Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
02-06-2005
27-05-2005
30-04-2005
14-04-2005
Date
SFU
SFU
SFU
SFU
Prepared by
Contractor:
Tideway BV Marine and
Offshore Contractors
Company:
Allseas Construction Contractors S.A.
DWR/GSP
GSP
GSP
GSP
QA/QC Check
JGO
JGO
JGO
JGO
HSE Check
HAB
HAB
HAB
HAB
Approved by
Company
Title:
Document No:
Revision: D1
1. DREDGING
This document is a synopsis of the full Dredging and Backfilling Procedure, where contractual
responsibilities and technical details are described in full. There will be two operational methods for
trench excavation, one for the nearshore, using marine equipment, and one for the intertidal-zone
using land based equipment. The trenching and backfilling works described in this document were
undertaken in 2002 except for 180 metres of rock material.
PURPOSE
LOCATION
SIZE OF TRENCH
3.0m
0.5m
3
Actual Fracture Profile
Theoretical Profile
Overdredge Level
3.0m
0.3m
Natural Post
TIMESCALE
Theoretical Profile
Overdredge Level
Title:
Document No:
Revision: D1
After pipe installation the trench will be backfilled using the same
equipment. The sand material will be used for backfill in the originate sand
areas and the rock material will be used for backfill in the originate rock
areas.
EQUIPMENT
RESTRICTIONS
The dredging pontoon cannot work in a swell of over 1.0 m. This is the only
physical constraint to the excavation of the nearshore trench. In the
intertidal-zone high tide will restrict activity.
Refuelling is restricted to good weather conditions.
Archaeological restrictions can arise due to the need for investigations.
If sea mammals such as cetaceans are present work may be restricted
Work will continue 24hours. Restrictions arising from this include noise
DISTURBANCE
FACTOR
ENVRONMENTAL
IMPACT
Title:
Document No:
Revision: D1
MITIGATION
CONTINGENCY
REINSTATEMENT
Title:
Document No:
Revision: D1