Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INDEX
Page
PART 1
25.1.1
25.1.2
25.1.3
25.1.4
25.1.5
25.1.6
25.1.7
5
5
5
6
7
7
7
PART 2
25.2.1
25.2.2
25.2.3
25.2.4
25.2.5
25.2.6
25.2.7
25.2.8
25.2.9
9
10
10
10
10
PART 3
14
25.3.1
25.3.2
25.3.3
25.3.4
25.3.5
Stringing
Checking and Cleanliness of Pipes and Fittings
Cutting of Pipe Lengths
Transition Pieces
Bends and Field Bending
14
14
14
15
15
11
11
12
12
25.3.6
16
PART 4
17
25.4.1
25.4.2
25.4.3
25.4.4
25.4.5
17
17
18
19
20
PART 5
25.5.1
25.5.2
25.5.3
25.5.4
25.5.5
25.5.6
25.5.7
25.5.8
25.5.9
21
21
22
23
23
23
24
24
24
PART 6
26
25.6.1
25.6.2
25.6.3
25.6.4
25.6.5
25.6.6
25.6.7
25.6.8
25.6.9
25.6.10
26
PART 7
32
25.7.1
General
32
25.7.2
25.7.3
25.7.4
32
33
34
PART 8
35
25.8.1
General
35
21
26
27
28
28
28
29
29
31
31
25.8.2
35
25.8.3
25.8.4
25.8.5
25.8.6
25.8.7
25.8.8
25.8.9
Depth of Cover
Concrete Sheathing of Pipes and Repairs
Handling, Transportation and Stacking of Pipes
Joints in Pipe Coating and Sheathing
Excavation of Pipe Trench
Lowering or Sinking Pipe into Trench
Backfilling - Tracked Equipment
36
36
37
38
37
39
39
PART 9
WATER CROSSINGS
40
25.9.1
25.9.2
25.9.3
25.9.4
25.9.5
25.9.6
25.9.7
25.9.8
25.9.9
25.9.10
General
Minimum Clearances Between Lines
Depth of Crossings and Cover
Surveying the Crossing
Excavating the Pipe Trench
Pressure Testing Pipe Before Launching
Sinking Pipe Into the Trench
Care of Pipe and Coating
Backfill and Reinstatement of Crossings
Signboards and Markers
40
41
41
42
43
43
43
44
44
45
PART 10
OFFSHORE WORKS
46
25.10.1
25.10.2
25.10.3
25.10.4
General
Down-Time
Pipe Trenching (Ditching)
Limiting Bending Stresses
46
46
46
47
25.1.1
25.1 .2
All preliminary works concerned with fencing and clearing the pipeline right-of-way
and construction and storage areas; use of access roads; grading and surface stripping
shall be carried out in accordance with the relevant parts of- the following Standard
Construction Specifications:
Section 2 - (Right of Way and Access Roads)
Section 3 - (Clearing, Grading and Surface Stripping)
Section 4 - (Earthwork at Construction Sites)
25.1.3
SPREAD CONTROL
The Contractor shall organise all stages of the construction works so as to cause the
minimum amount of disturbance to land occupiers and the general public. If in the
opinion of the Company Representative, the various construction activities become
spread over distances greater than those deemed advisable for the efficient execution
and inspection of the Works, with regard to the welfare and adequate protection of land
occupiers and the general public, the Company may require the Contractor to reduce the
work spread and take such other remedial actions as the Company Representative
considers necessary.
Acceptable lengths of construction spreads for differing environmental areas are
considered to be:
-
300 metres
2000 metres
14000 metres
The length of the work spread shall be subject to constant review by the Company
Representative and the Contractor shall make any changes required by the Company at
no additional cost to the Contract.
The Contractor shall co-operate with the Company Representative at all times
concerning the maximum length of spread. Due allowances shall be deemed to have
been made in the Contract Price for spread restrictions which may be required by local
authorities, in particular in the urban areas. The Company Representative shall interpret
these requirements and the Contractor shall make every reasonable effort to comply.
The limit to working length does not necessarily include crossings, valve sites, rock
excavation or similar works which may be undertaken as separate operations by prior
agreement with the Company Representative.
25.1 .4
PERMITS
The Contractor shall secure, without cost to the Company, any official permits
(including permits necessary for the transportation of pipe and other materials),
licences, or authorizations that may be necessary In connection with all construction
operations-hereunder, other than the usual pipeline right-of-way grants or easements
and railroad, highway, river or other crossing permits on the right-of-way, which the
Company shall secure beforehand. Railroad, highway, and river crossing permits for
the pipeline, as obtained by the Company, do not necessarily cover the general
movement of materials and equipment across such transportation routes.
25.1.5
TEMPORARY CROSSINGS
The Contractor shall provide and maintain suitable crossings over the pipeline right-ofway where required by property owners to allow free movement of livestock and
equipment at all times throughout the construction period.
25.1.6
25.1.7
(c)
(d)
(e)
(f)
(h)
It shall be the Contractor's responsibility to obtain and complete all official forms for
entering onto the various Authorities' properties for the Company's staff and the
Contractor's staff. The Contractor shall, ensure that such forms are valid for the duration
of the Contract and Maintenance Period and copies of same shall be provided to the
Company Representative.
No work shall commence at any crossing until all requirements in respect of
Indemnities, Bonds and Agreements have been secured and all official forms duly
stamped, signed and authenticated.
25.2.1
No pipes or other materials which have not been carefully inspected and any damage or
defects made good, shall be incorporated into the Construction Works.
The Contractor shall ensure that the progress of the Works is not delayed as a result of
his failure to allow sufficient time for the repairs to be completed.
25.2.2
MATERIALS DOCUMENTATION
All materials, whether supplied by the Company or by the Contractor, shall be subject
to a proper stores documentation procedure (as drawn up by the Contractor and
approved by the Company Representative) affording security for the materials and
providing permanent records of all receipts and issues.
25.2.3
25.2.4
DEMURRAGE
The Company will notify the Contractor of the expected dates and times of arrival of
consignments of material at specified delivery points.
The Contractor shall protect and idemnify the Company against any charges or losses
for demurrage, shortage, or other charges relating to the Contractor's failure to promptly
and efficiently unload or take delivery of materials. If at any time, loads of pipe, valves,
or other materials are diverted or shipped to points other than original destinations at the
request of (or for the convenience of) the Contractor, the expenses of such diversion and
any consequent or subsequent increased transport costs shall be borne by the Contractor.
25.2.5
SURPLUS MATERIALS
During the progress of the Works, surplus pipes and other materials shall be returned to
the Contractor's storage area.
Materials of differing specifications shall be clearly identified and stored separately.
Where pipes are cut, all pieces shall be clearly marked with the original pipe serial
number.
Re-bevelling of surplus pipe shall be carried out as directed by the Company
Representative, using an approved machine. All scrap shall be stacked separately.
Removal of surplus pipes and other materials from the storage sites shall be carried out
only on the written instructions of the Company Representative.
10
Any materials supplied by the Company to the Contractor which are neither
incorporated in the Works nor returned to the Company Stores shall be charged to the
Contractor at cost of the materials at Site. Any materials supplied by the Company to
the Contractor which are not incorporated in the Works and which are no longer
suitable for re-use by the Company, due to deterioration caused by the Contractor's.,
neglect, shall not be returned to the Company Stores and shall be charged to the
Contractor at cost of the materials at Site. The Company Representative may also direct
that quantities of Company supplied materials which have been used by the Contractor
appreciably in excess of the design requirements or reasonable expected requirements
for completing the Construction Works shall also be charged to the Contractor.
25.2.6
25.2.7
PIPE HANDLING
The Contractor shall provide and maintain all necessary slings and lifting equipment
suitable for properly handling pipes, to the approval of the Company Representative.
a)
Pipes- Generally
Pipes shall not be subjected to jars or impacts and shall be lifted or lowered from one
level to another. For pipes 6-ins (150mm) or more in diameter, special end hooks,
curved to fit the inside of the pipe ends shall be used for lifting. In the case of pipes
having end caps, band slings shall be used. Punching of end caps shall not be
permitted. Pipes shall be lowered into position in single lengths without dropping, and
each length shall nest evenly with the lengths previously stacked or loaded.
b)
Coated and wrapped pipe shall be handled at all times with approved rubber-covered
broad band slings or other equipment designed to prevent damage to the coating and
wrapping. All such equipment shall be kept in good order and repair or otherwise
removed from the worksite. The use of tongs, grabs, crowbars, chain slings, wire-rope
and rope slings (of any sort), narrow or defective belt slings, or any other handling
equipment which may be injurious to the pipe coating and wrapping, shall not be
permitted. All joints and sections of coated and wrapped pipe shall be picked up clear
of the ground and not dragged over the ground. Coated pipe shall not be subjected to
jarring impact and shall be set down on well padded skids. Walking on coated pipe
shall not be permitted. The requirements of Part 9 of Standard Specification
11
S-23 shall also apply to the handling, loading, transportation and stockpiling of coated
and wrapped pipes.
25.2.8
25.2.9
12
Bends, valves and other fittings and materials for pipeline construction shall be stored
in a manner approved by the Company Representative.
Any hay or straw or other combustible material which has been used for packaging
purposes shall be promptly removed from the Site by the Contractor. No waste
packaging materials shall be burnt on the Site.
13
25.3.1
STRINGING
The Contractor shall offload and string pipes along the route of the pipeline using
suitable approved plant. Pipes shall be strung out so as to cause the least practicable
interference with the use of the land, and at intervals gaps shall be left between pipes as
directed to permit the passage of stock and equipment across the right-of-way.
Coated and wrapped pipes and fittings shall not be sit down on the ground but placed on
well padded timbers provided by the Contractor, all as specified in Clause 25.2.9. The
pipes and specials shall at all times be adequately supported by the full effective width
of the padded timbers, so as to ensure no indentation of the pipe coating and wrapping
material.
25.3.2
2 5.3 .3
14
cutting shall be performed by an approved pipe cutter or thermal cutting and bevelling
machine. Manual cutting will not be permitted.
The Contractor shall carefully remove sufficient wrapping to allow for the cutting of
pipes and their. subsequent welding and re-wrapping in accordance with the Sections 10
and 21 of the Standard Specifications.
25.3.4
TRANSITION PIECES
Where transition pieces are not provided by' the Company as part of the Companysupplied materials, the Contractor shall manufacture (from the pipe supplied) a
sufficient number of machined transition pieces for the locations where the pipeline
changes in wall thickness, as required by the pipeline design. The transition shall be
effective in the bore of the pipe at an angle of 14' as detailed in the Welding
Specification (S-21).
Any additional expenses incurred in making the transition pieces, or for their inclusion
in the pipeline, shall be borne by the Contractor.
25.3.5
15
All field bends shall be proved in the presence of the Company Representative with a
gauging pig or device fitted with a circular plate not less than 97% of the internal
diameter of the pipe before bending.
All bends and other special pipes shall have the coating made good or replaced in
accordance with the coating and wrapping specifications detailed in Standard
Construction Specification Sections S-10 and S-23.
25.3.6
16
25.4.1
25.4.2
17
The locations where a double (or triple) coating and wrapping is required are generally
as follows:(a)
(b)
At all crossings with other pipelines. At these locations the double wrap shall
be extended 6 metres on each side of the crossing. The
existing pipeline being
crossed shall also be over-wrapped, using an approved cold applied tape as specified.
(c)
At all river or creek crossings or wet swamp areas where concrete coating
not specified.
25.4.3
(d)
At all locations where the pipeline passes through a sleeved pipe crossing.
(e)
is
18
b)
A piece of impregnated outer wrap shall be laid over the hole (holiday) made by
the point of the pit gauge in the selected area.
c)
The holiday detector brush or ring shall be passed over the piece of
wrap and the voltage output progressively increased to the level
where a
fault is indicated at the indentation in the pipe coating.
outer
holiday
The holiday detector shall thereafter be operated at this voltage for coating applied to
the thickness tested. The same procedure shall be followed for determining operating
voltages for other coating thicknesses.
During testing, the electrode shall not be kept over the holiday for longer than is
necessary to confirm the fault.
The Contractor shall provide any labour and assistance which may be required by the
Company's Representative and Inspection Staff in the inspection of coated pipe and
fittings.
Holiday detection shall be carried out only in dry weather conditions as approved by the
Company Representative. The Contractor shall make provision in his Contract price for
possible down time due to delay caused by adverse climatic conditions.
The Contractor shall, for any, pipe removed from the storage yard, make good all
defects in the coating and wrapping in the specified manner. Placing pipes in the trench
shall not proceed until coating/wrapping repairs and final holiday inspections have been
completed to the approval of the Company Representative. Allowance shall be made
for this in the timing of the work.
The Company Representative may for the purpose of inspection, remove or cause to be
removed any area of coating and wrapping which has been applied by the Contractor,
and the Contractor shall make good any such area after inspection. If in the opinion of
the Company Representative such removal has revealed any defective workmanship, the
making good shall be at the cost of the Contractor. The Contractor shall provide all
labour and facilities required by the Company Representative and Inspection Staff for
carrying out these inspections.
25.4.4
19
25.4.5
TESTING
Hydrostatic testing of the pipeline shall be carried out by the Contractor or other
appointed specialist testing contractor, in accordance with Section 29 of the Standard
Specifications.
20
25.5.1
25.5.2
21
The finished trench shall be free of roots, stones, rocks or other hard objects which may
damage the pipe or pipe coating. Provision shall be made for dewatering, as may be
required.
Where the trench has been over-excavated to a depth significantly greater than that
required in the Specification or Approved Working Drawings, or that required for
obtaining a smooth profile, the Contractor shall fill in the bottom of the trench to such a
depth and with such materials and degree of consolidation as the Company
Representative may direct.
Where the pipe is not laid to the required depth and has to be lowered, it shall be
completely removed from the trench before the additional excavation work is carried
out.
No spans except those specifically shown on the Approved Working Drawings shall be
permitted.
25.5.3
Land Lines
Flowlines on land shall not be buried.
Trunk and delivery pipelines on land, unless otherwise specified, shall have a
minimum cover from the top of the pipe to the ground level of 90 cms. The
minimum cover within 15.0 metres of any private dwelling, industrial building
or place of public assembly, in which persons work or congregate or assemble,
shall be 122 cms unless otherwise specified.
For depth of cover at trench excavations in rock, refer to Clause 25.5.6
hereafter.
(b)
Swamp Lines
Unless otherwise specified, the cover from the top of the pipe to
mud or ground level shall not be less than 60 cms.
consolidated
22
Drawings. Such crossings are dealt with more particularly in Part 7 of this
Specification but the overruling, requirements may be determined by the
particular Construction Permit for the crossing concerned.
25.5.4
25.5.5
25.5.6
EXCAVATIONS IN ROCK
The term 'Rock' shall be deemed to include any hard compact material (other than
concreted or paved surfaces of roadways, etc) which in the opinion of the Company
Representative, cannot be removed by mechanical excavators, rippers or manual means
and therefore requires the use of pneumatic drills or rock breakers', rock cutting
machines or blasting.
All excavation in rock, as indicated in the Contract Documents or Working Drawings,
shall be deemed to be included in the Contract Price.
If rock is found between the surface and 50 cms below the surface, the depth of cover
over the top of the pipeline shall be a minimum of 60 cms.
If rock is found more than 50 cms below the surface, the depth of cover to the pipeline
shall be the distance between the surface and the rock level plus 10 cms, up to a
maximum cover of 90 cms.
The minimum cover through rock in industrial, commercial, and residential areas shall
be 76 cms.
Where the bottom of the pipe trench is in rock, or has hard protrusions capable of
damaging the pipe coating, the bottom of the trench shall be excavated for a further 15
cms across the full width, so as to accommodate the necessary thickness of soft padding
material . The trench shall be of sufficient depth to accommodate the soft padding, pipe
and specified cover.
23
25.5.7
BLASTING
Rock blasting may only be carried out by the Contractor with the written approval of the
Company and after obtaining from the Local, State and Federal Police and Army
Authorities, all permissions, licences, permits and certificates necessary for the use of
blasting explosives.
The use of explosives for rock excavation shall be in accordance with the requirements
and restrictions set out in Part I of Section 3 of the Standard Construction
Specifications.
Care must be exercised by the Contractor to prevent damage to underground structures,
drains, conduits, pipelines, power cables and telephone cables.
The Contractor shall blanket blasts to prevent damage to pipe and equipment, or nearby
structures, telephone and telegraph lines, power lines, etc. If, during blasting,
operations, loose rock is scattered over the right-of-way or adjacent property, the
Contractor shall collect up such rock and dispose of it to the satisfaction of the
Company and the landowner and his tenants, at no extra cost to the Company.
Damage caused by blasting shall be paid for by the Contractor, whether caused by the
Contractor, his sub-contractors, employees, or agents.
25.5.8
25.5.9
24
No pipe shall be lowered into the trench without the agreement and approval of the
Company Representative and lowering-in shall always be carried out in the presence of
the Company Representative or Inspector.
The handling and lowering of coated and wrapped pipe into the trench shall be carried
out by, a method previously approved by the Company before commencement of the
work and shall take place as soon as possible after the trench has been prepared and the
coating and wrapping on the pipe finally made good and re-tested. During the loweringin operation, special care shall be taken to ensure that the pipe coating sustains no
damage and that the pipe is not overstressed. Holiday detection tests on the pipe coating
shall be performed throughout, and any damage to the coating and wrapping found or
indicated during the lowering-in operation shall be rectified before the operation is
completed.
Coated pipe shall be handled with rubber-covered broad-band slings suitable for the
particular pipe diameter. Slings shall be constructed so that they can be removed from
under the pipe without dragging any metal parts against the pipe coating. The lifting
eye and attachment bar at each end of' the sling band shall be of the same (or less)
thickness as the sling band, so as to facilitate withdrawal. The trench bottom shall also
be relieved beneath the sling to prevent pinching of the sling band and further facilitate
its withdrawal.
Alternatively the pipe may be cradled into the prepared trench, providing that the
cradles do not cut, deform or otherwise damage the pipe coating.
Where the pipe trench excavation has been carried out in rock or stony conditions,
protective shields of impregnated asbestos (Rockshield or similar approved material)
shall be placed along the trench walls, as approved or directed by the Company
Representative, so as to prevent damage to the pipe coating during lowering-in
operations. These shields shall be removed only after the pipe is in place and subject to
no further movement.
25
25.6.1
25.6.2
BACKFILLING - GENERALLY
No rubbish, vegetable growth or other perishable materials shall be put in the pipe
trench along with the backfill material.
The remaining excavated material shall be returned to the trench in layers not more than
20 cms thick and thoroughly
compacted by mechanical plate vibrators or rammers. Surplus excavated sub-soil shall
be removed from the Site, or spread evenly over the Working Width, as directed by the
Company Representative. When spread over the Working Width, the topsoil shall have
26
been previously removed and set aside and the surplus fill material spread only on top
of the exposed sub-soil . Where necessary, extra topsoil stripping shall be carried out at
the Contractor's own cost.
Any excavated material which, in the opinion of the Company Representative, is
unsuitable for backfill or alternative disposal within the Working Width, shall be
removed from the Site by the Contractor and any consequent deficiency of backfill shall
be made good with approved material supplied by the Contractor from other approved
sources.
Where the pipe trench is excavated in rock, the Contractor shall ensure that the
procedure set out in Clause 25.6.1 is diligently followed so as to form a protective
cushion of soft material around the pipe. Thereafter, (unless otherwise directed by the
Contract Documents and Drawings, or by the Company Representative) the excavated
rock, excluding large pieces, shall be used as backfill material in the trench. It shall be
an approved mixture of medium and small sized pieces, chippings and gravel, which
will pack down into the trench and become well consolidated without voids.
In carrying out backfilling operations, the Contractor shall make due allowance for
subsequent settlement, and he shall promptly make good any settlement that takes place
up to the end of the Maintenance Period.
The backfill material shall be crowned (heaped up) along the trench line to a height of
between 20 and 30 cms above the adjacent ground surface, except through irrigated
fields where the backfill shall be completed in accordance with Clause 25.6.3 herein.
Through rocky lands, where there are movements of livestock, 6 metre wide gaps shall
be provided across the backfilled line at intervals of 100 metres (or as otherwise
directed by the Company Representative) so as to provide passageway for livestock.
Gaps shall be level with surrounding ground and surfaced with backfill material free
from large or sharp rocks, all to the satisfaction of the landowner or land tenants, and
the Company Representative.
25.6.3
27
thick layers and each layer thoroughly compacted by hand or machine so as to provide a
good bond between the undisturbed sides of the ditch and the new backfill material.
On hillsides or sloping ground, diversionary furrows or levees shall be provided across
the pipe trench-backfill to direct the flow of rain water and flooding into the natural
drainage courses and away from the pipe trench. However, the surface drainage must
not be diverted into channels other than those followed before the pipeline was laid.
Particular care shall be exercised to ensure that all drainage ditches are properly
reinstated and left unobstructed so as to prevent the backing up of water and wrongful
flooding.
25.6.4
REINFORCEMENT OF BACKFILL
The Contractor shall reinforce the backfill where the pipe trench cuts through the banks
of rivers, streams, irrigation or drainage ditches and the banks or levees of any irrigated
fields. This shall be done with sand or earth-filled sacks, stabilised sand or soil, leanmix concrete, rock or concrete headwalls, as called for in the Contract Specifications or
Approved Drawings. Bags or sacks shall be of the polyurethene woven type, to allow
earth or sand fill to an equivalent of approximately 50 kg per bag.
The Contractor shall, at his own expense, repair damage to levees, roadways, lanes,
private drives, and farm terraces caused by settling or washing through the pipeline
trench, up to and including the date of acceptance of the Contract Works.
25.6.5
25.6.6
GENERAL REINSTATEMENT
Unless otherwise directed by the Company Representative, the Contractor shall
permanently reinstate all areas disturbed (either directly or indirectly) by the.
construction of the pipeline, to a condition not less than equal to that existing before the
commencement of the Works and shall provide all materials required to complete these
reinstatement works. This shall include all access roads, kerbs, footpaths, hedges,
walls, fences, ditches and land drains, etc.
28
All such reinstatement shall be to the approval and satisfaction of the Company
Representative and the local Authorities, landowners and occupiers concerned.
Reinstatement shall be carried out as soon as practicable after completion of backfilling.
Generally, in backfilling the pipe trench, all the surface material that was stripped and
set aside prior to excavation shall be replaced in its original position as far as possible
together with such new materials as may be required in order to reinstate the land to a
condition at least equal to that obtaining before the Contractor entered onto the land.
The Contractor shall remove all surplus excavated material (other than topsoil), waste,
scrap and rubbish from the working width and leave the whole right-of-way in a tidy
condition upon completion of the Works to the entire satisfaction of the Company
Representative. The Contractor shall ensure that no red lead paint, barbed wire or other
harmful materials are left where animals may have access.
The Contractor shall be responsible for maintaining all the reinstatement and making
good all sinkages, scouring, erosion or other defects until the expiry of the Contractual
Maintenance Period.
25.6.7
25.6.8
29
The Contractor shall temporarily reinstate all damaged surfaces of roads and highways
within two weeks of the completion of backfilling of that section of the pipe trench. The
Contractor shall carry out any temporary rein-statement to a standard which will permit
its inclusion in the permanent reinstatement.
For flexible bituminous paved roads, the temporary reinstatement shall consist of a 70
mm thick layer of hot rolled asphalt or dense bitumen macadam (DBM) laid on a
compacted sub-base which shall have sufficient thickness to leave the required depth of
sub-base when the permanent reinstatement is later carried out. The compacted surface
of the asphalt or DBM shall be finished slightly higher than the surrounding road
surface.
The Contractor shall maintain the temporary reinstatement for a period of six months
and shall then carry out the permanent reinstatement to the satisfaction of the
responsible local government, road and highway Authorities and the Company
Representative. Any areas of temporary reinstatement that have not stabilised by this
time shall be excavated to the full depth of the trench, if necessary, and refilled in an
approved manner to prevent subsequent settlement. The surface shall then be
temporarily reinstated and maintained for a further period, as directed by the Company,
after which the permanent reinstatement shall be completed.
To carry out the permanent reinstatement, the Contractor shall first remove the
temporary surfacing by cutting back to a neat vertical edge in the original road surfacing
on either side of the trench. The sub-base shall also be removed to a depth necessary to
accommodate the permanent reinstatement and the surplus materials arising from both
these operations shall be disposed of as specified. The loosened surface of the sub-base
shall then be thoroughly wall recompacted, using mechanical rammers.
The edges of the original road surfacing shall be coated with a suitable grade of hot
bitumen immediately before the permanent reinstatement material is laid against them.
Compaction shall be carried out by mechanical means to the specified standard and
shall ensure that the final reinstated surface is finished flush with the original road
surfacing.
The permanent reinstatement of roads and highways shall be equal to the original
construction of the road or carried out in accordance with the following table, unless
otherwise directed by the Contract Specification, Working Drawings or the Company.
30
Side Roads
in Towns
Minor
Roads
12 mm
Chippings
12 mm
Chippings
Asphalt Wearing
40 mm
Course (If required)
30 mm
Base Course
90 mm
70 mm
)70mm
) single
) course
)
225 mm
225 mm
225 mm
Surface Dressing
Sub-base
(Remaining from
temporary
reinstatement)
25.6.9
Major Highways
Main Roads and
Regular Bus or
Lorry Routes
12 mm
Chippings
25.6.10
31
25.7.1
GENERAL
Pipe crossings beneath railways, roads and highways shall be bored, tunnelled or cutand-cased in accordance with the requirements of the Federal and State Authorities and
agencies concerned.
Before starting the construction of any crossing, the Contractor shall obtain written
approval from the Company and the Authorities concerned, regarding the detailed
procedure to be used and their agreement to the programming and timing of the
operation. Any of the Authorities official representatives may be present on Site
throughout the Works.
Care shall be taken not to block traffic while such crossings are being installed and the
Contractor shall furnish all necessary signs, signals, safety barriers, watchmen and
lookouts to warn traffic and safeguard his employees, other employees and
Representatives, and all members of the public.
The Company shall be advised of any unavoidable late changes in the established
programme of work at least 3 days before the work is due to start.
The operation of heavy equipment in close proximity to an existing pipeline crossing
shall generally not be permitted, except with the written consent of the Company
Representative.
The Contractor shall construct all such rail and road crossings as part of his scheduled
pipeline construction works and at unit prices as stated in the Price Schedule for such
crossings unless otherwise specified or agreed by the Company.
25.7.2
32
The casing shall be continuously jacked forward immediately behind the boring
machine cutting head. The diameter of the bored hole shall be larger that the outside
diameter of the casing b the minimum amount necessary to allow forward movement of
the casing, and not more than 30 mm larger without the agreement of the Company.
The section of pipeline to be installed in the casing shall be subjected to pre-installation
pressure tests in accordance with Part 2 of Standard Construction Specification S-29.
During these tests, the whole length of the pipe (as well as the joints), shall be carefully
examined for very small leakages caused by minute defects in the pipe material.
After satisfactory completion of these pressure/leakage tests, the whole length of pipe to
be installed in the cased crossing shall be double coated and wrapped in accordance
with Part 4 of this specification; the specific requirements of the Contract Specification
and Approved Working Drawings, and the relevant parts of Section 10 of the Standard
Construction Specifications.
An approved method shall be used for the installation of the pipeline in the casing and
all due precautions taken to avoid damage to the coating and wrapping. The wrapped
pipe shall be supported in the casing, using proprietary spacer rings of suitable thickness
for the annulur space between the pipe and sleeve. After installation, an electrical test
shall be made under supervision of the Company Representative, prior to tieing-in the
cased crossing pipe to the pipeline on either side, to confirm (and measure) the
electrical insulation resistance between pipeline and casing. Bare ends of the pipe shall
be cleared of contact with soil, water, or other conductive materials during the test . The
test shall be made using 500 volt dc megger type meter. If the insulation resistance is
found to be less than 100,000 ohms the Contractor shall withdraw the pipe and
eliminate any point(s) of unsatisfactory insulation resistance, before replacing the pipe
and retesting until satisfactory readings are obtained.
Casing seals and vent pipes are to be installed after permanent support for the pipe at
entry and exit from the casing is installed and established to the approval of the
Company Representative.
The pipeline on each side of the crossing shall also be supported and anchored with
sacks of lean concrete at intervals of 3 metres from the ends of the casing to the point
where the pipe is bedded firmly in the bottom of the ditch, so as to prevent movement
of the pipe within the casing.
Backfill within the boundary limits of a road or railway crossing shall be carried out in
controlled layers of not more than 15 cms thickness. Each layer shall be thoroughly
tamped and consolidated (using mechanical rammers) to the satisfaction of the
Company Representative and the road or railway Authorities concerned. Any culverts
and drainage ditches shall be restored to their original profile and condition.
25.7.3
33
All pipeline road crossings shall be installed with a minimum cover of 1.5 metres
between road surface and the top of the pipeline.
The pipe within road crossings shall be of special (heavy wall thickness) line pipe,
where called for in the Contract Specification or Drawings.
The pipe shall be double coated and triple wrapped in accordance with Section 23 (and
Section 10) of the Standard Construction Specifications.
The coated pipe shall be placed on a sand bedding not less than 15 cms thick and shall
then be surrounded with similar well compacted material to at least 15 cms above the
top of the pipe. A 20 cms thick compacted layer of, assorted sand and gravel shall then
be placed in the trench and on top of this layer, a reinforced concrete slab shall be
constructed over the entire length of the road crossing. The slab shall be not less than
10 cms thick and the width shall not be less than the overall diameter of the wrapped
pipe plus 30 cms.
Above the concrete slab, the road bed and road surfacing shall be backfilled and fully
reinstated in accordance with Standard Construction Specifications Sections S-2 and S4 and Clause 25.6.8 herein. All reinstatement work shall be subject to the approval of
the road and highway Authorities concerned.
25.7.4
34
25.8.1
GENERAL
This part of Specification S-25 is intended to be complimentary to all the foregoing
parts but where conflict with the particular requirements of construction on land occurs,
the specific requirements of this part of the specification shall prevail.
In working in marsh and swamp areas, the Contractor shall comply with any and all
regulations imposed by the Nigerian Ports Authority, Inland Waterways Authority and
other Governing Bodies. The Contractor shall take special care that traffic lanes in open
water and in all rivers and creeks are kept open for, traffic and shall warn such traffic of
the movements of large floating pieces of construction equipment and the placement of
equipment anchor lines. Any obstruction which might create a navigational hazard shall
exist only by permission of Local, Federal or other Governing Agencies and shall be
marked and maintained in accordance with the instructions issued these Agencies and
also as approved by the Company.
In marsh and swamp areas, pipelines (including flowlines) shall be laid to the spacings
and depths as specified herein or as called for in the particular contract specification or
the Approved Working Drawings. No bridging or spanning of creeks, canals or ditches
will be permitted, unless specifically shown on the Approved Working Drawings. The
submerged crossing of waterways is dealt with separately, under Part 9 of this
specification.
25.8.2
15.0 metres
(b)
1.5 metres
15.0 metres
35
(c)
(d)
25.8.3
0.3 metre
3.0 metres
1.2 metres
DEPTH OF COVER
The minimum depth of cover above the top of the wrapped pipe for pipelines and
flowlines buried in marsh and swamp areas shall be as follows:(a)
0.6 metre
(b)
For flowlines
0.6 metre
Note: The depth of cover shall be progressively increased at the approaches to water
crossings so as to accommodate the specified minimum bending radii required for the
downturn/upturn in the pipe profile and required depth of cover at each crossing (See
Part 9 herein).
25.8.4
Surface Spalling
(Due to excessive pipe flexure or localised impact against other objects, which
causes a loss of not more than 25 percent of the total thickness of the coating).
36
An area of less than 0.1 square metre, where the remaining concrete is sound,
shall be accepted without repairs. Should the area affected be more than 0.1
square metre but less than 0.3 square metre, the concrete remaining in place over
that area shall be undercut so as to provide a key for the addition of similar
concrete material to the original sheathing. Should the damaged area be more
than 0.3 square metre, the whole concrete sheathing shall be removed from
around the periphery of the pipe throughout the entire damaged area, and the
area-recoated.
Repairs shall be made by removing all cracked or broken material back to sound
concrete, removing and replacing damaged reinforcement wire, wetting the fresh
surface of the parent concrete and trowelling a stiff mixture of the same
materials and proportions as the original concrete sheathing, into and through
the reinforcing. This mixture shall be built up until the surface is level with the
concrete around the repair. The repaired pipe shall then be carefully laid aside
and allowed to moist cure undisturbed for a minimum of four days.
The resulting repair area shall be equal in density, uniformity and strength
characteristics to the originally applied concrete sheathing. Care shall be
exercised to minimise cracks due to pipe deflection in handling.
(b)
Cracks in Sheating
(Due to excessive flexure of the pipe in handling, storage or
transportation).
Circular cracks that are more than 2mm wide and extend more than 180o
circumferentially around the pipe and longitudinal cracks more than 30 cms long
irrespective of width, shall all be repaired.
The repair shall be made by chiselling the crack out to a width of rot less than 20
mm throughout the length of the crack. The crack shall be repaired with
material similar to that from which the coating is made and in a manner similar
to that outlined above. The repaired pipes shall be allowed to moist cure
undisturbed for a period not less than four days.
25.8.5
37
25 .8.6
25.8.7
Minimum Width of
trench (cm)
4
6
8
10
12
14
16
18
20
22
24
26
28
45
50
60
70
80
90
100
105
110
115
120
135
140
NOTE:The Contractor shall dig the flotation ditch wide enough and deep enough to
accommodate buoyancy vessels or other necessary flotation equipment.
38
25.8.8
25.8.9
39
WATER CROSSINGS
25.9.1
GENERAL
Where the route of the pipeline crosses any river, creek, canal or other waterway
(including minor streams, creeks and drainage ditches) the pipeline shall be buried in
the natural bed of the waterway and constructed as shown on specific (Approved for
Construction) Working Drawings based on the Company's Standard Drawings for
typical water crossings.
No spanning or bridging of rivers, streams, creeks, ditches, drains or any other
permanent or seasonal watercourses will be permitted unless specifically approved by
the Company and shown on the Approved Working Drawings.
At all water crossings, heavy wall pipe and transition pieces shall be used (unless
otherwise specified by the Company) and on each side of all larger water crossings a
fully piled block valve installation with operating platform shall be constructed in
accordance with the Company's Standard Drawings (S-2600 series) and Standard
Construction Specification S-30 (Marine Construction and Piling).
The Contractor shall submit a detailed working procedure and programme, for carrying
out each water crossing, to the Company at least 2 months before the crossing is due to
be made, so that sufficient time is allowed for study and possible amendments required
before approval by the Company and the Water Authorities concerned.
In carrying out water crossings, the Contractor shall comply with any and all regulations
imposed by the Nigerian Ports Authority, Inland Waterways and other Authorities. The
Contractor shall take special care that traffic lanes in open water and in all rivers and
creeks are kept open for traffic and shall provide river patrols to warn such traffic of the
movements of large floating pieces of construction equipment and the placement of
equipment anchor lines. Any obstruction which might create a navigational hazard shall
exist only by permission of Local, Federal or other Governing Agencies and shall be
marked and maintained in accordance with instructions issued by these Agencies and
also as approved by the Company.
All dredging shall be carried out in accordance with good and accepted dredging
practice and to the satisfaction of the Nigerian Ports and Inland Waterways Authorities
and the Company.
40
25.9.2
60 metres
(b)
3 metres
60 metres
2 5 .9.3
60 metres
For potential drilling or well location dredged access slots and specified
waterways, the minimum depth of the pipe below L.L.W.S. shall be 4.5
metres.
(b)
For specified major navigable waterways, the minimum depth of the pipe shall
be 4.5 metres below L.L.W.S OR 1.5 metres below natural bottom level of river or
creek bed: - whichever gives greater depth.
(c)
For all other (non-navigable) waterways and smaller water crossings, the depth
of the pipe shall be-such that it is just covered by the natural bed of the river or creek.
41
(c)
(d)
42
25.9.6
25.9.7
43
The flotation of the pipe and the procedure for sinking it into the prepared trench shall
be similar to that detailed under Clause 25.8.8 for marsh and swamp areas.
After sinking, the pipe shall be completely filled with filtered water from an approved
source, dosed as necessary with the approved inhibitor. The Contractor and the
Company shall jointly take depth soundings of the pipe crown throughout the whole
crossing and its approaches where practicable. All depths shall be referred to mud level
as marked by the tide gauge.
Horizontal distances shall be established by stakes driven as close to the ditch as
practicable and at some known measured distances apart (say 10 metres).
Based on the depth soundings at known horizontal distances, the Contractor shall
prepare a graphical representation of the profile of the pipe crossing as laid, and submit
this to the Company Representative for vetting and approval.
After acceptance of the crossing as laid, the trench shall be backfilled as soon as
possible. Under no circumstance shall any part of the pipe be lifted subsequent to its
acceptance.
If the profile/depth is not satisfactory, the Contractor shall propose remedial actions
and carry these out until the installallation of the crossing is acceptable to the
Company.
25.9.8
25.9.9
44
The banks of all water crossings- (with the exception of creek crossings in the
mangrove swamps) shall be backfilled and consolidated in a like manner to the original
slope but in no case steeper than a 2 to 1 slope also the trench at the toe of the bank sag
shall be completely filled.
Where the Contractor is unable to re-establish the required bank slope satisfactorily, he
shall layer the entire excavated and backfilled area with earthfilled bags or sacks,
extending the sack filled area a distance of 1.8 metres beyond the backfill. This work,
including the placing of filled sacks, shall be considered as part of the Contract Works
and shall not qualify for extra payment.
The banks of all creek crossings in mangrove swamp areas shall have the pipe trench
filled at the toe of the bank sag and shall have as much as possible of the previously
excavated material replaced in the river bank slot. Any additional fill necessary shall be
taken from the unexcavated surrounds. Care shall be taken to ensure that spud piles are
kept well clear of the pipeline during these operations.
The Contractor shall dig drainage ditches on each side of the backfilled area at all
crossings to divert drainage water away from the backfill, and also carry out any
necessary terracing and levelling.
25.9.10
45
OFFSHORE WORKS
25.10.1
GENERAL
Offshore pipeline construction works shall include the construction and laying of
marine pipelines, the installation and clamping of risers at the offshore structures, the
shore approach (including part of the corresponding landline normally up to the
insulating flange) and, where necessary, the burying of sections of the offshore lines.
The Contractor shall provide all necessary barges, tugs and other craft for the
transportation of materials, equipment and personnel to and from the offshore worksite.
25.10.2
DOWN TIME
It is recognised that offshore construction will occasionally be subject to stoppages due
to adverse weather and sea conditions. Under these conditions, down-time will be paid
for by the Company at the hourly rates specified in the Schedule of Prices in the
Contract Documents. These rates shall comprehensively include all minor equipment,
personnel and any other costs associated with the main items of equipment listed.
Down-time shall not be reimbursed to the Contractor for interruptions of less than three
hours duration and the total delay shall be rounded off downwards to the next full hour.
"Waiting-for-the-right-tide" will not be considered as down-time due for reimbursement
by the Company and no down-time due to mechanical failure of equipment will be
payable.
In the event that the Contractor has to cease operations due to adverse weather and sea
conditions, the Contractor shall state in writing, the time, duration and reasons for the
stoppage, giving the readings of approved and calibrated wind velocity and tidal current
meters and wave heights at half-hourly intervals. This down-time report must be'
countersigned by the Company Representative.
25.10.3
46
Unless otherside specified, the depth of the pipe trench (or 'ditch') shall be sufficient to
provide a minimum of 90 cms of cover above the crown of the pipe.
Trenching shall be conducted in such a manner as to cause no damage to the pipe
coating. The rate of change of incline of the trench bottom shall be controlled so that
the installed pipe will not be overstressed.
In-cases where trenching by the use of a jetting sled may result in possible damage to
any adjacent installed facility or the crossing of some other facilities, the Company may
require the trench to be excavated by hand jetting, In such cases, the work shall be
carried out by the Contractor at no additional cost to the Company. Such locations shall
be near risers being installed and near pipeline crossings or valve installations.
The trenching equipment shall have accurate load gauges with indicators visible to the
machine operator. The indicators shall also be readily available for observation by the
Company Inspectors. The load gauges on the jetting sled shall continuously monitor the
instantaneous forces being applied to the pipe at right angles to the pipes axis. The load
gauges shall measure the forces being applied to the bottom, top and sides of the pipe.
The Contractor shall be responsible for locating and protecting all underground
structures and lines.
All existing pipelines and other facilities crossed shall be lowered by trenching to obtain
a minimum clearance of 60 cms or such other clearance as required by the Owners,
whichever is greater.
When ditching across or adjacent to reefs, bottom scour troughs, and sediment beds, or
at other points where the contour of the sea, river or creek bed may require extra depth,
the Contractor shall excavate to such additional depth as may be necessary to meet the
requirements of the Company, and of any Public or Private Authority having
jurisdiction over the same, at no extra cost to the Company.
25.10.4
47
The Company shall be empowered to increase the radius of curvature if there is any
evidence of overstressing the pipe or damage to the pipe coating and wrapping (or
concrete sheathing) and the Contractor shall comply with the Company's requirements
in this respect at no additional cost to the Contract Works.
48