used, in
which case it shall not exceed 60 per cent.
The gross area of the compression flange shall be not less than the
gross area of the tension flange.
Flange plates shall be of equal thickness, or shall decrease in thick
ness from the flange angles outward.
No plate shall have a thickness
greater than that of the flange angles.
flange plates are used, at least one plate of the top flange shall
extend the full length of the girder, except where the flange is to be covered
with concrete. Any additional flange plates shall extend at least 1 foot
beyond the theoretical end but shall be not less than 2d+3 feet in length,
and there shall be a sufficient number of rivets at each end of each plate
to develop its full stress value before the end of the next outside plate is
reached.
The term "d" equals the depth of girder.
If
3. 6. 75. Thickness
of Web Plates.
of
The thickness
web plates, except those to be encased in concrete or
those properly stiffened longitudinally, shall be not less than Vi70 D for
carbon steel, not less than ^45 D for silicon steel, not less than ^40 D for
low-alloy steel and not less than Vi30 D for nickel steel, in which "D" is
the clear distance in inches between flanges (including side plates).
When one longitudinal stiffener is used, properly located with respect
to the toe of the compression flange and of adequate rigidity, both as pro
vided in article 3. 6. 81, the thickness of web plates shall be not less than
%70 D for carbon steel, not less than ^30 D for silicon steel, not less than
HIGHWAY BRIDGES
182
Mao
D for low-alloy steel and not less than %io D for nickel steel, in which
the clear distance in inches between flanges (including side plates).
"D" is
The number of rivets connecting the flange angles to the web plate
shall be sufficient to develop the increment of flange stress transmitted to
the flange angles, combined with any load that is applied directly to the
flange.
3.6.77. Flange
Splices.
Over the end bearings of plate girders there shall be stiffener angles,
the outstanding legs of which shall extend as nearly as practicable to the
End stiffeners shall be proportioned for
outer edge of the flange angles.
bearing on the outstanding legs of the flange angles, no allowance being
made for the portions of the legs fitted to the fillets of the flange angles.
End stiffeners shall be arranged, and there shall be a sufficient number of
rivets in their connection to the web, to transmit the entire end reaction
They shall not be crimped.
to the bearings.
3. 6. 80. Transverse
Intermediate
Stiffeners.
= the
t = the
s = the
9000
vr
in which
DESIGN
loading and shall
183
Such stiffeners
web.
The gage line of the longitudinal stiffener shall be % D from the toe
of the compression flange. The longitudinal stiffener shall be proportioned
so that:
Where
be cut at
3. 6. 84. Masonry
Bearings.
shall be so supported
be above the bridge seat,
on metal pedestals
than 6 inches.
3. 6. 85. Camber.
for long
amount
Trusses
HIGHWAY
184
BRIDGES
Top chords and end posts usually shall be made of two side segments
with one cover plate, and with stay plates and lacing on the open side.
If the shape of the truss permits, compression chords shall be continu
ous. The splice shall be as near the panel point as practicable and, prefer
ably on the side of the panel point where the smaller stress occurs.
3. 6. 88
Bottom Chords.
The length of the truss members shall be such that the camber
equal to or greater than the deflection produced by the dead load.
3. 6. 91. Riveted
will
be
Trusses.
If
Eyebars.
less than
DESIGN
185
Intersecting diagonal bars not far enough apart to clear each other
at all times shall be clamped together at the intersection.
Steel filling rings shall be provided, if needed, to prevent lateral move
ment of eyebars or other members connected on the pin.
3. 6. 95. Diaphragms.
97. Masonry
shall
% inch thick.
Bearings.
be so supported on metal
be above the bridge seat,
plates or pedestals
preferably not less
inches.
3. 6. 98. Type.
Viaducts
trusses supported
and free spans.
and
Batter.
be designed
to resist
bending.
3. 6. 102. Bracing.
The bottom struts of viaduct towers shall be strong enough to slide the
movable shoes with the structure unloaded, the coefficient of friction being
Provision for expansion of the tower bracing shall be
assumed as 0.25.
made in the column bearings.
HIGHWAY BRIDGES
186
preferably shall
be
uniform.
and Bracing.
Girders of tower spans shall be fastened at each end of the tops of
the columns or to the cross girders. Preferably, there shall be a line of
girders resting directly over the columns. One end of the girders between
towers shall be riveted to the support, and there shall be an effective expan
sion bearing at the other end. No bracing or sway frame shall be common
to abutting spans.
If girders are not supported directly on the column, provision shall be
made for the transmission of the longitudinal forces to the tower bracing.
3. 6. 106. Sole and Masonry Plates.
Sole plates, masonry
inch thick.
plates,
shall
be not less
than %
For computations
For computations
of deflection
of strength
15
12
10
n=|r
Ec
\
j
>
>
DESIGN
181
(a)
Rectangular
Notations.
Beams.
area of
concrete in beam =
bd
=
z
depth from compression surface of beam to resultant of compressive
stresses.
(b)
T-Beams.
b = width of flange,
b' = width of stem.
t= thickness of flange.
( c)
bd
f ' compressive
A'
=(
r
HIGHWAY BRIDGES
188
stress in steel.
d' = depth from compression surface of beam to center of compression
reinforcement.
z = depth from compression surface of beam to resultant of compressive
stresses.
(d)
(a) Flexure of
V2pn + (pn)2
- pn.
3-1-3
Compressive unit stress in extreme fiber of concrete
.
2M
2pf8
jkbd2
IC =7
M.
Asjd^pjbd2'
V=V2
fcUfc
A"
computations,
the following
assumptions may be
VsUd
6M
,
fc=bd2
(See figure 8)
Jt>,
DESIGN
189
|/2n(p+p'jj-')+n2(p+p')2-n(p+p').
Kk3d+2p'nd'(k-^).
k*+2p'n(k-j)
Arm of resisting couple,
jd = d z.
Compressive unit stress in extreme fiber of concrete.
6M
K)]
''"C*-^k-f)
Tensile stress in longitudinal
reinforcement,
fs
'pjbd^-
reinforcement,
f'.-nf.
^k~H-^.
Concrete T-Beams: (See figure 9)
Computations of flexure in reinforced concrete T-beams shall be based on th
following formulas:
'
2ndAi+bt '
2nAs+2bt
<.;
/3kd-2t\t
z-^2kd-t
h'
,;
U
nU-kj
8f,
\,
Mkd
bt(kd-}^t)jd
reinforcement,
M
Asjd
beams
may be used).
HIGHWAY BRIDGES
190
The following formulas take into account the compression in the stem :
they are recommended where the flange is small compared with the stem:
Position of neutral axis,
/2ndA.+(b-b')t*
xa-y
, ^
+\
nA.+(b-b')t
nA. + (b-b')t'V
b'
b'
(kdt2
- %t)b+[(kd-t)(t+M(kd-t))]b>
t(2kd-t)b+(kd-t)2b'
concrete
2Mkd
[(2kd
-t)bt+(kd -t)*b'] jd
Aljd
(c)
be calcu
V
bjd
Stress
fT
V's
- Avjd
so as to reinforce
shall be designed
fv
sin a
V
jdZo
DESIGN
FIGURE
191
HIGHWAY BRIDGES
192
(d)
Columns
The safe load for short and long columns shall he determined
to formulas given in article 3. 4. 11.
(e) Spiral
according
Columns.
shall he determined
according
to
3. 7. 4. Span Lengths.
from the section where the combined depth of the slab and fillet is at least
one-half times the thickness of slab. Maximum negative moments
are to be considered as existing at the ends of the span, as above defined.
No portion of the fillet shall be considered as adding to the effective depth
of the slab.
one and
3. 7. 5. Expansion.
changes.
by means of
3. 7. 6. T-Beams.
(a)
Effective
Flange Width.
In
beam and slab construction, effective and adequate bond and shear
resistance shall be provided at the junction of the beam and slab. The slab
may then be considered an integral part of the beam, but its assumed
effective width as a T-beam flange shall not exceed the following:
(1) One-fourth of the span length of the beam.
(2) The distance center to center of beams.
(3) Twelve times the least thickness of the slab plus the width of the
girder stem.
For beams having a flange on one side only, the effective overhanging
flange width shall not exceed one-twelfth of the span length of the beam,
nor six times the thickness of the slab, nor one-half the clear distance to
the next beam.
(b)
Shear.
the shear
DESIGN
(c)
Isolated
193
Beams.
( d)
Diaphragms.
For
shall
3. 7. 7. Reinforcement.
(a)
Spacing.
(b)
Covering.
(c) Splicing.
Tensile reinforcement shall not be spliced at points of maximum stress.
When reinforcement is spliced, the spliced bars shall lap sufficiently to
develop the full strength in bond.
(d) Allowable
Hooks.
HIGHWAY BRIDGES
194
quirements under which normal working stresses for bond or shear are
permitted.
(2) Negative tensile reinforcement at the supported end of a restrained
or cantilever beam or member of a rigid frame shall be extended in or
through the supporting member in such a manner as to develop the maximum
tension in the bar with a bond stress not exceeding the normal .working
stress provided in article 3. 4. 12.
the supports of continuous or simple beams, every re
be extended at least 15 diameters but not less than %o
of the span length, beyond the point at which computations indicate it is
no longer needed to resist stress.
(3) Between
(f) Maximum
Sizes.
Reinforcement in Beams.
in girders and beams shall be secured
reinforcement
Compression
against buckling by ties or stirrups adequately anchored in the concrete,
and spaced not more than 16 bar diameters apart.
Where compression rein
forcement is used, its effectiveness in resisting bending may be taken as
twice the value indicated from the calculations assuming a straight-line
relation between stress and strain and the modular relation of stress in steel
to stress in concrete given in article 3. 7. 1. (4). However, in no case should
greater than 16,000 pounds per
a stress in compression
reinforcement
square inch be allowed.
3. 7. 9. Web Reinforcement,
(a)
General.
When the allowable unit shearing stress for concrete is exceeded, web
reinforcement shall be provided by one of the following methods:
(1) Longitudinal bars bent up in series or in a single plane.
(2) Vertical stirrups.
(3) Combination of bent-up bars and vertical stirrups.
When any of the above methods of reinforcement are used, the concrete
may be assumed to carry external vertical shear not to exceed 60 pounds per
square inch for bars not anchored nor 90 pounds per square inch for bars
the remainder
of the shear being carried by the web
anchored,
reinforcement.
be
DESIGN
(b) Bent-up
195
Bars.
( c)
Vertical Stirrups.
(d)
Anchorage.
(1) The stress in a stirrup or other web reinforcement shall not exceed
the capacity of its anchorage in the upper or lower one-half of the effective
depth of the beam.
(2) Web reinforcement which is provided by bending into an inclined
position one or more bars of the main tensile reinforcement where not
required for resistance to positive or negative bending, may be considered
or
completely anchored by continuity with the main tensile reinforcement,
by embedment of the requisite length in the upper or lower half of the beam,
provided at least one-half of such embedment is as close to the upper or
lower surface of the beam as the requirements of fire and rust protection
allow.
A hook placed close to the upper or lower surface of the beam may
be substituted for a portion of such embedment.
(3) Stirrups shall be anchored at both ends by one of the following
methods, or by a combination thereof:
as by welding, to the main longitudinal rein
forcement.
(b) Bending around and closely in contact with a bar of the longi
tudinal reinforcement, in the form of a U-stirrup or hook.
(c) A hook placed as close to the upper or lower surface of the beam
In esti
as the requirements of fire and rust protection will allow.
mating the capacity of this anchorage the stress developed by bond
between midheight of the beam and the center of bending of the
hook may be added to the capacity of the hook.
(d) An adequate length of embedment in the upper or lower one-half
of the effective depth of the beam, whether straight or bent.
Anchorage of this type alone should not be relied on for stirrups in
cases where the shearing stress in the web exceeds that recom
mended for beams without end anchorage of the reinforcement.
(See article 3.4. 12.)
3. 7. 10. Columns,
fa)
General.
length
HIGHWAY BRIDGES
196
to their least dimension shall not exceed 3. The minimum dimension of any
column shall be 15 inches.
For the design of short and long columns see article 3. 4. 11.
(b)
forcement.
( c) Spiral
Columns.
(d) Flexure
(1)
General.
DESIGN
197
Mi = component
of moment parallel to
axis.
axis.
Xo = coordinate distance from center of gravity of the cracked section
parallel to the X axis, in inches.
Y0 = coordinate distance from center of gravity parallel to Y axis, in inches.
Ii=the amount of inertia of "A" along the X axis about the centroidal
axis Y, in inches4.
Iy=the moment of inertia along the axis Y, in inches.4
Ixy= product of inertia of "A" about the axes X and Y through the
centroid.
In solving
either Xo or Yq.
Formulas
it
to assume
is necessary
a value
for
for Stresses
With the position and the direction of the neutral axis determined, the
unit stress in the concrete shall be computed with the formula,
maximum
, Mjv
, Myv
f = T^.in or f =^-Xd
ly
Ix.
, . ,
in which
axis.
Note:
The above formulas are based on a study by Professor Hardy Cross on
"Column Analogy."* For the procedure and methods employed in the appli
cation of the formulas reference is made to an article by William G. S.
Saville.t "Analyzing Non-Homogeneous Sections Subjected to Bending and
Direct Stress."
(3) Columns in Earth Fills.
Columns placed in earth fills, as in the case of "pedestals" or "buried"
abutments, shall be designed to withstand the earth pressure from the rear,
disregarding the effect of the fill in front.
3. 7. 11. Concrete Arches.
( a)
Arch rings shall be selected as to shape in such manner that the axis
of the ring shall conform, as nearly as practicable, to either the equilibrium
polygon for full dead load or to the equilibrium polygon for full dead plus
one-half live load over the full span, whichever produces the smallest bend
ing stresses under combined loads.
* Engineering
14, 1930.
Experiment
Station,
University
10, March
1940.
of
Illinois,
Bulletin
No.
215,
October
HIGHWAY BRIDGES
198
(b) Spandrel
Walls.
When the spandrel walls of filled spandrel arches exceed 8 feet in height
above the extrados they shall be designed as vertical slabs supported by
transverse diaphragm walls or deep counterforts. Vertical cantilever walls
over 8 feet in height, or counterforts having a back slope of less than 45
degrees with the vertical, shall not be used, on account of the excessive
and indeterminate stresses set up in the arch ring by torsion.
(d) Reinforcement.
Arch ribs in reinforced concrete construction shall be reinforced with
a complete double line of longitudinal reinforcement consisting of an intradosal system and an extradosal system connected by a series of stirrups
or tie-rods.
For barrel arches, a system of transverse reinforcement, thoroughly
anchored to the longitudinal reinforcement,
shall be used in both intrados
and extrados.
The transverse reinforcement shall be proportioned to resist
the bending stresses due to any overturning action of the spandrel wall.
For rib arches, hoops or tie bars shall be used in connection with the
longitudinal rib reinforcement, as in the case of reinforced concrete columns.
(e) Waterproofing.
Preferably, the top of the arch ring and the interior faces of the
spandrel walls of all filled spandrel arches shall be waterproofed with a
membrane waterproofing constructed in accordance with the requirements
specified in division II.
(f)
SECTION 8Timber
Structures
3. 8. 1. Bolts.
DESIGN
199
Washers.
A washer shall
A standard circular
washer
shall
be used under
screws.
3. 8. 3. Hardware
for
Seacoast Structures.
be
galvanized
or
plated.
3. 8. 4. Columns
and Posts.
length
greater than
50 times
its
least dimension.
spaced columns
shall
be
determined
as provided
(a) Pile
Bents.
Pile bents generally shall not exceed 40 feet in height. Pile bents over
10 feet high shall be sway-braced transversely with diagonal braces on each
In general,
side of the bent, and shall be adequately braced longitudinally.
pile bents shall contain not less than four piles each and the outside piles,
The piles shall be designed for safe bearing
preferably, shall be battered.
and for column action.
(b) Framed
Bents.
(c) Sills
Mud sills, and all sills which are to be located in close proximity to the
When
ground surface, preferably, shall be given a preservative treatment.
possible, sills shall be located clear of all earth so that there may be a free
circulation of air around them. Sills shall be fastened to mud sills or piles
with drift bolts of not less than %-inch diameter and extending into the
Sills shall be fastened to pedestals with
mud sills or piles at least 6 inches.
9
HIGHWAY
200
BRIDGES
dowels of not less than 94 -inch diameter, set in the pedestals and extending
into the sills at least 6 inches.
Posts shall be fastened to sills by dowels of not less than %-inch
diameter, extending at least 6 inches into the posts and sills, or by drift
bolts of not less than %-inch diameter driven diagonally through the base
of the posts and extending at least 9 inches into the sill. Posts shall be
fastened to pedestals with dowels of not less than %-inch diameter and
extending into the posts at least 6 inches.
(d)
Caps.
be not less
(e) Bracing.
Single-story bracing shall not exceed 20 feet in height. The minimum
size of transverse sway braces shall be 3 by 8 inches. All bracing shall be
bolted through the piles, posts or caps at the ends; at intermediate inter
In all cases, spikes shall be provided
sections it may be bolted or spiked.
in addition to bolts. The bolts used shall be of not less than %-inch diam
eter.
(f)
Splices.
DESIGN
201
(b) Floor
Beams.
(c)
Hangers.
(d)
Eyebars
and Counters.
The requirements
(e) Bracing.
Timber trusses shall be provided with a rigid system of laterals in the
plane of the loaded chord. When the details will permit, this lateral bracing
shall be securely fastened to all longitudinal stringers. Lateral bracing,
preferably rigid, in the plane of the unloaded chord, and rigid portal and
sway-bracing shall be provided in all trusses having sufficient headroom.
Outrigger brackets connected to extensions of the floor beams shall be used
for bracing through trusses having headroom insufficient for a top lateral
system.
(f)
Camber.
(a)
Stringers.
Stringers shall be of sufficient length to take bearing over the full width
of caps or floor beams, except outside stringers which may have butt joints.
Preferably, they shall be of two panel lengths placed with staggered joints.
The lapped ends of untreated stringers shall be separated at least % inch
for air circulation. Stringers shall be secured to caps or floor beams.
( b) Bridging.
shall
The bridging
When timber floors are supported by steel joists, the joists shall be
provided with nailing strips which shall be bolted either to the top flanges
or the webs.
HIGHWAY
202
BRIDGES
When nailing strips are bolted to the flanges, they shall be used on all
joists. They shall be not less than 4 inches deep and shall be wider than
the supporting flange.
They shall be secured with %-inch bolts through
the flanges, spaced not more than 4 feet apart and not more than 18 inches
from the ends of the strips.
Nailing strips bolted to the webs shall be not less than 4 inches thick
and shall be fastened with bolts spaced not farther apart than 5 feet. They
shall be held clear of the flanges by blocks between the web and strip, and
bolted through the web with %-inch bolts spaced not more than 4 feet apart
and not more than 18 inches from the ends of the strips.
(&) Flooring.
Roadway floor plank shall have a nominal thickness of not less than 3
inches. Sidewalk floor plank shall have a nominal thickness of not less than
2 inches.
The minimum
be 2 by 4 inches.
(e) Retaining
Pieces.
Retaining pieces, where required, shall be not less than 6 inches in width.
general, they shall be secured in place by %-inch bolts at 3-foot intervals
and spiked at 1-foot intervals.
In
(f)
Wheel Guards.
Wheel guards having a cross section of not less than 4 by 6 inches shall
be provided on each side of the roadway.
The guard timbers shall be in
lengths of not less than 12 feet. They shall be secured with %-inch bolts
at the ends and at intermediate points not more than 4 feet apart.
In strip floors or cambered floors, not provided with retaining pieces,
the wheel guards shall be placed directly on the flooring with scupper holes
at suitable intervals. In other floors the wheel guards shall be supported
by scupper blocks not less than 4 inches thick and 1 foot long, held in place
by spikes and a bolt through the wheel guard and flooring, and spaced not
more than 4 feet center to center.
(g)
Drainage.
Adequate
floors.
provision shall
be made
of timber
(h) Railings.
Wood railings shall consist of not less than 2 horizontal lines of rails.
Rails shall have a cross-section not less than 2 by 6 inches.
Rail posts shall have a cross-section not less than 4 by 6 inches and
shall be spaced not more than 8 feet apart.
Preferably, rails shall be surfaced 4 sides (S4S) and painted.
Fire Stops.
To check the spread of fire lengthwise of the structure, timber floors
or trestles of any considerable length, preferably, shall be provided with
3. 8. 8
fire
stops.
In timber
not
ma
and
fire
DESIGN
203
3. 9. 1. General
SECTION 9 Composite
Beams
Assumptions:
In
as a T-beam
For beams having a flange on one side only, the effective flange width
shall not exceed one-twelfth of the span length of the beam, nor six times
the thickness of the slab, nor one-half the distance center to center of the
next beam.
Composite beam type construction
shall not
be used
3. 9. 3. Stresses.
means
I
in which S = the horizontal shear per linear inch at the junction of the
slab and beam at the point of the beam in question.
V = total shear due to superimposed load after concrete in slab has
set.
be determined
HIGHWAY BRIDGES
204
sistance value of the individual shear device by the shear per linear inch
"S," with a maximum spacing of two feet.
The flange of the composite beam shall not be considered effective in
These
computing the resistance to vertical shear and diagonal tension.
forces shall be assumed to be resisted entirely by the beam or girder web.
3. 9. 5. Deflection.
The requirements relative to live load deflection in article 3. 6. 10 shall
Where the beams are not pro
govern in the design of composite beams.
vided with falsework or support during the placing of the concrete slab,
the deflection due to the slab and other permanent dead loads added before
the slab concrete sets, shall be computed without composite beam action.
3. 9. 6. Shear Devices.
Mechanical means which are used at the junction of beam and slab for
the purpose of furnishing the shear resistance necessary to produce com
of the respective
posite beam action shall conform to the specifications
materials as provided in division 4. The shear devices shall be of such
construction as will permit a thorough compaction of the concrete mass and
will insure entire surfaces of shear devices being in contact with surrounding
concrete.
The nature of the shear devices shall be such as to prevent a vertical
separation of the slab and beams or else additional means shall be provided
for this purpose.
3. 10.
SECTION 10Sectional
1. General.
Plate Pipe
The material for sectional plate pipe shall conform to division IV, and
the construction shall conform to division II. The minimum gage shall be
according to the following tables or as otherwise specified herein.
The pipe
shall be according to table 1, if strutted, or table 2, if unstrutted. Unless
unstrutted pipe is called for on the plans or by special provisions, the
strutted pipe shall be used.
3. 10. 2. Gage of Side and Top Plates.
(For live load not to exceed H20 or H20-S16)
Diameter
60
2
6
11
16
21
26
31
36
41
46
51
56
61
71
to 5. inclusive
to 10, inclusive
to 15, inclusive
to 20, inclusive
to 25, inclusive-.
to SO, inclusive
to 35, inclusive
to 40, inclusive
to 45, Inclusive
to 50, inclusive
to 55, Inclusive
to 60, Inclusive
to 70, inclusive
to 80, Inclusive
10
10
10
10
10
10
10
10
8
8
8
7
5
3
75
10
10
10
10
10
8
8
8
7
7
5
5
3
90
10
10
8
8
8
8
7
7
5
5
3
of Pipe, in Inches
105
120
135
150
165
180
8
8
8
7
7
5
5
5
3
3
8
8
7
5
5
S
3
3
7
7
5
5
3
3
3
7
5
5
3
3
1
1
5
5
3
3
1
1
5
3
3
1
DESIGN
206
Unstrutted
TABLE 2
Height of Cover in Feet
Diameter
60
2
6
11
16
21
26
31
36
41
46
51
56
61
71
to
to
to
to
to
to
to
to
to
to
to
to
to
to
10
10
8
8
8
7
5
5
5
3
3
6
5f inclusive
10, inclusive
15, inclusive
20, inclusive
25, inclusive
80, inclusive
85, inclusive
40, inclusive
45, inclusive
50, inclusive
55, inclusive
60, inclusive
70, inclusive
80, inclusive
of Pipe, in Inches
75
90
105
120
135
150
165
180
10*
10
8
7
5
5
3
8
1
1
1
10*
8
7
5
3
1
1
10*
7*
5
3
1
8*
5
3
1
7*
3
1
5*
3*
5*
1*
3*
1
1
* Gage shown with (*) to be used only when there is to be no live load over pipe.
carry live load use strutted pipe as given in table 1.
of
If
the pipe is to
Cover.
The height of cover, measured from finished grade to the top of the
pipe shall be not less than 2 feet.
3. 10. 4. Gage of Bottom Plate*.
For pipes having a lighter gage than one, the bottom plates shall have
the next heavier gage shown in the gage table, unless otherwise provided
The additional metal is
by special provisions or by notes on the plans.
provided to resist abrasion.
3. 10. S. Bolts.
Not less than four bolts shall be used per foot of longitudinal seam.
the culvert is to be placed under greater height of cover than given in
table 1, the bolts shall be increased in number as specified in article 3. 10. 6.
Where ends are skewed, not less than iVie inch hook bolts at 12-inch centers
shall be used to anchor the plates to headwalls.
If
of Pipe
not in Tables.
For sizes of pipe which are between those in the tables, the gage shall
interpolated where possible, otherwise the gage of the next larger size
shall be used.
be
Where multiple lines of pipe are installed, the adjacent sides shall be
at least one-half diameter apart up to 4 feet to permit careful tamping of
the filling material.
3. 10. 9. Strutting.
be done as specified
HIGHWAY
206
SECTION
BRIDGES
3. 11. 1. General.
The material for arches shall conform to division IV, and the construc
tion shall conform to division II. The minimum gage shall be according to
the following table.
3. 11. 2. Gages
Span
I
r
V
V
w
w
ir
13'
14'
15'
16'
17'
18'
19'
20"
22'
for
Plate Arches.
Sectional
Height of Cover
Height of Cover
Height of Cover
t y
0'
7'
10' 2'
3'
4'
5'
6'
tt
9"
If
2'
3'
4'
S'
r r
If
10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
10 M 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 8 10 10 10 10 10 10 10 10
M 10 10 10 10 10 10 10 10 8 10 10 10 10 10 10 10 10 7 8 10 10 10 10 10 10 10
10 10 10 10 10 10 10 10 10
8 10 10 M 10 10 10 8
8
S 10 10 10 10 10 8
8 7
7
7
7
7
8
7
7
7
8
8
7
7
8
7
S
5
7
s
3
3
7
7
8
s
5
3
3
1
1
3
I
1
10 10 10
s
1 s
7 7
7
7
7 7
s
5
7
5
6
7
7
6
.1
1
1
3
3
1
5
3
3
3
3
5
5
3
l
l
1
1
3
1
23'
24'
3. 11.3
7
7
5
Ratio
5
3
3
1
7
7
7
8 10 10 10 10 10 10 10
8 10 10 10 10 10 8
8
7 8 8 10 8 8 7 7
5
5
3
1
7
7
5
3
7
7
5
5
8
7
7
5
8
7
7
7
8
7
5
5
7
5
5
3
3
3
1
5
3
1
5
5
3
3
3
1
1
I
7
5
3
1
s
3
I
7
7
5
8 10 10 10 10 10 10
7 8 8 10 10 8 8
7 7
7 8 8 8
7
8
8
7
3
1
5
3
1
5
3
1
7
5
3
1
7
5
5
3
7
7
5
5
7
7
5
3
3
1
7
5
3
1
5
3
3
1
Ri*e
Span
The designs of the arches given in the table are based on ratios of
rise to span varying from .2 to .5 inclusive except as provided in article
3. 11. 5.
The height of cover, measured from finished grade to the top of the
arch shall be not less than 2 feet of earth alone ; or 18 inches of earth under
a flexible type pavement; or 6 inches of earth under a rigid type pavement.
3. 11. 5. Adjustment
of Table.
In
case the ratio of rise to span is less than .3, in combination with a
height of cover of 3 feet or less, the gage of the plates shall be the next
heavier than required by the table and those for which number one gage
is specified shall not be used.
3. 11. 6. Bolts.
be used per
DESIGN
207
The skew shall not exceed 45. When the skew is more than 15 the
length of the structure shall be such that no portion of the live load will
be carried by the cut portion of the arch end. Where right of way or other
conditions do not permit the required length the cut end shall be supported
by a rigid headwall designed to meet the conditions.
The plates shall be
anchored to the headwall with not less than H/ig-inch hooked bolts at not
over 12-inch centers.
Where mutiple arch spans are used the distance between plates at
skewback shall be not less than
of the longer adjoining span.
3. 11. 8. Substructure
Design.
SECTION 12Rating of
3. 12.
Existing
to specifications
herein
Bridges
1. General.
be
HIGHWAY
208
BRIDGES
The dead load on the structure shall consist of the weight of the struc
ture plus any attachments thereto.
It shall be determined by actual field
The unit weights shall be assumed to be those set forth in
inspection.
article 3. 2. 2.
3. 12. 5. Live Load.
The minimum wind load provision of paragraphs (2) and (3), article
shall not apply in the calculations for operating rating.
3. 2. 14.
Traffic Lanes.
or eccentrically)
DESIGN
209
Plate Columns.
To allow for the reduced strength of batten plate columns, the actual
length of the column shall be increased by the following factor to obtain
the value of L/r to be substituted in the formulae given in article 3. 4. 2
or
3. 12. 9.
Actual
L/r
Up to
40
80
120
160
200
1.3
1.1
1.0
1.0
1.0
2d
4d
6d
lOd
2.0
1.3
1.2
1.1
1.0
2.8
1.7
1.3
1.2
1.1
4.5
2.3
1.8
1.5
1.3
For
columns having a solid plate on one side and batten plates on the other,
the foregoing increase factors shall be reduced 50 per cent.
3. 12. 11. Compression
on Flanges
(a)
Strength
For
of
of Design.
Connections.
(b)
equal to the
Splices.
For
210
HIGHWAY BRIDGES
and
shelf angles
shall
be
considered
effective
in
(c) Pins.
For the
DIVISION
IV
Materials *
SECTION I Cement
4. 1. 1. General.
shall
be
furnished.
4. 2. 1. Quality.
Tests.
When required by the engineer the quality of the mixing water shall be
determined by the Standard Method of Test for Quality of Water to be
Used in Concrete of the A. A. S. H. O. Methods of Sampling and Testing,
Designation: T 26-35.
* Note: Also refer to division 1, Section 6, for "Control of Materials" and to article 1. 6. 2
regarding amendments and revisions to the A. A. S. H. O. and A. S. T. M. Specifications
for Materials and Testing:.
211
HIGHWAY
212
BRIDGES
In sampling; water for testing, care shall be taken that the containers
are clean and that samples are representative.
When comparative tests are made with a water of known satisfactory
quality, any indication of unsoundness, marked change in time of setting, or
a reduction of more than 10 per cent in mortar strength, shall be sufficient
cause for rejection of the water under test.
SECTION 3 Fine Aggregate
4. 3. 1. Fine Aggregate.
All fine aggregate for concrete shall conform to the Specification for
Pine Aggregate for Portland Cement Concrete of the A. A. S. H. 0. Specifi
cations for Highway Materials, Designation: M 6-48. Note: Requirements
for soundess should be stipulated in the special provisions (Refer to A. A.
5. H. O., Designation: M 6-48, 4 (a), (b) and (c)).
4. 3. 2. Sand for Mortar.
Sand for mortar shall conform to the Specifications for Mortar Sand of
for Highway Materials, Designation:
the A. A. S. H. 0. Specifications
M 46-42.
SECTION
Coarse
Aggregates
4. 4. 1. Coarse Aggregates.
Aggregate.
SECTION
5 Reinforcement
4. 5. 1. Bar Reinforcement.
be
MATERIALS
213
A 305-47T).
Wire shall conform to the Specification for Cold-Drawn Steel Wire for
Reinforcement,
of the A. A. S. H. O. Specifications for Highway
Materials, Designation: M 32-42 (A. S. T. M. Designation: A 82-34).
Wire mesh, when used as reinforcement in concrete shall conform
to the Specification
for Welded Steel Wire Fabric for Concrete Reinforce
ment of the A. A. S. H. 0. Specifications
for Highway Materials,
Designation: M 55-37 (A. S. T. M. Desigination : A 185-37). The type of
mesh shall be approved by the engineer.
Concrete
to
the requirements
SECTION
6 Structural,
Eyebar
4. 6. 1. General.
to the following specifications,
Steel shall be furnished according
supplemented by the additional requirements of articles 4. 6. 9. to 4. 6. 14.,
inclusive.
Unless otherwise specified, structural carbon steel (4.6.2) and
structural rivet steel (4. 6. 6) shall be furnished.
4. 6. 2. Structural Carbon Steel and Eye Bar Steel.
Structural carbon steel shall conform to the Specification for Steel for
Bridges and Buildings of the A. S. T. M., Designation: A 7-46.
for Steel for
Steel for eye bars shall conform to the Specifications
Bridges and Buildings of the A. S. T. M. Designation: A 7-39.
4. 6. 3. Structural Silicon Steel.
for Struc
for Low-
HIGHWAY
214
BRIDGES
for Structural
Full
not less
Size Tests.
When tests of full-sized eyebars are required, the number and size of
the bars to be tested shall be designated by the engineer before the mill
order is placed.
The number shall not exceed 5 per cent of the whole
number of bars ordered, with a minimum of two bars on small orders.
4. 6. 11
Selection
of
Test Bars.
Test bars shall be of the same section as the bars to be used in the
structure and of the same length if within the capacity of the testing
machine.
They shall be selected by the inspector from the finished bars,
Test bars representing bars too long for the
preferably after annealing.
testing machine shall be selected from the full-length bar material after
the heads on one end have been formed and shall have the second head
formed upon them after being cut to the greatest length which can be
tested.
4. 6. 12. Failure to Meet Requirements.
If
MATERIALS
4. 6. 14. Payments
for Full-Size
215
Tests.
SECTION 7Wrought
the
the
by
the
Iron
4. 7. 1. Wrought-Iron Plates.
Wrought-Iron
Shapes
and
for Wrought-
Bars.
for
for Carbon-Steel
Steel Forgings shall conform to the Specifications
Forgings for General Industrial Use of the A. S. T. M. Designation:
A 235-46. Class C 1 forgings shall be furnished unless otherwise specified.
Steel Castings.
Alloy-Steel
for mild to
to the Specification
application of the
general
Grade 65-35 shall be furnished
for
Castings.
Iron
Castings.
Gray iron castings shall conform to the specification for Gray Iron
Class No. 30 shall be
Castings of the A. S. T. M. Designation: A 48-46.
furnished unless otherwise specified.
HIGHWAY BRIDGES
216
and perfect.
4. 10. 3. Cleaning.
Castings.
12 Bronze
or Copper-Alloy
Bearing
and Expansion
Plates
4. 12. 2. Rolled
SECTION 13 Steel
Piles
MATERIALS
217
Composition
to the following
requirements
as to chemical
A minimum
permitted
to the following
minimum,
requirements
as to physical
inches, minimum,
per cent
70,000
1,400,000
tensile
strength
for piling
Requirements.
Floors
Steel.
All steel shall conform to the Specification for Steel for Bridges and
Unless the material
Buildings of the A. S. T. M. Designation: A 7-46.
is galvanized, it shall have a copper content of 0.2 per cent.
4.
I5.
2. Protective
Treatment
(Shop Coat).
HIGHWAY BRIDGES
218
4.
3. Concrete.
I5.
All
SECTION 16 Paint
Paint for Timber Structures
4. 16.
Structures.
If
Composition.
Maximum
per cent
Pigment
oil)
Water
Coarse particles and "skins" (total residue re
tained on No. 325 sieve based on pigment) . .
Minimum
per cent
32
28
72
0.5
68
1.5
9.0 lbs.
(2) Pigment.
The pigment in both semipaste and ready-mixed paints shall consist
of carbon, lead oxide, insoluble mineral material, and, at the option of the
manufacturer, oxide of iron. The pigment shall show on analysis not less
than 20 per cent of carbon and not less than 5 per cent of lead oxide calcu
lated as PbaQj.
(Since oxide of lead may be dissolved by the oil in paint,
in all cases when the amount of lead in the pigment calculated as Pb304
is found to be less than 5 per cent of the pigment, lead should be determined
in the vehicle and the total lead in the paint computed to percentage of
The total of the lead oxide, iron oxide, insoluble mineral material,
pigment.)
and loss on ignition shall be not less than 90 per cent.
(3) Vehicle.
The liquid in semipaste paint shall be entirely linseed oil; in readymixed paint it shall contain not less than 80 per cent of linseed oil, the
balance to be combined drier and thinner. The thinner shall be turpentine,
volatile mineral spirits, or a mixture thereof.
MATERIALS
219
Ready-Mixed Paint.
Unless otherwise authorized by the engineer the paint shall be "readymixed" (factory-mixed).
Ready-mixed paint shall be well-ground, shall not settle badly or cake
in the container, shall be readily broken up with a paddle to a smooth
uniform paint of good brushing consistency, and shall dry within 18 houre
The color anu
to a full oil gloss, without streaking, running, or sagging.
hiding power when specified shall be equal to those of a sample mutually
(4)
of Analysis.
in accordance with methods given in Federal
Nos. TT-P-141a and TT-P-27.
Methods
Paint shall
Specifications
be analyzed
(Prime Coat).
The shop or prime coat of paint for metal shall be a red lead paint
and shall conform to the Specification for Red Lead (Dry and Paste-in-Oil)
and Paint Made Therefrom, Designation: M 71-42 or to the Specification
for Red Lead Ready-Mixed Paint, Designation: M 72-48 of the A. A. S. H. O.
Specifications
for Highway Materials. Note: If a mixture of raw and
boiled linseed oil is desired, the percentages of each kind shall be stipulated
in the special provisions. Refer to footnote of A. A. S. H. 0., Designation:
M 71-42, article 5 (a).
The paint, preferably, shall be factory mixed. As an alternative the
pigment shall be furnished in the form of red lead paste.
Coat.
(a)
Second Field
Coat.
(Finish Coat.)
General.
The paint to be used for the second field coat shall be as required
by the special provisions or as noted on the plans.
It shall conform to
one of the following specification3 :
If
coat
it shall
be
tinted with
HIGHWAY
220
(b)
BRIDGES
Scope
These
for bridges.
1.
specifications
cover
linseed
oil
green
ready-mixed
paint
General Requirements
The paint shall be well-ground, shall not settle badly or cake in
the container, shall be readily broken up with a paddle to a smooth uniform
paint of good brushing consistency, and shall dry to a full-oil gloss with
out streaking, running or sagging when applied to a vertical surface. The
shade and hiding power shall be that which may be specified in the contract.
2.
Pigment
shall consist of graphitic carbon, chrome green,
red lead and insoluble siliceous mineral matter.
The chrome green shall
be a mixture of prussian blue and chrome yellow.
The pigment shall show
on analysis not more than 50 per cent siliceous pigment and not less than
10 per cent graphitic carbon.
The red lead calculated as PbsCU shall not
be less than 20 per cent by weight of the pigment.
Since oxide of lead
may be dissolved by the oil in the paint, in all cases when the amount of
lead in the pigment, calculated as PbsCt, is found to be less than 20 per
cent of the pigment, lead shall be determined in the vehicle and the total
lead (as PbsCU) in the paint computed to percentage of pigment.
The lead
to be calculated as PbsC^ shall not include the lead in the lead chromate.
(b) The materials used in the preparation of the pigment shall conform
to the requirements given in the following:
3.
Graphite.
1. The material required shall contain at least 82 per cent of
graphitic carbon and shall be free from grit, dirt, or any other
deleterious
substance.
General Requirements.
2. The general
paragraph.
requirements'
shall
be
as stated
in the following
Detail Requirements.
(a) Amorphous graphite shall be ground to such fineness that
100 per cent will pass through a No. 20 bolting cloth.
(b) The graphite shall not lose more than 3 per cent in weight
when tested for ignition, as required in paragraph 4 (c).
3.
MATERIALS
221
before submitting to the Bunsen flame and after being heated and
cooled, shall be taken as ignition loss referred to in paragraph 3 (b).
A. A. S. H. O. Designation: M 130-42
Chrome green
A. A. S. H. O. Designation: M 71-42
Red lead
Vehicle
(a) The liquid or vehicle in the paint shall contain not less than
80 per cent of raw linseed oil and the balance to be combined thinner and
dryer. The thinner shall be turpentine, volatile mineral spirits or a
mixture thereof.
(If desired the raw linseed oil may be wholly or partially replaced
with boiled oil. The desired percentage shall be stated in the contract.)
(b) The materials used in the preparation of the vehicle shall
conform to the requirements given in the following specifications:
4.
A. A. S. H. 0. Designation : M 125-42
S. H. O. Designation: M 126-42
A. A. S. H. O. Designation: M 127-42
A. A. S. H. O. Designation : M 128-42
Federal Specification TT-D 651a
A. A.
Boiled
Composition
The paint shall conform to the following requirements:
5.
Minimum
Maximum
per cent
Pigment
Liquid (containing at
least
oil)
Water
Coarse particles and "skins" (total residue re
tained on No. 325 sieve)
Drying
per cent
45
40
60
0.5
55
1.5
Time
6. When applied in a normal brushing coat the paint shall dry hard
and tough in not more than 24 hours, under normal conditions of temper
ature and humidity.
Weight
7.
77
F.
11
pounds.
the .contract.
Methods of Analysis
Paint shall be analyzed in accordance with the methods given in
Federal Specification No. TT-P-141a and TT-P-27.
9.
bridges.
specifications
cover linseed
oil black
ready-mixed
paint for
HIGHWAY BRIDGES
222
General Requirements
2. The paint shall be well-ground, shall not settle badly or cake in
the container, shall be readily broken up with a paddle to a smooth uniform
paint of good brushing consistency, and shall dry to a full oil gloss with
The
out streaking, running or sagging when applied to a vertical surface.
covering or hiding power shall be that which may be specified in the contract.
Pigment
3. (a) The pigment shall consist of gaphitic carbon, red lead, iron
The pigment shall show on
oxide and insoluble siliceous mineral matter.
analysis not less than 35 per cent carbon and 20 per cent lead oxide,
calculated as Pb304.
Since some oxide of lead may be dissolved by the oil
in the paint, in all cases when the amount of lead in the pigment, calculated
as PbsO-i, is found to be less than 20 per cent of the pigment, lead shall
be determined in the vehicle and the total lead (as PbsGj) in the paint
computed to percentage of pigment.
The total of the lead oxide, iron
oxide, insoluble mineral matter and loss on ignition shall not be less than
90 per cent.
in the preparation of
given in the following:
conform
to the requirements
the
pigment
shall
Graphite.
1. The material required
graphitic carbon and shall
deleterious
be
substance.
General
2. The general
paragraph.
Requirements.
requirements
shall
be
as stated
in the following
Detail Requirements.
(a) Amorphous graphite shall be ground to such fineness that
will pass through a No. 20 bolting cloth.
(b) The graphite shall not lose more than 3 per cent in weight
when tested for ignition, as required in paragraph 4 (c).
S.
Method
h.
obtained
(a)
Samples
for inspection
shall
be
(b)
as required
Red lead
Iron oxide
in paragraph
A. A. S. H. O. Designation: M
A. A. S. H. O. Designation : M
71-42
129-42
MATERIALS
223
Vehicle
(If desired, the raw linseed oil may be replaced with boiled oil to
the extent of 50 per cent of the total oil content.
The desired percentage
shall be stated in the contract.)
(b) The materials used in the preparation of the vehicle
conform to the requirements given in the following specifications :
linseed
Turpentine
Mineral spirits
Drier
shall
A. A.
S. H. 0. Designation : M 125-42
A. A. S. H. 0. Designation : M 126-42
A. A. S. H. 0. Designation : M 127-42
A. A. S. H. O. Designation : M 128-42
Federal Specification TT-D 651a
oil
Composition
5.
oil)
Water
Coarse particles and "skins" (total residue re
tained on No. 325 sieve)
Drying
Minimum
per cent
40
35
65
0.5
60
1.6
Time
6. When
not more
humidity.
Weight
7.
77
Packing
F. shall not
and Marking
Methods of Analysis
Paint shall be analyzed in accordance with the methods given in
Federal Specifications Nos. TT-P-141a and TT-P-27.
9.
SECTION
17 Welding
HIGHWAY BRIDGES
224
1. Sheet
Copper.
4.18.3
Sheet Zinc
II
of the
Sheet zinc shall conform to the requirements
for Type
for Rolled Zinc of the A. A. S. H. 0. Specifications for
Specifications
Highway Materials, Designation: M 113-39 (A. S. T. M. Designation:
B 69-39).
SECTION 19Sectional
4. 19. 1. General.
Plates shall
be
Composition
Chemical
Tolerances
Elements
Pure
Iron
Carbon, maximum %
Manganese, maximum %
Phosphorus, maximum %
Silicon, maximum %
Copper, minimum
Molybdenum, minimum
Sum of first 5 elements,
maximum %
Sum of first 6 elements,
maximum %
.015
.040
Copper
Bearing
Pure
Iron
Copper
Molyb
Copper
Iron
denum
Iron
Copper
Steel
.bis
.bis
.bis
.040
.050
.20
.20
.40
.05
.20
.10
.25
.25
.70
.040
.040
.10
Genuine
Wrought
Iron
.05
.06
.12
.04
.15
.01
.01
.42
.04
.bi
.02
.04
....
NOTE These requirements conform to the Specification for Corrugated Metal Culvert
Pipe of the A. A. S. H. O. Specifications for Highway Materials, Designation: M 36-42.
4. 19. 2. Spelter
Coating.
60 to 120 inches
8
1
Pipe
in diameter
(inclusive),
3 oz.
MATERIALS
225
If
All pipe and arches for which 3-ounce spelter is required shall bt
When gages No. 8 and lighter are used, the
galvanized after fabrication.
metal may be galvanized either before or after fabrication.
4. 19. 4. Sampling.
For testing weight of spelter coating and for chemical analysis of base
metal, when required, a sample approximately 3 inches square, or a sample
of equivalent area, shall be cut from the corner of one plate in each 100
plates of a shipment or fraction thereof.
4.19. S. Chemical
Analysis
and Tests
for
Spelter Coating.
The manufacturer of the base metal shall file with the engineer a
certificate setting forth the name or brand of metal to be furnished and
a typical analysis showing the percentage of carbon, manganese, phos
phorus, sulphur, silicon and copper; also molybdenum, when provided for
under the particular kind of base metal. The certificate shall be sworn to for
the manufacturer by a person having legal authority to bind the company.
The manufacturer shall include in the certificate a guarantee providing
that all metal furnished shall conform to requirements of that particular
base metal as set forth in section 4. 19. 1, shall bear a suitable identification
brand or mark, and shall be replaced without cost to the purchaser when
not in conformity with the specified analysis, gage, or spelter coating, the
cost to be limited to the replacement of sectional plate material only; and
the guarantee shall be so worded as to remain in effect so long as the
manufacturer continues to furnish material.
One brand, and one brand only, shall be approved for each kind of base
metal furnished by each of the actual manufacturers of the base metal.
4. 19. 7. Identification.
HIGHWAY BRIDGES
226
Bolt Heads.
Bolt heads and nuts shall
uniform bearing on the curved
shall be used in lieu thereof.
be
a tolerance
Gage
Theoretical
wt. before
galvanizing
(Lbs./sq. ft.)
Theoretical
wt. after
galvanizing
(Lbs./sq. ft.)
1
S
S
7
8
10
11.25
10.00
8.75
7.50
6.875
5.625
11.438
10.188
8.938
7.688
7.031
5.781
Under
S
3
S
8
5
5
* The term "lot" means all the plates of one gage in the shipment, for gages
heavier, and not less than 6,000 pounds constitutes a "lot" for gages 8 and lighter.
vidual plates shall not underrun the theoretical weights by more than 10 per cent.
7 and
Indi
shall be fur
of the plates
requirements
shipment fail
Ashlar Stone.
Stone for ashlar masonry shall be of the kind specified on the plans or
The stone shall be tough, dense, sound and durable, resist
in the contract.
ant to weathering action, reasonably fine grained, uniform in color, and
MATERIALS
227
SECTION 21 Brick
4. 21. 1. Paving Brick.
for
Masonry.
SECTION
4. 22. 1. Oil
22 Bituminous
Asphalt Fillers.
visions
HIGHWAY BRIDGES
228
Type A.
Asphalt filler for brick wearing surfaces and poured expansion joints
shall conform to the Specification for Oil Asphalt Filler of the A. A. S. H. O.
Specifications for Highway Materials, Designation: M 18-42.
Type B.
The filler shall consist of:
80 to 85 parts of asphalt cement
15 to 20 parts of mineral filler.
Penetration at 77 F
Ductility at 77 F
Inorganic material insoluble in carbon disulphide.
Test Loss on heating at 325, 5 hours
4. 22. 2. Premolded Expansion
40 +
20 cms. +
. 15 to 26% by weight
2%
Joint Fillers.
Non-extruding
shall conform to the Specification
for Preformed Expansion Joint Fillers for Concrete of the A. A. S. H. O.
for Highway Materials, Designation: M 58-42.
Specifications
Bituminous fiber types shall conform to the specification for Preformed
Expansion Joint Filler for Concrete of the A. A. S. H. O. Specifications
for Highway Materials, Designation: M 59-42.
Bituminous type filler shall conform to the Specification for Preformed
Expansion Joint Filler for Concrete of the A. A. S. H. O. Specifications
for Highway Materials, Designation: M 33-42.
and resilient types
Bituminous
4. 22.
Carpets
3. Tar.
The first or prime coat (cold application) for tar carpets, on concrete
wood bridge floors, shall be a homogeneous tar conforming to the Specifi
cations for Highway Materials, Designation : M 52-42, Grade RT-2. Grades
RT-1, RT-3 or RT-4 may be used when designated by the engineer.
The second coat (hot application) shall be Grade RT-8 or RT-9. The
grade to be used, dependent on local conditions, shall be designated by the
engineer.
jr
4. 22. 4. Asphalt.
For the first or prime coat (cold application) for either mixed or
the
penetration asphalt carpets, asphalts Type MC or RC shall be used.
S. H. O.
surfaces are lean or absorbent, asphalt Type MC-0 or MC-1 (A.
the surfaces are well compacted
Designation: M 82-42) shall be used.
or nonabsorbent, asphalt Type RC-0 or RC-1 (A. A. S. H. O. Designation :
M 81-42) shall be used. For heavier prime coats than those obtainable with
If
If
MATERIALS
229
4. 22. 5. Asphalt.
Waterproofing
Materials
Pitch.
The fabric shall conform to the Specification for Woven Cotton Fabrics
Saturated with Bituminous Substances for Use in Waterproofing of the
A. A. S. H. O. Specifications for Highway Materials, Designation: M 117-40.
4. 22. 8. Tar for Absorptive Treatment.
Tar for absorptive treatment shall be a liquid water-gas
conforms to the following requirements:
tar which
1.030 to 1.100
Specific gravity, 25/25 C. (77/77 F.)
Specific viscosity at 40 C. (104 F.) (Engler), not
more than
3.0
Total distillate, per cent by weight, to 300 C. (572
F.), not more than
50.0
Bitumen (soluble in carbon disulphide), not less than,
98.0
per cent
Water, not more than, per cent
3.0
4.22.9
Tar
seal coat shall conform to the Specification for Tar for Use in
for Highway
Road Construction of the A. A. S. H. O. Specifications
Materials, Designation: M 52-42, Grade RTCB-5.
HIGHWAY BRIDGES
230
Joint Fillers.
Filler for use in horizontal joints in waterproofing work shall
4. 22. 10
straight
refined
be a
requirements:
per cent.
otherwise
4. 23. 1. General.
SECTION 23 Asphalt
Paving
Blocks
requirements:
MATERIALS
231
Light
Low
15-25
15-25
15-20
Moderate
Heavy
F.),
Moderate
High
15-25
15-20
10-20
10-15
10-15
5-15
4. 23. 3. Mineral
Aggregate.
4. 23. 4. Inorganic
Dust.
Before being mixed, the asphaltic cement and crushed mineral aggre
In no case shall either be heated to a
gate shall be heated separately.
higher temperature than 350 F. but the temperature of each shall be so
regulated that the temperature
of the mixture as delivered to the press
moulds shall be not less than 225" F.
The mineral aggregate, inorganic dust and asphaltic cement in the
proper proportions shall be thoroughly mixed to produce a homogeneous
mass in which all particles are thoroughly coated with asphaltic cement.
The blocks shall receive a compression in the moulds of not less than
4,000 pounds per square inch, applied on the 3-inch by 12-inch surface.
After pressing, they shall be cooled by passing through water or by other
suitable means.
4. 23. 6. Physical Characteristics.
(a)
HIGHWAY BRIDGES
232
(b)
Composition.
The composition
follows:
Mineral matter:
(c) Absorption
cent.
cent.
cent.
than
Test.
Plank
4. 24. 1. General.
Botanical Name
Thuja occidentalis
Chamaecyparis lawsoniana
Thuja plicata
Castanea dentata
Taxodium distichum
Pseudotsuga taxifolia (Coast)
Pseudotsuga taxifolia
(Inter-mountain type)
Nyssa sylvatica
Tsuga canadensis
Tsuga heterophylla
Larix occidentalis
Quercus borealis and
Quercus borealis maxima
MATERIALS
233
Common Name
Southern Red Oak
Water Oak
Willow Oak
Scarlet Oak
Pin Oak
Shumard Red Oak
Swamp Red Oak
Blackjack Oak
Laurel Oak
Texas Red Oak
Botanical Name
Quercus rubra
Quercus nigra
White Oak
Quercus alba
Quercus montana
Quercus stelata
Quercus macrocarpa
Quercus lyrata
Quercus prinus
Quercus tricolor
Quercus virginiana
Quercus muehlenbergii
Pinus monticola
Pinus contorta
Pinus strobus
Pinus resinosa
Pinus ponderosa
Quercus
Quercus
Quercus
Quercus
Quercus
Quercus
Quercus
Quercus
Chestnut Oak
Post Oak
Bur Oak
Overcup Oak
Swamp Chestnut Oak
Swamp White Oak
Live Oak
Chinquapin Oak
Tamarack
Pinus
Pinus
Pinus
Pinus
Pinus
Pinus
Pinus
phellos
coccinea
palustris
shumardii
rubra pagodaefolia
marilandica
laurifolia
texana
taeda
palustris
rigida
serotina
echinata
caribaea
lambertiana
Sequoia
sempervirens
Picea mariana
Picea rubra
Picea glauca
:
Picea engelmanni
Picea parryana
Picea sitchensis
Larix laricina
shall conform
in all
HIGHWAY BRIDGES
234
Grading of Structural
4. 25. 5. General.
Timber
( a)
Grade of Timber.
The grade to be used shall be as specified in article
modified in the special provisions or as shown on the plans.
(b)
as
shall
be
Grading Rules.
Commercial
In referring
stipulated
or
2. 20. 1
to
commercial
grading
Requirements.
no heartwood requirement
for timber that is to be
pressure treated and the amount of sapwood shall not be limited.
It is generally considered advisable to specify a minimum heartwood
requirement for untreated structural timbers.
Also it is considered advis
If
able to specify sidecut material for stringers, floor beams and caps.
either of these provisions are adopted, definite requirements
shall be
stipulated in the special provisions or on the plans.
There shall
be
4. 25. 7. General.
Timber Piles
Timber piles which will be below water level at all times may be of
any species of wood which will satisfactorily withstand driving.
In untreated piling for use in exposed work, the diameter of the
heartwood at the butt shall be not less than $io of the required diameter
of the piles.
4. 25. 8. Quality.
All piling shall be cut from sound trees and shall be free from any
defects which might impair their strength or durability.
Pieces showing
decay or attack by grubs, worms or borers will not be accepted. Fire-killed
MATERIALS
235
will
shall contain
4. 25. 9. Dimensions.
diameter
Tip diameter
8
7
6
inches
inches
inches
SECTION
4. 26. 1. Preservatives.
26 Timber Preservatives
Timber preservatives
shall conform to the Specification for Timber
Preservatives of the A. A. S. H. O. Specifications for Highway Materials,
Designation: M 133-42.
The type of preservative furnished shall be in accordance with that
specified in the special provisions or as noted on the plans.
HIGHWAY BRIDGES
236
4. 27. 1. General.
for
For
0.18
0.21
0.27
MATERIALS
4.27.5,
Clan-Plate
237
Connectors.
APPENDIX
Loading H 15-44
Table of Maximum Moments, Shears and Reactions
Simple
1...
2...
8...
4...
5...
Moment
6.0 (b)
12.0 (b)
18.0 (b)
24.0 (b)
30.0 (b)
End shear
and end
Span
reaction (a)
24.0 (b)
24.0 (b)
24.0 (b)
24.0 (b)
24.0 (b)
42
44
46
48
50
Moment
274.4 (b)
289.3 (b)
304.3 (b)
319.2 (b)
334.2 (b)
and end
reaction (a)
29.6
30.1
80.5
81.0
81.5
6.
7.
8.
9.
10.
36.0
42.0
48.0
54.0
60.0
(b)
(b)
(b)
(b)
(b)
24.0
24.0
24.0
24.0
24.0
(b)
(b)
(b)
(b)
(b)
52
54
56
58
60
349.1 (b)
364.1 (b)
379.1 (b)
397.6
418.5
82.0
32.5
82.9
88.4
88.9
11.
12.
13.
14.
15.
66.0
72.0
78.0
84.0
90.0
(b)
(b)
(b)
(b)
(b)
24.0
24.0
24.0
24.0
24.4
(b)
(b)
(b)
(b)
(b)
62.
64.
66.
68.
70.
439.9
461.8
484.1
506.9
530.3
34.4
84.9
85.3
85.8
86.3
16
17
18
19
20
96.0
102.0
108.0
114.0
120.0
(b)
(b)
(b)
(b)
(b)
24.8
25.1
25.3
25.6
25.8
(b)
(b)
(b)
(b)
(b)
75.
80.
85.
90.
95.
590.6
654.0
720.4
789.8
862.1
87.5
88.7
89.9
41.1
42.3
21
22
23
24
25
126.0
132.0
138.0
144.0
150.0
(b)
(b)
(b)
(b)
(b)
26.0
26.2
26.3
26.5
26.6
(b)
(b)
(b)
(b)
(b)
100
110
120
130
140
937.5
1,097.3
1,269.0
1,452.8
1,648.5
43.5
45.9
48.3
50.7
58.1
26
27
28
29
30
156.0
162.7
170.1
177.5
185.0
(b)
(b)
(b)
(b)
(b)
26.8
26.9
27.0
27.1
27.2
(b)
(b)
(b)
(b)
(b)
150
160
170
180
190
1,856.3
2,076.0
2,307.8
2,551.5
2.807.3
55.5
57.9
60.3
62.7
65.1
31
32
83
34
35
192.4
199.8
207.3
214.7
222.2
(b)
(b)
(b)
(b)
(b)
27.3 (b)
27.4 (b)
27.5 (b)
27.7
27.S
200
220
240
260
280
3,075.0
3,646.5
4,266.0
4,933.5
5,649.0
67.5
72.3
77.1
81.9
86.7
36
37
38
39
40
229.6
237.1
244.5
252.0
259.5
(b)
(b)
(b)
(b)
(b)
28.1
28.4
28.6
28.9
29.1
300
6,412.5
91.5
placed
at the support.
(a) Concentrated load is considered
stipulated for shear.
(b) Maximum value determined by Standard Truck Loading.
Otherwise the Standard Lane Loading governs.
238
Loads
used
are those
APPENDIX "A"
239
Loading H 20-44
Table of Maximum Moments, Shears and Reactions Simple Spans, One Lane
Spans in feet; moments in thousands of foot-pounds; shears and reac
tions in thousands of pounds.
reduction
for loading of
These values are subject to specification
multiple lanes.
Impact not included.
End shear
End shear
Span
1...
2...
S...
4...
5...
Moment
8.0 (b)
16.0 (b)
24.0 (b)
22.0 (b)
40.0 (b)
and end
reaction (a)
82.0 (b)
32.0 (b)
32.0 (b)
32.0 (b)
82.0 (b)
Span
42
44
46
48
50
Moment
865.9 (b)
385.8 (b)
405.7 (b)
425.6 (b)
445.6 (b)
and end
reaction (a)
39.4
40.1
40.7
41.4
42.0
6.
7.
8.
>.
10.
48.0
56.0
64.0
72.0
80.0
(b)
(b)
(b)
(b)
(b)
32.0
32.0
32.0
32.0
82.0
(b)
(b)
(b)
(b)
(b)
52
54
56
58
60
465.5 (b)
485.5 (b)
505.4 (b)
530.1
558.0
42.6
48.1
4S.9
44.6
45.2
11
12
18
14
15
88.0
96.0
104.0
112.0
120.0
(b)
(b)
(b)
(b)
(b)
32.0
82.0
32.0
32.0
32.5
(b)
(b)
(b)
(b)
(b)
62.
64.
66.
68.
70.
586.5
615.7
645.5
675.9
707.0
45.8
46.5
47.1
47.8
48.4
16
17
18
19
20
128.0
186.0
144.0
152.0
160.0
(b)
(b)
(b)
(b)
(b)
83.0
83.4
33.8
84.1
34.4
(b)
(b)
(b)
(b)
(b)
75
80
85
90
95
787.5
872.0
960.5
1,053.0
1,149.5
50.0
51.6
58.2
54.8
56.4
21
22
28
24
25
168.0
176.0
184.0
192.0
200.0
(b)
(b)
(b)
(b)
(b)
34.7
34.9
35.1
85.3
35.5
(b)
(b)
(b)
r(b)
i
(b)
100
110
120
130
140
1,250.0
1,463.0
1,692.0
1,937.0
2,198.0
58.0
61.2
64.4
67.6
70.8
26
27
28
29
SO
208.0
216.9
226.8
286.7
246.6
(b)
(b)
(b)
(b)
(b)
35.7
35.9
36.0
36.1
36.3
(b)
(b)
(b)
(b)
(b)
150
160
170
180
190
2,475.0
2,768.0
8,077.0
8,402.0
8.743.0
74.0
77.2
80.4
8S.6
86.8
21
82
88
84
85
256.E
266.5
276.4
286.8
296.2
(b)
(b)
(b)
(b)
(b)
86.4 (b)
86.5 (b)
86.6 (b)
86.9
200
220
240
260
280
4,100.0
4,862.0
5,688.0
6,578.0
7,532.0
90.0
96.4
102.8
109.2
115.6
86
87
88
29
40
806.2
816.1
826.1
886.0
846.0
(b)
(b)
(b)
(b)
(b)
87.5
87.8
88.2
88.5
88.8
800.
8,550.0
122.0
87J
...
placed
at the support.
(a) Concentrated load ie considered
stipulated for shear.
Loading.
by
Standard
Truck
(b) Maximum value determined
Otherwise the Standard Lane Loading: governs.
Loads
used
are
those
HIGHWAY BRIDGES
240
Simple
..
2...
S...
4...
5...
Moment
6.0 (b)
12.0 (b)
18.0 (b)
24.0 (b)
80.0 (b)
and end
reaction (a)
24.0 (b)
24.0 (b)
24.0 (b)
24.0 (b)
24.0 (b)
End shear
Span
and end
42
44
46
48
50
Moment
864.0 (b)
8*0.7 (b)
417.4 (b)
444.1 (b)
470.9 (b)
reaction (a)
42.0 (b)
42.5 (b)
48.0 (b)
48.5 (b)
48.9 (b)
52
54
56
58
60
497.7
524.5
551.3
578.1
604.9
(b)
(b)
(b)
(b)
(b)
44.3
44.7
45.0
45.8
45.6
(b)
(b)
(b)
(b)
(b)
(b)
(b)
(b)
(b)
(b)
24.0
24.0
24.0
24.0
24.0
(b)
(b)
(b)
(b)
(b)
24.0
24.0
24.0
24.0
25.6
(b)
(b)
(b)
(b)
(b)
62
64
66
681.8
658.6
685.5
712.8
712.3
739.2
(b)
(b)
(b)
(b)
(b)
45.9
46.1
46.4
46.6
46.8
(b)
(b)
(b)
(b)
(b)
96.0
102.0
108.0
114.0
120.0
(b)
(b)
(b)
(b)
27.0
28.2
29.3
30.8
31.2
(b)
(b)
(b)
(b)
(b)
75
80
85
90
95
806.3
878.7
941.0
1,008.3
1,074.9
(b)
(b)
(b)
(b)
(b)
47.8
47.7
48.1
48.4
48.7
(b)
(b)
(b)
(b)
(b)
21
22
23
24
25
126.0
132.0
188.0
144.5
155.5
(b)
(b)
(b)
(b)
(b)
32.0
82.7
83.4
84.0
34.6
(b)
(b)
(b)
(b)
(b)
100
110
120
130
140
1,148.0
1,277.7
1,412.5
1,547.8
1,682.1
(b)
(b)
(b)
(b)
(b)
49.0 (b)
49.4 (b)
49.8 (b)
50.7
58.1
26
27
28
29
30
166.6
177.8
189.0
200.8
211.6
(b)
(b)
(b)
(b)
(b)
35.1
85.6
36.0
86.6
37.2
(b)
(b)
(b)
(b)
(b)
150
160
170
180
190
1,856.8
2,076.0
2.807.8
2,551.5
2,807.8
65.5
57.9
60.3
62.7
65.1
81
82
83
84
35
228.0
234.4
245.8
257.7
270.9
(b)
(b)
(b)
(b)
(b)
87.7
88.8
88.7
39.2
89.6
(b)
(b)
(b)
(b)
(b)
200
220
240
260
280
8,075.0
8,646.5
4,266.0
4.933.5
5,649.0
7J
72.8
77.1
81.9
86.7
86
284.2
297.5
310.7
324.0
337.4
(b)
(b)
(b)
40.0
40.4
40.7
41.1
41.4
(b)
(b)
(b)
(b)
(b)
800
6,412.5
91.1
10.
86.0
42.0
48.0
54.0
60.0
(b)
(b)
(b)
(b)
11.
12.
13.
14.
15.
66.0
72.0
78.0
84.0
90.0
16
17
18
19
20
6.
7.
8.
9.
87...
88
89
40
<b)
<b)
(b)
(b)
placed
at the support.
Loads used are those
(a) Concentrated load is considered
stipulated for shear.
by Standard Truck Loading:
(b) Maximum value determined
(one H-S truck).
Otherwise the Standard Lane Loading: governs.
APPENDIX "A"
Loading H 20-S
241
16-44
Table of Maximum Moments, Shear* and Reactions Simple Spans, One Lane
Spans in feet; moments in thousands of foot-pounds; shears and reac
tions in thousands of pounds.
These values are subject to specification
reduction
for loading of
multiple lanes.
Impact not included.
Span
Moment
8.0 (b)
16.0 (b)
24.0 (b)
32.0 (b)
40.0 (b)
1...
2...
I...
4...
6...
End shear
and end
reaction (a)'
32.0 (b)
32.0 (b)
32.0 (b)
32.0 (b)
32.0 (b)
End shear
Span
42
44
46
48
50
Moment
485.3 (b)
520.9 (b)
556.5 (b)
592.1 (b)
627.9 (b)
and end
reaction (a)
6.0 (b)
56.7 (b)
57.3 (b)
58.0 (b)
58.5 (b)
48.0
56.0
64.0
72.0
80.0
(b)
(b)
(b)
(b)
(b)
32.0
32.0
32.0
32.0
32.0
(b)
(b)
(b)
(b)
(b)
52
54
56
58
60
668.6
699.3
785.1
770.8
806.5
(b)
(b)
(b)
(b)
(b)
59.1
59.6
60.0
60.4
60.8
(b)
(b)
(b)
(b)
(b)
88.0
96.0
104.0
112.0
120.0
(b)
(b)
(b)
(b)
(b)
32.0
32.0
32.0
32.0
34.1
(b)
(b)
(b)
(b)
(b)
62
64
66
68
70
842.4
878.1
914.0
949.7
985.6
(b)
(b)
(b)
(b)
(b)
61.2
61.5
61.9
62.1
62.4
(b)
(b)
(b)
(b)
(b)
128.0
136.0
144.0
152.0
160.0
(b)
(b)
(b)
(b)
(b)
36.0
87.7
39.1
40.4
41.6
(b)
(b)
(b)
(b)
(b)
75
80
85
90
95
1,075.1
1,164.9
1,254.7
1,344.4
1,433.2
(b)
(b)
(b)
(b)
(b)
68.1
68.6
64.1
64.5
64.9
(b)
(b)
(b)
(b)
(b)
168.0
176.0
184.0
192.7
207.4
(b)
(b)
(b)
(b)
(b)
42.7
43.6
44.5
45.3
46.1
(b)
(b)
(b)
(b)
100
110
120
180
140
1,524.0
1,703.6
1,883.3
2.063.1
2,242.8
(b)
(b)
(b)
(b)
(b)
65.3 (b)
65.9 (b)
66.4 (b)
67.6
70.S
222.2
237.0
252.0
267.0
282.1
(b)
(b)
(b)
(b)
(b)
46.8
47.4
48.0
48.8
49.6
(b)
(b)
(b)
(b)
(b)
150
160
170
180
190
2,475.1
2,768.0
3,077.1
3,402.0
8,743.1
74.0
81
32
38
84
85
297.3
312.5
827.8
348.5
S61.2
(b)
(b)
(b)
(b)
(b)
50.3
51.0
51.6
52.2
52.8
(b)
(b)
(b)
(b)
(b)
200
220
240
260
280
4,100.0
4,862.0
5,688.0
6,578.0
7,582.0
90.0
6.4
102.8
109.2
115.6
36
87
38
39
378.9
896.6
414.3
432.1
449.8
(b)
(b)
(b)
(b)
(b)
53.3
53.8
54.3
64.8
55.2
(b)
(b)
(b)
(b)
(b)
300
8,550.0
122.0
6.
7.
8.
(.
10.
11
12
1S
14
15
16
17
18
19
20
..
21
22
23
24
25
26
27
28
29
30
.40
M>)
77J
80.4
88.6
86.8
placed
( a ) Concentrated load i: considered
at the support.
Loads used are
stipulated for ahear.
by Standard Truck Loading;
(b) Maximum value determined
(one H-S truck).
Otherwise the Standard Lane Loading governs.
those
HIGHWAY BRIDGES
242
APPENDIX "B"
Formulas for Steel Columns*
The permissible average unit
f, =
v1
(.25
B Cosec
(A)
inch inclusive.
lbs. per sq. in. for low-alloy steel, thickness over 1 Yi inch to
inclusive.
t) = factor of safety based on yield point,
= 1.76 for carbon steel.
= 1.80 for silicon steel.
= 1.83 for nickel steel.
= 1.82 for low-alloy steel, thickness % inch and under.
= 1.80 for low-alloy steel, thickness % inch to 114 inch inclusive.
= 1.78 for low-alloy steel, thickness 1H inch to 2 inch inclusive.
c= distance from neutral axis to the extreme fiber in compression.
r= radius of gyration in the plane of bending
=40,000
~\
inch
radians
^lt~
L = 75%
E
=29,000,000
a =
-^a2-2a
When eB and es lie on the same side of the column axis, o is positive;
when on opposite sides, o is negative; i.e.
When +es = +eg, a = +1
When es=0, cc=0
When +es = eg, a = 1
=
eccentricity
of applied load at the end of column having the greater com
eg
puted moment, in inches.
es= eccentricity at opposite end.
:
68
* Refer also to the column formulas given in articles 3.4.2, 3.4.7 and 3.4.8.
** When the radius of gyration perpendicular to the plane of bending is less
than "r", the column shall be investigated for the case of a long column concen
a greater value of -
APPENDIX "B
For values of
L
-
-1\
j
243
rE^14V
the permissible
fs
25 4- e-^\
r2
fy
A
1+.25
When the values of end moments are not computed but considered negli
gible in amount, a shall be assumed equal to +1.
a shall be assumed equal to +1 for a member subject to bending stresses
induced by the components of externally applied loads acting perpendicular to
its axis. For this case the general formula becomes:
(0,=
1+
.25
(eb+d)]
*
Sec^0
^.f&j-h^'
a =0
and 1
244
HIGHWAY BRIDGES
OZ
09
09
001
OZI
001
091
081
002
OZZ
02
Ofr
09
09
001
OZI
0l
091
OBI
003
OZZ
0*Z
9fZ
avmhoih saoama
HIGHWAY BRIDGES
248
APPENDIX C
TRUCK TRAIN AND EQUIVALENT LOADINGS-
1935 SPECIFICATIONS
AMERICAN ASSOCIATION OF STATE HIGHWAY OFFICIALS
o
o
o
o
o
f\J
,20 TON TR
3 0' . I . 14'
14'
30'
14'
H-20-35
ill^TON TRUCK,
30'
30
14'
30'
H-15-35
30'
30'
LOADING
,15TON TRUCK,
TEL.
. .
,llaT0N TRUCK ,
I4'
30'
l4'
()
.. .
30'
LOADING
o
o
o
,7jT0N TRUCK.
14'
12
30'
D_
30'
H-IO-35 LOADING
TRUCK TRAIN LOADING
H-20-35
30'
LOADING
" "M ENT
'
-CONCENTRATED L0Ad{
[ 19,500 FOR SHE):ar
LINEAR FOOT OF LANE
^.UNIFORM LOAD 480-LBS.PER
H-15-35
l^-CONCENTRATED
^UNIFORM
LOAD
LOADING
,000 FOR MOMENT
13/,000 FOR SHEAR
H-IO-35
LOADING
EQUIVALENT LOADING
LANE WIDTH
FEET
FOOT OF LANE
INDEX
Abutment :
Design, general
Distribution of earth pressure
Drainage
General
Pile bents
Reinforcement for temperature
Wing walls
(See also Foundations and Substructures.)
Acceptance :
Pinal payment
No waiver of legal rights
Aggregate:
Bituminous carpet
Coarse, for concrete
Fine, for concrete
Rubble or cyclopean
Sand for mortar
Anchor Bolts and Anchorages 2.10.51, 3.5.2b, 3.6.43,
Angle of Repose (various materials)
Annulment of Contract
Appendixes :
Charts for, Appendix B
reinforced concrete tied
Permissible stresses,
columns, Appendix D
Tables of moments, shear and reactions for H 15,
H 20, H 15-S 12, H 20-S 16 loadings. App'x A
Truck train and equivalent loadings. App x C
for reference use.)
(1935 specifications
Arbitration, Board of
Arches :
Ashlar masonry
Concrete
Class of concrete
Drainage of fill
Expansion joints
Placing concrete
Reinforcement
Shape of ring
Spandrel walls
Surface finish
Waterproofing
General
Centering (see Centering and Falsework).
Drainage
Fill
3.
3.
3.
3.
3.
3.
3.
5.
5.
5.
4.
8.
5.
5.
Page
3
2
3d
3a
5f
3b
3c
163
161
164
163
200
164
164
1. 9. 7
1. 7.12
24
18
2.24.22
4. 4. 1
4. 3. 1
4. 4. 2
4. 3. 2
3. 6.53
3. 4.16
1. 8. 8
117
212
212
212
212
.78, 161, 176, 177
155
21
242, 244
249
238, 239, 240, 241
248
1. 5.12
15
2. 6.15
64
2.
3.
3.
2.
3.
3.
3.
2.
3.
4. 4
7.1 1f
7.11c
4. 9
7. lid
7.11a
7.11b
4.23
7. lie
38
198
198
44
198
197
198
53
198
3.
2.
3.
2.
7.11f
1. 9
7. lie
7. 8
198
27
198
66
2.
2.
2.
2.
6.14
6. 1
6.13
6. 5
64
2.6.8, 2. 6.15
2.6.6, 2 . 6 . 7
62,64
Waterproofing
Rubble masonry
Sectional plate (see Sectional Plate Arches).
Ashlar Masonry :
Arches (see Arches)
Copings
Description
Dowels and cramps
Dressing stone
Laying
Article
61
64
61
62
Article
Laying stone
2.
2.
2.
2.
2.
2.6.2, 4.20.
2.6.2, 2. 6.
Material
Mortar and mixing
9
2 . 6 . 17
Payment conditions
Pointing
Resetting
Size of stone
Surface finish
Asphalt Mat (see Bridge Floors.)
Asphalt Paving Blocks :
Absorption test
Bridge wearing surface (see Bridge Floors).
Composition
General
Manufacture
Materials
Asphaltic cement
Inorganic dust
Mineral
6.10d
6.10b
6.10a
6.10c
6.11
aggregate
Physical characteristics
Asphalt Plank
2.
2.
2.
2.
6.16
6.12
6. 3
6. 4
4.23.
6c
4.23.
4.23.
4.23.
6b
4.23.
4.23.
4.23.
1
5
4
3
4 . 23 . 6
4.24.
2.5.1,2.5.6, 4. 5.
1.4.5, 1. 7 .
1.
3 .
1
1
!.
2.11
1. 1.1
1. 2.10
1 .
4.22.
4.22.
4
3
4.22.
4.22.
1
2
1.
Tar
Material
252
3. 1.14
1. 5.12
1. 1. 1
4.
I.
2 . 20 . 13
3 .
6.72
3 .
8 .
4.21.
4.21.
Article
Brick Masonry:
Construction
Copings, bridge seats, backwalls
Description
Material
Mortar
2. 9.
Page
68
69
68
2. 9. 4
2.9.2,4.21.1,
Payment conditions
Railings (see Railings and Parapets).
Bridge:
Clearances, roadway
Highway loadings (see Loads)
Bridge Floors:
Asphalt plank
Concrete
Class of
Curing
Drainage
Expansion joints
Placing concrete
Placing reinforcement
Surface finish
Laminated or strip, general
Nonskid
Plank-
Details
Design
Drainage
Fire stops
General
Materials
Retaining pieces
Wheel guards
Steel grid
Computed weight
Construction
Arrangement of sections
Concrete filler
Connection to supports
Field assembly
General
Materials
2. 9.
68,227
2. 9.
2
2
5
3. 1. 8
3. 2. 5
122
129
4.24.
232
4.21.
2 .
9 .
2. 4. 4
2. 4.21
3. 1.11
2.4.22, 3. 7. 5
2. 4. 9a, b,
2. 5. 7
2.4.23, 2. 4.31
2.20.18
3. 1.13
2.20.17
3. 8. 7d
3. 8. 7g
3. 8. 8
2.20.17
2.20.17
3. 8. 7e
3. 8. 7f
2.10.67g
2.12.
2.12.
2.12.
2.12.
2.12.
2.12.
Painting
3
9
6
5
1
2
2.12.10
Provision for camber
2.12. 4
Repairing damaged galvanized coatings 2 . 12 . 8
Welding
2.12. 7
3. 3. 5
Design, distribution, moments
Materials
Concrete filler
4.15. 3
Protective treatment
4.15. 2
Steel
4.15. 1
Measurement and payment
2.12.11
Wearing surfaces
3. 2. 2
Allowance for
Asphalt block
2.24.15
General requirement
2.24.19
Laying
Materials
2.24.16
Measurement and payment
2.24.21
Mortar bed
2.24.18
2.24.20
Opening to traffic
2.24.17
Preparation to subfloor
253
68
69
38
52
124
c, d
52,192
4447
59
53,56
103
124
103
202
202
202
103
103
202
202
82
83
84
83
83
83
83
84
83
84
84
143
218
217
217
85
127
116
116
116
117
116
117
116
Article
Bituminous carpet
Aggregate
Asphalt mat surface, construction
Mixed method
Prime coat
Seal coat
Second coat
Penetration method
Prime coat
Second coat
2.24.23,4.22.3,
Materials
Measurement and payment
Opening to traffic
Preparation of subfloor
Concrete subfloor
Wood subfloor
Tar mat surface
Construction
Prime coat
Seal coat
Second coat
Brick-
Asphalt filler
Application
Bedding course, placing
General requirements
2.24.23
117
2.24.26a
2.24.26c
2.24.26b
119
119
119
2.24.27a
2.24.27b
120
120
4.22.
2.24.29
Materials
Measurement and payment
Opening to traffic
Preparation of subfloor
Rolling the brick
Sand cement bed
Surface dressing
Testing the surface
Concrete
Description
Measurement and payment
Broken Stone for Concrete
Bronze Bearing and Expansion Plates :
Bronze sliding expansion bearings
Bronze plates
Copper-alloy plates
General
Material
120
120
2.24.24b
2.24.24a
118
117
2.24.25
118
118
118
118
2.24.25a
2.24.25b
2.24.25c
2.24.
2.24.
2.24.
2.24.4, 4.21.
7
3
8
1
2.24.14
2.24.13
2.24.
2.24.
2.24.
9
6
2.24.12
2.24.10
2.24.
2.24.
4. 4.
1
2
2
3. 6.48
2.11.
2.11.
2.11.
2.11.2, 4.12.
2.11.
2.11.
4
1
113,227
115
115
113
115
114
115
115
113
113
212
177
82
82
82
82,216
82
82
148
3. 4. 9
3. 2.17
3. 5. 4d
Camber :
Diagram required
Steel girders
Steel trusses
Timber trusses
Cantilever Slabs
2.10.13
3. 6.85
3. 6.90
3. 8. 6f
3. 3. 2f
254
115
114
113
114
Buoyancy
Buttresses and Counterforts
stresses
....117,228,228
2.24.28
2.24.11
Laying
Unit
Page
137
165
71
183
184
201
141
Castings
Article
:
Gray iron
Cleaning
Workmanship and finish
Malleable
Steel (see Steel, Castings).
Unit
stresses
(see Stresses,
4.10.
4.10.
4.10.
4.11.
Page
215
216
216
216
1
3
2
1
Unit).
Cement:
Sampling and testing
Types I, II, III, IV and V
2.4.17,
Centering and Falsework
Removal of falsework, forms and housing
Channel of Stream:
Erosion
Openings
Preservation
Claims :
1.7.7,
Contractor's responsibility, damages
Disputed
Cleaning Up
Clearance Diagrams
Cofferdams and Cribs:
Construction
Construction plans
General
Preservation of channel
Protection of concrete
Pumping
Removal
(See also Concrete Cribbing; Timber Cribbing.)
Cold Weather:
Concrete construction
Painting
Commission :
Appointment of arbitration board
Definition
Personal liability
Composite Beams :
Deflection
Effective flange width
General assumptions
Shear
Shear devices
Steel-concrete
Stresses
Timber-concrete
Concrete :
Bearing piles (see Pile Concrete).
Bonding
Cement for
Classes of
Classification and proportioning
Coarse aggregate
Cold weather construction.. . .2. 3. 13c, 2.3. 13g,
Consistency
Construction joints
Bonding
General
Curing
2.3.13g,
Cyclopean or rubble
Depositing under water
Discontinuance of placing
255
4. 1. 2
4. 1. 1
2.10.49
2. 4.19
2. 1.
3. 1.
2. 1.
2 . 1 . 5c
2. 1. 5a
2.1.2
2. 1. 5b
2. 1. 6
2. 1. 5d
2. 4.20
2.14.
51
25
121
25
2
3
2
1. 7.10
1. 5.11
1. 4. 8
Figs. 1,2
2. 1.
211
211
50, 78
1. 5.12
1. 1. 1
1. 7.11
17,
18
14
12
121, 122, 123, 125
26
26
26
25
26
26
26
52
87
15
6
18
3.
3.
3.
3.
3.
3.
3.
3.
9. 5
9. 2
9. 1
9. 4
9. 6
9. 1
9. 3
9. 1
204
203
203
203
204
203
203
203
2.
4.
2.
2.
4.
4.13b
1. 1
4. 4
4. 5
4. 1
49
211
38
2.4.20
2. 4.
2. 4.13b
2. 4.13a
2. 4.21
2 . 4.14
2. 4.12
2. 4. 9a
38-41
212
33,34,52
41
49
49
34,52
49
48
44-46
Arrte
2. 4.22
expansion joints in
Expansion and fixed joints and bearings
Bearing devices
Filled joints
Open joints
Steel joints
Water stops
Exposed to alkali soil or watpr
Exposed to sea water .
Fine
aggregate
Finishing surfaces
Class 1, Ordinary
Class
Class
Class
Class
Class
Floating
Longitudinal floating
Straightedging
Striking off
Transverse floating
General
Forms
Handling ;and placing
Arche
hea..
Culverts
Girders, slabs and columns
General
Measurement and payment
Measuring materials
2. 4. 9d
4. 9b
4. 9c
4. 9a
4.32
2. 4. 7
2.
2.
2.
2.
Mixing
Delivery
General.
Hand mixing
Mixing at site
Partial mixing at central plant
Plant mix
Re tempering
Time of hauling and placing mixed concrete .
Truck mixing
Pneumatic placing
Pneumatically applied mortar
Bond
2. 4. 8h
2.
2.
2.
2.
2.
2.
4.
8a
4.
4.
8d
8e
8i
4. 8g
4. 8b
4.
2 . 4 . 8f
2. 4. 8c
2. 4.10
2. 4. Se
2. 4.31k
2. 4.31h
2. 4.31a
2. 4.31i
2. 4.31d
2. 4.31f
2. 4.31e
2. 4.31b
2. 4.31g
2. 4.31c
2. 4.11
2. 4. 8i
2.2.1,2. 2. 3
2. 4. 2
2. 4.23
curing
Forms
General
Joints
Mixing
. .
4.24
4.25
4.26
4.27
4.28
2. 4.29f
2. 4.29b
2. 4.29c
2. 4.29e
2. 4.29a
2. 4.29d
2. 4.23
2.4.9,2.4.18,2. 4.19
.....
Nozzle position
Nozzle velocity
Proportions
Rebound sand
Water content
Pumping
Re tempering
Sheet piles
Storage of materials
Surface finish
4.22e
4.22b
4.22a
4.22c
4.22d
4.16
2. 4.15
*- 3- 1
2.
2.
2.
2.
2.
2, Rubbed
3, Tooled
4, Sand blasted
5, Wire brushed
6, Floated
Final finishing
2.
2.
2.
2.
2.
2.
256
Article
Sidewalk
2. 4.30
(See also Finishing Surfaces.)
Water for
4. 2. 1
2.3.13,2. 4.20
Weather protection
Weighing equipment
2. 4. 7
Concrete Arches (see Arches Concrete).
Concrete Cribbing:
Construction
2.16. 2
General
2.16. 1
Measurement and payment
2.16. 3
Concrete Culverts Monolithic :
Class of concrete
2. 4. 4
Footings
3 . 5 . 2
Inverts, aprons, curtain walls
3. 5. 2
Placing concrete
2 . 4 . 9b
Surface finish
2. 4.23
Concrete Railings (see Railings and Parapets).
Concrete Reinforcement :
Anchorage
3. 7. 9d
Bar mat
2. 5. 6
Cleaning
2. 5. 7
Design
Sec. 7
Fabrication
2. 5. 4
Formulas
3. 7. 3
Lapping
2. 5. 9
2.5.1,4. 5. 1
Material
Mesh
2. 5. 5
2.5.11,2. 5.12
Measurement and payment
Placing and fastening
2. 5. 7
,
Protection of
2 . 5 . 3
Splices
2. 5. 8
Stirrups
3. 7. 9
Structural shapes
4. 5. 4
Substitutions
2. 5.10
Substructure and retaining wall. .. .3.5.2, 3.5.3,3. 5. 4
(See also Reinforcement, Concrete.)
Concrete Slabs and Girders :
(See also Slabs.)
Camber
2. 4.17
Class of concrete
2. 4. 4
Drainage
3. 1.11
Placing concrete
2 . 4 . 9c
Surface finish
2. 4.23
Waterproofing
Sec. 17
Concrete Structures :
Arches (see Arches Concrete).
Cold weather construction
2. 4.20
Cribbing (see Concrete Cribbing).
Culverts (see Concrete Culverts).
Design
Allowable stresses
Bearing on bridge seats
3. 4.11f
Bond on piles (in seals)
3. 4. lie
Columns
3. 4.11g
Flexure
3. 4.11c
General
3. 4.11b
Shear
3. 4. lid
Standard notations and assumptions. . . 3. 4.11a
Arches
Drainage of fill
3. 7.11f
Expansion joints
3. 7.11c
257
Article
Page
3. 7. lid
Reinforcement
3. 7.11a
Shape of ring
3. 7.11b
Spandrel walls
3. 7. lie
Waterproofing
3. 9. 1
Beams (Composite)
Columns
3. 7.10b
Columns with lateral ties
3. 7.10d
Flexure and direct stress
3. 7.10a
General
3. 7.10c
Spiral columns
3. 4.11g
Stresses, Appendix D
3. 7. 6d
Diaphragms
2.4.22, 3 . 7 . 5
Expansion joints
Formulas
3. 7. 3d
Columns with lateral ties
Flexure of rectangular reinforced con
3. 7. 3a
crete beams and slabs
Flexure of reinforced concrete T-beams 3. 7. 3b
3. 7. 3c
Shear, bond and web reinforcement
3. 7. 3e
Spiral columns
3.4.11b, 3. 7. 1
General assumptions
3. 3. 2
Moments in floor slabs
Reinforcement
3. 7. 7d
Anchorage
3. 7. 8
Compression in beams
3. 7.76b
Covering
3. 7. 7e
Extension
3 . 7 . 7f
Maximum size
3. 7. 7a
Spacing
3. 7. 7c
Splicing
Reinforcement web
3. 7. 9d
Anchorage
3. 7. 9b
Bent-up bars
3. 7. 9c
Vertical stirrups
3.3.2i, 3. 7. 4
Span lengths
3.4.11a, 3. 7. 2
Standard notations
T-Beams
Unit
3.
3.
3.
3.
Diaphragms
Effective flange width
Isolated beams
Shear
stresses
(see Stresses).
7.
7.
7.
7.
6d
6a
6c
6b
198
197
198
198
203
196
196
195
196
150
193
52,192
192
188
189
190
192
149,186
139
193
194
193
193
194
193
193
195
195
195
142,192
148,187
193
192
193
192
3. 7.12
198
4. 4
38
49
2 .
2. 4.13
3. 5. 4g
3. 5. 2
2 . 4.
2. 4.23
3. 7.12
2 .
4. 4
2. 4.18
2. 4. 9c
4.27.
1. 7.12
1. 5. 9
1. 4. 8
137,165
161
44
53
198
38
50
46
.99,152,199,236
18
14
12
Article
Limitation of (operations
1.
1.
8.
2
2 . 10 . 39
1. 8 . 2
1. 9. 1
1.5.5,
1.
1.
1.
1.
8.
8.
8.
5.
1.
8.
1.
1.
1.
1.
6
4
5
4
3. 6
1. 5.12
1. 3. 2
1.
1. 3. 4
1. 8.10
1.4.8,
Final acceptance
Final payment
Included documents
Omitted terms
Prosecution and progress
1.4.3,
Quantity changes
Quantity measurements
Special work
'. . .
Subletting or assignment
Termination
Time extension
Contract Bond, requirement of
Contractor :
Claim for extras
Compensation for delays
1.5.5,1.8.2,
Cooperation of
Definition
May use certain materials
Notice of beginning of work
Responsibility for construction stakes
1.4.5, 1.7.7,
Responsibility for damages
Responsibility for temporary constructions
1.7.7,
Responsibility for work
Sub-contractor, definition
1.7.7,
Termination of responsibility
Working drawings
Copper Alloy Bearing and Expansion Plates :
Materials
Measurement and payment
Placing
Unit
8.
stresses
1.
1.
1.
1.
1.
1.
5.11
3. 5
8. 6
4. 4
8. 7
3. 7
1. 9. 7
1 . 9. 7
1.
1 .
1. 9.
1. 8.
1. 9.
1. 9.
1- 4.
1.
8 .
1
5
2
3
1
2
1
9
1. 8.
1 . 8. 6
1.
3 .
5.11
8.10
2.10.40
1.
1.
1.
it
1.
4.
1
7
2 . 10 . 38
1. 5. 6
1. 7. 9
1. 4. 5
1. 7.10
1. 8.
5.
9
2
4.12.
2.11.
2
6
1.
2.11.
3. 4.
5
6
3 .
5.
4d
1.
1.
1. 4.
Culverts :
Concrete (see Concrete Culverts, Monolithic).
Foundations
Length
Loads on :
Weight of earth
Weight on rigid culverts
Size of waterway
3.2.11,
Curbs, Safety
2.20.19,3.1.9,
Curbs and Wheel Guards
Current, force of
Page
Article
3. 5.
3. 1.
161
122
3. 1. 5
3. 1. 9
3. 8. 7f
3 .
2 .
1. 7.
2.18.
2.18.
2.18.
2.18.
2.18.
4
2
1.5.7, 1. 5.
128
128
122
134,122
....104,122,202
137
D
Damage, responsibility
Dampproofing :
Application
General
Materials
Measurement and payment
Preparation of surface
Dead Load (see Loads Dead Load).
Defective Workmanship
Definition of Terms
Deflection, steel beams and girders
Delivery of Materials
Department, definition
Depressed Roadways
Clearance between walls
Curbs, minimum width
Width between curbs
Design, General Features:
Analysis (Rational Acceptable).
Blast protection
Channel openings
Classes of loadings
Clearances
Culvert, length
Culvert, size
Curbs and safety curbs
Depressed roadways
Drainage, roadway .. .'
Floor
1.4.5,1.7.7,
5
3
1. 1. 1
3. 6.10
2.10.47
1. 1. 1
surfaces
13,14
6-8
168
78
6
126
126
126
3.
3.
3.
3.
3.
3.
3.
3.
3.
1.14
1. 3
2. 5
1. 8
1. 6
1. 5
1. 9
1.17
1.11
1.13
124
121
129
122
122
122
122
126
124
124
1. 4
121
25
124
122
124
125
126
3.
2.
3.
3.
3.
3.
3.
(see Stresses).
97
97
97
100
97
3. 1.17
3. 1.17
3. 1.17
3 .
Unit stresses
Utilities
11,17,18
1.2
1.10
1. 7
1.12
1.16
1.18
3. 1.15
125
Waterway area
3. 1. 1
121
Waterway restricted
3. 1.2
121
Detours, construction and maintenance
1. 4. 5
11
Disqualification of Bidders
1 . 2.10
9
Distribution of Loads (see Loads).
Drainage of Structures 2.6.15,2.7.8,3.1.11,3.2.18,3.
5. 4g ..64,66,124,137
3.7.11f, 3. 8. 7g ....165,198,202
260
Article
Drawings :
Contractor's
Deviation from
Engineer's approval
1.
1.
1.
5.
5.
5.
E
Earth Pressure :
3. 4.16
Angle of repose
3. 2.18
Pressure
Engineer :
1. 9 . 7
Acceptance by
1. 5. 8
Access to work
1.5.1, 1.8.2
Authority of
1. 1. 1
Definition
1. 9. 1
Measurement of quantities
1. 7.11
Personal liability
1. 5. 2
Plans and working drawings
1. 7. 7
Precautions for public safety
1. 1. 1
Resident, definition
1. 5. 6
Stakes for construction uses
1. 8 . 4
Equipment, adequacy of
Erosion Protection:
3. 5. la
Piles
2.15.1, 2.15.11
Riprap
(See also Foundations and Substructures.)
Estimate :
1. 2 . 2
Interpretation of
1. 4. 3
Quantities
Excavation and Fill :
2. 1. 9
Arches, spandrel filled
Backfill-
.
Construction
2.1.8,
Drainage
Materials
Cofferdams and cribs
Construction
Pumping
Removal
Sheet piles
Embankment
Approach
Construction
Measurement and payment
Excavation
Backfill
Classification
Cofferdam and crib protection
Foundation, preparation
Inspection
Measurement and payment
(See also Foundations and Substructures.)
Existing Bridges, rating of :
General
Inventory
Operating
(See also Rating of Existing Bridges.)
1 . 4.. 6,
Existing Structures
Expansion Joints:
Bituminous
2.4.22,
Bridge floor
Bridge railing
2.4.22,
Concrete structures
261
2. 1.
3. 7.
8
1
If
2. 1. 8
2. 1.
2. 1.
2. 1.
5
6
5
Sec. 2
1.10
2. 1.10
2. 1.12
2 .
2. 1.
2 .
1.11
1. 5
1. 4
1. 7
2.
2.
2.
2. 1.12
3.12.
3.12.
3.12.
1
2
3
2 . 10 . 58
4.22.
3. 6.64
2.13.11
3. 7. 5
Article
Extra Work
Eyebars:
2 . 10 . 32,
Annealing and annealing record
3.6.93,3.6.94,
Design
Fabrication
Full size test
2.10.59,
Payment for full size tests
3.8.6,4.6.8,
Physical requirements
Test bars and testing
1. 4. 4
4 . 6.13
3. 8. 6
2.10.31
4. 6. 9
4. 6.14
4. 6.12
4. 6.10
Earth
pressure
Angles of repose
Pressure
Excavation
Footings
Anchorage
Depth
Distribution of pressure
Internal stresses in spread footings
Piles
Sec. 3,
Preparation of foundation
Protection against erosion
Reinforcement
Spread footings
Transfer of stress from verical reinforcement .
Ice breakers
262
2 . 10 .
1.
7 . 4
1. 5.10
3. 8. 8
2.14.10d
2.10.22
2. 1. 1
2. 4.17
3. 5. 1
Sec. 22
2.10.51
3. 5. 2b
3. 4.15
2 . 10 . 51
2. 1.
2. 4. 4
2. 4.13
2.
2.
3.
3.
3.
4. 9
4.23
5. 2a
5. 2c
5. 3d
3. 4.16
3. 2.18
2. 1. 4
3. 5. 2b
3. 5. 2a
3. 5. 2 c
3 . 5 . 2e
3. 5.
2. 1. 4
3. 5. 2
3. 5. 2f
3 . 5 . 2d
. 3 .
5 . 2g
5
3. 5.
Article
Ice pressure
Inspection and approval
Piers (see Piers).
Tubular steel piers (see Tubular Steel Piers).
3. 2.16
2 . 1. 7
1. 1.
4. 4 .
2. 3.
H
Hammers, pile-driving
Highway Lave Loads (see Loads Live Load).
Horizontal Shear in Beams
3. 4.14
I
Ice Breakers
Impact (see Loads Impact).
Inspection :
Engineers and inspectors, access for
3.
1.5.8,
Final
1.5.8, 2.10.40
1.5.7, 2.10.41
1.
Joints
2 . 10 . 40
1. 9.
Inspector :
Access to work
Authority and duties
Definition
Iron
5 .
1.
4.10.
3.4.4, 4. 7.
2.10.24,
Abutting, metal
Construction joints, concrete (see Concrete).
Expansion (see Expansion Joints).
Fillers-
Oil asphalt
Premoulded
3. 8.
4.22.
4.22.
L
1. 1. 1
3. 6.36
Laboratory, definition
Lacing Bars, design
Lane (see Loads).
Lateral Forces (see Loads).
Laws (see Legal Relations).
Legal Relations :
Federal participation
Legal rights of state
Observance of laws
Patented processes
Permits and licenses
Live Loads (see Loads).
Loads :
Application
1.
1.
1.
1.
1.
7. 4
7.12
7.
7.
7.
1
3
2
3. 2. 8
263
Article
Loads :
Application
H-lane loadings continuous spans
Loading for maximum stress
Number and position, traffic lane units
Traffic lane units
Buoyancy
Current, floating ice and drift
Culverts :
Weight of earth assumed
Earth pressure by formula
Dead load weights
Distribution of wheel loads
Design of concrete slabs
Bending moment
Cantilever slabs
Distribution reinforcement
Edge beams (longitudinal)
Edge distance
Shear
Slabs supported on four sides
Span lengths
Unsupported edges (transverse)
Steel grid floor
Floor filled with concrete
General
Open floors
Stringers and floor beams
Bending moment in floor beams
Bending moment in stringers
Position of loads for shear
Through earth fills
Timber flooring
Continuous flooring
Longitudinal
Transverse
Earth Pressure
Electric railway
General
Impact
Live, highway
Application
Classes
Designation
General
H loadings
H-S Loadings
Lane Loadings
Minimum
...
3 .
3 .
2 .
2 .
2a
2b
3. 2.
3 .
3 .
3 .
3 .
3 .
3 .
3 .
3 .
3 .
3 .
2a
3f
2c
2b
2h
2d
2g
2i
2e
3. 3 .
5b
3 .
3. 3.
3. 3.
3. 3.
3 .
3. 3. 5a
3 .
5c
3. 3.
lc
lb
la
3 .
3. 3.
3. 3.
3. 3.
4c
4b
3 . 3 . 4a
3 .
3 .
3 .
3 .
3. 2.18
3. 2.10
3. 2. 1
3 .
2 . 12
2.
2.
2.
2.
2.
2.
2.
2.
2.
3 .
2 .
Bearing value
3.4.17,
Design
Reduction in intensity
Sidewalk and safety curb
Tables of moments, shears, etc., Appendix A
Thermal
264
2. 8c
2. 8d
2. 8b
2. 8a
2.17
2.16
3.
3.
3.2.3, 3.
3.
3.
3.
3.2.6, 3.
3.
3.
Standard trucks
Traffic lanes
Live, highway (1935 specifications), App'x C
Longitudinal forces
Overload provision
Piles-
3.
3.
3.
3.
3.
3.
5d
5e
5a
5b
5c
7
5f
7
3. 2.13
3. 2. 4
2.
3.
3.
3.
3. 6
5. 1
2. 9
2.11
3. 2.15
Article
Wearing surface, allowance for
Wind
Longitudinal
Longitudinal
Low-Alloy
Lumber
Malleable Castings
Cleaning
Material
Workmanship
Masonry:
3. 2. 2
3. 2.14
Steel
(see Timber,
Page
3. 6.
3.4.7, 4. 6.
127
136
183
147,213
216
216
216
M
:
4.11.
4.11.
4.11.
and finish
1
2
Brick
Brick
Bronze
Cement
Chromium alloy-steel castings
Copperi alloy
Defective
Eyebars (see Structural Steel).
Found on site
Gray iron castings
Malleable castings
4. 4.
4. 3.
1. 6. 4
212
212
232
227
227
216
211
215
216
16
1. 4. 7
Sec. 10
Sec. 11
215
216
4.24.
Sec.
Sec.
Sec.
Sec.
1
1
1
22
21
12
1
4. 9.
Sec. 12
Paint-
11
Aluminum
4.16. la
218
Black
4.16. lb
218
First field coat
4.16. 3
219
Second field coat
4.16. 4
219
4.16. 2
219
Shop coat
Timber structures
4.16. 1
218
Patented
1. 7. 3
17
Preservative treatment for timber section
Sec. 21
104
Reinforcement
Sec. 5
212
Sectional plate arches
224
Sec. 19
Sectional plate pipe
Sec. 19
224
Sheet metal
Sec. 18
224
Source and quality of
1. 6. 1
15
Steel castings (see Steel, castings).
Steel forgings (see Steel, forgings).
Steel grid
217
Sec. 15
Steel piles
216
Sec. 13
Steel sheet piles
Sec. 14
217
Stone for concrete
212
Sec. 4
61, 226
Stone for masonry
Sees. 6, 20
1.6.3,2.4.3,2.10.3,
Storage
2.20.3 ....16,37,69.99
Structural and rivet steels (see Steels).
Tests
1. 6. 2
15
Timber preservative oils
4.26. 1
235
Water
4. 2. 1
211
Waterproofing
229, 230
4 . 22 . 5-4 . 22 . 1 1
Welding
Sec. 17
223
265
Article
Wood preservatives
Woods, structural
Wrought iron
Mortar
Sec. 26
Sec. 25
Sec. 7
Ashlar masonry
Cement for
Pneumatically applied
Rubble masonry
Sand for
Water for. ,
2.
4.
2.
2.
4.
4.
6. 2
1. 1
4.31
Sec. 19 3.
6.54
7 .
3. 2
2. 1
N
Name Plate
Nickel Steel (see Steel, structural).
Notation, concrete design, Figs. 10, 11, 12
Nuts:
Pilot and driving
3. 7. 2
2 . 10 . 37,
Pin
Sleeve
2 . 10 . 55
3. 6.42
3. 6.45
O
Officials, personal liability
Oil Asphalt Filler
Oil, wood preservatives
Overload Provision
Timber structures
Metal structures
Application
1. 7.11
4.22.
4.26.
3. 2. 4
P
4.16.2,4.16.3,
Brushing
General
Inaccessible surfaces
Spraying
Cleaning surfaces
General
Method A
Method B
Method C
Surfaces inaccessible after assembly.
Coats and colors
Contact and inaccessible surfaces
Erection marks
Field
Galvanized surfaces
General
Machine finished surfaces
1
1
4.16.
4.16.
4
1
2.14.
2.14.
6b
6a
2 . 14 . 6d
2.14. 6c
. .
2.14.12,4.16.3,
2.14.10a
2.14.10b
2.14.10c
2.14.10d
2.14.10e
2 . 14 .
2 . 14 . lOe
2.14.11
4.16.
2.14.
2.14.
4
9
1
2 . 14 . 11
Mixing
Removal
Shop
2.14.11,
Thinning
Weather conditions
Welded surfaces
Patented Processes and Materials
Payment :
Ashlar masonry
Asphalt block wearing surfaces
Bituminous mat surfaces
2.14.
2.14.
4.16.
2.14.
2 . 14 .
4
7
2
8
5
2.14.11
1. 7. 3
2. 6.17
2 . 24 . 21
2 . 24 . 29
266
Article
Brick masonry
Brick wearing surface
2. 9.
2 . 24 . 14
2. 4.32
Concrete
Concrete cribbing
Concrete wearing surface
Embankment
Excavation and fill
Extra work
2.16.
2.24.
3
2
2. 1.12
2. 1.12
1. 9. 4
9.
J.
1. 9. 4
Final
2 . 10 . 59
4. 6.14
1. 9. 5
Partial
1.
2. \.
3.20
2. 3.18
1.4.3, 1. 9. 3
1. 9. 1
2.13.14
2. 5.12
2. 5.11
2. 8. 8
1. *. 2
2. 2. 5
2.12.11
Riprap
Rubble masonry
Scope of
Sheet piles
Steel grid
Steel structures
Timber cribbing
Timber structures
Waterproofing
Permits and Licenses
Phosphor Bronze (see Bronze).
2 . 10 . 60
2 . 22 . 6
2 . 20 . 23
2.17.
7 .
1 .
Piers:
Design
General
1. 4
5. 5a
3. 5. 5b
3. 5. 2 c
13.
Pier nose
Distribution of earth pressure
Tubular (see Tubular Steel Piers).
Piles:
Additional equipment
Battered
Bearing Values
Capacity as structural member
Capacity to transfer load to ground
Capacity of ground to support piles
General
Group Loading
Sub-Surface investigations uplift
Uplift
Design loads
General
Group Loading
Leads
Loading test
Methods of driving, general
Order lists
Payment
Additional requirements
Cutoff
, ,
o
o
^ . o. 4a
3. 5. le
3 . 4.17
3. 4.17b
3. 4.17c
3 .
3.
3.
3.
3.
2.3.2, 3.
3.
3.
2.
2.3.6,
4 . 17d
4.17a
4.17g
4.17d
4.17f
5. 1
5. 1
4.17
3. 4e
2. 3.20
2 .
3 .
2. 3.
2.
2.
2.
2.
Driving
4a
8
3.18e
3.18b
3.18c
3.18d
2 . 3 . 1 8b,
267
Page
Article
Method A
Method B
Payment
Projection into footings
Protection against scour
Spacing
2.
2.
2.
3.
3.
3.
2.
2.
Steel
Steel sheet
Steel shell (concrete filled)
3. 4.17
3. 5. 6
3. 4.17
Uplift
Piles, concrete
Accuracy of driving
Bearing values
Caps
Cast in place
Class of concrete
Extension or "build-ups"
General
shells
Painting
Payment conditions
Placing concrete
Reinforcement
Defective
Details
Batter
Buoyancy
Cast in place
Design loads
General
Limitation
of use
Precast
Spacing, clearances and embedment
Steel piles
Steel pile and shell protection
Driver
2.3.3
Sub-surface Investigations
Tubular Steel Piers
Metal
3.18b
3.18c
3.18b,
5. lc
5. 1
5. 1
3. 3
2. 1
leads
Extensions or "build-ups"
Followers....
General requirements
Hammer for driving
Loading tests
Precast
Casting.
Class of concrete
Curing
Finish
Form work
General
Handling and storage
Measurement and payment
Placing concrete
Projection in footings
Reinforcement
Size and shape
Test piles
Water jets
Piles, steel:
Accuracy of driving
Bearing values, formulas
2. 3. 4h
2. 3. 6
2. 3. 3b
31
2.
2.
2.
2.
2.
2.
2.
2.
2.
3.15c
3.16
3.15a
3.15b
3.17
3.18
3.15e
3.15d
3. 5
34
35
34
34
35
35
34
34
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
2.
2.
2.
3.
5. le
5. 1f
5. lh
5. 1d
5. la
5. lb
5. lg
5. 1d
5. li
5. lj
3. 4e
3.16
3. 4f
5. 1
2 .
3 .
4c
31
29
'.
2. 3. 6a, c
2.
2.
2.
2.
2.
2.
2.
2.
2.
3.
2.3.13d, 3.
3.
3.13e
3.13b
3.13g
3.131
3.13c
3.13a
3.14
3.18
3.15
5. 1
5. lg
5. lg
2. 3.19
2.3.7,
2.3.4g, 2. 3.
6b
2. 3. 4h
2.3.6
268
35
36
36
159
158
158
29
28
29
155
165
155
31
159
159
160
159
158
158
159
159
160
161
30
35
30
158
30
31,32
33
33
33
33
33
33
34
3d
34
158
33, 159
159
32,37
31,32
31
31
Article
Bearing values, general
2. 3.
2. 6.
CnrtK
Sfe:::::::::::::::...
Page
31
6D
2.3.3c
29
33
Cutting off
2. 3.11
Defective piles
6. a
<u
Design
Buoyancy
&.
g.
|
3. 5. i
Caps
160
. . . .
Core stoppers
..
2.3.2, 3. 5. la
29,158
General
3.4.1,3.4.17,3. 5. lc ....144,155,159
Loads ;.
3. 5. 1d
Spacing, clearance, embedment
159
3. 5. h
Splices
1M)
3. 5. li
Thickness of metal
160
Excavation
2. 3. 3a
9
Followers
2. 3. 4f
30
Hammers for driving
.
.
f.
j
Loading tests
\. 4.17
Va}\..
144,
Loads (for design)
3.4. ,3.
loo
29,216
2.3.1,4 .13. 1
Material
Measurement and payment
2. 3 .18
6a
Order lists
2. 3. 8
2.3.3f,2. 3.17
30,35
Painting
Preparation for driving
. .
j|
3e
Splicing
29
i.
...
"
"
J-
|- |.
wlt^S.v.
Piles, wooden:
Accuracy of cut-off
Accuracy of driving
Bearing values, formulas
Bents
Caps, driving'.
Collars, dnving
Defective
Design loads
Dimensions
Driver
:::::::::::2:3:4g,2:
::::
31,32
.
IJ.1"4h
2. d.
o'n\,
2.20.12
2. 3. 3b
2. o3. 5c
3
4.17
leads
Follower
Hammer for driving
Handling and storage
Heads, treatment of
Limitations of use
Loading test, bearing value
Payment conditions
4.25.
2. '
3.
if
2.20.
2. 3. 4b
2. 8. 9
3. 5. lb
2. 3. bb
2. 3.18
2. 3. 3d
2. 3
Pointing
.Ji
,i
iu29
qi
61
155
tio
So
30
30
66
100
is>
61
60
.3
Preparation
Preservatives
Preservative treatment
Projection into footings
4.26.
2 .21.
4.2o.
^o
|*
io
234
3. 5. 1d
Quality
2. 3. 3e
SSs/.:::::::::::::::::::::::::^^^:
also Timber, Lumber and Piles; Timber
3: 6b
Structures.)
, .
2 10.34
2.10.35
2.10.55
2.10.33
(See
3: eb
269
30
...31,32
76
76
80
/b
Article
Holes
2.10.34,
Location, pins
Pilot and driving nuts
2 . 10 . 37,
Pin nuts
Plates
Size
Pipe Railing (see Railings and Parapets).
Pipe, Sectional Plate (see Sectional Plate Pipe).
3. 6.37
3. 6.39
2 . 10 . 55
3. 6.42
3. 6.40
3. 6.18
Plans:
Contractor's approval
.
Coordination with specifications
Definition
Deviation from
Examination
1. 5. 2
1. 5. 4
1.
1.
5.
2. 3
Intent
1. 4. 1
Working drawings
1. 5. 2
Plate Girders (see Steel Structures Design and Details).
Preservative Treatments for Timber :
Construction
Amount of preservative
2 . 21 . 4
Creosote
2.21. 4a
Salt treatments
2.21. 4b
General
2.21. 1
Limitations of treatments
2.21. 1
Preparation for treatments
2.21. 3
Framing
2.21. 3b
Incising
2.21. 3c
Sorting
2.21. 3a
Pressure treatment processes
2.21. 5
Materials
Chromated zinc chloride
4 . 26 . 1
Creosote-coal -tar solution
4.26. 1
Creosote oil
4.26. 1
Creosote-petroleum solution
4 . 26 . 1
Sodium fluoride-arsenate dinitrophenol solu
tion (Wolman Salts)
4.26. 1
Zinc chloride
4 . 26 . 1
Zinc meta arsenite (Z.M.A.)
4.26. 1
Property Protection and Restoration
1.4.8, 1. 7. 8
Proposal :
Competency of bidders
1. 2.11
Contents of proposal form
1. 2. 1
Definition
Delivery
1. 2. 7
Disqualification of bidders
1 . 2 . 10
Examination of plans, specifications and site. .. . 1. 2. 3
Form for
1.2.1, 2. 2. 4
Guaranty (see Proposal Guaranty).
Interpretation of estimates
1. 2. 2
Preparation
1. 2. 4
Public opening
1. 2 . 9
Rejection
1. 2. 5
Requirements and conditions
Sec. 2
Withdrawal
1. 2. 8
Proposal Guaranty:
Definition
Forfeiture
1. 2. 6
Return
1. 3. 3
Submitted
1. 2. 7
Public Safety and Convenience
1. 7. 6
270
Article
2.13.
2.13.11
2.13.
2.13.
2.13.
2.13.
2.13.
2.13.
4
2
2.13.10
2.13. 1
3.1.10, 3. 2.11
2.13. 3
3. 2. lid
Metal-
Construction
Materials
Painting
Weight
Payment conditions
Stone and brick
Types and general requirements
Wooden
Ratings of Existing Bridges :
Columns
Batten plate
Eccentrically loaded
Long
Compression, flanges of beams and girders
Dead load
Details of design
Pins
Splices
Strength of connections
Field inspection
General
Inventory ratings
Live load
Operating rating
Stresses, unit
Traffic lanes
2.10.62f
2 . 13 . 14
2.13.12
3. 1.10
2.13.13
3.12.10
3.12.
3 . 12 .
9
9
3.12.11
3.12.
3.12.12c
3.12.12b
3 . 12 . 12a
3.12.13
3.12.
3.12.
3.12.
3.12.
1
2
5
3
3 . 12 . 7
3.12.
Wind load
3.12.
Reinforcement, concrete:
Anchorage
3.
4.
4.
4.
2.
2.
2.
2.
2.
2.
2.5.8, 2.
4.
Bar
Bar deformations
Bar mat
Fabrication
Material
Order lists
Payment conditions
Placing and fastening
Protection of
Splices and lapping
Structural shapes
Substructure and retaining wall
(See also Concrete Reinforcement.)
Wire and wire mesh
Retaining Walls :
Base or footing slabs
Counterforts and buttresses
Drainage
Expansion and contraction joints
3 .
8
6
7. 9d
5. 1
5. 1
5. 3
5. 4
5. 1
5. 2
5.12
5. 7
5. 3
5. 9
5. 4
5.
2f
4. 5. 2
3 .
3 .
5.
5.
4b
4d
3. 5. 4g
3. 5. 4f
271
Article
General
Reinforcement for temperature
Vertical walls
Right to Reject Bids
Right of Way, definition
Riprap :
Concrete (in bags)
Concrete slab
3.
3.
3.
1.
1.
5.
5.
4a
4e
5. 4c
3.
1.
2.15.7, 2.15.
2.15.
2.15.2, 2.15.
Dry
Foundation protection
Grouted
Material
Measurement and payment
Mortared
Placing
Rivets (see Steel and Steel Structures).
Roadway :
Access to abutting property
Clearances
Curbs
Definition
Drainage
Opening to traffic
2.15.1,
1
1
9
8
3
2.15. 6
2.15. 5
4.20. 3
2.15.11
2.15. 4
2.15.10
1.
3.
2.20.19, 3.
1.
3.1.11, 3.
1.
Width-
Page
6.
1.
1.
1.
8.
7.
91
92
92
91,227
93
92
93
16
122
.104, 122
9
1
7
124,201
17
1. 8
1.17
122
126
8 .
1
4
2.
2.7.10, 2.
2.
2.7.5, 2.
2.7.3, 2.
7.
8.
7.
8.
8.
93
93
8.
8.
2.7.2,2.8.2,2.20.1,
10
7
3.1.7, 3.
Bridges, Figs. 1 to 4
3.
Depressed roadways
Depressed roadways
Clearance
3.
Curbs
3.
Roadway width
3.
Minimum required, Figs. 1 to 3 . . 3.1.7,3.1.8, 3.
Tunnels, Fig. 3
3.
3.
Underpasses
Rolled Plates and Shapes :
3.
Angles, effective area
3.
Angles, minimum size (bracing)
3.
Angles, outstanding leg
3.
Beams
3.
Thickness of metal
2.10.33,3.4.2, 3.
Rollers
Rubble Masonry:
Arches
2.
Arch rings
Backing
2.
General
2.
2.7.7, 2.
Copings, bridge seats and backwalls
2.7.1, 2.
Description
2 .
Dry rubble masonry
2.7.4, 2.
Headers
2.7.6, 2.
Laying
Material
Mortar rubble masonry
164
165
165
1.17b
1.17c
1.17a
1 . 17
1.16
1.18
6.13
6.66
6.17
6. 8
6.14
6.51
7.
7.
7.
7.
8.
8
8
8
8
1
2.20.2
8
9
126
126
127
122, 126
125
126
169
180
170
167
169
76,145,177
66
66
66
66
65,67
67
65,67
65,67
....65,67,98,99
65
67,68
67
65,67
65
6
2
17
212
S
1. 7.
4. 3.
Safety, public
Sand, for mortar
272
Page
Article
Sandblasting
Sanitary Provisions
Sectional Plate Arches:
Construction
Description, general
Description of plates
Erection
Forming and punching plates
Measurement
Payment
Substructure and headwalls
Workmanship
Design
Adjustment of table
Bolts
Gage of plates
General
Minimum height of cover
Multiple spans
Ratio, rise to span
Skewed spans
Substructure
Material
Base metal
Bolts
Certified analysis and guarantee
Chemical analysis and tests for spelter coat
ing
Corrugations
Field inspection and acceptance of plates . .
Gage determination and tolerance
Galvanizing
Identification
Nuts and bolt heads
Sampling
Spelter coating
Sectional Plate Pipe :
Construction
Description, general
Description of plates
Erection
Forming and punching plates
Measurement
Payment
Strutting
Workmanship
Design
Bolts
Cover exceeding heights in Table 1
Gage of bottom plates
Gage of plates
General
Minimum height of cover
Multiple pipes spacing
Size of pipe not in table
Strutting
Material
Base metal
Bolts
Certified analysis and guarantee
273
2.14.10c
1. 7. 5
89
2.23. 1
2.23. 3
2.23. 6
2.23. 4
2.23.10
2.23.11
2.23. 8
2.23. 9
108
109
110
3.11.
3.11.
3.11.
3.11.
3.11.
3.11.
3.11.
3.11.
3.11.
206
206
206
206
206
207
206
207
207
4.19.
4.19.
4.19.
5
6
2
1
4
7
3
7
8
17
109
113
113
1ll
1ll
8
6
224
226
225
4.19. 5
4.19.10
4.19.12
4.19.11
4.19. 3
4.19. 7
4.19. 9
4.19. 4
4.19. 2
225
226
226
226
225
225
226
225
224
2.23. 1
2.23. 3
2.23. 5
2.23. 4
2.23.10
2.23.11
2.23. 7
2.23. 9
108
109
109
109
113
113
3.10.
3.10.
3.10.
3.10.
3.10.
3.10.
3.10.
3.10.
3.10.
205
205
205
204
204
205
205
205
205
4.19.
4.19.
4.19.
5
6
4
2
1
3
8
7
9
1
8
6
1ll
1ll
224
226
225
Sheet Metal:
Copper
Lead
Zinc
Sheet Piles:
Concrete
Payment conditions
Steel
Wooden
Sidewalk :
Brackets
Article
4.19.
4.19.
4.19.
4.19.
4.19.
4.19.
4.19.10
4.19.12
4.19.11
4. 18.
4.18.
4. 18.
2.
2.
2.
2.
7
9
4
2
1
2
3
2. 3
2. 5
2. 4,!
2. 2
Finish
Load
3. 6.63
2. 4. 30
3. 2. 11
Width
1. 2.
1. 4.
1. 4.
Intent
Silence of
274
3
8
5
3. 3. 2f
Distribution
Reinforcement perpendicular
Edge supports
Moments
Shear
Span lengths
Supported four sides
Sodium Fluoride-Arsenage Dinitrophenol
(Wolman Salts)
Soils, bearing power
Span lengths:
Concrete
Steel
Special Provisions :
Coordination
Definition
Examination of
Special Work
Specifications :
Coordination with plans
Definition
Examination of
Solution
3.3.2(i),
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
2f
3
2
2
2
2b
2
2d
2i
28
4.26. 1
3. 4.15
3. 7.
3. 6.
4
3
1.
1.
1.
1.
4
1
5.
1.
2.
4.
1. 5.
1.
1.
1.
1.
1.
1.
1.
2.
4.
6.
1.
1.
3
2
4
1
3
1
5
1
1
Article
Steel:
Castings
Carbon
4. 9. 1
Chromium -alloy
4. 9. 2
Malleable
4.11. 1
Copper bearing
4. 6. 8
Forgings
4. 8. 1
General
4. 6. 1
Grid floor (see Bridge Floors).
4.13.1,4.14. 1
Piles
Reinforcement (see Reinforcement, Concrete).
Rivet-
High strength
Structural
Sheet piles
Structural
Carbon
Low-alloy
4. 6.
4. 6.
4.14.
4. 6. 2
6. 4
4. 6. 5
4. 6. 3
Tests-
4. 6.12
4. 6. 9
size
4.6.10
Minimum size of
Portal and sway
3.4.7,4.
steel
Nickel
Silicon
Structures (see Steel Structures).
Full
'. . . .
4. 6.14
4. 6.13
4. 6.11
3. 6. 5
3. 6.53
3. 6.13
3. 6.16
Sec. 9
2.10.52
3. 6.43
3. 6.69
.
3. 6.65
3. 6.70
3. 6.67
3 .
6 . 72
3. 6.66
angles
3 .
3.
Through plate girders
Closed sections and pockets
3.
Columns
3.4.2, 3., 4., 5., 7., 3.
Formulas
Formulas, Appendix B.
Combined stresses
3.
Compression members
3.
Cover plates (perforated)
3.
Depth ratios
3.
Eccentric connections
3.
Effective area, angles
3.
3.6.46,3.
Expansion
.3.6.47, 3.
Expansion bearings
Fabrication, riveted unless otherwise speci
6 . 68
6.71
6.28
4.
6. 6
6.15
6.36
6.11
6.29
6.13
6.64
6.48
2.10.
fied
Fillers
3. 6.33
275
Article
Fixed bearings
Floor Steel grid (see Bridge Floors).
Floor system
Cross frames
End floorbeams
End connections
,
End panels, skew
Expansion joints
Floorbeams
Sidewalk brackets
Stiffness
Stringers
Forked ends
Gusset plates
Inclined bearings
Intermediate stiff eners
Lacing and perforated cover plates
Limiting length of members
Loads (see Loads).
Minimum thickness of metal
Name plates
Net sections, riveted members
Outstanding legs of angles
Parts accessible
Payment conditions
Pedestals and shoes
Pin holes, net section at
Pin plates
Pins and pin nuts
Pins, location of
Pins, size of
Plate girders
Camber
Depth
Flange
Rivets
Section
Splice
General
Masonry bearings
Sole plates
Stiffener, transverse, end
Stiff eners, transverse, intermediate
Stiff eners, longitudinal
Through, ends of
Web plates, thickness
Web splices
Plates in compression
Plates for arches (Solid Rib)
Rivets :
Deduction for net section
Edge distance
Lone grip
Size of
Stitch
Tension
Rolled beams
Rollers
3. 6.49
177
6.58
6.60
6.62
6.61
6.64
6.59
6.63
6.65
6.57
6.41
6.34
6.52
6.80
6.36
6. 9
178
179
179
179
179
178
179
178
178
176
173
177
182
174
167
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3. 6.14
2.19.1, 3. 6.54
175
170
171
80
177
175
176
176
175
170
3. 6.85
3. 6.104
183
186
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
6.76
6.74
6.77
6.73
6.84
6.83
6.79
6.80
6.81
6.82
6.75
6.78
6.15
6.16
182
181
182
181
183
183
182
182
183
183
181
182
169
170
6 . 38
175
171
171
170
3.
3.
3.
3.6.21, 3.
3.
3.
3.
3.
6.24
6.25
6.20
6.22
6.19
6.23
6.26
6. 8
3.4.2,3.4.7,3.4.8,3.6.51
276
169
97,178
3. 6.38
3. 6.17
3. 6.27
2.10.58
3. 6.50
3. 6.37
3. 6.40
3. 6.42
3. 6.39
3. 6.18
3 .
Pitcn
Pitch
Page
170,171
170
171
171
167
....145,146,177
Article
Secondary stresses
Sleeve nuts
Splices
Splices, indirect
Stay plates
3.6.79,3.6.80,
Stiffener, plate girders
.
Strength of connections
Symmetrical sections
Thickness of metal
T ru ssgs
Bottom chords
Camber
Counters
Diaphragms
Eyebars
General
Half -through
Masonry bearings
Riveted tension members
Sole plates
Top chords and end posts
Working lines and axes
Trusses and girders
Effective depth
Effective span
Number
Sidewalk brackets
Spacing
Upset ends
Viaducts
Bents and towers
Batter
Bents and towers
Bottom struts
Bracing
Single
Girder connections, bracing
Girder
Sole and masonry plates
Types
Welding
Erection
Assembling steel
Bearings and anchorages
Bedplates, setting
Bolted connections
Camber diagram
Delivery of material
Erection of structure
2.10.49,
Falsework
Handling and storing material
Methods and equipment
Misfits
Plant
3.
3.
3.
3.
3.
3.
3.
3.
3.
6. 7
6.45
6.31
6.32
6.35
6.81
6.30
6.12
6.14
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
6.88
6.90
6.92
6.95
6.93
6.86
6.70
6.97
6.91
6.96
6.87
6.89
184
184
184
185
184
183
180
185
184
185
184
184
3.
3.
3.
3.
3.
3.
6. 4
6. 3
6. 1
6.63
6. 2
6.44
167
166
166
179
166
176
3.
3.
3.
3.
3.
3.
3.
3.
3.
3.
6.100
6.99
6.103
6.102
6.101
6.105
6.105
6.106
6.98
6.55
185
185
185
185
185
186
186
186
185
178
2.10.53
2 . 10 . 51
2.10.51
2.10.18
2.10.13
2.10.47
2.10.47
2.10.57
2.10.48
2.10.50
2.10.56
2 . 10 . 57
2.10.55
2.10.45
2.10.46
2.10.54
Riveted connections
Straightening bent material
Work to include
2 . 10 . 52
2.10.44
277
Page
167
176
172
172
173
182,183
179
162
169
79
78
78
72
71
78
78
78,80
78
78
80
80
80
77
78
79
79
77
Article
Inspection and tests2.10.39
Facilities for
4. 6. 8
Full size tests
2.10.40
Inspector's authority
Materials
2.10.32
Annealing eyebars
4. 6.13
Annealing record
4. 6.12
Failure to meet requirements
2.10.41
Mill orders
4. 6.10
Number and size test bars
2.10. 3
Storage
2.10.4,2 10.52
Straightening
4
6.10
Test bars and test eyebars
2 10.42
Weighing finished pieces
Payment conditions
.. 2.10.59
Basis of payment
.. 2.10.62(i) to (8).
Computed weight
.. 2.10.59
Eyebars, tested
59,4. 6.14
Full size tests
.. 2.10.60
Pay weight
.. 2.10.61
Variance in weight . .
Workmanship and fabrication
.. 2.10.24
Abutting joint
.. 2.10.32
Annealing
12,2.10.53
Assembling, shop
2.10.23
Bearing surfaces
2.10.29
Bent plates
Bolts and bolting
2.10.18
Field connections
Field connections
. 2.10.18d
Special ribbed bolts
. 2.10.18c
Turned bolts
. 2.10.18b
Unfinished bolts . . .
. 2.10.18
Fitting up
. 2.10.13
Camber diagram
. 2.10.25
End connections angles
. 2.10.31
Eyebars
. 2.10.17
Field rivets
2,2.10. 5
Finish
. 2.10.27
Finished members
. 2.10.30
Fit of stiffeners
. 2.10.22
Flame cutting
. 2.10.48
Handling finished material .
. 2.10.26
Lacing bars
. 2.10.43
Marking and shipping
. 2.10.15
Match marking
Milled and planed surfaces
2.10.24
Abutting joints
2.10.25
End connection angles
2 . 10 . 23
Facing bearing surfaces
2 . 10 . 20
Planing sheared edges
Paints and painting (see Paints and Painting).
2 . 10 . 37
Pilot and driving nuts
Pins (see Pins, Pin Holes and Rollers).
Punched, reamed and drilled
2 . 10 . 11
Accuracy of drilled holes
Accuracy of punched and sub -drilled
2.10.10
holes
2.10.11
Accuracy of reamed holes
2.10.14
Drifted holes
2.10.6,2.10. 8
Drilled holes
2.10. 7
Punched holes
....
278
81
71
Article
10.6,2.10.
2.10.
2.10.
2.10.
2.10.
Punched work
Reamed work
Reaming
Reaming, field connections
Sub-punched holes
Rivets and riveting-
Field
Field connections
Riveting
2.10
2.10
2.10
2.10
Page
8
9
9
9
70
70
70
70
70
17
54
19
16
72
79
73
72
61,226
3
2
227
227
Riprap
Rubble
(See also Ashlar Masonry; Rubble Masonry.)
Stresses:
Alternating
Combined
Concrete piles (due to handling)
Moments
Secondary
Sheets
Steel structures-
'
4.20.
4.20.
3.
3.
3.
3.
8.
1.
6. 5
6. 6
5. lK
4. 18
6. 7
5. 2
Carbon
3. 4.
Cast iron
3 . 4.
Cast steel
3.4.
.3.4.2, 3.4.7,3. 4.
Column formulas. . .
.
Column formulas (Appendix B)
Low-Alloy
3.
3.
3.
3.
4.
4.
4.
4.
3. 4.
3. 4.
Nickel
Rivets
Rivets (high strength)
Silicon
7
Welding
Wrought iron
3. 4.
Timber-
Column formulas
Column formulas, round columns
Column formulas (connector joined)
Horizontal shear
Inclined surfaces, bearing
Notched beams
Timber connectors
Treated
Untreated
Unit
stresses
Bearing on masonry
Bronze
Concrete structures
Concrete
Reinforcement
Copper-alloy
General
2
5
5
8
7
8
2
3
8
9
4
3. 4.14
3. 4.14d
3. 4.14c
3 . 4 . 14a
3. 4.14f
3 .
4 . 14e
3. 4.14g
3. 4.13
3. 4.13
3. 4.10
3. 4.
3. 4.11
3. 4.12
3. 4.
3. 4.
279
6
1
76
77
75
176
74
73
167
167
159
158
167
12
145
146
146
. .145, 146, 147
242
146
147
145
146
147
148
146
152
153
153
152
154
154
154
151
151
148
146
148
150
146
144
Article
3.
3.
3.
3.
3.
Steel
4.17
4.17
4.17
4. 1
4.15
Timber
Reduction (load in combination)
Soils, bearing power
Structural Steel (see Steel).
Structure :
1.4.6,2.10.58
Existing
Temporary, definition
1. 4. 6
Temporary, removal
Sub-contractor, definition
Substructure :
2.10.51,3. 52b, 3 . 6 . 53
Anchor bolts in
Definition
3. 5. 2c
Distribution of pressure
3. 5. 4g
Drainage
3. 5. 5
Ice breakers
Piles (see Foundations and Substructures).
2.15.6,3. 5. la
Scour protection
Tubular steel piers (see Tubular Steel Piers).
Substructures and Foundations (see Substructures and
Foundations).
1 . 5 . 5, 1 . 8 . 4
Superintendent, competence of
Superstructure :
2 . 10 . 51
Anchor bolts, setting
2.10.51
Bedplates
1. 1. 1
Definition
1. 1 . 1
Surety, definition
2. 4.23
Surface Finish, concrete
1. 8. 5
Suspension of Operations
T
Appendix A
Tables of Moments, Shears, etc.
Temporary Structures :
Construction and maintenance
Definition
Removal
Terms, definition of
Thermal Force
Timber Cribbing :
Construction
Face logs of timbers
Filling
Foundation
Material
Mudsills
1. 4.
1. 4.
1 .
1.
3. 2.15
2 .22 .
2.22.
2.22.
2.22.
2.22.
2.24.
2.22.
2.22.
2.22.
4.25.
4.25.
4.25.
4.25.
4.25.
4.25.
280
4c
5
4a
1
4b
3, e
3
2
6
4
3
5
6
2
1
Article
Structural beams and stringers
3. 4.13
Stress grades and working stresses
Structural joist and plank
3 . 4.13
Stress grades and working stresses
Structural posts and timbers
3. 4.13
Stress grades and working stresses
Timber piles
Dimensions
4.25. 9
General
4.25. 7
Quality
4.25. 8
Wooden.)
(See also Piles
Treated (see Preservative Treatment for Timber).
Timber preservative oils
4.26. 1
Timber structures :
Application of grades and sizes
4.25. 5
3. 9. 1
Beams (composite)
2.20.15, 3.85e, 3. 8. 6e
Bracing
Bridging
2.20.16
Caps
2.20.14
Columns and posts
3.4.14c, 3. 8. 4
Connector joined
3. 8. 4
Design
Formulas
3. 4.14
3. 4.13
Stresses
Connectors
Construction
2.20. 2
3. 4.14
Design
Material
4.27.1-4.27. 6
Countersinking
2.20.10
Cribs (see Cofferdams and Cribs; also Tim
ber Cribbing).
3. 8. 7g
Drainage
Erection, housing and railings
2.20.22
Fire stops
3. 8. 8
Formulas
Axial compression on connector
joined spaced columns
3. 4.14c
Axial compression in rectangular col
3. 4.14b
umns
3 . 4 . 14f
Bearing on inclined surfaces
Horizontal shear in rectangular beams . 3.4. 14a
3 . 4 . 14e
Notched beams
3. 4.14d
Safe load on round columns
3. 4.14g
Timber connectors
Framed bents
2.20.15, 3. 8. 5e
Bracing
3. 8. 5d
Caps
3. 8. 5b
Framed bents
Pile bents
3. 8. 5a
Pile bent abutments
3 . 8 . 5f
Sills and mud sills
3. 8. 5c
2.20.14, 3. 8. 5
Caps
2.20.13a, 3. 8. 5
Mudsills
Pedestals, concrete
2.20.13b
2.20.13d,3.8.4, 3. 8. 5
Posts
2.20.13c, 3. 8. 5c
Sills
Framing
2.20.11
Hewn and round timbers
4.25. 4
Holes, bolt, dowel and lag screw
2.20. 8
Lumber and timber
2.20. la
Metal parts
2.20.9, 3. 8. 1
Bolts and washers
281
Page
Article
2.20.1c,
Castings
2.20.1b,
Eyebars
Hangers
2.20. Id,
Hardware
2.20.1b,
Structural shapes
Painting
Payment conditions
2.20.12,
Pile bents
Pile bents, abutment
Pile heads, treatment
Fabric covering
General
Zinc covering
Plank, laminated and strip floors (see Bridge
Floors).
2.20.19,
Railings
Storage of material
Stringers
Treated timber
Bolt holes, treatment
Cuts and abrasions
Framing and boring
Handling
Pile heads, treatment
Temporary attachment
Trusses
Bracing
Bridging
2.20.20,
Camber
Drainage
Eyebars and counters (see Eyebars).
Fire stops and curtains
Floorbeams
Flooring
Hangers
Housing
Joints and splices
Nailing strips
2.20.19,
Railing.
Retaining pieces
Stringers
Wheel guards
...r
Unit
stresses
(see Stresses).
Tubular
Steel
Bracing
Depth
Details
Piers:
3. 8. 6a
3. 8. 6d
99,200
99,201
3. 8. 6c
3. 8. 3
3. 8. 6
201
99,199
99,200
2.20.23
104
104
2.20.24
3. 8. 5f
3. 8. 5f
2.20.
2.20.
2.20.
2.20.
102,200
200
100
101
100
7c
7a
7b
101
104,202
3. 8. 7h
2.20.
2.20.16
99
103
2.20.
2.20.
2.20.
2.20.
2.20.
2.20.
100
100
100
100
100
100
3. 8.
5
5
5
7
5e
201
201
6e
3. 8. 7b
3. 8. 6f
3. 8. 7g
104,201
202
3. 8. 8
3. 8. 6b
3. 8. 7d
3. 8. 6c
2.20.21
3. 8. 6a
3. 8. 7c
3. 8. 7h
202
201
202
201
104
200
201
104,202
3 . 8 . 7e
3. 8. 7a
202
201
202
3. 8. 4
199
100
104
3. 8. 7f
2.20. 6
2.20.19
2.20.20
3. 8. 2
1. 1. 1
3. 2. 6
3. 2. 7
...100,102,104
199
$
130
130
3. 5. 6f
3. 5.
3.
3.
3.
Piling
Use of
282
6b
5. 6
5. 6c
5. 6a
. :
166
166
165
166
165
Article
Tunnels:
3. 1.16b
3. 1.16d
3. 1.16c
3. 1.16a
U
Underpasses :
Clearance, vertical
Curbs, minimum width
Width between curbs
Unit Stresses (see Stresses).
Utilities, provision for
3. 1.18b
3 .
1 . 18c
3. 1.18a
3. 1.15
V
Viaducts :
Concrete (see Concrete Viaducts).
Steel (see Steel Structures Viaducts).
w
Warning Signs and Barricades
Water:
1.4.5, 1.
7 .
4. 2 .
7
1
4. 2.
4. 2.
2.17.
2.17.
2.17.1, 2.17.
6
5
Fabric
2.17.2, 4.22.
2.17.2, 4.22.
Joint filler
Pitch
Tar
4.22.
4.22.8, 4.22.
Payment conditions
Preparation of concrete surfaces
Protection course
Storage of fabric
Waterway Area (see Design).
Waterway Restricted (see Design).
Wearing Surface, allowance for (see Loads).
Wearing Surfaces (see Bridge Floors).
Weight of Materials
Welding:
Construction
Design
General
Material
Specifications
Stresses
2.20.19,3.1.9,
Wheel Guards and Curbs
Wind Loads (see Loads).
Wolman Salts
Wood, Wooden (see Timber, Lumber and Piles ; also
Timber Structures).
4.22.11
4.22.10
2 . 17 .
6
9
2.17.
2.17.
2.17.
4
8
3
2 .
3 .
2.10.21
3. 6.55
3 .
6 . 55
4.17.
4.26.
3. 6.55
3. 4. 9
3. 8. 7f
Article
Wood Preservatives:
Material (see Preservative Treatment for Timber).
Work, definition
1. 1.
1. 1 .
Working Day, definition
1
Workmen, competence of
Wrought Iron :
Plates
4. 7.
Shapes and bars
4. 7.
4. 7.
Pipe.
J1
4
1
2
3
2.21.1, 4.26.
2.21.1, 4.26.
Zinc Chloride
Zinc meta Arsenate (Z.M.A.)
284
1
1
TLoicA
VhobLtu
4228?
TG
American Association of
State Highway
Officials .
Standard specifications
for highway bridges
tf.
.A6
Of
M.