Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
And
LEGAL NOTICE
This report was prepared as a result of work sponsored by the California Energy
Commission (Commission). It does not necessarily represent the views of the
Commission, its employees, or the State of California. The Commission, the State of
California, its employees, contractors, and subcontractors, make no warranty, express or
implied, and assume no legal liability for the information in this report; nor does any
party represent that the use of this information will not infringe upon privately owned
rights. This report has not been approved or disapproved by the Commission, nor has the
Commission passed upon the accuracy or adequacy of the information in this report.
USR040230003.DOC
Contents
Section
Page
Preface................................................................................................................................................. v
Executive Summary.................................................................................................................... ES-1
1
USR040230003.DOC
III
CONTENTS, CONTINUED
Section
3.3
3.4
3.5
3.6
3.7
Page
3.2.1
Gas Drying ...................................................................................................3-3
3.2.2
H2S Removal ................................................................................................3-3
3.2.3
Package Siloxane Treatment System ........................................................3-3
Expanded Process Flow Diagram ............................................................................3-4
Test Plan ......................................................................................................................3-4
3.4.1
Process Overview........................................................................................3-4
3.4.2
Rationale for Test ........................................................................................3-4
3.4.3
Predicted Performance ...............................................................................3-6
3.4.4
Test Objectives and Technical Approach.................................................3-6
3.4.5
Facilities, Equipment, Instrumentation to Conduct Test.......................3-7
3.4.6
Test Procedures ...........................................................................................3-8
3.4.7
Data Analysis Procedures ..........................................................................3-9
3.4.8
Quality Assurance Procedures ................................................................3-10
3.4.9
Contingency Measures .............................................................................3-10
Existing Data Summary Table................................................................................3-10
Energy Balance .........................................................................................................3-10
Test Recommendations and Schedule...................................................................3-11
Appendix
RP-1 Gas Production 2002 Data
Tables
2-1
2-2
2-3
2-4
2-5
3-1
3-2
3-3
Figures
2-1
2-2
2-3
3-1
3-2
3-3
3-4
3-5
3-6
IV
USR040230003.DOC
Preface
The Public Interest Energy Research (PIER) Program supports public interest energy
research and development that will help improve the quality of life in California by bringing
environmentally safe, affordable, and reliable energy services and products to the
marketplace.
The PIER Program, managed by the California Energy Commission (Commission), annually
awards up to $62 million to conduct the most promising public interest energy research by
partnering with Research, Development, and Demonstration (RD&D) organizations,
including individuals, businesses, utilities, and public or private research institutions.
PIER funding efforts are focused on the following six RD&D program areas:
For more information on the PIER Program, please visit the Commissions Web site at:
http://www.energy.ca.gov/research/index.html or contact the Commissions Publications
Unit at 916-654-5200.
For Commonwealth Program-specific information, please visit
http://www.pierminigrid.org.
What follows is a report for the California Energy Commission, Public Interest Energy
Research Program, Contract Number 500-00-036, conducted by the Commonwealth Energy
Team. The report is entitled Site Selection and Test Plan Report. This project contributes to
the Renewable Energy component of the PIER program.
USR040230003.DOC
Executive Summary
Background
The Project Prioritization Assessment, delivered under Task 1.1.10 of this PIER program,
recommended prioritized sites and technologies for research testing and evaluation to
advance renewable energy. Sites for testing of technologies for enhanced anaerobic
digestion and gas cleaning for microturbines at wastewater treatment plants ranked highly
in that prioritized list.
The Process Selection Report for Wastewater Treatment Plants, delivered under Task 2.2.1 of
this PIER program, recommended an ultrasound process for enhanced anaerobic digestion
and a package of combined treatment technologies for gas cleaning, to be carried into a site
selection and test phase.
This site selection and test plan report carries forward the conclusions from the abovementioned reports and provides specific site recommendations, further definition of the
processes and their integration into the host facilities at the recommended sites, and test
plans for the recommended processes.
USR040230003.DOC
ES-1
EXECUTIVE SUMMARY
Next to the existing treatment equipment (iron sponges and gas compressors) at that
facility
ES-2
USR040230003.DOC
SECTION 1
Introduction
In June 2001, the Commonwealth Energy Team was awarded a programmatic contract
under the California Energy Commissions Public Interest Energy Research (PIER) Program
to conduct research on strategies for making renewable energy more affordable in
California. The Commonwealth Energy approach involves assessing the combined potential
of biogas and photovoltaic (PV) resources in a defined study area and identifying how these
resources could be developed in a complementary and cost-effective manner. The
Commonwealth Energy Team conducted this research in a real world setting so that the
findings could be applied elsewhere in California and thereby benefit more California
ratepayers. The local area Commonwealth Energy selected for its renewable energy research
activities is the Chino Basin, referred to in this report as the study area.
1.1 Background
The Chino Basin is rich in PV and biogas resources. Moreover, it is a rapidly growing area
with substantial and increasing electrical loads. The underlying goal of the Commonwealth
Energy PIER Renewables Mini-Grid Program is to identify potential Building Integrated PV
(BIPV) and biogas energy projects, bring innovative technologies and business practices to
these projects, assess the benefit to the local electricity distribution system (the mini-grid),
and then use the findings to develop a business model for siting cost-effective, renewable
energy projects. A description of the Commonwealth Energy PIER Program, including the
results of some of the work undertaken to date, is presented on the project Web site,
http://www.pierminigrid.org.
An important element of the Commonwealth PIER Renewables Mini-Grid Program is a
project devoted to research on improving energy recovery from biogas derived from
anaerobic digestion. This project is identified as Project 2.2, Enhanced Energy Recovery
Through Optimization of Anaerobic Digestion and Microturbines. The work summarized
in this report (Task 2.2.2) is the second activity of Project 2.2, and carries forward the results
of the Process Selection Report completed for Task 2.2.1.
USR040230003.DOC
1-1
INTRODUCTION
Increase and optimize digester gas production through thermal hydrolysis and
ultrasound processes.
Evaluate and quantify environmental benefits that result from using microturbines at
sewage treatment plants.
Evaluate performance and cost during operation so sewage treatment plants have
greater certainty on cost and reliability of using microturbines.
The first task, 2.2.1, evaluated several different processes and selected an ultrasound process
for enhanced anaerobic digestion and a custom treatment package for gas cleaning for
microturbines, to be carried further to site selection and testing.
This report fulfills the scope of Task 2.2.2, which includes a report on selection of the best
sites at which to deploy the technologies and processes for enhanced anaerobic digestion
and gas cleaning that were selected in Task 2.2.1. The report also provides (1) expanded
process flow diagrams that further define the selected processes and show their integration
into the selected host facilities, and (2) test plans for the new systems.
Section 2 describes the selected test site for the enhanced anaerobic digestion process.
Expanded process flow diagrams are presented, and process definition, test plans,
recommendations and schedule are discussed.
Section 3 describes the selected test site for the microturbine gas cleaning process.
Expanded process flow diagrams are presented, and process definition, test plans,
recommendations and schedule are discussed.
1-2
USR040230003.DOC
SECTION 2
USR040230003.DOC
2-1
performance of these digesters, which may be referred to during this test as necessary.
Digesters #1 and #2 are similar in size, design, and mixing and heating equipment and have
been in operation for the same duration. Plant data (provided in Section 2.5) show that the
digesters have similar performance, although plant staff have recommended a more
detailed evaluation of the two digesters prior to testing. The similarities between these two
digesters and the background data available make these suitable for side-by-side testing of
two different ultrasound systems.
Three locations of the ultrasound equipment were considered. The evaluation criteria
included ease of supply of TWAS to the ultrasound systems, routing of the sonicated solids
from each system to the respective digester, piping for bypassing the ultrasound systems in
case of a shutdown, and electrical hookup for the test equipment. The TWAS feed line to the
digesters is buried for most of its length, and is only accessible at the DAFT pump room, or
in the digester pump room basement, where the digester feed pipe header and valve
systems are located. The three locations considered were:
The location next to the DAFTs provided easy access to the feed TWAS line, but produced
complications as it required routing of multiple temporary pipelines to convey sonicated
TWAS from each ultrasound system to the respective digesters, as well as bypass lines,
across an onsite roadway that plant staff would need to use. This location significantly
increased the total pipe length that would be required.
Location of the test equipment on the north side of the digesters was also considered. At this
location, a single TWAS feed line could be installed from the DAFT pump room to the
equipment, which would reduce the pipe length and access issued associated with the first
location. Alternatively, the TWAS feed to the test equipment could be connected to a T
section on the feed header in the digester pump room basement. This avoided having to run
lines across the access road, but the line from the pump room basement required routing it
up the main access staircase, which could cause a potential safety issue for plant staff. The
sonicated TWAS from the test equipment to the digesters could be routed into the external
digester mixing lines on the north side of the digesters. However, electrical connections
would have to be routed from a control room on the opposite side of an access road.
Location of the test equipment on south side of the digesters was also considered. There is
an existing electrical control room adjacent to the digester pump room on this side, which
has spare capacity and could accommodate electrical needs of the test equipment. The
TWAS feed to the test equipment could be accessed at the same T-connection in the
basement that was considered for the above location. However, by locating the equipment
on the south side, the line could be run up an existing ladder, rather than the main access
stairway, and would not be a safety concern. There are mixing line access points on the
external digester walls on the south side that could be used for routing the sonicated TWAS
into the digesters.
2-2
USR040230003.DOC
FIGURE 2-1
USR040230003.DOC
2-3
FIGURE 2-2:
2-4
USR040230003.DOC
Increase in probe power, from 4 kW to potentially 16 kW. Probes over 4 kW have a new
water cooling system
Change in probe design from a single-cast piece to a two-piece probe to allow the lower
portion, which has the most wear, to be replaced more frequently, while the upper
portion can be replaced less frequently
Data from IWE Tec ultrasound systems in Germany show that the older design, using 2-kW
probes at the lower amplitude range, typically provided improvements in anaerobic
digestion as follows:
USR040230003.DOC
2-5
Data from Sonico ultrasound systems show that the older design, using 3 kW probes at the
lower amplitude range, typically provided improvements in anaerobic digestion as follows:
2-6
USR040230003.DOC
USR040230003.DOC
2-7
FIGURE 2-3
2-8
USR040230003.DOC
PDX\040230003.DOC
2-9
optimizing gas production at municipal plants. There are three primary suppliers with
systems developed for municipal applications, and these suppliers are continuing to
develop and optimize their equipment to improve cost-effectiveness. Most of the work to
date has been conducted in Europe, and there is a need to develop this technology for
application in the United States.
The longest-running ultrasound installation at a municipal treatment plant is around three
years using low power probes (2 kW). Most of the work to date has been done in Europe,
where conditions at municipal plants are often different from plants in the U.S., and as
mentioned earlier, digester performance in Europe tends to be lower than in the U.S.
Sonico has conducted trials at Orange County Sanitation District (OCSD), and is currently
testing the same equipment at a Los Angeles County Sanitation District plant, which is very
similar to OCSD. The testing was done with 3 kW probes and was on a biological sludge
produced from Pure Oxygen Activated Sludge Process. Additionally, data needs to be
collected with sludges produced at air aerated sludge plants, which are the most common
biological treatment processes in the U.S. The secondary solids from air aerated sludge
plants are more highly oxidized and the structure of the solids may be stronger. Therefore,
the biogas production potential with ultrasound treatment may be different, and the
required energy input to achieve sufficient disintegration might be higher.
The presence of multiple vendors is beneficial for the market, as the suppliers are seeking to
improve life-cycle costs for their systems to be increasingly competitive. Each of the three
suppliers in the market has a very different approach to the application of their ultrasound
systems and very different operational parameters, which make direct comparison of the
systems difficult. Testing of the different suppliers at the same site would enable such a
comparison to be done for the first time, and the potential advantages of each system to be
verified.
2-10
USR040230003.DOC
Digester #2
No Ultrasound
With Sonico
Ultrasound
No Ultrasound
Pretest Phase
1 month
1 month
Baseline Phase
3 months
3 months
6 months
6 months
3 months
3 months
Phase
Ultrasound Phase
Continuation Phase
PDX\040230003.DOC
2-11
Complete ultrasound equipment, including but not limited to reactor chamber, horns/
probes, boosters, extenders, transducers, generators, and cooling system, to treat the
specified TWAS flow to one digester.
One container or skid system to house the ultrasound equipment and all appurtenances,
to be located outside and adjacent to the digesters.
Flowmeter(s) and required motorized valves (if needed) to control and protect
demonstration equipment.
Bypass line and valves to proportion flow for IWE Tec Ultrasound System
A 10, 000-gallon TWAS holding tank with low, high, and high-high level controls to
allow continuous flow through the ultrasound equipment systems.
Temporary piping between the TWAS feed line, the ultrasound demonstration systems
and the digesters.
Power supply, temporary power and control cable to be connected to plant system.
2-12
USR040230003.DOC
between them. This will then be repeated towards the end of the ultrasound phase, after the
digesters are at steady state operation and again during the continuation phase.
TABLE 2-2
Parameter
Daily Flow (mgd)
Primary Sludge
To Each
Digester
TWAS To
Each Digester
Digested Sludge
From each
Digester
Quantity (wtpd)
Dewatered
1
Cake
Frequency
daily
daily
TS (%)
3 x week
VS (%)
3 x week
Alkalinity (mg/l)
3 x week
pH
3 x week
1 x month
3 x week
Viscosity
VFA (mg/l)
Ammonia (mg/l)
3 x week
Nitrate (mg/l)
3 x week
3 x week
TKN (mg/l)
Sulfate (mg/l)
3 x week
daily
daily
Temperature (F)
Iron Salts (mg/l)
Polymer (lb/ton)
daily
daily
Operation (hr/d)
daily
# of Duty Units
daily
1 Conduct 1 week of more intensive dewatering tests to characterize dewatering variability between each
digester.
2 If bottom sludge is withdrawn from the digesters, the volume and solids should be recorded.
PDX\040230003.DOC
2-13
TABLE 2-3
Landfill
Gas
Natural
Gas
Total (entire
Co-gen)
Frequency
daily
Methane (%)
weekly
H2S (ppm)
weekly
BTU
Parameter
City of Riverside plant staff assistance will be required to check operation of the ultrasound
systems. Both units will be provided with control panels for automated operation. A log
sheet will be provided for once daily monitoring of the systems, which will include:
Test Procedures
The parameters listed in Table 2-2 and Table 2-3 will be measured using existing plant
equipment and sample procedures. Flow measurements will be made with existing solids
flow and gas flowmeters, which will be calibrated before the start of the test, and will be
cross-checked with strap-on flowmeters. The flowmeters will be checked every six months
during the test. Chemical data for the digester feed and exit sludges and biogas will be
conducted using the standard methods for laboratory analysis of the listed parameters.
Tests that the City of Riverside laboratory is not certified to conduct will be sent to a
certified external laboratory.
Digester temperature measurements will be taken from on-line temperature sensors on the
digester recirculation lines, with additional daily manual readings, as currently done by
plant staff. Iron salt addition and dewatering polymer use will be calculated from the volumes and concentration of chemicals used, as currently monitored at the plant. Dewatering
capture rate will be calculated from solids measurements in the feed biosolids and in the
2-14
USR040230003.DOC
filtrate. The hours of operation and number of dewatering units in use will be recorded by
plant staff, and cross-checked with digested biosolids flows to the dewatering facility.
Ultrasound operating parameters will be recorded by the plant staff in a daily operating log,
using meters installed on the two systems. Chemical and microscope analyses of the
sonicated TWAS will be conducted by the City of Riverside laboratory, or by a certified
external laboratory.
PDX\040230003.DOC
2-15
Plant Data
Description
Unit
Min
Max
Avg
MGD
0.08
0.19
0.12*
PS % TS
Percent
2.55
5.85
4.35
PS % VS
Percent
43.82
85.57
79.89
DAF In Flow
MGD
0.16
0.79
0.55
MGD
0.04
0.17
0.11*
DAF % TS
Percent
2.99
5.62
3.74
DAF % VS
Percent
63
90
78.13
MGD
0.124
0.27072
0.23*
Dig 1 pH
SU
6.94
7.81
7.49
Dig 1 VA
mg/l
26
425
82
Dig 1 Alk
mg/l
2,777
3,916
3,447
Dig 1 VA/Alk
ratio
0.01
0.13
0.02
Dig 2 pH
S.U.
7.3
7.8
7.5
Dig 2 VA
mg/l
23
367
70
Dig 2 Alk
mg/l
2,882
4,239
3,588
Dig 2 VA/alk
ratio
0.01
0.11
0.02
Dig In % TS
Percent
3.1
5.1
4.0
Dig In % VS
Percent
72
86
79
AVG VS Reduction
Percent
4.01
66
50
Percent
54
79
65
2-16
USR040230003.DOC
TABLE 2-4
Plant Data
Description
Unit
Min
Max
Avg
BP In Flow
MGD
0.43
0.23
BP In % TS
Percent
1.5
2.6
2.2
BP dtpd
Tons
42
21
BP wtpd
Tons
342
171
BP CAKE % TS
Percent
10.6
16.4
12.5
Dig 1 Temp
Deg. C
36
41
39
Dig 2 Temp
Deg. C
36
41
39
Dig Detention
Days
12
26
14
ppm
25
111
73
ppm
91
10
Total H2S
LBS/Day
1.340
6.877
3.523
LBS/Day
0.6
PDX\040230003.DOC
2-17
TABLE 2-5
Duration
Date
Pretest Phase
1 month
April 2004
Baseline Phase
3 months
Ultrasound Phase
6 months
Continuation Phase
3 months
2-18
USR040230003.DOC
SECTION 3
The purpose of the microturbine gas cleaning pilot test is to collect and analyze data for
different technologies to determine their efficacy in removing hydrogen sulfide and
siloxane. This section discusses the pilot testing site location, the technologies to be tested,
the process flow diagram, the testing plan, and the test recommendations and schedule.
The biogas used for operating microturbines must meet stringent quality requirements
(maximum of 150 parts per million [ppm] moisture, 25 ppm hydrogen sulfide [H2S], and 10
ppbv siloxanes) to prevent early deterioration of the microturbines. The biogas produced in
the digesters at a wastewater treatment plant is typically saturated and contains
approximately 500 to 2,000 ppm H2S, and 2 to 5 ppm siloxane. Biogas from manure
digestion is also saturated, contains approximately 500 to 2,000 ppm H2S and typically no
siloxanes. The content of each of these contaminants needs to be decreased to meet the
biogas quality stated above.
USR040230003.DOC
3-1
FIGURE 3-1
Location Map
Vicinity Map
TABLE 3-1
Company
IEUA
CH2M HILL
825 NE Multnomah,
Suite 1300, Portland,
OR 97232
CH2M HILL
Bill Kitto
Fred Soroushian
Carmen Quan
3-2
Address
Telephone
909-993-1685
909-993-1699
Fax
909-357-3884
E-mail
Ewhitman@ieua.org
rgross@ieua.org
Bkitto@ch2m.com
714-435-6232
714-424-6232
Fsoroush@ch2m.com
714-435-6117
714-424-2063
Cquan@ch2m.com
USR040230003.DOC
FIGURE 3-2
USR040230003.DOC
3-1
USR040230003.DOC
3-1
FIGURE 3-3
3-2
USR040230003.DOC
PDX\040230003.DOC
3-3
The other company is Pioneer Air Systems, Inc. The gas drying unit in the Pioneer system
consists of cyclic refrigeration capable of achieving an outlet temperature of 20 degrees F.
The removal of siloxanes in the Pioneer system depends on liquid condensation (by
adsorption with the condensed water) and polishing with activated carbon.
Both these companies will be contacted to determine if a unit can be rented or obtained for a
low capital cost. If available, the unit will be tested and used to compare technologies for
siloxane removal.
The package system for this pilot test program will be sized to treat 50 scfm of biogas, which
is enough to run 4 of the existing 30-kW microturbines at RP-1.
3-4
USR040230003.DOC
FIGURE 3-4
FIQ
PI
TI
PI
TI
BIOGAS
FROM EXST
GAS
COMPRESSORS
DRIED
BIOGAS
TO
HEADER
SAMPLE
POINT
SAMPLE
POINT
REFRIGERATION
CIRCUIT
CONDENSATE
SAMPLE POINT
FIGURE 3-5
S
WATER
SUPPLY
FIQ
PI
TI
BLOWER
NPK
NUTRIENTS
H2S REMOVAL
TANK
PI
RECIRC PUMP
BIOGAS
FROM
DIGESTER No. 4
SAMPLE
POINT
TI
H2SREDUCED
BIOGAS
TO
BIOGAS
HEADER
SAMPLE
POINT
TO
DISPOSAL
CONDENSATE
SAMPLE POINT
PDX\040230003.DOC
3-5
FIGURE 3-6
PI
PI
TI
TI
CLEANED
BIOGAS
TO
MICRO
TURBINES
SILOXANE
REMOVAL
MODULE
GAS COOLING
MODULE
SAMPLE
POINT
SAMPLE
POINT
CONDENSATE
SAMPLE POINT
SAMPLE
POINT
Current technologies for H2S removal require either chemical feed (i.e., iron salts) or media
replacement (i.e., iron sponge), which typically result in high operating costs. Local
experience in operating the biological H2S removal system (level of difficulty and
operational labor requirements) needs to be acquired and documented to analyze this
system. This is also the case for the packaged siloxane removal system.
The proposed technologies (refrigerated dryer and biological H2S removal) for this pilot test
program have the potential of substantially reducing the gas treatment cost. However, the
available data for these systems is not comprehensive to allow analysis of their efficiency or
cost effectiveness.
The purpose of the Digester Gas Cleaning Pilot Test program is to collect the necessary
information to determine the removal efficiency and cost effectiveness of these technologies.
3-6
USR040230003.DOC
The other is to obtain the necessary data to determine the cost effectiveness of operating
each of these technologies.
The pilot test equipment and system design will include sample ports and instrument ports
to facilitate the collection of samples and measuring of parameters necessary to achieve the
goals of this program. Before starting the design of the digester cleaning pilot test system, it
will be necessary to analyze the composition of the biogas in the main header and in
Digester No. 4. This is required to optimize the size of the pilot test equipment.
For the gas drying system, samples of the biogas will be taken upstream and downstream of
the refrigerated dryer once a week. These samples will be sent to the laboratory to test the
moisture and siloxane content in the biogas samples and the results recorded. Samples of
the condensate will also be collected once a week and sent to the laboratory to test its
composition and pH and the results will be recorded. Condensate testing will help in
determining the alternatives for its disposal. In addition, the pressure and temperature of
the biogas and the power consumed by the refrigerated dryer will be recorded daily. A
flowmeter with a totalizer will be provided upstream of the gas drying system to measure
and record the biogas flow daily. The daily amount of condensate will also be measured and
recorded.
The influent and effluent pipes of the biological H2S treatment system will be provided with
ports to collect biogas samples once a week. These samples will be sent to the lab to test the
H2S content in the biogas and the results recorded. The temperature and pressure of the
biogas and the amount of air supplied to the system will be recorded daily. The amount of
power consumed by the entire system (recirculation pump, motorized valves and the air
compressor supplying the air to the system) will be measured and recorded daily. A
flowmeter with a totalizer will also be provided upstream of the biological H2S treatment
system to measure and record the biogas flow daily.
The packaged siloxane treatment system pilot unit will be furnished with ports upstream
and downstream of each of its main elements to collect samples of biogas to test the
moisture and siloxanes content. If the package unit produces condensate, a sample will be
collected and its composition tested, as well. These samples will be collected and send to the
laboratory once a week and the results recorded. The pressure and temperature of the
biogas and the power consumed by each of the elements in the package unit will be
recorded daily. A flowmeter with a totalizer will also be provided upstream of the gas
drying system to measure and record the biogas flow daily. The daily amount of condensate
will also be measured and recorded.
PDX\040230003.DOC
3-7
Pressure gauges and thermowells will be used to measure the pressure and temperature of
the biogas. The reading and recording of this parameter will be done manually.
A thermal mass flowmeter with totalizer will be used to measure the flow of biogas. The
reading and recording of this parameter will be done manually.
Sampling Plan
Sample/Parameter Monitored
Test
Frequency
Moisture/siloxane
Once a week
Moisture/siloxane
Once a week
Temperature
--
Once a day
Pressure
--
Once a day
Flow
--
Once a day
--
Once a day
H2S
Once a week
H2S
Once a week
Temperature
--
Once a day
Pressure
--
Once a day
Flow
--
Once a day
--
Once a day
3-8
USR040230003.DOC
TABLE 32
Sampling Plan
Sample/Parameter Monitored
Test
Frequency
Siloxane
Once a week
Siloxane
Once a week
Temperature
--
Once a day
Pressure
--
Once a day
Flow
--
Once a day
--
Once a day
--
Once a day
Package System
Each of the equipment systems that will be used in this pilot testing program is provided
with its own proprietary control system for proper and safe operation. The refrigerated
system contains the controls for the refrigeration cycle. The packaged siloxane removal
system is provided with controls for the condensation cycle (the siloxane removal process
uses media and does not require control).
The biological H2S removal system is provided with equipment, instrumentation,
appurtenances and a PLC unit to control the process. The air compressor supplying the
necessary air to the process is controlled by an oxygen sensor. If the oxygen sensor reaches
the high level setpoint, the air compressor stops operation. The pH of the fluid is also
measured on-line and allows water to enter the tank if the pH sensor reaches the low
setpoint. The system is also equipped with Drgertubes for local measurement of H2S.
The laboratory must follow the equipment calibration recommendations to meet the ASTM
and EPA requirements for the tests that are required above. Pressure gauges, thermowells
and power meters will require calibration every year. Thermal mass flowmeters will require
calibration every 3 months.
Other data that will be collected are the cost of supplies for each system and the labor hours
dedicated to the operation and maintenance of each system. The time to inspect instruments
and collect and record parameters will be documented separately for each system.
PDX\040230003.DOC
3-9
3-10
USR040230003.DOC
Duration
Date
1 month
May 2004
1 month
4 months
October 2004
February 2005
3 months
October 2004
January 2005
(1)
(1)
Baseline and technology phase testing for these technologies will be done concurrently.
A continuation phase is not required for any of these technologies.
PDX\040230003.DOC
3-11
Appendix
RP-1 Gas Production 2002 Data
USR040230003.DOC
A-1