REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4

S.
No
.
1.

2.

Clause
Reference

Clause description in the Document

Pg. No.102 ADVANCES


Clause 34 34.1 Mobilisation advance in the form of Equipment advance (Plant and
of Section
machinery) shall be paid up to 10% of Contract price, payable in two
3.
equal instalments. The first instalment shall be paid after mobilisation
Description
of required equipment at site limited to 90% of assessed cost of
of Works
machinery and next instalment shall be paid after satisfactory utilisation
& Other
of earlier advance.
conditions 34.2 Mobilisation advance shall be paid at SBI PLR + 2%. P.a (as on date of
payment) interest rate at the discretion of the employer and on
submission of unconditional Bank Guarantee(s) for the equivalent
amount from a Scheduled Bank in the format provided in Appendix.
34.3 Mobilisation advance shall be repaid with percentage deductions from
the interim payments certified by the Engineer or his nominee under the
Contract. Recovery will start when 15% of the work is executed and the
recovery of total advance should be completed by the time 80% of the
original contract work is executed.
34.4 The mobilisation advance shall be recovered in 15 equal instalments.
The contractor can submit multiple BGs so as to always cover the
recoverable advance.
34.5 The interest at the rate stated above shall be charged on the amount of
advance from the actual date of payment to the actual date of recovery
of the instalments. The interest accrued up to the end of the previous
month shall be recovered from each interim certificate along with
recovery of each instalment. In case the interim certificate is not
sufficient to recover the interest and instalment, the statutory levies and
retention money shall be adjusted first. Out of the balance payable, the
interest due will be appropriated first and the balance towards
instalment.
34.6 The equipment against which the advance is given shall not be allowed
to be withdrawn from site until the recovery of instalment is made
Page No.24 Bid Security (Earnest Money Deposit EMD)
of Section
1, ITB
The EMD of Rs. 20,00,000/- (Rupees twenty lakhs only) shall be paid by
demand draft/Pay Order/Bankers Cheques in the name of Kamarajar
Port Limited from any Nationalized/Scheduled Bank (except
Cooperative Banks) encashable at Chennai.Balance EMD amount of Rs.
2,55,79,820/- (Rupees Two crore Fifty Five Lakhs Seventy Nine Thousand
Eight Hundred and Twenty only) in the form of Bank Guarantee shall be
submitted to KPLin favour of Kamarajar Port Limited issued by any
Nationalized/Scheduled Bank (except Cooperative Banks) encashable at
Chennai.

Bidders queries / Clarifications sought

Addendum No. 2

Clarifications by KPL

The Bidder request the employer to modify the referred provision as follows:
Tender conditions Prevail.
34.1 Mobilisation advanceshall be paid up to 10% of Contract price, payable in two
equal instalments. The first instalment shall be paid after mobilisation of SBI PLR to be read as SBI Base
required resources at site and next instalment shall be paid after satisfactory Rate
utilisation of earlier advance.
34.2 Mobilisation advance shall be paid as interest free advance for mobilization of
contractors resources to site against submission of unconditional Bank
Guarantee(s) for the equivalent amount from a Scheduled Bank in the format
provided in Appendix.
34.3 Mobilisation advance shall be repaid with percentage deductions from the
interim payments certified by the Engineer or his nominee under the Contract.
Recovery will start when 15% of the work is executed and the recovery of total
advance should be completed by the time 90% of the original contract work is
executed.
34.4 The mobilisation advance shall be recovered in 15 equal instalments. The
contractor can submit multiple BGs so as to always cover the recoverable
advance.

The Bidder requests the Employer to modify the referred provision to allow the Modified as The EMD of Rs.
bidder to submit Bid Security in the form of Bank Guarantee only.
20,00,000/- (Rupees twenty lakhs only)
Please Confirm.
shall be paid by demand draft/Pay
Order/Bankers Cheques in the name of
Kamarajar Port Limited from any
Nationalized Bank encashable at
Chennai.Balance EMD amount of Rs.
2,55,79,820/- (Rupees Two crore Fifty
Five Lakhs Seventy Nine Thousand
Eight Hundred and Twenty only) in the
form of Bank Guarantee shall be
submitted to KPLin favour of
Kamarajar Port Limited issued by
any Nationalized Bank encashable at
Chennai.

Page 1 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
3.

Page No.
31
Clause
No30 of
Section 1:
ITB

4.

Page No.
39
Clause
No3.5 of
Section 2:
General
Condition
of Contract

5.

Page No.
40 Clause
No. 5 of
Section 2:
General
Condition
of Contract

6.

Page No.
42 Clause
No. 6.4 of
Section 2:
General
Condition
of Contract

Advance Payment
KPL shall not pay any Advances to the contractor.

In view of above in Sl.No. 1, please delete the referred provision from tender Modified as KPL shall not pay any
conditions.
Advances to the contractor except
Mobilization advance as per clause 34
of section 3.

The Bidder requests the Employer to modify the referred clause as follows
Engineer to Act Impartially
Wherever, under the contract, the Engineer is required to exercise his Engineer to Act Impartially:
discretion by:
Wherever, under the Contract, the Engineer.............................
a) ....................................
a) giving his decision, opinion or consent, or
b) ...........................
b) expressing his satisfaction or approval, or
c) ....................................
c) determining value, or
d) ...............................................
d) otherwise taking action which may affect the rights and obligations of the He shall exercise such discretion impartially within the terms of the contract and
Employer or the contractor.
having regard to all the circumstances. Any such decisions, opinion, consent,
expressing of satisfaction or approval, determination of value may be opened up,
He shall exercise such discretion impartially within the terms of the contract reviewed or revised.
and having regard to all the circumstances. Any such decisions, opinion, The Contractor shall be entitle to request the Employer directly to open the
consent, expressing of satisfaction, or approval, determination of value or matter for Employer's review and revision.
action may be opened up, reviewed or revised
Extent of contract:
The Bidder requests the Employer to provide the schedule of site possession in the
The contract comprises the manufacture, supply, construction, completion event site will be handed over to the Contractor in a phased manner.
andmaintenance of the works and excepting so far as the contract otherwise
the provisions of all labour, materials, constructional plant, temporary or
permanent nature required in and for such construction, completion and
maintenance so far as the necessity for providing the same in specified in or
reasonably to be inferred from the contract. The entire site over which the
works are to be executed will be given possession immediately after the
work order. In such cases where it is possible to give possession in piece
meal or in parts in a phased manner, the period of completion of work shall
vary depending upon the date of handing over the site to the contractor.
Custody of Drawings:
The Engineer shall have full power and authority to supply to the
contractor, from time to time during the progress of the works such further
Drawings and instructions as shall be necessary for the purpose of the
proper and adequate execution and completion of the works. Such
supplementary drawings, issued / approved during the currency of contract
will also form part of the contract and the Contractor shall carry out and be
bound by the same

Addendum No. 2

Tender conditions Prevail.

Except electrical substation and North


West corner of the berth and retaining
structure junction, entire area will be
handed over at the time of taken over of
site by the contractor.

The electrical substation and North


West corner of the berth and retaining
structure junction, entire area will be
handed over within a maximum period
of 9 months from the date of taken over
of site by the contractor.
The Bidder requests the Employer to modify the referred clause considering that the Tender conditions Prevail.
issuance of Good for Construction drawings shall be as per the mutually agreed time
schedule between the Employer and Contractor. However, any delay due to such
drawings shall entitle the Contractor to an extension of time for completion under
the Clause. 31 [Extension of Time] and payment of any such cost of idling of
Contractor's resources.

Page 2 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
7.

Page.
No.58
Clause No.
31 of
Section 2:
General
Condition
of Contract

EXTENSION OF TIME
The contractor shall commence the works on site within the period named
in the tender after the receipt by him of on order in writing to this effect
from the Engineer and shall proceed with the same with due expedition and
without delay except as may be expressly sanctioned or ordered by the
Engineer or be wholly beyond the control of the contractor

8.

Page.
No.60
Clause No.
35 of
Section 2:
General
Condition
of Contract

LIQUIDATED DAMAGES FOR DELAY IN COMPENSATION


If the contractor fails to complete the work in all respects within the time
specified or within the extended time that may be allowed by the Engineer
as per Clause 31, the contractor shall pay or allow to the Port a sum
equivalent to % (half percent) per week or part thereof of the total value
of the contract subject to a maximum of 10% of the total value of contract
as liquidated and ascertained damages and not by way of penalty, for every
week or part thereof beyond the said period or extended period as the case
may be during which the work shall remain unfinished. Such damages will
be deducted from any moneys due or to become due to the contractor. The
payment of such damages does not relieve the contractor of his obligations
to complete the works or from any other of his obligations or liabilities
under this contract.
SITE INFORMATION AND CONDITIONS
The berth construction work has to be carried out in Southern side of the
proposed inner dock Basin. The berth structure construction has to be
carried out partly in water and remaining part in land. The Hardening work
shall be carried out in the area between CB3 diaphragm wall rear side and
existing conveyor.

9.

Addendum No. 2

The bidders requests for incorporation of suitable provision in the tender document Tender conditions Prevail.
where the contractor shall be entitled for payment of additional cost incurred by
them in the event of time for completion of the work extended due to reasons
described as follows.
a. Delay due to issuance of Construction drawing
b. Delay due to providing suitable Contractors area for setting up their site
establishment together with Labour Colony
c. Exceptionally adverse climatic condition
d. Delay in possession of site
e. Delay due to any suspension of work instructed by the Engineer or any suspension
of work for which Contractor is entitled
f. the amount or nature of extra or additional work,
g. any cause of delay referred to in these Conditions, any delay, impediment or
prevention by the Employer, or
h. other special circumstances which may occur, other than through a default of or
breach of contract by the Contractor or for which he is responsible,
being such as fairly to entitle the Contractor to an extension of the Time for
Completion of the Works, or any Section or part thereof, the Engineer shall, after
due consultation with the Employer and the Contractor, determine the amount of
such extension and shall notify the Contractor accordingly, with a copy to the
Employer.
The Bidder requests the Employer for modification of the referred Clause as follows Tender conditions Prevail.
If the contractor fails to complete the work in all respects within the time specified
or within the extended time that may be allowed by the Engineer as per Clause 31,
the contractor shall pay or allow to the Port a sum equivalent to % (One-Fourth
percent) per week or part thereof of the total value of the contract subject to a
maximum of 5% of the total value of contract......................................
The bidder also understands that the liquidated damages shall be imposable only on
delay in achievement of overall completion of the work i.e. 24 month together with
approved extension under the contract.
Please Confirm.

Page.
An area of about 25,000 sq.m within the
No.85
The bidder requests the Employer for allotment of an area not less than 5000 sq.m radius of one (1) km shall be allotted to
Clause No.
for Contractor's site establishment and also request to specify the distance from the contractor free of cost for
2 of
proposed project location.
establishing site for the work for
Section
fabrication etc
3: General
Description
of Works There is an area available near the site of work for fabrication of liners,
& Other
reinforcement and batching plant for concrete mixing and pre-casting the
Conditions elements, site office, laboratory etc. No rental charges will be levied for the
working area spared to the contractor during the tenure of the contract
including extended period, if any granted.

Page 3 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
10.

11.

Page.
No.86
Clause No.
5 of
Section
3: General
Description
of Works
&
Other
Conditions
Page.
No.23
Clause No.
15
of
Section 1:
ITB

Addendum No. 2

Tax
The rates shall also include all taxes such as VAT, Income tax, service tax,
general tax and building and other construction workers welfare cess Act
1996 and the entire contractors obligations under the contract and all
matters and things necessary for the proper completion and maintenance
works

The Bidder understands that there shall be no exemption on Service Tax available The rate shall include all taxes.
and therefore service tax at input and output side to be included in their estimate.

Bid Validity:
Bids shall remain valid for a period not less than 120 days after the deadline
date for bid submission specified in Clause 19. A bid valid for a shorter
period shall be rejected by the Employer as non-responsive.

The Bidder requests to incorporate following condition under tender document


1) Bid validity shall be for 120 days. In the event the contract is not awarded within Tender conditions Prevail.
such time EMD shall be released, however if Employer requires the Contractor to
keep the bid valid and not release the EMD even after 120 days then the Contractor
shall be entitled to revise their rate and re-submit.

Accordingly the bidder understands that there shall be no exemption on LabourCess The rates shall include Cess as per the
available and therefore LabourCess at input and output side to be included in their applicable Laws / Act
estimate.
Please Confirm.

2) In the event work awarded within 120 days form the last date for tender Tender conditions Prevail.
and
submission and commencement of work delayed beyond 120 days, then the
DATE OF COMMENCEMENT AND COMPLETION OF WORK:
Contractor shall be entitled to revise their rate and Contract Price thereof which
Page.
The work shall be taken to have been commenced from the date on which Employer shall approve for payment within 15 days from Contractor's submission of
No.99
the contractor takes over the site or the twenty first (21st ) days of receipt of above.
Clause No. the letter of acceptance by the contractor, whichever is earlier and the
25
of contractor shall complete the works within Twenty Four(24) Months from
Section 3: this date.
Description
of Works
&
Other
Conditions

Page 4 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
12.

Page. No.
100 Clause
No. 29.2 of
Section 3:
Description
of Works
&
Other
Conditions

13.

Page. No.
103 Clause
No. 37 of
Section 3:
Description
of Works
&
Other
Conditions

14.

Page. No.
103 Clause
No. 38 of
Section 3:
Description
of Works
&
Other
Conditions

Addendum No. 2

The bidder requests the Employer to make the Electricity charges fixed for the entire Tender conditions Prevail.
contract duration.
Electrical power required by the contractor will be provided from the Please Confirm
However, the consumption charge
Substation to the extent that can be conveniently spared by the company
applicable at present is Rs. 11/- per unit.
from time to time. The KPL will provide the power in the grade of 3 phase,
440 volts.
1. The power point will be provided at the Substation or at the nearest
pillar box.
2. The contractor has to make his own arrangement for the cable required
to extend the power supply to the load point, energy meter of the rated
capacity, control switch and other safety devices.
3. The power cables shall be properly laid and the switch board shall be
erected as per the electricity rules and guidelines.
4. Power supply will be provided after the inspection of the installations
by the KPL Engineer.
5. Electrical safety regulations shall be strictly followed.
6. A caution deposit of Rs 300/ KVA of maximum demand to be paid
initially to Employer which is refundable after surrendering the power
supply . Each month Rs.300/ KVA of maximum demand charges plus
unit consumption charges of Rs.7/- per unit for the actual units
consumed plus Electricity Tax @ 5% will be collected on monthly
basis.
7. The above rates are subjected to change from time to time as and when
the TNGEDCO effects the tariff changes
The Bidder requests the Employer to allow the Contractor to submit Bank Guarantee Tender conditions Prevail.
RETENTION MONEY
Retention Money at 5% will be deducted from each running bill subject to a equivalent to 5% of the Contract Value in-lieu of cash retention. Such bank
maximum accumulation of 5% of the contract price. Retention money shall guarantee shall be valid until the release of final bill.
be refunded within 14 days from the date of payment of final bill. Balance Please confirm
performance security deposit in the form of Bank Guarantee shall be
returned immediately not later than 14 days of completion of defect liability
upon satisfactorily maintaining the works free from defects for a period of
12 months, pursuant to Clause 22 of this section. Notwithstanding the
provisions contained in clause 22 and 27 of this section, if during this
period of 12 months, any defects are notified which in the opinion of the
Engineer are due to bad materials used and/ or defective workmanship, the
contractor shall be required to carry out at the contractor's cost, such repairs
as the Engineer considers necessary or in the event of contractor failing to
do this within the notified time, the Engineer may arrange for such repairs
to be carried out and deduct the cost of such rectification of the defects from
the amount retained, without prejudice to the recovery of any amount that
may have been spent in excess of the deposit.
The bidder requests the Employer to modify the referred clause as follows.
Tender conditions Prevail.
ESCALATION
38.1 Compensation for escalation in the prices of materials, labour and 38. ESCALATION
POL, when due shall be worked out based on the following provisions:
38.1 Compensation for escalation in the prices of materials, labour and POL, when
38.2.1 The base date for working out such escalation shall be the last date due shall be worked out based on the following provisions:
on which tenders were stipulated to be received.
38.2.1 The base date for working out such escalation shall be 28 days prior to the
last date on which tenders were stipulated to be received.
Electricity Supply for Works:

Page 5 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
15.

16.

17.

18.

Addendum No. 2

Page. No.
106 Clause
No. 39.2 of
Section 3:
Description
of Works
&
Other
Conditions
Page. No.
110 Clause
No. 39.16
of Section
3:
Description
of Works
& Other
Conditions

NOTICE OF OPERATIONS
The contractor shall not carry out any operation without the consent in
writing of the Engineer, as the site is a part of the operational area.
Reasonable notice shall be given by the contractor to the Engineer in
advance

The Bidder requests for following information


1) Existing operation and type of occupancy
2) Existing traffic data in area of operation
3) Notice period for starting any Contractor's activity in such operational area.
Please provide.

The available data / information shall be


provided to the successful bidder at the
time of commencement of work.

EXISTING SERVICES
The contractor's attention is drawn to the possibility that there might be
existing underground or overhead services & service line inside and around
the port areas i.e., within the site of the proposed works. It is the contractor's
responsibility to work cautiously and carefully so that these are not
damaged. Any damage to the services shall be repaired and restored
immediately as directed by the Engineer without any extra cost. The
contractor is required to ascertain and allow in his cost for any rerouting of
the services that may be necessary for the due execution of the contract and
any claim resulting from his failure to do so will not be admitted The
Contractor's attention is drawn to the possibility that there might be existing
underground or overhead services & service line inside and around the port
areas etc.

The Bidder requests the Employer to provide available drawings of existing utilities
which is passing through the proposed project/site location. Also the bidder requests
for modify of the referred provision, in the event during execution of the work, the
Contractor encounters any utilities below ground and it requires any diversion
and/or protection from damage shall be done by the Contractor subject to following.
1) any additional time required for undertaking such activity shall entitle the
Contractor for extension of time for completion of work.
2) any additional cost of protection/diversion shall be reimbursed by the Employer
as per actual plus 20% basis.
Please Confirm.

Available data / drawings shall be


provided to the successful bidder at the
time of commencement of work. Except
for any re-routing, the cost of shifting of
any utilities shall be borne by KPL.

Page. No.
112 Clause
No. 39.18
of Section
3:
Description
of Works
& Other
Conditions
Page. No.
114 Clause
No. 39.27
of Section
3:
Description
of Works
& Other
Conditions

MAINTAINING UTILITY AND SERVICES


The contractor shall not damage, close or obstruct any utility areas, roads,
Port traffic or other property until permits thereof have been obtained. If
facilities are closed, obstructed, damaged or rendered unsafe by contractor's
operation, the contractor shall, at his own cost, make such repairs and
provide such temporary guards, lights and other signals or as necessary or
required for safety and as will be acceptable to the Engineer and / or the
Employer of the utility, highway, road or other property
It is difficult to foresee the impact of referred events and its implication during Tender conditions Prevail.
Interruptions of work and idle time charges
The contractor shall allow in his rates for any loss of working hours due to execution. Therefore the bidder requests for deletion of referred provision from the
weather, and shifting of plants and other equipment from one area to tender document for the purpose of competitive bidding.
another area depending upon the traffic operations or for maintenance.
Kindly confirm.

Any claim for idling of the contractor's plant and machinery or any other
inputs shall not be entertained by the Port for reasons whatsoever including
non-availability of working area and therefore the contractor may consider
all such events including the normal Port operations and submit their offer
accordingly. For the reasons stated or for any other reasons, no claim on
idle time charges shall be entertained by the Port
Page. No. The date on which a Cheque of payment is handed over to the contractor by The bidder requests the Employer to modify the referred provision, so that the Tender conditions Prevail.
69 Clause the Employer will be considered as the date of payment for all purposes. Contractor shall entitle to receive a reasonable compensation for any delay in
No. 45.3 of Delay in making such payments by the Employer due to exceptional payment beyond stipulated time for payment.
Section 2: circumstances shall not nullify or vitiate in any way or other, the conditions
General
of the contract and the contractor shall have no claim on this account. The
condition employer will not pay any interest on account of any delay in the payment
of
to the Contractor under any point of time and Contractor cannot prefer any
Contracts claim on this account
Page 6 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
19.

Page. No.
182, Clause
5 in Part
V,
Diaphragm
wall
specificatio
ns
of
Section 4:
Technical
specificatio
ns
of
Materials
and works.

20.

General

21.

General

22.

General

23.

General

24.

Page. No.
14 Clause
No. 1.1.1
of Section
1:ITB

The Bidder requests the Employer to provide the Soil investigation and/ or Sub-soil
data for better understanding of the ground conditions.
In the event the soil and sub-surface conditions actually encountered at Site be
substantially different from those provided in the Tender Documents including
tender data, background information etc., and the Contractor has incurred additional
The Contractor shall satisfy himself regarding subsoil conditions and the cost thereof, the Contract Price shall be adjusted accordingly with such amount of
underground water table. No claims for extra cost or time shall be additional cost. In such event Employer shall reimburse such additional cost to the
entertained on these grounds. The soil report included in this contract is Contractor based on contractor's actual cost +25% basis.
based on the site investigation carried out in this site. Factual report(s) of
site investigation(s) is available for the reference of the Contractor. The
Contractor may at his own cost and with the written approval of the
Engineer, conduct additional soil test if he so desires.
SITE CONDITIONS
The contractor prior to the submission of the tender is required and deemed
to have inspected the site and satisfied himself with regard to access, site
condition. The work shall be carried out on the basis of ground as found.

The report on geotechnical investigation carried out for the construction of


coal berths 3 and 4 is attached in Addendum No. IV. The information
provided shall be scrutinized by the bidder to make a clear understanding of
the ground and underground conditions exist at the site. It is the
responsibility of the contractor to conduct additional bore holes, if required
prior to starting of the pile and diaphragm wall works. No additional
payment or time extension will be entertained due to variation in
geotechnical strata during the execution of the work
Compensation for reasons not attributable to the Contractor
The bidder requests for incorporation of suitable provision in the tender document
where the contractor shall be entitled for payment of additional cost incurred by
them in the event of completion of time of the work extended due to reasons
described under Sl. No. 7. above
Secured Advance
The bidder requests the Employer to amend a suitable provision for payment of
secured advance:
Secured Advance shall be paid to the maximum of 5% of Contract Price.
(i) payment of secured material advance up to 75% of actual value against
submission of invoice along with monthly Running Account bill for nonperishable materials.
(ii) payment of secured advance up to 75% of actual value against submission
of invoice along with monthly running account bill for perishable materials and
also against submission of equivalent amount of Bank Guarantee.
(iii) recovery shall be commence from next running account bill.
(iv) no advance shall be paid after 80% of contract price paid to the contractor.
Fly Ash
The Bidder request the Employer to confirm whether use of Fly Ash allowed for
blending with Cement for Permanent Works. Please Confirm.
Crushed/Manufactured Sand
The Bidder request the Employer to clarify whether Crushed/Manufactured Sand
will be allowed to use in-lieu of River Sand. Since the river sand becomes scarcity
due to ban in quarrying by the state government.
Kindly Confirm.
Bidder requests the Employer to incorporate the following under tender conditions
Construction of Coal Berth No. 4:
(v) Dredging in front of the berth area will be executed by KPL by a 1.) Dredging activity shall be carried out as per the Programme agreed with
separate contract. It is expected that the soil below the coal berth deck to Contractor.
form a natural slope towards the basin. However, if the soil collapse did not 2.) Delay due to interface with dredging contractor shall entitle the Contractor for an
form slope, the same has to be removed by grab method from the deck prior extension of time for completion and any additional cost incurred by the Contractor
due to delay shall be reimbursed by the Employer at actual.
to forming the deck slab.

Page 7 of 22

Addendum No. 2
The available soil investigation data /
information is given in Addendum No.
3. However, the information provided
shall be scrutinized by the bidder to
make a clear understanding of the
ground and underground conditions
exist at the site. It is the responsibility of
the contractor to conduct additional bore
holes, if required prior to starting of the
pile and diaphragm wall works. No
additional payment or time extension
will be entertained due to variation in
geotechnical strata during the execution
of the work.

Not Acceptable

Not Acceptable

Not Acceptable
Not Acceptable

Tender conditions prevail.

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
25.

Sl. No. 5 of
BOQ No 1,
Foundation
for Berth
No.4,
Section 7

26.

Section 2,
Condition
of Contract

27.

Section 2,
Condition
of Contract

Reinforcement for Piles


Supplying, fabricating and placing of CRS Fe 500 grade steel for piles
reinforcement cage in piles including cutting, bending, welding, binding,
with binding wire, positioning of pile reinforcements from founding level
up to protection of reinforcement bars above pile cutoff level in to deck
beams with adequate lapping lengths all as per drawing, technical
specifications and including all labour, materials, tools transport, cage
lowering, equipment, fuel, etc., complete.

Addendum No. 2

Bidder understands that the referred provision for measurement of lapping, hooking Tender conditions prevail.
arrangements etc. shall also be applicable to the reinforcement items for all type of
structures as mentioned in Bill of Quantities.
Please Confirm

Note: Provision of authorized lapping, hooking arrangements, etc. as per the


approved bar bending schedule shall also be measured and paid under this
item.
Add New Clause - Limitation of Liability
The Bidder requests the Employer for incorporation of the following additional Not Acceptable
clause under referred section of the tender documents;
Neither party shall be liable to the other party for loss of use of any works, loss of
any contract or for any indirect or consequential loss or damage which may be
suffered by the other party in connection with the contract. The aggregate liability of
the Contractor to the Employer, under or in connection with the Contract shall not
exceed 25% of the Contract Price.
Add New Clause - Contractor's Entitlement to Terminate the Contract
The Bidder requests the Employer for incorporation of the following additional Not Acceptable
clause under referred section of the tender documents;
The Contractor shall be entitled to terminate the Contract if:
i) the Contractor does not receive the amount due within 42 days after the expiry of
the time stated in Clause 45.2 within which payment is to be made,
ii) the Employer substantially fails to perform his obligations under the contract,
iii) a prolonged suspension affects the whole of the works. In any of these events or
circumstances, the contractor may, upon giving 14 days notice to the Employer,
terminate the Contract. The contractor's election to terminate the contract shall not
prejudice any other rights of the contractor, under the contract or otherwise. After a
notice of termination under this Clause has taken effect, the Employer shall
promptly:
(a) return the Performance Security to the Contractor,
(b) pay the Contractor in accordance with Clause 23.6 [Payment if contract
terminated], and
(c) pay to the contractor the amount of any loss of profit or other lossor damage
sustained by the Contractor as a result of this termination.

Page 8 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
28.

Page. No.
76 Clause
No. 55 of
Section 2:
General
Condition
of Contract

Subsequent Legislation:
If, after the date 28 (Twenty eight) days prior to the date for submission of
tenders for the contract there occur changes to any National or Statute
Stature, Ordinance or Decree or other Law or any regulation or bye law of
any local or other duly constituted authority or introduction of any such
state statute, Ordinance, Decree, Law, regulation or bye law which causes
additional or reduced cost to the contractor in execution of the contract,
such additional or reduced cost shall, after due consultation with the
Employer and the Contractor be determined by the Engineer or Engineer's
representative and shall be added to or deducted from the contract price and
the Engineer or Engineer's representative shall notify the contractor
accordingly with a copy to the Employer

Page. No.
86 Clause
No. 5 of
Section 3:
General
Description
of Work
and Other
Conditions

Tax
The rates shall also include all taxes such as VAT, Income tax, service tax,
general tax and building and other construction workers welfare cess Act
1996 and the entire contractors obligations under the contract and all
matters and things necessary for the proper completion and maintenance
works

29.

Page. No.
31 Clause
No. 29.1 of
Section 1:
ITB

30.

General

31.

General

Addendum No. 2

Pursuant to the interpretation between Cl No(55) of Section(2) and Cl No(5) of Tender conditions Prevail.
Section(3), the Bidder shall include all taxes prevailing as on 28 days prior to the
date of submission of tender. In this connection, the Bidder would like to highlight
the following issues: Service Tax for Original Works of Port was exempted vide Notification No.
25/2012
Whereas the above exemption was withdrawn by recent Notification No.06/2015
The rate of Service Tax is being increased from 12.36% (incl. Education Cess) to
16% (incl. SwachBharat cess @2%)
Hence the Service Tax Component including Swach Bharat Cess on the current
tender value would be 16% w.e.f 01.04.2015 as of now.

The above issues were deliberated in the Pre-Bid Meeting on 10.03.2015 by various
Bidders and the Employer confirmed as follows;
The Bid should EXCLUDE the Service Tax Component and Swach Bharat Cess. Tender conditions Prevail.
The applicable Service Tax and Swach Bharat Cess shall be to the account of the
Employer
Apart from above , Bidder shall include all other applicable taxes / levies / cesses
in their Bid except Subsequent Legislation.

Bidder request for issuance of necessary amendment in this regards.


As deliberated in the Pre-Bid Meeting, request the Employer to confirm the
Performance Security
Performance Securities Deposit should be 10% of Contract price of which following provision:5% of contract price should be submitted as Bank Guarantee or Demand
Draft within 21 days of receipt of letter of acceptance and balance 5% The maximum amount of Performance Security- cum-Retention obligation is 10%
recovered as retention money from Running Bills. Recovery of 5% of of the Contract Value in the form of Bank Guarantee submitted in two parts. First
retention money is to commence from the first bill onwards @ 5 % of bill half shall be released upon Completion of Works and the balance half shall be
value from each bill. Retention money shall be refunded within 14 days released after DLP.
from the date of payment of final bill. Balance performance security deposit
in the form of Bank Guarantee shall be returned immediately not later than
14 days of completion of defect liability period
Statutory Clearances
The Bidder requests the Employer to confirm whether the project related Statutory
Clearances such as MoEF / CRZ / TNPCB etc. are already been obtained by the
Employer.
Please Confirm.
Demolition of Existing Sub-station
During the Pre-Meeting, it was deliberated that Existing Sub-Station Building for
the Length of 27m shall be demolished after a year period and area shall be handed
over thereafter. Please confirm the date on which this portion of site would be given
for possession in order to consider in our Programme.

Page 9 of 22

Tender conditions Prevail.

Yes. KPL has already obtained the


clearance for construction of Coal Berth
4.
The existing substation area shall be
handled over within 9 months from the
date of taken over of site by the
contractor.

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
32.

Page. No.
15 Clause
No. 4 of
Section 1:
ITB

Addendum No. 2

We have a lot of experience of executing several marine projects like Jetties, Dry Tender Conditions Prevail
Eligibility Criteria
Similar Work means construction of marine Jetty/Wharf/berth with pile, Dock, bulk berth, multipurpose berth, cargo berth, coal berth, Container berth,
diaphragm wall and superstructure works in ports.
container terminal (Similar Type-berths/Jetties) of substantial value upto 585
Crore in a single project, involving piling, Diaphragm Wall, Sheet Pile Wall and
Offshore Superstructure work of different type and complexity
In view of that Bidder requests Employer to confirm the Following :
1. Whether it is mandatory that the Bidder should have the experience of
Constructing Jetties/Berths/Wharfs consisting of Piles, Diaphragm Wall and
Superstructure in that particular/same project only.
2. Whether bidder having experience of installing Piles and Diaphragm Wall in
separate projects will be considered for meeting the eligibility criteria.
3. Whether Bidder having experience of constructing Berth with Sheet Pile/Pile and
RCC Superstructure work will be also considered under the category of Similar
Work defined in the clause.
Whether Bidders meeting the criteria in terms of project value as per the clause 4
with relevant experience of constructing Berth/Jetties/Wharf with Pile or Diaphragm
Wall and having experience of installing both Pile and Diaphragm wall separately in
different projects ,will be eligible to participate in the tender

33.

Page. No.
14 Clause
No. 1.1.1
of Section
1: ITB

34.

General

35.

Page. No.
15 Clause
No. 1.1.4
of Section
1: ITB
Page. No. 1
of 3 Clause
No. 1.8 of
NIT

36.

Dredging in front of the berth area will be executed by KPL by a separate


contract. It is expected that the soil below the coal berth deck to form a
natural slope towards the basin. However, if the soil collapse did not form
slope, the same has to be removed by grab method from the deck prior to
forming the deck slab

Please Confirm.
Usually the berth area is dredged to the final level before taking up the construction
of the berth. However, in this project these two operations are proposed by two
agencies, which may lead to following problems:
(a) In case of improper co-ordination between the two agencies the project is
expected to be delayed.
(b) In case dredging is delayed and wharf construction starts, dredging or
Grabbing operation after piles are driven may cause damage to piles.
(c) In case the soil collapse did not form slope, the earth removed by grab
method from the deck has to be paid for at special agreed rates.
Constricted Space:
Space of 13770mm between the existing conveyor system and the proposed
diaphragm wall (bottom level-40m) is not sufficient for the construction activities
and movement and operation of heavy equipment. Also there are chances of
damage to conveyor system foundations. This aspect requires reconsideration.

The Contract period is 24 months from the date of award of the work as
detailed elsewhere in the contract. The successful bidder is expected to
complete the works by the scheduled completion date specified in the
Contract

Construction Period:
Compared to other similar projects already constructed in other Ports (Ex: Coal
Berth at Paradip Port Constructed by M/s. Afcons in 36 months), contract period of
24 months is very less. It also involves a work out turns costing about 10 crores
every month. A minimum of 36 months will be required.
The due date of submission of offers will be 30.03.2015@ 1500Hrs, unless Date of submission of tender:
otherwise notified. In the event of changes in the schedules, the Kamarajar This being a major project, it is proposed to form a joint venture with an
Port Limited notifies the same through its web site.
experienced Foreign Construction Company. As this process takes time the date of
submission of Tender on 30th March 2015 is short and the same may be postponed
by another 15 days.

Page 10 of 22

Tender Conditions Prevail

The contractor should carry out the


work in the available space only without
damage to the nearby conveyor
structure. In case of any damage to the
conveyor structure, the contractor will
be held responsible for restoring the
same and any financial loss occurs will
be paid by the contractor to the user.
Tender conditions Prevail.

Refer Addendum No. 1 dated


27.03.2015. The date of submission of
tender is extended up to 16.04.2015

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
37.

38.

39.

40.

Page. No.
101 Clause
No. 34.1 of
Section 3:
general
description
of works
and other
conditions
Page. No.
19 Clause
No. 5.2 of
Section 1:
ITB

Page. No.
23 Clause
No. 13.3 of
Section 1:
ITB
Page. No.
15 Clause
No. 2.1 of
Section 1:
ITB

Advances
Mobilisation advance in the form of Equipment advance (Plant and
machinery) shall be paid up to 10% of Contract price, payable in two equal
instalments. The first instalment shall be paid after mobilisation of required
equipment at site limited to 90% of assessed cost of machinery and next
instalment shall be paid after satisfactory utilisation of earlier advance

This being a major Port project, for commencing work various infrastructural
facilities have to be mobilized and work executed at our cost during the initial few
months before the payment for the first RA Bill is received. Hence as provided in
all Govt. contracts, a Mobilization Advance of 10% may be paid on production of
B.G. and recovered in the RA Bills. You may also consider advance payment for
materials brought / lying at site.

Addendum No. 2
Tender conditions Prevail. However,
The clause is modified as: KPL shall
not pay any Advances to the contractor
except Mobilisation advance as per
clause 34 of section 3.

The eligibility criteria for each member of the joint venture are not clear. This may If the bidder is Joint Venture (JV) while
be drawn out in detail. Please confirm if foreign player can be the lead contractor in evaluating the qualification for the
JV.
Minimum Qualifying Criteria(MQC),
KPL will consider the credentials of JV
if the same JV has executed the work.
Otherwise the credentials of Lead
Member of the JV will be considered for
evaluating MQC along with the
credentials of other JV members. The
bidder has to declare the Lead Member
in the JV agreement or any such
document and submit the same along
with the tender.
All duties, taxes and other levies payable by the contractor under this Is this a Mega Port Project? Construction machinery and berth fittings may have to The import if any is at the risk and cost
contract, or for any other cause shall be included in the rates, prices and be imported for which exemption of Customs & Excise Duties may have to be of contractor and KPL is not liable for
total Bid Price submitted by the Bidder
arranged. Kindly confirm.
any such arrangement.
Joint Venture

Funds for this Coal Berth No:4 for TANGEDCO is being arranged from internal Tender conditions Prevail.
Source of Funds:
The Employer has arranged the funds from internal resources and will have resources. In case of delayed payments we must be able to claim interest on delayed
sufficient funds in Indian Currency for execution of the works
payments.
Clause No:45.2 specifies date on which RA Bills will be paid (75% within 10 days The clauses are self-explanatory and
and balance in 30 days).
there is no contradiction.
However, Clause 45.3 has specified that KPL will not be responsible for delay in
payment to the Contractor.

41.

General

These two clauses are contradictory. Kindly confirm, since this is a vital factor in
cash flow.
Are we allowed payment for materials like steels, cement, etc,.
No.

Page 11 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
42.

Page. No.
102 Clause
No. 37 of
Section 3:
general
description
of works
and other
conditions

43.

General

44.
45.

46.

47.

Is Retention amount refundable against BG


RETENTION MONEY
Retention Money at 5% will be deducted from each running bill subject to a
maximum accumulation of 5% of the contract price. Retention money shall
be refunded within 14 days from the date of payment of final bill. Balance
performance security deposit in the form of Bank Guarantee shall be
returned immediately not later than 14 days of completion of defect liability
upon satisfactorily maintaining the works free from defects for a period of
12 months, pursuant to Clause 22 of this section. Notwithstanding the
provisions contained in clause 22 and 27 of this section, if during this
period of 12 months, any defects are notified which in the opinion of the
Engineer are due to bad materials used and/ or defective workmanship, the
contractor shall be required to carry out at the contractor's cost, such repairs
as the Engineer considers necessary or in the event of contractor failing to
do this within the notified time, the Engineer may arrange for such repairs
to be carried out and deduct the cost of such rectification of the defects from
the amount retained, without prejudice to the recovery of any amount that
may have been spent in excess of the deposit
Soil investigation report may be furnished

Addendum No. 2
Tender conditions Prevail.

The available data / information is given


in Addendum No. 3. However, the
information
provided
shall
be
scrutinized by the bidder to make a clear
understanding of the ground and
underground conditions exist at the site.
It is the responsibility of the contractor
to conduct additional bore holes, if
required prior to starting of the pile and
diaphragm wall works. No additional
payment or time extension will be
entertained due to variation in
geotechnical strata during the execution
of the work.
General
Balance of drawings may be furnished
Good for Construction drawings will be
provided to the successful bidder.
Page. No.
Which Form (MOU for JV Form 15) or (JV Agreement Form 16) has to be Form 15 or Form 16 whichever is
260 &
submitted along with the tender documents. Please clarify
applicable has to submitted along with
Page. No.
the tender. However form 16 & 17
264 of
have to be submitted by the successful
Section 6:
bidder at the time of signing the
Forms
agreement.
General
We request that, Approaches to work site to be made available by the department.
The successful bidder has to make
approaches to the site at his cost from
the existing nearby approach road.
Page. No. 1 The due date of submission of offers will be 30.03.2015@ 1500Hrs, unless We request you to postpone the bid due date by at least 2 weeks from current date of Refer Addendum No. 1 dated
of 3 Clause otherwise notified. In the event of changes in the schedules, the Kamarajar submission.
27.03.2015. The date of submission of
No. 1.8 of
Port Limited notifies the same through its web site.
tender is extended up to 16.04.2015
NIT

Page 12 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
48.

49.

50.
51.

52.

Page. No.
101 Clause
No. 34.1 of
Section 3:
general
description
of works
and other
conditions
Page. No.
101 Clause
No. 34.6 of
Section 3:
general
description
of works
and other
conditions
General
Page. No.
69 Clause
No. 45.2 of
Section 2:
conditions
of contract
Page. No.
101 Clause
No. 34.2 of
Section 3:
general
description
of works
and other
conditions

Addendum No. 2

We request you to provide 10% of Contract price as Mobilization Advance against Tender conditions Prevail.
Advances
Mobilisation advance in the form of Equipment advance (Plant and Ban Guarantee instead of Equipment advance.
machinery) shall be paid up to 10% of Contract price, payable in two equal
instalments. The first instalment shall be paid after mobilisation of required
equipment at site limited to 90% of assessed cost of machinery and next
instalment shall be paid after satisfactory utilisation of earlier advance

The equipment against which the advance is given shall not be allowed to We request you to provide 5% of Contract Price as Equipment advance against Tender conditions Prevail.
be withdrawn from site until the recovery of instalment is made
hypothecation of Plant to the department.

Secured Advance

We request the department to provide 90% of cost of non-perishable materials Not Acceptable.
brought at site as secured advance.
75 % of the net amount of interim or running bill shall be paid by the Request you to release 90% of net amount within 7 days from the date of submission Tender conditions Prevail.
employer within ten (10) days from the date of submission of interim or of RA Bill and the balance within 30 days from the date of submission of RA Bill.
running bill certificate and the balance within thirty (30) days from the date
of submission of interim certificate or running bill, subject to certification
by Engineer and enclosures of supporting documents
Mobilisation advance shall be paid at SBI PLR + 2%. P.a (as on date of We request you to provide interest free Mobilization / Equipment advance against Tender conditions Prevail.
payment) interest rate at the discretion of the employer and on submission Bank Guarantee
of unconditional Bank Guarantee(s) for the equivalent amount from a
Scheduled Bank in the format provided in Appendix

Page 13 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
53.

Page. No.
103 Clause
No. 37 of
Section 3:
general
description
of works
and other
conditions

54.

General

RETENTION MONEY
Retention Money at 5% will be deducted from each running bill subject to a
maximum accumulation of 5% of the contract price. Retention money shall
be refunded within 14 days from the date of payment of final bill. Balance
performance security deposit in the form of Bank Guarantee shall be
returned immediately not later than 14 days of completion of defect liability
upon satisfactorily maintaining the works free from defects for a period of
12 months, pursuant to Clause 22 of this section. Notwithstanding the
provisions contained in clause 22 and 27 of this section, if during this
period of 12 months, any defects are notified which in the opinion of the
Engineer are due to bad materials used and/ or defective workmanship, the
contractor shall be required to carry out at the contractor's cost, such repairs
as the Engineer considers necessary or in the event of contractor failing to
do this within the notified time, the Engineer may arrange for such repairs
to be carried out and deduct the cost of such rectification of the defects from
the amount retained, without prejudice to the recovery of any amount that
may have been spent in excess of the deposit
Utility Shifting and Encumbrance free construction area handing over to
Contractor

Addendum No. 2

We request you to accept Bank Guarantee for Retention Money equivalent to 5% of Tender conditions Prevail.
Contract Value initially for smooth cash flow during execution of works.

Please confirm that, Utility shifting if any will be responsibility of KPL and Except electrical substation and North
encumbrance free Construction Area will be handed over to Contractor.
West corner of the berth and retaining
structure junction, entire area will be
handed over immediately after taken
over of site by the contractor.
The electrical substation and North
West corner of the berth and retaining
structure junction area will be handed
over within a maximum period of 9
months from the date of taken over of
site by the contractor.

55.

General

Handing over of Site / Working area

We presume that, total work area will be handed over for construction immediately.
We request you to provide work area handing over schedule if any.

Except for any re-routing, the cost of


shifting of any utilities shall be borne by
KPL.
Except electrical substation and North
West corner of the berth and retaining
structure junction, entire area will be
handed over immediately after taken
over of site by the contractor.
The electrical substation and North
West corner of the berth and retaining
structure junction area will be handed
over within a maximum period of 9
months from the date of taken over of
site by the contractor.

Page 14 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
56.

57.

Addendum No. 2

Page. No.
113 Clause
No. 39.22
of Section
3: general
description
of works
and other
conditions

Request to consider compensation towards idling of resources in case of non- Tender conditions Prevail.
Stoppage of Works
Contractor may be instructed to stop the works from time to time due to availability of working area for construction or due to conditions not in the control
security reason, movement of ships or any other reasons as per the of contractor.
instruction of Port Authorities

Page. No.
114 Clause
No. 39.27
of Section
3: general
description
of works
and other
conditions

Interruptions of work and idle time charges


The contractor shall allow in his rates for any loss of working hours due to
weather, and shifting of plants and other equipment from one area to
another area depending upon the traffic operations or for maintenance.

Page. No.
60 Clause
No. 35 of
Section 2:
conditions
of contract

Any claim for idling of the contractor's plant and machinery or any other
inputs shall not be entertained by the Port for reasons whatsoever including
non-availability of working area and therefore the contractor may consider
all such events including the normal Port operations and submit their offer
accordingly. For the reasons stated or for any other reasons, no claim on
idle time charges shall be entertained by the Port
We request you to modify the clause and keep provision of maximum limit for Tender conditions Prevail.
Liquidated Damages for Delay in Compensation
If the contractor fails to complete the work in all respects within the time Liquidated Damages for complete contract as 5% of Contract Price.
specified or within the extended time that may be allowed by the Engineer
as per Clause 31, the contractor shall pay or allow to the Port a sum
equivalent to % (half percent) per week or part thereof of the total value
of the contract subject to a maximum of 10% of the total value of contract
as liquidated and ascertained damages and not by way of penalty, for every
week or part thereof beyond the said period or extended period as the case
may be during which the work shall remain unfinished. Such damages will
be deducted from any moneys due or to become due to the contractor. The
payment of such damages does not relieve the contractor of his obligations
to complete the works or from any other of his obligations or liabilities
under this contract.
In case of part / portions of the contract work completed and taken
possession by the Employer and the Ports operates /can be made for
operation of the part portion, the calculation of liquidated damages will be
restricted to the uncompleted value of the work subject to the amount of the
maximum percentage prescribed for the liquidated damages / late delivery
charges of the total value of the contract

Page 15 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
58.

Page. No.
14 Clause
No. 1.1.1
(v) of
Section 1:
ITB
Page. No.
14 Clause
No. 1.1.2
(iii) of
Section 1:
ITB
Sl. No. 1 of
Section 7:
BOQ No 6,
Formation
of Bund
and Stone
Pitching

59.

60.

Sl. No. 11
of Section
7:
BOQ No 1,
Foundation
for Berth
No. 4

Page. No.
273 Clause
No. 3.4 of
Section 7:
BOQ

Addendum No. 2

As per BOQ No.6, Sl.No.1, we understand that, Dredging work will be carried out Tender conditions Prevail.
by other agency and this item may be operated in case soil collapse did not
happened due to clayey material or other reason. As this item will be executed after
casting of deck slab, we request you to,
1. Keep this work in the scope of Dredging Contractor
or
2. Make this item Rate only and delete the Tender quantity. The payment
shall be made for actual quantity of dredged material only. Please
Construction of Earth Retaining Structure:
Dredging in front of the berth area will be executed by KPL by a separate
confirm.
contract
Construction of Coal Berth No. 4:
Dredging in front of the berth area will be executed by KPL by a separate
contract. It is expected that the soil below the coal berth deck to form a
natural slope towards the basin. However, if the soil collapse did not form
slope, the same has to be removed by grab method from the deck prior to
forming the deck slab

Soil Excavation
Dredging the basin area in front of the coal berth no. 4 as shown in the
drawing upto a depth of 20m below CD has been assigned in another
contract. It is assumed that the soil below the deck of CB 4 will form a
natural slope. In case the soil collapse did not happen due to clayey material
or other reasons, the same shall be removed by manual grabbing method
from the deck with suitable machinery and transporting the dredged
materials in the land fill area within the port with a lead of 4km by suitable
method as directed by the Engineer including all labour, materials, tools,
plants
&equipments,
fuel
etc.,complete.
Note:
1. No separate payment will be made to the contractor for Mobilization,
demonization charges of equipment. The contractor shall include this
charge in the bill of quantities.
2. The payment will be made for actual quantity of dredged material only.
3. The dredging quantity shall be measured in terms of pre & post survey.
Please review and confirm that the test load shall be 3 x 500 = 1500 T for 1500mm /
Initial Vertical Pile load test
Supply necessary Kent ledge and perform vertical initial load test on the 1600 mm diameter Pile.
marine pile of 1500mm diameter according to the specifications and as
directed by the Engineers representative all as per relevant IS 2911 code,
etc., complete.
Note:
1. The tenderer shall furnish details of the load testing method he proposes
to adopt.
2. The test load shall be 3 x 500 = 2400 T for 1300mm diameter pile.
3. Test shall be done initially at the ground level and soil upto 0.0 CD shall
be removed. The test results shall be re-calibrated to the actual pile depth
from -18m to penetration.
Payment for PCC & RCC items
75 % of the rate quoted for the items will be released only after the concrete
is laid and cured and after satisfactory test results for 7 days cube strength.
The balance will be released after finishing work if any and satisfactory test
results for 28 days cube strength as specified in the tender. If 28 days cube
strength is not satisfactory, the payment made earlier will be recovered from
any moneys due to the contractor in respect of the execution of the works

Test shall be carried out as per IS &


CPWD Specifications. Test load details
shall be provided at the time of pile load
test.

Request you to release 90% of the rate quoted for the items after the concrete is laid Tender conditions Prevail.
and cured and after satisfactory test result for 7 days cube strength. Balance shall be
released after finishing work if any and satisfactory test results for 28 days cube
strength.

Page 16 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
61.

General

Geotechnical Investigation Results

Request you to provide Geotechnical Investigation results for reference.

Page 17 of 22

Addendum No. 2
The available data / information is given
in Addendum No. 3. However, the
information
provided
shall
be
scrutinized by the bidder to make a clear
understanding of the ground and
underground conditions exist at the site.
It is the responsibility of the contractor
to conduct additional bore holes, if
required prior to starting of the pile and
diaphragm wall works. No additional
payment or time extension will be
entertained due to variation in
geotechnical strata during the execution
of the work.

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
62.

Page. No.
31 Clause
No. 29 of
Section 1:
ITB

Addendum No. 2

Instead of two parts we will submit BG for 10% in lieu of cash retention also. Modified as
Performance Security
Performance Security Deposit shall consist of two parts; a) Performance Hence there will not be any deduction from our bills.
Performance Security
Guarantee to be submitted at award of work and b) Retention money to be
Performance Security Deposit shall
recovered from Running Bills.
consist of two parts; a) Performance
29.1 Performance Securities Deposit should be 10% of Contract price of
Guarantee to be submitted at award of
which 5% of contract price should be submitted as Bank Guarantee or
work and b) Retention money to be
Demand Draft within 21 days of receipt of letter of acceptance and
recovered from Running Bills.
balance 5% recovered as retention money from Running Bills.
29.1 Performance Securities Deposit
Recovery of 5% of retention money is to commence from the first bill
should be 10% of Contract price of
onwards @ 5 % of bill value from each bill. Retention money shall be
which 5% of contract price should
refunded within 14 days from the date of payment of final bill. Balance
be submitted as Bank Guarantee or
performance security deposit in the form of Bank Guarantee shall be
Demand Draft within 21 days of
returned immediately not later than 14 days of completion of defect
receipt of letter of acceptance and
liability period.
balance 5% recovered as retention
29.2 Performance Security Deposit in the form of Demand Draft / Banker
money from Running Bills.
Cheque must be made out in favour of Kamarajar Port Limited. No
Recovery of 5% of retention money
interest will be allowed. The successful bidder can also furnish
is to commence from the first bill
towards Performance Security Deposit as Bank Guarantee from State
onwards @ 5 % of bill value from
Bank of India or their associates or any Nationalized Bank or from
each bill. Retention money shall be
Scheduled Bank issued by their branches at Chennai enforceable and
refunded within 14 days from the
encashable at Chennai.
date of payment of final bill.
29.2 Failure of the successful bidder to comply with the requirements of
Balance
performance
security
Clause 29.1 shall constitute sufficient grounds for cancellation of the
deposit in the form of Bank
award and forfeiture of the Bid Security.
Guarantee shall be returned
29.3 The Performance Security Deposit shall remain valid till the
immediately not later than 14 days
satisfactory completion of the defects liability period pursuant to
of completion of defect liability
period.
Clause 22 of Section 3
29.2 Performance Security Deposit in
the form of Demand Draft / Banker
Cheque must be made out in favour
of Kamarajar Port Limited. No
interest will be allowed.
The
successful bidder can also furnish
towards Performance Security
Deposit as Bank Guarantee from
any Nationalized Bank issued by
their
branches
at
Chennai
enforceable and encashable at
Chennai.
29.2 Failure of the successful bidder
to comply with the requirements of
Clause 29.1 shall constitute
sufficient grounds for cancellation
of the award and forfeiture of the
Bid Security.
29.3 The Performance Security
Deposit shall remain valid till the
satisfactory completion of the defects
liability period pursuant to Clause 22 of
Section 3
Page 18 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
63.

General

64.

Sl. No. 11
of Section
7:
BOQ No 1,
Foundation
for Berth
No. 4

65.

Sl. No. 12
of Section
7:
BOQ No 1,
Foundation
for Berth
No. 4
Sl. No. 4 of
Section 7:
BOQ No 6,
Formation
of Bund
and Stone
Pitching

Secured Advance

As huge amount is involved in procurement of steel, concrete and liner and there is
no provision for Mobilization Advance, it is requested to consider a secured advance
@75% of the material cost against supply of materials at site.
As per item no.13, Pile capacity is 410 MT but in item no.11 test load mentioned as
Initial Vertical Pile load test
Supply necessary Kent ledge and perform vertical initial load test on the 2400MT, where as test load will be 1230 MT. Accordingly we will be quoting our
marine pile of 1500mm diameter according to the specifications and as rates considering pile capacity of 410MT and test load as 1230 MT.
directed by the Engineers representative all as per relevant IS 2911 code,
etc., complete.

Addendum No. 2
Not Acceptable.

Test shall be carried out as per IS &


CPWD Specifications. Test load details
shall be provided at the time of pile load
test.

Note:
1. The tenderer shall furnish details of the load testing method he proposes
to adopt.
2. The test load shall be 3 x 500 = 2400 T for 1300mm diameter pile.
3. Test shall be done initially at the ground level and soil upto 0.0 CD shall
be removed. The test results shall be re-calibrated to the actual pile depth
from -18m to penetration.
1500 mm diameter piles (Estimated Working Load is 410 Tonnes)

Unit of stone pitching shown in MT, please let us know the method of measurement. Tender conditions prevail.
Stone Pitching
Supply and Transport the stones consisting of 25% between 500 kg and
1000 kg and 75 % over 1000 kg and place them between the piles to form a
slope, as shown in the drawing and as specified in relevant schedules or as
directed at site of work, including all operations, handling, labour,
materials, transport, fuel, tools, tackles, plants and equipments etc.,
complete.
Note:
1. The contractor shall make own arrangements for transporting the required
materials.
2. The contractor shall engage cranes of suitable boom length and capacity
for easy handling.
3. The contractor shall engage skilled workmen for the work.

Page 19 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
66.

Page. No.
23 Clause
No. 13.3 of
Section 1:
ITB

All duties, taxes and other levies payable by the contractor under this
contract, or for any other cause shall be included in the rates, prices and
total Bid Price submitted by the Bidder

Addendum No. 2
No. The quoted rate shall include all
taxes.

As per discussion, we have to quote our rates excluding service tax. In addition to
our rates service tax as applicable shall be paid separately.
Page. No.
86 Clause
No. 5 of
Section 3:
general
description
of works
and other
conditions

67.

Page. No.
268 Para 2
of Section
7: BOQ
General

Tax
The rates shall also include all taxes such as VAT, Income tax, service tax,
general tax and building and other construction workers welfare cess Act
1996 and the entire contractors obligations under the contract and all
matters and things necessary for the proper completion and maintenance
works

GST / New Tax


Tax:

As announced by Govt. GST may be applicable from April 2016. In case it is levied No. The quoted rate shall include all
the same is to be compensated.
taxes.

68.

General

The rates shall also include all taxes such as VAT, Income tax, service tax,
general tax and building and other construction workers welfare cess Act
1996 and the entire contractors obligations under the contract and all
matters and things necessary for the proper completion and maintenance
works
Bore Log
We request you to provide the Bore log details (Soil Investigation Report).

69.

General

Reinforcement Details

70.

General

List of Approved Brand

The available data / information is given


in Addendum No. 3. However, the
information
provided
shall
be
scrutinized by the bidder to make a clear
understanding of the ground and
underground conditions exist at the site.
It is the responsibility of the contractor
to conduct additional bore holes, if
required prior to starting of the pile and
diaphragm wall works. No additional
payment or time extension will be
entertained due to variation in
geotechnical strata during the execution
of the work.
We request you to provide reinforcement details for piling D wall and Pre-stressed There are no pre-stressed members.
members.
Reinforcement details will be provided
to successful bidder.
List of approved brand of steel and cement may kindly be informed.
Already provided in Clause 6 & 2 of
Part II : specifications of materials
resp.

Page 20 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
71.

72.

73.

Page. No. 1
of 3 Clause
No. 1.8 of
NIT
Page. No.
260 &
Page. No.
261 of
Section 6:
Forms
Page No.
87 , Clause
No. 9 of
Section 3
General
Description
of Works
and Other
Conditions.

Last Date of Submission of Tender

The quantities given under the Bill of Quantities are those upon which the
approximate estimated cost of work are based but they are subject to
alterations, omissions, deduction and additions and not necessarily show the
actual quantities of work to be done and can be increased or decreased at the
discretion of the Engineer. The rates payable for the variations up to 25%
in respect of individual items in the contract shall be as per the contract
rates. The rates quoted shall be firm for such variation. In case the variation
results in the total contract value exceeding the prescribed percentage, the
revision of rates, if any, shall be applicable only for that portion of contract
carried out in excess of the permissible percentage.

Addendum No. 2

It was requested in the meeting by all to extend the date of submission. It was Refer Addendum No. 1 dated
agreed that date of submission will be extended suitably. The same may be kindly 27.03.2015. The date of submission of
confirmed.
tender is extended upto 16.04.2015
As discussed in the meeting both forms are to be submitted only by the successful Form 15 or Form 16 whichever is
bidder. Kindly clarify.
applicable has to submitted along with
the tender. However form 16 & 17
have to be submitted by the successful
bidder at the time of signing the
agreement.
Utmost care has been taken in
preparation of design/ quantities.
However, if required, necessary changes
would be made depending on the site
conditions
and
any
subsequent
requirement
by
the
end
user(TANGEDCO)

Page 21 of 22

REPLIES TO THE PRE BID MEETING QUERIES FOR THE TENDER CONSTRUCTION OF COAL BERTH - 4
74.

Page
Safety and Security Measures
No.111 ,
Clause
39.17 of
section - 3
General
Description
of Works
and Other
Conditions.

Addendum No. 2
New clause is included in addition to a
to d of clause 39.17 and the same is as
follows.
e. Health and Safety
The Contractor shall at all times take all
reasonable precautions to maintain the
health and safety of the Contractors
Personnel. In collaboration with local
health authorities, the Contractor shall
ensure that medical staff, first aid
facilities, sick bay and ambulance
service are at all times at the Site and at
any accommodation for Contractors
Personnel,
and
that
suitable
arrangements are made for all necessary
welfare and hygiene requirements and
for the prevention of epidemics.
The Contractor shall appoint an accident
prevention officer at the Site,
responsible for maintaining safety and
protection against accidents. This person
shall be qualified for this responsibility,
and shall have the authority to issue
instructions
and
take
protective
measures
to
prevent
accidents.
Throughout the execution of the Works,
the Contractor shall provide whatever is
required by this person to exercise this
responsibility and authority.
The Contractor shall send, to the
Engineer, details of any accident as soon
as practicable after its occurrence. The
Contractors shall maintain records and
make reports concerning health, safety
and welfare of persons, and damage to
property, as the Engineer may
reasonably require.

75.

BOQ No.1,
Foundation
for Berth

Reinforcement for pile muffs

Please confirm the quantity indicated in the BOQ is 1733.00 MT.

Page 22 of 22

No. The quantity of Sl.No.10 of BOQ


No. 1 is 173.30 MT and the same is
modified in the BOQ also.