Sei sulla pagina 1di 33

Chapter 3

Implementation of Tank Cleaning Work


Precautions during implementation of various tasks in the tank cleaning work are explained here.

1. Crude oil washing at the previous discharging terminal (P.3-2 to P.3-3)


2. Filling of washing water (P.3-4 to P3-8)
3. Heating of washing water (P3-9)
4. Rough washing of cargo line and cargo pump (P.3-10)
5. Line washing and valve flushing (P.3-11)
6. Tank washing work (P.3-12)
7. HC gas purging (P.3-13)
8. Airing (P.3-14)
9. Settling and discharging water (P.3-15 to P.3-16)
10. Final line washing (P.3-17)
11. Sludge removal (P.3-18 to P.3-19)
12. Slop removal (P.3-20)
13. Primary slop tank washing and HC gas purging (P.3-21)
14. Gas-freeing and sludge removal of primary slop tank (P.3-22)
15. Final line stripping (P.3-23)
16. Gas-free certificate (P.3-24)

(Gass free) 3- 1
2002/10 (Ver.1)

1.

Crude oil washing at the previous discharging terminal


1.1

Precautions

The precautions below should be taken during crude oil washing (COW hereafter) at the previous
discharging terminal.
1) Thoroughly study the bell mouth position of the stripping line in each tank and adjust the trim and
heel of the ship to the optimum levels.
2) Ensure that the accumulation of crude oil does not become greater than the stripping capacity of the
eductor and that the defeat of stripping capacity does not occur when implementing COW.
3) As far as possible, consider open-cycle washing in the discharging plan.
1.1.1 Adjusting trim and heel of the ship to the optimum levels
Perform trim and heel adjustments as given below.
1) Trim
A trim by the stern of about 2% (6 m to 7 m) of the ships length is necessary when the bell mouth
is at the aftermost part of the tank.
Examine the main engine and boiler for defects referring to past records of the ship and adjust to
obtain an appropriate trim as far as possible.
2) Heel
Stripping efficiency is generally good when the heel is about 1 to 1.5 degrees. Reports from SBT
ships indicate that the stripping efficiency was good when the heel was about 2 degrees.
If the ship is heeled when berthed at the pier, take into account the condition of the mooring lines
and give instructions to the deck watch to adjust the mooring lines suitably.
1.1.2 Measures against defeat of stripping capacity
If COW is continued so that the defeat of stripping capacity is reached, there is a risk of
accumulation of a large amount of sludge near the bell mouth at the aft part of the tank. The method
described below may be adopted as a measure against the defeat of stripping capacity.
a) If extra time for discharging is available, use some COW machines on the aft side only at the final
state of COW, and again perform the bottom washing near the bell mouth.
b) Temporarily stop the COW and assign adequate stripping time.
1.1.3 Bottom wash by open-cycle method
The sludge gathered by the eductor during the stripping can be adequately discharged to the shore tanks
if bottom wash is implemented using the open-cycle method, thereby enabling the accumulation of
sludge in the slop tank to be reduced. Wherever possible, tank bottom wash should be implemented
using the open-cycle method. In such cases, care should be taken against reduction of intake pressure
of the tank cleaning pump due to the ullage reduction of the slop tank.
1.1.4 Effective use of AUS (Automatic Unloading System)
Implement sludge control according to the method given below at the final stage of discharging when
AUS has been provided.
1) Perform COW of slop tank used as the eductor gathering tank, using the fresh oil stored in the slop
tank on the opposite side of the ship.
2) At this stage, do not use the eductor at all for tank stripping. Use the cargo pump of the AUS and
directly discharge the contents of the tank.
3) This results in discharging the sludge accumulated in the eductor gathering tank directly to the
shore tank.
4) After completing COW of the eductor gathering tank, a large amount of sludge is likely to remain
in the cargo line used for discharge. By forcefully discharging the fresh oil remaining in the slop
tank on one side to the shore tank, the sludge in the cargo line can be completely removed.
(Gass free) 3- 2
2002/10 (Ver.1)

Compared to not implementing the method mentioned above, the quantity of gathered sludge in the eductor
gathering tank has reduced considerably using this method, as is evident from past records. If time permits, the
method should be incorporated in the discharging plan, explained to the terminal and their understanding
obtained.

(Gass free) 3- 3
2002/10 (Ver.1)

2.

Filling of washing water


2.1

Measures to prevent accidents during work

Take the measures to prevent accidents given below before starting the filling work.
1) Keep ready the line diagram clearly showing the valve operating sequence at the operating
location.
2) To prevent errors in valve operation, frame measures that make use of valve sealing tape.
3) Confirm valve lineup by the method of pointing with the finger and repeating the actions aloud.
(promote confirmation by pointing out and repeating the actions aloud)
Backflow may sometimes occur due to operational errors such as error in the valve opening sequence or
opening a different valve by mistake (for instance, opening the sea chest valve first, opening a valve located
on a pipe that is higher than the sea water level). Thus, it is important that the operators be educated and
trained in the valve operating sequence such that errors are prevented in the normal course of work.

2.2

Work before valve lineup

Perform the tasks mentioned below before the valve lineup for filling water.
1) Start the stripping pump before starting the water filling operation, strip all the necessary lines in
the cargo line, and gather the remaining oil in the primary slop tank. Also discharge the oil on the
discharge side (riser part) of the stripping pump to the same tank.
2) Perform the leak test of the overboard sea chest valve.
3) Adjust the vent valve of the filling tank before the filling operation and reduce the tank pressure
(200 to 300 mmAq) such that this pressure does not become negative. If the IGS interlock switch
has been provided, cancel it before starting the filling operation.
IGS interlock switch
If the tank pressure in the IGS system drops below 100 mmAq, a protective device provided in the tank trips
the cargo pump and the tank cleaning pump. During tank cleaning however, the cargo pump will be operated
when the tank pressure is low. Therefore, this protective device has to be canceled to enable the pump to be
operated. The IGS control panel has a switch for key operation. The position of this switch during normal
cargo handling operation is at INTERLOCK, but during tank cleaning it should be set at the CANCEL
position.

2.3

Filling sea water (from the sea chest) by gravity

(Refer to "Line Diagram" in Fig. G-3-1 of P2-68 and "Line Diagram" in Fig. G-3-2 of P2-69 in
the "Documents Section.)
1) Station a look-out carrying a portable transceiver near the overboard sea chest to monitor the sea
water level and to ensure a sound monitoring system.
2) Valve lineup (1)
Take adequate care to configure the line from the overboard sea chest valve to the initial filling tank
such that the sea water does not flow in the reverse direction by the shortest distance.

5C tank valve

V252

Open

Bulkhead valve

V121

Open

Common line valve

V152

Open

Sea chest valve (inboard side)

V192

Open

3) Start of water filling


(Gass free) 3- 4
2002/10 (Ver.1)

Sea chest valve (outboard side, adjusting


V191
valve)

Open

Suction line

V121, V122

Open

Riser common valve

V114, V124

Open

Deck main line master valve

V321, V322, V333

Open

Crossover valve

V331, V332, V333

Open

Return line to 5C

V144, V174, V176, V182

Open

Gradually open the overboard sea chest valve (avoid opening it suddenly) after confirming that all the
valves in the filling line, including valves of the tank to be filled, are open and start filling the water.
4) Completion of filling
When the expected volume of water has been filled in the 5C tank, close the sea chest valve (outboard
side) and complete the filling operation. Take care to avoid closing first the upstream valves, such as
the tank valves .

Sea chest valve (outboard side, adjusting


V191
valve)

Close

5) Valve lineup (2)


Shift the washing water from the 5C tank to the slop tank using the cargo pump.

No. 2 COP suction valve

V122

Open

Deck master valve

V322

Open

Crossover valve

V331,V332

Open

Direct filling valve

V311

Open

Tank main valve of slop tank

V274

Open

Common line valve

V152

Close

Sea chest valve (inboard side)

V192

Close

6) Priming
Open the tank valve and pass sea water into the pump. When the pump is full of sea water, slightly
open the delivery valve and perform priming.

5C tank valve

V252

Open

No. 2 COP delivery valve

V123

Slightly
open

7) Close the cargo pump delivery valve and start the pump. Then slowly open the delivery valve, and
shift the washing water in the 5C tank to the slop tank.
2.4 Filling sea water from the sea using pump
(Refer to "Line Diagram" in Fig. G-3-3 of P2-70 and "Line Diagram" in Fig. G-3-4 of P2-71 in
the "Documents Section.)
(Gass free) 3- 5
2002/10 (Ver.1)

1) Station a look-out carrying a portable transceiver near the overboard sea chest to monitor the sea
water level and to ensure a sound monitoring system.
2) Valve lineup (1)

SLOP (P) tank high suction valve

V173

Open

Common line valve

V154

Open

Sea chest valve (inboard side)

V192

Open

Take adequate care to configure the line from the overboard sea chest valve to the initial filling tank
such that the sea water does not flow in the reverse direction by the shortest distance.
3) Start of water filling

Sea chest valve (outboard side, adjusting


V191
valve)

Open

Suction line

V121, V122

Open

Riser common valve

V114, V124

Open

Deck main line master valve

V321, V322, V333

Open

Crossover valve

V331, V332, V333

Open

Return line to 5C

V144, V174, V176, V182

Open

Gradually open the overboard sea chest valve (avoid opening it suddenly) after confirming that all the
valves in the filling line including valves of the tank to be filled are open and start filling the water.
4) Preparations for tank cleaning pump and valve lineup (2)
After the flow from the sea chest to the SLOP (P) tank is established, make preparations for starting
the tank cleaning pump.
Monitor the balance between the water level in the SLOP (P) tank and the sea water level. As the flow
is established, start the tank cleaning pump and change over the line.

Riser common valve


Riser master valve
ODM line bypass valve
ODM re-circulation valve

V146
V195
V197
V196

Open
Open
Open
Open

Tank cleaning pump suction valve

V143

Open

5) Start the tank cleaning pump.


6) When the tank cleaning pump has been started and is ready for use, check the governor.
7) Gradually open the tank cleaning pump delivery valve. In this case, adjust the pump rpm such that
the pump delivery pressure becomes 0.4 Mpa to 0.5 Mpa.

Tank cleaning pump delivery valve

V145

Open

8) When the flow from the tank cleaning pump is established, close the line through which water was
being filled by gravity from the sea chest, while carefully monitoring the suction pressure.
(Gass free) 3- 6
2002/10 (Ver.1)

SLOP (P) tank high suction valve

V173

Close

9) Completion of water filling


When the expected volume is reached, fully close the delivery valve while reducing the rpm of the
tank cleaning pump.

SLOP (P) tank high suction valve

V173

Close

10) Stop the tank cleaning pump and close the sea chest valve. At this stage, make sure that you close
from the outboard side.

2.5

Sea chest valve (outboard side)

V191

Close

Sea chest valve (inboard side)

V192

Close

Filling water by gravity from the ballast tank

(Refer to "Line Diagram" in Fig. G-3-5 of P2-72 in the "Documents Section.)


1) Fit the spool piece that connects the ballast line and the cargo line.
2) Valve lineup
Fill washing water from the ballast tank with a high water level (advisable to select tank on forward
side considering the trim) to the slop tank through the spool piece.
The hatch cover of the ballast tank at the source should be open during the valve lineup.

SLOP (P) tank stripping valve

V162

Open

Common line stripping master valve

V163

Open

Common line valve

V151

Open

Cargo ballast connection valve (cargo tank side) V551

Open

3) Open the valve in the ballast tank used for washing water, fill the ballast line with sea water, and
apply pressure. Station a person beforehand to monitor the ballast water surface of the said ballast
tank.
4) Passing water through the cargo line

Cargo ballast connection valve (ballast tank


V550
side)

Open

Gradually open the cargo ballast connection valve and allow sea water to pass through. To be prepared
for emergencies, station a worker near the valve until the filling operation is completed.
Always monitor the water level in the ballast tank at the source from the cargo control room and
confirm that reverse flow does not occur.
5) When the estimated volume is reached, close the cargo ballast connection valve (ballast tank side)
and finish the filling operation. Note that you should take care to close the cargo ballast connection
valve (on the ballast tank side) first, otherwise oil may flow back to the ballast line.
(Gass free) 3- 7
2002/10 (Ver.1)

Cargo ballast connection valve (ballast tank


V550
side)

Close

(Gass free) 3- 8
2002/10 (Ver.1)

Heating of washing water


3.1

Heating using heating coils

Follow the procedure given below for heating the water using heating coils.
1) Open all the valves of the branch pipes.
2) Keep the steam supply valve slightly open.
3) Drain out the contents.
4) Gradually open the steam supply valve until it is fully open.
5) Wait until the setting temperature is reached while confirming the temperature (remote indication is
normally displayed on the console of the COC).
6) When the setting temperature is reached, adjust the steam supply valve and maintain the setting
temperature.
The temperature of washing water decreases when tank washing is started because the unheated washing water
on the secondary slop tank side circulates. Accordingly, the setting temperature should be maintained by
continuing to heat using the heating coils.

3.2

Heating using tank cleaning heater

Maintain the tank washing pressure at a constant level and ensure that the same quantity of water flows
into the heater at all times while the tank cleaning heater is being used. This is to prevent abnormalities
such as overheating that may occur when the flow rate of water through the heater changes. Take
particular care when you change over the washing water tank.
The cleaning records in recent days show a trend of not using the said heater. Moreover, newly-built VLCC tankers
are not being provided with heaters.

(Gass free) 3- 9
2002/10 (Ver.1)

4.

Rough washing of cargo line and cargo pump


Rough washing of cargo line and cargo pump should be implemented taking the precautions mentioned
below.
1) Adequate flow should be maintained for washing each line so that washing can be performed
efficiently in a short period of time.
2) Before changing over the line, reduce the pump rpm to minimum and close the pump delivery
valve.
3) Make sure that the oil in the U-shaped tube of the surface valve is replaced by sea water (using the
fire extinguishing line or by other means).

(Gass free) 3- 10
2002/10 (Ver.1)

5. Line washing and valve flushing


Perform line washing and valve flushing taking the precautions mentioned below.
1) Perform valve flushing by opening/closing all the valves 2 to 3 times during line washing.
2) To shorten the tank stripping time after washing, restrict the flushing of washing water to locations
other than the slop tank to a minimum.

(Gass free) 3- 11
2002/10 (Ver.1)

6.

Tank washing work


6.1

Precautions during the work

For details of the work procedure for valve opening/closing and so on, please refer to 2. Implementing
crude oil washing work of P4-4 in the Discharging Section. Consider the points below related to work
implementation.
1) The oxygen concentration in the tanks atmosphere should always be less than 8% during the tank
washing work.
2) Consider the washing water stripping efficiency and adjust the ballast such that the optimum ships
attitude (trim greater than 6 m, heel of about 1 to 2 degrees) is maintained.
3) Perform washing speed adjustments (refer to the instruction manual of the COW machine provided
on board each ship) in parallel, if necessary.
4) If defeat of stripping capacity is initiated due to ship motions in rough seas, measures to raise the
stripping efficiency may be considered, such as suspending tank washing at each stage temporarily
to set adequate stripping time, or using only a few washing machines at the aft part of the tank and
removing the sludge near the bell mouth at the final stage of washing.
5) After the washing with fixed washing machine is completed, inspect the shadow areas in the tank.
If sludge and oil have accumulated, wash using the portable washing machine.
Note that some portable machines may be provided with hoses of short length and the washing water may not
be delivered up to the desired locations.

6.2

Precautions when using the tank cleaning heater

When performing hot water washing of tank using the tank cleaning heater, a constant flow of sea
water should be passed through so as to prevent overheating of the tank cleaning heater during the
washing work. For this reason, personnel should be stationed at the release valve of the slop tank when
the washing tank is to be changed over or when the tank washing is to be suspended temporarily so that
the associated valves can be closed or opened carefully, as required. Two procedures are available for
opening/closing the release valve, as given below.
1) While confirming that a steady flow rate is maintained, open/close the release valve by
opening/closing washing machine valves one by one.
2) When washing tank after tank continuously, slightly open the release valve, then open the washing
machine valve of the next tank, close the washing machine valve of the tank in which the washing
has been completed. Proceed with the work in this way carefully, one tank after another.
If there is a mistake even in one step of this series of operations, it may lead to damage to the tank
cleaning heater. Therefore, all steps of the procedure should be thoroughly explained at the meeting
before the work so that workers can perform the work skillfully.

(Gass free) 3- 12
2002/10 (Ver.1)

7.

HC gas purging

(Refer to Fig.4-1(A) ,Fig.4-1(B) of P1-12 and Fig.4-2 ,Fig.4-3 of P1-13 in the Discharging
Section)

7.1

Precautions during parallel operation of IG fans

Take adequate precautions during parallel operation in relation to the points given below.
1) Change in tank pressure
2) Allowable gas flow rate in the vent line
3) Boiler load
4) O2 concentration of supplied inert gas (maintained below 8%)

7.2

Precautions during work

The environment above deck becomes extremely dangerous because flammable and toxic HC gas is
discharged to the atmosphere from the vent riser. Accordingly, special care should be taken during HC
gas purging work, such as control of bare flames (including static electricity, lightning, etc.), ventilation
controls in accommodation spaces, and flow of air above deck (wind speed and wind intensity). SMS
regulations related to safety and prevention of oil pollution should be followed and the items below
should be implemented.
1) Restrictions on smoking and use of flames
Designate smoking places, take measures against static electricity and sources of ignition, such as
soot from the smokestack and lightning bolt.
2) Preparations for fire extinguishing equipment and rescue appliances
Keep ready fire extinguishing hoses and portable fire extinguishers so that they can be immediately
used when required. Keep ready equipment that can be used in an emergency such as breathing
apparatus, spare air cylinders, lifelines and oxygen resuscitation equipment.
3) Ventilation control of accommodation spaces
Prohibit the opening of all passage access openings and other openings in accommodation spaces.
Close mechanical vent intake openings, use internal circulation system and prevent the entry of
petroleum gases. Gases that are harmful to the human body are discharged from the cargo tanks.
Thus, ventilation controls within accommodation spaces should be continued even during the
airing operation.
4) Control of access to enclosed spaces
Perform gas detection before entering enclosed spaces for internal inspection of tank, station the
required personnel and continue with the ventilation even during the access, in accordance with
established procedures. Workers should never enter enclosed spaces for which access is not
permitted.
5) Appropriate pressure control of cargo tank
During water filling/discharging operations to/from cargo tanks, check whether the watertight
hatches and manholes are open and adopt measures to prevent damage to tanks.
6) Controlling the environment in the cargo tank
Confirm that the oxygen concentration in the tank environment is maintained below 8% during the
tank washing work.
7) Perform safety checks periodically based on the Safety Check List.
8) Check that the scupper plugs on upper deck are closed.
9) Make preparations (to check quantity) for materials required for oil removal.

(Gass free) 3- 13
2002/10 (Ver.1)

8.

Airing
8.1

Precautions before airing

Perform the tasks below before implementing the airing work.


1) Inserting blind plates
Before implementing the airing work, insert blind plates in the IG branch lines of tanks to be aired
so that they can be completely isolated from tanks that are filled with inert gas.
2) Closing and confirming closure of valves in tank
Confirm that the tank main valve and the tank stripping valve in the tank are fully closed. Affix
sealing tape on the valve switches on the CCR console so that no careless mistakes are made and
gases do not enter the airing tank.
3) Double-shutting valves
Wherever possible, double-shut valves in the tanks.

(Gass free) 3- 14
2002/10 (Ver.1)

9.

Settling and discharging water


9.1

Work procedure
Perform the work of settling and discharging water by the procedure described below.
1) After the cleaning of all tanks except the slop tank is completed, allow the slop water in the primary
and secondary slop tanks to settle.
2) Make preparations to discharge water from the slop during the settling operation.
3) Perform the first discharging operation. (Cut down the settling time and discharge the water from
the slop.
4) Collect all the slop water in the primary slop tank.
5) Wash the secondary slop tank which has become empty with the collected slop water.
6) Allow the primary slop to settle.
7) Perform the second discharging operation.
8) Repeat 6) and 7) above to perform settling and discharging operations two to three times.

9.2

Preparations for discharging water from slop

Before discharging water, make the preparations and perform the checks mentioned below.
1) Preparations of the IG system
During the discharging of water, inert gas needs to be supplied to the relevant tank, therefore, make
preparations of the IG system.
2) Preparations of the ODM equipment
If the sampling line and overboard line are contaminated, oil concentration cannot be measured
accurately. The ODM drain valve opens automatically to the slop tank simultaneously with the start
of the water discharging operation, which may destroy the separated layers of oil and water due to
settling. To avoid this situation, the discharging line should be washed beforehand. (See 6-2 Line
diagram of the Documents Section.)
3) Checking the blind plates in the overboard lines
Check that the blind plates have been removed.
4) Studying the condition of separation of oil and water
Measure the overall ullage of slop water and the ullage of the oil-water interface using MMC.
Calculate the remaining quantity of water and the oil quantity to know the condition of separation
of oil and water.

9.3

First discharging operation (by TCP)

(Refer to "Line Diagram" in Fig. G-3-6 of P2-73 in the "Documents Section.)


1) Use the normal tank cleaning pump and start discharging at a low rate during the first discharging
operation.
2) Draw out the sea water from the sea chest with TCP and check the working condition of ODM
while discharging the sea water from the sea valve.
3) Open the high suction valve of the secondary slop tank to start discharging water. Stabilize the oil
concentration (ppm) using the control monitor of the ODM equipment while throttling the sea chest
valve.
4) Fully close the sea chest valve and gradually raise the rate to the expected discharging rate.
5) While carefully noting the ullage, change over from high suction to main suction.
6) At the final state of the discharging operation, the oil concentration of the discharged water starts
becoming unstable. When this tendency is observed, decrease the discharge rate. (Take sea water
from the sea chest and reduce the instantaneous discharge rate.)
7) When discharging is completed, transfer the water remaining in the secondary slop tank to the
primary slop tank.

(Gass free) 3- 15
2002/10 (Ver.1)

9.4

Secondary slop tank washing

After the first discharge operation is completed, transfer the washing water remaining in the secondary
slop tank to the primary slop tank. Perform cleaning of the secondary slop tank using this collected
washing water.
Perform the washing of the primary slop tank after discharging the slop to the barge at the anchorage
before dry-docking.

9.5

Discharging of water for the second time and later (by stripping pump)

(Refer to "Line Diagram" in Fig. G-3-7 of P2-74 in the "Documents Section.)


After the second time and later, discharge the water from the slop carefully using the stripping pump. If
a small quantity of slop water is forcibly discharged, the oil concentration rises, the drain valve opens,
the separated oil and water layers are destroyed (become mixed) and once again settling is required,
resulting in considerable waste of time and money.
Although the final volume of slop water remaining in VLCC class vessels may vary depending on conditions such
as settling time and ship motions, it is generally about 180 to 220 m3.

9.6

Precautions

9.6.1 Settling
The precautions below should be adopted during the settling operation.
1) Although the washing water is heated during tank washing and its temperature maintained at 50 to
60 degrees, stop the heating beforehand during the settling operation so that convection of the
washing water does not occur, and maintain its temperature at 45 to 55 degrees.
2) Avoid ship motions as far as possible.
9.6.2 Discharging water from slop
During the discharge of water from slop, take the precautions given below.
1) Station a look-out for monitoring the sea water surface near the shell overboard discharge opening.
Strive to prevent pollution of the sea by monitoring the oil concentration and visually checking the
discharge condition.
2) Do not forget to check the oil content of the discharged water by appropriately sampling the water
from the pump air bleed cock in addition to the ODM equipment.
3) If the level of liquid in the slop tank is adequately high from the tank bottom, discharge the water
using the suction at the high location in the slop tank, and take care not to suck in the oily sludge
that has settled at the bottom of the tank.

(Gass free) 3- 16
2002/10 (Ver.1)

10.
10.1

Final line washing

Precautions

Precautions related to the implementation of final line washing are as given below.
1) If the excessive time is taken up for final line washing and the amount of water drawn in is
considerable, the settling and water discharging operations to be implemented subsequently will
require considerable time. Therefore, perform the final line washing work efficiently.
2) After washing is completed, strip the line thoroughly so that no water remains in the pump and in
the line.
3) Check the finished condition of final line washing by confirming the drain line and air bleed cock
of each manifold. If necessary, take appropriate measures to ensure proper finishing..
4) Collect all the bilge generated in the pump room and other locations in the primary slop tank so
that it can be discharged to shore together with the slop during slop removal.

(Gass free) 3- 17
2002/10 (Ver.1)

11.

Sludge removal
11.1

Communications

The sub-contractor for removing /recovering sludge and slop to the anchorage is to be arranged by the
ship owner or the ship management company. Communications with the sub-contractor will be
specified, but in general, the items listed below are necessary. These items should be studied
beforehand.
1) ETA at the slop removal anchorage
2) Estimate amount of sludge in tons in each tank (or total amount)
3) Amount of slop carried, estimate washing water quantity for slop tank and line washing quantity
4) Details of previously-loaded cargo
5) Indication of side of slop barge in contact with berth
6) Bore of slop removal line and specifications of connecting flanges

11.2

Preparatory work

1) Continuing the airing work


Continue airing the spaces even after the sludge gangs board the ship, so that they can start the
work quickly. Before starting the work, the ship should issue authorization for access in accordance
with the established procedures for access to enclosed spaces.
2) Confirming sub-contractor arrangements
Confirm that an adequate number of workers for sludge removal, adequate number of slop vessels,
work boats and work equipment and accessories for sludge removal are kept ready and available
for the estimated working days.
3) Ensuring shipboard security
Ensure that measures against robbery are taken before the workers board the ship. These measures
should include locking the cabins and stores in accommodation spaces, deck stores and lifeboat
equipment and provisions boxes, etc. After the work is completed, confirm that all workers have
disembarked and none remain on board the ship.
4) Measures to prevent oil pollution
Before starting the work, hold detailed discussions on measures to prevent oil pollution and the
work plan (including condition of accumulation of sludge in each tank, areas where workers are
prohibited from entering) with the sub-contractors supervisor. This is to ensure the ships crew and
the workers become thoroughly familiar with the work plan so that no oil pollution accidents occur,
such as leakage of oil from sludge bags to the ships sides since they are stacked on the deck and
work is being performed within the port premises.

11.3

Precautions

Take the precautions mentioned below during sludge removal.


1) Ensure that sludge storage bags are stacked at the appropriate locations on deck.
2) Adopt measures to prevent oil pollution ensuring that the oily sludge does not leak overboard due
to the effect of rainfall.
3) Confirm that continuous ventilation is provided during work in the tank and ensure that the
environment in the tank is checked periodically using gas detectors.
4) Ensure that measures have been adopted to prevent falls into open tank hatches and portable man
holes .
5) Patrol the deck periodically during the sludge removal work.
6) Sequentially inspect the internal parts of tanks from which sludge has been removed. If necessary,
request the workers to finish up the work.
7) After the work is completed, ensure that the workers meticulously clean and remove oil sticking to
the upper decks and to other structures.
(Gass free) 3- 18
2002/10 (Ver.1)

12.

Slop removal

12.1 Work procedure


(Refer to "Line Diagram" in Fig. G-3-8 of P2-75 in the "Documents Section.)
Perform slop removal according to the procedure described below.
1) After the slop barge berths, connect the transfer hose to the ships line (generally MARPOL LINE).
2) Start inerting in accordance with the requirements (Part D60, D62) of Chapter 2 of SOLAS-II.
3) Start the stripping pump and transfer the slop to the barge.

12.2

Precautions

Take the precautions mentioned below during slop removal.


1) Always monitor the water level during the slop transfer and strive to prevent pollution of the sea.
2) When gas-freeing the slop tank, carefully monitor the wind direction and the wind force. If gas is
likely to accumulate above deck, consider suspending the gas-freeing work temporarily.
3) Cut off the tank from which slop is removed and other tanks using two ore more valves.
4) While the barge is being berthed, monitor the condition of the mooring ropes and the transfer hose.
5) A considerable amount of sludge collected from various tanks accumulate in the primary slop tank
during slop removal. The strainer in the stripping pump is likely to clog causing the pump to stop.
Keep ready the spare strainer (if not available, arrange to procure it), chain block and tools so that
the strainer replacement work can be performed beforehand.
To prevent clogging of the strainer, open up the strainer and wash it before starting the transfer of slop water.

(Gass free) 3- 19
2002/10 (Ver.1)

13.

Primary slop tank washing and HC gas purging


13.1

Precautions

Take the precautions mentioned below related to the work implementation.


1) Measure the oxygen concentration in the tank before washing the tank and confirm that it is below
8%.
2) To prevent the defeat of stripping capacity during tank washing, consider suspending the tank
washing operation temporarily at each stage and perform stripping.
Washing becomes more effective if it is implemented while passing steam through the heating coil. During the
washing operation, slightly open the steam supply valve, fully open all the branch pipes, and heat to such an
extent that the coils do not get overheated.

3) The construction within the primary slop tank differs from that of other tanks since heating coils
are installed at the bottom of the primary slop tank. Accordingly, the bottom washing should be
performed with additional care.
4) The strainer of the stripping pump used for stripping the tank clogs easily because a large amount
of sludge accumulates in the tank. Preparations should be made to allow for replacement with a
spare strainer or for opening up and cleaning the strainer.
5) Perform HC gas purging in parallel with tank washing. Measures should be considered such as
temporary suspension of work considering the effect of discharged gas on sludge removal workers
of other tanks.

(Gass free) 3- 20
2002/10 (Ver.1)

14.

Gas-freeing and sludge removal of primary slop tank


14.1

Precautions

1) Confirm that the HC gas concentration in the tank atmosphere is below 2% by volume and then
start airing the tank.
2) During the airing of the same tank, sludge is being removed from other tanks.
If the discharged gas has accumulated on the deck, suspend the work temporarily to prevent the
adverse affects of the gas o the human body.

(Gass free) 3- 21
2002/10 (Ver.1)

15.

Final line stripping


15.1

Work procedure

Perform the final line stripping by the procedure described below.


1) Using the stripping pump and drawing sea water from the sea chest, wash the piping on the
discharge side of the stripping pump and the MARPOL line on deck. At this stage, the stripping
suction line of the primary slop tank is contaminated. Therefore, pass the washing water through
this line.
(Refer to "Line Diagram" in Fig. G-3-9 of P2-76 in the "Documents Section.)
2) After washing the MARPOL line, close the sea chest valve. Strip the water remaining in all the
lines and finish the washing work.

(Gass free) 3- 22
2002/10 (Ver.1)

16.

Gas-free certificate
16.1

Precautions

General precautions for gas inspection when the ship is to dry-dock at Singapore Dock are given below.
Note that these precautions may vary depending on the location, and should be confirmed beforehand.
1) Even if the sludge removal has not been completed, gas inspection can be received.
2) The spaces in which gas inspection is to be carried out include cargo tanks, ballast tanks, fuel oil
tanks, void spaces and cargo lines. The access to these spaces should always be kept open. Open up
the blind plate of the manifold and keep all the valves in the open condition.
3) The allowable gas concentration during inspection should be less than 3% LEL. However, when
the F.O . tank contains fuel oil, then this value should be taken as less than 30%.
4) A ships officer should be present during the gas inspection.
5) If the hydrostatic pressure test has been carried out during the periodic survey, more than half the
cargo tank would have been filled with water. In this condition, the gas inspection cannot be
performed.

(Gass free) 3- 23
2002/10 (Ver.1)

Line Diagram

Title

Page

G-3-1

Filling sea water (from the sea chest)by gravity (1/2)

2-25

G-3-2

Filling sea water (from the sea chest)by gravity (2/2)

2-26

G-3-3

Filling sea water from the sea using pump (1/2)

2-27

G-3-4

Filling sea water from the sea using pump (2/2)

2-28

G-3-5

Filling water by gravity from the ballast tank

2-29

G-3-6

First discharging operation (by TCP)

2-30

G-3-7

Discharging of water for the second time and later (by stripping
pump)

2-31

G-3-8

Slop removal

2-32

G-3-9

Final line stripping

2-33

(Gass free) 3- 24
2002/10 (Ver.1)

(Gass free) 3- 25
2002/10 (Ver.1)

(Gass free) 3- 26
2002/10 (Ver.1)

(Gass free) 3- 27
2002/10 (Ver.1)

(Gass free) 3- 28
2002/10 (Ver.1)

(Gass free) 3- 29
2002/10 (Ver.1)

(Gass free) 3- 30
2002/10 (Ver.1)

(Gass free) 3- 31
2002/10 (Ver.1)

(Gass free) 3- 32
2002/10 (Ver.1)

(Gass free) 3- 33
2002/10 (Ver.1)

Potrebbero piacerti anche